JP2005061021A - Ground reinforcing method - Google Patents
Ground reinforcing method Download PDFInfo
- Publication number
- JP2005061021A JP2005061021A JP2003291591A JP2003291591A JP2005061021A JP 2005061021 A JP2005061021 A JP 2005061021A JP 2003291591 A JP2003291591 A JP 2003291591A JP 2003291591 A JP2003291591 A JP 2003291591A JP 2005061021 A JP2005061021 A JP 2005061021A
- Authority
- JP
- Japan
- Prior art keywords
- ground
- layer
- anchor member
- embankment
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
本発明は自然地山を改良あるいは補強する工法に関し、特に、アンカー部材を打ち込むとともに緊張する構成とした地盤補強工法に関するものである。 The present invention relates to a method for improving or reinforcing natural ground, and more particularly, to a ground reinforcing method in which an anchor member is driven and tensioned.
従来、地盤を改良したり補強する際には、不良土を除去して良質な土と入れ替える置換工法や、固化材を用いて地盤改良を行う強制地盤攪拌改良工法や、薬剤を注入することで地盤改良を行う地盤注入工法や、地盤の上に盛土を形成し予め地盤に加わる全圧力を増加させて基礎地盤の圧密沈下を促進させると共に強度増加を図るプレローディング工法等が採用されている。 Conventionally, when improving or reinforcing the ground, a replacement method that removes defective soil and replaces it with good quality soil, a forced ground agitation improvement method that improves the ground using a solidifying material, or a chemical injection A ground injection method for ground improvement, a preloading method for forming a fill on the ground and increasing the total pressure applied to the ground in advance to promote consolidation settlement of the foundation ground and to increase the strength are adopted.
前記置換工法では、不良土を除去して処分する作業が必要であり、前記強制地盤攪拌改良工法ではセメント系固化材等の重金属類を地盤に混入することになり土壌汚染等の不安がある。また、前記地盤注入工法では注入する薬液による公害等の不安がある。さらに、前記プレローディング工法では、地盤上に盛土で載苛した後で一定期間放置しておき、その後盛土を撤去し除荷することが必要であり、盛土材の搬出、撤去手間がかかっており、また、施工期間が長くなっている。 In the replacement method, it is necessary to remove and dispose of defective soil. In the forced ground agitation improvement method, heavy metals such as cement-based solidification material are mixed into the ground, and there is a concern about soil contamination. Moreover, in the ground injection method, there is anxiety such as pollution due to the chemicals to be injected. Furthermore, in the preloading method, it is necessary to leave the soil for a certain period after being filled with the embankment on the ground, and then remove and unload the embankment, which takes time and labor to remove and remove the embankment material. Also, the construction period is longer.
そのために多層の盛土層を転圧しながら積層して、アンカーにより盛土層全体を圧縮することで、橋台や橋脚などの上部構造物を支持するための基礎構築体を形成する工法が公開されている。(例えば、特許文献1参照)
上記の特許文献1に記載の基礎構築体は、鋼板等からなる高剛性の基礎支持体上に、一定厚さの盛土層を複数積み重ねて、各盛土層間に、摩擦係数及び引張強度が大きいフラット若しくは略フラットな補強材を介装した基礎構築体であり、さらには、多層の盛土層と補強材とを貫通する複数本のアンカーを装着して、締め上げて、各盛土層と補強材とを一体化した構成である。
For this purpose, a method of forming a foundation structure to support upper structures such as abutments and piers by laminating multiple embankment layers while rolling and compressing the entire embankment layer with anchors has been released. . (For example, see Patent Document 1)
The foundation construction described in
さらには、盛土層を締付けて構成される基礎構築体に、アンカー頂部に緩み止め機構を装着して、常に一定のプレストレスを継続的に維持するように構成した補強土構造物も既に公開されている。(例えば、特許文献2参照)
また、アンカーなどの補強棒材に一定の緊張力を付与し、緩みを阻止するために、皿ばねを多数積層した構成の締着装置も公開されている。(例えば、特許文献3参照)
In addition, a fastening device having a configuration in which a number of disc springs are stacked in order to impart a certain tension to a reinforcing bar such as an anchor and prevent loosening has been disclosed. (For example, see Patent Document 3)
しかしながらコンクリートやセメント系固化材を用いた地盤改良工法では、軟弱な地盤を掘り返して、固化材を添加して締め固める作業が必要であり、また硬化する期間工期が長くなり、大型の施工重機が必要であると共に、工事が長期化し大変である。 However, in the ground improvement method using concrete or cement-based solidification material, it is necessary to dug up the soft ground, add the solidification material and compact it, and the period of time for hardening becomes long, and large construction heavy machinery It is necessary, and the construction is long and difficult.
一方、特許文献1に記載の補強土を使用した基礎構築体は、高剛性の基礎支持体と、天板となる高剛性の床版との間に積層した盛土層を、上下から締付けてプレストレスを加える構成であって、各盛土層間に敷設した補強材自身に引張プレストレスが導入される。その結果前記プレストレスにより、積層された盛土層全体が高い剛性と強度を保持し一体化された基礎構築体を構成している。
On the other hand, the foundation construction body using the reinforced soil described in
しかし、高剛性の基礎支持体上に、盛土層を積層していく構成であって、堅固な岩盤を基礎支持体とする場合には、前記岩盤が露出するまで掘削する必要があり、さらに、傾斜面に盛土層を構築する図10に示す場合では、鉛直方向のアンカー部材6に加えて、傾斜面に略直交する斜め方向のアンカー部材6Cを設ける必要がある。
However, it is a configuration in which the embankment layer is stacked on a highly rigid foundation support, and when a solid rock is used as the foundation support, it is necessary to excavate until the rock is exposed, In the case shown in FIG. 10 in which the embankment layer is constructed on the inclined surface, in addition to the
また、特許文献2に記載の補強土構造物は、常に一定の緊張力(プレストレス)を付与するために、複雑な緩み止め機構を必要としている。
Further, the reinforced earth structure described in
本発明の目的は、プレローディング工法と補強土工法とのそれぞれの特徴を併せ持つと共に、さらに工事の規模が小さくまた短い工期で容易に地盤を補強することができる地盤補強工法を提供することである。 An object of the present invention is to provide a ground reinforcement construction method that has both the characteristics of a preloading construction method and a reinforced earth construction method and that can further reinforce the ground with a small construction scale and a short construction period. .
上記の目的を達成するために請求項1に係る発明は、表層部分を水平にならし掘削して、その上に高剛性の上盤を配設して、前記上盤と該上盤下部の堆積層とを貫通して支持地盤に達するアンカー部材を設け、前記アンカー部材上端部に形成されたネジ部に第一のナット部材を螺合させ、前記アンカー部材を締め上げて緊張することで堆積層に圧縮力を作用させて堆積層の強度増加を図り地盤を補強する構成としたことを特徴としている。 In order to achieve the above object, according to the first aspect of the present invention, the surface layer portion is leveled and excavated, and a highly rigid upper board is disposed thereon, and the upper board and the lower part of the upper board are arranged. An anchor member that penetrates the deposited layer and reaches the support ground is provided, and a first nut member is screwed into a screw portion formed at the upper end portion of the anchor member, and the anchor member is tightened and tightened to deposit. It is characterized in that the ground is reinforced by increasing the strength of the sedimentary layer by applying a compressive force to the layer.
上記の構成を有する請求項1に係る発明によれば、水平にならし掘削した表層部に上盤を設置してアンカー部材を打ち込み締め上げるだけで、上盤下部の堆積層を補強土擬似躯体とすることができ、地盤を補強することができる。
According to the invention according to
請求項2に係る発明は、表層部分を水平にならし掘削して、その上に多層の盛土層と、各盛土層間に介装され、摩擦係数及び引張強度が大きいフラット若しくは略フラットな網状又は格子状の補強材と、最上の盛土層上に高剛性の上盤を配設して補強土躯体を造成後に、該上盤と前記補強材と前記盛土層と、該盛土層下部の堆積層を貫通して支持地盤に達するアンカー部材を設け、前記アンカー部材上端部に形成されたネジ部に第一のナット部材を螺合させ、前記アンカー部材を締め上げて緊張することで、前記盛土層だけでなく、前記堆積層にも圧縮力を作用させて補強土擬似躯体を形成し、前記補強土躯体よりも拡大した荷重導入補強土基礎を構成して地盤を補強する構成としたことを特徴としている。
In the invention according to
上記の構成を有する請求項2に係る発明によれば、水平にならし掘削した表層部に多層の盛土層を形成して、上盤を載置すると共にアンカー部材を堆積層を貫通して支持地盤にまで打ち込むことで、荷重導入補強土基礎を構築する際に、打ち込んだ堆積層までをも一体の補強土基礎とすることで見かけ上大型の基礎地盤を構築することができる。
According to the invention according to
請求項3に係る発明は、表層部分から支持地盤に至るまで掘削して、該支持地盤を段切りして平面部を造成すると共に、該平面部に埋め戻し土或いは良質土を転圧しながら積層して、その上に多層の盛土層と、各盛土層間に介装され、摩擦係数及び引張強度が大きいフラット若しくは略フラットな網状又は格子状の補強材と、最上の盛土層上に高剛性の上盤を配設して補強土躯体を造成後に、該上盤と前記補強材と前記盛土層と、該盛土層下部の転圧積層部を貫通して支持地盤に達するアンカー部材を設け、前記アンカー部材上端部に形成されたネジ部に第一のナット部材を螺合させ、前記アンカー部材を締め上げて緊張することで、前記盛土層だけでなく、前記転圧積層部にも圧縮力を作用させて補強土擬似躯体を形成し、前記補強土躯体よりも拡大した荷重導入補強土基礎を構成して地盤を補強する構成としたことを特徴としている。 The invention according to claim 3 excavates from the surface layer portion to the supporting ground, cuts the supporting ground to create a flat portion, and laminates the flat portion while rolling back-filled soil or high-quality soil. And a multi-layered embankment layer, a flat or substantially flat mesh-like or lattice-like reinforcing material having a large friction coefficient and tensile strength, and a high rigidity on the top embankment layer. After the upper board is disposed and the reinforced earth body is formed, an anchor member that penetrates through the rolling laminate of the upper board, the reinforcing material, the embankment layer, and the lower part of the embankment layer to reach the support ground is provided, The first nut member is screwed into the threaded portion formed at the upper end portion of the anchor member, and the anchor member is tightened and tensioned, so that not only the embankment layer but also the rolling lamination portion is compressed. A reinforced soil pseudo-body is formed by acting, It constitutes a remote enlarged load introduced reinforced soil foundation was being characterized in that it is configured to reinforce the ground.
上記の構成を有する請求項3に係る発明によれば、支持地盤の傾斜した自然地山等においても有効な荷重導入補強土基礎とすることができる。
According to the invention according to
請求項4に係る発明は、前記アンカー部材上端部に形成されたネジ部に第一のナット部材を螺合させ、前記アンカー部材を締め上げて緊張する際に、中空円筒状の内金具とケーシング金具との間にゴム状弾性体層が挟設された構造のせん断ゴムばね材を加圧手段とする締着部材を介して緊張する構成としたことを特徴としている。 According to a fourth aspect of the present invention, when the first nut member is screwed into the threaded portion formed at the upper end portion of the anchor member, and the anchor member is tightened and tensioned, the hollow cylindrical inner metal fitting and the casing It is characterized in that it is configured to be tensioned via a fastening member using a shear rubber spring material having a structure in which a rubber-like elastic body layer is sandwiched between the metal fittings as a pressurizing means.
上記の構成を有する請求項4に係る発明によれば、単一部品のせん断ゴムばね材を介してアンカー部材を緊張するだけで、盛土や基礎地盤の沈下やアンカー部材の伸長に追随して一定の緊張力を付与することができる。
According to the invention which concerns on
請求項5に係る発明は、前記締着部材が、前記加圧手段に加えてさらに、第二のナット部材と該第二のナット部材を締付け方向に付勢するゼンマイばね材とを備える緩み防止手段を有していることを特徴としている。 According to a fifth aspect of the present invention, the fastening member further includes a second nut member and a spring spring material that biases the second nut member in the tightening direction in addition to the pressurizing means. It has the means.
上記の構成を有する請求項5に係る発明によれば、常時一定の緊張力を長期に渡って安定して付与することができる。
According to the invention which concerns on
請求項6に係る発明は、前記第二のナット部材外縁部にウォームホイールを成形し、該ウォームホイールに係合するウォームを配設すると共に、前記第二のナット部材を締付け方向に前記ウォームを回転させるように付勢する構成としていることを特徴としている。 According to a sixth aspect of the present invention, a worm wheel is formed on the outer edge of the second nut member, a worm that engages with the worm wheel is disposed, and the second nut member is tightened in the tightening direction. It is characterized by being configured to be urged to rotate.
上記の構成を有する請求項6に係る発明によれば、第二のナット部材の緩みをさらに確実に防止することができる。
According to the invention which concerns on
請求項7に係る発明は、請求項4に記載のせん断ゴムばね材を加圧手段とする締着部材に替えて、バネ鋼製の波板からなる締着部材を介して緊張する構成としたことを特徴としている。
The invention according to
上記の構成を有する請求項7に係る発明によれば、波板を介してアンカー部材を緊張させるだけで、常に一定の緊張力を付加することができ、さらに緊張力の緩みを防止することができる。
According to the invention according to
上記したように本発明によれば、自然地山の表層部分を水平にならし掘削して、上盤を載置すると共に、アンカー部材を堆積層を貫通して支持地盤に達するまで打ち込むことで、打ち込んだ堆積層を補強土擬似躯体とすることができ、地盤を補強することができる。また、掘削した地盤に盛土層を形成し、荷重導入補強土基礎を構築する際に、打ち込んだ堆積層をも一体の補強土基礎とすることで、見かけ上さらに大型の補強された基礎地盤を構築することができる。 As described above, according to the present invention, the surface layer portion of the natural ground is leveled and excavated, the upper plate is placed, and the anchor member is driven through the deposited layer until it reaches the support ground. The deposited layer that has been driven in can be used as a reinforced soil pseudo-enclosure, and the ground can be reinforced. In addition, when an embankment layer is formed on the excavated ground and a load-introducing reinforced soil foundation is constructed, the piled-up sedimentary layer is also used as an integral reinforced soil foundation, so that an apparently larger reinforced foundation ground can be obtained. Can be built.
そのために、小規模の土木工事により大型の荷重導入補強土基礎を構築する地盤補強工法ともなり、山間部等の狭隘な地形に適した工法であると共に、環境に優しく低コスト化が達成可能である。 Therefore, it is also a ground reinforcement method for constructing a large load-introducing reinforced soil foundation by small-scale civil engineering work, and it is suitable for narrow terrain such as mountainous areas, and it can achieve environmentally friendly and low cost reduction. is there.
さらには、基礎を構成する補強土と同時に下部の堆積層を締め上げて周囲の土と一体化するので、安定した大型の基礎地盤とすることができる。 Furthermore, since the lower sedimentary layer is tightened simultaneously with the reinforcing soil constituting the foundation and integrated with the surrounding soil, a stable large-scale foundation ground can be obtained.
自然地山を改良あるいは補強する際に、表層部分を水平にならし掘削して上盤を配設して、アンカー部材を支持地盤まで打ち込むかまたは、比較的小さな荷重導入補強土基礎を構成してアンカー部材を支持地盤まで打ち込むことで、容易にまた短期間で施工可能となる地盤補強工法とした。 When improving or reinforcing natural ground, leveling the surface layer and excavating it, placing the upper plate and driving the anchor member to the supporting ground, or constructing a relatively small load-introducing reinforced soil foundation In this way, the anchor member is driven to the supporting ground, so that the ground reinforcement method can be constructed easily and in a short period of time.
以下、本発明に係る地盤補強工法の第一の実施例について、図1から図8に基づいて説明する。 Hereinafter, a first embodiment of the ground reinforcement method according to the present invention will be described with reference to FIGS.
図1は本発明に係る荷重導入補強土基礎の第一の実施例を示す断面図である。図2は本発明に係る荷重導入補強土基礎の有効性を示す概略説明図である。図3は法面すべりを防止する実施例を示す概略説明図であり、(a)は荷重導入補強土基礎による地盤補強工法を示し、(b)は上盤とアンカー部材による地盤補強工法を示している。図4には河川流路に本発明に係る荷重導入補強土基礎を配置した例を示しており、(a)は透過型堰堤を示し、(b)は導流堤を示す。図5は従来の工法による補強土基礎を示す断面図である。図6は締着部材と緩み防止手段とを備えるアンカー部材の上端部構成を示す断面図であり、図7はウォームギヤを備える第二の緩み防止手段を示す斜視図である。図8は締着部材として波板を備えるアンカー部材の上端部構成を示す概略説明図である。 FIG. 1 is a sectional view showing a first embodiment of a load-introducing reinforced soil foundation according to the present invention. FIG. 2 is a schematic explanatory view showing the effectiveness of the load-introducing reinforced soil foundation according to the present invention. FIG. 3 is a schematic explanatory view showing an embodiment for preventing slope slip, (a) showing a ground reinforcement method using a load-introducing reinforcing soil foundation, and (b) showing a ground reinforcement method using an upper plate and an anchor member. ing. FIG. 4 shows an example in which the load-introducing reinforced soil foundation according to the present invention is arranged in a river channel, where (a) shows a transmission type dam and (b) shows a diversion bank. FIG. 5 is a sectional view showing a reinforced soil foundation by a conventional construction method. FIG. 6 is a cross-sectional view showing the structure of the upper end portion of the anchor member provided with the fastening member and the loosening prevention means, and FIG. 7 is a perspective view showing the second loosening prevention means provided with the worm gear. FIG. 8 is a schematic explanatory view showing a configuration of an upper end portion of an anchor member provided with a corrugated plate as a fastening member.
図5に示すように、従来型の荷重導入補強土基礎10は地山の堆積層21に大きな掘削部20Bを設けて構築されており、該掘削部20Bの底ならし施工後に底盤2を設置し、アンカー部材6を装着固定する。次いで基礎を構築していくがこの基礎構築とは、多層の盛土層(4a、4b、4c、4d)間に補強材5を敷設して順次転圧しながら突き固めて、盛土層4を構築するものである。さらに、上盤3を設置して該上盤3の上方に突き出たアンカー部材6の上端部に形成されたネジ部にナット部材7を螺合させアンカー部材6を締め上げて、底盤2と上盤3とに挟まれた盛土層4を一体的に圧縮して補強土躯体となし、荷重導入補強土基礎10を構築している。つまり、従来工法による荷重導入補強土基礎10は、底盤2と上盤3と盛土層4とを一体的に締め上げた補強土躯体と同等の大きさの基礎体となっている。
As shown in FIG. 5, the conventional load-introducing reinforced
さらに詳細に説明すると、上記基礎10は、鋼板等の高剛性の底盤2に設けられた穿孔穴に、PC棒鋼からなるアンカー部材6を挿入して装着固定した後、最下層の盛土4dを造成して転圧機などで突き固めながら補強材5を敷設し、その上に次の盛土4cを造成しさらに突き固め、新たな補強材5を敷設しさらに盛土4b、補強材5、最上段の盛土層4aを順次積み重ね、最後に高剛性の上盤3を設置して形成したものである。
More specifically, the
この時に、補強材5として、摩擦係数及び引張強度が大きいフラット若しくは略フラットな網状又は格子状の補強材(ジオテキスタイルやエキスパンドメタル等)を採用し、厚みの薄い多重の盛土層間に介装しながら、順次所定厚みの基礎10を形成するまで積み重ねていく構成である。この際、盛土層4として、掘削部20Bから掘削された残土を用いる構成とすると、余分な廃棄物を生じることもなく、また、残土の輸送を行う必要もない。
At this time, a flat or substantially flat net-like or lattice-like reinforcing material (geotextile, expanded metal, etc.) having a large friction coefficient and tensile strength is adopted as the reinforcing
本発明に係る荷重導入補強土基礎1は図1に示すように、地山の堆積層21の表層部分のみを掘削して割りと浅い掘削部20Aを形成して、底ならし後に、直接に盛土層4を構築するものである。前記掘削部20Aに底盤を敷設することなく、そのまま複数の各盛土層を転圧しながら、それぞれの盛土層間に補強材を敷設して積層していき、最上段に上盤3を設置して、最後にアンカー部材6を打ち込む構成である。
As shown in FIG. 1, the load-introducing reinforced
アンカー部材6は、上盤3、盛土層4、補強材5、堆積層21を貫通して支持地盤22にまで達するアンカー部材であって、地山補強に一般的に採用されているアースアンカーでも、また、下部に螺旋状の突起部を備えたネジ式アースアンカーでもよく、自然地山の土質に応じて選択して採用すればよい。
The
前記支持地盤22は荷重導入補強土基礎1を支持することができる程度の強度を備える地盤であって、基礎岩盤であっても、標準貫入試験によるN値30以上の地盤であってもよく、共に十分支持地盤22としての役割を果すことができる。
The
前記アンカー部材6として、ボルト・ナット型のアンカー部材を採用することも可能であるが、地盤補強等の土木工事に一般的に採用されるアンカー部材をそのまま採用することで、通常の土木工事により荷重導入補強土基礎を造成することができ好適である。また、前記アンカー部材6の数量は、前記基礎1を形成するのに必要な締め付け力を発揮する程度の本数でよく、特に限定するものではない。
As the
アンカー部材6を堆積層21の地中深くまで打ち込んだ後で、アンカー部材6の上端部に形成されたネジ部にナット部材7を螺合して締め上げて前記アンカー部材6を締結すると、堆積層21の地中深く打ち込まれているアンカー部材6は移動せずに、各盛土層が締付けられてプレストレスが付加されると共に、アンカー部材6が打ち込まれている堆積層21にもプレストレスが付加された状態となる。また、このプレストレスは図中の破線に示すように、前記アンカー部材6が打ち込まれている堆積層21にまで付加されており、図中の破線で示すように断面台形状に下側に大きく拡大していることが明らかとなった。
After the
これは自然地山の地盤は、砂質土と粘性土が混在あるいは互層状態となっている堆積層21であるために、圧縮力が付加されても、側方流動せずに、そのまま圧縮されてプレストレス状態となるためである。 This is because the ground of natural ground is a sedimentary layer 21 in which sandy soil and cohesive soil are mixed or in an alternating layer state, and even if a compressive force is applied, it is compressed as it is without lateral flow. This is because it is in a prestressed state.
基礎に当たる砂質系の堆積土周辺は、元々周囲の地盤から拘束されており、アンカー力により載荷された場合、周辺に土が側方流動することなく、また、躯体下部地盤はプレロード効果により、強度増加と沈下が促進されるため、補強材が配置されなくても基礎として安定している。前記基礎の安定とは、滑動・転倒・支持力に対して安定しているということである。 The sandy sediments surrounding the foundation are originally restrained from the surrounding ground, and when loaded by anchor force, the soil does not flow laterally to the surroundings, and the lower ground of the frame is due to the preload effect, Since strength increase and settlement are promoted, it is stable as a foundation even if a reinforcing material is not arranged. The stability of the foundation means that the foundation is stable with respect to sliding, falling, and supporting force.
そのために、砂質土と粘性土とが混在している堆積層を備える自然地山では、表層部分を水平にならし掘削して補強土基礎を構築し、アンカー部材を堆積層深く打ち込むことで、構築した補強土基礎を地下に延設した大きさに拡大した補強土擬似躯体を形成することが可能になる。つまり、本発明に係る荷重導入補強土基礎は、多層の盛土層と上盤とから構成される補強土躯体の大きさ以上に拡大された基礎地盤を構成することになる。 For this reason, in natural ground with a sedimentary layer in which sandy soil and cohesive soil are mixed, the surface layer is leveled and excavated to construct a reinforced soil foundation and anchor members are driven deep into the sedimentary layer. Thus, it is possible to form a reinforced soil pseudo-enclosure that is expanded to a size obtained by extending the constructed reinforced soil foundation to the basement. That is, the load-introducing reinforced soil foundation according to the present invention constitutes a foundation ground that has been expanded beyond the size of a reinforced earth body composed of a multi-layered embankment layer and an upper board.
この時に、図中の実線に示すように、アンカー部材6として、堆積層21を貫通して支持地盤22にまで打ち込まれたアンカー部材6Aとしても、また、堆積層21が深くて強固な場合には、該堆積層21内に深く打ち込むアンカー部材6B(想像線で示す)としてもよい。これは、堆積層21が厚くて深い地盤の場合には、該堆積層21内のみにアンカー部材6Bを設置すればよく、堆積層21が比較的薄く支持地盤22が地表近くにある場合には支持地盤22まで打ち込むことで、アンカー部材6Aの設置強度をさらに増加することができる。アンカー部材6Aを支持地盤22まで打ち込んだ状態でも、荷重導入補強土基礎1と支持地盤22間にある堆積層21にはプレストレスが付加された拡大化した補強土基礎地盤(図中の破線に示す範囲)が形成されている。
At this time, as shown by a solid line in the figure, as the
つまり、プレストレスが付加された荷重導入補強土基礎は、図2に示すように、補強土躯体としての大きさが擬似躯体1aでその荷重がHaであっても、プレストレス状態であるので該擬似躯体1aの上部に荷重Hbの土換算荷重高さ1bを配設したことに相当する状態となり、堆積層中にHa+Hbに相当するプレローディング荷重が付加された見かけ上の地盤改良ゾーン1cを形成していることになる。そのために、荷重導入補強土基礎としては図中に示すHa+Hb+Hcに相当する荷重を有する補強土擬似躯体1a+1b+1cに拡大された基礎を構成すると共に、該基礎の周囲の土に受動土圧を発生させ、その見かけ荷重は補強土躯体自重の数倍となり、前記擬似躯体1aの自重以上のすべり抑止力を発揮する。 That is, the load-introducing reinforced soil foundation to which prestress is applied is in a prestressed state even when the size of the reinforced soil body is a pseudo skeleton 1a and the load is Ha, as shown in FIG. It becomes a state equivalent to disposing the soil equivalent load height 1b of the load Hb on the upper part of the pseudo housing 1a, and an apparent ground improvement zone 1c is formed in which a preloading load corresponding to Ha + Hb is added in the deposited layer. Will be. Therefore, as the load-introducing reinforced soil foundation, a foundation expanded to the reinforced soil pseudo-enclosure 1a + 1b + 1c having a load corresponding to Ha + Hb + Hc shown in the figure is formed, and passive earth pressure is generated in the soil around the foundation, The apparent load is several times the weight of the reinforced earthen body, and exhibits a slip suppression force that is greater than the weight of the pseudo-body 1a.
そのために、図3(a)に示すように本発明に係る荷重導入補強土基礎1を、法面すべりを抑止する盛土工法に適用すると好適である。特に長大法面の下部にあたる法尻に設置される荷重導入補強土基礎1Aは、上記のように自重以上のすべり抑止力を発揮するために、構築する荷重導入補強土基礎1Aが比較的小型であっても大型の補強土擬似躯体からなる大きな基礎を構築していることになり、プレストレスの効果を最大に発揮して長大すべりS1を防止すると共に地すべり23に対する補強擁壁として好適である。
Therefore, as shown in FIG. 3A, it is preferable to apply the load-introducing reinforced
また、前記法尻に設置する荷重導入補強土基礎1Aの上部に別の荷重導入補強土基礎1Bを設置して、順次滑りを分断するようにし、分断すべりS2を防止する構成とすることもできる。この分断すべりS2はすべりの方向が構築体に水平となり、躯体抵抗力が大きくなって、すべり抑止力に大きな効果がある。つまり、この荷重導入補強土基礎1Bは、傾斜面部の堆積層の補強と土石流24の防止機能を備えている。
Further, another load introduction reinforcing soil foundation 1B may be installed on the upper part of the load introduction reinforcing soil foundation 1A to be installed on the above-mentioned butt, so as to sequentially separate the slip and prevent the fragmentation slip S2. . In this divided slip S2, the slip direction is horizontal to the construction body, and the frame resistance is increased, which has a great effect on the slip prevention force. That is, the load-introducing reinforced soil foundation 1B has a function of reinforcing the sedimentary layer on the inclined surface portion and preventing the
さらには、法面の任意の位置の表層部分を水平にならし掘削した後で、地表に突出しない程度の小型の荷重導入補強土基礎1Cを設置して、斜面部分の地盤を補強する補強土基礎とすることも有効である。 Furthermore, after leveling and digging the surface layer at an arbitrary position on the slope, a small load-introducing reinforced soil foundation 1C that does not protrude to the ground surface is installed to reinforce the ground of the slope portion. A foundation is also effective.
さらには、図3(b)に示すように、表層部分を水平にならし掘削したあとで上盤3を配設して、アンカー部材6を支持地盤22まで打ち込んで締め付けるだけで、堆積層21に圧縮力を作用させて、図中の破線で示す範囲の補強土擬似躯体を形成することになり、この簡単な構成でも自然地山の地盤を補強する工法となりえるものである。
Furthermore, as shown in FIG. 3 (b), after the surface layer portion is leveled and excavated, the
以上説明したように、自然地山の堆積層に鉛直方向の圧力を付与すると、堆積層内部の周囲の土に受動土圧が付加されて、地盤強度が増大する。これは、自然地山の地盤が砂質土と粘性土とが混在した堆積層からなっており、プレストレスをかけても側方流動を起こし難いからである。また、その地盤強度が増加する範囲は、押圧する上盤の面積だけに留まらずに、断面台形状に下部に行くほど拡大して広範囲に広がっており、自然地山の地盤補強に最適である。 As described above, when vertical pressure is applied to the sedimentary layer of natural ground, passive earth pressure is applied to the surrounding soil inside the sedimentary layer, increasing the ground strength. This is because the ground of natural ground is composed of sedimentary layers in which sandy soil and cohesive soil are mixed, and it is difficult for side flow to occur even when prestressed. In addition, the area where the ground strength increases is not limited to the area of the upper board to be pressed, but expands to a lower part in a trapezoidal cross section, which is optimal for ground reinforcement of natural ground. .
また、プレストレスをかける前に、鉄筋類挿入による補強工法等の従来の自然地山の補強工法を施工して組み合わせ工法とすると、さらに地盤の補強効果を増加させることができる。 In addition, if a conventional natural ground reinforcement method such as a reinforcement method by inserting reinforcing bars is applied before the prestress is applied to form a combination method, the ground reinforcement effect can be further increased.
本発明に係る地盤補強工法では、地盤の表層部分を水平にならし掘削するだけなので、掘削する土量が少なくてよい。そのために、工事規模を小さくすることができる。さらに、底盤を使用せずに、荷重導入補強土基礎造成後にアンカー部材を打ち込んで締め上げる工程であるので、従来の補強土基礎工法ように、底盤を設置してアンカー部材を装着した後に、盛土転圧と補強材敷設とを繰り返し作業していく必要もなく、工程が簡単になると共に工期も短縮でき、安価な地盤補強工法となる。 In the ground reinforcement method according to the present invention, since the surface layer portion of the ground is only leveled and excavated, the amount of soil to be excavated can be small. Therefore, the construction scale can be reduced. Furthermore, since the anchor member is driven and tightened after the load-introducing reinforced soil foundation is constructed without using the bottom plate, after the bottom plate is installed and the anchor member is installed, as in the conventional reinforced soil foundation method, It is not necessary to repeat the rolling and laying of the reinforcing material, the process is simplified, the construction period can be shortened, and an inexpensive ground reinforcement method is provided.
図4には河川流路に本発明に係る荷重導入補強土基礎を配置した例を示しており、(a)は透過型堰堤を示し、(b)は導流堤を示す。 FIG. 4 shows an example in which the load-introducing reinforced soil foundation according to the present invention is arranged in a river channel, where (a) shows a transmission type dam and (b) shows a diversion bank.
図4(a)に示す荷重導入補強土基礎1Dは、川底を少し掘削して構築した補強土基礎であり、流域の上流から下流に向かって順に互い違いに複数個配列した構成であり、流れる土砂は堆積せず通過し、水の流れエネルギーは複数の前記基礎に衝突する際に吸収されて減衰するように構成したものである。そのために、図中の矢印は、元の流れエネルギー30がこの透過型堰堤を通過すると、流れエネルギー31にまで減衰することを示している。 The load-introducing reinforced soil foundation 1D shown in FIG. 4 (a) is a reinforced soil foundation constructed by excavating the riverbed a little, and has a configuration in which a plurality of staggered flows are arranged in order from the upstream to the downstream of the basin. Passes through without depositing, and the flow energy of water is absorbed and attenuated when colliding with a plurality of the foundations. Therefore, the arrows in the figure indicate that the original flow energy 30 is attenuated to the flow energy 31 when passing through the transmission type dam.
また、前記荷重導入補強土基礎1Dはそれぞれが、小規模の構築物構成であって、川幅全体に渡って構築する不透過型堰堤に比べてはるかに小規模な土木工事でよい。また、掘削する土量も少量であるので、環境に対する悪影響もない。 Further, each of the load-introducing reinforcing earth foundations 1D has a small-scale structure configuration, and may be a civil engineering work that is much smaller than an impervious type dam constructed over the entire river width. Moreover, since the amount of soil to be excavated is small, there is no adverse effect on the environment.
図4(b)に示す荷重導入補強土基礎1Eは川の流れを蛇行させて緩やかな流れとする導流堤であって、川の両側に互い違いに複数配設した例である。この配置例では、水流が順にそれぞれの基礎に衝突して、流れを偏向して蛇行するようになる。そのために、図中の矢印は、元の流れエネルギー32がこの導流堤を通過すると、流れエネルギー33にまで減衰することを示している。
A load-introducing reinforcing earth foundation 1E shown in FIG. 4B is a diversion bank that causes a gentle flow by meandering the flow of the river, and is an example in which a plurality of staggered foundations are arranged alternately on both sides of the river. In this arrangement example, the water flow sequentially collides with each foundation, and the flow is deflected to meander. Therefore, the arrow in the figure indicates that the
また、自然地山の地盤補強工法や河川流路における堰堤構築の際に、アンカー部材6を締付ける時に、図6に示すように、緊張力を付与すると共に緩みを阻止する締着部材8を配設する構成とすれば、所定の締付け力を付加することができ、さらには締付け力の緩みを防止することができる。
Further, when the
アンカー部材6により盛土に鉛直方向にプレロードを加えて塑性ひずみを進行させ、供用時の残留沈下を抑制する。次にプレロードの一部を除荷しプレストレス状態にすることによって盛土内の拘束圧を高い値に維持し、供用時でのせん断抵抗力と剛性を飛躍的に増加させることができる。
The
そのために、プレストレス状態を維持する構成とすることで、地震等の繰り返し荷重が付加されても、曲げ変形を抑制して盛土の鉛直拘束力を維持することで、一体的な補強土擬似躯体を維持することができる。 Therefore, by adopting a configuration that maintains a prestressed state, even if a repeated load such as an earthquake is applied, by suppressing bending deformation and maintaining the vertical restraining force of the embankment, an integrated reinforced soil pseudo-enclosure Can be maintained.
図6(a)に示す締着部材8は、アンカー部材6が挿通自在な円形の開口部80Aを中央に備える設置台80に、前記開口部80Aを塞ぐようにせん断ゴムばね材Eを配設した構成である。つまり、上盤3から突き出した状態のアンカー部材6に、下側が開放した溝型台状の設置台80を被せるように止めネジ80aで固設して、前記開口部80A上にアンカー部材6を挿通して前記せん断ゴムばね材Eを配設した構成としている。
In the
前記せん断ゴムばね材Eは、中空円筒状の内金具81とケーシング金具82との間に、円環状のゴム状弾性体層83を挟設した構成であり、これらの界面は加硫接着等の方法で強固に接着されている。そのために、円筒軸方向には前記ゴム状弾性体層83を介して、内金具81とケーシング金具82とが変位自在な構成である。
The shear rubber spring material E has a configuration in which an annular rubber elastic body layer 83 is sandwiched between a hollow cylindrical
設置台80の上端中央部に設けられた円形の開口部80Aに前記せん断ゴムばね材Eを設置する。この時に前記開口部80Aの周縁に突出部80Bを設け、該突出部80Bに前記ケーシング金具82の下端部を外嵌するように載置する構成とすると、設置位置が規制されて好適である。前記せん断ゴムばね材Eを設置後に、前記アンカー部材6上端部のネジ部6aに第一のナット部材7を螺合させてワッシャ9を介して内金具81の上端を押下していくと、内金具81が押圧されながらゴム状弾性体層83が弾性変形し、図中の実線に示すように81A位置まで押下される。
The shear rubber spring material E is installed in a
前記ゴム状弾性体層83の弾性変形量に相当する緊張力が前記アンカー部材6に付加された状態となり、さらに、盛土や基礎地盤の沈下やアンカー部材の伸長に追随して弾性変形しながら所定の緊張力を付与する構成である。つまり、せん断ゴムばね材Eは、設置台80と第一のナット部材7とで、アンカー部材6に緊張力を付与する加圧手段を構成している。
A tension force corresponding to the elastic deformation amount of the rubber-like elastic body layer 83 is applied to the
上記緊張力の程度としてその一例を示すと、前記ゴム状弾性体層83の厚みTが40mmで長さHが450mmの場合に、内金具81を60mm押下してゴム状弾性体の伸びが60mmの場合で約600kN(約60トン)、内金具81を100mm押下してゴム状弾性体の伸びが100mmの場合で約1000kN(約100トン)の緊張力が得られている。
As an example of the degree of tension, when the thickness T of the rubber-like elastic body layer 83 is 40 mm and the length H is 450 mm, the
そのために、ゴム状弾性体の伸びを60〜100mmの範囲でアンカー部材6の緊張力を付与する構成としておけば、アンカー部材一箇所に常に600kN以上の緊張力を付加している状態を維持することができる。
Therefore, if the extension of the rubber-like elastic body is configured to apply the tension of the
また、この時に、前記加圧手段に加えてさらに、第二のナット部材84とゼンマイばね材85と支持体86とを備える緩み防止手段Fを備える構成の締着部材8とすれば、締付け力の緩みをさらに防止することができ好適である。
At this time, in addition to the pressurizing means, if the
前記第二のナット部材84と半径方向にわずかに間隔をあけて円環状で内側に凹部を設けた支持体86を、複数本の止めネジ86aにより上盤3に固着する構成であり、前記凹部にゼンマイばね材85を収容可能にしている。
The
前記ゼンマイばね材85の両端の一方を第二のナット部材84に止着し、他方を支持体86に止着すると共に、ゼンマイばね材85の付勢力が第二のナット部材84を締める方向に向かうように設定している。
One end of the spring spring member 85 is fixed to the
そのために、前記せん断ゴムばね材Eを締付けて固定した後で、アンカー部材6の第二ネジ部6bに装着している第二のナット部材84を回転し上盤3に固着する。その後で、ゼンマイばね材85を締めた状態で支持体86を止めネジ86aで上盤3に固定すると、前記第二のナット部材84が締付けられる方向に前記ゼンマイばね材85の付勢力が作用する構成とすることができる。
Therefore, after the shear rubber spring material E is fastened and fixed, the
上記の構成にしておけば、補強土基礎体を構成する上盤3とアンカー部材6とを締結する第二のナット部材84が常に締付けられる方向に付勢されている構成となるので、前記のせん断ゴムばね材Eの加圧力をアンカー部材6と上盤3に確実に、さらに長期に渡って安定して付与することができる。また、ゼンマイばね材85の上面を覆うカバー部材87を配設することで、前記ゼンマイばね材85部に異物等が混入するのを防止することができる。
If it is set as said structure, since it becomes the structure currently urged | biased in the direction in which the
前記せん断ゴムばね材Eを図6(b)に示すように、内金具81とケーシング金具82とを上下にずらして段違い型に成形した形状(図中の想像線に示す)とし、ケーシング金具82を設置台80Cに載置する構成とすれば、第一のナット部材7によりワッシャ9を介して内金具81の上端を押下する際に、前記内金具81の上端面がケーシング金具82の上端面と略水平になるまで押圧する(図中の実線に示す)ことで、所定の緊張力を付与する構成とすることができる。
As shown in FIG. 6B, the shear rubber spring material E has a shape (indicated by an imaginary line in the figure) in which the
上記の構成では、緊張力の緩みが生じると、前記内金具81の上端面とケーシング金具82の上端面との水平状態が破棄されて、内金具81の上端面が競り上がる方向に変移するので、一目瞭然となり直ちに第一のナット部材7の締め直しすることで、緊張力の再調整を実施することができる。
In the above configuration, when the tension force is loosened, the horizontal state between the upper end surface of the
いずれにしても、単体構成のせん断ゴムばね材Eを用いて所定の緊張力を付加する締着部材を構成することができるので、構造が簡単であるだけでなく、操作も楽になる。 In any case, the fastening member for applying a predetermined tension force can be configured using the shear rubber spring material E having a single structure, so that not only the structure is simple but also the operation becomes easy.
上記のせん断ゴムばね材Eは、基礎の塑性変形による沈下分(体積減少分)だけゼンマイばね材85が第二のナット部材84を回転させて追随してプレストレス状態を維持する構成である。また、密に締め固めた盛土体に外力を与えた場合、盛土体がせん断変形により、体積膨張をおこそうとするが、前記第二のナット部材84を常にアンカー部材6の引張り方向に回転力を与えているので、逆転をおこさずに補強土基礎の体積膨張を阻止している。
The above-described shear rubber spring material E has a configuration in which the mainspring spring material 85 follows the rotation of the
つまり、盛土の高さを一定に保つ機能を備えており、補強土基礎の体積膨張を抑制すると共に、前記第二のナット部材84を締付け方向に常時付勢しているので、地震や土砂崩落などの衝撃による繰り返し曲げ変形をも抑制することができる。
In other words, it has a function to keep the height of the embankment constant, suppresses volume expansion of the reinforced soil foundation, and constantly urges the
また、図7に示すように、ゼンマイばね材85に替えてウォーム88と第二のナット部材84Aの外縁に形成されるウォームホイールとで構成されるウォームギヤを備える第二の緩み防止手段FAを配設する構成としてもよい。
Further, as shown in FIG. 7, second loosening prevention means FA including a worm gear constituted by a
上盤3に固着される設置台80Dに、ブッシュ88Aを介して回転自在に装着されるウォーム88が第二のナット部材84Aの外縁に形成されたウォームホイールに噛合うウォームギヤ構成として、ウォーム88を回動させることで、第二のナット部材84Aを回転可能にしたものである。
As a worm gear configuration in which a
前記ウォーム88の一方の軸端にハンドル89Aを備える円盤89を設けた。円盤89の外縁部に装着されるハンドル89Aを回すことで、ウォーム88を軽く回動させることができる。さらに、円盤89と設置台80D間に第二のゼンマイばね材85Aを配設して前記ウォーム88の回転方向を一方向に付勢するように構成し、第二のナット部材84Aが締まる方向に常に付勢しておく構成としておけば、前記と同様に第二のナット部材84Aの逆転を防止して、補強土基礎の体積変化に追随し、躯体の強度・剛性を維持することができる。
A disk 89 having a handle 89 </ b> A is provided at one shaft end of the
また、前記第二のゼンマイばね材85A部にラチェット機能を備えるクラッチ部材を装着して、緩みをさらに抑制する構成とすることもできる。 Further, a clutch member having a ratchet function may be attached to the second spring spring member 85A so as to further suppress loosening.
ただし、第二のゼンマイばね材85Aのみで構成した例では、前記補強土基礎の体積変化に追随して回動する前記ハンドル89Aの位置により、その変化具合を目視にて確認することができ好適である。
However, in the example constituted only by the second spring spring material 85A, the degree of change can be visually confirmed by the position of the
さらに、締着部材8として図8に示す波板8Aを上盤3の上に載置して、第一のナット部材7を締付ける構成とするだけでも、強力な緊張力が得られて好適である。このような簡単な構成でも、所定の緊張力を付加するだけではなく、締付け力の緩み防止を図ることができる。
Furthermore, even if the corrugated plate 8A shown in FIG. 8 is placed on the
前記波板8Aはバネ鋼製の波板であって、波状の板鋼を締付ける際に生じる弾性反力を補強土の締付け力とする構成である。そのために、バネ性の明確な波板8Aを前記ナット部材7で締付ける構成としているので、波板8Aの変形量により、前記ナット部材7の締め付け程度を判定することができ、一定の締付け量とすることができると共に、長期に渡って安定した締付け力を維持することができる。さらに、補強土の変形や流失等により締め付けが緩む場合でも、所定の締め付け力を維持しながら、波板8Aの弾性範囲内で変形量が変化するので、再度の締め付け時期も明確に判定され好適である。
The corrugated plate 8A is a corrugated plate made of spring steel and has a configuration in which an elastic reaction force generated when the corrugated plate steel is tightened is used as a tightening force of the reinforcing soil. For this purpose, the corrugated plate 8A having a clear spring property is tightened by the
もちろん前記波板8Aに替えて、大型の波ワッシャを採用することもできるが、盛土層を押圧する大きな締付け力を得るためには、大きな面積に加工可能なバネ鋼板の波板が好ましい。 Of course, a large wave washer can be used instead of the corrugated plate 8A, but in order to obtain a large clamping force for pressing the embankment layer, a corrugated plate of a spring steel plate that can be processed into a large area is preferable.
アンカー部材6の緩み止め機構として単なる板金部品である波板8Aを介して締付ける構成としたので、構成の複雑な緩み止め装置を使用せずに簡単にアンカー部材6の緩み止めを行うことができるという効果を有する。
Since the
上記のように、自然地山の表層部分のみを水平にならし掘削して、荷重導入補強土基礎1を構築すると、該基礎1の下部地盤である堆積層をも荷重導入補強土基礎状態とする工法であるので、土木工のみにより効率的に作業することができる。また、従来のコンクリートやセメント系固化材を用いた地盤改良工法では、軟弱な地盤を掘り返して、固化材を添加して締め固める作業が必要であり、また硬化する期間工期が長くなり、大型の施工重機が必要であると共に、工事が長期化し大変であるが、本実施例では、補強土基礎構築の全工程を一連の連続工程として短期間に施工することができる。そして、自然地山の表層部分のみを掘削して補強土構築工事を行うので、自然にやさしい工法ともいえ、環境保全にも好適である。
As described above, when only the surface layer portion of the natural ground is leveled and excavated to construct the load-introducing reinforced
つまり、上記の本発明に係る荷重導入補強土基礎による地盤補強工法は、割に小規模の土木工事により大型の荷重導入補強土基礎を構築する地盤補強工法ともなり、山間部の狭隘な地形でも比較的容易に工事を行うことができる工法であり、工事工程を短くすることができ、工事コストを低く押えることができる。 In other words, the ground reinforcement method using the load-introducing reinforced soil foundation according to the present invention is also a ground reinforcement method for constructing a large load-introducing reinforced soil foundation by small-scale civil engineering work, even in a narrow terrain in a mountainous area. It is a construction method that allows construction to be performed relatively easily, shortens the construction process, and keeps construction costs low.
次に図9と図10により第二の実施例について説明する。 Next, a second embodiment will be described with reference to FIGS.
図9は本発明に係る荷重導入補強土基礎を利用して地山の斜面部に構造物の基礎を構成した例であり、図10には従来の荷重導入補強土基礎による構造物の基礎構成を示している。 FIG. 9 shows an example in which the foundation of the structure is constructed on the slope of the natural ground using the load-introducing reinforced soil foundation according to the present invention, and FIG. Is shown.
図9に示す荷重導入補強土基礎1Fは、斜面表層の堆積層21を支持地盤25に至るまで掘削して、支持地盤25の上面を段切りして平面部25aを造成し、掘削した現地発生土または良質土を埋め戻して転圧し置換層20Cを造成し、その上に補強材5と盛土4を積層して補強土基礎を構築して、上盤3を設置した後で、アンカー部材6を前記支持地盤25に達するまで打ち込んで、先端をモルタル注入などで固定し、緊張締着した構成である。また、前記上盤3に台座12を設置し、該台座12に橋桁13等を設置することができる。
The load-introducing reinforced soil foundation 1F shown in FIG. 9 excavates the sediment layer 21 on the slope surface up to the supporting
上記の荷重導入補強土基礎1Fは土から構成されているので、軽量な構成であり、傾斜面の山側ではなく傾斜地近くに構築することができ、橋台とした時に、橋桁スパンを短くすることができる。 The load-introducing reinforced soil foundation 1F is made of soil, so it is light in weight, and can be constructed near the slope rather than the mountain side of the slope. When it is used as an abutment, the bridge girder span can be shortened. it can.
前記の荷重導入補強土基礎1Fは、水平状態の支持地盤上に基礎構築体を構築する構成であるので、特殊な斜面設計も不要であり容易な施工となる。また、図10に示す従来の斜め状の補助アンカーが不要であり、アンカー緊張力の複合設計計算も不要である。 Since the load introduction reinforcing soil foundation 1F is configured to construct a foundation structure on a support ground in a horizontal state, a special slope design is not required and the construction is easy. Moreover, the conventional diagonal auxiliary anchor shown in FIG. 10 is unnecessary, and the complex design calculation of anchor tension force is also unnecessary.
図10に示す従来の基礎構成では、支持地盤25の鉛直方向にアンカー部材6を設置すると共に、傾斜した支持地盤25に略直交する方向に斜めに打ち込む補助アンカー6Cを設けて、荷重導入補強土基礎11を支持地盤25に付勢して該基礎の側方移動と沈下を防止する必要があって、アンカー部材6と補助アンカー6Cの緊張力を設定することが困難であり、さらにはその施工も困難である。
In the conventional basic structure shown in FIG. 10, the
上記のアンカー部材6と補助アンカー6Cを傾斜面25bに対して打ち込み、それぞれの緊張力を作用させる際に、その緊張力に不均衡が生じると、図中の想像線に示すように前記傾斜面25bに沿ってすべりが生じて、側方移動した基礎11Aとなり、地盤支持力の低下につながる。
When the
そのために、施工段階において鉛直方向のアンカー部材6と斜め状の補助アンカー6Cとの緊張力の不均衡により、側方移動や沈下が生じて所要の支持力が得られない場合には、施工を中止して手戻りとなることがある。
Therefore, in the construction stage, if the required support force cannot be obtained due to lateral movement or settlement due to the tension imbalance between the
図9に示す本発明に係る荷重導入補強土基礎1Fは、設計計算が容易であり、施工中に掘削地盤の地耐力現認もできるので、状況に応じて置換工部分と擬似躯体工部分との高さを変えることができ、設計変更も容易である。また、通常の盛土施工であるので、転圧管理を行うことで通常の土木作業者で作業可能であり、特殊な技能工を必要としない。 The load-introducing reinforced soil foundation 1F according to the present invention shown in FIG. 9 is easy in design calculation and can confirm the ground strength of the excavated ground during construction. The height can be changed, and the design can be easily changed. Moreover, since it is normal embankment construction, it can be operated by a normal civil engineer by performing rolling pressure management, and does not require a special technician.
本実施例においても、補強土による擬似躯体は表層部分のみの浅い部分だけでよく、ただアンカー部材を支持地盤25に達するまで打ち込んで、前記擬似躯体と置換層20Cとを同時に緊張することで、補強土擬似躯体下部に断面台形状に下側に大きく拡大した基礎体を構成している。 Also in the present embodiment, the simulated skeleton by the reinforced soil may be only a shallow portion of the surface layer portion. A foundation body that is greatly expanded downward in a trapezoidal cross section is configured at the lower part of the reinforced soil simulated housing.
さらには、掘削残土である現地発生土が不良な場合には、石灰混合改良などにより脱水や改質を図り再利用することができるので、掘削残土を廃棄する必要もなく、また搬送する必要もないことになり、この点からも山間部等の狭隘な地形に適した工法であると共に、環境に優しく低コスト化が達成可能である。 Furthermore, if the locally generated soil that is excavated residual soil is poor, it can be reused by dewatering and reforming by improving lime mixing, etc., so it is not necessary to discard the excavated soil and transport it. From this point, it is a construction method suitable for narrow terrain such as a mountainous area, and it is environmentally friendly and can achieve cost reduction.
また、多層の盛土層から構成される基礎を貫通して、堆積層の地中深くにまでアンカー部材を打ち込む構成であるので、前記基礎だけではなく、該基礎下部の堆積層をも一体的な荷重導入補強土擬似躯体を形成し、大型の基礎地盤を構築したものと同等の効果を得ることができる。さらには、該基礎躯体にプレストレスを掛ける際に、周囲の土に受動土圧が発生し、地盤強度がさらに向上するので、地盤補強工法として有効である。 Further, since the anchor member is driven through the foundation composed of the multi-layered embankment layer and deep into the ground of the sedimentary layer, not only the foundation but also the sedimentary layer below the foundation is integrated. It is possible to obtain the same effect as that obtained by forming a load-introducing reinforced soil pseudo-frame and constructing a large foundation ground. Furthermore, when prestressing is applied to the foundation frame, a passive earth pressure is generated in the surrounding soil and the ground strength is further improved, which is effective as a ground reinforcement method.
1 荷重導入補強土基礎
1a (荷重導入)補強土擬似躯体
3 上盤
4 盛土層
5 補強材
6 アンカー部材
8 締着部材
10 荷重導入補強土基礎(従来の)
20A 掘削部
20B (従来の深い)掘削部
21 堆積層
22 支持地盤
81 内金具
82 ケーシング金具
83 ゴム状弾性体層
84 第二のナット部材
84A 第二のナット部材(ウォームホイールを備える)
88 ウォーム
E せん断ゴムばね材(加圧手段)
F 緩み防止手段
FA 第二の緩み防止手段
DESCRIPTION OF
20A excavation part 20B (conventional deep) excavation part 21
88 Worm E Shear rubber spring material (Pressurizing means)
F Loosening prevention means FA Second loosening prevention means
Claims (7)
A ground reinforcement construction method characterized in that, instead of a fastening member using the shear rubber spring material according to claim 4 as a pressurizing means, the tension is made via a fastening member made of a corrugated plate made of spring steel. .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003291591A JP4252860B2 (en) | 2003-08-11 | 2003-08-11 | Ground reinforcement method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003291591A JP4252860B2 (en) | 2003-08-11 | 2003-08-11 | Ground reinforcement method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005061021A true JP2005061021A (en) | 2005-03-10 |
JP4252860B2 JP4252860B2 (en) | 2009-04-08 |
Family
ID=34369232
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003291591A Expired - Fee Related JP4252860B2 (en) | 2003-08-11 | 2003-08-11 | Ground reinforcement method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4252860B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014037679A (en) * | 2012-08-10 | 2014-02-27 | Taisei Corp | Water channel and construction method for the same |
JP2016156148A (en) * | 2015-02-23 | 2016-09-01 | 公益財団法人鉄道総合技術研究所 | Construction method for enhancing seismic resistance of banking wall reinforced at both ends and having large slenderness ratio, and ease of long-term maintenance and management by mitigating residual deformation |
JP2016160628A (en) * | 2015-02-27 | 2016-09-05 | 旭コンクリート工業株式会社 | Retaining wall, and installation method thereof |
-
2003
- 2003-08-11 JP JP2003291591A patent/JP4252860B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014037679A (en) * | 2012-08-10 | 2014-02-27 | Taisei Corp | Water channel and construction method for the same |
JP2016156148A (en) * | 2015-02-23 | 2016-09-01 | 公益財団法人鉄道総合技術研究所 | Construction method for enhancing seismic resistance of banking wall reinforced at both ends and having large slenderness ratio, and ease of long-term maintenance and management by mitigating residual deformation |
JP2016160628A (en) * | 2015-02-27 | 2016-09-05 | 旭コンクリート工業株式会社 | Retaining wall, and installation method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP4252860B2 (en) | 2009-04-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Alexiew et al. | Geotextile encased columns (GEC): load capacity, geotextile selection and pre-design graphs | |
CN103958780B (en) | The method for forming cementing retaining wall | |
JP2007321452A (en) | Construction method for bridge and bridge structure thereof | |
JP5180022B2 (en) | Constraining method for mountain retaining wall head | |
US20230091971A1 (en) | System and Method for Protection of Under-Slab Utilities From Changes in Soil Volume | |
JPH06294136A (en) | Soil improvement pile | |
JP3789127B1 (en) | Seismic structure | |
JP3855198B2 (en) | Seismic reinforcement structure for pile foundation structures | |
JP2002242186A (en) | Bank structure constructing method | |
JP4575800B2 (en) | Embankment reinforcement structure and reinforcement method | |
JP4252860B2 (en) | Ground reinforcement method | |
US6745421B2 (en) | Abutment with seismic restraints | |
JP4089717B2 (en) | Earthquake-proof basement structure and its construction method | |
JP2597116B2 (en) | Embankment foundation and its construction method | |
JP2016156147A (en) | Construction method of anti-gigantic tsunami seacoast earth structure with highly rigid geosynthetic reinforced earth retaining wall having rigid integral wall surface | |
KR101203289B1 (en) | Reinforced retaining wall with curb element and its construction method | |
JP2004183347A (en) | Pipe line installation method for columnar article and load introduction reinforcement foundation | |
JP2007247225A (en) | Continuous girder structure formed of a plurality of simple girder bridges, and construction method | |
JP3770665B2 (en) | Ground improvement composite foundation | |
JP2015055076A (en) | Support structure, and method for constructing support pillar | |
SHINDO et al. | Restoration of Sanriku railway by utilizing reinforced soil structures to enhance earthquake-and-tsunami-resistance | |
JP6324916B2 (en) | Measures to improve long-term maintenance performance by reducing earthquake resistance and residual deformation of double-wall reinforced embankment method with large slenderness ratio | |
Naesgaard et al. | The construction and performance of post-grouted micro-piles for Vancouver International Airport Domestic Terminal Building | |
JP7008663B2 (en) | Column pile rotation suppression structure | |
JP4153826B2 (en) | Column installation method using the load-introducing reinforced soil foundation method and the column structure installation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060607 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080108 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080306 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080624 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080819 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090113 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090122 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 4252860 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120130 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120130 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130130 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140130 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |