JP2005282839A - Construction method for pipeline - Google Patents
Construction method for pipeline Download PDFInfo
- Publication number
- JP2005282839A JP2005282839A JP2004102215A JP2004102215A JP2005282839A JP 2005282839 A JP2005282839 A JP 2005282839A JP 2004102215 A JP2004102215 A JP 2004102215A JP 2004102215 A JP2004102215 A JP 2004102215A JP 2005282839 A JP2005282839 A JP 2005282839A
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- pipeline
- manhole
- lining
- power cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
Description
本発明は管路の施工方法に関し、複数本並設電力ケーブル管路の一部をガス輸送用管路として臨機応変に転用することを可能にするものである。 The present invention relates to a method for constructing a pipeline, and makes it possible to divert a part of a plurality of juxtaposed power cable pipelines as gas transport pipelines.
地中送電線路においては、洞道式の場合、ガス輸送等と合わせた合同式とすることがあるが、管路式の場合は同一ルートであってもガス輸送管路等を別個に施工し、電力ケーブル用とガス輸送用のそれぞれの専用設備を構築している。 In the underground transmission line, in the case of the tunnel type, it may be combined with the gas transportation, etc., but in the case of the pipeline type, the gas transportation pipeline etc. is constructed separately even if it is the same route. The company has built dedicated facilities for power cables and gas transportation.
電力ケーブル用管路の構築とガス輸送用管路の構築とは、路面の掘削、管材の接続・敷設、マンホールの打設、掘削溝の埋め戻しの点で共通し、送電やガス輸送開始後は、マンホール内での定期的な保守・点検を必要とする点でも共通する。
而るに、従来では、同一ルートの場合でも、電力ケーブル用管路とガス輸送用管路とを個別に構築しており、(1)構築コストが高くつく、(2)工期が長く、付近住民への迷惑、交通障害の長期化が懸念される、(3)掘削面積の拡大が避けられずアスファルトや再生不可掘削土等の産業廃棄物の増大による環境悪化が余儀なくされる、(4)別設備による維持・保守コストのアップが避けられない等の不都合がある。
前記電力ケーブル管路とガス輸送管路の基本的な相違点は、後者が気密性を不可欠とするのに対し、前者では気密性は勿論のこと水密性も要求されないことにある。すなわち、電力ケーブル管路では、ガラス繊維強化プラスチック管やアスベスト管等の管路材を単なる嵌合により接合し、その接合箇所の非水密性のために管路内へ侵入する雨水等がマンホール内に管路口を経て流入するのを防止するように、その管路口に防水部を装着している。
Construction of pipelines for power cables and pipelines for gas transportation are common in terms of excavating road surfaces, connecting and laying pipe materials, placing manholes, and filling back excavation grooves, and after power transmission and gas transportation start Is common in that it requires regular maintenance and inspection in the manhole.
Thus, conventionally, even in the case of the same route, the power cable conduit and the gas transport conduit are individually constructed, (1) the construction cost is high, (2) the construction period is long, and the vicinity There are concerns about inconvenience to residents and prolonged traffic obstacles. (3) Expansion of excavation area is inevitable, and environmental degradation will be inevitable due to increase in industrial waste such as asphalt and non-renewable excavated soil. (4) There are inconveniences such as an increase in maintenance and maintenance costs due to separate equipment.
The basic difference between the power cable pipeline and the gas transport pipeline is that the latter requires airtightness, whereas the former does not require watertightness as well as airtightness. In other words, in power cable pipelines, pipe materials such as glass fiber reinforced plastic pipes and asbestos pipes are joined by simple fitting, and rainwater that enters the pipelines due to the non-watertightness of the joints in the manholes. A waterproof part is attached to the pipe opening so as to prevent it from flowing into the pipe through the pipe opening.
ガス輸送管、水道管等の老朽既設管路を構成する方法として、プラスチックパイプを元の円形断面形状を記憶させて屈曲縮小させ、これを既設管内に挿入し、挿入後に管端から蒸気を吹き込んで加熱し、その後エアーに切り替えて拡径しながら冷却していく内面ライニング法が知られている。(例えば、特許文献1参照) As a method of constructing aging existing pipes such as gas transport pipes and water pipes, plastic pipes are memorized in their original circular cross-sectional shape, bent and reduced, inserted into existing pipes, and steam is blown from the pipe ends after insertion. There is known an inner lining method in which heating is performed at a temperature and then cooling is performed while switching to air and expanding the diameter. (For example, see Patent Document 1)
本発明の目的は、前記内面ライニング法により複数本並設電力ケーブル用管路の一部をガス輸送用管路に転用できるようにして電力ケーブル用管路とガス輸送用管路の構築施工の共通化により構築コストの低廉化等を図り、前記した不都合を排除することにある。 An object of the present invention is to construct a power cable conduit and a gas transport conduit by allowing a part of a plurality of parallel power cable conduits to be diverted to a gas transport conduit by the inner surface lining method. The common purpose is to reduce the construction cost and to eliminate the inconveniences described above.
請求項1の管路の施工方法は、複数本並設の電力ケーブル管路の少なくとも一本の管路内面をポリオレフィンパイプでライニングし、その少なくとも一本の管路をガス輸送管路とすることを特徴とする。
The pipe line construction method according to
請求項2の管路の施工方法は、請求項1の電力ケーブル管路の施工方法において、円形断面形状を記憶させた屈曲縮小ポリオレフィンパイプを少なくとも一本の管路内に挿入し、この挿入パイプを元の形状に拡径させることによりライニングを行なうことを特徴とする。
The pipe construction method according to claim 2 is the construction method of the power cable pipe construction according to
請求項3の管路の施工方法は、途中にマンホールを含む複数の径間にわたって請求項1または2の施工方法により少なくとも一本の管路内面をポリオレフィンパイプでライニングし、前記のマンホール内において両側のライニングポリオレフィンパイプ間を気密に接続することを特徴とする。 According to a third aspect of the pipe construction method, at least one pipe inner surface is lined with a polyolefin pipe by a construction method according to the first or second aspect over a plurality of spans including manholes in the middle, and both sides are disposed in the manhole. The lining polyolefin pipes are hermetically connected.
請求項4の管路の施工方法は、途中にマンホールを含む複数の径間にわたって請求項1または2の施工方法により少なくとも一本の管路内面をポリオレフィンパイプでライニングし、マンホール両側のライニングポリオレフィンパイプ間をマンホールを迂回するガス管で導通することを特徴とする。 The pipe line construction method according to claim 4 is a method of lining at least one pipe inner surface with a polyolefin pipe by a construction method according to claim 1 or 2 over a plurality of spans including manholes in the middle, and lining polyolefin pipes on both sides of the manhole. It is characterized by being connected with a gas pipe that bypasses the manhole.
請求項5の管路の施工方法は、請求項3の電力ケーブル管路の施工方法において、マンホール内のガス輸送管部分とその接続部を同じマンホール内の電力ケーブル部分とその接続部に対して迂回させることを特徴とする。
The construction method of the pipeline of claim 5 is the construction method of the power cable pipeline of
請求項6の管路の施工方法は、請求項5の電力ケーブル管路の施工方法において、マンホール内のガス輸送管部分とその接続部を保護管で包囲することを特徴とする。 A construction method for a pipeline according to claim 6 is characterized in that, in the construction method for a power cable pipeline according to claim 5, the gas transport pipe portion in the manhole and its connecting portion are surrounded by a protective tube.
請求項7の管路の施工方法は、請求項1〜6何れかの電力ケーブル管路の施工方法において、ポリオレフィンパイプとしてポリエチレンパイプを使用することを特徴とする。 According to a seventh aspect of the present invention, there is provided a method for constructing a pipeline, wherein a polyethylene pipe is used as the polyolefin pipe in the method for constructing a power cable pipeline according to any one of the first to sixth aspects.
請求項8の管路の施工方法は、請求項1〜7何れかの施工方法により構築した電力ケーブル用・ガス輸送用複合管路のライニングポリオレフィンパイプを撤去してガス輸送用管路を電力ケーブル用管路に戻すことを特徴とする。
The pipe construction method according to claim 8 is the power cable / gas transport composite pipeline constructed by the construction method according to any one of
複数本並設電力ケーブル管路の少なくとも一本の管路内面をポリオレフィンパイプでライニングするだけでガス輸送管路を構築でき、路面の掘削、管材の接続・敷設、マンホールの打設、掘削溝の埋め戻しを電力ケーブル用管路とガス輸送用管路に共通化できる。
而して、(1)ライニングによる工費増加よりも上記の共通化による工費コスト低減の方が勝り、この工費コスト低減の有利性を充分に保持でき、構築工費を低減できる、(2)ライニング工期よりも上記の共通化による工期短縮の方が大きく、この工期短縮の有利性を充分に保持でき、構築工期を短縮できる、(3)上記の共通化による掘削面積の減少によりアスファルトや再生不可掘削土等の産業廃棄物量を低減でき、環境悪化を軽減できる、(4)マンホールの共通化により電力ケーブルとガスの保守・点検作業のコストダウンを図ることができる。
また、ライニングポリオレフィンパイプを土圧等の外圧に対し管材で補強でき、ポリオレフィンパイプをそれだけ薄くでき、ライニングポリオレフィンパイプの可撓性向上のために、ライニングポリオレフィンパイプの挿入作業の容易化を図ることができる。
A gas transport pipeline can be constructed simply by lining the inner surface of at least one pipeline of multiple power cable pipelines with polyolefin pipes, excavating road surfaces, connecting and laying pipe materials, placing manholes, Backfilling can be made common to power cable pipelines and gas transport pipelines.
Thus, (1) the cost reduction due to the above-mentioned commonization is superior to the increase in the labor cost due to the lining, and the advantages of this cost reduction can be sufficiently retained, and the construction cost can be reduced. The shortening of the construction period due to the above-mentioned standardization is larger than the above, and the advantages of this shortening of the construction period can be fully maintained, and the construction period can be shortened. The amount of industrial waste such as soil can be reduced and environmental degradation can be reduced. (4) The common use of manholes can reduce the cost of maintenance and inspection work for power cables and gas.
In addition, the lining polyolefin pipe can be reinforced with pipe material against external pressure such as earth pressure, the polyolefin pipe can be made thinner, and the lining polyolefin pipe can be easily inserted to improve the flexibility of the lining polyolefin pipe. it can.
特に、請求項2によれば、円形の原形を記憶させたライニング用ポリオレフィンパイプを加熱による原形復元力によっても拡径させているから、拡径のための内圧をそれだけ低くでき、ライニング用ポリオレフィンパイプの挿入も低い牽引力で行ない得、ライニングを容易に行ない得る。 In particular, according to the second aspect of the present invention, since the diameter of the lining polyolefin pipe in which the circular original shape is memorized is also expanded by the original shape restoring force by heating, the internal pressure for the diameter expansion can be lowered accordingly, and the lining polyolefin pipe can be reduced accordingly. Can be inserted with low traction, and lining can be performed easily.
特に、請求項3によれば、ガス輸送距離を電力ケーブル管路の径間を単位として設定でき、ガス供給地点の遠近に容易に対応できる。 In particular, according to the third aspect, the gas transport distance can be set in units of the span of the power cable conduit, and can easily correspond to the distance of the gas supply point.
特に、請求項4によれば、マンホール内にガス管配設のためのスペースをとる必要がなく、電力ケーブルの保守・点検作業を容易に行ない得、ケーブルオフセットによる管路内ケーブルの熱伸縮も通常通り行なわせることができる。また、電力ケーブルとガスラインとをマンホール箇所においても土砂を介して安全に隔離でき、電力工作物基準及びガス工作物基準の保証に万全を期することができる。 In particular, according to the fourth aspect, it is not necessary to provide a space for disposing the gas pipe in the manhole, the maintenance and inspection work of the power cable can be easily performed, and the thermal expansion and contraction of the cable in the pipeline due to the cable offset is also possible. It can be done as usual. In addition, the power cable and the gas line can be safely isolated via the earth and sand even at the manhole location, and it is possible to make sure that the power work standard and the gas work standard are guaranteed.
特に、請求項5によれば、マンホールでのガス点検を容易に行ない得、また、管路内ケーブルの熱収縮に伴うマンホール内ケーブルオフセットの変動をスムーズに行なわせて管路内ケーブルの熱収縮を良好に吸収できる。 In particular, according to the fifth aspect, the gas inspection in the manhole can be easily performed, and the cable offset in the manhole is smoothly changed due to the thermal contraction of the cable in the duct so that the thermal contraction of the cable in the duct is performed. Can be absorbed well.
特に、請求項6によれば、管路材により外圧に対し補強されたライニングポリオレフィンパイプと同等の耐外圧強度をマンホールのガス輸送管部分にも付与でき、ガス輸送管全体の耐外圧性を保証できる。 In particular, according to claim 6, the external pressure strength equivalent to the lining polyolefin pipe reinforced against the external pressure by the pipe material can be given to the gas transport pipe portion of the manhole, and the external pressure resistance of the entire gas transport pipe is guaranteed. it can.
特に、請求項7によれば、ポリエチレンの柔軟性(引っ張り破断伸びが大)、軽量性(比重が小)のために、ライニング作業の一層の容易化を図ることができる。 In particular, according to the seventh aspect, the lining work can be further facilitated due to the flexibility (high tensile elongation at break) and lightness (small specific gravity) of polyethylene.
以下、図面を参照しつつ本発明の実施の形態について説明する。
図1の(イ)は本発明により構築される電力ケーブル用・ガス輸送用複合管路を示す縦断面図、図1の(ロ)は図1の(イ)におけるA部分の拡大上面説明図である。
図1において、1,…は多段・多行(3段・3行)の複数本並設電力ケーブル管路を示し、所定の径間(通常300m)で設置したマンホール10の間に定尺管路材(ガラス繊維強化プラスチック管、アスベスト管等)11を単純な嵌合方式で接続・敷設し、その一連の接続管路材の両端を砂付け加工のうえマンホール10のコンクリート壁101に埋着してある。21は電力ケーブル用管路1c内に引き込んだ電力ケーブル、22はケーブル接続部であり、ケーブル接続管両側のケーブル部分23にオフセットを形成し、管路口に防水部24を装着してある。1gはガス輸送管路として使用する管路であり、ポリオレフィンパイプ例えばポリエチレンパイプ3を内面にライニングすることにより気密性としてある。
前記ポリオレフィンパイプ3においては、土圧等の外圧が管路材11で支承されるから、輸送ガス圧(内圧)のみから寸法、材質を設定でき、その最高使用内圧MOPが、最小要求強度(50年後)をMRS、総合安全係数をk(ガス協会では3以上を推奨)、管外径/管厚みをSDRとすると、
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 (a) is a longitudinal sectional view showing a composite conduit for power cable and gas transport constructed according to the present invention, and FIG. 1 (b) is an enlarged top view of the portion A in FIG. 1 (a). It is.
In FIG. 1,
In the
MOP=2MRS/〔k(SDR−1)〕
で与えられ、例えば輸送ガス圧0.3Mpa(天然ガス)に対しては、安全率kを3、SDRを17として、温度40℃(通常輸送ガス温度は20℃とされるが、ケーブル発熱による加熱を勘案し40℃とすることが安全である)でのMRSが7.95Mpaの高密度ポリエチレンを使用できる。
MOP = 2MRS / [k (SDR-1)]
For example, for a transport gas pressure of 0.3 Mpa (natural gas), the safety factor k is 3 and the SDR is 17, and the temperature is 40 ° C. (normally the transport gas temperature is 20 ° C. A high-density polyethylene having an MRS of 7.95 Mpa at 40 ° C. in consideration of heating can be used.
本発明に係る管路の施工方法は、同一ルートで電力ケーブル線路とガス輸送導管路とを同時期に構築する場合、既設の電力ケーブル線路の空き管路を途中からガス輸送管路として使用する場合等に適用できる。 The construction method of a pipeline according to the present invention uses an existing pipeline of an existing power cable line as a gas pipeline from the middle when a power cable line and a gas pipeline are constructed at the same time on the same route. Applicable to cases.
ガス輸送管路の一端側をガス供給源基地に、中間や他端側をガスユーザにそれぞれ導通する必要があり、ガス輸送管路の一端側、中間や他端側の地上への導出にマンホールを使用できない場合、径間の途中を掘削してその導出を行なわなければならないが、その掘削時に他の管路材や電力ケーブルを傷付けることのないように、最上段の何れかの管路、例えば上段中央の管路をガス輸送用として利用することが望ましい。 One end of the gas transport line must be connected to the gas supply source base, and the middle and other end must be connected to the gas user. Must be excavated in the middle of the span and led out, but to avoid damaging other pipe materials and power cables during the excavation, one of the uppermost pipes, For example, it is desirable to use the upper center pipe for gas transportation.
図2は請求項2の管路の施工方法において使用するライニング用ポリエチレンパイプの一例の断面を示し、点線で示す円形断面を記憶させて屈曲縮小させたオメガ型であり、管路内径Dに対し、巾WをW≦0.75D、高さHをH≦0.75D、内間隙d≧5mmとしてあり、管路内径100〜150mmに対し、口径150A、厚みt=8.5mmのポリエチレンパイプを使用できる。
このライニング用ポリエチレンパイプを製造するには、ポリエチレンを円形パイプに押出し、これを冷却する間の高温域で上記オメガ型に漸次に成形し、次いで常温近くに急冷してそのオメガ形状を冷凍・記憶させる方法をとることができる。
FIG. 2 shows a cross section of an example of a polyethylene pipe for lining used in the pipe line construction method according to claim 2, which is an omega type in which a circular cross section indicated by a dotted line is stored and bent and reduced, The width W is W ≦ 0.75D, the height H is H ≦ 0.75D, the inner gap d ≧ 5 mm, and a polyethylene pipe having a diameter 150A and a thickness t = 8.5 mm is used for a pipe inner diameter of 100 to 150 mm. Can be used.
In order to manufacture this polyethylene pipe for lining, polyethylene is extruded into a circular pipe, and it is gradually formed into the above-mentioned omega type at a high temperature range while it is cooled, and then rapidly cooled to near room temperature to freeze and store the omega shape. Can be taken.
請求項2の管路の施工方法によりガス輸送用管路にポリエチレンパイプをライニングするには、図2に示すライニング用ポリエチレンパイプを巻き取ったドラムを図3の(イ)に示すようにマンホール上に固定し、ライニング用ポリエチレンパイプ30の先端に牽引ワイヤ31を連結し、ウインチ32でワイヤ31を牽引してライニング用ポリエチレンパイプ30を前記したガス輸送用管路1g内に挿入する。ライニング用ポリエチレンパイプ30の断面の巾W及び高さHを、W≦0.75D、H≦0.75Dとして管路内径Dよりも充分に小さくしてあるから、この挿入は容易である。
この挿入後は、図3の(ロ)に示すように挿入パイプ一端を高圧・高温ホース配管33によりボイラー34に連通し、前記挿入パイプをスチームによる加熱で原形の円形に向け拡径復元させて管路内面に密着させ、而るのち、ボイラーをエアーコンプレッサーに切り替えてエアーの送入により冷却していく。
In order to line the polyethylene pipe on the gas transport pipe by the pipe line construction method according to claim 2, the drum around which the polyethylene pipe for lining shown in FIG. 2 is wound is placed on the manhole as shown in FIG. The pulling
After this insertion, as shown in FIG. 3 (b), one end of the insertion pipe is connected to the
図4は請求項3の管路の施工方法の要部を示す図面であり、マンホール10を挾む両側の管路部の少なくとも一本の管路、例えば上段中央の管路の内面に前記と同様にしてポリエチレンパイプをライニングし、次いでそれらのライニングポリエチレンパイプ間をマンホール10内で接続管300により気密に接続している。
FIG. 4 is a view showing a main part of the method for constructing a pipeline according to
図5は請求項4の管路の施工方法により構築した電力ケーブル用・ガス輸送用複合管路の要部を示し、マンホールを挾む両側の管路部の最上段中央管路内にポリエチレンパイプをライニングした後、各ライニングポリエチレンパイプの管路口端部を栓体3001の融着またはパイプ端部の圧潰融着等により閉塞し、マンホール10を迂回するガス管3000、例えばポリエチレン管で両ライニングパイプ端部を気密に接続している。
FIG. 5 shows the main part of the composite cable pipeline for power cable and gas transport constructed by the pipeline construction method of claim 4, and the polyethylene pipe is placed in the uppermost central pipeline on both sides of the manhole. After lining the pipe, the end of the pipe opening of each lining polyethylene pipe is closed by fusing the
請求項5の管路の施工方法では、前記ライニングしたポリエチレンパイプ間を直接に、またはポリエチレンガス管を介して気密に接続し、マンホール内でのガス管部分を保護管で包囲する二重管構造としている。
ライニングパイプとして用いるポリエチレンパイプの線熱膨張係数は電力ケーブルの線熱膨張係数に較べてかなり大であるが(電力ケーブルの線熱膨張係数2×10−5/Kに対し14〜15×10−5/K)、保護管(例えばSUS)の曲げ剛性をポリエチレンパイプの曲げ剛性よりも相当に大とすれば、ライニングポリエチレンパイプのマンホールへ向けての熱伸縮を保護管で抑制し、その熱伸縮を管路内で吸収させることが期待できる。
また、保護管を気密構造としてあり、マンホール内へのガス漏れ防止に万全をきすることができ、マンホール内での保守・点検作業を安全に行うことができる。
6. The pipe construction method according to claim 5, wherein the lined polyethylene pipes are hermetically connected directly or via a polyethylene gas pipe, and the gas pipe portion in the manhole is surrounded by a protective pipe. It is said.
Although linear thermal expansion coefficient of the polyethylene pipes to be used as lining pipe is considerably large compared to the linear thermal expansion coefficient of the power cable (power linear thermal expansion of the cable coefficient 2 × 10 -5 / K to 14 to 15 × 10 - 5 / K), if the bending rigidity of the protective pipe (for example, SUS) is made considerably larger than the bending rigidity of the polyethylene pipe, the thermal expansion and contraction of the lining polyethylene pipe toward the manhole is suppressed by the protective pipe. Can be expected to be absorbed in the pipeline.
In addition, the protective tube has an airtight structure, which can prevent gas leaks into the manhole and can safely perform maintenance and inspection work in the manhole.
図6の(イ)及び(ロ)は上記したマンホール内でのポリエチレンパイプの接続及び保護施工の一例を示している。
この施工に先立ち、ガス輸送用とする管路1gの管路口1g’に図7に示すように保護短管301を挿入し、この挿入した保護短管301の奥端を管路材(ガラス繊維強化プラスチック管、アスベスト管)内面に接着材301’で固定しておく。
この保護短管301には、例えばSUSを使用できる。接着材には、例えばガラスクロスとガラス不織布との積層物にエポキシ樹脂を含浸したものを使用し、エポキシ樹脂未硬化の状態で接合面に貼り付け、次いで加熱により樹脂を硬化させることができる。
図6に示す施工例では、ガス輸送用と定めた管路にライニング用ポリエチレンパイプを引込み、図6の(イ)に示すようにマンホール内にライニング用ポリエチレンパイプを所定長さ引出し、この引出したポリエチレンパイプ端部3eに保護管本体302を挿通し、保護管本体302を保護短管301に気密に連結(通常、フランジ連結)する。この保護管本体はテレスコープスライド部302’を中間に有している。この保護管本体302も保護短管301と同様にSUS製とすることができる。
このようにマンホール内のポリエチレンパイプ引出し端部3eに保護管本体302を挿通したのちは、既述したライニング用ポリエチレンパイプの拡径復元を行ない、而るのち、拡径復元された両ポリエチレンパイプ引出し端部を継手41により気密に接続する。この継手41には、内面に電熱線を埋め込んだポリエチレン製の電気融着継手を用い、前記接続を加熱融着により行なうことができる。
このようにして両ポリエチレンパイプ引出し端部を気密に接続したのちは、図6の(ロ)に示すように保護管本体302のテレスコープスライド部302’を伸ばして保護管本体302,302相互間を気密に連結し(通常、フランジ連結)、前記テレスコープスライド部302’,302’をシールテープの巻き付け等で気密化し、保護短管と管路材との前記接着材による気密性及保護管本体と保護短管間の接続箇所の気密性との協働で保護管の気密性を確保し、これにて施工を終了する。
FIGS. 6A and 6B show an example of connection and protective construction of polyethylene pipes in the manhole.
Prior to this construction, as shown in FIG. 7, a protective
For example, SUS can be used for the protective
In the construction example shown in FIG. 6, a polyethylene pipe for lining is drawn into a pipe line designated for gas transportation, and the polyethylene pipe for lining is drawn out into a manhole for a predetermined length as shown in FIG. The protective tube
After inserting the protective tube
After the polyethylene pipe lead-out ends are connected in an airtight manner in this way, the
図8の(イ)及び(ロ)はマンホール内でのポリエチレンパイプの接続及び保護施工の上記とは別の例を示している。
この施工例では、ガス輸送用と定めた管路にライニング用ポリエチレンパイプを引込み、図8の(イ)に示すようにマンホール10内にライニング用ポリエチレンパイプを所定長さ引出し、この引出したポリエチレンパイプ端部3eに、保護管本体(例えばSUS製)303を挿通し、この保護管本体303を保護短管301に連結する。ポリエチレン直線管42には、テレスコープスライド付き保護管本体(例えばSUS製)304を挿通しておく。
マンホール10内のポリエチレンパイプ引出し端部3eに保護管本体303を挿通したのちは、既述したライニング用ポリエチレンパイプの拡径復元を行ない、而るのち、図8の(ロ)に示すように拡径復元された両ポリエチレンパイプ引出し端部管30e,30eを継手43,43を介してポリエチレン直線管42により気密に接続する。
継手43には、内面に電熱線を埋め込んだポリエチレン製の電気融着継手を用い、前記接続を加熱融着により行なうことができる。
この接続後は、保護管本体304のテレスコープスライド304’を伸ばしたうえで保護管本体304の両端と保護管本体303,303とを気密に連結し、これにて施工を終了する。
(A) and (b) of FIG. 8 show another example of connection and protection construction of polyethylene pipes in the manhole.
In this construction example, a polyethylene pipe for lining is drawn into a pipe line designated for gas transportation, and a polyethylene pipe for lining is drawn into a
After the protective pipe
As the joint 43, a polyethylene electric fusion joint having an inner surface embedded with a heating wire is used, and the connection can be performed by heat fusion.
After this connection, the
図9の(イ)及び(ロ)はマンホール内でのポリエチレンパイプの接続及び保護施工の上記とは別の例を示している。
この施工例では、ガス輸送用と定めた管路を既述したライニング用ポリエチレンパイプの拡径復元によりライニングし、而るのち、図9の(イ)に示すように、このライニングポリエチレンパイプ3の管路口にポリエチレンベント管44を継手45により気密に接続し、このベント管44に逆方向のポリエチレンベント管441を継手46により気密に接続し、逆方向ベント管441,441間をポリエチレン直線管42で継手47,47を介して気密に接続する。
継手45,46,47には、内面に電熱線を埋め込んだポリエチレン製の電気融着継手を用い、前記接続を加熱融着により行なうことができる。
この接続後は、図9の(ロ)に示すように、ポリエチレンベント管、ポリエチレン直線管、継手を分割保護管本体305で気密に包囲し、保護管本体305の両端と保護短管301,301とを気密に連結し、これにて施工を終了する。
この分割保護管本体305は、SUS製とすることができ、図9の(ハ)に示すように一方の割れ片305aの両側にアダプタ306を溶接し、他方の割れ片305bをパテテープ307を介して嵌合し、両片305a,305bをステンレスバンド308で締め付けて上下割れ目の締結・シールを行ない、長手方向に対する割れ目をパッキングを介してのフランジ連結で締結・シールを行なう構成とすることができる。
(A) and (b) of FIG. 9 show an example different from the above-described connection and protection construction of the polyethylene pipe in the manhole.
In this construction example, the pipeline defined for gas transportation is lined by expanding the diameter of the polyethylene pipe for lining described above, and then, as shown in FIG. A
For the
After this connection, as shown in FIG. 9B, the polyethylene vent pipe, the polyethylene straight pipe, and the joint are hermetically surrounded by the divided protective pipe
The split protective tube
図10の(イ)及び(ロ)はマンホール内でのポリエチレンパイプの接続及び保護施工の上記とは別の例を示している。
この施工例では、ガス輸送用と定めた管路を既述したライニング用ポリエチレンパイプの拡径復元によりライニングし、而るのち、図10の(イ)に示すように、このライニングポリエチレンパイプ3の管路口にポリエチレン直線管440をエルボ継手450により気密に接続し、ポリエチレン直線管440,440の間を逆方向のエルボ460,460を介してポリエチレン直線管42により気密に接続する。
エルボ450,460には、内面に電熱線を埋め込んだポリエチレン製の電気融着エルボを用い、前記接続を加熱融着により行なうことができる。
この接続後は、図10の(ロ)に示すように、ポリエチレン直線管42,440,440、エルボ450,450,460,460を分割保護管本体315で気密に包囲し、保護管本体315の両端を保護短管301,301に気密に連結し、これにて施工を終了する。
この施工例で使用する分割保護管本体315の上下割れ目の締結・シール構造や長手方向に対する割れ目の締結・シール構造は、図9の施工例で使用した分割保護管本体305と同様な構成とすることができる。
(A) and (b) of FIG. 10 show another example of connection and protection construction of polyethylene pipes in the manhole.
In this construction example, the pipeline defined for gas transportation is lined by expanding the diameter of the polyethylene pipe for lining described above, and then, as shown in FIG. A polyethylene
For the
After this connection, as shown in FIG. 10B, the polyethylene
The structure of the split protective tube
本発明に係る管路の施工方法は、低廉かつ迅速に電力及びガス供給設備を提供して大口ガス事業ビジネスを支援すると共に既設電力設備を有効に活用して管路資産価値の向上を図るところに意義があり、ガス需要がなくなれば、ライニングポリエチレンパイプ及びマンホール内二重管等を撤去し、送電専用の管路に戻すことができる。 The pipeline construction method according to the present invention is intended to provide a power and gas supply facility at low cost and promptly to support a large gas business and to improve the asset value of the pipeline by effectively utilizing the existing power facility. If there is no need for gas, the lining polyethylene pipe, the double pipe in the manhole, etc. can be removed and returned to the pipeline dedicated for power transmission.
1,… 複数本並設管路
1c 電力ケーブル用管路
1g ガス輸送用管路
10 マンホール
11 管路材
21 電力ケーブル
22 ケーブル接続管
23 ケーブルオフセット
3 ライニングポリエチレンパイプ
30 形状記憶ポリエチレンパイプ
30e マンホール内ポリエチレンパイプ引出し端部
300 マンホール内ガス接続管
3000 マンホール迂回ガス管
301 保護管
302 保護管
303 保護管
304 保護管
305 保護管
315 保護管
DESCRIPTION OF
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004102215A JP2005282839A (en) | 2004-03-31 | 2004-03-31 | Construction method for pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2004102215A JP2005282839A (en) | 2004-03-31 | 2004-03-31 | Construction method for pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2005282839A true JP2005282839A (en) | 2005-10-13 |
Family
ID=35181445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2004102215A Pending JP2005282839A (en) | 2004-03-31 | 2004-03-31 | Construction method for pipeline |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2005282839A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009191960A (en) * | 2008-02-14 | 2009-08-27 | Osaka Prefecture Univ | Pipeline for helium gas |
CN105221835A (en) * | 2015-10-29 | 2016-01-06 | 浙江铭仕集团有限公司 | The method of construction of gas pipeline system |
CN114418137A (en) * | 2021-12-02 | 2022-04-29 | 中冶南方(武汉)自动化有限公司 | Cable tunnel intelligent inspection and maintenance method and system based on SCADA platform |
-
2004
- 2004-03-31 JP JP2004102215A patent/JP2005282839A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009191960A (en) * | 2008-02-14 | 2009-08-27 | Osaka Prefecture Univ | Pipeline for helium gas |
CN105221835A (en) * | 2015-10-29 | 2016-01-06 | 浙江铭仕集团有限公司 | The method of construction of gas pipeline system |
CN114418137A (en) * | 2021-12-02 | 2022-04-29 | 中冶南方(武汉)自动化有限公司 | Cable tunnel intelligent inspection and maintenance method and system based on SCADA platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101424649B1 (en) | A pipe repair tube with reinforced crack- resistant property | |
JP5666551B2 (en) | Composite hose for low temperature fluid transfer | |
AU2013249208B2 (en) | A system and method for reinforcing composite pipes | |
RU132461U1 (en) | COMMUNICATION COLLECTOR MODULE, MAIN TUNNEL AND INPUT CAMERA MODULE | |
JP2005282839A (en) | Construction method for pipeline | |
JP5620675B2 (en) | Pipe repair structure, repair method and laminated lining material | |
JP5537254B2 (en) | Tunnel fire extinguishing piping structure | |
JP4890312B2 (en) | Pipe bridge rehabilitation method | |
JP2008183840A (en) | Construction method of regenerating pipe line, and liner for pipe line regeneration | |
JP4364568B2 (en) | Pipe line forming method and pipe line structure | |
JP4909795B2 (en) | Pipeline rehabilitation method | |
FI77923B (en) | FOERFARANDE FOER AOSTADKOMMANDE AV EN TRANSPORTKANAL. | |
CN112987210A (en) | Sensing optical fiber unit structure for pipeline risk monitoring and early warning and construction method | |
JP6944181B2 (en) | Connecting pipe and laying method of connecting pipe | |
JP2021045948A (en) | Lining material and manufacturing method of lining material | |
JP4889615B2 (en) | Existing line lining method | |
US20210285590A1 (en) | Methods, systems, and apparatus for providing access for telecommunication cables in utility piping | |
US9273801B1 (en) | Method of in-situ pipeline replacement | |
JP5656665B2 (en) | Tunnel fire-extinguishing piping structure, tunnel fire-extinguishing pipe branching structure, tunnel fire-extinguishing pipe heat insulation structure, and prevention method for strength reduction of tunnel fire-extinguishing pipe | |
CN110904781B (en) | Structure and method for paving refrigeration pipeline of ice rink | |
KR101523270B1 (en) | A Water Turning Method and Repairing Method for Pipe Lines with Non-Excavation | |
KR100915950B1 (en) | method for connecting a tube of underground cable to the other | |
JP5733903B2 (en) | Partial repair structure for pipes for sewerage | |
JP2018091433A (en) | Repairing method of fire extinguishing piping in tunnel | |
JP5066288B2 (en) | Line rehabilitation liner |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20061130 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090907 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090915 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20100202 |