CN100557144C - A kind of method of removing the bored pile construction obstacle - Google Patents

A kind of method of removing the bored pile construction obstacle Download PDF

Info

Publication number
CN100557144C
CN100557144C CNB200710119583XA CN200710119583A CN100557144C CN 100557144 C CN100557144 C CN 100557144C CN B200710119583X A CNB200710119583X A CN B200710119583XA CN 200710119583 A CN200710119583 A CN 200710119583A CN 100557144 C CN100557144 C CN 100557144C
Authority
CN
China
Prior art keywords
steel casing
beating
vibrating hammer
bored pile
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB200710119583XA
Other languages
Chinese (zh)
Other versions
CN101130980A (en
Inventor
孙彪
金传宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Oilfield Services Ltd
China National Offshore Oil Corp CNOOC
Original Assignee
China Oilfield Services Ltd
China National Offshore Oil Corp CNOOC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Oilfield Services Ltd, China National Offshore Oil Corp CNOOC filed Critical China Oilfield Services Ltd
Priority to CNB200710119583XA priority Critical patent/CN100557144C/en
Publication of CN101130980A publication Critical patent/CN101130980A/en
Application granted granted Critical
Publication of CN100557144C publication Critical patent/CN100557144C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of method of removing the bored pile construction obstacle, comprise the steps: a) on wharf slab, to offer hole than design stake slightly larger in diameter; B) put into the steel casing in the above-mentioned stake hole of offering, steel casing internal diameter is than the design stake big 5~15cm in footpath; C) fixing replacing of a connection steel casing and vibrating hammer in the vibrating hammer bottom beats; D) the steel casing is sunk establish, when the top of steel casing exceeds the scope of operation 50~60cm, stop hammering, will separate for beating by vibrating hammer vibration hammering for beating with the steel casing; E) carry out the butt joint of partial node steel casing as required, repeat above-mentioned connection and heavy step of establishing after butt joint is finished again, sink to preposition until the steel casing; F) will separate for beating, remove the obstruction in the steel casing, carry out bored pile then with the steel casing.The present invention has influences advantages such as minimum, expense is low, penetration power is strong to original old structure.

Description

A kind of method of removing the bored pile construction obstacle
Technical field
The present invention relates to a kind ofly in the transformation process of harbour, remove the method for bored pile construction obstacle.
Background technology
Along with the high speed development of national economic development, the problem of whole nation industry, shipping business infrastructure scarce capacity exposes to such an extent that become increasingly conspicuous, and has seriously hindered the paces of economic high speed and sustainable development.In the infrastructure in China coastal port area, it is aging that ubiquity facility, and harbour face bearing capacity is not enough, can not satisfy the growing needs of cargo handling capacity, and these problems bring great resistance for the development of China's shipping interest.Though can invest to build the contradiction that new harbour relaxes this demand, have a lot of adverse factors: bankroll problem (investing huge); Construction period problem (from project verification, demonstration, to design, construction period is very long); Environmental factor (construction project is to the influence of surrounding environment) or the like.
Therefore, for addressing the above problem, in port infrastructure is in recent years built, often take terminal facilities is carried out the method that segmentation is transformed.Its advantage is: small investment instant effect (transform on the basis of existing facility, can make full use of the useful structure of old building, thereby cost is low, the duration lacks) can guarantee investor's interests.Therefore, in this class engineering, some new technologies, new technology continue to bring out.Some workmanshiies are guaranteed, construction safety, reliable, and construction costs is reasonable, the construction technology and the measure of saving, more and more is subjected to the attention of the parties concerned.
At present, in China's long piled wharf improvement project, because the structure of harbour causes inevitably running into huge thick rock mound, for bored pile construction, must find simple, fast processing method to remove these obstacles on the stake position, guarantee construction safety, efficiently carry out.Traditional handicraft often adopts the construction processing scheme of heavy excavation, because excavation inevitably causes the surrounding soil passive resistance to reduce, soil body unstability produces the landslide and make all round, the lighter causes surrounding piles plinth inclination and distortion, produces potential safety hazard, weight person's pile foundation is sheared destruction, harbour (or surrounding buildings thing) collapses, and causes great security incident.Therefore before scheme implementation, not only need to carry out the necessary security demonstration, and must reinforce the soil body around the excavation area, the variation of necessary precision monitor surrounding soil situation in construction simultaneously, in case note abnormalities, must stop excavation, and take the measure of setting each other off further the soil body on every side to be carried out consolidation process.And to remove the harbour cover plate earlier before the construction, after excavation is finished, the erection construction platform.Therefore, exist huge construction safety risk; Operation increases, and efficient reduces greatly; The input of upkeep operation safety is very big.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of method that periphery is influenced little and the removing bored pile construction obstacle that efficient is very high.
A kind of method of removing the bored pile construction obstacle of the present invention comprises the steps:
A) on wharf slab, offer than the hole of designing the stake slightly larger in diameter, as the heavy vertically-guided of establishing of control steel casing;
B) put into the steel casing in the above-mentioned stake hole of offering, steel casing internal diameter is than the design stake big 5~15cm in footpath;
C) fixing replacing of a connection steel casing and vibrating hammer in the vibrating hammer bottom beats;
D) the steel casing is sunk establish, when the top of steel casing exceeds the scope of operation 50~60cm, stop hammering, will separate for beating by vibrating hammer vibration hammering for beating with the steel casing;
E) carry out the butt joint of partial node steel casing as required, repeat above-mentioned connection and heavy step of establishing after butt joint is finished again, sink to preposition until the steel casing;
F) will separate for beating, remove the obstruction in the steel casing, carry out bored pile then with the steel casing.
Preferably, described for the packing draw together upper end and bottom, the bottom can be inserted in the described steel casing, the upper end is used for fixing described vibrating hammer.
Preferably, described is about 60cm for the height of beating, and described height for the bottom of beating is about 30cm.
The present invention has following advantage:
1) to the minimum that influences of original old structure.Because this technology is just handled at point (stake position) one by one, and is therefore little to the influence of peripheral structure thing;
2) expense is low.Because this technology does not damage original rock mound and original old structure, therefore just do not recover the expense of these structures;
3) penetration power is strong.Can penetrate 12 meters thick riprap layers;
4) efficiency of construction height.A plurality of points can carry out simultaneously, thereby have improved processing speed greatly.
Description of drawings
Fig. 1 is the invention process schematic diagram.
The specific embodiment
As shown in Figure 1, specific implementation method of the present invention comprises the steps:
A) at first use the pneumatic pick perforate according to the stake position of putting well on wharf slab 6, opening diameter as steel casing 4 heavy guiding of establishing, is controlled its verticality than designing about the big 15cm in stake footpath;
B) in the above-mentioned stake hole of offering, put into steel casing 4, steel casing 4 generally adopts to connect more than or equal to the thick roll of steel plate pressure welding of 8mm and forms, the casing internal diameter is than the design stake big 5~15cm in footpath, can make by merogenesis, first joint length generally than the scope of operation to the height of mud face have more 2~3 meters (if oversize, wayward verticality during hammering.For example: the scope of operation is 5 meters to the height of mud face, then first joint length is controlled at 7~8 meters and is advisable), steel casing 4 bases add the reinforcement steel plate guard ring of the thick 8mm of the wide 200mm of weldering, and do tough angle in the bottom side and (guarantee that steel casing 4 is at the heavy not crimping of establishing in the process of vibration, strengthen its penetration power simultaneously), all the other respectively save length should not be greater than 4 meters, and the total length fibrous root determines according to the geological condition of job location, and the bottom of general steel casing 4 should enter clay or silty clay more than 1 meter.(length overall is 19 meters in the present embodiment).
C) after steel casing 4 inserts the stake hole, subsequently steel casing 4 is adjusted, to guarantee that it is within deviation (comprising pile position deviation and the perpendicularity deviation) scope that allows, 20 * 30cm timber wedge 3 filled in the slit between the hole of being opened on steel casing 4 and the wharf slab 6, and jam-packed, do not change to guarantee steel casing 4 heavy position and verticality of establishing in the process.
D) will be fixed with for making a call to 2 vibrating hammer 1 with crane and sling, and will be inserted in the steel casing 4 for making a call to 2.Be mainly used in connection vibrating hammer 1 and steel casing 4 for making a call to 2, be made of upper end 21 and bottom 22 for making a call to 2, for making a call to about 2 high 60cm, its bottom 22 is the steel cylinder (external diameter is slightly less than the internal diameter of steel casing 4) about high 30cm, can insert in the steel casing 4, play the guide-localization effect; Its upper end 21 is thick than the bottom, can adopt bolt to be connected and fixed between itself and the vibrating hammer 1.Replace and make a call in the 22 insertion steel casings 4 of 2 bottoms, fix with the top of steel casing 4 and for bottom 22 welding of making a call to 2.
E) open vibrating hammer 1, first joint steel casing 4 is sunk in vibrating hammer 1 hammering, heavy establishing in the process, the sling hook 5 of vibrating hammer 1 of crane should keep slightly lax and state that do not break off relations, to monitor the position and the verticality of steel casing 4 simultaneously, as not satisfying the deviation requirement, stop proceeding after hammer is adjusted, when the top that head saves steel casing 4 exceeds the scope of operation 50~60cm (be convenient to next step sever between casing and casing dock weld job), stop hammering, sever for making a call to 2 and the welding position of steel casing 4 with gas welding;
F) hang out for making a call to 2 and vibrating hammer 1, carry out the butt joint of partial node steel casing 4 then as required, repeat the above-mentioned connection and the step of establishing of sinking after butt joint is finished again, till head saves steel casing 4 and sinks to preposition.
G) sever for making a call to 2 and the attachment weld of 4 of casings, will for make a call to 2 and vibrating hammer 1 hang, with dashing obstruction such as the removing steel casing 4 interior rubbles of grabbing bucket, just can carry out Bored Pile Construction then.
Above-mentioned power-equipment is generally selected more powerful vibrating hammer 1 for use, as 90 hammers or 80 hammers.
This technology can be widely used in the pile foundation engineering (bored pile of improvement project of the long piled wharf of coastal subgrade, steel pipe pile, steel sheet pile), also can be applicable among the new harbour pile foundation engineering construction, the pile extension that also can be applicable to the underground broken pile of shallow-layer is handled, and has positive dissemination.

Claims (3)

1, a kind of method of removing the bored pile construction obstacle is characterized in that, comprises the steps:
A) on wharf slab, offer than the hole of designing the stake slightly larger in diameter, as the heavy vertically-guided of establishing of control steel casing;
B) put into the steel casing in the above-mentioned stake hole of offering, steel casing internal diameter is than the design stake big 5~15cm in footpath;
C) fixing replacing of a connection steel casing and vibrating hammer in the vibrating hammer bottom beats;
D) the steel casing is sunk establish, when the top of steel casing exceeds the scope of operation 50~60cm, stop hammering, will separate for beating by vibrating hammer vibration hammering for beating with the steel casing;
E) carry out the butt joint of partial node steel casing as required, repeat above-mentioned connection and heavy step of establishing after butt joint is finished again, sink to preposition until the steel casing;
F) will separate for beating, remove the obstruction in the steel casing, carry out bored pile then with the steel casing.
2, the method for claim 1 is characterized in that, described for the packing draw together upper end and bottom, the bottom can be inserted in the described steel casing, the upper end is used for fixing described vibrating hammer.
3, method as claimed in claim 2 is characterized in that, described is about 60cm for the height of beating, and described height for the bottom of beating is about 30cm.
CNB200710119583XA 2007-07-26 2007-07-26 A kind of method of removing the bored pile construction obstacle Active CN100557144C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB200710119583XA CN100557144C (en) 2007-07-26 2007-07-26 A kind of method of removing the bored pile construction obstacle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB200710119583XA CN100557144C (en) 2007-07-26 2007-07-26 A kind of method of removing the bored pile construction obstacle

Publications (2)

Publication Number Publication Date
CN101130980A CN101130980A (en) 2008-02-27
CN100557144C true CN100557144C (en) 2009-11-04

Family

ID=39128379

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200710119583XA Active CN100557144C (en) 2007-07-26 2007-07-26 A kind of method of removing the bored pile construction obstacle

Country Status (1)

Country Link
CN (1) CN100557144C (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155516B (en) * 2015-08-14 2016-11-30 江苏省华建建设股份有限公司 The method of construction drill bored concrete pile before making an overall screening underground obstacle
CN109208594B (en) * 2018-08-29 2020-11-17 中铁大桥局集团有限公司 Treatment method for steel casing sinking meeting boulder, steel casing structure and drilled pile
CN110331724B (en) * 2019-07-17 2024-07-02 中交第四航务工程局有限公司 Device and method for rapidly removing pile-embedded pile pad residues after pile hammer pile sinking

Also Published As

Publication number Publication date
CN101130980A (en) 2008-02-27

Similar Documents

Publication Publication Date Title
Viggiani et al. Piles and pile foundations
Fleming et al. Piling engineering
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN106545007A (en) The method of pile in stratum of the bottom for hard rock stratum
CN104532853B (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN107700479A (en) A kind of construction method of large diameter drill hole pile
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN104746519A (en) Obstacle clearing construction method
CN113605383A (en) A steel protects a section of thick bamboo is transferred in merogenesis for bored concrete pile construction
CN113174961A (en) Side slope foundation pit supporting method
CN100557144C (en) A kind of method of removing the bored pile construction obstacle
CN112281880A (en) Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam
JP6319935B2 (en) Tubing pile driving method
CN108978661B (en) Construction method for removing cast-in-situ bored pile
CN203007940U (en) Tubular pile protection structure in side slope hammering construction
CN206143760U (en) Ally oneself with formula of arranging bored concrete pile device on water
CN108330963A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN109989346B (en) Bridge large-diameter precast concrete tubular column foundation and construction method thereof
CN104264679A (en) Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles
CN207633225U (en) The small spacing abutment constructing structure of neighbouring running railway line
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN102758434B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN210621709U (en) Inclined support foundation pit supporting structure based on steel pipe pile and Larsen steel plate
CN103306291B (en) Oblique pull concrete pile solid protection wide-angle abrupt slope device
CN206173949U (en) Concatenation formula does not have spin of spoir and strengthens piling bar

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: China Oilfield Services Limited

Patentee after: China Offshore Oil Group Co., Ltd.

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee before: China Oilfield Services Limited

Patentee before: China National Offshore Oil Corporation