JP2005242844A - Process planning processor and program - Google Patents

Process planning processor and program Download PDF

Info

Publication number
JP2005242844A
JP2005242844A JP2004053797A JP2004053797A JP2005242844A JP 2005242844 A JP2005242844 A JP 2005242844A JP 2004053797 A JP2004053797 A JP 2004053797A JP 2004053797 A JP2004053797 A JP 2004053797A JP 2005242844 A JP2005242844 A JP 2005242844A
Authority
JP
Japan
Prior art keywords
work
plan
data
parallel
process plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2004053797A
Other languages
Japanese (ja)
Inventor
Sukemasa Nakamoto
祐昌 中本
Katsunori Sako
勝則 迫
Toshio Suzuki
俊夫 鈴木
Hajime Okamoto
肇 岡本
Takeshi Misu
健 三栖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wood One Co Ltd
Original Assignee
Wood One Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wood One Co Ltd filed Critical Wood One Co Ltd
Priority to JP2004053797A priority Critical patent/JP2005242844A/en
Publication of JP2005242844A publication Critical patent/JP2005242844A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To solve the problem in a conventional process planning that the necessary construction period from start to completion of construction on a process plan is determined by building up times necessary for individual works, and when the construction period desired by a consumer is shorter than the necessary construction period, the process plan is corrected by trial and error. <P>SOLUTION: To enable the systematic correction of the process plan in a case that the desired construction period is shorter than the necessary construction period, parallel work attribute information showing whether each process is workable in parallel or not and order replacement attribute information showing whether the work order of each process is replaceable or not are assigned to routing data 2. When a correction of the process plan such as shortening of the construction period is needed, it is examined whether the attribute information of each process is ON or OFF, and processes which are ON are preferentially selected, and set as a parallel work, or the order of the processes are replaced to facilitate the parallel working with another process, whereby the construction period is shortened. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、建築工事などの多数の工程を含む工事についての工程計画を作成する工程計画作成処理装置とそのプログラムに関する。本発明は、特に着工日から竣工日までの工期に制約がある場合の工程計画の最適化に関するものである。   The present invention relates to a process plan creation processing apparatus and program for creating a process plan for construction including a number of processes such as construction work. The present invention relates to optimization of a process plan particularly when there is a restriction in the work period from the start date to the completion date.

住宅などの建築工事では、工事の進捗状況にあわせて、土台から躯体、造作、建具、内装など、様々な種類の工事が入り組んで行われる。それぞれの工事に必要な資材は、工事の時期に合わせて準備しておかなければならず、また専門性をもつ作業者は予め確保しておかなければならない。そのため、その場その場で工事の手順を決めたり、変更したりすることは難しいので、しっかりした工程計画を作成しておくことが重要である。   In building construction such as housing, various types of construction are carried out from the foundation to the frame, construction, joinery, interior, etc. according to the progress of construction. Materials necessary for each construction must be prepared in accordance with the time of construction, and specialist workers must be secured in advance. For this reason, it is difficult to decide or change the construction procedure on the spot, so it is important to create a solid process plan.

建築工事の工程計画は、着工から竣工までに必要とされる個々の工事単位を工程として捉えて、各工程を施工順に結んでシーケンスを作り、バーチャート図やネットワーク図で表わしたものである。従来の工程計画作成システムでは、工事に必要な工期は、工程計画で与えられる着工から竣工までの工程シーケンス中の個々の工程に必要とされる作業時間を積み上げて計算していた。たとえば、〔特許文献1〕に示す特開2000−1988号公報には、工事(工程)別の個々の必要実働日数を求めて、それらの個々の必要実働日数を集計することにより全体の必要実働日数(必要工期)を算出し、この必要工期をさらに希望工期から差し引いて全体の余裕日数を求め、この余裕日数を種々の工事遅延リスクに応じて各工程に配分し、想定工期を決定する技術が開示されている。
特開2000−1988号公報
The construction work process plan is a process in which each work unit required from the start to the completion is regarded as a process, and a sequence is created by connecting the processes in the order of construction, and is represented by a bar chart diagram or a network diagram. In the conventional process plan creation system, the work period required for the work is calculated by accumulating the work time required for each process in the process sequence from start to completion given in the process plan. For example, in Japanese Patent Laid-Open No. 2000-1988 shown in [Patent Document 1], the total necessary working days are obtained by calculating the individual necessary working days for each construction (process) and totaling those individual working days. Technology that calculates the number of days (required work period), further subtracts this necessary work period from the desired work period, finds the total number of days, and allocates this time to each process according to various construction delay risks to determine the expected work period Is disclosed.
Japanese Unexamined Patent Publication No. 2000-1988

従来の工程計画作成システムでは、着工から竣工までの全体に必要な工期は、個々の工事に必要な時間を積み上げて求めており、顧客の希望工期が必要工期よりも長いことを前提にしていた。しかし、顧客によっては、希望工期が必要工期ぎりぎりであったり、希望工期が必要工期よりも短い場合もあった。そのような場合、従来の工程計画作成システムでは、試行錯誤的方法で工程計画を修正するほかない状況であった。   In the conventional process planning system, the time required for the entire process from start to completion is determined by accumulating the time required for each work, and the customer's desired time is longer than the required time. . However, depending on the customer, the desired work period may be just below the required work period, or the desired work period may be shorter than the necessary work period. In such a case, in the conventional process plan creation system, the process plan must be corrected by a trial and error method.

本発明は、顧客の希望工期が工程計画上の必要工期よりも短い場合であっても、システム的に工程計画を修正して、必要工期の短縮を図ることを可能にするものである。そのため本発明では、工程計画立案のベースになる各工順の情報に、予め、工程は並行作業が可能かどうかを示す並行作業属性情報と、その工程の作業順序を前後させることが可能かどうかを示す順序入替属性情報をもたせ、工程計画立案処理で工期短縮等の隘路の緩和が必要となった場合に、まず各工程についてこれらの属性情報がONかOFFかを調べ、ONである工程を優先的に選択して、その工程自身を並行作業化するなり、前後の工程を入れ替えて他の工程との並行作業化を容易にして、工期短縮が可能となるようにするものである。   The present invention makes it possible to correct the process plan systematically and shorten the required work period even when the customer's desired work period is shorter than the necessary work period in the process plan. Therefore, in the present invention, in the information of each routing that becomes the basis of the process planning, the parallel work attribute information indicating whether or not the process can be performed in parallel and the work order of the process can be changed in advance. If it is necessary to alleviate the bottleneck such as shortening the work period in the process planning process, first check whether these attribute information is ON or OFF for each process. It is selected preferentially and the process itself is converted into parallel work, and the previous and subsequent processes are replaced to facilitate parallel work with other processes so that the construction period can be shortened.

本発明は、以下のように構成することができる。
〔1〕工程計画を立案し、立案した工程計画の隘路を検出して修正提案を作成できる工程計画作成処理装置であって、
工程計画立案の基礎となる各工程の工順データにそれぞれの工程の作業が並行化可能であるかどうか、およびシーケンス中で前後の入替が可能かどうかについての属性情報をもたせて記憶装置に記憶する工順データ記憶部と、
立案した工程計画の隘路検出時に、上記工順データの属性情報を参照して、作業が並行化可能な工程の並行化あるいは前後の入替が可能な工程の入替を行うように修正提案を作成する修正提案作成処理部とを備え、
修正提案に基づき工順データ記憶部の工順データを更新し、工程計画を修正することを特徴とする工程計画作成処理装置の構成。
〔2〕 工程計画作成の要素となる個々の工程の作業と資源の情報を管理する工程データを記憶した工程データ記憶部と、
上記工程データの工程ごとに、所定の施工単位内での当該工程に関わるシーケンス情報と、当該工程の作業が並行作業できるものかどうかを識別可能にする並行作業属性情報と、シーケンス中で当該工程の順序を入替できるものかどうかを識別可能にする順序入替属性情報とを管理する工順データを記憶した工順データ記憶部と、
希望工期や作業人員などの工程計画立案条件の入力に基づき、上記工順データを組み合わせて工程計画を立案処理し、工程計画データを作成する工程計画立案処理部と、
作成された工程計画データを解析して、隘路となる部分を検出する隘路検出処理部と、 検出された工程計画の隘路について、上記工順データの並行作業属性情報あるいは順序入替属性情報を参照し、並行作業が可能な工程の作業の並行化あるいは順序入替が可能な工程の順序入替により隘路を緩和する修正提案を作成する修正提案作成処理部と、
を備えていることを特徴とする工程計画作成処理装置の構成。
〔3〕 上記工順コードは、シーケンス情報として、少なくとも当該工程の工程コード、シーケンスを起動するトリガ工程の情報、シーケンス中での当該工程の前および後ろの工程の情報を含むことを特徴とする前項2に記載の工程計画作成処理装置の構成。
〔4〕 上記修正提案作成処理部が並行作業が可能な工程を並行作業化する場合は、必要とされる作業の熟練度の低い工程を優先的に選択することを特徴とする前項2に記載の工程計画作成処理装置の構成。
〔5〕 上記工程計画立案処理部は、工程計画を立案する際、つながりのある複数の工程があればそれらを優先的に選択して工程計画を組むことを特徴とする前項2に記載の工程計画作成処理装置の構成。
〔6〕 上記修正提案作成処理部は、並行作業が可能な工程を選択してそれを並行作業化する場合、作業効率アップの度合いに作業人員増加に伴うロス率を掛けて修正することを特徴とする前項2ないし5のいずれかに記載の工程計画作成処理装置の構成。
〔7〕 工程の作業が並行化可能であるかどうか、およびシーケンス中で前後の入替が可能かどうかについての属性情報をもたせた工順データを用いて工程計画を立案する工程計画立案処理手段と、
立案した工程計画の隘路を検出する隘路検出処理手段と、
検出された隘路について、上記工順データの属性情報を参照し、作業が並行化可能な工程の並行化あるいは前後の入替が可能な工程の入替を行うように修正提案を作成する修正提案作成処理手段と、
修正提案に基づき工順データ更新する工順データ更新処理手段と、
を備えていることを特徴とする工程計画作成処理プログラムの構成。
The present invention can be configured as follows.
[1] A process plan creation processing apparatus capable of drafting a process plan, detecting a bottleneck in the drafted process plan and creating a correction proposal,
Store in the storage device with attribute information about whether or not the work of each process can be performed in parallel with the routing data of each process that is the basis of process planning, and whether or not replacement is possible before and after in the sequence A routing data storage unit,
When a bottleneck is detected in the drafted process plan, a correction proposal is created by referring to the attribute information of the above routing data so that the process can be parallelized or the process can be replaced before and after. A correction proposal creation processing unit,
A configuration of a process plan creation processing device, wherein the process plan data in the process data storage unit is updated based on a correction proposal, and the process plan is corrected.
[2] A process data storage unit that stores process data for managing information on work and resources of individual processes that are elements of process plan creation;
For each process of the process data, sequence information related to the process within a predetermined construction unit, parallel work attribute information that makes it possible to identify whether the work of the process can be performed in parallel, and the process in the sequence A routing data storage unit that stores routing data for managing the order replacement attribute information that makes it possible to identify whether or not the order can be replaced;
Based on the input of process plan planning conditions such as the desired work period and work personnel, the process plan planning processing unit that creates the process plan data by formulating the process plan by combining the above routing data,
Analyze the created process plan data and refer to the parallel work attribute information or the order change attribute information of the above routing data for the bottleneck detection processing unit that detects the part that becomes the bottleneck and the bottleneck of the detected process plan. A correction proposal creation processing unit that creates a correction proposal that relaxes the bottleneck by parallelizing the work of processes that can be performed in parallel or by changing the order of processes that can be changed in order;
The structure of the process plan preparation processing apparatus characterized by comprising.
[3] The route code includes, as sequence information, at least a process code of the process, information of a trigger process for starting the sequence, and information of processes before and after the process in the sequence. A configuration of the process plan creation processing apparatus according to the preceding item 2.
[4] The method described in the above item [2], wherein when the correction proposal creation processing unit converts a process capable of parallel work into parallel work, a process having a low skill level of the required work is preferentially selected. Of the process plan creation processing apparatus.
[5] The process according to item 2 above, wherein when the process plan is drafted, the process plan is created by preferentially selecting a plurality of processes that are connected to form a process plan. Configuration of the plan creation processing device.
[6] The correction proposal creation processing unit, when selecting a process capable of parallel work and converting it to parallel work, corrects the degree of increase in work efficiency by multiplying by the loss rate accompanying the increase in work personnel. The configuration of the process plan creation processing apparatus according to any one of the preceding items 2 to 5.
[7] Process planning processing means for planning a process plan using routing data having attribute information about whether or not process operations can be performed in parallel and whether or not replacement can be performed before and after the sequence. ,
A bottleneck detection processing means for detecting a bottleneck in the planned process plan;
Correction proposal creation processing for creating a correction proposal for the detected Kushiro, referring to the attribute information of the above-mentioned routing data, and performing the parallelization of the process in which the work can be performed in parallel or the replacement of the process capable of being replaced before and after Means,
Routing data update processing means for updating routing data based on the correction proposal;
The structure of the process plan creation processing program characterized by comprising.

図1は、本発明による工程計画作成処理装置の概念図である。図中、1は工程データ記憶部、2は工程データ記憶部に記憶されている工程データ、3は工順データ記憶部、4は工順データ記憶部に記憶されている工順データ、5は工程計画立案処理部、6は立案された工程計画データ、7は工程計画データ6を解析して隘路(ボトルネック)を検出する隘路検出処理部、8は検出された隘路データ、9は隘路データ8を解析して隘路を緩和する工順修正提案を作成する修正提案作成処理部、10は工順修正提案データ、11は作成された工順修正提案データ10に基づいて工順データ4を更新する工順データ更新処理部である。ここで、工程データ記憶部1と工順データ記憶部3は、コンピュータのファイル記憶手段を用いて実現され、また工程計画立案処理部5、隘路検出処理部7、修正提案作成処理部9は、工順データ更新処理部11は、それぞれコンピュータのCPUによるプログラム処理手段を用いて実現される。   FIG. 1 is a conceptual diagram of a process plan creation processing apparatus according to the present invention. In the figure, 1 is the process data storage unit, 2 is the process data stored in the process data storage unit, 3 is the routing data storage unit, 4 is the routing data stored in the routing data storage unit, 5 is A process plan planning processing unit, 6 is the planned process plan data, 7 is a bottleneck detection processing unit that analyzes the process plan data 6 and detects a bottleneck, 8 is the detected bottleneck data, and 9 is the bottleneck data. A correction proposal creation processing unit that analyzes the process 8 and creates a process correction proposal that relaxes the bottleneck, 10 updates the process correction proposal data, 11 updates the process data 4 based on the created process correction proposal data 10 The routing data update processing unit. Here, the process data storage unit 1 and the routing data storage unit 3 are realized by using a file storage means of a computer, and the process plan planning processing unit 5, the bottleneck detection processing unit 7, and the correction proposal creation processing unit 9 are The routing data update processing unit 11 is realized by using program processing means by a CPU of a computer.

図示の工程データ記憶部1に記憶されている工程データ2は例示的なものであるが、個々の工程の作業内容や資源に関わる情報を保持しており、たとえばCAD図面から抽出される情報を元に編集して作成される。そのデータ項目としては、工程データの識別情報ID、工程コード、工程名、商品品目コード、歩掛(必要時間と商品単位)などの情報を含む。また工順データ記憶部3に記憶されている工順データ4の情報は、工程計画対象の全施工スケジュールの中で、部分的な施工単位にかかわる少数の工程からなる作業グループの手順のシーケンスを管理するものである。工順データ4は、各工程について作成され、図示の例では、データ項目として、工順データの識別情報ID、シーケンス中の当該工程の工程コード、シーケンスの先頭の工程を示すトリガ工程の情報、当該工程の前と後の工程の情報、当該工程の作業が並行作業できるものかどうかを識別可能にする並行作業属性情報、シーケンス中で当該工程の順序を入替できるものかどうかを識別可能にする順序入替属性情報などの情報を含んでいる。   The process data 2 stored in the illustrated process data storage unit 1 is exemplary, but holds information related to work contents and resources of each process, for example, information extracted from a CAD drawing. Originally created by editing. The data items include information such as process data identification information ID, process code, process name, merchandise item code, and yield (required time and merchandise unit). In addition, the information of the routing data 4 stored in the routing data storage unit 3 is a sequence of work group procedures consisting of a small number of processes related to a partial construction unit in the entire construction schedule to be processed. It is something to manage. The routing data 4 is created for each process, and in the example shown in the figure, as data items, the routing data identification information ID, the process code of the process in the sequence, the trigger process information indicating the first process in the sequence, Information on the process before and after the process, parallel work attribute information that makes it possible to identify whether the work of the process can be performed in parallel, and whether the order of the process can be switched in the sequence Information such as order replacement attribute information is included.

工程計画立案処理部5は、工程計画の立案条件として与えられる希望工期(着工日、竣工日)、投入人員数などの条件と、あらかじめ編集された工順データの作業手順のシーケンスにもとづき各工程を結合し、工程計画を立案し、工程計画データ6として出力する。   The process plan planning processing unit 5 determines each process based on conditions such as a desired work period (start date, completion date) and the number of input personnel given as process plan planning conditions and a sequence of work procedures of route data edited in advance. Are combined to create a process plan and output as process plan data 6.

隘路検出処理部7は、工程計画データ6を解析して、先に与えた工期や作業人員などの立案条件が満たされているかどうかをチェックする。たとえば、工程計画データ6の工程計画において、その計画全体の実行に必要な工期や作業人員の総数が希望工期や希望人員数を上回っていた場合には、所要時間の長い工程や投入人員数の多い工程を隘路部分として抽出する。   The bottleneck detection processing unit 7 analyzes the process plan data 6 and checks whether or not the planning conditions such as the construction period and work personnel given previously are satisfied. For example, in the process plan of the process plan data 6, if the total work period and the total number of workers required for the execution of the entire plan exceed the desired work period and the desired number of persons, Many processes are extracted as the Kushiro part.

修正提案作成処理部9は、隘路として抽出された工程について、その工順データの並行作業属性情報と順序入替属性情報を参照し、並行作業が可能な工程、あるいは前後入替が可能な工程を選択する。たとえば並行作業が可能な工程については、その工程の投入人員数を増やして作業の並行化を図り、所要時間を短縮し、また前後入替が可能な工程は、その工程を前あるいは後ろにずらして他の工程との並行化を図ることによりトータルの所要時間を短縮する修正提案を作成する。   The correction proposal creation processing unit 9 refers to the parallel work attribute information and the order replacement attribute information of the routing data for the process extracted as a bottleneck, and selects a process that can be performed in parallel or a process that can be replaced before and after. To do. For example, for a process that can be performed in parallel, increase the number of input personnel for that process to parallelize the work, shorten the required time, and for processes that can be switched back and forth, shift the process forward or backward. A correction proposal is made to shorten the total time required by paralleling with other processes.

工順データ更新処理部11は、作成された修正提案に基づき、工順データ記憶部3の工順データ4を更新する。工程計画立案処理部5は、更新された工順データ4に基づき再び工程計画の立案処理を実行し、修正された工程計画データ6を作成する。   The routing data update processing unit 11 updates the routing data 4 in the routing data storage unit 3 based on the created correction proposal. The process plan planning processing unit 5 executes the process planning process again based on the updated routing data 4 and creates corrected process plan data 6.

図2は、隘路検出と作業並行化(人員増)による修正提案作成例の説明図である。図2の(a)は、作業手順のシーケンスのモデルを例示したものであり、A,B,C,D,Eは、シーケンスに結合された工程である。この例では、A,B,Eの工程は単独作業であるが、CとDの工程の作業はすでに並行化されている。図2の(b)は、(a)のモデルについての工程計画データと修正提案例を示す。ここで、並行化されている工程CとDに注目すると、それぞれの所要時間は8時間と16時間であり、他の工程の所要時間よりも長いので、計画上の隘路(*で示す)として判定されている。特に、工程Cの所要時間は8時間であるが、Dの所要時間は16時間となっており、工程Cは自己の作業が終了しても8時間経たないと工程Eへ進むことができない。この場合、工程Dの作業時間を短縮できれば、それだけ工程Eの作業開始を早めることが可能であるので、工程Dの現在の投入人員数1を2に増やす修正提案を作成する。ただし、投入人員数と所要時間との間には必ずしも比例関係は働かないことが経験的に分かっているので、ここでは12%のロス率を見込み、得られる所要時間を9時間として修正提案することになる。   FIG. 2 is an explanatory diagram of an example of creating a correction proposal by detecting a bottleneck and paralleling work (increasing personnel). FIG. 2A illustrates a model of a sequence of work procedures, and A, B, C, D, and E are processes connected to the sequence. In this example, the processes of A, B, and E are independent operations, but the operations of the processes of C and D are already parallelized. FIG. 2B shows process plan data and a correction proposal example for the model of FIG. Here, paying attention to the parallel processes C and D, the required time is 8 hours and 16 hours, which is longer than the time required for other processes. It has been judged. In particular, the time required for the process C is 8 hours, but the time required for D is 16 hours, and the process C cannot proceed to the process E until 8 hours have passed even after its work is completed. In this case, if the work time of the process D can be shortened, the start of the work of the process E can be accelerated accordingly, so a correction proposal for increasing the current number of input personnel 1 of the process D to 2 is created. However, since it is empirically known that the proportional relationship does not always work between the number of input personnel and the required time, here a 12% loss rate is expected and the proposed required time is 9 hours. It will be.

図3は、他の隘路検出と工程並行化による修正提案作成例の説明図である。図3の(a)は、現在の工程計画における直列モデルの例を示す。また図3の(c)は、その工程計画データと修正提案例を示す。ここで、工程CとDの所要時間は8時間と16時間であり、他の工程の所要時間よりも長いので、それぞれ計画上の隘路(*で示す)として判定されている。一方、工程CとDの並行作業属性には並行作業可(×で示す)が設定されているので、工程Cとを並行化する修正提案を作成する。図3の(b)は、作成された提案並列化モデルを示し、工程Dが前にずらされて、工程Cと一緒に作業を開始できるようになる結果、トータルの所要時間が8時間短縮される。   FIG. 3 is an explanatory diagram of an example of creating a correction proposal based on another bottleneck detection and process parallelization. FIG. 3A shows an example of a serial model in the current process plan. FIG. 3C shows the process plan data and a correction proposal example. Here, the time required for the processes C and D are 8 hours and 16 hours, which are longer than the time required for the other processes, and thus are determined as planned bottlenecks (indicated by *). On the other hand, since the parallel work attribute of processes C and D is set to allow parallel work (indicated by x), a correction proposal for making process C parallel is created. FIG. 3 (b) shows the created proposed parallel model, where the process D is shifted forward and the work can be started together with the process C. As a result, the total required time is reduced by 8 hours. The

本発明によれば、工程計画立案の基礎となる工程が、並行作業可能なものか、前あるいは後に順序入替できるものかを示す情報を、予め工順データに付加しておくので、工程計画に隘路が検出されたとき、改善すべき工程と改善の方法を簡単に判断することが可能になり、工程管理の効率化、迅速化が図られる。   According to the present invention, since information indicating whether the process that is the basis of the process planning is a work that can be performed in parallel or can be changed in order before or after is added to the routing data in advance, When a bottleneck is detected, it is possible to easily determine the process to be improved and the improvement method, and the process management can be made more efficient and faster.

図4ないし図7を用いて、本発明の実施例を説明する。図4は、本発明による工程計画作成処理装置の1実施例の機能説明図であり、必要な処理部とデータファイルをブロックで示し、ブロック間の関係と処理の流れを矢線で示す。また図5と図6の(a)〜(g)に、図4中の各データファイルのデータ構成を示す。図7はハードウエア構成図である。   An embodiment of the present invention will be described with reference to FIGS. FIG. 4 is a functional explanatory diagram of one embodiment of the process plan creation processing apparatus according to the present invention, showing necessary processing units and data files in blocks, and showing the relationship between the blocks and the flow of processing by arrows. 5 and 6 (a) to 6 (g) show the data structure of each data file in FIG. FIG. 7 is a hardware configuration diagram.

図4において、20は工程マスター管理部、21は商品マスター管理部、22は工順マスター管理部、23は工数計算部、24は並行作業ロス率マスター管理部、25は工程計画立案処理部、26は立案条件入力部、27は工程計画照会・変更部、28は隘路検出処理部、29は修正提案作成処理部、30は工順マスター更新処理部、31は工程マスター、32は商品マスター、33は積算見積データ、34は工順マスター、35は工程別作業時間データ、36は並行作業ロス率マスター、37は工程計画データ、38は隘路データ、39は工順修正提案データ、40aは工程計画ネットワーク図、40bは工程計画バーチャート図である。   In FIG. 4, 20 is a process master management unit, 21 is a product master management unit, 22 is a routing master management unit, 23 is a man-hour calculation unit, 24 is a parallel work loss rate master management unit, 25 is a process planning processing unit, 26 is a planning condition input unit, 27 is a process plan inquiry / change unit, 28 is a bottleneck detection processing unit, 29 is a correction proposal creation processing unit, 30 is a routing master update processing unit, 31 is a process master, 32 is a product master, 33 is integrated estimate data, 34 is a route master, 35 is work time data by process, 36 is a parallel work loss rate master, 37 is process plan data, 38 is Kushiro data, 39 is route correction proposal data, and 40a is a process. A plan network diagram 40b is a process plan bar chart diagram.

工程マスター管理部20は、工程の種類ごとに、工程コード、工程名、商品品目コード、歩掛(時間/商品単位)の各データにより工程データを編集して、工程マスター31を作成あるいは更新する。なお、商品品目コードは商品コードとリンクさせるためのコードである。   The process master management unit 20 creates or updates the process master 31 by editing the process data based on the process code, the process name, the product item code, and the yield (time / product unit) for each type of process. . The product item code is a code for linking with the product code.

商品マスター管理部21は、部材商品ごとに、商品コード、商品名、サイズ、単位、商品品目コードの各データにより商品データを編集して、商品マスター32を作成あるいは更新する。   The merchandise master management unit 21 creates or updates the merchandise master 32 by editing the merchandise data with each data of the merchandise code, the merchandise name, the size, the unit, and the merchandise item code for each member merchandise.

工順マスター管理部22は、図示されていない建築設計のCAD図面から必要な工程を抽出し、物件番号、工順種別、工順名、工順番号、工程コード、投入人員数、トリガー工程1、トリガー工程2、トリガー工程3、前工程1、前工程2、前工程3、後工程1、後工程2、後工程3、養生日数1、養生日数2、養生日数3、並行作業可能作業グループ区分、順序入替可能作業グループ区分の各データにより工順データを編集して、工順マスター34を作成あるいは更新する。ここで、工順種別は工法ID、工順名は工法名、トリガー工程1〜3はそれぞれ当該工程(工順データが対応している工程)を開始する上での条件工程の1番目〜3番目、前工程1、前工程2、前工程3と、後工程1、後工程2、後工程3はそれぞれ当該工程の直前と直後の工程、養生日数1、養生日数2、養生日数3はそれぞれトリガー工程の開始前または終了後の当該工程の終了または開始までの日数、並行作業可能作業グループ区分は並行作業が可能な作業グループとしての区分、順序入替可能作業グループ区分は順序の入れ替えが可能な作業グループとしての区分である。   The route master management unit 22 extracts necessary steps from the CAD drawing of the architectural design not shown, and the property number, route type, route name, route number, process code, number of workers, trigger process 1 , Trigger process 2, trigger process 3, pre-process 1, pre-process 2, pre-process 3, post-process 1, post-process 2, post-process 3, curing days 1, curing days 2, curing days 3, work group capable of parallel work The routing data is edited based on the data of the section and the work group section whose order can be changed, and the routing master 34 is created or updated. Here, the route type is the work method ID, the route name is the work method name, and the trigger steps 1 to 3 are the first to third of the condition steps for starting the step (step corresponding to the route data). The first step, the previous step 2, the previous step 3, the post step 1, the post step 2, and the post step 3 are the steps immediately before and after the step, the curing days 1, the curing days 2, and the curing days 3, respectively. The number of days until the end or start of the process before or after the start of the trigger process, the work group classification that can be performed in parallel work is classified as a work group capable of parallel work, and the order of work group sections that can be reordered can be switched This is a division as a work group.

工数計算部23は、工程マスター31の各工程データと、商品マスター32の関連する商品データと、関連する積算見積データ33とに基づいて、工程ごとの工数計算を行い、工程別作業時間データ35を作成する。ここで、積算見積データは物件番号、商品コード、積算数量の各データからなり、工数計算部23は、工程マスター31の各工程データの歩掛で積算見積データの積算数量を除算して、作業時間を算出する。出力される工程別作業時間データ35は、物件番号、工程コード、工程名、作業時間の各データからなる。   The man-hour calculation unit 23 calculates man-hours for each process based on each process data of the process master 31, related product data of the product master 32, and related integrated estimated data 33, and process-specific work time data 35. Create Here, the integrated estimate data is composed of each data of the property number, the product code, and the integrated quantity, and the man-hour calculating unit 23 divides the integrated quantity of the integrated estimated data by the step of each process data of the process master 31 to work Calculate time. The output work time data 35 by process is composed of each data of property number, process code, process name, and work time.

並行作業ロス率マスター管理部24は、並行作業が可能な工程ごとに、投入人員を増やした時の干渉等により効率低下するロス率を、過去のデータ等から求めて並行作業ロス率データとして、並行作業ロス率マスター36に登録する。並行作業ロス率データは、工程コード1、工程コード2、工程コード3、人員数、ロス率の各データからなる。工程コード1〜3は、並列化により同時進行する工程のコードであり、1工程のみの人員数を増やして複数人員で並列化する場合も含む。人員数は並列化されている人員の数であり、ロス率は、その人員数におけるロス率を示す。   The parallel work loss rate master management unit 24 obtains, as parallel work loss rate data, a loss rate that decreases in efficiency due to interference or the like when increasing the number of employees for each process that can be performed in parallel work, from past data, etc. Register in the parallel work loss rate master 36. The parallel work loss rate data includes data of process code 1, process code 2, process code 3, number of personnel, and loss rate. The process codes 1 to 3 are codes of processes that proceed simultaneously by parallelization, and include cases where the number of personnel in only one process is increased and parallelized by a plurality of personnel. The number of personnel is the number of personnel in parallel, and the loss rate indicates the loss rate in the number of personnel.

工程計画立案処理部25は、工順マスター34の各工順データと、並行作業ロス率マスター36のロス率データと、立案条件入力部26から与えられた立案条件とに基づいて、工程計画を立案し、工程計画データ37を作成する。工程計画は予めモデルごとにパターン化したものを登録しておき、工程計画をする際、建築対象にもっとも近いパターンを選択して使用する。工程計画立案処理部25は、選択したパターンに沿って各工程を配置し、工程ごとにその所要時間から、順次、開始日時と終了日時を設定し、その他関連するデータを編集して行く。   The process plan planning processing unit 25 performs process planning based on each routing data of the routing master 34, loss rate data of the parallel work loss rate master 36, and planning conditions given from the planning condition input unit 26. A process plan data 37 is created. The process plan is registered in advance for each model, and when the process plan is made, the pattern closest to the building object is selected and used. The process planning processing unit 25 arranges each process along the selected pattern, sets the start date and time and the end date and time sequentially from the required time for each process, and edits other related data.

このようにして作成された工程計画データ37には、物件番号、工順種別、工順番号、工程コード、投入人員数、所要時間、開始日時、終了日時、前工程、後工程、並行作業可能作業グループ区分、順序入替可能作業グループ区分、希望終了日、実際終了日の各データが含まれる。ここで、開始日時は当該工程についての予定での開始日時、終了日時は当該工程までの各工程の所要時間を積み上げることで得られる予定での終了日時であり、実際終了日は実績での当該工程の終了日時のデータである。実際終了日を入力するようにしておくと、修正提案作成処理では、開始日からではなく、まだ実際終了日が入力されていない(施工できていない)工程についてのみ、修正提案を作成できる。工程計画データ37に対しては、工程計画照会・変更部27から直接照会して参照したり、データを書き換えて変更することができ、また工程計画ネットワーク図40aや工程計画バーチャート図40bを印刷出力することができる。   In the process plan data 37 thus created, the property number, routing type, routing number, process code, number of workers, required time, start date / time, end date / time, previous process, subsequent process, and parallel work are possible. Each data includes work group category, order changeable work group category, desired end date, and actual end date. Here, the start date / time is the scheduled start date / time for the process, the end date / time is the planned end date / time obtained by accumulating the time required for each process up to the process, and the actual end date is the actual date / time It is data of the end date and time of the process. If the actual end date is input, in the correction proposal creation process, the correction proposal can be created only for the process for which the actual end date has not yet been input (not completed), not from the start date. The process plan data 37 can be referred to directly from the process plan inquiry / change unit 27, or can be changed by rewriting the data, and the process plan network diagram 40a and the process plan bar chart diagram 40b are printed. Can be output.

隘路検出処理部28は、工程計画データ37を読み出して解析し、図2、図3で説明したように、隘路となっている箇所の工程を指摘する隘路データ38を作成する。   The bottleneck detection processing unit 28 reads out and analyzes the process plan data 37, and creates the bottleneck data 38 indicating the process at the location that is a bottleneck, as described with reference to FIGS.

修正提案作成処理部は、隘路データ38により、工程計画データ37中で隘路とされた工程について、並行作業可能作業グループ区分、順序入替可能作業グループ区分の情報を参照して、並行作業が可能であったり、順序入替が可能であった場合には、工順修正提案データ39を作成する。投入人員を増やして工期を短縮しようとする場合には、投入可能な各工程についてそれぞれ投入効率を調べ、もっとも投入効率の良い工程から順次選択して工順修正提案データ39を作成する。工順修正提案データ39は、物件番号、工順種別、工順番号、工程コード、投入人員数、提案投入人員数、前工程、後工程、提案前工程、提案後工程の各データからなっている。工順修正提案で投入する人員数は、予め決められている最大投入可能人員数まで、順次増やして行くようにする。   The correction proposal creation processing unit can perform parallel work by referring to the information on the work group classification capable of parallel work and the work group classification capable of order change with respect to the process designated as a bottleneck in the process plan data 37 based on the bottleneck data 38. If there is a change in the order, the route correction proposal data 39 is created. In order to shorten the work period by increasing the number of input personnel, the input efficiency is checked for each process that can be input, and the process correction proposal data 39 is created by sequentially selecting the processes with the highest input efficiency. The route correction proposal data 39 is composed of data of property number, route type, route number, process code, number of input personnel, number of proposed input personnel, pre-process, post-process, pre-proposed process, post-proposed process data. Yes. The number of personnel to be input in the routing correction proposal is increased gradually up to a predetermined maximum number of personnel that can be input.

工順マスター更新処理部30は、工順修正提案データ39を工順マスター34に反映させるための更新処理を行う。工程計画立案処理部25は、更新された工順マスター34のデータにより再び工程計画立案処理を行い、希望の工期が満たされるまで、上記の過程が繰り返される。   The route master update processing unit 30 performs an update process for reflecting the route correction proposal data 39 on the route master 34. The process planning process unit 25 performs the process planning process again with the updated data of the routing master 34, and the above process is repeated until the desired schedule is satisfied.

図7は、本発明による工程計画作成処理装置の1実施例のハードウエア構成図である。図中、41はCPU,42はキーボード、43は表示装置、44はプリンタ、45は通信インタフェース、46は記憶装置を示し、いずれも、一般的なコンピュータが備えているものである。記憶装置46には、ハードウエアを本発明の工程計画作成処理装置として機能させるためのプログラム50〜60と、データファイル61〜69が格納されている。ここで、50は工程マスター管理プログラム、51は商品マスター管理プログラム、52は工順マスター管理プログラム、53は工数計算プログラム、54は並行作業ロス率マスター管理プログラム、55は工程計画立案処理プログラム、56は立案条件入力プログラム、57は工程計画照会・変更プログラム、58は隘路検出処理プログラム、59は修正提案作成処理プログラム、60は工順マスター更新処理プログラムであり、それぞれ、図4の工程マスター管理部20、商品マスター管理部21、工順マスター管理部22、工数計算部23、並行作業ロス率マスター管理部24、工程計画立案処理部25、立案条件入力部26、工程計画照会・変更部27、隘路検出処理部28、修正提案作成処理部29、工順マスター更新処理部30の各機能を実現するためにCPU41により実行されるプログラムである。   FIG. 7 is a hardware configuration diagram of an embodiment of a process plan creation processing apparatus according to the present invention. In the figure, 41 is a CPU, 42 is a keyboard, 43 is a display device, 44 is a printer, 45 is a communication interface, and 46 is a storage device, both of which are provided in a general computer. The storage device 46 stores programs 50 to 60 and data files 61 to 69 for causing the hardware to function as the process plan creation processing device of the present invention. Here, 50 is a process master management program, 51 is a product master management program, 52 is a work order master management program, 53 is a manhour calculation program, 54 is a parallel work loss rate master management program, 55 is a process planning process program, 56 Is a planning condition input program, 57 is a process plan inquiry / change program, 58 is a bottleneck detection processing program, 59 is a correction proposal creation processing program, and 60 is a routing master update processing program. 20, product master management unit 21, work order master management unit 22, man-hour calculation unit 23, parallel work loss rate master management unit 24, process plan planning processing unit 25, planning condition input unit 26, process plan inquiry / change unit 27, Kushiro detection processing unit 28, correction proposal creation processing unit 29, routing master update processing unit 30 A program executed by the CPU41 to implement each function.

また図7の工程マスター61、商品マスター62、積算見積データ63、工順マスター64、工程別作業時間データ65、並行作業ロス率マスター66、工程計画データ67、隘路データ68、工順修正提案データ69の各データファイルは、それぞれ図4に31〜39で示されるデータファイルに対応するものである。   In addition, the process master 61, the product master 62, the integrated estimate data 63, the work order master 64, the work time data 65 for each process, the parallel work loss rate master 66, the process plan data 67, the Kushiro data 68, and the work order correction proposal data in FIG. Each of the data files 69 corresponds to the data files indicated by 31 to 39 in FIG.

図8は、本発明の実施例における作業工程シーケンスの説明図である。図示の例では、作業工程あるいは作業工程グループがブロックA,B(B1(B11,B12),B2(B21,B22),B3(B31,B32)),Cで示されている。この中で、AとBとCのような作業工程グループ間の順列関係は、下方向の矢線で結合して示され、B11、B12のように、1つのブロックで囲まれた作業工程同士は,並行化可能な作業工程のグループである。そしてまたB1とB2のように作業工程グループのブロック同士で入替可能なものは、上下の双方向の矢線で結合され、さらにB2とB3のように並行化可能な作業工程のブロック同士は、左右の双方向の矢線で結合して示される。   FIG. 8 is an explanatory diagram of a work process sequence in the embodiment of the present invention. In the illustrated example, work processes or work process groups are indicated by blocks A and B (B1 (B11, B12), B2 (B21, B22), B3 (B31, B32)), C. Among these, permutation relationships between work process groups such as A, B, and C are shown connected by a downward arrow, and work processes surrounded by one block like B11 and B12. Is a group of work processes that can be parallelized. And what can be exchanged between the blocks of the work process group like B1 and B2 are connected by the upper and lower bidirectional arrow lines, and the work process blocks that can be parallelized like B2 and B3 are It is shown connected with the left and right bidirectional arrows.

工程計画作成処理では、まず工程計画の立案条件として着工日時と竣工日時により希望工期を入力する。この立案条件のもとで工程計画立案処理を実行し、工順データにしたがって各作業工程を結合して計画を組み立てて行くが、このとき互いにつながりのある作業工程を優先的に組み込むようにする。このようなつながりのある作業工程間の直列的関係を考慮して工程計画を立案処理し、工程計画ができると、その必要工期を算出し、必要工期が立案条件として与えられている希望工期を満たしているかどうかを判定する。希望工期が満たされていれば、その工程計画を処理結果として終了するが、希望工期が満たされていない場合には隘路検出処理を行い、所要時間が長くて並行化が可能な作業工程を検出する。次に、検出した並行化が可能な作業工程の中で、歩掛のかかる(つまり手間のかかる)作業工程を優先的に選択して、作業人員を投入し、並行作業量を増やして工期の短縮を図る。しかし、投入作業人員数を増やしても通常は人数に比例して仕事量は増加せず、干渉により効率が低下するので、歩掛にはロス率を掛けて補正する必要がある。また歩掛は実際値を測定して可変とする。   In the process plan creation process, first, the desired work period is input by the start date and time and the completion date as process conditions. Under this planning condition, process planning process is executed, and each work process is combined according to the routing data to assemble the plan. At this time, work processes connected to each other are preferentially incorporated. . Considering the serial relationship between such connected work processes, the process plan is drafted, and when the process plan is made, the required work period is calculated, and the desired work period for which the required work period is given as the planning condition is calculated. Determine if it meets. If the desired work schedule is satisfied, the process plan ends as a processing result. If the desired work schedule is not satisfied, a bottleneck detection process is performed to detect work processes that can be parallelized for a long time. To do. Next, among the detected work processes that can be performed in parallel, the work process that requires a lot of work (that is, the time-consuming process) is selected preferentially, the workforce is added, and the amount of parallel work is increased. Shorten. However, even if the number of input workers is increased, the amount of work does not normally increase in proportion to the number of workers, and the efficiency decreases due to interference. Therefore, it is necessary to correct the yield by multiplying the loss rate. In addition, the actual value of the step is made variable.

次の〔表1〕は、異なる作業条件で作業人員数を1人から2人と3人に増やしたときのロス率をそれぞれ示したものである。なお、ロス率の値は、作業場所の部屋数や広さ(m2 )などの作業条件により異なってくるので、最適値を設定する。 The following [Table 1] shows the loss rates when the number of workers is increased from one to two and three under different working conditions. Note that the value of the loss rate varies depending on the work conditions such as the number of rooms and the area (m 2 ) of the work place, so an optimum value is set.

Figure 2005242844
作業の並行化は、同一種の作業の人員増による並行化ばかりでなく、前後に順序を変更できる作業を前あるいは後にずらすことによって、他の種類の作業との並行化を図ることができる。前後に順序を変更できる作業には、前あるいは後の作業とは作業手順上無関係な作業や、前あるいは後の作業の作業者の専門性とは異なる専門性を持つ作業者の行う作業、あるいは熟練不要の作業で作業者を投入しやすい作業などがある。このような並行化により隘路の作業を効率化する工順修正提案を作成して工程計画を修正し、希望工期が満たされるようにする。
Figure 2005242844
The parallelization of work is not limited to parallelization by increasing the number of people of the same type of work, but parallelism with other types of work can be achieved by shifting the work whose order can be changed forward or backward. Work that can be reordered back and forth includes work that is irrelevant to the work procedure of the previous or subsequent work, work performed by an operator with expertise different from that of the previous or subsequent work, or There are tasks that are easy to throw in workers without requiring skills. Such a parallelization creates a routing correction proposal that makes the Kushiro work more efficient and corrects the process plan so that the desired schedule is satisfied.

工期は、それぞれの作業工程の所要時間を積算することにより得られる。積算された結果の工期が希望工期を上回れば、前述した隘路検出により問題のある工程を検出して、人員投入による作業の並行化あるいは工程の前後入替を行って、工期の短縮を図る。   The work period is obtained by integrating the time required for each work process. If the accumulated work period exceeds the desired work period, the problem process is detected by the above-described Kushiro detection, and the work period is paralleled or replaced before and after the process by introducing personnel to shorten the work period.

本発明による工程計画作成処理装置の概念図である。It is a conceptual diagram of the process plan preparation processing apparatus by this invention. 隘路検出と作業並行化(人員増)による修正提案作成例の説明図である。It is explanatory drawing of the correction proposal preparation example by a Kushiro detection and work parallelization (personnel increase). 隘路検出と工程並行化による修正提案作成例の説明図である。It is explanatory drawing of the correction proposal preparation example by a Kushiro detection and process parallelization. 工程計画作成処理装置の1実施例の機能説明図である。It is function explanatory drawing of 1 Example of a process plan preparation processing apparatus. データファイルの構成説明図(その1)である。FIG. 3 is a first explanatory diagram illustrating the structure of a data file. データファイルの構成説明図(その2)である。FIG. 6 is a second diagram illustrating the structure of a data file. 工程計画作成処理装置の1実施例のハードウエア構成図である。It is a hardware block diagram of one Example of a process plan preparation processing apparatus. 作業工程シーケンスの説明図である。It is explanatory drawing of a work process sequence.

符号の説明Explanation of symbols

1:工程データ記憶部
2:工程データ
3:工順データ記憶部
4:工順データ
5:工程計画立案処理部
6:工程計画データ
7:隘路検出処理部
8:隘路データ
9:修正提案作成処理部
10:工順修正提案データ
11:工順データ更新処理部
1: Process data storage unit 2: Process data 3: Route data storage unit 4: Route data 5: Process plan processing unit 6: Process plan data 7: Kushiro detection processing unit 8: Kushiro data 9: Correction proposal creation processing Part 10: Route correction proposal data 11: Route data update processing part

Claims (7)

工程計画を立案し、立案した工程計画の隘路を検出して修正提案を作成できる工程計画作成処理装置であって、
工程計画立案の基礎となる各工程の工順データにそれぞれの工程の作業が並行化可能であるかどうか、およびシーケンス中で前後の入替が可能かどうかについての属性情報をもたせて記憶装置に記憶する工順データ記憶部と、
立案した工程計画の隘路検出時に、上記工順データの属性情報を参照して、作業が並行化可能な工程の並行化あるいは前後の入替が可能な工程の入替を行うように修正提案を作成する修正提案作成処理部とを備え、
修正提案に基づき工順データ記憶部の工順データを更新し、工程計画を修正することを特徴とする工程計画作成処理装置。
It is a process plan creation processing device that can formulate a process plan, detect a bottleneck in the drafted process plan and create a correction proposal,
Store in the storage device with attribute information about whether or not the work of each process can be performed in parallel with the routing data of each process that is the basis of process planning, and whether or not replacement is possible before and after in the sequence A routing data storage unit,
When a bottleneck is detected in the drafted process plan, a correction proposal is created by referring to the attribute information of the above routing data so that the process can be parallelized or the process can be replaced before and after. A correction proposal creation processing unit,
A process plan creation processing apparatus, wherein the process plan is corrected by updating the process data in the process data storage unit based on the correction proposal.
工程計画作成の要素となる個々の工程の作業と資源の情報を管理する工程データを記憶した工程データ記憶部と、
上記工程データの工程ごとに、所定の施工単位内での当該工程に関わるシーケンス情報と、当該工程の作業が並行作業できるものかどうかを識別可能にする並行作業属性情報と、シーケンス中で当該工程の順序を入替できるものかどうかを識別可能にする順序入替属性情報とを管理する工順データを記憶した工順データ記憶部と、
希望工期や作業人員などの工程計画立案条件の入力に基づき、上記工順データを組み合わせて工程計画を立案処理し、工程計画データを作成する工程計画立案処理部と、
作成された工程計画データを解析して、隘路となる部分を検出する隘路検出処理部と、 検出された工程計画の隘路について、上記工順データの並行作業属性情報あるいは順序入替属性情報を参照し、並行作業が可能な工程の作業の並行化あるいは順序入替が可能な工程の順序入替により隘路を緩和する修正提案を作成する修正提案作成処理部と、
を備えていることを特徴とする工程計画作成処理装置。
A process data storage unit that stores process data for managing information on work and resources of individual processes that are elements of process planning;
For each process of the process data, sequence information related to the process within a predetermined construction unit, parallel work attribute information that makes it possible to identify whether the work of the process can be performed in parallel, and the process in the sequence A routing data storage unit that stores routing data for managing the order replacement attribute information that makes it possible to identify whether or not the order can be replaced;
Based on the input of process plan planning conditions such as the desired work period and work personnel, the process plan planning processing unit that creates the process plan data by formulating the process plan by combining the above routing data,
Analyze the created process plan data and refer to the parallel work attribute information or the order change attribute information of the above routing data for the bottleneck detection processing unit that detects the part that becomes the bottleneck and the bottleneck of the detected process plan. A correction proposal creation processing unit that creates a correction proposal that relaxes the bottleneck by parallelizing the work of processes that can be performed in parallel or by changing the order of processes that can be changed in order;
A process plan creation processing apparatus characterized by comprising:
上記工順コードは、シーケンス情報として、少なくとも当該工程の工程コード、シーケンスを起動するトリガ工程の情報、シーケンス中での当該工程の前および後ろの工程の情報を含むことを特徴とする請求項2に記載の工程計画作成処理装置。   3. The route code includes, as sequence information, at least a process code of the process, information of a trigger process for starting the sequence, and information of processes before and after the process in the sequence. The process plan creation processing device described in 1. 上記修正提案作成処理部が並行作業が可能な工程を並行作業化する場合は、必要とされる作業の熟練度の低い工程を優先的に選択することを特徴とする請求項2に記載の工程計画作成処理装置。   3. The process according to claim 2, wherein when the correction proposal creation processing unit converts a process capable of performing parallel work into parallel work, a process having a low skill level of the required work is preferentially selected. Plan creation processing device. 上記工程計画立案処理部は、工程計画を立案する際、つながりのある複数の工程があればそれらを優先的に選択して工程計画を組むことを特徴とする請求項2に記載の工程計画作成処理装置。   3. The process plan creation according to claim 2, wherein when the process plan is drafted, if there are a plurality of processes that are connected, the process plan is created by preferentially selecting them. Processing equipment. 上記修正提案作成処理部は、並行作業が可能な工程を選択してそれを並行作業化する場合、作業効率アップの度合いに作業人員増加に伴うロス率を掛けて修正することを特徴とする請求項2ないし請求項5のいずれかに記載の工程計画作成処理装置。   The correction proposal creation processing unit, when selecting a process capable of parallel work and converting it to parallel work, corrects by multiplying the degree of increase in work efficiency by a loss rate accompanying an increase in work personnel. The process plan creation processing apparatus according to any one of claims 2 to 5. 工程の作業が並行化可能であるかどうか、およびシーケンス中で前後の入替が可能かどうかについての属性情報をもたせた工順データを用いて工程計画を立案する工程計画立案処理手段と、
立案した工程計画の隘路を検出する隘路検出処理手段と、
検出された隘路について、上記工順データの属性情報を参照し、作業が並行化可能な工程の並行化あるいは前後の入替が可能な工程の入替を行うように修正提案を作成する修正提案作成処理手段と、
修正提案に基づき工順データ更新する工順データ更新処理手段と、
を備えていることを特徴とする工程計画作成処理プログラム。
A process plan drafting processing means for drafting a process plan using routing data having attribute information on whether or not the work of the process can be performed in parallel and whether or not replacement can be performed before and after in the sequence;
A bottleneck detection processing means for detecting a bottleneck in the planned process plan;
Correction proposal creation processing for creating a correction proposal for the detected Kushiro, referring to the attribute information of the above-mentioned routing data, and performing the parallelization of the process in which the work can be performed in parallel or the replacement of the process capable of being replaced before and after Means,
Routing data update processing means for updating routing data based on the correction proposal;
A process plan creation processing program characterized by comprising:
JP2004053797A 2004-02-27 2004-02-27 Process planning processor and program Pending JP2005242844A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004053797A JP2005242844A (en) 2004-02-27 2004-02-27 Process planning processor and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004053797A JP2005242844A (en) 2004-02-27 2004-02-27 Process planning processor and program

Publications (1)

Publication Number Publication Date
JP2005242844A true JP2005242844A (en) 2005-09-08

Family

ID=35024496

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004053797A Pending JP2005242844A (en) 2004-02-27 2004-02-27 Process planning processor and program

Country Status (1)

Country Link
JP (1) JP2005242844A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007304942A (en) * 2006-05-12 2007-11-22 Nec Fielding Ltd Information processor, method for providing work procedure information, and program
JP2014048897A (en) * 2012-08-31 2014-03-17 Kobe Steel Ltd Production management system and production management method
KR20160032447A (en) * 2014-09-16 2016-03-24 현대건설주식회사 Interference management system of work space based on BIM and the method of the same
JP2020160638A (en) * 2019-03-26 2020-10-01 パナソニックIpマネジメント株式会社 Production management device and production plan creation method
JP2021051664A (en) * 2019-09-26 2021-04-01 株式会社東芝 Work support management system
WO2023043846A1 (en) * 2021-09-14 2023-03-23 Procore Technologies, Inc. Computer systems and methods for generating predictive change events
JP7500459B2 (en) 2021-02-16 2024-06-17 日立Geニュークリア・エナジー株式会社 Work process optimization support method and work process optimization support device

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60135167A (en) * 1983-12-24 1985-07-18 Masato Nishikata Surface treatment method of lens
JPH01257553A (en) * 1988-03-02 1989-10-13 Hitachi Ltd Scheduling/managing system
JPH08180106A (en) * 1994-12-22 1996-07-12 Hitachi Plant Eng & Constr Co Ltd Method and device for preparing process schedule
JPH08212264A (en) * 1994-12-09 1996-08-20 Toshiba Corp Scheduling device and scheduling method
JPH0916069A (en) * 1995-06-30 1997-01-17 Hitachi Plant Eng & Constr Co Ltd Creating method for process design and device thereof
JP2002007656A (en) * 2000-06-21 2002-01-11 Mitsubishi Heavy Ind Ltd Task progress estimation device and method, task schedule review device and method, and process progress expectation device and method
JP2002021175A (en) * 2000-07-10 2002-01-23 Kinden Corp Interior construction method for multiple dwelling house
JP2003050839A (en) * 2001-06-01 2003-02-21 Ishin Co Ltd Process management system for construction
JP2004013517A (en) * 2002-06-06 2004-01-15 Sekisui Chem Co Ltd Prefabricated house production planning system, production planning method and production planning program, and recording medium stored with its production planning program

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60135167A (en) * 1983-12-24 1985-07-18 Masato Nishikata Surface treatment method of lens
JPH01257553A (en) * 1988-03-02 1989-10-13 Hitachi Ltd Scheduling/managing system
JPH08212264A (en) * 1994-12-09 1996-08-20 Toshiba Corp Scheduling device and scheduling method
JPH08180106A (en) * 1994-12-22 1996-07-12 Hitachi Plant Eng & Constr Co Ltd Method and device for preparing process schedule
JPH0916069A (en) * 1995-06-30 1997-01-17 Hitachi Plant Eng & Constr Co Ltd Creating method for process design and device thereof
JP2002007656A (en) * 2000-06-21 2002-01-11 Mitsubishi Heavy Ind Ltd Task progress estimation device and method, task schedule review device and method, and process progress expectation device and method
JP2002021175A (en) * 2000-07-10 2002-01-23 Kinden Corp Interior construction method for multiple dwelling house
JP2003050839A (en) * 2001-06-01 2003-02-21 Ishin Co Ltd Process management system for construction
JP2004013517A (en) * 2002-06-06 2004-01-15 Sekisui Chem Co Ltd Prefabricated house production planning system, production planning method and production planning program, and recording medium stored with its production planning program

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007304942A (en) * 2006-05-12 2007-11-22 Nec Fielding Ltd Information processor, method for providing work procedure information, and program
JP4669813B2 (en) * 2006-05-12 2011-04-13 Necフィールディング株式会社 Information processing apparatus, work procedure information providing method, and program
JP2014048897A (en) * 2012-08-31 2014-03-17 Kobe Steel Ltd Production management system and production management method
KR20160032447A (en) * 2014-09-16 2016-03-24 현대건설주식회사 Interference management system of work space based on BIM and the method of the same
KR101663106B1 (en) * 2014-09-16 2016-10-06 현대건설 주식회사 Interference management system of work space based on BIM and the method of the same
JP2020160638A (en) * 2019-03-26 2020-10-01 パナソニックIpマネジメント株式会社 Production management device and production plan creation method
JP7403041B2 (en) 2019-03-26 2023-12-22 パナソニックIpマネジメント株式会社 Production control device and production planning method
JP2021051664A (en) * 2019-09-26 2021-04-01 株式会社東芝 Work support management system
JP7475832B2 (en) 2019-09-26 2024-04-30 株式会社東芝 Work support management system
JP7500459B2 (en) 2021-02-16 2024-06-17 日立Geニュークリア・エナジー株式会社 Work process optimization support method and work process optimization support device
WO2023043846A1 (en) * 2021-09-14 2023-03-23 Procore Technologies, Inc. Computer systems and methods for generating predictive change events

Similar Documents

Publication Publication Date Title
US7058588B2 (en) Dependency-based work flow integration and reduction
US20160070258A1 (en) Method for increasing the work performance of a manufacturing executing system (mes) and an enterprise resource planning system (erp)
US20020007297A1 (en) Method and system for enterprise wide production scheduling
US20010032108A1 (en) Process automation system
US8620708B2 (en) Progress status management method, program, and progress status management device
EP0300456A2 (en) Improved scheduling method and system
CN1755620A (en) Workflow schedule authoring tool
JP2019117454A (en) Production planning support system
JP2005242844A (en) Process planning processor and program
JP2015005032A (en) Engineering schedule management system, engineering schedule management method and engineering schedule management program
US20050171827A1 (en) A method for supply chain compression
JP2003203148A (en) Information processing system
JP4388714B2 (en) Cooperation program
CN107122849B (en) Spark R-based product detection total completion time minimization method
CN111612411B (en) Target task detection method, system, device and storage medium
JP5255796B2 (en) Operation management support system, program
CN113592288B (en) Discharging plan scheduling method based on non-equivalent parallel machine model
US20040193299A1 (en) System and method for scheduling production of molds
JP2009245117A (en) Business process model comparison method, and device and program thereof
JP2005352934A (en) Production process management system and its device
JP5336906B2 (en) Design process management device
JPH1086044A (en) Worker&#39;s discretion utilization schedule planning method and device therefor
Woodruff et al. A model for multi-stage production planning with load dependent lead times
JP2007265229A (en) Time series analysis program, time series analysis system and terminal unit used for the same
Esmaeilian et al. Application of MATLAB to create initial solution for tabu search in parallel assembly lines balancing

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070223

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090715

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090804

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091005

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20091222

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100323

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20100518

A912 Re-examination (zenchi) completed and case transferred to appeal board

Free format text: JAPANESE INTERMEDIATE CODE: A912

Effective date: 20100618