JP2005149414A - Retrieval method for project risk, evaluation system and common database utilization method - Google Patents

Retrieval method for project risk, evaluation system and common database utilization method Download PDF

Info

Publication number
JP2005149414A
JP2005149414A JP2003389734A JP2003389734A JP2005149414A JP 2005149414 A JP2005149414 A JP 2005149414A JP 2003389734 A JP2003389734 A JP 2003389734A JP 2003389734 A JP2003389734 A JP 2003389734A JP 2005149414 A JP2005149414 A JP 2005149414A
Authority
JP
Japan
Prior art keywords
risk
project
evaluation
sheet
item
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003389734A
Other languages
Japanese (ja)
Inventor
Takayoshi Nakamoto
宇香 中本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Software Engineering Co Ltd
Original Assignee
Hitachi Software Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Software Engineering Co Ltd filed Critical Hitachi Software Engineering Co Ltd
Priority to JP2003389734A priority Critical patent/JP2005149414A/en
Publication of JP2005149414A publication Critical patent/JP2005149414A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a database utilization method and an evaluation system, in which potential risk and a problem which should be treated beforehand are evaluated comprehensively and treated in a planning stage of a project, by referring to a past result database . <P>SOLUTION: A risk evaluation sheet 10 and a problem management sheet 11 which a project promoter can refer to/update are stored in a shared data base 3. An evaluation point is inputted in a risk evaluation item in the risk evaluation sheet. Problems, failures generated during project execution and their treating contents are inputted in the problem management sheet. Scale of the project to be examined, and the scale of a project whose evaluation point, etc. is similar are extracted from the past result data base of a past project and displayed in a radar chart system. Candidates for a reference project are displayed, and risk becomes clear, by carrying out risk evaluation at the planning stage of a new project. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、多数のソフトウェア開発プロジェクトを手がける部門において利用するのに適した、プロジェクトの計画段階における潜在リスク又は事前対応策の検討に用いる補助手段に関する。但し、プロジェクトの体制・開発形態・開発環境・適用技術に限定されるものではない。   The present invention relates to an auxiliary means used for examining potential risks or proactive measures at the project planning stage, which is suitable for use in a department that handles a large number of software development projects. However, it is not limited to the project system, development form, development environment, and applied technology.

ソフトウェア開発プロジェクトにおける潜在リスク又は事前対応策に関しては、一管理者の過去の経験又は勘などに基づいて検討される場合、或いは、自部署内での類似プロジェクトを参考にして、潜在リスクや事前対応策を検討している場合が多かった。   Regarding potential risks and proactive measures in software development projects, when considering based on the past experience or intuition of one manager, or referring to similar projects in their department, potential risks and proactive measures In many cases, measures were being considered.

しかしながら、上記従来の技術では、1)参考となるプロジェクトとして集められるのは自課・部内の範囲でのプロジェクトに留まる場合が多く、データ総量が極めて少なくなる傾向にある、2)参考とするプロジェクトの選定条件が、適用技術や開発規模などの限られた条件となりがちであり、プロジェクトの持つリスク面に起因する問題点や対応を把握することが難しい、3)参考としたい類似プロジェクトが存在しても、問題や対応内容の情報の保存方法がプロジェクトによりまちまちである場合が多く、検索し参照することが難しい、などの問題点を有している。   However, in the above-mentioned conventional technology, 1) Projects that are collected as reference projects are often limited to projects within their own section or department, and the total amount of data tends to be extremely small. 2) Reference projects The selection conditions tend to be limited conditions such as applied technology and development scale, and it is difficult to grasp the problems and countermeasures caused by the risks of the project. 3) There is a similar project to be referred to However, there are many cases where the method of storing information on the problem and the contents of correspondence varies depending on the project, and it is difficult to search and refer to it.

この点、上記問題点を解決する一手法として、特許文献1に記載された技術であって、リスク評価結果が類似するプロジェクトの対策結果を表示するシステムが挙げられる。   In this regard, as a technique for solving the above problem, there is a system described in Patent Document 1 that displays a countermeasure result of a project having a similar risk evaluation result.

特開平11−66150号公報JP-A-11-66150

上記特許文献1に記載された技術は、リスク評価結果に表れるリスク項目自体を過去のプロジェクトの障害対策事例からシステムで絞り込む。ところが、現実には、あるリスク項目について検索された対策事例は、他のリスク項目の状態によっては適当でなかったり、実行不可能であったりする場合が多い。また、各リスク項目の持つリスク評価値の偏りに起因して、新たな問題が発生する可能性もある。さらに、上記技術においては、対策が実施された事例しか参照できない。   The technique described in Patent Document 1 narrows down the risk items themselves appearing in the risk evaluation result from the failure countermeasure examples of past projects by the system. However, in reality, countermeasure examples searched for a certain risk item are often not appropriate or impossible to execute depending on the state of other risk items. In addition, there is a possibility that a new problem may occur due to the risk evaluation value bias of each risk item. Furthermore, in the above technology, only cases where countermeasures are implemented can be referred to.

本発明は、プロジェクトリスクの複合評価による対策事例検索方法及び検索システムを提供することを目的とする。   An object of the present invention is to provide a countermeasure case retrieval method and retrieval system based on a composite evaluation of project risks.

本発明のプロジェクトリスクの複合評価による対策事例検索システムは、以下の手段により実現される。   The countermeasure case search system by the composite evaluation of the project risk of the present invention is realized by the following means.

(1)開発部門(開発セクション)共通の『リスク評価シート』および『問題点管理シート』を作成・使用する。1)リスク評価シートにはリスク評価項目を列挙する。リスク評価項目は大項目に整理する。プロジェクト計画段階において、リスク評価シートに評価点(本明細書では、評価点が高いほどリスクが大きいことを意味する。)を入力する。
2)問題点管理シートに、対応リスク項番欄を持たせる。開発中〜安定稼動段階において、開発の過程で判明した問題点や障害及びその対応内容を入力する時に、合わせて、問題点発生の要因につながるリスク項番を選択し入力しておく。
(2)リスク評価シート・問題点管理シートの入力情報は、各開発部門より参照・更新可能な共有DBに蓄積しておく。
(3)リスク評価シートのリスク評価項目に対するリスク評価点までを入力し抽出条件を設定すると、該当するプロジェクトを複数抽出し、大項目毎のリスク評価点によるチャート、例えばレーダーチャートを表示するシステムを作成する。
(1) Create and use "risk evaluation sheet" and "problem management sheet" common to development departments (development sections). 1) List risk assessment items on the risk assessment sheet. Organize risk assessment items into major items. In the project planning stage, an evaluation score (in this specification, the higher the evaluation score, the higher the risk is) is entered in the risk evaluation sheet.
2) Provide a corresponding risk item number column in the problem management sheet. During the development to the stable operation stage, when inputting problems and failures found during the development process and corresponding contents, risk item numbers that lead to the cause of the problem are selected and entered.
(2) The input information of the risk evaluation sheet / problem management sheet is stored in a shared DB that can be referenced and updated by each development department.
(3) Once the risk evaluation points for the risk evaluation items on the risk evaluation sheet are entered and extraction conditions are set, a system that extracts a plurality of applicable projects and displays a chart with risk evaluation points for each major item, for example, a radar chart create.

さらに抽出されたプロジェクトを選択することにより、該当プロジェクトの問題点管理シートの情報を、リスク管理シートのフォーマットに紐付けた形で表示する機能を持つ。抽出条件としては、大項目単位の評価点数の偏りに関する類似、リスク評価点の合計点数に関する類似といったリスク評価点に関する特性に関連する検索キーを用いる。   Furthermore, by selecting the extracted project, the problem management sheet information of the project is displayed in a form linked to the format of the risk management sheet. As an extraction condition, a search key related to characteristics relating to risk evaluation points such as similarity regarding bias of evaluation scores in units of large items and similarity regarding total score of risk evaluation points is used.

本発明のプロジェクトリスクの複合評価による対策事例検索システムによれば、共通フォーマットに基づき情報が整理されているため、参照が容易であるという利点がある。また、同種のリスクを持つプロジェクトを抽出して参考にできるため、リスクの高い部分について事前に対策を講じることができ、また、同様のリスクの偏りを持つために発生しうる問題点を事前に把握して対策を講じることもできる。   According to the measure case retrieval system based on the composite evaluation of project risk according to the present invention, information is organized based on a common format, so that there is an advantage that reference is easy. In addition, because projects with the same type of risk can be extracted and used as a reference, measures can be taken in advance for high-risk parts, and problems that may occur due to similar risk biases are identified in advance. It is also possible to grasp and take measures.

さらに、参照プロジェクトの選択時にあたって、リスクの偏りの類似を選択したり、特定分野のリスクの評価点の高低の類似を選択したりする等、目的に応じた選択の自由度が保たれている。選択の際にグラフ化を行えば、判断がしやすくなるという利点もある。   Furthermore, when selecting a reference project, the degree of freedom of selection according to the purpose is maintained, such as selecting similarities in risk bias or selecting similarities in risk evaluation scores in specific fields. . If graphing is performed at the time of selection, there is an advantage that it is easy to make a judgment.

リスク管理においては、まだ解決できていない問題に関しても、検出された問題点や障害を把握しておくことは重要である。   In risk management, it is important to understand detected problems and failures even for problems that have not been solved yet.

以下、本発明の一実施の形態によるプロジェクトリスクの複合評価による対策事例検索システムについて図面を参照しつつ説明を行う。その際、準備段階・データ蓄積過程・活用段階の3段階に分け、全体の構成と処理の流れを図1に示し、その詳細な事例を図2〜図4までを参照しつつ説明する。   Hereinafter, a countermeasure case search system based on a composite evaluation of project risks according to an embodiment of the present invention will be described with reference to the drawings. At that time, it is divided into three stages of a preparation stage, a data accumulation process, and a utilization stage, and the overall configuration and processing flow are shown in FIG. 1, and detailed examples will be described with reference to FIGS.

1.準備段階
まず、図1に示すプロジェクトリスクの複合評価による対策事例検索システム1(以下、「本システム」と呼ぶ)において、全部門共通のフォーマットとして『リスク評価シート』と『問題点管理シート』とを、全開発部門より参照・更新が可能な共有DB3(リスク評価シートデータベース10、問題点管理シートデータベース11)上に用意しておき、各プロジェクトの入力者は、これらの共有DB3上に入力を行うこととする。リスク評価シートデータベース10と、問題点管理シートデータベース11とは、後述するリスク評価項番10aと対応リスク評価項番11aとにより関連付けされている。
1. Preparatory stage First, in the countermeasure case search system 1 (hereinafter referred to as “this system”) based on the composite assessment of project risks shown in FIG. 1, “risk evaluation sheet” and “problem management sheet” Are prepared on the shared DB 3 (risk evaluation sheet database 10 and problem management sheet database 11) that can be referred to and updated by all development departments, and the input person of each project inputs the information on these shared DBs 3 I will do it. The risk evaluation sheet database 10 and the problem management sheet database 11 are associated with each other by a risk evaluation item number 10a and a corresponding risk evaluation item number 11a described later.

図2(A)、(B)を参照して、『リスク評価シート』21及び『問題点管理シート』22の一例を示す。
まず、図2(A)に示すように、プロジェクトの基本情報20として、開発部署・プロジェクト名称・開発規模・適用技術を登録する。ここで、プロジェクト名称については、本システムで対象プロジェクトを識別するためのキーワードとなるため、システム内で一意になるように入力チェックを行う。開発規模については、開発ステップ数・入出力ファイル数・入出力画面数等、定量的に算出できる尺度ならば種別を問わないが、対象とする全プロジェクトに対して共通の尺度(例えば開発ステップ数)を用いることとする。また、適用技術についてはネットワーク技術・データベース管理技術等、ベースとなる技術で分類する方法や、製造業・金融業等、顧客の業務種別によって分類する方法等が考えられるが、いずれの分類方法を用いてもよく、複数の分類方法を併用してもよい。また、適用技術が同種であることをシステムで自動的に判断可能とするために、あらかじめ選択肢をいくつか用意しておき、入力者にはその中から選択入力させることとする。
An example of a “risk evaluation sheet” 21 and a “problem management sheet” 22 is shown with reference to FIGS.
First, as shown in FIG. 2A, the development department, project name, development scale, and applied technology are registered as the basic information 20 of the project. Here, since the project name is a keyword for identifying the target project in this system, the input check is performed so as to be unique within the system. As for the development scale, any type can be used as long as it can be calculated quantitatively, such as the number of development steps, the number of input / output files, and the number of input / output screens. ). In addition, as for applicable technology, there are a method of classification based on the base technology such as network technology and database management technology, a method of classification according to the type of business of the customer such as manufacturing industry and financial industry, etc. It may be used, and a plurality of classification methods may be used in combination. Also, in order to enable the system to automatically determine that the applied technology is the same type, several options are prepared in advance, and the input person selects and inputs them.

リスク評価シート21には、リスク評価項目(列25)を列挙し、リスク評価項目毎に評価点を付けるための評価点欄(列26)を設ける。本実施の形態においては、評価点は1から5までの5段階評価とし、最もリスクの高い評価点を5としているが、定量的に計算できる評価方法ならば別の評価法(評価点の付け方)でもよい。評価点の付け方は、入力者の主観に偏らず全プロジェクトにとって共通の客観的尺度となるように、別途評価基準を設け、適宜参照可能とする。例えば図2(B)の評価項目「発注元とは取引実績があるか。」については、全く取引実績がない場合を5点とし、以下、取引回数や取引金額合計によって1点ずつ順次下げていくような評価基準を設けておく。また評価項目「他社製品の選定は顧客が当社か。」については、完全に顧客側事情によって選定される場合はリスクが高いとして評価点5とし、当社に完全に選択が任されている場合はリスクが低いとして評価点1とし、中間の場合には主導権の度合いによって2〜4とする。リスク評価項目は、大項目(列24)に整理したものである。また、リスク評価項目毎にリスク項番を付与する(列23)。なお、本システムの対象となるプロジェクトは、すべて共通の大項目・評価項目に対して評価点を記入するものとする。   The risk evaluation sheet 21 is provided with an evaluation score column (column 26) for listing risk evaluation items (column 25) and assigning an evaluation score for each risk evaluation item. In this embodiment, the evaluation score is a five-level evaluation from 1 to 5, and the highest risk evaluation score is 5. However, if the evaluation method can be calculated quantitatively, another evaluation method (how to assign evaluation points) ) For the method of assigning evaluation points, a separate evaluation standard is set up so that it can be referred to as appropriate so that it becomes an objective scale common to all projects regardless of the subjectivity of the input person. For example, with regard to the evaluation item “Is there an actual transaction with the ordering party” in FIG. 2B, 5 points are given when there is no actual transaction, and the points are sequentially reduced one by one depending on the number of transactions and the total transaction amount. Establish an evaluation standard. In addition, regarding the evaluation item “Will the customer select the product of the other company?”, If the customer is completely selected according to the circumstances of the customer, the risk is high and the evaluation score is 5. If the selection is completely left to the Company If the risk is low, the evaluation point is 1, and in the middle case, it is 2-4 depending on the degree of initiative. The risk evaluation items are organized into large items (column 24). A risk item number is assigned to each risk evaluation item (column 23). In addition, all projects that are the targets of this system shall enter evaluation points for common large items and evaluation items.

一方、問題点管理シート(22)には、発見工程、問題点を同時入力し、対応リスク項番の入力欄(列27)を入力した後、対策・効果の入力欄に入力を行うようになっている。尚、対応リスク項番は、複数のリスク項番を入力しても良い。   On the other hand, in the problem management sheet (22), the discovery process and the problem are simultaneously input, and the corresponding risk item number input field (column 27) is input, and then the countermeasure / effect input field is input. It has become. As the corresponding risk item number, a plurality of risk item numbers may be input.

2.データ蓄積過程
次に、図1のリスク評価12について説明する。プロジェクトの計画段階において、プロジェクト基本情報20、リスク評価シートの評価点欄(列26)に対する入力処理を行う。
2. Data Accumulation Process Next, the risk assessment 12 in FIG. 1 will be described. At the project planning stage, input processing is performed for the basic project information 20 and the evaluation score column (column 26) of the risk evaluation sheet.

次に、図1の問題点13、対策14に関して、開発開始〜安定稼動の工程において、発覚した問題点及び障害とその対応内容とを、問題点管理シート22に入力する。その際、リスク評価シート21のリスク評価項目(固定した項目)25より問題発生の要因に関わると思われる項目を選択し、対応するリスク項番23を列27に入力する。対応リスク項番27は、複数選択可能である。同じような内容の問題点に対して、入力する対応リスク項番が入力者の主観に左右されないように、リスク項番を指定すると過去に当該リスク項番に対応づけられて入力された問題点の一覧が表示されるようにしても良い(図示せず)。また、入力した問題点に含まれるキーワードを指定することによって、当該キーワードを含む過去に入力された問題点と対応リスク項番の一覧が表示されるようにしても良い(図示せず)。これらの一覧を入力者に参照させながら対応リスク項番を入力させることによって、入力者による対応リスク項番のバラツキを防止することができる。   Next, regarding the problem 13 and the countermeasure 14 in FIG. 1, in the process of starting development to stable operation, the detected problem and failure and the corresponding contents are input to the problem management sheet 22. At that time, an item that seems to be related to the cause of the problem is selected from the risk evaluation items (fixed items) 25 of the risk evaluation sheet 21, and the corresponding risk item number 23 is input in the column 27. A plurality of correspondence risk item numbers 27 can be selected. If a risk item number is specified so that the corresponding risk item number to be entered does not depend on the subject's subjectivity for problems with the same content, problems that have been input in association with the risk item number in the past May be displayed (not shown). In addition, by specifying a keyword included in the input problem, a list of previously input problems including the keyword and corresponding risk item numbers may be displayed (not shown). By causing the input person to refer to these lists and inputting the corresponding risk item numbers, variations in the corresponding risk item numbers by the input person can be prevented.

各プロジェクトでの図1のリスク評価12、問題点抽出13、対策検討14を実施することにより、リスク評価シート・問題点管理シートの情報は共有DBへ蓄積されていく。   By performing the risk assessment 12, problem extraction 13 and countermeasure examination 14 of FIG. 1 in each project, information on the risk assessment sheet / problem management sheet is accumulated in the shared DB.

3.活用過程
図1のリスク評価において、新規プロジェクトの計画段階における、リスク評価シートの評価点欄(図2:列26)に入力する。検索キー16として以下に述べるキーを選択指定することにより、プロジェクト検索・表示サーバ(計算機)5が蓄積DBから類似するプロジェクトを検索する。検索キーは複数選択することが可能である。
3. Utilization process In the risk assessment of FIG. 1, the risk assessment sheet is entered in the assessment score column (FIG. 2: column 26) in the planning stage of the new project. By selecting and specifying the key described below as the search key 16, the project search / display server (computer) 5 searches for similar projects from the storage DB. A plurality of search keys can be selected.

検索キー1:問題点管理シートの入力があること。
検索キー2:大項目単位の評価点数の偏りが類似すること。
検索キー3:リスク評価点の合計点数または平均点数が類似すること。
検索キー4:開発規模が類似すること。
検索キー5:適用技術が同種であること。
検索キー6:特定の大項目の評価点が類似すること。
Search key 1: A problem management sheet is input.
Search key 2: Similarity of evaluation score bias for large items.
Search key 3: The total score or average score of risk evaluation points is similar.
Search key 4: The development scale is similar.
Search key 5: Applicable technology is the same type.
Search key 6: The evaluation score of a specific large item is similar.

尚、ここでいう「類似」とは、例えば新規プロジェクトの開発規模・評価点等の数値に対して、蓄積DB中のプロジェクトの対応項目の数値が±10%以内に入っている場合等をいう。   Note that “similarity” here refers to the case where the numerical value of the corresponding item of the project in the accumulation DB is within ± 10% with respect to the numerical value such as the development scale / evaluation point of the new project, for example. .

図1のプロジェクト選択画面17に、システムが検索した結果に基づく参考プロジェクト選択画面を表示する。   A reference project selection screen based on the search result of the system is displayed on the project selection screen 17 in FIG.

図3(A)はレーダーチャートの表示例を示す図である。図3(B)は、レーダーチャートと対応する表を示す。図3(A)は、システムが抽出したプロジェクトを、大項目単位の評価点を軸30としてレーダーチャート表示31を行った図である。図3(B)は、抽出プロジェクト情報32として、参照プロジェクト選択のための補足情報のため開発部署・開発規模・適用技術34を合わせて表示させた表である。この表は、選択チェックボックス33を持つ。図3(A)と図3(B)とは対応しており、太い実線が新規入力プロジェクトであり、その他の線が過去のプロジェクトa〜dまでに関するレーダーチャート表示である。レーダーチャートは、受注、顧客、難易度、新技術・新規性、開発日程、開発環境などの大項目に相当する軸を有しており、大項目毎に評価点がプロジェクト毎にプロットされている。複数のプロジェクトのうち表示させるプロジェクトは選択することができる。このレーダーチャートに基づいて、バランス、合計点、軸を中心とした評価点の大小やある項目の評価点、評価点の絶対値出なく形状の相似性などから類似性又は相違点を一見して把握することができる。   FIG. 3A shows a display example of a radar chart. FIG. 3B shows a table corresponding to the radar chart. FIG. 3A is a diagram in which a radar chart display 31 is performed on a project extracted by the system with an evaluation point of a large item unit as an axis 30. FIG. 3B is a table in which the development department, the development scale, and the applied technology 34 are displayed together as the extracted project information 32 for supplementary information for selecting a reference project. This table has a selection check box 33. FIG. 3A and FIG. 3B correspond to each other, and a thick solid line is a new input project, and the other lines are radar chart displays related to past projects a to d. The radar chart has axes corresponding to major items such as orders, customers, difficulty, new technology and novelty, development schedule, development environment, etc., and evaluation points are plotted for each major item for each project. . A project to be displayed can be selected from a plurality of projects. Based on this radar chart, look at similarities or differences at a glance based on the balance, total score, the size of the score centered around the axis, the score of a certain item, the similarity of the shape without the absolute value of the score, etc. I can grasp it.

例えば、入力プロジェクトに対して、プロジェクトaとプロジェクトbとは、総計の評価点はほぼ同じでありかつほぼ相似の形状であり。プロジェクトcは、評価点もほぼ同じでありさらに形状もほぼ相似であり、プロジェクトdは、ほぼ相似形であるが、全ての評価点が入力プロジェクトよりも小さいことがわかる。   For example, with respect to the input project, the project a and the project b have substantially the same evaluation point and a substantially similar shape. The project c has almost the same evaluation point and the shape is almost similar, and the project d is almost similar, but it can be seen that all the evaluation points are smaller than the input project.

例えば、評価点の偏りに類似性があれば、偏りの似ている評価項目に関する今後の注意点を知ることができ、また、全体形状に相似性があれば、相似する過去のプロジェクト全体の項目を参照する必要があることがわかる。このように、大量の情報を、レーダーチャート化して表示することで、リスクの予測がしやすくなる。すなわち、だれにとってもわかりやすく、専門性が必要ないユーザインターフェイスを提供することができるという利点がある。   For example, if there is similarity in evaluation point bias, you can know future caution points regarding evaluation items with similar bias, and if there is similarity in overall shape, items of similar past projects as a whole It is necessary to refer to In this way, it becomes easier to predict risk by displaying a large amount of information in a radar chart. That is, there is an advantage that it is possible to provide a user interface that is easy for anyone to understand and does not require specialization.

図3(A)と図3(B)とを参照すれば、過去の蓄積データを、レーダーチャートの類似性などから容易に検索することができるため、開発するプロジェクトを始めるにあたって、いかなる問題点が発生しうるかなどを簡単に調べることができる。   3A and 3B, it is possible to easily search past accumulated data based on the similarity of radar charts, so there are no problems when starting a development project. You can easily check whether it can occur.

図1のプロジェクト選択18において、参照したいプロジェクトの選択チェックボックス(図3の符号33)にチェックを入れると、プロジェクトが選択され、該当するプロジェクトの『リスク−問題点対応シート』(図4の符号41、42)を参照することができる。   In the project selection 18 of FIG. 1, when a selection check box (reference numeral 33 in FIG. 3) of a project to be referred to is checked, the project is selected and a “risk-problem correspondence sheet” (reference numeral in FIG. 4) of the corresponding project. 41, 42).

尚、レーダーチャートによる分析を簡単にするために、全プロジェクトの平均からの新規リスク評価点の差分のみをプロットして特異点をわかりやすくするように表示させても良い。また、レーダーチャートの内部の面積が同じになるようにノーマライズして特異点をわかりやすくしても良い。また、季節、場所、年度などの要因が同じプロジェクトだけを表示させ、プロジェクトのカテゴリ別に表示させるようにしても良い。特異点をポイントすると、特異点に関連する問題点と対応策とが表示されるようにしても良い。   In order to simplify the analysis by the radar chart, only the difference of the new risk evaluation points from the average of all projects may be plotted and displayed so that the singular points can be easily understood. In addition, the singularity may be easily understood by normalizing so that the area inside the radar chart is the same. Alternatively, only projects with the same factors such as season, place, year, etc. may be displayed and displayed by project category. When a singular point is pointed, a problem related to the singular point and a countermeasure may be displayed.

また、過去のレーダーチャートを素早く表示させるために、表に基づいてチャートを表示させるのではなく、チャート自体をプロジェクト毎に蓄積するデータベースを設けておき、これに基づいてレーダーチャートを表示させることにより、迅速に表示を行わせることができる。   Also, in order to quickly display past radar charts, instead of displaying charts based on tables, a database that stores charts for each project is provided, and radar charts are displayed based on this database. , Can be displayed quickly.

図1のリスク−問題点対応シート19において、システムが図4に示す『リスク−問題点対応シート』を表示する。この際、リスク評価シートの情報を、リスク評価シートのフォーマットに従い表示する(符号41)とともに、問題点管理シートの情報を、対応リスク項番をキーとして、リスク評価シートのフォーマットに従ってリスク項目毎に表示する(符号42)。これにより、リスク項番により対応対けされたリスク−問題点対応シートを作成することができる。尚、評価点は、適宜見直しすることが可能であるが、過去の評価点と現在の評価点との差分を掲載しておくことにより、後の見直しの際に役立つ。例えば、プロジェクト計画時点では、顧客に通常の仕様決定能力があると想定して評価項目「顧客に仕様決定能力があるか。」の評価点を3にしていた場合に、プロジェクトの途中で顧客事情による仕様変更が度々発生して工程が大幅に遅延したことにより評価点を事後的に5に変更した場合に、その事実を残しておくことによって、後の同種のプロジェクト(適用技術、開発規模、レーダーチャートの特性等が類似)の参考とすることができる。尚、リスク項番には発見工程から対策・効果に関する記載が無い(該当なし)のケースもあり得る。   In the risk-problem correspondence sheet 19 of FIG. 1, the system displays a “risk-problem correspondence sheet” shown in FIG. At this time, information on the risk evaluation sheet is displayed according to the format of the risk evaluation sheet (reference numeral 41), and information on the problem management sheet is displayed for each risk item according to the format of the risk evaluation sheet using the corresponding risk item number as a key. Display (reference numeral 42). As a result, a risk-problem correspondence sheet corresponding to the risk item number can be created. Although the evaluation points can be reviewed as appropriate, posting the difference between the past evaluation points and the current evaluation points is useful for subsequent review. For example, at the time of project planning, if the evaluation item “Is the customer have specification determination capability?” Is set to 3 on the assumption that the customer has normal specification determination capability, the customer situation in the middle of the project If the evaluation score is changed to 5 afterwards due to frequent delays in the process due to frequent changes in specifications, the fact remains that way, so that later projects of the same type (applied technology, development scale, The characteristics of the radar chart are similar). In addition, there may be cases where the risk item number has no description of countermeasures / effects from the discovery process (not applicable).

このリスク−問題点対応シートを用いれば、リスク項番と、大項目と、リスク項番に対応する評価項目と、その評価点(図では1〜5まで)と、発見工程と、発見工程における問題点とそれに対する対策及び効果を一覧することができ、リスクの高い部分についての事前対策や、同様のリスクの偏りを持つために発生しうる問題点を事前に把握し、対策を講じることが簡単にできるようになる。   If this risk-problem correspondence sheet is used, the risk item number, large item, evaluation item corresponding to the risk item number, its evaluation point (from 1 to 5 in the figure), the discovery process, and the discovery process It is possible to list problems, countermeasures against them, and their effects. It is possible to grasp in advance prior measures for high-risk parts and problems that may occur due to similar risk bias, and take countermeasures. It will be easy.

本発明を応用すると、種々のプロジェクトを立ち上げる際の最善の方法を予測することも可能となる。   Application of the present invention also makes it possible to predict the best way to launch various projects.

本発明の一実施の形態によるプロジェクトリスクの複合評価による対策事例検索システムの構成例を示すブロック図である。It is a block diagram which shows the structural example of the countermeasure example search system by the composite evaluation of the project risk by one embodiment of this invention. 図2(A)は基本情報の例、図2(B)はリスク評価シートと問題点管理シートのフォーマット例である。FIG. 2A shows an example of basic information, and FIG. 2B shows an example format of a risk evaluation sheet and a problem management sheet. 参考プロジェクト選択画面の表示例であり、図3(A)はレーダーチャート図、図3(B)は表により示した図である。FIG. 3A is a display example of a reference project selection screen. FIG. 3A is a radar chart, and FIG. 3B is a table. 表示される参照プロジェクトのリスク−問題点対応シートの表示例を示す図である。It is a figure which shows the example of a display of the risk-problem correspondence sheet | seat of the reference project displayed.

符号の説明Explanation of symbols

10…リスク評価シートDB、10a…リスク項番、11…問題点管理シートDB、11a…対応リスク項番、12…リスク評価入力、13…問題点入力、14…対策入力、15…リスク評価入力、16…検索キー選択入力、17…プロジェクト選択画面表示、18…プロジェクト選択入力、19…リスク−問題点対応シート表示画面、20…プロジェクト基本情報、21…リスク評価シート、22…問題点管理シート、23…リスク項目欄、24…大項目欄、25…評価項目欄、26…評価点欄、27…対応リスク項番欄、30…レーダーチャート軸、31…レーダーチャート、32…抽出プロジェクト情報、33…選択チェックボックス、34…プロジェクト補足情報、41…リスク評価シート情報、42…問題点管理シート情報。   DESCRIPTION OF SYMBOLS 10 ... Risk evaluation sheet DB, 10a ... Risk item number, 11 ... Problem management sheet DB, 11a ... Corresponding risk item number, 12 ... Risk evaluation input, 13 ... Problem input, 14 ... Countermeasure input, 15 ... Risk evaluation input 16 ... Search key selection input, 17 ... Project selection screen display, 18 ... Project selection input, 19 ... Risk-problem correspondence sheet display screen, 20 ... Project basic information, 21 ... Risk assessment sheet, 22 ... Problem management sheet 23 ... Risk item column, 24 ... Large item column, 25 ... Evaluation item column, 26 ... Evaluation point column, 27 ... Corresponding risk item number column, 30 ... Radar chart axis, 31 ... Radar chart, 32 ... Extracted project information, 33 ... Selection check box, 34 ... Project supplement information, 41 ... Risk assessment sheet information, 42 ... Problem management sheet information.

Claims (5)

異なるセクション間及び異なるプロジェクト間で共通のフォーマット形式を有し、プロジェクト毎に作成されたシートであって、プロジェクトの遂行にあたってリスク要因となりうるリスクに対して付与されるリスク項番と、該リスク項番が付されたリスク要因に関連する評価項目と、該評価項目毎に付与されリスクの大小に基づくリスク評価点と、により管理されるリスク評価シートと、前記リスク項番と対応する対応リスク項番と、問題点発見工程と問題点と対策及びその効果とのうちから選択される少なくともいずれかと、により管理される問題点管理シートと、を前記セクション間で共通に入力し参照することができる共通データベースに入力手段を介して蓄積していくステップと、
新規プロジェクトの計画段階において、該新規プロジェクトに関する新規リスク評価シートに対して初期リスク評価点を前記リスク項番毎に入力手段により入力するステップと、
前記初期評価点に対応するリスク項番を検索キーとして該リスク項番に対応する対応リスク項番を有する問題点管理シートの記載を計算機により抽出するステップと
を有するプロジェクトリスクの検索方法。
A risk item number assigned to a risk that has a common format format between different sections and between different projects and is created for each project and can be a risk factor in the execution of the project, and the risk item A risk evaluation sheet managed by an evaluation item related to the numbered risk factor, a risk evaluation point assigned to each evaluation item based on the magnitude of the risk, and a corresponding risk item corresponding to the risk item number The problem management sheet managed by the number, at least one selected from the problem finding process, the problem, the countermeasure, and the effect thereof can be input and referenced in common between the sections. Storing in the common database via input means;
In the planning stage of a new project, a step of inputting an initial risk evaluation point for each risk item number with respect to a new risk evaluation sheet relating to the new project by an input means;
A project risk search method comprising: using a computer to extract a description of a problem management sheet having a corresponding risk item number corresponding to the risk item number, using the risk item number corresponding to the initial evaluation point as a search key.
さらに、前記新規プロジェクトの開始時点からプロジェクトが安定して稼動する状態になった時点までの間に発生した問題点発見工程と問題点と対応策と、のうちから選択される少なくともいずれかを前記対応リスク項番毎に入力手段により入力していくステップを順次行うことを特徴とする請求項1に記載のプロジェクトリスクの検索方法。   Further, at least one selected from a problem finding process, a problem, and a countermeasure that occurred between the start time of the new project and the time when the project is in a stable operation state is selected. 2. The project risk search method according to claim 1, wherein the step of inputting by the input means is sequentially performed for each corresponding risk item number. 請求項1又は2に記載の検索方法に基づいて作成された共通データベースの活用方法であって、
新規プロジェクトの計画段階におけるリスク評価シートの評価点を入力手段により入力するステップと、
検索キーとして以下の検索キー1〜6までの少なくともいずれかを検索キーとして選択することにより、前記共通データベースから類似するプロジェクトを計算機により検索するステップと、
検索結果に基づく参考プロジェクト選択画面を表示手段により表示するステップと
を含む活用方法。
検索キー1:前記問題点管理シートの入力があること。
検索キー2:評価項目又は該評価項目のうち関連する前記リスク項目をまとめた大項目単位の評価点数の偏りが類似すること。
検索キー3:前記リスク評価点の合計点数又は平均点数が類似すること。
検索キー4:プロジェクトの開発規模が類似すること。
検索キー5:プロジェクトに関連する技術が同種であること。
検索キー6:特定の前記大項目の評価点が類似すること。
A method of utilizing a common database created based on the search method according to claim 1,
A step of inputting an evaluation point of a risk evaluation sheet at a planning stage of a new project by an input means;
Searching a similar project from the common database by a computer by selecting at least one of the following search keys 1 to 6 as a search key:
And a step of displaying a reference project selection screen based on the search result by a display means.
Search key 1: The problem management sheet is input.
Retrieval key 2: The evaluation item or the evaluation item biases of the large items obtained by collecting the related risk items among the evaluation items are similar.
Search key 3: The total score or average score of the risk evaluation points is similar.
Search key 4: The project development scale is similar.
Search key 5: The technology related to the project is the same.
Search key 6: The evaluation score of a specific large item is similar.
請求項1又は2に記載の検索方法に基づいて作成された共通データベースの活用方法であって、
前記新規プロジェクトの計画段階における潜在リスク又は事前対応策検討のための他の参考プロジェクト候補の問題点と対応策事例とその効果との少なくともいずれかを参照する場合に、前記新規プロジェクトのリスク評価を実施した結果と、複数の参考プロジェクト候補のリスク評価値と、を評価項目又は該評価項目のうち関連する項目をまとめた大項目と評価点とを変数とするレーダーチャートにより表示手段を介して表示するステップと、
該レーダーチャートに基づいて、プロジェクトに関する複数のリスク評価値をプロットしたグラフ形状の類似性又は評価点の偏りの類似性を含む特徴点を比較することにより、特徴点に関連性がある参考プロジェクト候補を計算機により抽出し、該参考プロジェクト候補に関する問題点と対応策事例とその効果との少なくともいずれかを表示手段を介して参照するステップと
を有する共通データベース活用方法。
A method of utilizing a common database created based on the search method according to claim 1,
The risk assessment of the new project is performed when reference is made to potential risks in the planning stage of the new project or at least one of the problems of other reference project candidates for proactive measures examination, countermeasure examples and their effects. The results and the risk evaluation values of multiple reference project candidates are displayed via the display means using a radar chart with the evaluation items or large items that summarize related items of the evaluation items and evaluation points as variables. And steps to
Based on the radar chart, reference project candidates that are related to the feature points are compared by comparing the feature points including the similarity of the graph shape in which a plurality of risk evaluation values related to the project are plotted or the similarity of the bias of the evaluation points. A common database utilization method including a step of extracting at least one of a problem related to the reference project candidate, a countermeasure example, and its effect through a display means.
異なるセクション間及び異なるプロジェクト間で共通のフォーマット形式を有し、プロジェクト毎に作成されたシートであって、プロジェクトの遂行にあたってリスク要因となりうるリスク項番と、該リスク項番が付されたリスク要因に関連する評価項目と、該評価項目毎に付与されリスクの大小に基づくリスク評価点と、により管理されるリスク評価シートに対してプロジェクトのリスク評価点を入力するリスク評価入力部と、
前記リスク項番と対応する対応リスク項番入力欄と、問題点発見工程と、問題点と、対応策と効果とのうち少なくともいずれかと、を有する問題点管理シートに対して、それぞれの項目を入力する問題点・対策入力部と、
前記リスク評価シートを蓄積したリスク評価シートデータベースと、前記リスク項番と前記対応リスク項番とにより、前記リスク評価シートデータベース内のリスク評価シートと関連付けされる前記問題点管理シートを蓄積した問題点管理シートデータベースと、
新規リスク評価点の前記リスク入力部への入力に応じて、前記リスク評価シートデータベースと問題点管理シートデータベースとを検索し、関連するプロジェクトを検索しその内容を表示するプロジェクト検索・表示サーバと
を有するプロジェクトリスク評価システム。
A risk item number that has a common format format between different sections and between different projects and is created for each project and can be a risk factor in the execution of the project, and the risk factor to which the risk item number is assigned A risk evaluation input unit for inputting a risk evaluation score of a project with respect to a risk evaluation sheet managed by the evaluation item related to the item, a risk evaluation point assigned to each evaluation item based on the magnitude of the risk, and
Each item for a problem management sheet having a corresponding risk item number input field corresponding to the risk item number, a problem finding step, a problem, a countermeasure and an effect Problems to be input and countermeasure input section,
The risk assessment sheet database that accumulates the risk assessment sheet, and the problem management sheet that is associated with the risk assessment sheet in the risk assessment sheet database by the risk item number and the corresponding risk item number Management sheet database,
A project search / display server that searches the risk evaluation sheet database and the problem management sheet database in response to input of a new risk evaluation point to the risk input unit, searches for related projects, and displays the contents thereof. Project risk assessment system.
JP2003389734A 2003-11-19 2003-11-19 Retrieval method for project risk, evaluation system and common database utilization method Pending JP2005149414A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003389734A JP2005149414A (en) 2003-11-19 2003-11-19 Retrieval method for project risk, evaluation system and common database utilization method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003389734A JP2005149414A (en) 2003-11-19 2003-11-19 Retrieval method for project risk, evaluation system and common database utilization method

Publications (1)

Publication Number Publication Date
JP2005149414A true JP2005149414A (en) 2005-06-09

Family

ID=34696382

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003389734A Pending JP2005149414A (en) 2003-11-19 2003-11-19 Retrieval method for project risk, evaluation system and common database utilization method

Country Status (1)

Country Link
JP (1) JP2005149414A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007188314A (en) * 2006-01-13 2007-07-26 Takuto:Kk Video data extraction system and computer program
JP2007249572A (en) * 2006-03-15 2007-09-27 Mitsubishi Electric Corp Project management support device, project management support method, and project management support program
JP2009098954A (en) * 2007-10-17 2009-05-07 Fuji Xerox Co Ltd System, device, and program for managing risk classification
EP2116962A1 (en) * 2006-12-26 2009-11-11 Fujitsu Limited Detailed data storage device, detailed data storing program, and detailed data storing method
JP2011018294A (en) * 2009-07-10 2011-01-27 Fourlink Systems:Kk Data matching device
JP2013196297A (en) * 2012-03-19 2013-09-30 Ntt Data Corp Method for determining management item used in project management server, program and server
JP2015167049A (en) * 2015-07-01 2015-09-24 株式会社エヌ・ティ・ティ・データ Method for determining management item used in project management server, program and server
KR101618779B1 (en) * 2013-11-15 2016-05-12 심화준 system and method for managing project
CN110717646A (en) * 2019-09-03 2020-01-21 福建省农村信用社联合社 Method and system for realizing bank demand post-evaluation
JP2021071912A (en) * 2019-10-31 2021-05-06 株式会社日立製作所 Mapping system and mapping method
CN113344539A (en) * 2021-06-22 2021-09-03 上海外高桥造船有限公司 Project planning system and method, electronic device and storage medium
CN113537662A (en) * 2020-04-15 2021-10-22 上海汽车集团股份有限公司 Risk detection method and device
CN117094184A (en) * 2023-10-19 2023-11-21 上海数字治理研究院有限公司 Modeling method, system and medium of risk prediction model based on intranet platform

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007188314A (en) * 2006-01-13 2007-07-26 Takuto:Kk Video data extraction system and computer program
JP2007249572A (en) * 2006-03-15 2007-09-27 Mitsubishi Electric Corp Project management support device, project management support method, and project management support program
EP2116962A1 (en) * 2006-12-26 2009-11-11 Fujitsu Limited Detailed data storage device, detailed data storing program, and detailed data storing method
EP2116962A4 (en) * 2006-12-26 2011-03-02 Fujitsu Ltd Detailed data storage device, detailed data storing program, and detailed data storing method
US8775370B2 (en) 2006-12-26 2014-07-08 Fujitsu Limited Data storage apparatus and method
JP2009098954A (en) * 2007-10-17 2009-05-07 Fuji Xerox Co Ltd System, device, and program for managing risk classification
JP2011018294A (en) * 2009-07-10 2011-01-27 Fourlink Systems:Kk Data matching device
JP2013196297A (en) * 2012-03-19 2013-09-30 Ntt Data Corp Method for determining management item used in project management server, program and server
KR101618779B1 (en) * 2013-11-15 2016-05-12 심화준 system and method for managing project
JP2015167049A (en) * 2015-07-01 2015-09-24 株式会社エヌ・ティ・ティ・データ Method for determining management item used in project management server, program and server
CN110717646A (en) * 2019-09-03 2020-01-21 福建省农村信用社联合社 Method and system for realizing bank demand post-evaluation
JP2021071912A (en) * 2019-10-31 2021-05-06 株式会社日立製作所 Mapping system and mapping method
JP7284687B2 (en) 2019-10-31 2023-05-31 株式会社日立製作所 Mapping system and mapping method
CN113537662A (en) * 2020-04-15 2021-10-22 上海汽车集团股份有限公司 Risk detection method and device
CN113344539A (en) * 2021-06-22 2021-09-03 上海外高桥造船有限公司 Project planning system and method, electronic device and storage medium
CN117094184A (en) * 2023-10-19 2023-11-21 上海数字治理研究院有限公司 Modeling method, system and medium of risk prediction model based on intranet platform
CN117094184B (en) * 2023-10-19 2024-01-26 上海数字治理研究院有限公司 Modeling method, system and medium of risk prediction model based on intranet platform

Similar Documents

Publication Publication Date Title
JP6847801B2 (en) Design support device and design support method
US20080097937A1 (en) Distributed method for integrating data mining and text categorization techniques
US8250637B2 (en) Determining the degree of relevance of duplicate alerts in an entity resolution system
JP5823943B2 (en) Forensic system, forensic method, and forensic program
JP2005149414A (en) Retrieval method for project risk, evaluation system and common database utilization method
CN109213773B (en) Online fault diagnosis method and device and electronic equipment
JP2007257223A (en) Financial relevant information integrated display program, device, and method
JP2019086940A (en) Relevant score calculating system, method and program
JP5827206B2 (en) Document management system, document management method, and document management program
JP5379927B2 (en) Promising stage judging device using promising technology life cycle
JP5140509B2 (en) Design case search device, design case search program
KR101671890B1 (en) apparatus for analyzing business traction information and method fornalyzing business traction information
JP6160503B2 (en) Information input system and program
JP6655582B2 (en) Data integration support system and data integration support method
JP7295792B2 (en) Data analysis device and data analysis method
TW201539217A (en) A document analysis system, document analysis method and document analysis program
JP5060601B2 (en) Document analysis apparatus and program
JP7386501B2 (en) Document processing program and information processing device
WO2020070929A1 (en) Plant apparatus information management system
WO2018016001A1 (en) Data modeling system and data modeling method
JP2009134375A (en) Financing examination support system and its method
JP5078960B2 (en) Text processing apparatus and computer program
JP6440351B2 (en) Product sales support system, product sales support method, and product sales support device
KR102519538B1 (en) Data flow tracking method and system
WO2016157707A1 (en) Table operation system, method, and program