JP2004355417A - Project information management device and program - Google Patents

Project information management device and program Download PDF

Info

Publication number
JP2004355417A
JP2004355417A JP2003153654A JP2003153654A JP2004355417A JP 2004355417 A JP2004355417 A JP 2004355417A JP 2003153654 A JP2003153654 A JP 2003153654A JP 2003153654 A JP2003153654 A JP 2003153654A JP 2004355417 A JP2004355417 A JP 2004355417A
Authority
JP
Japan
Prior art keywords
project
information
document
change
screen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003153654A
Other languages
Japanese (ja)
Other versions
JP3970205B2 (en
Inventor
Hajime Shiba
肇 柴
Takeshi Maeda
剛 前田
Takafumi Nakayama
隆文 中山
Makoto Morita
誠 森田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanyo Electric Co Ltd
Original Assignee
Sanyo Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanyo Electric Co Ltd filed Critical Sanyo Electric Co Ltd
Priority to JP2003153654A priority Critical patent/JP3970205B2/en
Publication of JP2004355417A publication Critical patent/JP2004355417A/en
Application granted granted Critical
Publication of JP3970205B2 publication Critical patent/JP3970205B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a project information management device capable of managing all information about a project, and if there are all operations for changing the information managed, creating a report format indicating the changes in the information caused by the operations, specifying members related to the information changed, and notifying the members of the report format. <P>SOLUTION: When a project state notification process part 220 is notified of a command from a document information processing part 204, a schedule information processing part 209, a project information processing part 213 or a user information processing part 217, it creates an appropriate document matching the command and determines whether the document is distributed to members of the project about the command or to all the users registered. It then creates a list of addresses to which the document should be distributed, and distributes the document to the addresses on the list. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

【0001】
【産業上の利用分野】
本発明は、プロジェクト情報管理装置に関し、特に該プロジェクト情報管理装置が管理する情報に変更が生じた場合に、自動的に情報の変更の詳細を、該プロジェクトに関わっているユーザ又はプロジェクトに関わっていないユーザに通知するプロジェクト情報管理装置に関する。
【0002】
【従来の技術】
プロジェクト業務の円滑な遂行には、メンバー間での情報共有が極めて重要であり、従来のプロジェクト情報管理装置は、メンバー間での情報共有のための手段としてコンピュータネットワーク上でのファイル共有や電子メールを利用していた。
【0003】
しかしながら、共有情報の更新が頻繁なプロジェクトでは、共有情報が更新された場合にその旨の通知が要求される場合がある。このような場合において、上記のファイル共有と電子メールだけでは不十分であり、例えば次のような問題が生じていた。
【0004】
▲1▼情報更新の通知を発行する際、電子メール等が利用できるが、プロジェクトメンバー数の増大に伴い、通知すべきユーザを選択するのに時間と手間がかかる。更に悪いことには、メンバー変更に伴う配布リストのアップデートを厳格に実施していないと、適切なユーザへタイムリーに通知されない。
【0005】
▲2▼情報更新を通知する文面は、情報変更を行なったメンバーが作成しなければならないが、文面フォーマットについては統一化を厳格に施行しなければ、通知内容のレベルがユーザによってまちまちとなり、情報変更が認識されるレベルに差が生じる。
【0006】
▲3▼どの情報に対する更新通知を誰に発行するかをプロジェクトとして厳格に施行しない場合、連絡漏れが発生する可能性がある。
【0007】
以上のような問題を解決するために、プロジェクトの共有情報の更新を適切なタイミングで、適切なメンバーに、適切な内容で発行する仕組みが求められていた。
【0008】
尚、上記の他、プロジェクト情報管理装置に関する技術は以下の特許文献1に開示されている。
【0009】
【特許文献1】特許 第2956667号
【0010】
【発明が解決しようとする課題】
それゆえ、本発明の主たる目的は、上記問題を鑑みて、プロジェクトに関する全ての情報を管理し、管理されている情報を変更するあらゆる操作があった場合に、その操作による情報の変更を示す定型文書を作成し、変更のあった情報に関係するメンバーを特定し、そのメンバーに対してこの定型文書を通知することができるプロジェクト情報管理装置を提供することである。
【0011】
【課題を解決するための手段】
本願請求項1の発明に係るプロジェクト情報管理装置は、1又は2以上のプロジェクトに関する情報を管理するプロジェト情報管理装置において、前記情報を変更するための画面を提供する変更画面提供手段と、プロジェクトを構成するユーザと該ユーザの配信先アドレスとを関連付けて記憶すると共に前記変更画面からユーザの変更が入力されたことに応じて記憶内容を更新するユーザ情報記憶手段と、前記情報の変更種別に応じた定型文書を格納する定型文書格納手段と、前記変更画面から所定のプロジェクトに関する情報の変更が入力されたとき当該変更に応じた配信文書を前記定型文書格納手段に格納された定型文書に基づいて作成する配信文書作成手段と、前記変更画面から所定のプロジェクトに関する情報の変更が入力されたとき当該プロジェクトに関するユーザの配信先アドレスを前記ユーザ情報記憶手段の記憶情報に基づいて決定し、当該配信先アドレスに対して前記配信文書作成手段によって作成された配信文書を配信する文書配信手段とを有することを特徴とする。
【0012】
本願請求項2の発明に係るプロジェクト情報管理装置は、前記変更画面提供手段は、変更対象とする情報の種別に応じた変更画面を提供することを特徴とする。
【0013】
本願請求項3の発明に係るプロジェクト情報管理装置は、前記変更画面提供手段は、前記プロジェクトに関する文書情報の変更を入力するための画面を提供することを特徴とする。
【0014】
本願請求項4の発明に係るプロジェクト情報管理装置は、前記変更画面提供手段は、前記プロジェクトに関する日程情報の変更を入力するための画面を提供することを特徴とする。
【0015】
本願請求項5の発明に係るプロジェクト情報管理装置は、前記変更画面提供手段は、前記プロジェクトに関する現況情報の変更を入力するための画面を提供することを特徴とする。
【0016】
本願請求項6の発明に係るプロジェクト情報管理装置は、前記変更画面提供手段は、前記プロジェクトに関するユーザ情報の変更を入力するための画面を提供することを特徴とする。
【0017】
本願請求項7の発明に係るプロジェクト情報管理装置は、前記文書配信手段は、前記配信文書作成手段によって作成された配信文書を格納する配信文書格納手段を備え、前記変更画面から変更の完了が入力されるまでは、当該情報に関してそれまでに作成された配信文書を前記配信文書格納手段に格納し、前記変更画面から変更の完了が入力されたことに応じて、前記配信文書格納手段に格納された文書を配信することを特徴とする。
【0018】
本願請求項8の発明に係るプロジェクト情報管理装置は、前記文書配信手段は、プロジェクトを構成するユーザのみを配信先とするか、プロジェクトを構成しないユーザをも含めて配信先とするかを前記情報の変更内容に関連付けて記憶する区分記憶手段をさらに有し、前記情報の変更が入力されたとき、当該区分記憶手段の記憶内容に基づいて、配信先ユーザを決定することを特徴とする。
【0019】
本願請求項9の発明は、コンピュータを請求項1乃至8のいずれかに記載のプロジェクト情報管理装置として機能させるためのプログラムである。
【0020】
尚、本願請求項1乃至8に記載の変更とは、本来の変更の意味だけでなく、削除及び追加等の意味も広く含むものである。
【0021】
本発明の特徴は、以下に示す実施の形態の説明により更に明らかとなろう。
【0022】
但し、以下に示す実施の形態はあくまでも本発明のひとつの実施の形態であって、本発明に係る各構成要件の用語の意義は以下の実施の形態に記載されたものに制限されるものではない。
【0023】
【発明の実施の形態】
図1は、本発明の一実施形態であるプロジェクト管理サーバを利用したのプロジェクト管理サーバシステムの構成図である。
プロジェクト管理サーバ100では、後述するプロジェクト管理プログラムが実行され、複数のプロジェクト情報が管理される。
【0024】
プロジェクト管理サーバ100にアクセスするユーザは、ユーザ端末300からネットワークを経由して、プロジェクト管理サーバ100にアクセスすることにより、ユーザ端末300に所望のプロジェクトに関する情報を表示し、或いはユーザ端末300からプロジェクトに関する情報の編集を行なうことができる。
【0025】
図2は、本発明の一実施形態であるプロジェクト管理サーバ100の構成図である。
【0026】
図2を参照して、プロジェクト管理サーバ100は、記憶装置101、CPU102、入力装置103、および表示装置104からなる。
【0027】
記憶装置101は、後述する機能を実行するためのプロジェクト管理プログラムを格納すると共に、この機能を実行する際に参照される各種テーブル等を格納する。CPU102は、記憶装置101に格納された当該プロジェクト管理プログラムに従って処理を実行する。入力装置103は、ユーザが、プロジェクト管理プログラムの実行に当たって必要な情報を入力する際に使用される。表示装置104は、CPU102によるプロジェクト管理プログラムの実行結果が表示される。
【0028】
図3は、プロジェクト管理サーバの機能別の構成図である。
【0029】
プロジェクト管理サーバ100は、マイポータル画面処理部201、プロジェクトポータル画面処理部202、文書情報操作画面処理部203、文書情報処理部204、文書情報管理部205、文書管理情報テーブル206、文書情報テーブル207、日程情報操作画面処理部208、日程情報処理部209、日程情報管理部210、日程管理情報テーブル211、プロジェクト情報操作画面処理部212、プロジェクト情報処理部213、プロジェクト情報管理部214、プロジェクト管理情報テーブル215、ユーザ情報操作画面処理部216、ユーザ情報処理部217、ユーザ情報管理部218、ユーザ管理情報テーブル219、プロジェクト状態通知処理部220、コマンド管理情報テーブル221、文書格納手段222を含む。
【0030】
マイポータル画面処理部201は、ユーザがユーザ端末300からネットワーク経由でプロジェクト管理サーバ100にログインしたときに、プロジェクト管理サーバ100を利用するためのユーザインターフェース画面(以下、マイポータル画面と記載する。)をユーザ端末300に表示させる。
【0031】
図4を参照して、マイポータル画面上には、ログインユーザが担当する全てのプロジェクト及びそれらに関する情報が表示される(図4の担当プロジェクトリストを参照。)。ログインユーザは、マイポータル画面上のプロジェクトポータルアイコン、プロジェクト管理アイコン、又はユーザ管理アイコンを選択することにより、それぞれ後述するプロジェクトポータル画面処理部202、プロジェクト情報操作画面処理部212、又はユーザ情報画面処理部216が表示する画面に移行することができる。
【0032】
また、マイポータル画面上には、後述するプロジェクト状態通知処理部220からログインユーザに配信された状態変化通知も表示される(図4の更新通知一覧を参照。)。
【0033】
ここで、状態変化通知とは、プロジェクト管理プログラム200が管理している文書情報、日程情報、プロジェクト情報、及びユーザ情報が、他のユーザ又は本人によって変更、追加、または削除された場合に、後述するプロジェクト状態通知処理部220から配信される、当該変更、追加、または削除に関する通知をいう。
【0034】
マイポータル画面上の更新通知一覧には、プロジェクト情報のうち、プロジェクトの変更、追加、または削除があった場合、又はユーザ情報のうち、ユーザの変更、追加、または削除があった場合の状態変化通知が表示される。
【0035】
ログインユーザは、この通知により、プロジェクト情報およびユーザ情報についての変更、追加、または削除を認識することができる。
【0036】
プロジェクトポータル画面処理部202は、ログインユーザに対してログインユーザが選択したプロジェクトに対応する後述の文書情報操作画面処理部203及び日程情報操作画面処理部208が表示する画面へ移行するためのユーザインターフェース画面(以下プロジェクトポータル画面と記載する。)を表示する。
【0037】
即ち、図4のマイポータル画面上の担当プロジェクトから、例えば、プロジェクト「1UR***1」を選択すると、プロジェクトポータル画面処理部202は、図5に示す如く、プロジェクト「1UR***1」についてのプロジェクトポータル画面を表示する。
【0038】
図5を参照して、プロジェクト「1UR***1」についてのプロジェクトポータル画面上には、プロジェクト「1UR***1」を担当する複数のメンバーからなるグループの一覧(図5のメンバリストを参照。)が表示される。
【0039】
また、ログインユーザは、図5のプロジェクトポータル画面上の文書管理アイコンを選択することにより、文書情報操作画面処理部203が表示する画面に移行でき、日程管理アイコンを選択することにより日程情報操作画面処理部209が表示する画面に移行することができる。
【0040】
また、プロジェクトポータル画面上には、後述するプロジェクト状態通知処理部220から配信された状態変化通知のうち、ログインユーザが担当するプロジェクトに関する文書情報、日程情報についての変更、追加、または削除があった場合の状態変化通知が表示される(図5の更新通知一覧を参照。)。
【0041】
ログインユーザは、この通知により、自己が担当するプロジェクトについて文書情報及び日程情報の変更、追加、または削除があったことを認識することができる。
【0042】
文書情報操作画面処理部203は、ログインユーザに対しそのプロジェクトに関して作成された文書の一覧を示す画面(以下、文書情報画面と記載する。)を表示する。
【0043】
図6を参照して、ログインユーザは、文書情報画面から、文書の削除、変更、コピー、移動、または新規文書の作成といった文書情報を入力することが可能となる。
【0044】
即ち、ログインユーザは、図6のドキュメントツリーから一の文書を選択し、続いて、ファイル削除アイコン、ファイル変更アイコン、ファイルコピーアイコン、またはファイル移動アイコンを選択することにより、文書の削除、変更、コピー、または移動を行なうことができる。また、ファイル登録アイコンを選択することにより、新規文書の作成が可能となる。ファイル変更アイコン又はファイル登録アイコンを選択した場合は、文書の変更、または新規文書作成の画面(図示せず。)に移行する。ログインユーザが、それぞれの画面において、文書の変更、新規文書の作成を行った後、各画面上で完了アイコン(図示せず。)を選択することにより、それぞれの処理が完了し、再び文書情報画面に戻る。
【0045】
文書情報操作画面処理部203は、文書情報画面から文書情報の入力があると、当該文書情報を文書情報処理部204に出力する。
【0046】
文書情報処理部204は、文書情報操作画面処理部203から文書情報の入力があると、後述する文書情報管理部205よりこの文書情報に対応する文書を取得し、文書情報操作画面処理部203へ渡す。文書情報操作画面処理部203はログインユーザに対しその編集画面を表示する。上記文書情報が新規作成の場合には、新規文書の編集画面を表示させる。
【0047】
また、文書情報処理部204は、ログインユーザからの文書情報入力があると、削除、変更、コピー、移動、又は新規作成された文書のタイトルおよび当該文書が関連するプロジェクトの名前と共に文書情報入力があったことを示すコマンドを後述するプロジェクト情報通知処理部220へ通知する。
【0048】
文書情報管理部205は、文書情報処理部204からの文書情報に対応する文文書管理情報を後述する文書管理情報テーブル206から抽出すると共に、この文書管理情報に対応する文書を後述する文書情報テーブル207から抽出し文書情報処理部205へ渡す。
【0049】
文書管理情報テーブル206は、文書管理のための文書管理情報が蓄積されており、文書情報テーブル207には、文書管理情報に対応する文書が蓄積されている。
【0050】
日程情報操作画面処理部208は、ログインユーザに対し担当するプロジェクトの日程を構成するイベントのスケジュール画面(以下、スケジュール画面と記載する。)を表示する。ここで、プロジェクトの日程は、異なる複数の作業から構成されており、イベントとはプロジェクトを構成する作業をいう。
【0051】
図7を参照して、ログインユーザは、スケジュール画面から、イベントの削除、変更、担当するイベントの予定日の編集、またはイベント追加といったイベント情報を入力することが可能となる。
【0052】
即ち、ログインユーザは、スケジュール画面から、一のイベントを選択し、続いてイベント削除アイコン、イベント変更アイコン、または予定日編集アイコンを選択することにより、イベントの削除、変更、またはイベントの予定日の編集ができる。また、イベント追加アイコンを選択した場合は、イベント追加が可能となる。イベント変更アイコン、イベント追加アイコン、又は予定日編集アイコンを選択した場合は、イベント変更、イベント追加、又はイベントの予定日編集の画面(図示せず。)に移行する。ログインユーザが、それぞれの画面において、イベントの変更、イベントの追加、又はイベントの予定日の編集を行った後、各画面上で完了アイコン(図示せず。)を選択することにより、それぞれの処理が完了し、再びスケジュール画面に戻る。最後に、スケジュール画面上で、イベント編集終了アイコンを選択することにより、イベント情報の入力が終了する。
【0053】
日程情報処理部209は、スケジュール画面において、ログインユーザから日程情報が入力されると、後述する日程情報管理部209へ、入力された日程情報を出力すると共に、後述するプロジェクト状態通知処理部220へ、日程情報が入力されたことを示すコマンド、及びそのイベント名を通知する。イベントの予定日が変更された場合には、各メンバーの注意を喚起するために、変更後の日程ではなく、各メンバーに認識されていた変更前の日程が通知される。
【0054】
日程情報管理部210は、入力された日程情報に基づいて、後述する日程管理情報テーブル211に格納されている日程管理情報を更新する。
【0055】
プロジェクト情報操作画面処理部212は、ログインユーザに対し新規プロジェクトの作成、既存プロジェクトの削除又は変更を行なうためのユーザインターフェース画面(以下、プロジェクト情報画面と記載する。)を表示する。
【0056】
図8を参照して、ログインユーザは、プロジェクト情報画面から、プロジェクトの削除、変更、又はプロジェクトの登録といったプロジェクト情報を入力することが可能となる。
【0057】
即ち、ログインユーザは、プロジェクト情報画面から、一のプロジェクトを選択し、続いてプロジェクト削除アイコン、プロジェクト変更アイコンを選択することにより、プロジェクトの削除、または変更が行える。プロジェクト登録アイコンを選択した場合は、プロジェクトの登録が可能となる。プロジェクト変更アイコン、またはプロジェクト登録アイコンを選択すると、プロジェクトの変更、またはプロジェクト登録の画面(図示せず。)に移行する。ログインユーザが、それぞれの画面において、プロジェクトの変更、又はプロジェクトの登録を行った後、各画面上で完了アイコン(図示せず。)を選択することにより、それぞれの処理が完了し、再びプロジェクト情報画面に戻る。
【0058】
プロジェクト情報処理部213は、プロジェクト情報操作画面処理部212よりプロジェクト情報が入力されると、後述するプロジェクト情報管理部214に、そのプロジェクト情報を出力すると共に、後述するプロジェクト状態通知処理部220へプロジェクト情報が入力されたことを示すコマンドとともに、変更、追加、または削除があったプロジェクト名を通知する。
【0059】
プロジェクト情報管理部214は、後述するプロジェクト管理情報テーブル215にアクセスし、入力されたプロジェクト情報に基づいてプロジェクト管理情報を更新する。
【0060】
また、プロジェクト情報管理部214は、プロジェクトにメンバが追加されると、そのメンバーに対し、そのプロジェクトについてのプロジェクトポータル画面処理部202へのアカウントを割り当てる。例えば、プロジェクト「1UR***1」にメンバーAが追加されると、メンバーAには、プロジェクト「1UR***1」についてのプロジェクト画面処理部202へのアカウントとして“メンバA@1UR***1.COM”が割り当てられる。
【0061】
プロジェクト管理情報テーブル215には、図10に示す如く、プロジェクト管理プログラム上で管理されている全プロジェクト、各プロジェクトを担当するメンバー、及び各メンバーのプロジェクトポータル画面処理部202の各メンバーが担当するプロジェクトへのアカウントが格納されている。
【0062】
ユーザ情報操作画面処理部216は、ログインユーザに対しユーザ情報の更新を行うためのユーザインターフェース画面(以下、ユーザ情報画面と記載する。)を表示する。図9を参照して、ログインユーザは、ユーザ情報画面から、ユーザの削除、変更、又は登録といったユーザ情報を入力することが可能となる。
【0063】
即ち、ログインユーザは、ユーザ情報画面から、一のユーザを選択し、続いてユーザ削除アイコン、ユーザ変更アイコンを選択することにより、ユーザの削除、変更ができる。ユーザ登録アイコンを選択した場合は、ユーザ登録が可能となる。
【0064】
ユーザ変更アイコン、またはユーザ登録アイコンを選択した場合は、ユーザ変更、またはユーザ登録の画面(図示せず。)に移行する。ログインユーザが、それぞれの画面において、ユーザの変更、又はユーザの登録を行った後、各画面上で完了アイコン(図示せず。)を選択することにより、それぞれの処理が完了し、再びユーザ情報画面に戻る。
【0065】
ユーザ情報処理部217は、ユーザ情報操作画面処理部216からユーザ情報が入力されると、後述するユーザ情報処理部217に、そのユーザ情報を出力すると共に、後述するプロジェクト状態通知処理部220へユーザ情報が入力されたことを示すコマンドと共に変更、削除、または登録されたユーザ名を通知する。
【0066】
ユーザ情報管理部218は、後述するユーザ管理情報テーブル219にアクセスし、入力された情報に基づいてユーザ管理情報を更新する。
【0067】
また、ユーザ情報管理部218は、ユーザが登録されると、各ユーザに対してマイポータル画面処理部201へのアカウントを割り当てる。
【0068】
ユーザ管理情報テーブル219は、図11に示す如く、プロジェクト管理プログラムに登録されている全ユーザのマイポータル画面処理部201へのアカウントが格納されている。
【0069】
プロジェクト状態通知処理部220では、文書情報処理部204、日程情報処理部209、プロジェクト情報処理部213、およびユーザ情報処理部217から通知されるコマンド、および各コマンドに付随して通知される情報に基づき、コマンド管理情報テーブル221を参照して適切な文書を作成し、プロジェクト管理情報テーブル215、及びユーザ管理情報テーブル219を参照して配信すべきユーザを決定し、配信すべきユーザのプロジェクトポータル画面、又はマイポータル画面に作成した文書を配信する。
【0070】
文書格納手段222は、プロジェクト状態通知処理部220が作成する配信文書を格納する記憶手段である。
【0071】
コマンド管理情報テーブル221は、図12に示すように構成されている。図12を参照して、コマンド名の欄には、文書情報処理部204、日程情報処理部209、プロジェクト情報処理部213、またはユーザ情報処理部217からプロジェクト状態通知処理部220に通知されるコマンドが記載されている。
【0072】
通知タイプの欄には、“単発”又は“蓄積”が記載され、完了コマンドの欄には、“F”又は“T”が記載されている。
【0073】
通知タイプが“単発”とは、そのコマンドが通知される毎に文書配信が行なわれることを示している。他方、通知タイプが“蓄積”とは、そのコマンドが複数回通知されても、そのコマンドの完了コマンドが“F”である場合には、文書配信は行なわれず、通知タイプが“蓄積” かつ完了コマンドが“T”であるコマンドが通知された場合に、それまで配信されずに蓄積されていた文書と併せた文書が作成され、配信が行われる。
【0074】
配信画面の欄は、“マイポータル画面”又は“プロジェクトポータル画面”が記載されており、マイポータル画面かプロジェクトポータル画面のどちらに配信するかを示している。
【0075】
文面の欄は、コマンドに対応した適切な文書の雛形が記載されており、プロジェクト状態通知処理部220が、コマンドと共に通知されるファイル名、予定日、イベント名、プロジェクト名等を組み込んで文書を完成し、配信する。
【0076】
例えば、プロジェクト管理サーバの管理者が、ユーザ情報画面(図9を参照。)から“メンバZ”のユーザ登録処理を行うと、ユーザ情報処理部217は、“ユーザ追加”コマンドとユーザ名“メンバZ”をプロジェクト状態通知処理部220に通知する。
【0077】
プロジェクト状態通知処理部220は、“ユーザ追加”を受けると、コマンド管理テーブル221を検索する。図12のコマンド管理テーブル221を参照して、プロジェクト状態通知処理部220は、“ユーザ追加”コマンドを検出し、その文面より、「ユーザメンバZを追加」を作成し、一旦文書格納手段222に格納する。“ユーザ追加”コマンドは、配信タイプが“単発”であるから文書格納手段222に格納された文面を配信したのち、文書格納手段222からは当該文面を削除する。また、配信画面が“マイポータル”であるから、ユーザ管理情報テーブル219に登録されている全ユーザのマイポータル画面処理部201へのアカウントを検出し、このアカウントに文面「ユーザメンバZを追加」を配信する。
【0078】
この結果、プロジェクト管理サーバ100に登録されている全ユーザのマイポータル画面の更新通知一覧(図4を参照。)に“ユーザ「メンバZ」を追加”が通知される。
【0079】
また、例えば、ログインユーザであるメンバーAが、図7に示すスケジュール画面から、担当するプロジェクト「1UR***1」のイベント「設計」を選択し、イベント変更アイコンを選択すると、イベント変更画面(図示せず。)に移行する。メンバーAが、イベント変更画面でイベントの変更を行い、完了アイコン(図示せず。)を選択することによりイベントの変更を完了すると、日程情報処理部209は、“イベント変更”コマンドとプロジェクト名「1UR***1」とイベント名「設計」をプロジェクト状態通知処理部220に通知する。
【0080】
プロジェクト状態通知処理部220は、“イベント変更”を受けると、コマンド管理テーブル221を検索する。図12のコマンド管理テーブル221を参照して、プロジェクト状態通知処理部220は、“イベント変更”を検出し、その文面より、「イベント設計を変更」を作成し、一旦文書格納手段222に格納する。“イベント変更”コマンドは、配信タイプが“蓄積”であり、完了コマンドが“F”であるから文書格納手段222に格納された文面を配信せずに、蓄積する。続いて、メンバーAが、更に、図7のスケジュール画面から、イベント「製造」の変更を行なった場合についても同様に、「イベント製造を変更」を作成し、配信タイプが“蓄積”であり完了コマンドが“F”であるから配信せずに、文書格納手段222に蓄積する。
【0081】
最後に、メンバーAが、図7のスケジュール画面から、イベント編集終了アイコンを選択することにより一連のイベントの変更を終了すると、日程情報処理部209は、“日程編集終了”コマンドとプロジェクト名「1UR***1」をプロジェクト状態通知処理部220に通知する。
【0082】
プロジェクト状態通知処理部220は、“日程編集終了”を受けると、同様の操作を行ない、図12に示すコマンド管理テーブル221を参照して、文面「イベントを変更しました」を作成し、一旦、文書格納手段222に格納する。また、“日程編集終了”コマンドは、配信タイプが“蓄積”であり、完了コマンドが“T”であるから、文書格納手段222に蓄積されている文面、「イベント設計を変更」、および「イベント製造を変更」とともに「イベントを変更しました」を1つの文面として配信し、文書格納手段222からこれらの文面を削除する。
【0083】
ここで、これらのコマンド配信画面は、“プロジェクトポータル”であるから、プロジェクト状態通知処理部220は、プロジェクト管理情報テーブル215から、プロジェクト「1UR***1」の担当メンバーのプロジェクト「1UR***1」についてのプロジェクトポータル画面処理部202へのアカウントを検出し、このアカウントに作成した文面を配信する。
【0084】
この結果、プロジェクト管理サーバ100が管理しているプロジェクト「1UR***1」を担当する全メンバーのプロジェクト「1UR***1」についてのプロジェクトポータル画面の更新通知一覧(図5を参照。)に“イベントを変更しました。”が通知される。「1UR***1」を担当する全メンバーは、プロジェクトポータル画面の更新通知一覧(図5を参照。)のタイトル“イベントを変更しました。”を選択し、文面を参照することができる。
【0085】
次に、プロジェクト状態通知処理部220による文書配信フローを図13に基づいて説明する。
【0086】
図13を参照して、ステップS100では、文書格納手段222の内容をリセットし、ステップS101へ進む。
【0087】
ステップS101では、文書情報処理部204、日程情報処理部209、プロジェクト情報処理部213、またはユーザ情報処理部217からのコマンド通知があるかどうかを判定し、コマンド通知があれば、ステップS102へ進む。
【0088】
ステップS102では、プロジェクト状態通知処理部220は、コマンド管理情報テーブル221を参照して、通知されたコマンドの配信タイプが“単発”かどうかを判定し、“単発”であれば、ステップS107へ進み、そうでなければ、ステップS103へ進む。
【0089】
ステップS103では、蓄積フラグがONとなっているかどうかを判定する。蓄積フラグとは、通知されたコマンドに対する文書を配信するか、それとも配信せずに蓄積するかを示すフラグである。蓄積フラグがONであれば、ステップS105へ進み、そうでなければ、S104へ進む。
【0090】
ステップS104では、蓄積フラグをONとし、ステップS107へ進む。
【0091】
ステップS105では、コマンド管理情報テーブル221を参照して、通知されたコマンドの完了コマンドが“T”であるか“F”であるかを判定する。完了コマンドが“T”であれば、ステップS106へ進み、蓄積フラグをOFFとし、ステップS108へ進む。完了コマンドが“F”であれば、ステップS107へ進む。
【0092】
ステップS107では、通知されたコマンドの文面欄の文面の雛型に、操作が行なわれた対象である、プロジェクト名、文書のファイル名、イベント名、ユーザ名、又は変更前のイベントの予定日を組み込みんで、文面を完成させ、文書格納手段222に蓄積し、ステップS108に進む。
【0093】
ステップS108では、蓄積フラグがONであるかどうかを判定し、ONであれば、文書の配信を行なわず、ステップS101へ戻る。OFFであれば、ステップS109へ進む。
【0094】
ステップS109では、文書の配信先がマイポータル画面であるかどうかを判定し、マイポータル画面であれば、ステップS111へ進み、そうでなければ、ステップS110へ進む。配信先の判定は、コマンド管理情報テーブル221を参照して、通知されたコマンドに対応する配信画面欄に“マイポータル”と記載されていれば、配信先は、全ユーザのマイポータル画面であると判定し、“プロジェクトポータル”と記載されていれば、コマンドと共に通知されるプロジェクト名のプロジェクトを担当する全メンバーのそのプロジェクトについてのプロジェクトポータル画面であると判定する。
【0095】
ステップS110では、プロジェクト管理情報テーブル215を参照し、当該プロジェクトの担当メンバー全員のそのプロジェクトについてのプロジェクトポータルのアカウントを検出し、配信アドレスリストを作成し、ステップS112へ進む。
【0096】
ステップS111では、ユーザ管理情報テーブル219を参照し、登録されている全ユーザのマイポータルのアカウントを検出し、配信アドレスリストを作成し、ステップS112へ進む。
【0097】
ステップS112では、作成したアドレスリストのアドレスに、文書格納手段222に格納された文書を配信し、ステップS100へ戻る。
【0098】
以上の説明からわかるように、プロジェクト状態通知処理部220は、文書情報処理部204、日程情報処理部209、プロジェクト情報処理部213またはユーザ情報処理部217からコマンド通知があると、コマンド管理情報テーブル221を参照し、コマンドに応じて適切な文書を作成する。さらに、プロジェクト状態通知処理部220は、通知されたコマンドから、コマンドに関するプロジェクトのメンバーに文書を配信するか、それとも登録されているユーザ全員に配信するかを判定し、プロジェクト管理情報テーブル215およびユーザ管理情報テーブル219を参照し、配信すべきアドレスリストを作成し、作成した文書を該アドレスリストのアドレスに配信する。
【0099】
このような構成とすることにより、ログインユーザは、自己の担当するプロジェクトに関する文書情報や日程情報について変更、追加又は削除等があった場合、あるいは、プロジェクトや登録ユーザについて変更、追加又は削除等があった場合にでも、プロジェクト管理プログラムにログインするだけでそれらの情報の変更を知ることができる。
【0100】
他方、上記したようなプロジェクトに関する情報の変更、削除又は追加等を行なったログインユーザは、配信文書を作成し、情報の変更等の後に、膨大な数の登録ユーザの中から配信しなければならないユーザを特定し、文書を配信するというわずらわしい作業から開放されることになる。
【0101】
尚、本発明の実施の形態は、本発明の技術的思想の範囲内において、適宜、種々の変更が可能である。
【0102】
【発明の効果】
本発明によれば、プロジェクトに関する全ての情報を管理し、管理されている情報を変更するあらゆる操作があった場合に、その操作による情報の変更を示す定型文書を作成し、変更のあった情報に関係するユーザを特定し、そのユーザに対してこの定型文書を通知することができるプロジェクト情報管理装置を提供することができる。
【図面の簡単な説明】
【図1】実施の形態に係るプロジェクト管理システムの構成を示す図である。
【図2】実施の形態に係るプロジェクト管理サーバの構成を示す図である。
【図3】実施の形態に係るプロジェクト管理サーバの機能別の構成を示す図である。
【図4】表示装置104がログインユーザに表示するマイポータル画面の表示例である。
【図5】表示装置104がログインユーザに表示するプロジェクトポータル画面の表示例である。
【図6】表示装置104がログインユーザに表示する文書情報画面の表示例である。
【図7】表示装置104がログインユーザに表示するスケジュール設定画面の表示例である。
【図8】表示装置104がログインユーザに表示するプロジェクト設定画面の表示例である。
【図9】表示装置104がログインユーザに表示するユーザ設定画面の表示例である。
【図10】プロジェクト管理情報テーブル215のデータ構造である。
【図11】ユーザ管理情報テーブル219のデータ構造である。
【図12】コマンド管理テーブル221のデータ構造である。
【図13】実施の形態に係るフローチャートを示す図である。
【符号の説明】
200・・・プロジェクト管理プログラム
201・・・マイポータル画面処理部
202・・・プロジェクトポータル画面処理部
203・・・文書情報操作画面処理部
204・・・文書情報処理部
208・・・日程情報操作画面処理部
209・・・日程情報処理部
212・・・プロジェクト情報操作画面処理部
213・・・プロジェクト情報処理部
216・・・ユーザ情報操作画面処理部
217・・・ユーザ情報処理部
220・・・プロジェクト状態通知処理部
221・・・コマンド管理情報テーブル
[0001]
[Industrial applications]
The present invention relates to a project information management apparatus, and in particular, when a change occurs in information managed by the project information management apparatus, automatically changes details of the information to a user or a project involved in the project. The present invention relates to a project information management device for notifying a user who does not have any information.
[0002]
[Prior art]
Information sharing among members is extremely important for the smooth execution of project work. Conventional project information management devices use file sharing and e-mail on computer networks as a means for information sharing among members. Was used.
[0003]
However, in a project in which the shared information is frequently updated, a notification to that effect may be required when the shared information is updated. In such a case, the above-described file sharing and e-mail alone are not sufficient, and for example, the following problems have occurred.
[0004]
(1) When an information update notification is issued, e-mail or the like can be used. However, as the number of project members increases, it takes time and effort to select a user to be notified. To make matters worse, an appropriate user is not notified in a timely manner unless a distribution list is updated strictly according to a member change.
[0005]
(2) The text for notifying the information update must be prepared by the member who has changed the information, but if the text format is not strictly standardized, the level of the notification content varies depending on the user, There is a difference in the level at which changes are recognized.
[0006]
{Circle around (3)} If a project is not strictly enforced as to which update notification is issued to which information, there is a possibility that omission of communication will occur.
[0007]
In order to solve the above problems, there has been a demand for a mechanism for updating shared information of a project at an appropriate timing to an appropriate member with appropriate contents.
[0008]
Incidentally, in addition to the above, a technology relating to the project information management device is disclosed in Patent Document 1 below.
[0009]
[Patent Document 1] Japanese Patent No. 2956667
[0010]
[Problems to be solved by the invention]
Therefore, in view of the above problems, a main object of the present invention is to manage all information related to a project, and when there is any operation to change the managed information, a fixed form indicating the change of information by the operation. An object of the present invention is to provide a project information management device that creates a document, specifies a member related to changed information, and notifies the member of the fixed document.
[0011]
[Means for Solving the Problems]
The project information management device according to the first aspect of the present invention is a project information management device that manages information relating to one or more projects, a change screen providing unit that provides a screen for changing the information, A user information storage unit for storing a user to be configured and a delivery destination address of the user in association with each other and updating the storage content in response to a user change being input from the change screen; A fixed form document storing means for storing the fixed form document, and when a change of information relating to a predetermined project is input from the change screen, a delivery document corresponding to the change is based on the fixed form document stored in the fixed form document storing means. A delivery document creation unit to be created, and a change in information on a predetermined project is input from the change screen. A document distribution unit that determines a delivery destination address of a user related to the project based on the storage information of the user information storage unit, and distributes a delivery document created by the delivery document creation unit to the delivery destination address. It is characterized by the following.
[0012]
The project information management device according to the invention of claim 2 is characterized in that the change screen providing means provides a change screen according to the type of information to be changed.
[0013]
The project information management device according to a third aspect of the present invention is characterized in that the change screen providing means provides a screen for inputting a change in document information on the project.
[0014]
A project information management apparatus according to a fourth aspect of the invention is characterized in that the change screen providing means provides a screen for inputting a change in schedule information on the project.
[0015]
The project information management device according to the invention of claim 5 of the present application is characterized in that the change screen providing means provides a screen for inputting a change of current status information on the project.
[0016]
The project information management device according to the invention of claim 6 of the present application is characterized in that the change screen providing means provides a screen for inputting a change of user information on the project.
[0017]
In the project information management device according to the invention of claim 7, the document distribution unit includes a distribution document storage unit that stores the distribution document created by the distribution document creation unit, and completion of the change is input from the change screen. Until this is done, the distribution document created so far with respect to the information is stored in the distribution document storage unit, and stored in the distribution document storage unit in response to the completion of the change being input from the change screen. And delivering the document.
[0018]
The project information management device according to the invention of claim 8 is characterized in that the document distribution unit determines whether only a user who configures a project is a distribution destination or a distribution destination including users who do not configure a project. The storage device further includes a division storage unit that stores the information in association with the contents of the change, and when a change of the information is input, a distribution destination user is determined based on the storage contents of the division storage unit.
[0019]
A ninth aspect of the present invention is a program for causing a computer to function as the project information management device according to any one of the first to eighth aspects.
[0020]
The changes described in claims 1 to 8 of the present application broadly include not only the meaning of the original change but also the meaning of deletion and addition.
[0021]
The features of the present invention will become more apparent from the following description of embodiments.
[0022]
However, the embodiment described below is merely one embodiment of the present invention, and the meaning of the terms of the respective constituent elements according to the present invention is not limited to those described in the following embodiment. Absent.
[0023]
BEST MODE FOR CARRYING OUT THE INVENTION
FIG. 1 is a configuration diagram of a project management server system using a project management server according to an embodiment of the present invention.
In the project management server 100, a project management program described later is executed to manage a plurality of pieces of project information.
[0024]
A user accessing the project management server 100 accesses the project management server 100 from the user terminal 300 via a network, thereby displaying information on a desired project on the user terminal 300 or from the user terminal 300 regarding the project. Edit information.
[0025]
FIG. 2 is a configuration diagram of the project management server 100 according to one embodiment of the present invention.
[0026]
Referring to FIG. 2, project management server 100 includes storage device 101, CPU 102, input device 103, and display device 104.
[0027]
The storage device 101 stores a project management program for executing a function described later, and also stores various tables and the like that are referred to when executing this function. The CPU 102 executes processing according to the project management program stored in the storage device 101. The input device 103 is used when the user inputs information necessary for executing the project management program. The display device 104 displays the execution result of the project management program by the CPU 102.
[0028]
FIG. 3 is a configuration diagram of each function of the project management server.
[0029]
The project management server 100 includes a my portal screen processing unit 201, a project portal screen processing unit 202, a document information operation screen processing unit 203, a document information processing unit 204, a document information management unit 205, a document management information table 206, and a document information table 207. Schedule information operation screen processing unit 208, schedule information processing unit 209, schedule information management unit 210, schedule management information table 211, project information operation screen processing unit 212, project information processing unit 213, project information management unit 214, project management information It includes a table 215, a user information operation screen processing unit 216, a user information processing unit 217, a user information management unit 218, a user management information table 219, a project status notification processing unit 220, a command management information table 221, and a document storage unit 222.
[0030]
The my portal screen processing unit 201 is a user interface screen for using the project management server 100 when a user logs in to the project management server 100 from the user terminal 300 via a network (hereinafter, referred to as a my portal screen). Is displayed on the user terminal 300.
[0031]
Referring to FIG. 4, on the My Portal screen, all the projects in which the login user is in charge and information on the projects are displayed (see the list of projects in charge in FIG. 4). The logged-in user selects a project portal icon, a project management icon, or a user management icon on the My Portal screen, and thereby a project portal screen processing unit 202, a project information operation screen processing unit 212, or a user information screen processing, which will be described later, respectively. The screen can be shifted to a screen displayed by the unit 216.
[0032]
In addition, a status change notification distributed to the login user from the project status notification processing unit 220 described later is also displayed on the My Portal screen (see the update notification list in FIG. 4).
[0033]
Here, the status change notification is described below when document information, schedule information, project information, and user information managed by the project management program 200 are changed, added, or deleted by another user or the user. The notification related to the change, addition, or deletion delivered from the project status notification processing unit 220.
[0034]
In the update notification list on the My Portal screen, the status change when there is a project change, addition, or deletion in the project information, or when the user changes, addition, or deletion in the user information A notification is displayed.
[0035]
The login user can recognize the change, addition, or deletion of the project information and the user information from the notification.
[0036]
The project portal screen processing unit 202 is a user interface for shifting to a screen displayed by a document information operation screen processing unit 203 and a schedule information operation screen processing unit 208 corresponding to a project selected by the login user for the login user. Display the screen (hereinafter referred to as the project portal screen).
[0037]
That is, when, for example, the project “1UR ** 1” is selected from the project in charge on the My Portal screen of FIG. 4, the project portal screen processing unit 202 selects the project “1UR ** 1” as shown in FIG. Display the project portal screen about.
[0038]
Referring to FIG. 5, on the project portal screen for project "1UR *** 1", a list of groups consisting of a plurality of members in charge of project "1UR *** 1" (member list in FIG. 5 is displayed). Reference) is displayed.
[0039]
Also, the login user can shift to the screen displayed by the document information operation screen processing unit 203 by selecting the document management icon on the project portal screen of FIG. 5, and can select the schedule information operation screen by selecting the schedule management icon. The screen can be shifted to a screen displayed by the processing unit 209.
[0040]
Also, on the project portal screen, among the status change notifications distributed from the project status notification processing unit 220 described later, there was a change, addition, or deletion of document information and schedule information on the project for which the login user is in charge. The status change notification in the case is displayed (see the update notification list in FIG. 5).
[0041]
The log-in user can recognize from the notification that the document information and the schedule information have been changed, added, or deleted for the project in charge of the user.
[0042]
The document information operation screen processing unit 203 displays a screen (hereinafter, referred to as a document information screen) showing a list of documents created for the project to the login user.
[0043]
Referring to FIG. 6, the login user can input document information such as deletion, change, copy, move, or creation of a new document from the document information screen.
[0044]
That is, the login user selects one document from the document tree of FIG. 6, and then selects a file delete icon, a file change icon, a file copy icon, or a file move icon to delete, change, or delete the document. You can copy or move. By selecting the file registration icon, a new document can be created. When the file change icon or the file registration icon is selected, the screen shifts to a document change or new document creation screen (not shown). After the login user changes a document and creates a new document on each screen, the user selects a completion icon (not shown) on each screen to complete each process and return to the document information. Return to the screen.
[0045]
When receiving document information from the document information screen, the document information operation screen processing unit 203 outputs the document information to the document information processing unit 204.
[0046]
When document information is input from the document information operation screen processing unit 203, the document information processing unit 204 acquires a document corresponding to the document information from a document information management unit 205 described later, and sends the document to the document information operation screen processing unit 203. hand over. The document information operation screen processing unit 203 displays the edit screen for the login user. If the document information is newly created, a new document edit screen is displayed.
[0047]
Further, when there is an input of document information from the log-in user, the document information processing unit 204 inputs the document information together with the title of the deleted, changed, copied, moved, or newly created document and the name of the project to which the document is related. A command indicating the presence is notified to a project information notification processing unit 220 described later.
[0048]
The document information management unit 205 extracts text document management information corresponding to the document information from the document information processing unit 204 from a document management information table 206 described later, and extracts a document corresponding to the document management information from a document information table described later. Extracted from 207 and passed to document information processing section 205.
[0049]
The document management information table 206 stores document management information for document management, and the document information table 207 stores documents corresponding to the document management information.
[0050]
The schedule information operation screen processing unit 208 displays a schedule screen (hereinafter, referred to as a schedule screen) of events constituting a schedule of a project to be assigned to the login user. Here, the project schedule includes a plurality of different tasks, and an event refers to a task that constitutes the project.
[0051]
Referring to FIG. 7, the log-in user can input event information such as deletion and change of an event, editing of a scheduled date of an event in charge, or addition of an event from the schedule screen.
[0052]
That is, the login user selects one event from the schedule screen, and then selects the event deletion icon, the event change icon, or the scheduled date edit icon to delete, change, or schedule the event. Can edit. When the event addition icon is selected, an event can be added. When the event change icon, the event addition icon, or the scheduled date editing icon is selected, the screen shifts to a screen (not shown) for changing the event, adding an event, or editing the scheduled date of the event. After the login user changes the event, adds the event, or edits the scheduled date of the event on each screen, the user selects the completion icon (not shown) on each screen to perform each processing. Is completed, and the screen returns to the schedule screen again. Finally, by selecting the event editing end icon on the schedule screen, the input of the event information ends.
[0053]
When schedule information is input from the login user on the schedule screen, the schedule information processing unit 209 outputs the input schedule information to the schedule information management unit 209 described below, and outputs the schedule information to the project state notification processing unit 220 described below. , A command indicating that the schedule information has been input, and the event name thereof. When the scheduled date of the event is changed, not the schedule after the change but the schedule before the change that has been recognized by each member is notified to draw the attention of each member.
[0054]
The schedule information management unit 210 updates the schedule management information stored in the schedule management information table 211 described below based on the input schedule information.
[0055]
The project information operation screen processing unit 212 displays a user interface screen (hereinafter, referred to as a project information screen) for creating a new project, deleting or changing an existing project for a login user.
[0056]
Referring to FIG. 8, the login user can input project information such as deleting, changing, or registering a project from the project information screen.
[0057]
That is, the login user can delete or change the project by selecting one project from the project information screen and then selecting the project deletion icon and the project change icon. When the project registration icon is selected, a project can be registered. When the project change icon or the project registration icon is selected, the screen shifts to a project change or project registration screen (not shown). After the login user changes a project or registers a project on each screen, the user selects a completion icon (not shown) on each screen to complete each process and return to the project information again. Return to the screen.
[0058]
When the project information is input from the project information operation screen processing unit 212, the project information processing unit 213 outputs the project information to the project information management unit 214, which will be described later, and sends the project information to the project status notification processing unit 220, which will be described later. Notifies the name of the project that has been changed, added, or deleted, with a command indicating that the information has been entered.
[0059]
The project information management unit 214 accesses a project management information table 215 described later, and updates the project management information based on the input project information.
[0060]
Further, when a member is added to the project, the project information management unit 214 assigns an account to the project portal screen processing unit 202 for the project to the member. For example, when the member A is added to the project “1UR *** 1”, the member A receives “Member A @ 1UR **” as an account to the project screen processing unit 202 for the project “1UR *** 1”. * 1.COM ”is assigned.
[0061]
As shown in FIG. 10, the project management information table 215 includes all projects managed on the project management program, members in charge of each project, and projects in charge of each member of the project portal screen processing unit 202 of each member. The account to which is stored.
[0062]
The user information operation screen processing unit 216 displays a user interface screen (hereinafter, referred to as a user information screen) for updating the user information for the login user. Referring to FIG. 9, the login user can input user information such as deletion, change, or registration of the user from the user information screen.
[0063]
That is, the login user can delete or change the user by selecting one user from the user information screen and then selecting the user deletion icon and the user change icon. When the user registration icon is selected, user registration becomes possible.
[0064]
When the user change icon or the user registration icon is selected, the screen shifts to a user change or user registration screen (not shown). After the login user changes the user or registers the user on each screen, the user selects the completion icon (not shown) on each screen, thereby completing the respective processing and returning to the user information. Return to the screen.
[0065]
When the user information is input from the user information operation screen processing unit 216, the user information processing unit 217 outputs the user information to the user information processing unit 217 described later, and sends the user information to the project status notification processing unit 220 described later. Notify the user name that has been changed, deleted, or registered along with a command indicating that the information has been input.
[0066]
The user information management unit 218 accesses a user management information table 219 described later and updates the user management information based on the input information.
[0067]
When the user is registered, the user information management unit 218 assigns an account to the my portal screen processing unit 201 to each user.
[0068]
As shown in FIG. 11, the user management information table 219 stores accounts of all users registered in the project management program to the my portal screen processing unit 201.
[0069]
The project status notification processing unit 220 includes commands notified from the document information processing unit 204, the schedule information processing unit 209, the project information processing unit 213, and the user information processing unit 217, and information notified along with each command. Based on the command management information table 221, an appropriate document is created, the project management information table 215 and the user management information table 219 are used to determine a user to be delivered, and a project portal screen of the user to be delivered Or deliver the created document to the My Portal screen.
[0070]
The document storage unit 222 is a storage unit that stores a distribution document created by the project status notification processing unit 220.
[0071]
The command management information table 221 is configured as shown in FIG. Referring to FIG. 12, the command name column includes commands notified from document information processing unit 204, schedule information processing unit 209, project information processing unit 213, or user information processing unit 217 to project status notification processing unit 220. Is described.
[0072]
"Single" or "accumulation" is described in the notification type column, and "F" or "T" is described in the completion command column.
[0073]
The notification type “single shot” indicates that document distribution is performed each time the command is notified. On the other hand, when the notification type is “accumulate”, even if the command is notified a plurality of times, if the completion command of the command is “F”, document distribution is not performed, and the notification type is “accumulate” and the When a command whose command is “T” is notified, a document is created together with a document that has not been distributed and has been accumulated, and is distributed.
[0074]
The column of the distribution screen describes “My Portal Screen” or “Project Portal Screen”, and indicates whether to distribute to the My Portal Screen or the Project Portal Screen.
[0075]
In the text field, a template of an appropriate document corresponding to the command is described. The project status notification processing unit 220 incorporates the file name, scheduled date, event name, project name, etc. notified together with the command into a document. Complete and deliver.
[0076]
For example, when the administrator of the project management server performs a user registration process for “member Z” from the user information screen (see FIG. 9), the user information processing unit 217 issues a “user addition” command and a user name “member Z ″ is notified to the project status notification processing unit 220.
[0077]
When receiving the “user addition”, the project status notification processing unit 220 searches the command management table 221. Referring to the command management table 221 in FIG. 12, the project status notification processing unit 220 detects the “add user” command, creates “add user member Z” from the text thereof, and temporarily stores it in the document storage unit 222. Store. Since the distribution type is “single shot”, the “add user” command distributes the text stored in the document storage unit 222 and then deletes the text from the document storage unit 222. Further, since the distribution screen is “My Portal”, the accounts of all users registered in the user management information table 219 to the My Portal screen processing unit 201 are detected, and the text “Add User Member Z” is added to this account. To deliver.
[0078]
As a result, "add user" member Z "" is notified to the update notification list (see FIG. 4) on the My Portal screen of all users registered in the project management server 100.
[0079]
Also, for example, when the member A who is the login user selects the event “design” of the project “1UR *** 1” in charge from the schedule screen shown in FIG. 7 and selects the event change icon, the event change screen ( (Not shown). When the member A changes the event on the event change screen and completes the change of the event by selecting the completion icon (not shown), the schedule information processing unit 209 executes the “event change” command and the project name “ 1UR ** 1 "and the event name" design "are notified to the project status notification processing unit 220.
[0080]
When receiving the “event change”, the project status notification processing unit 220 searches the command management table 221. With reference to the command management table 221 in FIG. 12, the project status notification processing unit 220 detects “event change”, creates “change event design” from the text, and temporarily stores it in the document storage unit 222. . Since the “event change” command has the distribution type “accumulate” and the completion command “F”, the text stored in the document storage unit 222 is accumulated without being distributed. Subsequently, when the member A further changes the event “manufacturing” from the schedule screen of FIG. 7, similarly, “change event manufacturing” is created, and the distribution type is “accumulate” and the process is completed. Since the command is “F”, the command is not distributed and is stored in the document storage unit 222.
[0081]
Finally, when the member A finishes changing the series of events by selecting the event editing end icon from the schedule screen of FIG. 7, the schedule information processing unit 209 issues a “schedule editing end” command and a project name “1UR”. *** 1 "to the project status notification processing unit 220.
[0082]
When receiving the “schedule edit end”, the project status notification processing unit 220 performs the same operation, creates the text “event changed” with reference to the command management table 221 shown in FIG. The document is stored in the document storage unit 222. Further, since the distribution type is “accumulate” and the completion command is “T”, the “schedule edit end” command includes the texts stored in the document storage unit 222, “change event design”, and “event change”. “The manufacturing has been changed” and “the event has been changed” are distributed as one text, and these texts are deleted from the document storage unit 222.
[0083]
Here, since these command distribution screens are “project portal”, the project status notification processing unit 220 determines from the project management information table 215 the project “1UR ** 1” of the member in charge of the project “1UR ** 1”. An account for “* 1” to the project portal screen processing unit 202 is detected, and the created text is delivered to this account.
[0084]
As a result, a list of update notifications on the project portal screen for the project "1UR **** 1" of all members in charge of the project "1UR *** 1" managed by the project management server 100 (see FIG. 5). Will be notified that the event has been changed. All members in charge of "1UR ** 1" can refer to the text by selecting the title "Event has been changed" in the update notification list (see FIG. 5) on the project portal screen.
[0085]
Next, a document distribution flow by the project status notification processing unit 220 will be described with reference to FIG.
[0086]
Referring to FIG. 13, in step S100, the contents of document storage unit 222 are reset, and the process proceeds to step S101.
[0087]
In step S101, it is determined whether there is a command notification from the document information processing unit 204, the schedule information processing unit 209, the project information processing unit 213, or the user information processing unit 217. If there is a command notification, the process proceeds to step S102. .
[0088]
In step S102, the project status notification processing unit 220 refers to the command management information table 221 to determine whether the delivery type of the notified command is “single shot”, and if it is “single shot”, the process proceeds to step S107. Otherwise, the process proceeds to step S103.
[0089]
In step S103, it is determined whether the accumulation flag is ON. The accumulation flag is a flag indicating whether to distribute the document corresponding to the notified command or to accumulate without distributing the document. If the accumulation flag is ON, the process proceeds to step S105; otherwise, the process proceeds to S104.
[0090]
In step S104, the accumulation flag is turned on, and the process proceeds to step S107.
[0091]
In step S105, it is determined with reference to the command management information table 221 whether the completion command of the notified command is “T” or “F”. If the completion command is "T", the process proceeds to step S106, the accumulation flag is turned off, and the process proceeds to step S108. If the completion command is “F”, the process proceeds to step S107.
[0092]
In step S107, the project name, the file name of the document, the event name, the user name, or the scheduled date of the event before the change is performed in the text template of the text field of the notified command in the text template. By incorporating it, the text is completed and stored in the document storage means 222, and the process proceeds to step S108.
[0093]
In step S108, it is determined whether or not the accumulation flag is ON. If the accumulation flag is ON, the process returns to step S101 without distributing the document. If it is OFF, the process proceeds to step S109.
[0094]
In step S109, it is determined whether the document delivery destination is the My Portal screen. If the destination is the My Portal screen, the process proceeds to step S111; otherwise, the process proceeds to step S110. The determination of the distribution destination refers to the command management information table 221, and if "My Portal" is described in the distribution screen column corresponding to the notified command, the distribution destination is the My Portal screen of all users. If "project portal" is described, it is determined that the screen is a project portal screen for the project of all members in charge of the project of the project name notified together with the command.
[0095]
In step S110, referring to the project management information table 215, all the members in charge of the project detect accounts of the project portal for the project, create a distribution address list, and proceed to step S112.
[0096]
In step S111, the user management information table 219 is referred to, the accounts of my portal of all the registered users are detected, a distribution address list is created, and the process proceeds to step S112.
[0097]
In step S112, the document stored in the document storage unit 222 is distributed to the address of the created address list, and the process returns to step S100.
[0098]
As can be understood from the above description, when the project status notification processing unit 220 receives a command notification from the document information processing unit 204, the schedule information processing unit 209, the project information processing unit 213 or the user information processing unit 217, the command management information table With reference to H.221, an appropriate document is created according to the command. Further, the project status notification processing unit 220 determines from the notified command whether to deliver the document to the members of the project relating to the command or to all registered users, and With reference to the management information table 219, an address list to be delivered is created, and the created document is delivered to the addresses in the address list.
[0099]
With this configuration, the logged-in user can change, add, or delete document information or schedule information on the project for which the user is responsible, or change, add, or delete the project or registered user. If there is, you can know the change of the information only by logging in to the project management program.
[0100]
On the other hand, a logged-in user who has changed, deleted, or added information on a project as described above must create a distribution document and distribute it from a vast number of registered users after changing the information. This eliminates the troublesome task of identifying the user and distributing the document.
[0101]
The embodiments of the present invention can be variously modified as appropriate within the scope of the technical idea of the present invention.
[0102]
【The invention's effect】
According to the present invention, all information related to a project is managed, and when there is any operation that changes the managed information, a fixed document indicating the change of information by the operation is created, and the changed information is created. Can be provided, and a project information management apparatus capable of notifying the user of the fixed document by specifying the user related to the project information can be provided.
[Brief description of the drawings]
FIG. 1 is a diagram showing a configuration of a project management system according to an embodiment.
FIG. 2 is a diagram showing a configuration of a project management server according to the embodiment.
FIG. 3 is a diagram showing a configuration of each function of a project management server according to the embodiment.
FIG. 4 is a display example of a my portal screen displayed by a display device 104 to a login user.
FIG. 5 is a display example of a project portal screen displayed by the display device 104 to a login user.
FIG. 6 is a display example of a document information screen displayed by the display device 104 to a login user.
FIG. 7 is a display example of a schedule setting screen displayed by the display device 104 to a login user.
FIG. 8 is a display example of a project setting screen displayed by the display device 104 to a login user.
FIG. 9 is a display example of a user setting screen displayed by the display device 104 to a login user.
FIG. 10 is a data structure of a project management information table 215.
FIG. 11 is a data structure of a user management information table 219;
FIG. 12 is a data structure of a command management table 221.
FIG. 13 is a diagram showing a flowchart according to the embodiment.
[Explanation of symbols]
200 Project management program
201 ・ ・ ・ My portal screen processing unit
202 ・ ・ ・ Project portal screen processing unit
203: Document information operation screen processing unit
204: Document information processing unit
208: schedule information operation screen processing unit
209 ・ ・ ・ Schedule information processing unit
212 Project information operation screen processing unit
213 ... Project Information Processing Department
216 ... user information operation screen processing unit
217 ... user information processing unit
220 ・ ・ ・ Project status notification processing unit
221... Command management information table

Claims (9)

1又は2以上のプロジェクトに関する情報を管理するプロジェト情報管理装置において、
前記情報を変更するための画面を提供する変更画面提供手段と、
プロジェクトを構成するユーザと該ユーザの配信先アドレスとを関連付けて記憶すると共に前記変更画面からユーザの変更が入力されたことに応じて記憶内容を更新するユーザ情報記憶手段と、
前記情報の変更種別に応じた定型文書を格納する定型文書格納手段と、
前記変更画面から所定のプロジェクトに関する情報の変更が入力されたとき当該変更に応じた配信文書を前記定型文書格納手段に格納された定型文書に基づいて作成する配信文書作成手段と、
前記変更画面から所定のプロジェクトに関する情報の変更が入力されたとき当該プロジェクトに関するユーザの配信先アドレスを前記ユーザ情報記憶手段の記憶情報に基づいて決定し、当該配信先アドレスに対して前記配信文書作成手段によって作成された配信文書を配信する文書配信手段と、
を有することを特徴とするプロジェクト情報管理装置。
In a project information management device that manages information on one or more projects,
Change screen providing means for providing a screen for changing the information,
User information storage means for storing a user constituting a project in association with a delivery destination address of the user and updating the stored content in response to a user change being input from the change screen;
A standard document storage unit for storing a standard document according to the type of change of the information,
When a change of information on a predetermined project is input from the change screen, a delivery document creating unit that creates a delivery document corresponding to the change based on the standard document stored in the standard document storage unit,
When a change of information on a predetermined project is input from the change screen, a delivery destination address of a user related to the project is determined based on information stored in the user information storage unit, and the delivery document creation is performed on the delivery destination address. Document delivery means for delivering a delivery document created by the means;
A project information management device comprising:
前記変更画面提供手段は、変更対象とする情報の種別に応じた変更画面を提供することを特徴とする請求項1記載のプロジェクト情報管理装置。2. The project information management device according to claim 1, wherein the change screen providing unit provides a change screen according to a type of information to be changed. 前記変更画面提供手段は、前記プロジェクトに関する文書情報の変更を入力するための画面を提供することを特徴とする請求項2に記載のプロジェクト情報管理装置。3. The project information management device according to claim 2, wherein the change screen providing unit provides a screen for inputting a change in document information on the project. 前記変更画面提供手段は、前記プロジェクトに関する日程情報の変更を入力するための画面を提供することを特徴とする請求項2または3に記載のプロジェクト情報管理装置。The project information management device according to claim 2, wherein the change screen providing unit provides a screen for inputting a change in schedule information regarding the project. 前記変更画面提供手段は、前記プロジェクトに関する現況情報の変更を入力するための画面を提供することを特徴とする請求項2乃至4のいずれかに記載のプロジェクト情報管理装置。The project information management device according to claim 2, wherein the change screen providing unit provides a screen for inputting a change in current status information regarding the project. 前記変更画面提供手段は、前記プロジェクトに関するユーザ情報の変更を入力するための画面を提供することを特徴とする請求項2乃至5のいずれかに記載のプロジェクト情報管理装置。The project information management device according to claim 2, wherein the change screen providing unit provides a screen for inputting a change of user information regarding the project. 前記文書配信手段は、前記配信文書作成手段によって作成された配信文書を格納する配信文書格納手段を備え、前記変更画面から変更の完了が入力されるまでは、当該情報に関してそれまでに作成された配信文書を前記配信文書格納手段に格納し、前記変更画面から変更の完了が入力されたことに応じて、前記配信文書格納手段に格納された文書を配信することを特徴とする請求項1乃至6のいずれかに記載のプロジェクト情報管理装置。The document distribution unit includes a distribution document storage unit that stores the distribution document created by the distribution document creation unit. Until the completion of the change is input from the change screen, the document has been created with respect to the information. 3. A delivery document is stored in said delivery document storage means, and the document stored in said delivery document storage means is delivered in response to completion of change being input from said change screen. 6. The project information management device according to any one of 6. 前記文書配信手段は、プロジェクトを構成するユーザのみを配信先とするか、プロジェクトを構成しないユーザをも含めて配信先とするかを前記情報の変更内容に関連付けて記憶する区分記憶手段をさらに有し、前記情報の変更が入力されたとき、当該区分記憶手段の記憶内容に基づいて、配信先ユーザを決定することを特徴とする請求項1乃至7のいずれかに記載のプロジェクト情報管理装置。The document distribution means further includes a division storage means for storing, in association with the contents of change of the information, whether only the users constituting the project are to be the distribution destinations or the distribution destinations including the users who do not constitute the project. 8. The project information management apparatus according to claim 1, wherein when a change of the information is input, a distribution destination user is determined based on the storage content of the classification storage unit. コンピュータを請求項1乃至8のいずれかに記載のプロジェクト情報管理装置として機能させるためのプログラム。A program for causing a computer to function as the project information management device according to claim 1.
JP2003153654A 2003-05-30 2003-05-30 Project information management apparatus and program Expired - Fee Related JP3970205B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003153654A JP3970205B2 (en) 2003-05-30 2003-05-30 Project information management apparatus and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003153654A JP3970205B2 (en) 2003-05-30 2003-05-30 Project information management apparatus and program

Publications (2)

Publication Number Publication Date
JP2004355417A true JP2004355417A (en) 2004-12-16
JP3970205B2 JP3970205B2 (en) 2007-09-05

Family

ID=34048511

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003153654A Expired - Fee Related JP3970205B2 (en) 2003-05-30 2003-05-30 Project information management apparatus and program

Country Status (1)

Country Link
JP (1) JP3970205B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008282081A (en) * 2007-05-08 2008-11-20 Taisei Corp Drawing management system
CN110475136A (en) * 2019-07-05 2019-11-19 锐捷网络股份有限公司 A kind of method and device realized terminal and throw screen
JP2019537081A (en) * 2016-12-29 2019-12-19 ドロップボックス, インコーポレイテッド Creating a project in a content management system
US10970656B2 (en) 2016-12-29 2021-04-06 Dropbox, Inc. Automatically suggesting project affiliations
US10997189B2 (en) 2015-03-23 2021-05-04 Dropbox, Inc. Processing conversation attachments in shared folder backed integrated workspaces
US11017354B2 (en) 2016-12-30 2021-05-25 Dropbox, Inc. Managing projects in a content management system
US11226939B2 (en) 2017-12-29 2022-01-18 Dropbox, Inc. Synchronizing changes within a collaborative content management system

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008282081A (en) * 2007-05-08 2008-11-20 Taisei Corp Drawing management system
US11016987B2 (en) 2015-03-23 2021-05-25 Dropbox, Inc. Shared folder backed integrated workspaces
US11748366B2 (en) 2015-03-23 2023-09-05 Dropbox, Inc. Shared folder backed integrated workspaces
US11567958B2 (en) 2015-03-23 2023-01-31 Dropbox, Inc. Content item templates
US11354328B2 (en) 2015-03-23 2022-06-07 Dropbox, Inc. Shared folder backed integrated workspaces
US11347762B2 (en) 2015-03-23 2022-05-31 Dropbox, Inc. Intelligent scrolling in shared folder back integrated workspaces
US10997189B2 (en) 2015-03-23 2021-05-04 Dropbox, Inc. Processing conversation attachments in shared folder backed integrated workspaces
US10997188B2 (en) 2015-03-23 2021-05-04 Dropbox, Inc. Commenting in shared folder backed integrated workspaces
US10970656B2 (en) 2016-12-29 2021-04-06 Dropbox, Inc. Automatically suggesting project affiliations
US10970679B2 (en) 2016-12-29 2021-04-06 Dropbox, Inc. Presenting project data managed by a content management system
US10776755B2 (en) 2016-12-29 2020-09-15 Dropbox, Inc. Creating projects in a content management system
JP2019537081A (en) * 2016-12-29 2019-12-19 ドロップボックス, インコーポレイテッド Creating a project in a content management system
US11017354B2 (en) 2016-12-30 2021-05-25 Dropbox, Inc. Managing projects in a content management system
US11900324B2 (en) 2016-12-30 2024-02-13 Dropbox, Inc. Managing projects in a content management system
US11989694B2 (en) 2016-12-30 2024-05-21 Dropbox, Inc. Managing projects in a content management system
US11226939B2 (en) 2017-12-29 2022-01-18 Dropbox, Inc. Synchronizing changes within a collaborative content management system
CN110475136B (en) * 2019-07-05 2021-10-22 锐捷网络股份有限公司 Method and device for realizing screen projection of terminal
CN110475136A (en) * 2019-07-05 2019-11-19 锐捷网络股份有限公司 A kind of method and device realized terminal and throw screen

Also Published As

Publication number Publication date
JP3970205B2 (en) 2007-09-05

Similar Documents

Publication Publication Date Title
KR101120762B1 (en) Collaboration spaces
US7913161B2 (en) Computer-implemented methods and systems for electronic document inheritance
US20160140139A1 (en) Local representation of shared files in disparate locations
JP5681939B2 (en) Form providing device, form providing method, and program
KR100590982B1 (en) Memo and schedule management system
CN111708516A (en) Web application customization development system on network
CA2751941C (en) Content asset manager
JP3970205B2 (en) Project information management apparatus and program
JP2024515424A (en) Information processing, information interaction, label check, information display method and device
JP2011192078A (en) Task managing device and task management program
JP2003288458A (en) Integrated project management tool
JP5650018B2 (en) Information storage device
US9824400B2 (en) Cost item life cycle viewer with configurable document traversal options
US10726392B2 (en) Email file-and-refer system
JP2015111429A (en) Alteration management support apparatus, alteration management support method, and alteration management support program
JP3871794B2 (en) E-mail system and program storage medium thereof
JP2009157445A (en) Database development management system and program
JP2006277050A (en) Document management device, document management program, and object management device
JP4738704B2 (en) Database system
JP2015060280A (en) Data providing system and data providing method
KR20120095671A (en) Enterprise document management system supporting link function between file, and method of the same
JP2000347943A (en) Document access management system
JP5682452B2 (en) CHANGE MANAGEMENT SUPPORT DEVICE, CHANGE MANAGEMENT SUPPORT METHOD, AND CHANGE MANAGEMENT SUPPORT PROGRAM
JP2006039673A (en) Information display system
JP2005215743A (en) File attribute information management program, file attribute information management method, and file attribute information management device

Legal Events

Date Code Title Description
RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20051227

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060801

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060808

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061005

RD05 Notification of revocation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7425

Effective date: 20061017

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20061005

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20070109

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20070109

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070508

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070605

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100615

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees