JP2005099906A - Work management system and its method and its program - Google Patents

Work management system and its method and its program Download PDF

Info

Publication number
JP2005099906A
JP2005099906A JP2003329880A JP2003329880A JP2005099906A JP 2005099906 A JP2005099906 A JP 2005099906A JP 2003329880 A JP2003329880 A JP 2003329880A JP 2003329880 A JP2003329880 A JP 2003329880A JP 2005099906 A JP2005099906 A JP 2005099906A
Authority
JP
Japan
Prior art keywords
work
man
hour
person
initial target
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003329880A
Other languages
Japanese (ja)
Inventor
Kazuhiro Hayashi
和弘 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seiko Epson Corp
Original Assignee
Seiko Epson Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seiko Epson Corp filed Critical Seiko Epson Corp
Priority to JP2003329880A priority Critical patent/JP2005099906A/en
Publication of JP2005099906A publication Critical patent/JP2005099906A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a work management system for adjusting the workloads of each staff according to the actual progress. <P>SOLUTION: As for a project selected this time, a CPU of a work management computer assigns works which can not be processed until the initial target time limit among works assigned to staffs belonging to the project to staffs belonging to the same project who afford more works, or when any work which can not be processed until the initial target time limit is left even after the works are assigned to the staffs belonging to the same project who afford more works, the CPU assigns those works to the staffs belonging to a project whose importance is lower than the project. Thus, a plan is corrected in order to finish the project within the initial target time limit, and when any work which can not be processed until the initial target time limit is finally left, the initial target time limit is extended for dealing with that (S300 to S360). <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

本発明は、仕事管理システム、その方法及びそのプログラムに関する。   The present invention relates to a job management system, a method thereof, and a program thereof.

民間企業や官庁などにおける仕事には、プロジェクトを組んで複数の人員で処理するものがある。このようなプロジェクトには難度が易しいものから難しいものまで種々存在し、また優先度の低いものから高いものまで種々存在している。このようなプロジェクトを遂行するにあたり、その遂行前にどれだけの人員でどれだけの期間をかけて行うかとかプロジェクトの全仕事量を各人員にどのように割り振るか等が計画され、その計画に沿ってプロジェクトが遂行される。一方、プロジェクトが始まると、実際の進捗状況が当初の予定よりもずれることがしばしばあるため、この点を勘案しながら仕事を管理する必要がある。そのような仕事を管理するシステムとしては、例えば、特許文献1の仕事管理システムが知られている。この仕事管理システムでは、各工程で仕事が処理されるのに伴い、各工程ごとの仕事残量が自動的に算出されて画面表示されたりプリントアウトされたりする。このため、管理者はその出力結果を見ることにより仕事残量を正確に把握することができる。
特開平9−198434号公報
Some jobs in private companies and government offices are organized by projects and handled by multiple personnel. There are various kinds of such projects from easy to difficult, and from low to high priority. Before carrying out such a project, it is planned how many people and how long it will take before the execution, how to allocate the total work of the project to each person, etc. Along with the project. On the other hand, when a project starts, the actual progress often deviates from the original schedule, so it is necessary to manage work while taking this into consideration. As a system for managing such work, for example, a work management system of Patent Document 1 is known. In this work management system, as the work is processed in each process, the remaining work for each process is automatically calculated and displayed on the screen or printed out. Therefore, the administrator can accurately grasp the remaining work amount by looking at the output result.
JP-A-9-198434

ところで、同じプロジェクトに属する人員でも実際の進捗状況が当初の予定より早い人もいれば遅い人もいるし、複数のプロジェクトを見たときに実際の進捗状況が当初の予定より早いプロジェクトもあれば遅いプロジェクトもある。このため、実際の進捗状況に応じて各人員の仕事量を調整する必要が生じるが、これまでの仕事管理システムはこのような事情を十分加味していなかった。   By the way, there are some people who belong to the same project whose actual progress is earlier or later than the original schedule, and there are projects whose actual progress is earlier than the original schedule when looking at multiple projects. Some projects are slow. For this reason, it is necessary to adjust the work amount of each person according to the actual progress, but the work management systems so far have not fully taken into account such circumstances.

本発明の仕事管理システム、その方法及びそのプログラムは、実際の進捗状況に応じて各人員の仕事量を調整することができるようにすることを目的の一つとする。   One of the objects of the work management system, the method thereof, and the program thereof according to the present invention is to be able to adjust the work amount of each person in accordance with the actual progress.

本発明の仕事管理システム、その方法及びそのプログラムは、上述の目的の少なくとも一つを達成するために以下の手段を採った。   In order to achieve at least one of the above objects, the work management system, method and program thereof according to the present invention employ the following means.

本発明の仕事管理システムは、各人員に仕事を割り振り該仕事が完了するまでの初期目標工数及び初期目標期限を各人員ごとに設定したあと各人員の仕事の管理を行う仕事管理システムであって、
各人員ごとに初期目標工数を記憶する初期目標工数記憶手段と、
任意の管理時期にオペレータによって入力される各人員の実績工数を記憶する実績工数記憶手段と、
任意の管理時期にオペレータによって入力される各人員の仕事達成率を記憶する仕事達成率記憶手段と、
各人員ごとに前記実績工数と前記仕事達成率とに基づいて前記管理時期から前記初期目標期限までに処理すべき実績ベース残目標工数を算出する実績ベース残目標工数算出手段と、
各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分を他の人員に割り振り、余裕を持って処理可能と判定されたときには該人員に他の人員の処理不能な分を割り振る工数調整手段と、
を備えたものである。
The work management system of the present invention is a work management system for managing the work of each person after assigning the work to each person and setting the initial target man-hour and the initial target deadline until the work is completed for each person. ,
Initial target man-hour storage means for storing an initial target man-hour for each person;
Actual man-hour storage means for storing the actual man-hours of each person input by the operator at an arbitrary management time;
Work achievement rate storage means for storing the work achievement rate of each person input by the operator at an arbitrary management time;
A performance-based remaining target man-hour calculating means for calculating a performance-based remaining target man-hour to be processed from the management time to the initial target deadline based on the actual man-hour and the work achievement rate for each person;
It is determined based on the initial target man-hours for each person whether or not the performance-based remaining target man-hours can be processed from the management time to the initial target deadline for each person. The man-hour adjusting means for allocating the unprocessable portion of the remaining performance-based man-hours to other personnel, and allocating the unmanageable portions of other personnel to the personnel when it is determined that the manpower can be processed with a margin,
It is equipped with.

この仕事管理システムでは、各人員ごとに、実績工数と仕事達成率とに基づいて算出した実績ベース残目標工数を管理時期から初期目標期限までに処理できるか否かを各人員の初期目標工数をもとに判定する。そして、処理不能と判定されたときには実績ベース残目標工数のうち処理不能な分を他の人員に割り振り、余裕を持って処理可能と判定されたときにはその人員に他の人員の処理不能な分を割り振る。このため、実際の進捗状況に応じて各人員に仕事を適切に振り分け直すことができ、その結果、当初各人員に割り振った仕事が初期目標期限どおりに完了するケースが多くなる。   In this work management system, the initial target man-hour of each person is determined as to whether or not the performance-based remaining target man-hours calculated based on the actual man-hours and work achievement rate can be processed from the management time to the initial target deadline. Judge based. And when it is determined that it cannot be processed, the unprocessable part of the performance-based remaining target man-hour is allocated to other personnel, and when it is determined that it can be processed with a margin, the amount of other personnel that cannot be processed by that personnel is allocated. Allocate. For this reason, it is possible to appropriately reallocate the work to each person according to the actual progress, and as a result, there are many cases where the work initially assigned to each person is completed according to the initial target deadline.

本発明の仕事管理システムにおいて、前記工数調整手段は、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定するにあたり、各人員ごとに前記初期目標工数から前記実績工数を差し引いて算出した初期ベース残目標工数と前記実績ベース残目標工数とを比較し、前者が後者より小さいときには処理不能と判定し、前者が後者より大きいときには余裕を持ってその仕事を処理可能と判定してもよい。こうすれば、初期ベース残目標工数と実績ベース残目標工数との大小関係に基づいて初期目標期限までにその仕事が完了するか否かを適切に判定することができる。   In the work management system of the present invention, the man-hour adjusting means determines whether or not the performance-based remaining target man-hours can be processed from the management time to the initial target deadline for each manpower by using the initial target man-hour for each manpower. In making the determination based on the comparison, the initial base remaining target man-hour calculated by subtracting the actual man-hour from the initial target man-hour for each person is compared with the actual base remaining target man-hour. If the former is larger than the latter, it may be determined that the work can be processed with a margin. By doing this, it is possible to appropriately determine whether or not the work is completed by the initial target deadline based on the magnitude relationship between the initial base remaining target man-hour and the actual base remaining target man-hour.

本発明の仕事管理システムにおいて、前記実績ベース残目標工数算出手段は、各人員ごとに前記実績工数と前記仕事達成率とから1実績工数当たりの仕事達成率を仕事達成率として算出し、残余の仕事達成率を前記1実績工数当たりの仕事達成率で除して実績ベース残目標工数を算出してもよい。こうすれば、実績工数のみならず仕事達成率を考慮して管理時期から初期目標期限までに必要な工数(実績ベース残目標工数)を算出するため、実績ベース残目標工数の妥当性が高くなる。   In the work management system of the present invention, the performance-based remaining target man-hour calculating means calculates a work achievement rate per actual man-hour as a work achievement rate from the actual man-hour and the work achievement rate for each personnel, The actual achievement target remaining man-hour may be calculated by dividing the work achievement rate by the work achievement rate per one actual man-hour. In this way, the number of man-days required from the management period to the initial target deadline (actual base remaining target man-hours) is calculated in consideration of not only the actual man-hours but also the work achievement rate. .

本発明の仕事管理システムは、各仕事ごとに重要度を記憶する仕事重要度記憶手段、を備え、前記工数調整手段は、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分の少なくとも一部を該仕事よりも重要度の低い仕事を余裕を持って処理可能な人員に割り振ってもよい。こうすれば、重要度の高い仕事ほど初期目標期限に遅れることなく完了することができる。ここで、仕事の重要度は、仕事の重要性、優先性及び緊急性の少なくとも一つに基づいて決定してもよい。   The work management system of the present invention includes work importance storage means for storing importance for each work, and the man-hour adjusting means calculates the performance-based remaining target man-hour from the management time to the initial target for each person. Whether or not processing is possible by the deadline is determined based on the initial target man-hours for each person, and when it is determined that processing is impossible, at least a part of the performance-based remaining target man-hours that cannot be processed is The less important job may be allocated to a person who can handle it with a margin. In this way, the more important work can be completed without delaying the initial target deadline. Here, the importance of work may be determined based on at least one of importance, priority, and urgency of work.

本発明の仕事管理システムは、前記工数調整手段によって割り振ることのできなかった仕事につき前記初期目標期限を延長する期限調整手段、を備えていてもよい。こうすれば、どうしても初期目標期限どおりに完了するように調整できなかった仕事については期限を延長することにより対処できる。このように期限を延長する仕事は重要度の低いものが好ましい。あるいは、前記工数調整手段によって割り振ることのできなかった仕事につき新たな人員を追加して該人員に該仕事を割り振る人員増強調整手段、を備えていてもよい。こうすれば、当初各人員に割り振った仕事が初期目標期限どおりに完了するケースがより多くなる。   The work management system of the present invention may include a time limit adjusting means for extending the initial target time limit for a work that could not be allocated by the man-hour adjusting means. In this way, work that could not be adjusted to be completed according to the initial target deadline can be dealt with by extending the deadline. Thus, it is preferable that the work for extending the deadline is less important. Alternatively, it may be provided with personnel increase adjusting means for adding new personnel to the work that could not be allocated by the man-hour adjusting means and allocating the work to the personnel. This will increase the number of cases where work initially assigned to each person is completed according to the initial target deadline.

本発明の仕事管理システムにおいて、前記工数は、作業時間数としてもよい。例えば仕事が完了するまでに要する工程数を工数としてもよいが、各工程ごとに必要な時間が異なることが多いため、作業時間数を工数とした方が管理しやすい。ここで、作業時間数の単位は、時間を表す単位であればよく、例えば分、時、日、週、月などが挙げられる。   In the work management system of the present invention, the man-hour may be a work time. For example, the number of steps required to complete the work may be set as the man-hour. However, since the time required for each step is often different, it is easier to manage by setting the work time as the man-hour. Here, the unit of the number of working hours may be a unit representing time, and examples thereof include minutes, hours, days, weeks, months, and the like.

本発明の仕事管理システムは、所定のプロジェクト期間の開始前に該プロジェクトの全仕事を該プロジェクトに所属する各人員に割り振り前記プロジェクトが完了するまでの初期目標工数及び初期目標期限を各人員ごとに設定したあと各人員の仕事の管理を行うものとしてもよい。こうすれば、プロジェクトのうち多くの仕事が初期目標期限通りに完了するようになる。このとき、各プロジェクトごとに重要度を記憶するプロジェクト重要度記憶手段、を備え、前記工数調整手段は、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分の少なくとも一部を該プロジェクトよりも重要度の低いプロジェクトの仕事を余裕を持って処理可能な人員に割り振ってもよい。こうすれば、重要度の高いプロジェクトほど初期目標期限に遅れることなく完了する。ここで、プロジェクトの重要度は、プロジェクトの重要性、優先性及び緊急性の少なくとも一つに基づいて決定してもよい。   The work management system of the present invention allocates all the work of the project to each person belonging to the project before the start of a predetermined project period, and sets the initial target man-hour and the initial target deadline until the project is completed for each person. After setting, it is also possible to manage the work of each person. This will ensure that many tasks in the project are completed on time. At this time, a project importance degree storage means for storing the importance degree for each project is provided, and the man-hour adjusting means can process the performance-based remaining target man-hours for each person from the management time to the initial target deadline. Is determined based on the initial target man-hours for each person, and when it is determined that processing is impossible, at least a part of the performance-based remaining target man-hours that cannot be processed is more important than the project. You may allocate the work of a low project to a person who can handle it with ease. In this way, projects with higher importance will be completed without delay to the initial target deadline. Here, the importance of the project may be determined based on at least one of the importance, priority, and urgency of the project.

本発明の仕事管理方法は、各人員に仕事を割り振り該仕事が完了するまでの初期目標工数及び初期目標期限を各人員ごとに設定したあと、各人員ごとの初期目標工数を記憶する初期目標工数記憶手段、任意の管理時期にオペレータによって入力される各人員の実績工数を記憶する実績工数記憶手段及び任意の管理時期にオペレータによって入力される各人員の仕事達成率を記憶する仕事達成率記憶手段を利用して各人員の仕事の管理を行う、コンピュータ・ソフトウェアによる仕事管理方法であって、
(a)コンピュータが、各人員ごとに前記実績工数と前記仕事達成率とに基づいて前記管理時期から前記初期目標期限までに処理すべき実績ベース残目標工数を算出するステップと、
(b)コンピュータが、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分を他の人員に割り振り、余裕を持って処理可能と判定されたときには該人員に他の人員の処理不能な分を割り振るステップと、
を含むものである。
The work management method of the present invention allocates a work to each person, sets an initial target man-hour and an initial target deadline until the work is completed for each person, and then stores an initial target man-hour for each person. Storage means, actual man-hour storage means for storing the actual man-hours input by the operator at an arbitrary management time, and work achievement rate storage means for storing the work achievement ratio of each manpower input by the operator at an arbitrary management time Is a work management method using computer software that manages the work of each person using
(A) a computer calculating a result-based remaining target man-hour to be processed from the management time to the initial target time limit based on the actual man-hour and the work achievement rate for each person;
(B) The computer determines whether or not the performance-based remaining target man-hours can be processed for each person from the management time to the initial target deadline based on the initial target man-hours for each person and cannot be processed. Allocating the unprocessable portion of the performance-based remaining target man-hour to other personnel when it is determined, and allocating the unmanageable portion of the other personnel to the personnel when it is determined that it can be processed with a margin; ,
Is included.

この仕事管理方法では、各人員ごとに、実績工数と仕事達成率とに基づいて算出した実績ベース残目標工数を管理時期から初期目標期限までに処理できるか否かを各人員の初期目標工数をもとに判定する。そして、処理不能と判定されたときには実績ベース残目標工数のうち処理不能な分を他の人員に割り振り、余裕を持って処理可能と判定されたときにはその人員に他の人員の処理不能な分を割り振る。このため、実際の進捗状況に応じて各人員に仕事を適切に振り分け直すことができ、その結果、当初各人員に割り振った仕事が初期目標期限どおりに完了するケースが多くなる。なお、この仕事管理方法は、この方法を説明する前に述べた仕事管理システムが備えている種々の構成を利用するステップを含んでいてもよいし、その仕事管理システムの機能を実現するステップを含んでいてもよい。   In this work management method, the initial target man-hour of each person is determined whether or not the remaining performance-based target man-hour calculated based on the actual man-hours and work achievement rate can be processed from the management time to the initial target deadline. Judge based. And when it is determined that it cannot be processed, the unprocessable part of the performance-based remaining target man-hour is allocated to other personnel, and when it is determined that it can be processed with a margin, the amount of other personnel that cannot be processed by that personnel is allocated. Allocate. For this reason, it is possible to appropriately reallocate the work to each person according to the actual progress, and as a result, there are many cases where the work initially assigned to each person is completed according to the initial target deadline. The job management method may include a step of using various configurations provided in the job management system described before describing the method, and a step of realizing the function of the job management system. May be included.

本発明のプログラムは、上述した仕事管理方法の各ステップを1又は複数のコンピュータに実行させるためのプログラムである。このプログラムは、コンピュータが読み取り可能な記録媒体(例えばハードディスク、ROM、FD、CD、DVDなど)に記録されていてもよいし、伝送媒体(インターネットやLANなどの通信網)を介してあるコンピュータから別のコンピュータへ配信されてもよいし、その他どのような形で授受されてもよい。このプログラムを一つのコンピュータに実行させるか又は複数のコンピュータに各ステップを分担して実行させれば、上述した仕事管理方法の各ステップが実行されるため、上述した仕事管理方法と同様の作用効果が得られる。   The program of the present invention is a program for causing one or more computers to execute each step of the above-described work management method. This program may be recorded on a computer-readable recording medium (for example, hard disk, ROM, FD, CD, DVD, etc.), or from a computer via a transmission medium (communication network such as the Internet or LAN). It may be distributed to another computer, or may be exchanged in any other form. If this program is executed by a single computer or if each step is shared and executed by a plurality of computers, each step of the above-described work management method is executed. Is obtained.

次に、本発明の実施の形態を図面に基づいて説明する。図1は、本発明の一実施形態である仕事管理コンピュータ20の概略構成図、図2はハードディスク25に格納されているデータの説明図である。   Next, embodiments of the present invention will be described with reference to the drawings. FIG. 1 is a schematic configuration diagram of a work management computer 20 according to an embodiment of the present invention, and FIG. 2 is an explanatory diagram of data stored in a hard disk 25.

仕事管理コンピュータ20は、図1に示すように、各種制御を実行するCPU21と、各種制御プログラムを記憶するROM22と、データを一時記憶するRAM23、ハードディスク25にデータを記録したりハードディスク25からデータを読み出したりするハードディスクコントローラ(HDC)24と、ビデオ入出力端子に接続されたディスプレイ27の画面表示を制御するビデオコントローラ26と、USB端子に接続されたキーボードやマウス等の入力装置29を介して入力されるオペレータの指示を取り込むUSBコントローラ28とを備え、これらはバス30によってデータのやり取りが可能なように接続されている。   As shown in FIG. 1, the work management computer 20 records data in a CPU 21 that executes various controls, a ROM 22 that stores various control programs, a RAM 23 that temporarily stores data, a hard disk 25, and data from the hard disk 25. Input via a hard disk controller (HDC) 24 for reading, a video controller 26 for controlling the screen display of the display 27 connected to the video input / output terminal, and an input device 29 such as a keyboard or mouse connected to the USB terminal And a USB controller 28 that captures instructions from the operator, and these are connected by a bus 30 so that data can be exchanged.

ハードディスク25には、複数のプロジェクトにつき重要度の序列が記憶され、また、プロジェクトごとにそのプロジェクトの初期目標工数及び初期目標期限が記憶されている。重要度の序列や初期目標工数、初期目標期限は、入力装置29を介してオペレータによって入力されたあと、ハードディスク25に保存される。初期目標工数は、そのプロジェクトの全仕事が初期目標期限までに完了するようにそのプロジェクトに所属する各人員に仕事を割り振ったときの各人員の工数(作業時間数)であり、各プロジェクトが開始される前に計画されるものである。本実施形態では、図2に示すように、3つのプロジェクトA,B,Cにつき重要度の序列がプロジェクトA>プロジェクトB>プロジェクトCと記憶されている。この重要度は、本実施形態ではプロジェクトが企業の業績に及ぼす影響(重要性)に基づいて決められている。また、プロジェクトAについては等級「一般」の人員に難易度「単純」の仕事が初期目標工数「20d」(dは日数を表す、以下同じ)だけ割り振られ、等級「主任」の人員に難易度「やや難」の仕事が初期目標工数「10d」だけ割り振られ、等級「係長」の人員に難易度「難」の仕事が初期目標工数「20d」だけ割り振られている。プロジェクトB,Cについてもこれと同様に割り振られている。更に、3つのプロジェクトA,B,Cは、すべて初期目標期限が同日に設定されている。   The hard disk 25 stores an order of importance for a plurality of projects, and stores an initial target man-hour and initial target deadline for each project. The order of importance, initial target man-hours, and initial target deadline are input by the operator via the input device 29 and then stored in the hard disk 25. The initial target man-hours are the man-hours (working hours) of each person when work is allocated to each person who belongs to the project so that all work of the project is completed by the initial target deadline. It is planned before it is done. In the present embodiment, as shown in FIG. 2, the order of importance for the three projects A, B, and C is stored as project A> project B> project C. In this embodiment, the importance is determined based on the influence (importance) of the project on the business performance of the company. In addition, for Project A, a job with the degree of difficulty “simple” is allocated to personnel of the grade “general” for the initial target man-hour “20d” (d is the number of days, the same applies hereinafter), and the degree of difficulty is assigned to the personnel of the class “lead”. The “slightly difficult” job is assigned by the initial target man-hour “10d”, and the job of the difficulty “difficult” is assigned by the initial target man-hour “20d” to the personnel of the class “person in charge”. Projects B and C are allocated in the same manner. Further, all three projects A, B, and C have initial target deadlines set on the same day.

次に、こうして構成された仕事管理コンピュータ20の動作について説明する。仕事管理コンピュータ20のCPU21は、入力装置29を介してオペレータによって仕事管理プログラムの実行開始が指示されると、ROM22に記憶された仕事管理プログラムを読み出しこれを実行する。以下、このプログラムを図3のフローチャートに基づいて説明する。なお、仕事管理プログラムの実行開始を指示する時期を管理時期と称する。この管理時期は、オペレータ又はそのオペレータの上司によって任意に決定される。   Next, the operation of the work management computer 20 configured as described above will be described. The CPU 21 of the job management computer 20 reads out the job management program stored in the ROM 22 and executes it when the operator instructs the execution of the job management program via the input device 29. Hereinafter, this program will be described based on the flowchart of FIG. Note that the time for instructing the execution start of the work management program is referred to as a management time. This management time is arbitrarily determined by the operator or the supervisor of the operator.

仕事管理コンピュータ20のCPU21は、仕事管理プログラムが開始されると、まず、管理対象となるプロジェクトの指定、そのプロジェクトに所属する各人員ごとの実績工数、及びそのプロジェクトに所属する各人員ごとの仕事達成率の入力を促す画面をディスプレイ27に表示する(ステップS100)。この画面には、各項目の入力が完了したときにクリックする「次へ」ボタンが設けられている。ここで、仕事達成率とは、その仕事が完了したときを100%として現在の仕事の達成割合を表すものである。続いて、CPU21は、「次へ」ボタンがクリックされたか否かを判定し(ステップS110)、「次へ」ボタンがクリックされていないときにはそのまま待機し、「次へ」ボタンがクリックされたときには、今回指定されたプロジェクトに所属する各人員ごとに、1実績工数あたりの仕事達成率(=仕事達成率÷実績工数)、残余の仕事達成率(=100%−仕事達成率)、実績ベース残目標工数(=残余の仕事達成率÷1実績工数あたりの仕事達成率)、初期ベース残目標工数(=初期目標工数−実績工数)を算出する(ステップS120)。ここで、実績ベース残目標工数とは、これまでの実績と同じペースで今後も仕事を行うと仮定したときの残り工数をいう。   When the work management program is started, the CPU 21 of the work management computer 20 first designates a project to be managed, the actual man-hours for each person belonging to the project, and the work for each person belonging to the project. A screen urging input of the achievement rate is displayed on the display 27 (step S100). This screen is provided with a “Next” button that is clicked when input of each item is completed. Here, the job achievement rate represents the current job achievement rate, assuming that the job is completed as 100%. Subsequently, the CPU 21 determines whether or not the “next” button has been clicked (step S110). If the “next” button has not been clicked, the CPU 21 stands by, and when the “next” button has been clicked. , For each person who belongs to the project specified this time, the work achievement rate per actual man-hour (= work achievement rate ÷ actual man-hours), the remaining work achievement rate (= 100%-work achievement rate), the performance-based remaining A target man-hour (= remaining work achievement rate ÷ work achievement rate per one actual man-hour) and an initial base remaining man-hour (= initial target man-hour-actual man-hour) are calculated (step S120). Here, the performance-based remaining target man-hour refers to the remaining man-hour when it is assumed that work will continue at the same pace as the past results.

続いて、CPU21は、今回指定されたプロジェクトに所属する各人員ごとに初期ベース残目標工数から実績ベース残目標工数を差し引いた差分を算出し(ステップS130)、その差分が負の数か正の数かゼロかを判定し(ステップS140)、差分が負の数のときつまり初期ベース残目標工数が実績ベース残目標工数より小さいときには、その人員は自分に割り振られている仕事を初期目標期限までにこなすことができないとみなし、その仕事のうち差分に応じた仕事量を他の人員に割り振る対象としてRAM23の所定領域に記憶する(ステップS150)。一方、差分が正の数のときつまり初期ベース残目標工数が実績ベース残目標工数より大きいときには、その人員は自分に割り振られている仕事を初期目標期限までに余裕を持ってこなすことができるとみなし、その差分に応じた仕事量を受け入れ可能な人員としてRAM23の所定領域に記憶する(ステップS160)。また、差分がゼロのときつまり初期ベース残目標工数と実績ベース残目標工数とが一致したときには、過不足なく仕事を初期目標期限までにこなすことができるとみなす。その後、オペレータによってほかのプロジェクトについても同様の処理を実行する旨の指示が入力されたか否かを判定し(ステップS170)、ほかのプロジェクトについても同様の処理を実行する旨の指示が入力されたときには再びステップS100へ進む。一方、そのような指示が入力されなかったときには工数調整ルーチンを実行し(ステップS180、図4参照)、その後このプログラムを終了する。   Subsequently, the CPU 21 calculates a difference obtained by subtracting the actual base remaining target man-hour from the initial base remaining target man-hour for each person belonging to the project designated this time (step S130), and the difference is negative or positive. It is determined whether the number is zero or not (step S140), and when the difference is a negative number, that is, when the initial base remaining target man-hour is smaller than the actual base remaining target man-hour, the manpower is assigned to the work until the initial target deadline. The amount of work corresponding to the difference is stored in a predetermined area of the RAM 23 as a target to be allocated to other personnel (step S150). On the other hand, when the difference is a positive number, that is, when the initial base remaining target man-hour is larger than the actual base remaining target man-hour, the person can handle the work allocated to him by the initial target deadline. It is assumed that the work amount corresponding to the difference is stored in a predetermined area of the RAM 23 as an acceptable person (step S160). Further, when the difference is zero, that is, when the initial base remaining target man-hour and the actual base remaining target man-hour coincide with each other, it is considered that the work can be performed by the initial target deadline without excess or deficiency. Thereafter, it is determined whether or not an instruction to execute similar processing is input for another project by the operator (step S170), and an instruction to execute similar processing is input to another project. Sometimes go to step S100 again. On the other hand, when such an instruction is not input, a man-hour adjustment routine is executed (step S180, see FIG. 4), and then this program is terminated.

次に、工数調整ルーチンについて説明する。工数調整ルーチンが開始されると、CPU21は、図4に示すように、まず、工数調整がなされていないプロジェクトの中で重要度の最も高いものを選出する(ステップS300)。ここで、工数調整がなされていないプロジェクトとは、ステップS310の判定処理が行われていないプロジェクトをいう。続いて、今回選出したプロジェクトに関し、RAM23に他の人員に割り振る仕事が記憶されているか否かを判定し(ステップS310)、記憶されているときには今回のプロジェクトに関しRAM23に仕事を受け入れ可能な人員が記憶されているか否かを判定する(ステップS320)。そして、そのような人員が記憶されているときには、先ほどの他の人員に割り振る仕事を、仕事を受け入れ可能な人員に割り振る工数調整を実行する(ステップS330)。その後、今回のプロジェクトにつき他の人員に割り振る仕事がまだ残っているか否かを判定する(ステップS340)。そして、そのような仕事がまだ残っているときには、今回のプロジェクトよりも重要度の低いプロジェクトが存在するか否かを判定し(ステップS350)、そのようなプロジェクトが存在するときには再びステップS320以降の処理を実行し、そのようなプロジェクトが存在しないときにはステップS300で選出されたプロジェクトの初期目標期限を延長する(ステップS360)。つまり、あるプロジェクトに所属する人員に割り振られた仕事のうち初期目標期限までに処理不能な仕事については、同じプロジェクトに所属する人員のうち仕事に余裕のあるものに割り振るか、あるいは、同じプロジェクトに所属する人員のうち仕事に余裕のあるものに割り振っただけではまだ処理不能な仕事が残るときにはそのプロジェクトに比べて重要度の低いプロジェクトに所属する人員のうち仕事に余裕のあるものに割り振ることにより、そのプロジェクトが初期目標期限内に完了するように計画を修正するが、最終的に処理不能な仕事が残ってしまうときには初期目標期限を延長することにより対処する。なお、延長期間は、残っている仕事量に応じて設定する。   Next, the man-hour adjustment routine will be described. When the man-hour adjustment routine is started, as shown in FIG. 4, the CPU 21 first selects the project having the highest importance among the projects for which man-hour adjustment is not performed (step S300). Here, the project in which the man-hour adjustment is not performed refers to a project in which the determination process in step S310 is not performed. Subsequently, with respect to the project selected this time, it is determined whether or not the work to be allocated to other personnel is stored in the RAM 23 (step S310). It is determined whether it is stored (step S320). Then, when such personnel are stored, the man-hour adjustment for allocating the work allocated to the other personnel to the personnel who can accept the job is executed (step S330). Thereafter, it is determined whether or not there is still work to be allocated to other personnel for the current project (step S340). When such a job still remains, it is determined whether or not there is a project having a lower importance than the current project (step S350), and when such a project exists, the steps after step S320 are performed again. The process is executed, and when such a project does not exist, the initial target deadline of the project selected in step S300 is extended (step S360). In other words, work that cannot be processed by the initial target deadline among the work assigned to personnel belonging to a project is assigned to those belonging to the same project that have sufficient work, or assigned to the same project. By assigning to those who have sufficient work, among those who belong to a project that is less important than the project when work that still cannot be processed remains by simply assigning it to those with enough work The plan is corrected so that the project is completed within the initial target deadline, but when the work that cannot be processed eventually remains, the initial target deadline is extended. The extension period is set according to the remaining work amount.

さて、ステップS310で今回のプロジェクトに他の人員に割り振る仕事がないと判定されたときか、ステップS340で工数調整により他の人員に割り振る仕事がなくなったと判定されたときか、ステップS360で初期目標期限を延長したあとには、未処理のプロジェクトつまりステップS310の判定処理を行っていないプロジェクトがあるか否かを判定し(ステップS370)、そのようなプロジェクトがあるときには再びステップS300に戻り、そのようなプロジェクトがないときには工数調整後の全プロジェクトの今後の目標工数や目標期限をディスプレイ27に表示し(ステップS380)、このルーチンを終了する。   Now, when it is determined in step S310 that there is no work assigned to other personnel in the current project, or when it is determined in step S340 that there is no work assigned to other personnel due to man-hour adjustment, or in step S360 the initial target After extending the deadline, it is determined whether or not there is an unprocessed project, that is, a project that has not been subjected to the determination process in step S310 (step S370). If there is such a project, the process returns to step S300 again. If there is no such project, the future target man-hours and target deadlines for all projects after man-hour adjustment are displayed on the display 27 (step S380), and this routine is terminated.

次に、上述の仕事管理プログラムを実行したときの具体例について図5に基づいて説明する。ここでは、予めプロジェクトA,B,Cが図2に示すような重要度、初期目標工数及び初期目標期限でもってハードディスク25の所定領域に記憶されているものとし、プロジェクトAの初期目標期限の半分が経過した時点を管理時期としてオペレータが仕事管理プログラムを実行したものとする。オペレータは、仕事管理プログラムの実行開始を仕事管理コンピュータ20に指示したあと、管理対象となるプロジェクトとしてプロジェクトAを指定し、このプロジェクトAに所属する各人員ごとの実績工数及びそのプロジェクトに所属する各人員ごとの仕事達成率を入力したとする。ここでは、図5(b),(c)に示す実績工数及び仕事達成率を入力したとする。実績工数及び仕事達成率が入力されると、仕事管理コンピュータ20のCPU21は、図5(d)〜(g)に示すように、各人員ごとに1実績工数あたりの仕事達成率、残余の仕事達成率、実績ベース残目標工数、初期ベース残目標工数を算出し、初期ベース残目標工数から実績ベース残目標工数を差し引いた差分を算出し、その後、図5(h)に示すように、その差分をプロジェクトAの両残目標工数の比較結果としてRAM23に記憶する。ここで、負の数の差分は初期目標期限までに処理不能な仕事量を表し、正の数の差分は受入可能な仕事量を表す。続いて、プロジェクトB,Cについても、同様にして差分をRAM23に記憶する。   Next, a specific example when the above-described work management program is executed will be described with reference to FIG. Here, it is assumed that the projects A, B, and C are previously stored in a predetermined area of the hard disk 25 with the importance, the initial target man-hour, and the initial target deadline as shown in FIG. It is assumed that the operator has executed the job management program with the management time as the time when elapses. After instructing the work management computer 20 to start execution of the work management program, the operator designates the project A as a project to be managed, the actual man-hours for each person belonging to the project A, and each of the members belonging to the project. Suppose that the work achievement rate for each person is entered. Here, it is assumed that the actual man-hours and work achievement rates shown in FIGS. 5B and 5C are input. When the actual man-hours and the job achievement rate are input, the CPU 21 of the job management computer 20 performs the job achievement rate per one-hour man-hour and the remaining jobs for each person, as shown in FIGS. The achievement rate, actual base remaining man-hours, and initial base remaining target man-hours are calculated, and the difference obtained by subtracting the actual base remaining target man-hours from the initial base remaining target man-hours is calculated. Then, as shown in FIG. The difference is stored in the RAM 23 as a comparison result of both remaining target man-hours of the project A. Here, a negative difference represents a work amount that cannot be processed by the initial target deadline, and a positive difference represents an acceptable work amount. Subsequently, the difference between the projects B and C is stored in the RAM 23 in the same manner.

図6は、プロジェクトA〜Cの両残目標工数の比較結果をまとめて表した説明図である。図6の説明図に示すように、プロジェクトAについては、等級「主任」が「やや難」の仕事を工数「10d」だけ処理不能であり、等級「係長」が「難」の仕事を工数「6d」だけ受入可能となっている。このため、等級「主任」の仕事の処理不能分のうち工数「6d」を等級「係長」に割り振ることができるが、残りの工数「4d」はプロジェクトAの所属員に割り振ることができない。そこで、重要度の低いプロジェクトBについてみると、等級「一般」が「単純」な仕事を工数「1d」だけ処理不能であり、等級「主任」が「やや難」の仕事を工数「5d」だけ受入可能となっている。このため、先ほどのプロジェクトAの等級「主任」の仕事のうち残りの工数「4d」をプロジェクトBの等級「主任」の仕事に割り振る。この結果、プロジェクトAは仕事の過不足がなくなり、目標期限内に完了する目処が立つ。次に、プロジェクトBについてみると、等級「一般」が「単純」な仕事を工数「1d」だけ処理不能であり、等級「主任」が「やや難」の仕事を「1d」だけ受入可能である(もともと等級「主任」は工数「5d」だけ受入可能だったが、そのうち「4d」はプロジェクトAの仕事が振り分けられたため「1d」だけ受入可能になっている)。このため、等級「一般」の仕事の処理不能分である工数「1d」を等級「主任」の仕事に割り振る。この結果、プロジェクトBは仕事の過不足がなくなり、目標期限内に完了する目処が立つ。次に、プロジェクトCについてみると、等級「一般」が「単純」な仕事を工数「1d」だけ受入可能であり、等級「主任」が「やや難」の仕事を工数「1d」だけ受入可能である。このため、プロジェクトCには他の人員に割り振るべき仕事はなく、このままで目標期限内に完了する目処が立っていることになる。このようにして工数調整を行った後の目標工数を図7に示す。図7は、プロジェクトA〜Cの今回の管理時期以降の目標工数をまとめて表した説明図である。なお、プロジェクトCについて、例えば等級「一般」が「単純」な仕事を工数「1d」だけ処理不能で、等級「主任」が「やや難」の仕事を工数「1d」だけ処理不能だったとすると、これらの工数は割り振る先がないため、初期目標期限を延長することにより対処することになる。   FIG. 6 is an explanatory diagram collectively showing the comparison results of the remaining target man-hours of the projects A to C. As shown in the explanatory diagram of FIG. 6, for the project A, the work with the grade “chief” of “somewhat difficult” cannot be processed by the man-hour “10d”, and the work with the grade “person in charge” of “difficult” is the man-hour “ Only 6d "can be accepted. For this reason, the man-hour “6d” can be allocated to the class “person in charge” among the unprocessable portions of the work of the class “chief”, but the remaining man-hour “4d” cannot be allocated to the members of the project A. Therefore, in the case of Project B, which has a low importance level, it is impossible to process “simple” jobs with “general” grade by “1d”, and only “5d” jobs with “slightly difficult” grade “boss”. Acceptable. For this reason, the remaining man-hour “4d” is assigned to the job of the grade “Chief” of Project B among the jobs of the grade “Chief” of Project A. As a result, Project A is free from excess or shortage of work, and it is likely that it will be completed within the target deadline. Next, with regard to Project B, the grade “general” cannot process “simple” work by the man-hour “1d”, and the grade “boss” can accept “slightly difficult” work by “1d”. (Originally, the grade “Chief” was able to accept only the man-hour “5d”, but “4d” was accepted only for “1d” because the work of Project A was assigned). For this reason, the man-hour “1d”, which is the unprocessable part of the job of the class “general”, is allocated to the job of the class “chief”. As a result, Project B is free from overs and shorts of work, and is expected to be completed within the target deadline. Next, with regard to Project C, the grade “General” can accept “simple” work for the man-hour “1d”, and the grade “chief” can accept the work “slightly difficult” for the man-hour “1d”. is there. For this reason, there is no work to be allocated to other personnel in Project C, and there is a prospect of completion within the target deadline as it is. FIG. 7 shows the target man-hour after the man-hour adjustment is performed in this way. FIG. 7 is an explanatory diagram that summarizes the target man-hours for the projects A to C after the current management period. For project C, for example, if the grade “general” cannot process a “simple” job by the man-hour “1d”, and the job of the grade “chief” “somewhat difficult” cannot be processed by the man-hour “1d”, Since these man-hours have no place to allocate, they will be dealt with by extending the initial target deadline.

ここで、本実施形態の構成要素と本発明の構成要素との対応関係を明らかにする。本実施形態のハードディスク25が本発明の初期目標工数記憶手段、実績工数記憶手段、仕事達成率記憶手段、プロジェクト重要度記憶手段に相当し、CPU21が実績ベース残目標工数算出手段、工数調整手段及び期限調整手段に相当する。また、プロジェクト重要度の順序に応じて仕事重要度も決まるため、プロジェクト重要度を記憶しているハードディスク25は仕事重要度記憶手段にも相当するといえる。なお、本実施形態は、本発明の仕事管理システムの一例を説明すると同時に、本発明の仕事管理方法やその仕事管理方法をコンピュータに実行させるプログラムの一例も説明している。   Here, the correspondence between the components of the present embodiment and the components of the present invention will be clarified. The hard disk 25 of the present embodiment corresponds to the initial target man-hour storage means, the actual man-hour storage means, the work achievement rate storage means, and the project importance degree storage means of the present invention, and the CPU 21 has a result-based remaining target man-hour calculation means, man-hour adjustment means, and It corresponds to a deadline adjusting means. In addition, since the job importance is determined according to the order of the project importance, it can be said that the hard disk 25 storing the project importance corresponds to a work importance storage means. In addition, this embodiment describes an example of the work management system of the present invention, and also describes an example of the work management method of the present invention and an example of a program that causes a computer to execute the work management method.

以上詳述した本実施形態によれば、実際の進捗状況に応じて各プロジェクトに所属する各人員に仕事を適切に振り分け直すことができ、その結果、当初各人員に割り振った仕事が初期目標期限どおりに完了するケースが多くなる。また、初期ベース残目標工数と実績ベース残目標工数との大小関係に基づいて、ある人員に割り振られた仕事が初期目標期限までに完了しないのでその一部を他の人員に割り振るべきなのか、それともその人員に割り振られた仕事が初期目標期限までに余裕を持って完了しそうなので他の仕事をその人員が受け入れることができるかを、適切に判定することができる。更に、実績工数のみならず仕事達成率を考慮して任意の管理時期から初期目標期限までに必要な工数(実績ベース残目標工数)を算出するため、実績ベース残目標工数の妥当性が高くなる。更にまた、重要度の高いプロジェクト(そのプロジェクトの仕事)ほど初期目標期限に遅れることなく完了することができる。そして、どうしても初期目標期限どおりに完了するように調整できなかったプロジェクト(そのプロジェクトの仕事)については期限を延長することにより対処できる。   According to the present embodiment described in detail above, it is possible to appropriately reallocate the work to each member belonging to each project according to the actual progress, and as a result, the work initially assigned to each person is the initial target deadline. More cases will be completed. Also, based on the size relationship between the initial base remaining man-hours and the actual base remaining man-hours, the work allocated to one person will not be completed by the initial target deadline, so a part of it should be allocated to other persons. Or, since the work assigned to the person is likely to be completed by the initial target deadline, it is possible to appropriately determine whether the person can accept another work. Furthermore, since the number of man-hours (result-based remaining target man-hours) required from the arbitrary management period to the initial target deadline is calculated in consideration of the work achievement rate as well as the actual man-hours, the validity of the remaining performance-based target man-hours becomes high. . Furthermore, a project with higher importance (the work of the project) can be completed without delaying the initial target deadline. And it is possible to deal with the project (work of the project) that could not be adjusted to complete according to the initial target deadline by extending the deadline.

なお、本発明は上述した実施形態に何ら限定されることはなく、本発明の技術的範囲に属する限り種々の態様で実施し得ることはいうまでもない。   It should be noted that the present invention is not limited to the above-described embodiment, and it goes without saying that the present invention can be implemented in various modes as long as it belongs to the technical scope of the present invention.

例えば、上述した実施形態では、工数調整を実行したあと他の人員に割り振ることのできなかった仕事が残ったときには初期目標期限を延長することにより対処したが、新たな人員を追加してその人員に残った仕事を割り振るようにして初期目標期限内にプロジェクトが完了するようにしてもよい。   For example, in the above-described embodiment, when work that could not be allocated to other personnel remained after man-hour adjustment was performed, the initial target deadline was extended, but a new personnel was added to the personnel. The remaining work may be allocated so that the project is completed within the initial target deadline.

また、上述した実施形態のステップS330の工数調整において、等級「係長」の人員には「難」「やや難」「単純」のどの仕事も割り振ることができ、等級「主任」の人員には「やや難」「単純」のいずれかの仕事を割り振ることができ、等級「一般」の人員には「単純」な仕事のみ割り振ることができるものとして、工数調整を行うようにしてもよい。こうすれば、他の人員に割り振るべき仕事があったとき、その仕事の難易度に応じてどの等級の人員に割り振ればよいかが決まるため、例えば等級が低くて難しい仕事をこなせない人員に対して、「難」の仕事が割り振られてしまうことがない。   Further, in the man-hour adjustment in step S330 of the above-described embodiment, any job of “difficult”, “slightly difficult”, and “simple” can be assigned to personnel of the class “person in charge”, and personnel of the class “chief” can be assigned “ The man-hour adjustment may be performed on the assumption that either “slightly difficult” or “simple” work can be assigned, and only “simple” work can be assigned to personnel of the class “general”. In this way, when there is work to be assigned to other personnel, it is determined which grade of personnel should be assigned according to the difficulty level of the job, so for example, for personnel who are difficult to do difficult work due to low grade Therefore, the “difficult” work is never assigned.

更に、上述した実施形態では、1台のコンピュータで本発明の仕事管理システムを構成したが、例えばハードディスク25に記憶した内容をデータベースサーバに記憶しておき、クライアントコンピュータが仕事管理プログラムを実行する際にデータベースサーバの記憶内容を受信しながら処理を実行するようにしてもよい。   Further, in the above-described embodiment, the work management system of the present invention is configured by one computer. However, when the contents stored in the hard disk 25 are stored in the database server, for example, and the client computer executes the work management program. Alternatively, the processing may be executed while receiving the stored contents of the database server.

更にまた、上述した実施形態では、あるプロジェクトに所属する人員に割り振られた仕事が初期目標期限までに処理不能と判定されたとき、その仕事をそのプロジェクトよりも重要度の低いプロジェクトに所属する人員に割り振るようにしたが、ここで重要度の低いプロジェクトを選択するに際し、例えば今回のプロジェクトに比べて重要度が1ランク低いプロジェクト、2ランク低いプロジェクト、……というように重要度の高い順に選択してもよいし、重要度が最も低いプロジェクト、重要度が2番目に低いプロジェクト、……というように重要度の低い順に選択してもよい。   Furthermore, in the above-described embodiment, when it is determined that a job assigned to a person belonging to a certain project cannot be processed by the initial target deadline, the person belonging to a project having a lower importance than that project. However, when selecting a project with low importance here, for example, a project with a lower rank than the current project, a project with a lower rank, and so on. Alternatively, the project with the lowest importance level, the project with the second lowest importance level,... May be selected in ascending order of importance.

そしてまた、上述した実施形態では、重要度の高いプロジェクトから順に処理不能な仕事が初期目標期限内に完了するように工程調整を行ったが、まず各プロジェクト内で工数調整を行い、依然として処理不能な仕事が残ったときにプロジェクト間で工数調整を行うようにしてもよい。   In the above-described embodiment, the process adjustment is performed so that work that cannot be processed in order from the project with the highest importance is completed within the initial target deadline. You may be able to adjust the man-hours between projects when a lot of work remains.

そして更にまた、上述した実施形態では、各プロジェクトの仕事の割り振りについて説明したが、プロジェクトが組まれていない仕事についても同様にして割り振ることができる。   Furthermore, in the above-described embodiment, the assignment of work for each project has been described. However, work for which no project is assembled can also be assigned in the same manner.

仕事管理コンピュータ20の概略構成図。1 is a schematic configuration diagram of a work management computer 20. FIG. ハードディスク25に格納されているデータの説明図。FIG. 3 is an explanatory diagram of data stored in a hard disk 25. 仕事管理プログラムのフローチャート。The flowchart of a work management program. 工数調整ルーチンのフローチャート。The flowchart of a man-hour adjustment routine. プロジェクトAに関する具体例の説明図。Explanatory drawing of the specific example regarding the project A. FIG. プロジェクトA〜Cの各人員の仕事の過不足を表す説明図。Explanatory drawing showing the excess and deficiency of the work of each staff of Project AC. プロジェクトA〜Cの今回の管理時期以降の目標工数を表した説明図。Explanatory drawing showing the target man-hour after this management time of project AC.

符号の説明Explanation of symbols

20 仕事管理コンピュータ、21 CPU、22 ROM、23 RAM、24 ハードディスクコントローラ、25 ハードディスク、26 ビデオコントローラ、27 ディスプレイ、28 USBコントローラ、29 入力装置、30 バス。 20 work management computer, 21 CPU, 22 ROM, 23 RAM, 24 hard disk controller, 25 hard disk, 26 video controller, 27 display, 28 USB controller, 29 input device, 30 bus.

Claims (12)

各人員に仕事を割り振り該仕事が完了するまでの初期目標工数及び初期目標期限を各人員ごとに設定したあと各人員の仕事の管理を行う仕事管理システムであって、
各人員ごとに初期目標工数を記憶する初期目標工数記憶手段と、
任意の管理時期にオペレータによって入力される各人員の実績工数を記憶する実績工数記憶手段と、
任意の管理時期にオペレータによって入力される各人員の仕事達成率を記憶する仕事達成率記憶手段と、
各人員ごとに前記実績工数と前記仕事達成率とに基づいて前記管理時期から前記初期目標期限までに処理すべき実績ベース残目標工数を算出する実績ベース残目標工数算出手段と、
各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分を他の人員に割り振り、余裕を持って処理可能と判定されたときには該人員に他の人員の処理不能な分を割り振る工数調整手段と、
を備えた仕事管理システム。
A work management system for managing the work of each person after assigning work to each person and setting the initial target man-hour and initial target deadline until the work is completed for each person,
Initial target man-hour storage means for storing an initial target man-hour for each person;
Actual man-hour storage means for storing the actual man-hours of each person input by the operator at an arbitrary management time;
Work achievement rate storage means for storing the work achievement rate of each person input by the operator at an arbitrary management time;
A performance-based remaining target man-hour calculating means for calculating a performance-based remaining target man-hour to be processed from the management time to the initial target deadline based on the actual man-hour and the work achievement rate for each person;
It is determined based on the initial target man-hours for each person whether or not the performance-based remaining target man-hours can be processed from the management time to the initial target deadline for each person. The man-hour adjusting means for allocating the unprocessable portion of the remaining performance-based man-hours to other personnel, and allocating the unmanageable portions of other personnel to the personnel when it is determined that the manpower can be processed with a margin,
Work management system with
前記工数調整手段は、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定するにあたり、各人員ごとに前記初期目標工数から前記実績工数を差し引いて算出した初期ベース残目標工数と前記実績ベース残目標工数とを比較し、前者が後者より小さいときには処理不能と判定し、前者が後者より大きいときには余裕を持ってその仕事を処理可能と判定する、請求項1に記載の仕事管理システム。   The man-hour adjusting means determines whether or not the performance-based remaining target man-hours can be processed from the management time to the initial target deadline for each person based on the initial target man-hours for each person. The initial base remaining target man-hour calculated by subtracting the actual man-hour from the initial target man-hour for each person is compared with the actual base remaining target man-hour, and when the former is smaller than the latter, it is determined that processing is impossible, and the former is larger than the latter The work management system according to claim 1, wherein it is determined that the work can be processed sometimes with a margin. 前記実績ベース残目標工数算出手段は、各人員ごとに前記実績工数と前記仕事達成率とから1実績工数当たりの仕事達成率を仕事達成率として算出し、残余の仕事達成率を前記1実績工数当たりの仕事達成率で除して実績ベース残目標工数を算出する、請求項1又は2に記載の仕事管理システム。   The performance-based remaining target man-hour calculating means calculates a work achievement rate per actual man-hour as a work achievement rate from the actual man-hour and the work achievement rate for each person, and the remaining work achievement rate is calculated as the one actual man-hour. The work management system according to claim 1 or 2, wherein a remaining performance-based target man-hour is calculated by dividing by a per-work achievement rate. 請求項1〜3のいずれかに記載の仕事管理システムであって、
各仕事ごとに重要度を記憶する仕事重要度記憶手段、を備え、
前記工数調整手段は、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分の少なくとも一部を該仕事よりも重要度の低い仕事を余裕を持って処理可能な人員に割り振る、仕事管理システム。
The work management system according to any one of claims 1 to 3,
A job importance storage means for storing the importance for each job;
The man-hour adjusting means determines whether or not the performance-based remaining target man-hours can be processed from the management time to the initial target deadline for each person based on the initial target man-hours for each person and cannot be processed A work management system that allocates at least a portion of the performance-based remaining target man-hours that cannot be processed to a person who can process a job that is less important than the job with a margin.
前記重要度は、仕事の重要性、仕事の優先性及び仕事の緊急性の少なくとも一つに基づいて決定する、請求項4に記載の仕事管理システム。   The work management system according to claim 4, wherein the importance is determined based on at least one of work importance, work priority, and work urgency. 請求項1〜5のいずれかに記載の仕事管理システムであって、
前記工数調整手段によって割り振ることのできなかった仕事につき前記初期目標期限を延長する期限調整手段、を備えた仕事管理システム。
The work management system according to claim 1,
A work management system comprising deadline adjusting means for extending the initial target deadline for work that could not be allocated by the man-hour adjusting means.
請求項1〜6のいずれかに記載の仕事管理システムであって、
前記工数調整手段によって割り振ることのできなかった仕事につき新たな人員を追加して該人員に該仕事を割り振る人員増強調整手段、を備えた仕事管理システム。
The work management system according to any one of claims 1 to 6,
A work management system comprising: personnel increase adjustment means for adding a new person to a work that could not be assigned by the man-hour adjustment means and assigning the work to the person.
前記工数は、作業時間数である、請求項1〜7のいずれかに記載の仕事管理システム。   The work management system according to claim 1, wherein the man-hour is the number of work hours. 請求項1〜8のいずれかに記載の仕事管理システムであって、
所定のプロジェクト期間の開始前に該プロジェクトの全仕事を該プロジェクトに所属する各人員に割り振り前記プロジェクトが完了するまでの初期目標工数及び初期目標期限を各人員ごとに設定したあと各人員の仕事の管理を行う、仕事管理システム。
The work management system according to claim 1,
Prior to the start of a given project period, all the work of the project is allocated to each person belonging to the project, the initial target man-hours and the initial target deadline for completion of the project are set for each person, and Work management system that performs management.
請求項9に記載の仕事管理システムであって、
各プロジェクトごとに重要度を記憶するプロジェクト重要度記憶手段、を備え、
前記工数調整手段は、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分の少なくとも一部を該プロジェクトよりも重要度の低いプロジェクトの仕事を余裕を持って処理可能な人員に割り振る、仕事管理システム。
The work management system according to claim 9,
Project importance storage means for storing importance for each project,
The man-hour adjusting means determines whether or not the performance-based remaining target man-hours can be processed from the management time to the initial target deadline for each person based on the initial target man-hours for each person and cannot be processed A work management system for allocating at least a part of the performance-based remaining target man-hours that cannot be processed to a person who can process the work of a project having a lower importance than the project with a margin when it is determined.
各人員に仕事を割り振り該仕事が完了するまでの初期目標工数及び初期目標期限を各人員ごとに設定したあと、各人員ごとの初期目標工数を記憶する初期目標工数記憶手段、任意の管理時期にオペレータによって入力される各人員の実績工数を記憶する実績工数記憶手段及び任意の管理時期にオペレータによって入力される各人員の仕事達成率を記憶する仕事達成率記憶手段を利用して各人員の仕事の管理を行う、コンピュータ・ソフトウェアによる仕事管理方法であって、
(a)コンピュータが、各人員ごとに前記実績工数と前記仕事達成率とに基づいて前記管理時期から前記初期目標期限までに処理すべき実績ベース残目標工数を算出するステップと、
(b)コンピュータが、各人員ごとに前記実績ベース残目標工数を前記管理時期から前記初期目標期限までに処理可能か否かを各人員ごとの前記初期目標工数をもとに判定し、処理不能と判定されたときには前記実績ベース残目標工数のうち処理不能な分を他の人員に割り振り、余裕を持って処理可能と判定されたときには該人員に他の人員の処理不能な分を割り振るステップと、
を含む仕事管理方法。
An initial target man-hour storage means for storing an initial target man-hour for each person, after assigning a work to each person and setting an initial target man-hour and initial target deadline for the completion of the work for each person, at an arbitrary management time Each person's work using the actual man-hour storage means for storing the actual man-hours input by the operator and the work achievement ratio storage means for storing the work achievement ratio of each person input by the operator at an arbitrary management time A work management method using computer software,
(A) a computer calculating a result-based remaining target man-hour to be processed from the management time to the initial target time limit based on the actual man-hour and the work achievement rate for each person;
(B) The computer determines whether or not the performance-based remaining target man-hours can be processed for each person from the management time to the initial target deadline based on the initial target man-hours for each person and cannot be processed. Allocating the unprocessable portion of the performance-based remaining target man-hour to other personnel when it is determined, and allocating the unmanageable portion of the other personnel to the personnel when it is determined that it can be processed with a margin; ,
Including work management methods.
請求項11に記載された仕事管理方法の各ステップを1又は複数のコンピュータに実行させるためのプログラム。   A program for causing one or more computers to execute each step of the work management method according to claim 11.
JP2003329880A 2003-09-22 2003-09-22 Work management system and its method and its program Pending JP2005099906A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003329880A JP2005099906A (en) 2003-09-22 2003-09-22 Work management system and its method and its program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003329880A JP2005099906A (en) 2003-09-22 2003-09-22 Work management system and its method and its program

Publications (1)

Publication Number Publication Date
JP2005099906A true JP2005099906A (en) 2005-04-14

Family

ID=34459009

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003329880A Pending JP2005099906A (en) 2003-09-22 2003-09-22 Work management system and its method and its program

Country Status (1)

Country Link
JP (1) JP2005099906A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013189293A (en) * 2012-03-14 2013-09-26 Sumitomonacco Materials Handling Co Ltd Vehicle performance limiting device for industrial vehicle
JP2016042245A (en) * 2014-08-14 2016-03-31 インターナショナル・ビジネス・マシーンズ・コーポレーションInternational Business Machines Corporation System, method, and program for managing projects
WO2017130446A1 (en) * 2016-01-29 2017-08-03 日揮株式会社 Project management device, project management system, project management method and program
JP7486196B2 (en) 2021-07-16 2024-05-17 パナソニックIpマネジメント株式会社 Target management system, target management method and program

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013189293A (en) * 2012-03-14 2013-09-26 Sumitomonacco Materials Handling Co Ltd Vehicle performance limiting device for industrial vehicle
JP2016042245A (en) * 2014-08-14 2016-03-31 インターナショナル・ビジネス・マシーンズ・コーポレーションInternational Business Machines Corporation System, method, and program for managing projects
WO2017130446A1 (en) * 2016-01-29 2017-08-03 日揮株式会社 Project management device, project management system, project management method and program
JP7486196B2 (en) 2021-07-16 2024-05-17 パナソニックIpマネジメント株式会社 Target management system, target management method and program

Similar Documents

Publication Publication Date Title
US7774742B2 (en) Facilitation of multi-project management using task hierarchy
US9015723B2 (en) Resource optimization for real-time task assignment in multi-process environments
US7502747B1 (en) Automated job scheduling based on resource availability
US7921405B2 (en) Facilitation of multi-project management using throughput measurement
US7669179B2 (en) Facilitation of multi-project management using critical chain methodology
US9477460B2 (en) Non-transitory computer-readable storage medium for selective application of update programs dependent upon a load of a virtual machine and related apparatus and method
US20040098291A1 (en) Apparatus and method for visualizing resource consumption
US20120130907A1 (en) Project management system and method
US8214327B2 (en) Optimization and staging method and system
CN110806933B (en) Batch task processing method, device, equipment and storage medium
KR20060048381A (en) Hierarchical projects in a computer-enabled project management method and system
US10146587B2 (en) Future locking of resources
WO2012102782A1 (en) Method and system for allocation of resources in a project portfolio
US8458004B2 (en) Dynamically pooling unused capacities across an organization to execute atomic tasks
US20110302004A1 (en) Customizing workflow based on participant history and participant profile
US8656395B2 (en) Method and system for optimizing a job scheduler in an operating system
US8806505B1 (en) Service and project request processing within a business enterprise
US20190130328A1 (en) Methods and systems for simulating and optimizing a work environment using an agent based model for scheduling and staffing of resources
JP6102477B2 (en) Schedule management program, schedule management method, and schedule management apparatus
JP2005099906A (en) Work management system and its method and its program
JP2006018529A (en) Workflow system, method for controlling it, program, and recording medium
CN108521524B (en) Agent collaborative task management method and device, computer equipment and storage medium
US20210365872A1 (en) A system and method for management of project portfolios
JP6131725B2 (en) Information processing apparatus and information processing program
JP2006146530A (en) Scheduling support system