JP2005213799A - Method for constructing water channel - Google Patents

Method for constructing water channel Download PDF

Info

Publication number
JP2005213799A
JP2005213799A JP2004019570A JP2004019570A JP2005213799A JP 2005213799 A JP2005213799 A JP 2005213799A JP 2004019570 A JP2004019570 A JP 2004019570A JP 2004019570 A JP2004019570 A JP 2004019570A JP 2005213799 A JP2005213799 A JP 2005213799A
Authority
JP
Japan
Prior art keywords
water channel
shaped
shield machine
box culvert
shaped block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004019570A
Other languages
Japanese (ja)
Other versions
JP3868959B2 (en
Inventor
Makoto Uemura
誠 植村
Hiroaki Takegawa
廣明 竹川
Kenjiro Uemura
賢治郎 植村
Hiroshi Sekine
宏 関根
Atsuo Takahashi
厚夫 高橋
Mitsuo Okamoto
光男 岡本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
UDK KK
Uemura Engineering Co Ltd
Original Assignee
UDK KK
Uemura Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by UDK KK, Uemura Engineering Co Ltd filed Critical UDK KK
Priority to JP2004019570A priority Critical patent/JP3868959B2/en
Publication of JP2005213799A publication Critical patent/JP2005213799A/en
Application granted granted Critical
Publication of JP3868959B2 publication Critical patent/JP3868959B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To obtain a method for constructing a water channel by which the water channel can safely and easily be constructed by arranging L-shaped water channel blocks, and also an open shield construction method can effectively be utilized. <P>SOLUTION: The method for constructing the water channel properly repeats a process for digging/removing front soil and sand of an open shield machine 1 by vertically opposing L-shaped blocks 9a and 9b combined in the form of a box culvert, a process for advancing the open shield machine 1 by using a box culvert-like block body 9 as a reaction force, and a process for setting a new box culvert-like block body 9 in the tail of the open shield machine 1 to successively arrange the box culvert-like block body 9 along both sides of the constructing water channel in a vertical row. The method forms both side walls of the water channel and a bottom continued thereto by the L-shaped block 9a positioned at a lower side by removing the L-shaped block 9b positioned at an upper side, digs the remaining soil of an intermediate part 17 between both-side L-shaped blocks 9a, places cast-in-place concrete 18 on the dug bottom part ground, and constructs the water channel by the cast-in-place concrete 18 of the intermediate position and both-side L-shaped blocks 9a. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、L型水路ブロックを使用して構築する水路の構築方法に関するものである。   The present invention relates to a water channel construction method constructed using an L-shaped water channel block.

水路を構築する方法として、例えばL型のプレキャストコンクリートブロックを両側に並べて設置するものがあり、既設水路などにおいて底部地盤を切下げる場合などは、底部地盤を掘削機で掘削した後、基礎コンクリートの上に調整用モルタルを敷き均してからクレーンなどの重機でL型のプレキャストコンクリートブロックを吊り下ろして据え付けていた(例えば特許文献1参照)。   As a method for constructing a water channel, for example, there is a method in which L-shaped precast concrete blocks are installed side by side, and when the bottom ground is cut down in an existing water channel, etc., after excavating the bottom ground with an excavator, The mortar for adjustment was spread on the top, and then the L-shaped precast concrete block was suspended and installed with a heavy machine such as a crane (for example, see Patent Document 1).

ところで、上下水道、共同溝、電信・電話などの付設地下道等の地下構造物を市街地などに施工する工法としてオープンシールド工法がある。   By the way, there is an open shield method as a method for constructing underground structures such as water and sewerage systems, common ditches, telegraphs / telephones, etc. in underground areas.

オープンシールド工法は開削工法(オープンカット工法)とシールド工法の長所を活かした合理性に富む工法である。図4、図5にその概略を示すと、図中1はオープンシールド機1で、これは左右の側壁板1aと、これら側壁板1aに連結する底板1bとからなる前面、後面および上面を開口したシールド機である。   The open shield method is a highly rational method that utilizes the advantages of the open cut method (open cut method) and the shield method. 4 and 5, the open shield machine 1 in the figure is an open shield machine 1, which is open on the front, rear, and top surfaces including left and right side wall plates 1a and a bottom plate 1b connected to the side wall plates 1a. Shield machine.

このオープンシールド機1は、前記側壁板1aと底板1bの先端を刃口6として形成し、また側壁板1aの中央または後端近くに推進ジャッキ2を後方に向け上下に並べて配設する。   In the open shield machine 1, the front ends of the side wall plate 1a and the bottom plate 1b are formed as blade edges 6, and the propulsion jacks 2 are arranged in the vertical direction in the middle or near the rear end of the side wall plate 1a.

かかるオープンシールド機1を使用して施工するオープンシールド工法は、発進坑3内にこのオープンシールド機1を設置して、オープンシールド機1の推進ジャッキ2を伸長して発進坑内の反力壁に反力をとってオープンシールド機1を前進させ、地下構造物を形成する第1番目のコンクリート函体4を上方から吊り降ろし、オープンシールド機1のテール部1c内で縮めた推進ジャッキ2の後方にセットする。推進ジャッキ2と反力壁との間にはストラットを配設して適宜間隔調整をする。   The open shield construction method constructed using such an open shield machine 1 installs this open shield machine 1 in the start pit 3 and extends the propulsion jack 2 of the open shield machine 1 to the reaction wall in the start pit. The back side of the propulsion jack 2 that takes the reaction force to advance the open shield machine 1, suspends the first concrete box 4 that forms the underground structure from above, and contracts in the tail portion 1 c of the open shield machine 1. Set to. A strut is disposed between the propulsion jack 2 and the reaction wall to adjust the distance appropriately.

また、発進坑3は土留壁で構成し、オープンシールド機1を発進させるにはこの土留壁を一部鏡切りするが、必要に応じて薬液注入などで発進坑の前方部分に地盤改良を施しておくこともある。   In addition, the start pit 3 is constituted by a retaining wall, and in order to start the open shield machine 1, a part of this retaining wall is mirror-cut, but if necessary, the ground is improved at the front part of the starting pit by chemical injection or the like. Sometimes it is left.

ショベル等の掘削機5でオープンシールド機1の前面または上面から土砂を掘削しかつ排土する。この排土工程と同時またはその後に推進ジャッキ2を伸長してオープンシールド機1を前進させる。この前進工程の場合、コンクリート函体4の前にはボックス鋼材または型鋼を用いた枠体よりなる押角を配設し、オープンシールド機1は後方にセットされたコンクリート函体4から反力をとる。   Excavator 5 such as an excavator excavates and removes soil from the front or top surface of open shield machine 1. At the same time as or after this earth removal step, the propulsion jack 2 is extended to advance the open shield machine 1. In the case of this advancement process, a push angle made of a frame body made of box steel or mold steel is arranged in front of the concrete box 4, and the open shield machine 1 takes a reaction force from the concrete box 4 set rearward. .

そして第1番目のコンクリート函体4の前に第2番目のコンクリート函体4をオープンシールド機1のテール部1c内でクレーン8により吊り降ろす。以下、同様の排土工程、前進工程、コンクリート函体の4のセット工程を適宜繰返して、順次コンクリート函体4をオープンシールド機1の前進に伴い縦列に地中に残置し、さらにこのコンクリート函体4の上面に埋戻土を入れる。   Then, the second concrete box 4 is suspended by the crane 8 in the tail portion 1 c of the open shield machine 1 in front of the first concrete box 4. Thereafter, the same earth removal process, forward process, and concrete box 4 setting process are repeated as appropriate, and the concrete boxes 4 are sequentially left in the ground as the open shield machine 1 moves forward. Put backfill on top of body 4.

なお、コンクリート函体4をオープンシールド機1のテール部1c内に吊り降ろす際には、コンクリートブロック等による高さ調整材をコンクリート函体4下に配設し、このテール部1c内でコンクリート函体4の左右および下部の空隙にグラウト材7を充填する。   When the concrete box 4 is suspended in the tail part 1c of the open shield machine 1, a height adjusting material such as a concrete block is disposed under the concrete box 4 and the concrete box 4 is placed in the tail part 1c. Grout material 7 is filled in the left and right and lower spaces of the body 4.

このようにして、オープンシールド機1が到達坑まで達したならばこれを撤去して工事を完了する。   In this way, if the open shield machine 1 reaches the reaching mine, it is removed and the construction is completed.

このようなオープンシールド工法では、前記のごとくコンクリート函体4をオープンシールド機1の前進に伴い縦列に地中に残置し、コンクリート函体4は、オープンシールド機1のテール部1c内に吊り降ろされ、オープンシールド機1の前進とともに該テール部1cから出て地中に残されていくものであり、オープンシールド機1はこのように地中に残置したコンクリート函体4に反力をとって前進する。
特開平7−119164号公報
In such an open shield construction method, as described above, the concrete box 4 is left in the ground in a column as the open shield machine 1 advances, and the concrete box 4 is suspended in the tail portion 1c of the open shield machine 1. As the open shield machine 1 moves forward, it leaves the tail portion 1c and remains in the ground. The open shield machine 1 takes a reaction force on the concrete box 4 left in the ground in this way. Advance.
Japanese Patent Laid-Open No. 7-119164

L型のプレキャストコンクリートブロックは最近特に大型化の傾向にあり、高重量物の取り扱いとなるが、形状が不安定なものであるため、吊り下ろしや運搬の際には危険を伴う。   The L-shaped precast concrete block has recently been particularly large and tends to handle heavy objects, but its shape is unstable, so there is a danger in hanging and transporting.

一方、高重量物のコンクリート函体を取り扱うオープンシールド工法は、前記のように上下水道、共同溝、電信・電話などの付設地下道等の地下構造物の施工を本来の目的としており、それ以外の施工には採用されず、有効活用されていなかった。   On the other hand, the open shield method that handles heavy-weight concrete boxes is intended for the construction of underground structures such as water and sewage systems, common ditches, telegraphs and telephones as mentioned above. It was not adopted for construction and was not used effectively.

本発明の目的は前記従来例の不都合を解消し、安全かつ容易にL型水路ブロックの設置による水路を構築でき、同時にオープンシールド工法の有効活用も図れる水路の構築方法を提供することにある。   An object of the present invention is to provide a waterway construction method that eliminates the inconveniences of the conventional example, can construct a waterway by installing an L-shaped waterway block safely and easily, and at the same time, can effectively utilize the open shield method.

本発明は前記目的を達成するため、請求項1記載の発明は、L型ブロックを上下に対向させてボックスカルバート状に組合わせ、オープンシールド機の前面または上面開口より前方の土砂を掘削・排土する工程と、推進ジャッキを伸長して前記ボックスカルバート状のブロック体を反力にしてシールド機を前進させる工程と、シールド機のテール部内で縮めた推進ジャッキの後方に新たなボックスカルバート状のブロック体をセットする工程とを適宜繰返してボックスカルバート状のブロック体を構築される水路の両側にそって縦列に順次配設し、上側に位置するL型ブロックを撤去して下側に位置するL型ブロックで水路の両側壁とこれに連成される底部とを形成し、前記両側のL型ブロック間の中間部の残土を掘削し、掘削した底部地盤上にコンクリートを打設し、この中間位置の打設コンクリートと両側のL型ブロックとで水路を構築することを要旨とするものである。   In order to achieve the above object, the present invention is characterized in that the L-shaped block is combined in a box culvert shape with the L-shaped blocks facing up and down, and the soil in front of the open shield machine or the top opening is excavated and discharged. A step of earthing, a step of extending the propulsion jack and making the box culvert-shaped block body a reaction force to advance the shield machine, and a new box culvert-like shape behind the propulsion jack shrunk in the tail portion of the shield machine The step of setting the block body is repeated as appropriate to form a box culvert-like block body in series along the both sides of the water channel, and the L-shaped block located on the upper side is removed and located on the lower side. The L-shaped block forms both side walls of the water channel and the bottom part coupled to it, and excavates the remaining soil in the middle part between the L-shaped blocks on both sides, thereby excavating the bottom ground The concrete was Da設, it is an gist to build a waterway in the pouring concrete and both sides of the L-shaped block of the intermediate position.

請求項1記載の本発明によれば、L型ブロックを上下に対向させてボックスカルバート状のブロック体とすることで、これをオープンシールド工法で使用するコンクリート函体と同様に扱うことができる。よって、このボックスカルバート状のブロック体をオープンシールド機を使用してオープンシールド工法によって設置し、敷設後、上側に位置するL型ブロックを撤去すれば、下側に位置するL型ブロックのみが残置されるから、これにより水路の一方の側壁部とこれに続く底部とが構築される。よって、他方の側壁部も同様にしてL型ブロックを設置し、両L型ブロック間の中間部の残土を掘削し、ここの底部地盤上に現場打ちでコンクリートを打設すれば、水路が構築できる。   According to the first aspect of the present invention, by making the L-shaped block face up and down to form a box culvert-like block body, this can be handled in the same manner as a concrete box used in the open shield method. Therefore, if this box culvert-shaped block body is installed by an open shield method using an open shield machine, and the L-type block located on the upper side is removed after laying, only the L-type block located on the lower side remains. As a result, one side wall portion of the water channel and the bottom portion following the one water channel portion are constructed. Therefore, an L-type block is installed in the same manner on the other side wall, and the remaining soil in the middle part between the two L-type blocks is excavated, and concrete is placed on the bottom ground here to construct a waterway. it can.

請求項2記載の発明は、前記ボックスカルバート状のブロック体を設置した後に撤去する上側のL型ブロックは、これを次の施工時に使用可能であることを要旨とするものである。   The gist of the invention described in claim 2 is that the upper L-shaped block to be removed after the box culvert-shaped block body is installed can be used in the next construction.

請求項2記載の本発明によれば、撤去した上側のL型ブロックを次の施工において上側のL型ブロックとしてはもちろんのこと下側のL型ブロックとしても使用できるから、うって返しによる再使用ができ、資材が無駄にならない。   According to the second aspect of the present invention, the removed upper L-shaped block can be used not only as the upper L-shaped block but also as the lower L-shaped block in the next construction. It can be used and materials are not wasted.

本発明の水路の構築方法は、L型ブロックを対向させてボックスカルバート状に組合わせたものをオープンシールド機を使用してオープンシールド工法で設置することで、安全かつ容易にL型ブロックの設置による水路を構築でき、同時にオープンシールド工法の有効活用も図れるものである。   The water channel construction method of the present invention is a safe and easy way to install an L-shaped block by installing a combination of L-shaped blocks facing each other in a box culvert shape using an open shield machine. It is possible to construct a waterway by using the open shield method at the same time.

以下、図面について本発明の実施形態を詳細に説明する。図1は本発明の水路の構築方法の第1実施形態を示す工程図で、図4、図5について既に説明したオープンシールド工法によって施工するもので、本発明方法ではオープンシールド機1で設置していた従来のコンクリート函体4にかえて、水路ブロックとなる2個のプレキャストコンクリート製のL型ブロック9a,9bを対向させて組合わせる。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a process diagram showing a first embodiment of a waterway construction method according to the present invention, which is constructed by the open shield method already described with reference to FIGS. 4 and 5. Instead of the conventional concrete box 4 which has been used, two L-shaped blocks 9a and 9b made of precast concrete which become water channel blocks are combined facing each other.

このL型ブロック9a、9bは同じ形状のもので、下側に位置するL型ブロック9aと上側に位置するL型ブロック9bとは通しボルトで結合し、ボックスカルバート状のブロック体9とする。   The L-shaped blocks 9a and 9b have the same shape, and the L-shaped block 9a positioned on the lower side and the L-shaped block 9b positioned on the upper side are coupled with a through bolt to form a box culvert-shaped block body 9.

図1において10は新設の水路を構築する既設水路であり、底部地盤11を切下げて水路を新たに構築する場合であり、ボックスカルバート状のブロック体9を前記したオープンシールド工法で設置する場合、上側に位置するL型ブロック9bの上面が現状の水底になっている底部地盤11と同一レベルで既設水路10の下方に位置するような高さ位置にボックスルカルバート状のブロック体9を設置する。   In FIG. 1, 10 is an existing water channel for constructing a new water channel, and is a case where a water channel is newly constructed by lowering the bottom ground 11, and when a box culvert-shaped block body 9 is installed by the open shield method described above, The box-shaped culvert-shaped block body 9 is installed at a height position such that the upper surface of the L-shaped block 9b located on the upper side is located below the existing water channel 10 at the same level as the bottom ground 11 which is the current water bottom. .

オープンシールド工法によるボックスカルバート状のブロック体9の設置は、オープンシールド機1の前面または上面開口より掘削機5で前方の土砂を掘削・排土する工程と、推進ジャッキ2を伸長してボックスカルバート状のブロック体9を反力にしてオープンシールド機1を前進させる工程と、オープンシールド機1のテール部1c内で縮めた推進ジャッキ2の後方に新たなボックスカルバート状のブロック体9をセットする工程とを適宜繰返してボックスカルバート状のブロック体9縦列に順次配設するものであるが、ブロック体9はボックスカルバート状に形成してあるから、これを反力にしてシールド機1を前進させることが可能となる。   Installation of the box culvert-shaped block body 9 by the open shield construction method includes the step of excavating and discharging the soil in front of the open shield machine 1 from the front or top opening of the open shield machine 1 and the extension jack 2 to extend the box culvert. A step of advancing the open shield machine 1 by using the block-shaped block body 9 as a reaction force, and a new box culvert-shaped block body 9 is set behind the propulsion jack 2 contracted in the tail portion 1c of the open shield machine 1 The steps are repeated as appropriate to sequentially arrange the box culvert-shaped block bodies 9 in columns, but since the block bodies 9 are formed in a box culvert shape, this is used as a reaction force to advance the shield machine 1. It becomes possible.

このようにして図1(b)に示すように地盤を掘削しながらボックスカルバート状のブロック体9を既設水路10の一方の側(図示の例では左側)にそって側壁部位置で底部地盤11の下方の地中に埋設したならば、図1(c)に示すようにボックスカルバート状のブロック体9と周囲の地山との間に生じる隙間に裏込注入材14を充填して地山との一体化を図る。   In this way, while excavating the ground as shown in FIG. 1 (b), the box culvert-shaped block body 9 is moved along one side of the existing water channel 10 (left side in the illustrated example) at the side wall portion at the bottom ground 11. As shown in FIG. 1 (c), the gap between the box culvert-shaped block body 9 and the surrounding natural ground is filled with the back-filling injection material 14 as shown in FIG. 1 (c). Integrate with.

さらに、既設水路10の反対側(図1(c)の例では右側)にそって前記と同様にしてボックスカルバート状のブロック体9を埋設し、ブロック体9と周囲の地山との間に裏込め注入材14を充填する。   Further, a box culvert-shaped block body 9 is embedded along the opposite side of the existing water channel 10 (right side in the example of FIG. 1C) in the same manner as described above, and between the block body 9 and the surrounding natural ground. The backfilling injection material 14 is filled.

このようにして既設水路10の両側の側壁部位置で底部地盤11の下方の地中にボックスカルバート状のブロック体9を設置したならば(図1(d)参照)、両側のL型ブロック9b間の中間部17の残土を掘削し、上側に位置するL型ブロック9bを撤去して、ここに形成される空間の底部地盤11上に砕石15を敷き均した後、この上に場所打ちコンクリート18を打設する(図1(e)参照)。   Thus, if the box culvert-shaped block body 9 is installed in the ground below the bottom ground 11 at the side wall portions on both sides of the existing water channel 10 (see FIG. 1 (d)), the L-shaped blocks 9b on both sides are installed. After excavating the remaining soil in the intermediate portion 17 between the two, the L-shaped block 9b located on the upper side is removed, and the crushed stone 15 is laid on the bottom ground 11 of the space formed here, and then cast-in-place concrete is placed thereon. 18 is placed (see FIG. 1 (e)).

これにより、既設水路10の下方位置の側部に下側のL型ブロック9aの側部12が配置され、底部13が切下げられた底部地盤11と同一面に位置して、L型ブロック9aによる擁壁が構築され、両側のL型ブロック9a間にこれらL型ブロック9aと一体になるように場所打ちコンクリート18が打設されて新たな水路が構築される。   As a result, the side portion 12 of the lower L-shaped block 9a is disposed on the side portion of the lower position of the existing water channel 10, and the bottom portion 13 is located on the same plane as the bottom ground 11, and the L-shaped block 9a A retaining wall is constructed, and cast-in-place concrete 18 is placed between the L-shaped blocks 9a on both sides so as to be integrated with the L-shaped blocks 9a, thereby constructing a new water channel.

撤去した上側のL型ブロック9bは次の施工の際に上側または下側のブロックとして再使用する。   The removed upper L-shaped block 9b is reused as an upper or lower block in the next construction.

図2は第2実施形態を示し、基本構成は第1実施形態と同様であるが、裏込め注入を行わない場合であり、前進させるオープンシールド機1の底部の下方に砕石15とドライコンクリート16を布設してボックスカルバート状のブロック体9を設置する。   FIG. 2 shows the second embodiment, and the basic configuration is the same as that of the first embodiment, except that backfill injection is not performed, and the crushed stone 15 and the dry concrete 16 are provided below the bottom of the open shield machine 1 to be advanced. And a box culvert-shaped block body 9 is installed.

そして、オープンシールド機1を使用してオープンシールド工法でボックスカルバート状のブロック体9を既設水路10の一方の側(図2(b)の例では左側)にそって側壁部位置で底部地盤11の下方の地中に埋設したならば、図2(c)に示すようにボックスカルバート状のブロック体9と周囲の地山との間に生じる隙間に埋め戻し材19を充填して地山との一体化を図る。   Then, the box culvert-shaped block body 9 is opened by the open shield machine 1 using the open shield machine 1 along the one side of the existing water channel 10 (left side in the example of FIG. 2B) at the side wall portion at the bottom ground 11. 2 (c), the backfill material 19 is filled in the gap formed between the box culvert-shaped block body 9 and the surrounding natural ground, as shown in FIG. Integrate

さらに、既設水路10の反対側(図2(c)の例では右側)にそって前記と同様にしてボックスカルバート状のブロック体9を埋設し、ボックスルカルバート状のブロック体9と周囲の地山との間に埋め戻し材19を充填する。   Further, a box culvert-shaped block body 9 is embedded along the opposite side of the existing water channel 10 (on the right side in the example of FIG. 2 (c)) in the same manner as described above. The backfill material 19 is filled between the mountains.

このようにして既設水路10の両側の側壁部位置で底部地盤11の下方の地中にボックスカルバート状のブロック体9を設置したならば(図2(d)参照)、両側のL型ブロック9b間の中間部17の残土を掘削し、上側に位置するL型ブロック9bを撤去して、ここに形成される空間の底部地盤11上に砕石15を敷き均した後、この上に場所打ちコンクリート18を打設する(図1(e)参照)。 Thus, if the box culvert-shaped block body 9 is installed in the ground below the bottom ground 11 at the side wall portions on both sides of the existing water channel 10 (see FIG. 2 (d)), the L-shaped blocks 9b on both sides are installed. After excavating the remaining soil in the intermediate portion 17 between the two, the L-shaped block 9b located on the upper side is removed, and the crushed stone 15 is laid on the bottom ground 11 of the space formed here, and then cast-in-place concrete is placed thereon. 18 is placed (see FIG. 1 (e)).

これにより、既設水路10の下方位置の側部に下側のL型ブロック9aの側部12が配置され、底部13が切下げられた底部地盤11と同一面に位置して、L型ブロック9aによる擁壁が構築され、両側のL型ブロック9a間にこれらL型ブロック9aと一体になるように場所打ちコンクリート18が打設されて新たな水路が構築される。   As a result, the side portion 12 of the lower L-shaped block 9a is disposed on the side portion of the lower position of the existing water channel 10, and the bottom portion 13 is located on the same plane as the bottom ground 11, and the L-shaped block 9a A retaining wall is constructed, and cast-in-place concrete 18 is placed between the L-shaped blocks 9a on both sides so as to be integrated with the L-shaped blocks 9a, thereby constructing a new water channel.

上側のL型ブロック9bと下側のL型ブロック9aとの接合部の形状は、図3に示すように種々のタイプが考えられ、図3(a)のような凹凸による段部の組合わせ、図3(b)のような上方に突出する凸部と凹部の組合わせ、図3(c)のような水平内側方向に突出する凸部とこの凸部が挿入される水平方向の凹部との組合わせ、図3(d)のような山形の凸条とテーパー溝条との組合わせ、図3eのような長方形状の突条と長方形状の溝条との組合わせ、図3(f)のように一方の、例えば下側のL型ブロック9aの接合端面を幅広に形成して端面同士を突合せる構成、図3gのように一方の、例えば上側のL型ブロック9bの接合端面を僅かに突出させて端面同士を突合せる構造などがある。これらの場合、凸部と凹部との組合わせは、上下のL型ブロックで反対に形成してもよい。   As shown in FIG. 3, there are various types of joint portions between the upper L-shaped block 9b and the lower L-shaped block 9a. A combination of a convex portion and a concave portion projecting upward as shown in FIG. 3 (b), a convex portion projecting in the horizontal inward direction as shown in FIG. 3 (c), and a horizontal concave portion into which the convex portion is inserted. FIG. 3D shows a combination of a mountain-shaped protrusion and a tapered groove as shown in FIG. 3D, a combination of a rectangular protrusion and a rectangular groove as shown in FIG. 1), for example, a configuration in which the joining end surfaces of the lower L-shaped block 9a, for example, are formed wide so that the end surfaces abut each other, and the joining end surface of one, for example, the upper L-shaped block 9b, as shown in FIG. There is a structure in which the end faces are made to face each other slightly. In these cases, the combination of the convex part and the concave part may be formed oppositely with the upper and lower L-shaped blocks.

本発明の水路の構築方法の第1実施形態を示す工程図である。It is process drawing which shows 1st Embodiment of the construction method of the waterway of this invention. 本発明の水路の構築方法の第2実施形態を示す工程図である。It is process drawing which shows 2nd Embodiment of the construction method of the waterway of this invention. L型ブロックの接合構造を示す説明図である。It is explanatory drawing which shows the joining structure of an L-type block. オープンシールド工法の平面図である。It is a top view of an open shield construction method. オープンシールド工法の側面図である。It is a side view of an open shield construction method.

符号の説明Explanation of symbols

1 オープンシールド機 1a 側壁板
1b 底板 1c テール部
2 推進ジャッキ 3 発進坑
4 コンクリート函体
5 掘削機 6 刃口
7 グラウト材 8 クレーン
9 ボックスカルバート状のブロック体
9a,9b L型ブロック
10 既設水路 11 底部地盤
12 側部 13 底部
14 裏込め注入材 15 砕石
16 ドライコンクリート 17 中間部
18 場所打ちコンクリート 19 埋め戻し材
DESCRIPTION OF SYMBOLS 1 Open shield machine 1a Side wall plate 1b Bottom plate 1c Tail part 2 Propulsion jack 3 Start pit 4 Concrete box 5 Excavator 6 Cutting edge 7 Grout material 8 Crane 9 Box culvert block body 9a, 9b L-shaped block 10 Existing water channel 11 Bottom ground 12 Side 13 Bottom 14 Backfilling material 15 Crushed stone 16 Dry concrete 17 Middle part 18 Cast-in-place concrete 19 Backfill

Claims (2)

L型ブロックを上下に対向させてボックスカルバート状に組合わせ、オープンシールド機の前面または上面開口より前方の土砂を掘削・排土する工程と、推進ジャッキを伸長して前記ボックスカルバート状のブロック体を反力にしてシールド機を前進させる工程と、シールド機のテール部内で縮めた推進ジャッキの後方に新たなボックスカルバート状のブロック体をセットする工程とを適宜繰返してボックスカルバート状のブロック体を構築される水路の両側にそって縦列に順次配設し、上側に位置するL型ブロックを撤去して下側に位置するL型ブロックで水路の両側壁とこれに連成される底部とを形成し、前記両側のL型ブロック間の中間部の残土を掘削し、掘削した底部地盤上にコンクリートを打設し、この中間位置の打設コンクリートと両側のL型ブロックとで水路を構築することを特徴とする水路の構築方法。   A box culvert-shaped block body in which L-shaped blocks are vertically opposed to each other and combined in a box culvert shape, excavating and discharging soil in front of the open shield machine or from the top opening, and extending a propulsion jack The process of advancing the shield machine with the reaction force and the process of setting a new box culvert-like block body behind the propulsion jack shrunk in the tail part of the shield machine are repeated as appropriate to form the box-culvert block body. Sequentially arranged in tandem along both sides of the water channel to be constructed, the L-shaped block located on the upper side is removed, and the L-shaped block located on the lower side is provided with both side walls of the water channel and the bottom part coupled to this. Forming and excavating the residual soil in the middle part between the L-shaped blocks on both sides, placing concrete on the excavated bottom ground, and placing the concrete in the middle position Construction method of water passage, characterized by constructing a water passage between the two sides of the L-type blocks. 前記ボックスカルバート状のブロック体を設置した後に撤去する上側のL型ブロックは、これを次の施工時に使用可能であることを特徴とする請求項1に記載の水路の構築方法。   The method for constructing a water channel according to claim 1, wherein the upper L-shaped block to be removed after the box culvert-shaped block body is installed can be used in the next construction.
JP2004019570A 2004-01-28 2004-01-28 Waterway construction method Expired - Lifetime JP3868959B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004019570A JP3868959B2 (en) 2004-01-28 2004-01-28 Waterway construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004019570A JP3868959B2 (en) 2004-01-28 2004-01-28 Waterway construction method

Publications (2)

Publication Number Publication Date
JP2005213799A true JP2005213799A (en) 2005-08-11
JP3868959B2 JP3868959B2 (en) 2007-01-17

Family

ID=34903748

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004019570A Expired - Lifetime JP3868959B2 (en) 2004-01-28 2004-01-28 Waterway construction method

Country Status (1)

Country Link
JP (1) JP3868959B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013172677A2 (en) * 2012-05-17 2013-11-21 박준옥 Drain pipe for farmland and method for constructing agricultural waterway using same

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926357A (en) * 2012-11-02 2013-02-13 孙素元 Full-automatic water-saving drainage and irrigation seepage-proofing canal cast-in-situ forming machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013172677A2 (en) * 2012-05-17 2013-11-21 박준옥 Drain pipe for farmland and method for constructing agricultural waterway using same
WO2013172677A3 (en) * 2012-05-17 2014-01-23 박준옥 Drain pipe for farmland and method for constructing agricultural waterway using same

Also Published As

Publication number Publication date
JP3868959B2 (en) 2007-01-17

Similar Documents

Publication Publication Date Title
JP5351125B2 (en) Open shield machine start method of open shield method
JP5204063B2 (en) Box foundation construction method in open shield method
JP6629825B2 (en) Road lining method in open shield method
JP2007146533A (en) Friction cut plate used in open shield construction method and its fixing method
JP2010242374A (en) Open shield machine and open shield method using the same
JP3868959B2 (en) Waterway construction method
JP3766423B2 (en) Retaining wall construction method
JP3917146B2 (en) Laying method and removing method of lining plate in open shield method
JP2009114640A (en) Open shield machine
JP2010242373A (en) Installation method for covering plate in open shield method
JP5960786B2 (en) Shield machine collection method in open shield method
JP4402640B2 (en) Open shield method
JPH0249896A (en) Open shield method and machine thereof
JP2004316126A (en) Work execution method for large section tunnel and deformed section shield boring machine
JP3581332B2 (en) Earth retaining equipment and open-cutting method using it
JP4349570B2 (en) Construction method of division box and underground level crossing
JP5639213B2 (en) Open shield method
JP2004316125A (en) Work execution method for large sectional tunnel and deformed section shield machine
JP3926818B2 (en) Installation method of concrete box
JP4279818B2 (en) Open shield method
JP2018053467A (en) Open shield method
JP2587309B2 (en) Protective structure of concrete underground structure and its construction method
JP2006112100A (en) Open shield machine
JP2018053466A (en) Open shield method
JP2005030059A (en) Open shield construction method and open shield machine used in it

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060720

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20061010

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20061011

R150 Certificate of patent or registration of utility model

Ref document number: 3868959

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101020

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101020

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111020

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121020

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121020

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131020

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250