JP2004332487A - Shaft excavator - Google Patents
Shaft excavator Download PDFInfo
- Publication number
- JP2004332487A JP2004332487A JP2003133162A JP2003133162A JP2004332487A JP 2004332487 A JP2004332487 A JP 2004332487A JP 2003133162 A JP2003133162 A JP 2003133162A JP 2003133162 A JP2003133162 A JP 2003133162A JP 2004332487 A JP2004332487 A JP 2004332487A
- Authority
- JP
- Japan
- Prior art keywords
- excavation
- water
- shaft
- waste
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】本発明は立坑掘削装置に関し、特に、掘削ズリを地上へ搬送する為の技術を改善した立坑掘削装置に関する。
【0002】
【従来の技術】従来、深度が数100 mもの大深度立坑として、過去では炭坑が、また、最近では鉄道や道路が通る交通トンネルの換気用立坑が実用に供され、将来的には、放射性廃棄物の廃棄等のために、深度が1000mにも達する大深度立坑が必要であると考えられる。これら立坑の掘削方法は、発破掘削と機械掘削とに大別されるが、最近では、機械掘削用の種々の立坑掘削装置が実用化されている。立坑掘削装置の主要な構成は、胴部材と、この胴部材の先端側に装備されたカッターヘッドと、これら胴部材とカッターヘッドを推進させる複数の推進用ジャッキとを備えた掘削機と、掘削ズリ(土砂や礫等)を地上へ搬送する掘削ズリ排出装置である。
【0003】
特許文献1に記載の立坑掘削装置には、掘削機に、チャンバー内の掘削ズリを泥水にして上方へ輸送するスクリュウーコンベアと、スクリュウーコンベで搬送されてきた泥水を貯留する泥水槽が設けられ、この泥水槽から泥水を吸い上げて地上の泥水処理プラントへ送る排泥管と排泥ポンプ、泥水処理プラントで処理された水を泥水槽へ送る送泥管と送泥ポンプが設けられている。
【0004】
特許文献2に記載の立坑掘削装置には、掘削機に、掘削ズリを上方へ輸送するバケットコンベアが設けられ、このバケットコンベアは、センターポスト、センターポスト内に設けられた無端状のチェーン、このチェーンに連結された複数のバケット、複数のバケット(チェーン)を回動させる油圧モータを有し、各バケットの先端部に取り付けられた切刃でも地山を掘削可能になっている。尚、センターポストは油圧モータにより鉛直軸心回りに回動可能であり、そのセンターポストの先端部分にヘリカルドラム掘削機が連結されている。
【0005】
一方、掘削機に、チャンバー内の掘削ズリを水と共に上方へ吸引搬送する混気ジェットポンプと、混気ジェットポンプで搬送されてきた掘削ズリと水を分離する分離装置と、分離装置で分離された掘削ズリを貯留するズリストックビンを設け、この掘削ズリをカプセル輸送方式で地上へ搬送する掘削ズリ排出装置を設けた立坑掘削装置が知られている。分離装置で分離された水は、混気ジェットポンプにより掘削ズリを搬送する為の水として再利用される。
【0006】
尚、特許文献3には、掘削機前方の地山にボーリングを行い、ボーリングされた穴に挿入された反力受けロッドの下端部分を根固めした状態で、反力受けロッドで反力をとって掘削機を推進させる技術が開示されている。
【0007】
【特許文献1】特開2002−332792号公報
【特許文献2】特開2003−3780号公報
【特許文献3】特開2002−349181号公報
【0008】
【発明が解決しようとする課題】従来の立坑掘削装置において、特許文献1のような掘削ズリ排出装置を採用した場合、立坑深さが深くなる程、泥水を吸い上げて地上まで送る多数の排泥ポンプが必要となり、これら排泥ポンプの大多数を立坑途中部に設置しなければならないため、掘削ズリ排出装置の設備コストが非常に高価になり、この掘削ズリ排出装置の運転負荷も大きくなる。これら排泥ポンプを設置する作業負荷も大きく、更に、立坑深さが深くなり、掘削ズリを複数の中継地点で中継しながら搬送するようにすると、掘削ズリの排出を能率よく行うことができなくなり、立坑施工工期が長くなる。
【0009】
また、特許文献1のような掘削ズリ排出装置を採用した場合、排泥ポンプが故障したり停電等の緊急時に排泥ポンプが作動停止すると、排泥管内の搬送途中の掘削ズリが水と共に落下し、排泥管が閉塞・破損したりポンプが破損する虞がある。尚、前記カプセル輸送式の掘削ズリ排出装置でも、設備コストが高価になり、掘削ズリの排出を能率よく行うことが難しい。
【0010】
掘削機内において掘削ズリをカッターヘッド付近から上方へ輸送する掘削ズリ輸送機構として、特許文献1ではスクリューコンベアが設けられ、特許文献2ではバケットコンベアが設けられているが、これらの機構は何れも部品点数が多い複雑な構造であり、駆動用の油圧モータを必要とするため、掘削ズリ輸送機構の設備コストが高価になり、また、掘削ズリ輸送機構の駆動負荷も大きくなる。
【0011】
特許文献1〜3には、掘削機前方の地山からの湧水についての対策については何ら開示されていない。即ち、地山の湧水の状態に応じて、カッターヘッドには湧水よる水圧が作用する場合と作用しない場合とがあり、その水圧がカッターヘッドに作用した場合でも、その水圧は一定圧でなく安定しないことが多いため、常時、カッターヘッドを適度な押付力で前方の地山に押し付けることが難しく、その結果、地山の掘削を能率的に行えないという虞がある。
【0012】
従来の立坑掘削装置では、カッターヘッド付近の掘削ズリを取り残すことなく上方へ掘削ズリ輸送機構で輸送することは難しく、掘削ズリの取り残しがあると、その掘削ズリによってカッターヘッドが回転不良を起こす虞があるし、カッターヘッドが磨耗し易くなる。尚、掘削機は数100 トンの重量になるものもあり、その掘削機の荷重支持のために地上からウインチで吊り下げることは、設備コストや安全面で望ましくはなく、また、前記課題同様に、カッターヘッドを適度な押付力で前方の地山に押し付けることも難しい。
【0013】
本発明の目的は、掘削ズリ排出装置の構造を簡単化し設備コストを低減すること、掘削ズリ排出装置の運転負荷を低減すること、掘削ズリの排出を能率よく行い更に掘削ズリ排出管の増設を簡単に行えるようにして立坑施工工期を短縮すること、掘削機内において掘削ズリを上方へ輸送する掘削ズリ輸送機構の構造を簡単化し設備コストを低減すること、掘削ズリ輸送機構の駆動負荷を低減すること、カッターヘッドを適度な押付力で前方の地山に押し付けてカッターヘッドで地山掘削を能率的に行うこと、掘削ズリの取り残しを防止してカッターヘッドの回転不良や磨耗を極力防止すること、等々である。
【0014】
【課題を解決するための手段】請求項1の立坑掘削装置は、胴部材と、この胴部材の先端側に装備されたカッターヘッドと、これら胴部材とカッターヘッドを推進させる複数の推進用ジャッキとを備えた掘削機を有する立坑掘削用の立坑掘削装置において、立坑の上端付近から掘削機まで延びる送水管部と、この送水管部の下端に連通連結されて立坑の上端付近まで延び掘削ズリを水と共に地上へ搬送する排出管部とを備え且つ立坑深さが深くなるのに応じて継ぎ足される掘削ズリ搬送管と、前記送水管部にズリ搬送用水を供給する排土用ポンプとを備えた掘削ズリ排出装置を設け、前記掘削ズリ排出装置は、掘削ズリを掘削ズリ搬送管内の水流で地上へ搬送するように構成したことを特徴とするものである。
【0015】
この立坑掘削装置において、掘削ズリ排出装置は、立坑の上端付近から掘削機まで延びる送水管部と、この送水管部の下端に連通連結されて立坑の上端付近まで延びる排出管部とを備えた掘削ズリ搬送管を有し、この掘削ズリ排出装置の排土用ポンプにより送水管部にズリ搬送用水が供給されて、掘削ズリ搬送管内に水流が発生し、掘削ズリ搬送管内に掘削ズリを導入することにより、その掘削ズリが掘削ズリ搬送管内の水流で地上へ搬送され排出される。
【0016】
掘削ズリ搬送管は、送水管部と排出管部とを連通連結したサイフォン管的な管となり、この掘削ズリ搬送管と排土用ポンプとを用いた所謂サイフォン技術を採用することにより、排土用ポンプとして、非常に高出力のポンプや多数のポンプを設けなくても、立坑深さ、つまり掘削ズリ搬送管の上下方向長さに殆ど影響を受けず、立坑深さが深くなっても、掘削ズリ搬送管内に水流を発生させて掘削ズリを搬送することが可能になる。こうして、掘削ズリ排出装置の構造を簡単化し設備コストを低減することができ、掘削ズリ排出装置の運転負荷も低減できる。
【0017】
掘削ズリ排出装置は、立坑深さが深くなるのに応じて掘削ズリ搬送管を継ぎ足すことにより対応でき、この継ぎ足し作業も簡単に行うことができ、しかも、この掘削ズリ排出装置により、掘削ズリを掘削機から地上まで中継することなく一気に搬送できるため、掘削ズリの排出を能率よく行うことができ、その結果、立坑施工工期を大幅に短縮することができる。排土用ポンプが故障したり停電等の緊急時に排土用ポンプが作動停止しても、掘削ズリ搬送管内の少なくとも水は落下することなく保持されるため、掘削ズリ搬送管や排土用ポンプが破損するのを極力防止でき、安全面でも優れたものになる。
【0018】
請求項2の立坑掘削装置は、請求項1の発明において、前記掘削ズリを排出管部内に押し込む掘削ズリ投入装置を設けたことを特徴とするものである。立坑深さが深くなり、掘削ズリ搬送管の地上からの上下方向距離が長くなる程、掘削ズリを押し込む部分の掘削ズリ搬送管内の水圧は高圧になるが、この場合でも、掘削ズリ投入装置により、掘削ズリ搬送管からの水の流出を防止して、掘削ズリを排出管部内に確実に押し込むことができる。
【0019】
請求項3の立坑掘削装置は、請求項2の発明において、前記カッターヘッドの切羽に発生させた水圧を利用して、カッターヘッドで掘削された掘削ズリを水と共に掘削ズリ投入装置まで輸送可能な掘削ズリ輸送機構を設けたことを特徴とするものである。それ故、掘削ズリ輸送機構の駆動負荷を軽減可能とすると共に、掘削ズリを掘削ズリ投入装置まで簡単・確実に輸送することができる。
【0020】
請求項4の立坑掘削装置は、請求項3の発明において、前記掘削ズリ輸送機構で輸送されてきた掘削ズリと水とを分離する分離装置を設け、そこで分離された掘削ズリを掘削ズリ投入装置に供給することを特徴とするものである。分離装置で分離された掘削ズリを掘削ズリ投入装置により排出管部内に能率よく押し込むことができ、また、分離装置で分離された水を再利用したり、そのうちの余剰水については、掘削ズリ搬送管に排出することもできる。
【0021】
請求項5の立坑掘削装置は、請求項4の発明において、前記掘削ズリ輸送機構は、一端部がカッターヘッドの前側へ突出し他端部が分離装置に接続された輸送管と、分離装置で分離された水を切羽側へ導出可能な導出管と、この導出管に介装されて切羽の水圧を調節可能な切羽水圧調整ポンプとを有することを特徴とするものである。
【0022】
切羽水圧調整ポンプにより、分離装置で分離された水をカッターヘッドの切羽に積極的に供給することにより、切羽の水圧を高めて適正圧に調節することができ、その水圧で掘削ズリを水と共に輸送管を介して分離装置へ確実に安定的に輸送することができ、しかも、その水圧を加味して、掘削機の荷重支持を行うと共に、カッターヘッドを適度な押付力で前方の地山に押し付けて、カッターヘッドで地山掘削を能率的に行うことが可能になる。また、掘削ズリ輸送機構は、輸送管、導出管、切羽水圧調整ポンプを有する簡単な構造であるため、掘削ズリ輸送機構の設備コストを低減できる。
【0023】
請求項6の立坑掘削装置は、請求項5の発明において、前記輸送管の先端部に装備された先行排土カッターと、前記先行排土カッターを進退駆動する進退駆動機構と、先行排土カッターを回動駆動する回動駆動機構とを設けたことを特徴とするものである。進退駆動機構により先行排土カッターの突出位置を調節し、回動駆動機構により先行排土カッターを回動させて回収穴を形成し、その回収穴に掘削ズリを集め、場合によって、先行排土カッターを進退させ回動させながら、掘削ズリを輸送管で吸い上げて回収し輸送することができる。掘削ズリの取り残しを防止してカッターヘッドの回転不良や磨耗を極力防止することができる。
【0024】
請求項7の立坑掘削装置は、請求項5の発明において、前記分離装置で分離された余剰水を排出管部に排出する為の余剰水排出管と、この余剰水排出管に介装された余剰水排出ポンプとを設けたことを特徴とするものである。前方の地山からの湧水が多く切羽の水圧が適正圧以上になる場合、この余剰水排出管と余剰水排出ポンプにより、分離装置で分離された水を積極的に掘削ズリ搬送管に排出し、切羽の水圧を低下させ適正圧に調節することができる。
【0025】
請求項8の立坑掘削装置は、請求項5の発明において、前記カッターヘッドで掘削されたズリが、カッターヘッドのうち輸送管の先端部が突出している部分に集まるように、カッターヘッドを構成したことを特徴とするものである。ここで、カッターヘッドは、前記輸送管の先端部が突出している部分(先行部分)が最も先行した下向きの傘状に、更に、カッターヘッドの前面部に複数の寄せ板を渦巻き状に取り付けて構成される。こうして、カッターヘッドの先行部分に掘削ズリを確実に集め、その掘削ズリを輸送管で吸い上げて回収して輸送でき、掘削ズリの取り残しを防止してカッターヘッドの回転不良や磨耗を極力防止できる。
【0026】
請求項9の立坑掘削装置は、請求項5の発明において、前記カッターヘッド前方の地山にボーリングを行い地山内の湧水の状態を調査すると共に、大量の湧水がある場合に地盤改良可能なボーリング装置を設けたことを特徴とするものである。ボーリング装置により、カッターヘッド前方の地山にボーリングを行って地山内の湧水の状態を調査し、大量の湧水がある場合にモルタルを注入する等して地盤改良して、湧水を調整することができる。
【0027】
請求項10の立坑掘削装置は、請求項1〜9の何れかの発明において、前記掘削機で掘削されたトンネルの内面にセグメントを組付けるエレクタ装置を設け、前記胴部材は、掘削方向向きに相対的に移動自在の後胴と前胴とを有し、前記複数の推進用ジャッキとして、エレクタ装置で組付けられたセグメントに対して後胴を推進駆動する複数の第1ジャッキと、後胴に対して前胴を推進駆動する複数の第2ジャッキとを設けたことを特徴とするものである。
【0028】
エレクタ装置を設けることにより、掘削機で掘削されたトンネルの内面をセグメントで覆工しつつ、立坑を掘削していくことができる。トンネルの内面に組み付けられたセグメントに複数の第1ジャッキの反力をとって前胴及び後胴を推進させることができ、また、トンネルの内面に固定された後胴に複数の第2ジャッキの反力をとって前胴を推進さることもでき、この2通りの方法にて、先端側のカッターヘッドで前方の地山を掘削することができる。
【0029】
請求項11の立坑掘削装置は、請求項10の発明において、前記後胴をトンネルの内面に固定解除可能に固定する複数の第1グリッパー機構と、前記前胴をトンネルの内面に固定解除可能に固定すると共に掘削機の進行方向を調節可能な複数の第2グリッパー機構とを設けたことを特徴とするものである。複数の第1グリッパー機構により後胴をトンネルの内面に固定した状態で、複数の第2ジャッキを駆動して前胴を推進させる際、また、複数の第1ジャッキを駆動して前胴及び後胴を推進させる際に、複数の第2グリッパー機構により掘削機の進行方向を調節することができる。
【0030】
【発明の実施の形態】以下、本発明の実施の形態について図面を参照しながら説明する。本実施形態は、掘削機を有する立坑掘削用の立坑掘削装置に、本発明を適用した場合の一例である。尚、掘削機の掘削方向である下方を、適宜、前方、先端側として説明する。
図1〜図5に示すように、立坑掘削装置1は、立坑T(鉛直向きのトンネルT)を掘削する掘削機2と、掘削機2により掘削された掘削ズリを地上まで搬送して排出する掘削ズリ排出装置3を備えている。
【0031】
図1〜図4に示すように、掘削機2は、胴部材10と、胴部材10の先端側に装備されたカッターヘッド11と、胴部材10とカッターヘッド11を推進させる複数の推進用ジャッキ12と、掘削機2で掘削されたトンネルTの内面にセグメントSを組付けるエレクタ装置13を備えている。
【0032】
胴部材10は、掘削方向向き(上下方向向き)に相対的に移動自在の胴部材本体となる後胴10Aと前胴10Bとを有し、後胴10Aの下部に、前胴10Bの上部がスライド可能に外嵌されている。後胴10A又は前胴10Bには、これら後胴10Aと前胴10Bとの嵌合部間を、常時シールする環状のスライドシール20と、緊急時に止水する環状の緊急止水シール21が装備されている。
【0033】
複数の推進用ジャッキ12として、エレクタ装置13で組付けられたセグメントSに対して後胴10Aを推進駆動する複数の第1ジャッキ12Aと、後胴10Aに対して前胴10Bを推進駆動する複数の第2ジャッキ12Bが設けられている。後胴10Aの長さ方向中央部分の内面に後胴リングフレーム22が固着され、複数の第1ジャッキ12Aは上向きにして後胴10Aの内面に沿って周方向に適当間隔おきに配設され、後胴リングフレーム22に挿通状に固定されている。
【0034】
また、前胴10Bの前部の内面に、その前面板が隔壁となる前胴リングフレーム23が固着され、複数の第2ジャッキ12Bは上下方向向きにして胴部材10の内面に沿って周方向に適当間隔おきに配設され、第2ジャッキ12Bの上端部(ロッドの上端部)が後胴リングフレーム22に連結され、下端部(ジャッキ本体の下端部)が前胴リングフレーム23に連結されている。これら第1,第2ジャッキ12A,12Bに油圧を供給する油圧供給ユニット25が、後胴リングフレーム22に装備されている。尚、この油圧供給ユニット25は、後述の、第1グリッパー機構14Aの油圧シリンダ26、第2グリッパー機構14Bの油圧シリンダ28、掘削ズリ投入装置50の油圧ジャッキ66、進退駆動機構80の油圧シリンダ80a等にも油圧を供給する共通の装置となっている。
【0035】
ここで、図1〜図3に示すように、掘削機2には、後胴10AをトンネルTの内面に固定解除可能に固定する複数(例えば、4つ)の第1グリッパー機構14Aと、前胴10BをトンネルTの内面に固定解除可能に固定すると共に掘削機1の進行方向を調節可能な複数(例えば、4つ)の第2グリッパー機構14Bが設けられている。
【0036】
複数の第1グリッパー機構14Aは、後胴10Aの長さ方向中央部分に設けられ、これら第1グリッパー機構14Aを装備する為の複数の凹部10aが後胴10Aに形成されている。各第1グリッパー機構14Aは上下1対の油圧シリンダ26を有し、これら油圧シリンダ26がトンネルTの中心側に向くように凹部10aに装着されて、ピストンロッド26bの先端部が凹部底壁10bに連結されている。各第1グリッパー機構14Aの1対のシリンダ本体26aを内蔵したブロックに断面円弧状の押え板27が連結されて、複数の第1グリッパー機構14Aの複数の油圧シリンダ26が進出駆動されると、複数の押え板27がトンネルTの内面に押し付けられて、後胴10AがトンネルTの内面に固定される。
【0037】
複数の第2グリッパー機構14Bは、前胴10Bの前端部分に設けられ、これら第2グリッパー機構14Bを装備する為の複数の凹部10cが前胴10Bに形成されている。各第2グリッパー機構14Bは油圧シリンダ28を有し、この油圧シリンダ28がトンネルTの中心側に向くように凹部10cに装着されて、複数の第2グリッパー機構14Bの複数の油圧シリンダ28が進出駆動されると、これら油圧シリンダ28のシリンダ本体を内蔵したブロックがトンネルTの内面に押し付けられて、前胴10BがトンネルTの内面に固定される。
【0038】
複数の第1ジャッキ12A、複数の第2ジャッキ12B、複数の第1グリッパー機構14A、複数の第2グリッパー機構14Bを設けたことにより、複数の第1グリッパー機構14Aにより後胴10AをトンネルTの内面に固定した状態で、複数の第2グリッパー機構14Bにより掘削機1の進行方向を調節して、複数の第2ジャッキ12Bを駆動して前胴10Bを推進させ、カッターヘッド11で前方の地山を掘削させ、また、複数の第1ジャッキ12Aを駆動して後胴10A及び前胴10Bを推進させることができる。
【0039】
図1、図2、図4に示すように、カッターヘッド11は、短尺の筒状部30と、筒状部30の下端部に連結された前面板部31と、前面板部31に取り付けられた複数のローラカッター32とを有する。前面板部31には比較的大径の中央穴31aと複数の小径穴31bが形成され、中央穴31aからは、掘削ズリ輸送機構51の輸送管75と、輸送管75に外嵌されたスリーブ78の先端部が下側へ突出し、この輸送管75の先端部に先行排土カッター33が装備され、この先行排土カッター33には複数のビット33aが取り付けられている。
【0040】
カッターヘッド11の前面板部31は、その中央部分が最も下方へ突出する下向きの傘状に形成され、前面板部31には、複数の寄せ板34,35が渦巻き状に取り付けられている。このカッターヘッド11による掘削面は中央部分に向かって下がる傾斜面となり、カッターヘッド11が図4の矢印a方向に回転することにより、掘削ズリは複数の寄せ板34,35により掻き寄せられるように傾斜面を落ちて中央部分に集まってくる。このように、カッターヘッド11で掘削されたズリが、カッターヘッド11のうち輸送管75の先端部が突出している中央部分に集まるように、カッターヘッド11が構成されている。
【0041】
カッターヘッド11を回動駆動する機構については、カッターヘッド11の後端部にリング部材40が連結され、リング部材40の後端部にリングギヤ41が連結され、リングギヤ41には複数の駆動ギヤ42が噛合されている。リング部材40は、前胴リングフレーム23のリング状の穴に環状シール部材を介して回動自在に嵌合され、その穴の後部側スペースにリングギヤ41と複数の駆動ギヤ42が配設されている。複数の駆動ギヤ42が、前胴リングフレーム23に固定された複数の駆動モータ43で駆動されて、リングギヤ41及びリング部材42と共にカッターヘッド11が回動駆動される。
【0042】
図1に示すように、エレクタ装置13は、セグメントSを把持解除可能に把持する把持部45と把持部45をトンネルTの径方向に移動させる機構とを含むエレクタ本体46であって、後胴リングフレーム22に鉛直軸心回りに回動自在に支持されたエレクタ本体46と、エレクタ本体46を回動させる駆動モータ47を含む機構とを備えたものである。エレクタ装置13により組み付けられた複数のセグメントSのうち、上下方向に適当間隔おきのセグメントSはロックボルトSBによりトンネルTの内面に強固に固定される。尚、セグメントSを地上からエレクタ装置13まで搬送するセグメント搬送装置を備えている。尚、後胴10Aの上端部分には、この後胴10Aと組み付けられたセグメントSの間を、常時シールするテールシールと緊急時に止水する止水シールが設けられいる。
【0043】
さて、図1〜図5に示すように、この立坑掘削装置1は、掘削ズリ排出装置3、掘削ズリ投入装置50、掘削ズリ輸送機構51、分離装置52、余剰水排出機構53、ボーリング装置54が備えられ、この掘削ズリ排出装置3以外の装置及び機構50〜54が掘削機2に装備されている。
【0044】
先ず、掘削ズリ排出装置3について説明する。
図1、図5に示すように、掘削ズリ排出装置3には、立坑Tの上端付近の地上から掘削機2まで延びる送水管部61と、送水管部61の下端に連通連結されて立坑Tの上端付近の地上まで延び掘削ズリを水と共に地上へ搬送する排出管部62とを備えた掘削ズリ搬送管60と、立坑Tの上端付近の地上に設置されて送水管部61にズリ搬送用水を供給する排土用ポンプ63とが設けられ、掘削ズリ排出装置3は、掘削ズリを掘削ズリ搬送管60内の水流で地上へ搬送するように構成されている。尚、地上へ搬送された掘削ズリと水は掘削ズリ分離装置で分離され、その水については再利用して送水管部61に供給することができる。
【0045】
掘削ズリ搬送管60は、その送水管部61と排出管部62とが独立した管で構成されており、下端部がU字状になるサイフォン管的な管であるため、立坑Tの深さ、つまり掘削ズリ搬送管60の上下方向長さに殆ど影響を受けず、立坑Tの深さが深くなっても、地上に設置した排土用ポンプ63により給水管部61にズリ搬送用水が供給されると、掘削ズリ搬送管60内に水流が発生し、この水流によって掘削ズリが地上まで搬送される。
【0046】
排出管部62には、その下端位置付近において掘削ズリ投入装置50が接続され、この掘削ズリ投入装置50により排出管部62に掘削ズリが押し込まれ、また、掘削ズリ投入装置50との接続部よりも下流側に、余剰水排出機構53の余剰水排水管85が連通連結されている。尚、掘削ズリ搬送管60の途中数カ所がエレクタ装置13で組み付けられたセグメントSに連結され支持されている。
【0047】
この掘削ズリ搬送管60は、立坑Tの深さが深くなるのに応じて継ぎ足される。この場合、既設の送水管部61と排出管部62に、所定長さの送水増設管と排出増設管とをボルトにより連結して増設する。
【0048】
次に、掘削ズリ投入装置50、掘削ズリ輸送機構51、分離装置52、余剰水排出機構53について説明する。
掘削ズリ投入装置50は、前述の通り、掘削ズリを掘削ズリ搬送管60内に押し込む為の装置であり、エレクタ装置13の上側の架台8上に設置されている。この立坑掘削装置1では、深度が数100 m以上、更には深度が1000mに達する大深度立坑の掘削を想定しており、それ故、掘削ズリ搬送管60内の下端位置での水圧は非常に高圧になり、この高圧の水圧に抗して掘削ズリを掘削ズリ搬送管60内に押し込む為の掘削ズリ投入装置50である。
【0049】
この掘削ズリ投入装置50の一例として、図1、図6〜図9に示すように、左右1対のプランジャー65と、これらプランジャー65を夫々駆動する1対の油圧ジャッキ66とを有する。1対のプランジャー65の先端部がスライド板67に固定され、そのスライド板67がスライドガイド68にスライド移動自在に係合されている。1対のプランジャー65の基端部と1対の油圧ジャッキ66の基端部が連結板69a,69bで一体的に連結されている。
【0050】
スライド板67には、1対のプランジャー65のズリ出入口に連通する2つのスライド板穴が形成され、スライドガイド68の鉛直板部には3つのスライドガイド穴が形成され、隣合う2つのスライドガイド穴間の間隔は、2つのスライド板穴間の間隔と同じである。スライドガイド68には、3つのスライドガイド穴の真ん中の穴に連通するズリ導出管70と、両側の穴に連通する1対のズリ導入管71が連結されている。
【0051】
ズリ導出管70が排出管部62に連通連結され、1対のズリ導入管71が分離装置52のズリ貯留部51aの下端に連通連結されている。スライドガイド68は、図示略の油圧ジャッキによりスライド駆動され、図8、図9の矢印を左方とした場合、図8に示すように、左側のプランジャー65のズリ出入口がズリ導出管70に連通すると、右側のプランジャー65のズリ出入口が右側のズリ導入管71に連通し、この状態で、1対の油圧ジャッキ66を駆動して、左側のプランジャー65内の掘削ズリをズリ導出管70を介して排出管部62内に押し込み、右側のプランジャー65内に掘削ズリを導入することができる。
【0052】
また、図9に示すように、右側のプランジャー65のズリ出入口がズリ導出管70に連通すると、左側のプランジャー65のズリ出入口が左側のズリ導入管71に連通し、この状態で、1対の油圧ジャッキ66を駆動して、右側のプランジャー65内の掘削ズリをズリ導出管70を介して排出管部62内に押し込み、左側のプランジャー65内に掘削ズリを導入することができる。こうした動作を繰り返し行い、掘削ズリを排出管部62内に能率的に押し込むことができる。
【0053】
図1、図2、図5に示すように、掘削ズリ輸送機構51は、カッターヘッド11の前方の地山からの湧水の水圧を利用して、カッターヘッド11で掘削された掘削ズリを水と共に掘削ズリ投入装置50まで輸送可能な機構であり、この掘削ズリ輸送機構51で輸送されてきた掘削ズリと水が、架台8上に設置された分離装置52に供給され、その分離装置52で分離された掘削ズリが、前述のように、掘削ズリ投入装置50に供給される。
【0054】
掘削ズリ輸送機構51は、一端部(下端部)がカッターヘッド11の前側へ突出し他端部(上端部)が分離装置52に接続された輸送管75と、分離装置52で分離された水を切羽側であるカッターヘッド11の内側へ導出可能な導出管76と、導出管76に介装されて切羽側の水圧を調節可能な切羽水圧調整ポンプ77とを有する。切羽水圧調整ポンプ77は、架台8の上側の架台9上に設置されている。
【0055】
輸送管75は、掘削機2に固定的に設けられた固定輸送管75aと、この固定輸送管75aに対して伸縮且つ回動可能に連通連結された可動輸送管75bからなり、可動輸送管75bにスリーブ78が外嵌され、スリーブ78が前胴リングフレーム23に固定されたベアリング部材79により回動自在に支持されている。可動輸送管75bとスリーブ78の先端部分がカッターヘッド11の中央穴31aから前側へ突出し、その可動輸送管75bの先端部に先行排土カッター33が装備されている。この先行排土カッター33で掘削された先行穴に掘削ズリが集まり、その掘削ズリが水と共に輸送管75に入り込み、この輸送管75で分離装置52まで輸送される。
【0056】
導出管76は少なくとも2股76aに分かれて、前胴リングフレーム23の前側の切羽側へ突出している。輸送管75内の水流は切羽の水圧により発生するが、検出された切羽の水圧が掘削ズリを効果的に輸送する適正圧よりも低圧の場合、適正圧まで高めるために、切羽水圧調整ポンプ77が駆動され、分離装置52で分離された水が切羽側へ積極的に導出される。尚、切羽の水圧が適正圧よりも高圧の場合には、切羽水圧調整ポンプ77の作動を停止させ、後で説明する余剰水排出機構53を作動させて、切羽の水圧を適正圧まで低めるようにする。
【0057】
ここで、可動輸送管75bを進退駆動する油圧シリンダ80aを含む進退駆動機構80と、可動輸送管75bを回動駆動する駆動モータ81aを含む回動駆動機構81が設けられている。進退駆動機構80においては、油圧シリンダ80aのシリンダ本体が前胴リングフレーム23にブラケットにより固定され、ピストンロッドの先端部が、可動輸送管75bに対して回動可能に且つ上下方向に相対移動不能に連結されている。
【0058】
図1、図2、図5に示すように、余剰水排出機構53は、余剰水を排出管部61に排出する為の機構であり、分離装置52で分離された余剰水を排出管部62に排出する為の余剰水排出管85と、余剰水排出管85に介装された余剰水排出ポンプ86とを有する。前方の地山から湧水により余剰水がある場合、切羽の水圧が適正圧よりも高圧の場合に適正圧にするために、余剰水排出管85が駆動されて、分離装置52で分離された余剰水が排出管部62に積極的に排出される。尚、立坑Tの深さが深くなると、排出管部62との接続部分における排出管部61内の水圧は高圧になるため、余剰水排出ポンプ86については、その高圧の水圧に抗して余剰水を排出管部62に押し込むことが可能な油圧プランジャー型のポンプとしてもよい。
【0059】
次に、ボーリング装置54について説明する。
図1、図2に示すように、ボーリング装置54は、カッターヘッド11の前方の地山にボーリングを行い地山内の湧水の状態を調査すると共に、大量の湧水がある場合に地盤改良可能に構成されている。このボーリング装置54は、先端部にビットを取り付けたボーリングロッドを進退駆動且つ回転駆動可能なボーリング装置本体90を有し、ボーリング装置本体90の位置及び姿勢を調節可能な複数のリンク及び複数の油圧シリンダを有する位置姿勢調節機構91とを有する。
【0060】
前胴リングフレーム23には複数のガイド管92が挿通状に固定され、このうちの1本を使用し、その使用ガイド管92に対して位置姿勢調節機構91によりボーリング装置本体90の位置及び姿勢を調節することにより、ボーリング装置本体90により、ボーリングロッドを使用ガイド管92に挿通させ、カッターヘッド11の小径穴31bに挿通させて、回動させながら進出させて地山をボーリングしていく。ボーリングロッドに地盤改良材供給通路を形成し、ボーリングロッドの先端からモルタル等の地盤改良材を注入して地盤改良できる。尚、各ガイド管92には非使用時に管路閉止可能に開閉弁部材が装着されている。
【0061】
以上説明した立坑掘削装置1の作用・効果について説明する。
先ず、この立坑掘削装置1は、立坑Tの上端付近の地上から掘削機2まで延びる送水管部61と、この送水管部61の下端に連通連結されて立坑Tの上端付近の地上まで延び掘削ズリを水と共に地上へ搬送する排出管部62とを備え且つ立坑Tの深さが深くなるのに応じて継ぎ足される掘削ズリ搬送管60と、送水管部61にズリ搬送用水を供給する排土用ポンプ63とを備えた掘削ズリ排出装置3を設け、掘削ズリ排出装置3は、掘削ズリを掘削ズリ搬送管60内の水流で地上へ搬送するように構成したものである。
【0062】
つまり、掘削ズリ搬送管60は、送水管部61と排出管部62とを連通連結したサイフォン管的な管となり、この掘削ズリ搬送管60と排土用ポンプ63とを用いた所謂サイフォン技術を採用することにより、排土用ポンプ63として、非常に高出力のポンプや多数のポンプを設けなくても、立坑深さ、つまり掘削ズリ搬送管60の上下方向長さに殆ど影響を受けず、立坑Tの深さが深くなっても、掘削ズリ搬送管60内に水流を発生させて掘削ズリを搬送することが可能になる。こうして、掘削ズリ排出装置3の構造を簡単化し設備コストを低減することができ、掘削ズリ排出装置3の運転負荷も低減することができる。
【0063】
掘削ズリ排出装置3は、立坑Tの深さが深くなるのに応じて掘削ズリ搬送管60を継ぎ足すことにより対応でき、この継ぎ足し作業も簡単に行うことができ、しかも、この掘削ズリ排出装置3により、掘削ズリを掘削機2から地上まで中継することなく一気に搬送できるため、掘削ズリの排出を能率よく行うことができ、その結果、立坑施工工期を大幅に短縮することができる。また、排土用ポンプ63が故障したり停電等の緊急時に排土用ポンプ63が作動停止しても、掘削ズリ搬送管60内の少なくとも水は落下することなく保持されるため、掘削ズリ搬送管60や排土用ポンプ63が破損するのを極力防止することができ、安全面でも優れたものになる。
【0064】
掘削ズリを排出管部62内に押し込む掘削ズリ投入装置50を設けたので、立坑Tの深さが深くなり、掘削ズリ搬送管60の地上からの上下方向距離が長くなる程、ズリ押し込み部分における掘削ズリ搬送管60内の水圧は高圧になるが、この場合でも、掘削ズリ投入装置50により、掘削ズリ搬送60管からの水の流出を防止して、掘削ズリを排出管部62内に確実に押し込むことができる。
【0065】
カッターヘッド11の切羽に発生させた水圧を利用して、カッターヘッド11で掘削された掘削ズリを水と共に掘削ズリ投入装置50まで輸送可能な掘削ズリ輸送機構51を設けたので、掘削ズリ輸送機構51の駆動負荷を軽減可能とすると共に、掘削ズリを掘削ズリ投入装置50まで簡単・確実に輸送できる。
【0066】
掘削ズリ輸送機構51で輸送されてきた掘削ズリと水とを分離する分離装置52を設け、そこで分離された掘削ズリを掘削ズリ投入装置50に供給するので、分離装置52で分離された掘削ズリを掘削ズリ投入装置50により排出管部62内に能率よく押し込むことができ、また、分離装置52で分離された水を再利用したり、その内の余剰水については、余剰水排出管85から掘削ズリ搬送管60に排出することができる。
【0067】
掘削ズリ輸送機構51は、一端部がカッターヘッド11の前側へ突出し他端部が分離装置52に接続された輸送管75と、分離装置52で分離された水を切羽側へ導出可能な導出管76と、この導出管76に介装されて切羽の水圧を調節可能な切羽水圧調整ポンプ77とを有するものである。
【0068】
それ故、切羽水圧調整ポンプ77により、分離装置52で分離された水を再利用しカッターヘッド11の切羽に積極的に供給することにより、切羽の水圧を高めて適正圧に調節することができ、その水圧で掘削ズリを水と共に輸送管75を介して分離装置52へ確実に安定的に輸送でき、しかも、その水圧を加味して、掘削機1の荷重支持を行うと共に、カッターヘッド11を適度な押付力で前方の地山に押し付けて、カッターヘッド11で地山掘削を能率的に行うことが可能になる。また、掘削ズリ輸送機構75は、輸送管75、導出管76、切羽水圧調整ポンプ77を有する簡単な構造であるため、掘削ズリ輸送機構51の設備コストを低減することができる。
【0069】
可動輸送管75bの先端部に装備された先行排土カッター33と、可動輸送管75bを進退駆動する進退駆動機構80と、可動輸送管75bを回動駆動する回動駆動機構81とを設けたので、進退駆動機構80により先行排土カッター33の突出位置を調節し、回動駆動機構81により先行排土カッター33を回動させて回収穴を形成し、その回収穴に掘削ズリを集め、場合によって、先行排土カッター33を進退させ回動させながら、掘削ズリを輸送管75で吸い上げて回収し輸送することができる。掘削ズリの取り残しを防止してカッターヘッド11の回転不良や磨耗を極力防止することができる。
【0070】
分離装置52で分離された余剰水を排出管部62に排出する為の余剰水排出管85と、この余剰水排出管85に介装された余剰水排出ポンプ86とを有する余剰水排出機構53を設けたので、前方地山からの湧水が多く切羽の水圧が高圧過ぎる場合、分離装置52で分離された水を積極的に掘削ズリ搬送管60に排出し、切羽の水圧を低下させ調節することができる。
【0071】
カッターヘッド11で掘削されたズリが、カッターヘッド11のうち輸送管75の先端部が突出している部分に集まるように、カッターヘッド11を構成したので、カッターヘッド11の先行部分に掘削ズリを確実に集め、その掘削ズリを輸送管75で吸い上げて回収して輸送でき、掘削ズリの取り残しを防止してカッターヘッド11の回転不良や磨耗を極力防止できる。
【0072】
カッターヘッド11の前方の地山にボーリングを行い地山内の湧水の状態を調査すると共に、大量の湧水がある場合に地盤改良可能なボーリング装置54を設けたので、このボーリング装置54により、カッターヘッド11の前方の地山にボーリングを行って地山内の湧水の状態を調査し、大量の湧水がある場合にモルタルを注入する等して地盤改良して、湧水を調整することができる。
【0073】
次に、立坑掘削装置の変更形態について説明する。但し、基本的に、変更箇所以外の構成は前記実施形態の立坑掘削装置の構成と同様であり、前記実施形態と同じものには同一符号を付して説明する。
1]図10の立坑掘削装置1Aのカッターヘッド11Aにおいては、その前面板部31Aの中央部分が、前記カッターヘッド11Aの前面板部31よりも下方へ大きく突出する下向きの傘状に形成されている。尚、カッターヘッド11Aの平面視は前記カッターヘッド11の平面視と略同様である。このカッターヘッド11Aによる掘削面は中央部分に向かって大きく下がる傾斜面となり、カッターヘッド11が回転することにより、掘削ズリは複数の寄せ板34,35により掻き寄せられるように傾斜面を落ちて中央部分に確実に集まり易くなる。
【0074】
2]掘削ズリ排出装置3において、外管とこの外管に遊嵌状に挿入される内管とで掘削ズリ搬送管を構成し、内管と、内管と外管の間に、送水通路と、排水通路を形成してもよい。
【0075】
3]掘削ズリ投入装置51においては、ピストン式の投入装置の他に、ロータリー式の投入装置で構成してもよい。
4]尚、本発明の趣旨を逸脱しない範囲において種々の変更を付加して実施することが可能である。
【0076】
【発明の効果】請求項1の立坑掘削装置によれば、立坑の上端付近から掘削機まで延びる送水管部と、この送水管部の下端に連通連結されて立坑の上端付近まで延び掘削ズリを水と共に地上へ搬送する排出管部とを備え且つ立坑深さが深くなるのに応じて継ぎ足される掘削ズリ搬送管と、送水管部にズリ搬送用水を供給する排土用ポンプとを備えた掘削ズリ排出装置を設け、掘削ズリ排出装置は、掘削ズリを掘削ズリ搬送管内の水流で地上へ搬送するように構成した。
【0077】
つまり、掘削ズリ搬送管は、送水管部と排出管部とを連通連結したサイフォン管的な管となり、この掘削ズリ搬送管と排土用ポンプとを用いた所謂サイフォン技術を採用することにより、排土用ポンプとして、非常に高出力のポンプや多数のポンプを設けなくても、立坑深さ、つまり掘削ズリ搬送管の上下方向長さに殆ど影響を受けず、立坑深さが深くなっても、掘削ズリ搬送管内に水流を発生させて掘削ズリを搬送することが可能になり、掘削ズリ排出装置の構造を簡単化し設備コストを低減することができ、掘削ズリ排出装置の運転負荷も低減できる。
【0078】
掘削ズリ排出装置は、立坑深さが深くなるのに応じて掘削ズリ搬送管を継ぎ足すことにより対応でき、この継ぎ足し作業も簡単に行うことができ、しかも、この掘削ズリ排出装置により、掘削ズリを掘削機から地上まで中継することなく一気に搬送できるため、掘削ズリの排出を能率よく行うことができ、その結果、立坑施工工期を大幅に短縮することができる。排土用ポンプが故障したり停電等の緊急時に排土用ポンプが作動停止しても、掘削ズリ搬送管内の少なくとも水は落下することなく保持されるため、掘削ズリ搬送管や排土用ポンプが損傷するのを極力防止することができ、安全面でも優れたものになる。
【0079】
請求項2の立坑掘削装置によれば、掘削ズリを排出管部内に押し込む掘削ズリ投入装置を設けたので、立坑深さが深くなり、掘削ズリを押し込む部分の掘削ズリ搬送管内の水圧が高圧になった場合でも、掘削ズリ搬送管からの水の流出を防止して、掘削ズリを排出管部内に確実に押し込むことができる。
【0080】
請求項3の立坑掘削装置によれば、カッターヘッドの切羽に発生させた水圧を利用して、カッターヘッドで掘削された掘削ズリを水と共に掘削ズリ投入装置まで輸送可能な掘削ズリ輸送機構を設けたので、この掘削ズリ輸送機構の駆動負荷を軽減可能とすると共に、掘削ズリを掘削ズリ投入装置まで簡単・確実に輸送することができる。
【0081】
請求項4の立坑掘削装置によれば、掘削ズリ輸送機構で輸送されてきた掘削ズリと水とを分離する分離装置を設け、そこで分離された掘削ズリを掘削ズリ投入装置に供給するので、掘削ズリを掘削ズリ投入装置により排出管部内に能率よく押し込むことができ、また、分離された水を再利用したり、そのうちの余剰水については、掘削ズリ搬送管に排出することもできる。
【0082】
請求項5の立坑掘削装置によれば、切羽水圧調整ポンプにより、分離装置で分離された水をカッターヘッドの切羽に積極的に供給することにより、切羽の水圧を高めて適正圧に調節することができ、その水圧で掘削ズリを水と共に輸送管を介して分離装置へ確実に安定的に輸送することができ、しかも、その水圧を加味して、掘削機の荷重支持を行うと共に、カッターヘッドを適度な押付力で前方の地山に押し付けて、カッターヘッドで地山掘削を能率的に行うことが可能になる。また、掘削ズリ輸送機構は、輸送管、導出管、切羽水圧調整ポンプを有する簡単な構造であるため、掘削ズリ輸送機構の設備コストを低減することができる。
【0083】
請求項6の立坑掘削装置によれば、輸送管の先端部に装備された先行排土カッターと、先行排土カッターを進退駆動する進退駆動機構と、先行排土カッターを回動駆動する回動駆動機構とを設けたので、先行排土カッターの突出位置を調節し、先行排土カッターを回動させて回収穴を形成し、その回収穴に掘削ズリを集め、場合によって、先行排土カッターを進退させ回動させながら、掘削ズリを輸送管で吸い上げて回収し輸送することができる。その結果、掘削ズリの取り残しを防止してカッターヘッドの回転不良や磨耗を極力防止することができる。
【0084】
請求項7の立坑掘削装置によれば、分離装置を排出管部に接続する余剰水排出管と、この余剰水排出管に介装された余剰水排出ポンプとを設けたので、前方の地山からの湧水が多く切羽の水圧が適正圧以上になる場合、この余剰水排出管と余剰水排出ポンプにより、分離装置で分離された水を積極的に掘削ズリ搬送管に排出し、切羽の水圧を低下させ適正圧に調節することができる。
【0085】
請求項8の立坑掘削装置によれば、カッターヘッドで掘削されたズリが、カッターヘッドのうち輸送管の先端部が突出している部分に集まるように、カッターヘッドを構成したので、そのカッターヘッドの先行部分に掘削ズリを確実に集め、その掘削ズリを輸送管で吸い上げて回収して輸送でき、掘削ズリの取り残しを防止してカッターヘッドの回転不良や磨耗を極力防止できる。
【0086】
請求項9の立坑掘削装置によれば、カッターヘッド前方の地山にボーリングを行い地山内の湧水の状態を調査すると共に、大量の湧水がある場合に地盤改良可能なボーリング装置を設けので、カッターヘッド前方の地山にボーリング行って地山内の湧水の状態を調査し、大量の湧水がある場合にモルタルを注入する等して地盤改良して、湧水を調整することができる。
【0087】
請求項10の立坑掘削装置によれば、エレクタ装置を設けることにより、掘削機で掘削されたトンネルの内面をセグメントで覆工しつつ、立坑を掘削していくことができる。トンネルの内面に組み付けられたセグメントに複数の第1ジャッキの反力をとって前胴及び後胴を推進させ、また、トンネルの内面に固定された後胴に複数の第2ジャッキの反力をとって前胴を推進させることもでき、この2通りの方法にて、先端側のカッターヘッドで前方の地山を掘削できる。
【0088】
請求項11の立坑掘削装置によれば、複数の第1グリッパー機構により後胴をトンネルの内面に固定した状態で、複数の第2ジャッキを駆動して前胴を推進させる際、また、複数の第1ジャッキを駆動して前胴及び後胴を推進させる際に、複数の第2グリッパー機構により掘削機の進行方向を調節することができる。
【図面の簡単な説明】
【図1】本発明の実施形態に係る立坑掘削装置の縦断面図である。
【図2】掘削機の要部の縦断面図である。
【図3】図3のIII 矢視図である。
【図4】図3のIV−IV線断面図である。
【図5】掘削ズリ輸送機構と掘削ズリ排出装置の構成図である。
【図6】掘削ズリ投入装置の斜視図である。
【図7】掘削ズリ投入装置の部分的に切欠いた斜視図である。
【図8】掘削ズリ投入装置の作動説明図である。
【図9】掘削ズリ投入装置の作動説明図である。
【図10】変更形態に係る掘削機の要部の縦断面図である。
【符号の説明】
T 立坑(トンネル)
1 立坑掘削装置
2 掘削機
3 掘削ズリ排出装置
10 胴部材
10A 後胴
10B 前胴
11 カッターヘッド
12 推進用ジャッキ
12A 第1ジャッキ
12B 第2ジャッキ
13 エレクタ装置
14A 第1グリッパー機構
14B 第2グリッパー機構
33 先行排土カッター
50 掘削ズリ投入装置
51 掘削ズリ輸送機構
52 分離装置
53 余剰水排出機構
54 ボーリング装置
60 掘削ズリ搬送管
61 送水管部
62 排出管部
63 排土用ポンプ
75 輸送管
76 導出管
77 切羽水圧調整ポンプ
80 進退駆動機構
81 回動駆動機構
85 余剰水排出管
86 余剰水排水ポンプ[0001]
BACKGROUND OF THE
[0002]
2. Description of the Related Art In the past, coal mines have been used as deep shafts having a depth of several hundred meters, and recently, ventilation shafts for traffic tunnels passing through railways and roads have been put into practical use. It is considered that a deep shaft with a depth of up to 1000 m is required for waste disposal and the like. These shaft excavation methods are roughly classified into blasting excavation and mechanical excavation. Recently, various shaft excavation devices for mechanical excavation have been put into practical use. The main configuration of the shaft excavation apparatus is an excavator including a trunk member, a cutter head mounted on the tip side of the trunk member, a plurality of propulsion jacks for propelling the trunk member and the cutter head, This is an excavation debris discharge device that transports debris (such as earth and sand and gravel) to the ground.
[0003]
In the shaft excavation device described in
[0004]
The shaft excavator described in
[0005]
On the other hand, the excavator has an air-mixing jet pump that sucks and transports the drilling debris in the chamber together with the water, a separation device that separates the drilling debris and water that have been transported by the air-mixing jet pump, and a separation device. There is known a shaft excavator provided with a zristock bin for storing excavated debris and an excavated debris discharge device for transporting the excavated debris to the ground in a capsule transport system. The water separated by the separation device is reused as water for transporting excavation waste by an air-mixing jet pump.
[0006]
In
[0007]
[Patent Document 1] JP-A-2002-332792
[Patent Document 2] JP-A-2003-3780
[Patent Document 3] JP-A-2002-349181
[0008]
In a conventional shaft excavating apparatus, when a drilling waste discharging apparatus as disclosed in
[0009]
In addition, in the case of employing a drilling waste discharging device as disclosed in
[0010]
[0011]
[0012]
With a conventional shaft excavator, it is difficult to transport the excavation debris near the cutter head upward without leaving the excavation debris, and if there is any remaining excavation debris, the cutter head may cause rotation failure due to the excavation debris. And the cutter head is easily worn. Some excavators weigh several hundred tons, and it is not desirable to suspend the excavator with a winch from the ground to support the load of the excavator in terms of equipment cost and safety. Also, it is difficult to press the cutter head against the ground in front with an appropriate pressing force.
[0013]
An object of the present invention is to simplify the structure of the excavation waste discharging device and reduce the equipment cost, reduce the operation load of the excavation waste discharging device, efficiently discharge excavation waste, and further increase the number of excavating waste discharge pipes. To shorten the shaft construction period by making it easier to perform, to simplify the structure of the excavation waste transport mechanism that transports excavation debris upward in the excavator, to reduce equipment costs, and to reduce the driving load of the excavation debris transport mechanism To efficiently excavate the ground with the cutter head by pressing the cutter head against the ground in front with an appropriate pressing force, and to prevent leftover of excavation debris to minimize poor rotation and wear of the cutter head. , And so on.
[0014]
According to a first aspect of the present invention, there is provided a shaft excavating apparatus, comprising: a body member; a cutter head provided at a tip end of the body member; and a plurality of propulsion jacks for propelling the body member and the cutter head. A water pipe section extending from the vicinity of the upper end of the shaft to the excavator; and a drilling slide extending near the upper end of the shaft and connected to the lower end of the water pipe section. And a discharge pipe part that is added as the shaft depth becomes deeper, and an earth discharging pump that supplies water for transferring the slip to the water supply pipe part. The excavation waste discharging device is provided, and the excavation waste discharging device is configured to transport the excavation waste to the ground by a water flow in the excavation waste conveying pipe.
[0015]
In this shaft excavation apparatus, the excavation shear discharger includes a water pipe section extending from near the upper end of the shaft to the excavator, and a discharge pipe section connected to the lower end of the water pipe section and extending to near the upper end of the shaft. It has an excavated waste transport pipe, and water for debris transport is supplied to the water supply pipe section by the discharging pump of this excavated waste discharge device, a water flow is generated in the excavated waste transport pipe, and the excavated waste transport pipe is introduced into the excavated waste transport pipe. By doing so, the excavated waste is transported to the ground by the water flow in the excavated waste transport pipe and discharged.
[0016]
The excavated waste transport pipe is a siphon pipe connecting the water supply pipe section and the discharge pipe section. The so-called siphon technology using the excavated waste transport pipe and the discharging pump is used to remove the soil. Even if a very high output pump or a large number of pumps are not provided as a pump for the shaft, it is hardly affected by the depth of the shaft, i.e. It is possible to transport the excavation waste by generating a water flow in the excavation waste transport pipe. Thus, it is possible to simplify the structure of the excavation waste discharging device, reduce the equipment cost, and reduce the operation load of the excavation waste discharging device.
[0017]
The excavation chip discharging device can be adapted by adding a drilling conveyance pipe as the shaft depth becomes deeper, and this refilling operation can be easily carried out. Can be transported at once without relay from the excavator to the ground, so that excavation waste can be efficiently discharged, and as a result, the construction period of the shaft can be significantly reduced. Even if the pump for earth removal breaks down or the pump for earth removal stops operating in an emergency such as a power outage, at least water in the excavation waste conveyance pipe is retained without falling, so the excavation waste conveyance pipe and the earth removal pump Can be prevented from being damaged as much as possible, and safety can be improved.
[0018]
According to a second aspect of the present invention, there is provided the shaft excavation apparatus according to the first aspect, further comprising an excavation slip input device for pushing the excavation waste into a discharge pipe portion. As the shaft depth becomes deeper and the vertical distance from the ground of the excavation shear transport pipe becomes longer, the water pressure in the excavation shear transport pipe where the excavation shear is pushed in increases, but even in this case, the excavation In addition, it is possible to prevent the water from flowing out of the excavation debris conveyance pipe, and to reliably push the excavation debris into the discharge pipe portion.
[0019]
According to the third aspect of the present invention, the shaft excavator according to the second aspect of the present invention is capable of transporting excavation debris excavated by the cutter head together with water to the excavation debris input device by using water pressure generated at the face of the cutter head. The present invention is characterized in that an excavation shear transport mechanism is provided. Therefore, it is possible to reduce the driving load of the excavation waste transport mechanism and to easily and reliably transport the excavation waste to the excavation waste input device.
[0020]
According to a fourth aspect of the present invention, there is provided the shaft excavation apparatus according to the third aspect of the present invention, further comprising a separating device for separating the excavated waste and the water transported by the excavated waste transporting mechanism. It is characterized by being supplied to. The excavated waste separated by the separation device can be efficiently pushed into the discharge pipe by the excavated waste input device, and the water separated by the separation device can be reused. It can also be discharged into a pipe.
[0021]
According to a fifth aspect of the present invention, in the vertical shaft excavating apparatus according to the fourth aspect, the excavating shear transport mechanism is separated by a separating device from a transport pipe having one end protruding forward of the cutter head and the other end connected to the separating device. And a face water pressure adjusting pump interposed in the outlet pipe and capable of adjusting the water pressure of the face.
[0022]
By actively supplying the water separated by the separator to the cutter head face by the face water pressure adjustment pump, the water pressure of the face can be increased and adjusted to an appropriate pressure. It can be reliably and stably transported to the separation device via the transport pipe, while taking into account the water pressure to support the load of the excavator and to move the cutter head to the ground in front with an appropriate pressing force. Pressing the cutter head makes it possible to efficiently excavate the ground with the cutter head. In addition, the excavation waste transport mechanism has a simple structure having a transport pipe, an outlet pipe, and a face water pressure adjusting pump, so that the equipment cost of the excavation waste transport mechanism can be reduced.
[0023]
According to a sixth aspect of the present invention, there is provided the shaft excavator according to the fifth aspect of the present invention, wherein a preceding earth removal cutter provided at a tip portion of the transport pipe, an advance / retreat driving mechanism for driving the advance earth removal cutter forward and backward, and a preceding earth removal cutter And a rotation drive mechanism for driving the rotation. The advance / retreat drive mechanism adjusts the protruding position of the preceding discharging cutter, and the rotary driving mechanism rotates the preceding discharging cutter to form a collecting hole, and collects excavation debris in the collecting hole. While moving the cutter forward and backward, the drilling debris can be sucked up, collected, and transported by the transport pipe. Excessive removal of excavation debris can be prevented, and poor rotation and wear of the cutter head can be prevented as much as possible.
[0024]
According to a seventh aspect of the present invention, in the vertical shaft excavating apparatus according to the fifth aspect, a surplus water discharge pipe for discharging surplus water separated by the separation device to a discharge pipe portion, and the surplus water discharge pipe is interposed in the surplus water discharge pipe. A surplus water discharge pump is provided. When there is a lot of spring water from the ground in front and the water pressure of the face exceeds the appropriate pressure, the surplus water discharge pipe and surplus water discharge pump positively discharges the water separated by the separation device to the excavation waste transport pipe. Then, the water pressure of the face can be reduced and adjusted to an appropriate pressure.
[0025]
The shaft excavator according to
[0026]
The shaft excavation device according to
[0027]
A shaft excavation device according to
[0028]
By providing the elector device, it is possible to excavate the shaft while covering the inner surface of the tunnel excavated by the excavator with the segments. The front body and the rear body can be propelled by applying a reaction force of the plurality of first jacks to the segment assembled on the inner surface of the tunnel, and the plurality of second jacks can be mounted on the rear body fixed to the inner surface of the tunnel. The front body can be propelled by taking a reaction force, and the ground in front can be excavated with the cutter head on the front end side by these two methods.
[0029]
According to an eleventh aspect of the present invention, in the pit excavator according to the tenth aspect, a plurality of first gripper mechanisms for releasably fixing the rear body to the inner surface of the tunnel, and the first body being capable of releasing the front body to the inner surface of the tunnel. A plurality of second gripper mechanisms that are fixed and that can adjust the traveling direction of the excavator are provided. When driving the plurality of second jacks to propel the front body while the rear body is fixed to the inner surface of the tunnel by the plurality of first gripper mechanisms, and driving the plurality of first jacks to drive the front body and the rear. When the trunk is propelled, the traveling direction of the excavator can be adjusted by the plurality of second gripper mechanisms.
[0030]
Embodiments of the present invention will be described below with reference to the drawings. This embodiment is an example of the case where the present invention is applied to a shaft excavation apparatus for shaft excavation having an excavator. Note that the lower direction, which is the direction of excavation of the excavator, will be referred to as the front side or the tip side as appropriate.
As shown in FIGS. 1 to 5, a
[0031]
As shown in FIG. 1 to FIG. 4, the
[0032]
The
[0033]
As the plurality of
[0034]
A front
[0035]
Here, as shown in FIGS. 1 to 3, the
[0036]
The plurality of
[0037]
The plurality of
[0038]
By providing the plurality of
[0039]
As shown in FIGS. 1, 2, and 4, the
[0040]
The
[0041]
As for the mechanism for rotating and driving the
[0042]
As shown in FIG. 1, the
[0043]
Now, as shown in FIGS. 1 to 5, the
[0044]
First, the excavation
As shown in FIGS. 1 and 5, the excavation
[0045]
The excavated
[0046]
The
[0047]
The excavated
[0048]
Next, the excavation
As described above, the excavation-
[0049]
As shown in FIG. 1 and FIGS. 6 to 9, an example of the excavation
[0050]
The
[0051]
The
[0052]
Also, as shown in FIG. 9, when the slip inlet / outlet of the
[0053]
As shown in FIGS. 1, 2, and 5, the excavation
[0054]
The excavation
[0055]
The
[0056]
The
[0057]
Here, an advance /
[0058]
As shown in FIGS. 1, 2, and 5, the surplus
[0059]
Next, the
As shown in FIGS. 1 and 2, the
[0060]
A plurality of
[0061]
The operation and effect of the
First, the
[0062]
In other words, the excavated
[0063]
The excavation
[0064]
Since the excavated-
[0065]
By using the water pressure generated at the face of the
[0066]
A
[0067]
The excavation
[0068]
Therefore, the face water
[0069]
The
[0070]
A surplus
[0071]
The
[0072]
Boring is performed on the ground in front of the
[0073]
Next, a modified embodiment of the shaft excavator will be described. However, the configuration other than the changed part is basically the same as the configuration of the shaft excavation apparatus of the above-described embodiment, and the same components as those of the above-described embodiment are denoted by the same reference numerals.
1] In the
[0074]
2] In the excavated
[0075]
3] The excavation
4] Various changes can be made without departing from the spirit of the present invention.
[0076]
According to the shaft excavating apparatus of the first aspect, a water pipe section extending from the vicinity of the upper end of the shaft to the excavator, and the excavation slide extending near the upper end of the shaft and connected to the lower end of the water pipe section and extending near the upper end of the shaft. Excavation provided with a discharge pipe part for carrying water to the ground and excavated with a drilling waste transfer pipe that is added as the shaft depth becomes deeper, and an earth removal pump that supplies water for slip transportation to the water supply pipe part A waste discharging device is provided, and the drilling waste discharging device is configured to transport the drilling waste to the ground by a water flow in the drilling waste transport pipe.
[0077]
In other words, the excavated waste transport pipe is a siphon-like pipe communicating and connecting the water pipe section and the discharge pipe section, and by adopting a so-called siphon technology using this excavated waste transport pipe and a pump for discharging the earth, Even if a very high-output pump or a large number of pumps are not provided as the discharging pump, the vertical shaft depth is hardly affected by the vertical shaft depth, that is, In addition, it is possible to transport the excavation waste by generating a water flow in the excavation waste conveyance pipe, simplifying the structure of the excavation waste discharge device, reducing the equipment cost, and reducing the operation load of the excavation waste discharge device it can.
[0078]
The excavation chip discharging device can be adapted by adding a drilling conveyance pipe as the shaft depth becomes deeper, and this refilling operation can be easily carried out. Can be transported at once without relay from the excavator to the ground, so that excavation waste can be efficiently discharged, and as a result, the construction period of the shaft can be significantly reduced. Even if the pump for earth removal breaks down or the pump for earth removal stops operating in an emergency such as a power outage, at least water in the excavation waste conveyance pipe is retained without falling, so the excavation waste conveyance pipe and the earth removal pump Can be prevented from being damaged as much as possible, and safety can be improved.
[0079]
According to the shaft excavation device of
[0080]
According to the shaft excavation apparatus of
[0081]
According to the shaft excavation device of claim 4, a separation device for separating the excavation waste and the water transported by the excavation waste transport mechanism is provided, and the separated excavation waste is supplied to the excavation waste input device. The waste can be efficiently pushed into the discharge pipe portion by the excavation waste input device, and the separated water can be reused, and the surplus water can be discharged to the excavation waste transport pipe.
[0082]
According to the shaft excavation device of claim 5, the water pressure of the face is increased and adjusted to an appropriate pressure by actively supplying the water separated by the separator to the face of the cutter head by the face water pressure adjusting pump. With the water pressure, the drilling waste can be reliably and stably transported together with the water to the separation device via the transport pipe, and in addition to supporting the load of the excavator in consideration of the water pressure, the cutter head can be used. Can be pressed against the ground ahead with an appropriate pressing force, and the ground excavation can be efficiently performed by the cutter head. In addition, the excavation slide transport mechanism has a simple structure having a transport pipe, an outlet pipe, and a face water pressure adjusting pump, so that the equipment cost of the excavation slide transport mechanism can be reduced.
[0083]
According to the shaft excavation device of claim 6, the preceding discharging cutter mounted at the tip of the transport pipe, the advance / retreat driving mechanism for driving the preceding discharging cutter forward / backward, and the rotation for rotating / driving the preceding discharging cutter. Since a driving mechanism is provided, the projecting position of the pre-discharge cutter is adjusted, the pre-discharge cutter is rotated to form a collection hole, and excavation slips are collected in the collection hole. The drilling debris can be sucked up by the transport pipe, collected, and transported while moving forward and backward. As a result, it is possible to prevent leftovers of excavation debris and to prevent poor rotation and wear of the cutter head as much as possible.
[0084]
According to the shaft excavation device of claim 7, since the surplus water discharge pipe connecting the separation device to the discharge pipe portion and the surplus water discharge pump interposed in the surplus water discharge pipe are provided, If the spring pressure from the face is higher than the appropriate pressure, the surplus water discharge pipe and surplus water discharge pump will actively discharge the water separated by the separation device to the excavation shear transport pipe, The water pressure can be reduced and adjusted to an appropriate pressure.
[0085]
According to the shaft excavation device of
[0086]
According to the shaft excavation device of
[0087]
According to the shaft excavation device of the tenth aspect, by providing the erector device, the shaft can be excavated while the inner surface of the tunnel excavated by the excavator is covered with the segments. The front body and the rear body are propelled by applying the reaction force of the plurality of first jacks to the segments assembled on the inner surface of the tunnel, and the reaction force of the plurality of second jacks is applied to the rear body fixed to the inner surface of the tunnel. The front fuselage can also be propelled, and the ground ahead can be excavated with the cutter head on the tip side in these two ways.
[0088]
According to the shaft excavation apparatus of
[Brief description of the drawings]
FIG. 1 is a vertical sectional view of a shaft excavation apparatus according to an embodiment of the present invention.
FIG. 2 is a longitudinal sectional view of a main part of the excavator.
FIG. 3 is a view taken in the direction of the arrow III in FIG. 3;
FIG. 4 is a sectional view taken along line IV-IV of FIG. 3;
FIG. 5 is a configuration diagram of an excavation debris transport mechanism and an excavation debris discharge device.
FIG. 6 is a perspective view of an excavation slip loading device.
FIG. 7 is a partially cutaway perspective view of the excavation slide input device.
FIG. 8 is an explanatory view of the operation of the excavation slide input device.
FIG. 9 is an explanatory diagram of the operation of the excavation slide input device.
FIG. 10 is a longitudinal sectional view of a main part of an excavator according to a modified embodiment.
[Explanation of symbols]
T shaft (tunnel)
1 shaft excavation equipment
2 excavator
3 Excavation waste discharging device
10 torso members
10A Rear torso
10B front torso
11 Cutter head
12 Jack for propulsion
12A 1st jack
12B 2nd jack
13 Electa device
14A first gripper mechanism
14B second gripper mechanism
33 Advanced earth removal cutter
50 Excavation shear loading device
51 Excavation waste transport mechanism
52 Separation device
53 Excess water discharge mechanism
54 Boring equipment
60 Excavation shear transfer pipe
61 Water pipe section
62 Discharge pipe section
63 Pump for earth removal
75 Transport Pipe
76 Outlet tube
77 Face water pressure adjustment pump
80 Forward / backward drive mechanism
81 Rotation drive mechanism
85 Excess water discharge pipe
86 Excess water drainage pump
Claims (11)
立坑の上端付近から掘削機まで延びる送水管部と、この送水管部の下端に連通連結されて立坑の上端付近まで延び掘削ズリを水と共に地上へ搬送する排出管部とを備え且つ立坑深さが深くなるのに応じて継ぎ足される掘削ズリ搬送管と、
前記送水管部にズリ搬送用水を供給する排土用ポンプとを備えた掘削ズリ排出装置を設け、
前記掘削ズリ排出装置は、掘削ズリを掘削ズリ搬送管内の水流で地上へ搬送するように構成したことを特徴とする立坑掘削装置。In a shaft excavation device for shaft excavation having a body member, a cutter head equipped on the tip side of the body member, and a plurality of jacks for propulsion for propelling the body member and the cutter head,
A water pipe section extending from near the upper end of the shaft to the excavator; and a discharge pipe section connected to the lower end of the water pipe section and extending to near the upper end of the shaft to convey the excavation waste to the ground together with the water, and the depth of the shaft. Excavated waste conveying pipe that is added as the depth of
An excavation shear discharging device provided with an earth discharging pump that supplies the water for conveyance of the shear to the water pipe portion,
The shaft excavation device, wherein the excavation waste discharging device is configured to transport the excavation waste to the ground by a water flow in the excavation waste transport pipe.
前記胴部材は、掘削方向向きに相対的に移動自在の後胴と前胴とを有し、
前記複数の推進用ジャッキとして、エレクタ装置で組付けられたセグメントに対して後胴を推進駆動する複数の第1ジャッキと、後胴に対して前胴を推進駆動する複数の第2ジャッキとを設けたことを特徴とする請求項1〜9の何れかに記載の立坑掘削装置。An erector device for assembling a segment on the inner surface of a tunnel excavated by the excavator is provided,
The trunk member has a rear trunk and a front trunk that are relatively movable in the direction of the excavation,
As the plurality of jacks for propulsion, a plurality of first jacks for driving the rear trunk with respect to the segment assembled by the elector device, and a plurality of second jacks for driving the front trunk with respect to the rear trunk. The shaft digging device according to any one of claims 1 to 9, wherein the shaft digging device is provided.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003133162A JP4131493B2 (en) | 2003-05-12 | 2003-05-12 | Shaft excavator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003133162A JP4131493B2 (en) | 2003-05-12 | 2003-05-12 | Shaft excavator |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004332487A true JP2004332487A (en) | 2004-11-25 |
JP4131493B2 JP4131493B2 (en) | 2008-08-13 |
Family
ID=33507799
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003133162A Expired - Fee Related JP4131493B2 (en) | 2003-05-12 | 2003-05-12 | Shaft excavator |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4131493B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5702500B1 (en) * | 2014-09-09 | 2015-04-15 | 株木建設株式会社 | Tunnel drilling equipment |
KR20170106150A (en) * | 2016-03-11 | 2017-09-20 | 한국과학기술원 | Vertical shaft excavation system and the construction method of vertical shaft using thereof |
CN107762523A (en) * | 2017-12-06 | 2018-03-06 | 徐州迈斯特机械科技有限公司 | A kind of constructing tunnel shield structure |
CN109630123A (en) * | 2018-07-23 | 2019-04-16 | 中国铁建重工集团有限公司 | Deep shaft rock ripper |
CN110080776A (en) * | 2019-05-14 | 2019-08-02 | 中国矿业大学 | A kind of fluid well-flushing dreg removing system suitable for shaft excavation machine |
CN114278326A (en) * | 2021-12-27 | 2022-04-05 | 上海市机械施工集团有限公司 | Truss type vertical shield tunneling machine and vertical shaft construction method |
US11891865B1 (en) | 2022-08-25 | 2024-02-06 | Hefei Design & Research Institute Of Coal Industry Co., Ltd | Full-face shaft tunnel boring machine system |
WO2024040966A1 (en) * | 2022-08-25 | 2024-02-29 | 煤炭工业合肥设计研究院有限责任公司 | Full-face boring machine system for vertical shaft |
-
2003
- 2003-05-12 JP JP2003133162A patent/JP4131493B2/en not_active Expired - Fee Related
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5702500B1 (en) * | 2014-09-09 | 2015-04-15 | 株木建設株式会社 | Tunnel drilling equipment |
KR20170106150A (en) * | 2016-03-11 | 2017-09-20 | 한국과학기술원 | Vertical shaft excavation system and the construction method of vertical shaft using thereof |
KR102002526B1 (en) * | 2016-03-11 | 2019-07-22 | 한국과학기술원 | Vertical shaft excavation system and the construction method of vertical shaft using thereof |
CN107762523A (en) * | 2017-12-06 | 2018-03-06 | 徐州迈斯特机械科技有限公司 | A kind of constructing tunnel shield structure |
CN109630123A (en) * | 2018-07-23 | 2019-04-16 | 中国铁建重工集团有限公司 | Deep shaft rock ripper |
CN109630123B (en) * | 2018-07-23 | 2024-02-02 | 中国铁建重工集团股份有限公司 | Rock tunneller for deep shaft |
CN110080776A (en) * | 2019-05-14 | 2019-08-02 | 中国矿业大学 | A kind of fluid well-flushing dreg removing system suitable for shaft excavation machine |
CN110080776B (en) * | 2019-05-14 | 2020-11-06 | 中国矿业大学 | Fluid well-flushing deslagging system suitable for vertical shaft heading machine |
CN114278326A (en) * | 2021-12-27 | 2022-04-05 | 上海市机械施工集团有限公司 | Truss type vertical shield tunneling machine and vertical shaft construction method |
CN114278326B (en) * | 2021-12-27 | 2024-02-20 | 上海市机械施工集团有限公司 | Truss type vertical shield machine and shaft construction method |
US11891865B1 (en) | 2022-08-25 | 2024-02-06 | Hefei Design & Research Institute Of Coal Industry Co., Ltd | Full-face shaft tunnel boring machine system |
WO2024040966A1 (en) * | 2022-08-25 | 2024-02-29 | 煤炭工业合肥设计研究院有限责任公司 | Full-face boring machine system for vertical shaft |
Also Published As
Publication number | Publication date |
---|---|
JP4131493B2 (en) | 2008-08-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103256057A (en) | Replacing device and method for disc cutters of tool head | |
CN111535813B (en) | Full-face shaft heading machine | |
JP2004332487A (en) | Shaft excavator | |
CN111058852A (en) | High-speed intelligent shield constructs machine | |
CN110700838A (en) | Vertical shaft construction method and system from bottom to top | |
JP6479892B2 (en) | Cutting crushing system, cutting crushing method, reconstruction promotion method | |
JP6703343B2 (en) | Propulsion device | |
JP6124284B2 (en) | Tunnel excavator | |
JP2006037518A (en) | Gas hydrate collecting method and gas hydrate collecting system | |
JP5599346B2 (en) | Tunnel excavator for renewal of existing pipes | |
JP6012073B2 (en) | How to replace excavation members of tunnel excavator | |
JP2015155634A (en) | Tunnel excavation system | |
CN219974501U (en) | Step type shield device and construction shield system | |
RU2172836C2 (en) | Universal tunneling units | |
KR200281084Y1 (en) | A tunnel boring machine | |
JP5539245B2 (en) | How to update existing pipelines | |
KR100977212B1 (en) | Horizontal ring type rotary drill system and method using the same | |
JP7290621B2 (en) | rock excavator | |
JP6062677B2 (en) | tube | |
JP5116993B2 (en) | Tunnel drilling machine for irregular section excavation | |
JP2005188281A (en) | Removing/backfilling device of jacking tunnel | |
Ofiara et al. | Faster underground mine development: Getting to first ore quicker using a novel noncircular tunneling machine. | |
JP4230482B2 (en) | Reconstruction promotion method for underground pipes | |
JP2528025B2 (en) | Tunnel excavation Sediment transportation method | |
JP4982646B2 (en) | Solid recovery system for shield machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060209 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20071107 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071114 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080109 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080521 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080521 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110606 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4131493 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110606 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120606 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120606 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130606 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140606 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |