JP2004300698A - Joint structural of pier and girder - Google Patents
Joint structural of pier and girder Download PDFInfo
- Publication number
- JP2004300698A JP2004300698A JP2003093067A JP2003093067A JP2004300698A JP 2004300698 A JP2004300698 A JP 2004300698A JP 2003093067 A JP2003093067 A JP 2003093067A JP 2003093067 A JP2003093067 A JP 2003093067A JP 2004300698 A JP2004300698 A JP 2004300698A
- Authority
- JP
- Japan
- Prior art keywords
- girder
- pier
- steel
- steel frame
- main
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、鉄骨コンクリート造の橋脚とこの橋脚上に支承された鋼製の桁とを一体化して結合した構造に関するものである。
【0002】
【従来の技術】
従来、道路橋などの橋脚と桁との結合構造においては、鉄筋コンクリート造の橋脚を構築し、この橋脚の上に鋼製の桁を支承し、橋脚と桁とを互いに結合させている(たとえば、特許文献1を参照)。
従来の橋脚と桁との結合構造の一例を図8及び図9を参照しつつ説明する。図8に示すように、鉄筋コンクリート造の橋脚10がその上に鋼製の桁4を支承し、桁4の上に道路2が形成されている。橋脚10の内部には鉄筋である主筋12の集合体が鉛直方向に配筋されており、主筋12の集合体の全長にわたってその集合体の周囲には剪断補強筋14をなす鉄筋が間隔をあけて配筋されている(図9を参照)。なお、図8において、剪断補強筋14の図示は省略されている。
【0003】
橋脚10は、その下端から桁4の下端よりもやや低い高さまでを一次施工用のコンクリート22により充填されており、この一次施工用コンクリート22の上端から主筋12と剪断補強筋14が上方に突出して鉄筋の突出部分13を形成している。
桁4は主桁4Mと横桁4Sとからなり、主桁4Mは道路2の進行方向に延びるI型鋼の桁であり、横桁4Sは主桁4Mの間に張り渡されたI型鋼の桁であり、主桁4Mと横桁4Sは互いに交差して桁組を形成している。これらの横桁4Sと主桁4Mとからなる桁組の間に突出部分13の上部分が入り込んでいる。
【0004】
また、突出部分13の上部分にある主筋12の集合体は横桁4Sと向かい合っており、主桁4Mの一部分が突出部分13の主筋12の集合体の間に挟まれている。そして、橋脚10の一次施工用コンクリート22よりも上方には、二次施工用のコンクリート24が充填されており、突出部分13は二次施工用コンクリート24中に埋没し、突出部分13及びこの突出部分13に向き合う横桁4Sとの間も二次施工用コンクリート24が充填されている。したがって、突出部分13の主筋12の間に挟まれている主桁4Mの一部分も、二次施工用コンクリート24中に埋没している。
【0005】
さらに、充填された二次施工用コンクリート24と接する横桁4Sの腹板8Sの面上には、多数のスタッドジベル26が植設されている。このスタッドジベル26は鋲状部材であり、その頭部分が腹板8Sの面上から突出しており、この突出した頭部分は二次施工用コンクリート24中に埋没している。また、突出部分13の主筋12の間に挟まれて二次施工用コンクリート24中に埋没している主桁4Mの面上にも、同様にスタッドジベル26が植設されている。
そして、橋脚10の二次施工用コンクリート24が充填された部分と、二次施工用コンクリート24に接触している主桁4M及び横桁4Sの部分とが剛結部34を形成し、この剛結部34が橋脚10と桁4とを結合している。
【0006】
【特許文献1】
特開平4―92007号公報(第1〜4頁、第1〜15図)
【0007】
【発明が解決しようとする課題】
しかしながら、従来の橋脚10と桁4との結合構造においては、橋脚10の曲げ耐力を確保するために剪断補強筋14を密に配筋する必要があり、剛結部34内でスタッドジベル26が主筋12及び剪断補強筋14と干渉し合う箇所が多数発生してしまうという不具合があった。すなわち、剛結部34内の主筋12及び剪断補強筋14とこれらに対向する横桁4Sの腹板8Sとの間の距離が短いと、スタッドジベル26の頭部分が主筋12及び剪断補強筋14と接触して干渉箇所を生じる。このような干渉箇所があると、主筋12及び剪断補強筋14の配筋に支障をきたす。また、主筋12を桁4の下フランジに貫通させる必要が生じる場合もある。したがって、これらの干渉箇所を少なくするために、剛結部34内における主筋12及び剪断補強筋14の配筋状態を変えなければならず、作業が煩雑になっていた。
【0008】
また、スタッドジベル26と主筋12及び剪断補強筋14との間の干渉箇所が多数存在すると、剛結部34へ二次施工用コンクリート24を充填する作業が困難となる。このため、煩雑な型枠設置作業が必要となる等の施工上の不具合もあった。
さらに、桁4と橋脚10の主筋12及び剪断補強筋14とが剛結部34内において二次施工用コンクリート24を介して互いに結合しているが、主桁4Mや横桁4Sの高さが低い場合には、横桁4Sと橋脚10とを結合する剛結部34の部分の縦方向長さ(定着長L)が短くなってしまう。定着長Lを充分大きくとることができないと、継手等の手段を用いて桁4と橋脚10との間の結合を補強しなければならないという不具合もあった。
【0009】
また、剛結部34における橋脚10と桁4との結合は二次施工用コンクリート24を介して行われているので、橋脚10と桁4との結合面が開口してしまった場合に備えておく必要があり、主筋12及び剪断補強筋14に防食対策を施しておく必要もあった。
本発明は、上記した従来の技術の問題点を除くためになされたものであり、その目的とするところは、桁と橋脚との間を強固に結合でき、橋脚を構築して桁と結合する際に必要な配筋作業を簡略化して施工性を向上させることができ、桁の高さが低い場合でも橋脚と桁との間の強固な結合を確保できる橋脚と桁との結合構造を提供することである。
【0010】
【課題を解決するための手段】
本発明は、その課題を解決するために以下のような構成をとる。請求項1の発明は、鉄骨コンクリート造の橋脚と、当該橋脚上に支承された鋼製の桁との結合構造であって、前記橋脚上部から突出させた鉄骨の上端部と前記桁とを結合し、この突出部分と前記桁との間に硬化材を充填した橋脚と桁との結合構造である。
【0011】
請求項1の発明によると、橋脚の突出部分の鉄骨の上端部と桁との間の結合と、突出部分と桁との間の硬化材を介した結合とによって、橋脚と桁とは結合されている。鉄骨と桁を結合しているので、主筋としての鉄筋は不要である。したがって、剛結部内の鉄筋の配筋を省略でき、突出部分と桁との間に硬化材を充填する作業も容易になる。また、桁の高さが低い場合でも、鉄骨と桁と結合しているので、橋脚と桁の間の定着長Lの長さが不足して橋脚と桁の結合が弱くなることは防止される。
【0012】
請求項2の発明は、請求項1に記載の橋脚と桁との結合構造であって、前記鉄骨の上端部と前記桁の下面とを、溶接及び締結具のうち少なくともいずれか一方の手段を用いて結合した橋脚と桁との結合構造である。
請求項2の発明によると、橋脚の鉄骨の上端部と桁との結合を溶接と締結具のうち少なくともいずれか一方の手段により行うので、鉄骨は桁と強固に結合され、橋脚は桁と一体化する。なお、締結具としては、例えば、ボルトとナット等を挙げることができる。
【0013】
請求項3の発明は、請求項1又は請求項2に記載の橋脚と桁との結合構造であって、前記鉄骨を形鋼とした橋脚と桁との結合構造である。
請求項3の発明によると、形鋼によって橋脚の鉄骨は形成されており、橋脚の曲げ耐力が確保され、橋脚の強度が向上する。なお、形鋼としてH形鋼、山形鋼、みぞ形鋼、T形鋼、I形鋼等を挙げることができる。
【0014】
請求項4の発明は、請求項1又は請求項2に記載の橋脚と桁との結合構造であって、前記鉄骨を鋼管とした橋脚と桁との結合構造である。
請求項4の発明によると、鋼管によって橋脚の鉄骨は形成されており、橋脚の曲げ耐力が確保され、橋脚の強度が向上する。
請求項5の発明は、請求項1ないし請求項4に記載の橋脚と桁との結合構造であって、前記桁と結合された鋼板を介して前記鉄骨の上端部と前記桁とを結合した橋脚と桁との結合構造である。
【0015】
請求項5の発明によると、橋脚の鉄骨は桁の下の鋼板と結合し、この鋼板が桁と結合されているので、橋脚と桁が強固に一体化する。また、鋼鈑を介して鉄骨は桁と結合しているので、桁の直下に鉄骨の上端部がない場合であっても桁と鉄骨との結合が可能となる。
【0016】
【発明の実施の形態】
本発明の第1の実施の形態を図面に基づいて説明する。
まず、図1ないし図6を参照して本実施の形態の構成を説明する。図1は本実施の形態に係る橋の側面図であり、図2は図1のA−A線縦断面図、図3は本実施の形態に係る橋脚の正面図、図4は図3のB−B線横断面図、図5は図3のC−C線横断面図、図6は本実施の形態に係る鉄骨と桁の結合部分の構成図である。なお、図3及び図5において、一次施工用コンクリート又は二次施工用コンクリートの図示を一部分省略してある。
【0017】
図1及び図2に示すように、橋1は橋脚10、桁4、道路2とから形成されている。橋脚10の上に、I形鋼からなる主桁4MとI形鋼からなる横桁4Sとからなる桁4が組まれて載っており、桁4の上に道路2が載っている。
図3及び図4に示すように、橋脚10は水平断面が矩形をなす鉄骨鉄筋コンクリート製の柱状構築物であり、内部には主筋として作用するH型鋼からなる鉄骨16、剪断補強筋14をなす鉄筋を有する。
【0018】
橋脚10内で、複数本の鉄骨16からなる集合体が橋脚10の周方向に口の字形の水平断面を形成して配設されている。また、鉄骨16の集合体の周囲には剪断補強筋14が巻きつけられており、この剪断補強筋14は鉄骨16の下部から上部にかけてほぼ一様な間隔で複数配筋されている。さらに、鉄骨16の上端部18Aの高さは横桁4Sの下部フランジ6SLよりもやや低い高さである。
【0019】
そして、図3及び図6に示すように、鉄骨16の上端部18Aの上には、高さ及び水平位置を調節するための調整用部材20がつなげられており、鉄骨16の長さが上方に延長されている。調整用部材20の上端部18Bの上には、さらに、仕口部材21がつなげられており、鉄骨16の長さが上方に延長されている。仕口部材21の上端部は、延長された鉄骨16の最上端部18Cをなし、この最上端部18Cは後述の天板32の下面につながっている。調整用部材20及び仕口部材21は、鉄骨16と同じH形鋼である。鉄骨16の上端部18Aと調整用部材20との接続部分は、鉄骨16と調整用部材20との間に架け渡された鋼製の接合板36が高力ボルト30とナットを用いて止められている。また、調整用部材20の上端部18Bと仕口部材21との間も、鉄骨16と調整用部材20との間と同様に接続されている。
【0020】
また、鉄骨16の上端部18Aよりやや下の高さまで橋脚10の中に充填されているコンクリートは、橋脚10と桁4を結合する前に充填された一次施工用コンクリート22である。一次施工用コンクリート22の上端から上側にある鉄骨16及び剪断補強筋14が上方に突出して、突出部分13を形成している。
さらに、図6に示すように、各鉄骨16の最上端部18Cの上にはそれぞれ鋼製の天板32が溶接により取り付けられており、これらの天板32の上には鋼製の底板28がのっている。各天板32は底板28の下面とは、溶接または高力ボルト30を用いた締結手段により締結され、各鉄骨16、天板32及び底板28は一体化している。
【0021】
また、図3に示すように、図4において口の字形をなす鉄骨16のうち上下の各辺を形成する鉄骨16の上には、底板28を介して、横桁4Sa、4Sbの各下側フランジ6SLの下面が載っている。図3に示すように、図4において口の字形をなす鉄骨16のうち左右の各辺を形成する鉄骨16よりも外側上方に、主桁4Ma、4Mbが位置している。主桁4Ma、4Mbの各下側フランジ6MLは底板28よりも下方の高さに位置するとともに、横桁4Sa、4Sbの各下側フランジ6SLよりも低い位置にある。また、主桁4Ma、4Mbの各上側フランジ6MUは横桁4Sa、4Sbの各上側フランジ6SUよりも高い位置にある。そして、橋脚10の突出部分13は主桁4Ma、4Mbの間に挟まれている。
【0022】
また、底板28の縁は、主桁4Ma、4Mb及び横桁4Sa、4Sbまで張り出している。そして、底板28の各縁は主桁4Ma、4Mbの各腹板8Mに溶接と高力ボルトを用いた締結手段により結合されているとともに、横桁4Sa、4Sbの各下側フランジ6SLの下面とも溶接と高力ボルトを用いた締結手段により結合されている。
【0023】
また、図5に示すように、主桁4Ma、4Mb及び横桁4Sa、4Sbによって囲まれた井桁の中に、I型鋼からなる2枚の隔壁5a、5bが形成されている。隔壁5a、5bの各下側フランジ6WLは、底板28を介して、図4において口の字形をなす鉄骨16のうち左右の各辺を形成する鉄骨16の上端にある仕口部材21の上に載っている。隔壁5a、5bの各下側フランジ6WL、底板28及び仕口部材21は、溶接または高力ボルトを用いた締結手段により結合されている。また、隔壁5a、5bと横桁4Sa、4Sbとの間は、溶接または高力ボルトを用いた締結手段により結合されている。
【0024】
また、図3及び図5に示すように、橋脚10の一次施工用コンクリート22の上端から底板28にかけての部分は硬化材である二次施工用のコンクリート24によって充填されている。さらに、底板28から上の主桁4Ma、4Mb及び横桁4Sa、4Sbによって囲まれた部分も二次施工用コンクリート24を充填してあり、突出部分13の鉄筋はすべて二次施工用コンクリート24中に埋没しているとともに、隔壁5a、5bも二次施工用コンクリート24中に埋没している。
【0025】
また、主桁4の上側フランジ6MU上には道路2が形成されており、主桁4が道路2を支承している。
本実施の形態は上記のように構成されており、次にその作用について説明する。
橋脚10は鉄骨16を内側に有し、これらの鉄骨16が橋脚10の強度を支えているので、主筋は不要となる。主筋がないので、橋脚10を構築する際の配筋作業が簡易化される。
【0026】
また、鉄骨16の上端部18Aと底板28の下面との間には、調整用部材20及び仕口部材21が存在してつないでいるので、橋脚10に一次施工用コンクリート22を打設した後、鉄骨16の上端部18Aの高さ位置に誤差が存在しても、この誤差を調整用部材20及び仕口部材21により調整することができる。
【0027】
さらに、調整用部材20及び仕口部材21により延長された鉄骨16の最上端部18Cが底板28の下面と結合し、底板28は主桁4Ma、4Mb及び横桁4Sa、4Sb、隔壁5a、5bと結合しているので、鉄骨16は主桁4Ma、4Mb、横桁4Sa、4Sb、隔壁5a、5bと直結した構造となっており、桁4から曲げモーメント等の断面力は鉄骨16を介して橋脚10へ直接伝達される。したがって、剪断補強筋14の数を減らすことが可能となる。このため、突出部分13において、主筋12の集合体の周りに配筋する剪断補強筋14の数を減少させることができ、前述のように主筋12の数も減少させることができるので、突出部分13における配筋量が減少し、主筋12及び剪断補強筋14の間の間隔を大きくとることができる。このため、鋲部材であるスタッドジベルが主桁4Ma、4Mbの各腹板8M上に植設されている場合であっても、スタッドジベルが剪断補強筋14と干渉しあう箇所の数は減少する。
【0028】
また、底板28から上方の主桁4Ma、4Mb及び横桁4Sa、4Sbによって囲まれた部分に二次施工用コンクリート24を打設しているので、底板28、主桁4Ma、4Mb及び横桁4Sa、4Sbが二次施工用コンクリート24用の型枠の役割を果たす。したがって、二次施工用コンクリート24充填のための作業が簡易なものとなり、二次施工用コンクリート24充填時の施工性が向上する。
【0029】
また、二次施工用コンクリート24中に埋没している隔壁5a、5bは、二次施工用コンクリート24内で骨格をなし、二次施工用コンクリート24の強度が向上し、橋脚10と桁4との結合部分の剛性も向上する。
また、主桁4Mや横桁4Sの縦方向長さが短い場合であっても、主桁4Mや横桁4Sは鉄骨16と直結しているので結合上の問題はない。二次施工用コンクリート24を介した突出部分13の鉄骨16と主桁4Ma、4Mb及び横桁4Sa、4Sbとの間の定着長Lは短くなるが、鉄骨16が底板28を介して桁4と結合されている。したがって、継手等の手段を用いて桁4と橋脚10との間の定着長Lの短さを補う必要はなくなる。
【0030】
また、本実施の形態において橋脚10は断面が矩形で、鉄骨16をH形鋼により構成したが、替わりに、図7の変形例に示すような構成の橋脚10とすることも可能である。すなわち、鉄骨を円形鋼管38により形成し、この円形鋼管38の内周沿いに主筋12の集合体を配筋し、円形鋼管38の内側に一次施工用コンクリート22を充填し、橋脚10を構成する。円形鋼管38を鉄骨とすることで、橋脚10内への一次施工用コンクリート22の充填を型枠を使用せずに行うことができる。
【0031】
さらに、本実施の形態において鉄骨16をH形鋼により構成したが、H形鋼の替わりに、山形鋼、みぞ形鋼、T形鋼、I形鋼等により鉄骨16を構成できることは勿論である。
また、本実施の形態において鉄骨16を天板32及び底板28を介して桁4に結合したが、以下に説明する結合とすることも可能である。すなわち、各鉄骨16を主桁4Ma、4Mb、横桁4Sa、4Sbの直下に配置し、各鉄骨16の長さを高さ調整用部材20で調整し、延長された各鉄骨16の上端部18Bを直上にあるいずれかの主桁4Ma、4Mb、横桁4Sa、4Sbに溶接により直接結合する。このような鉄骨16と桁4との結合によっても、橋脚10と桁4を強固に結合して一体化することができる。
【0032】
【発明の効果】
本発明は、上記のような橋脚と桁との結合構造であるので、桁と橋脚との間を強固に結合でき、橋脚を構築して桁と結合する際に必要な配筋作業を簡略化して施工性を向上させることができ、桁の高さが低い場合でも橋脚と桁との間の強固な結合を確保できる橋脚と桁との結合構造を提供できるという効果がある。
【図面の簡単な説明】
【図1】本実施の形態に係る橋の側面図である。
【図2】図1のA−A線縦断面図である。
【図3】本実施の形態に係る橋脚の正面図である。
【図4】図3のB−B線横断面図である。
【図5】図3のC−C線横断面図であり、一部分の二次施工用コンクリートの図示及び一部分の底板の図示を省略した図である。
【図6】本実施の形態に係る鉄骨と桁の結合部分の構成図である。
【図7】本実施の形態の変形例に係る橋脚の横断面図である。
【図8】従来の橋脚と桁の結合部分の構成図である。
【図9】従来の橋脚が有する主筋と剪断補強筋の構成図である。
【符号の説明】
1 橋
2 道路
4 桁
4M、4Ma、4Mb 主桁
4S、4Sa、4Sb 横桁
5a、5b 隔壁
6ML 主桁の下側フランジ
6MU 主桁の上側フランジ
6SU 横桁の上部フランジ
6SL 横桁の下部フランジ
6WL 隔壁の下部フランジ
8M 主桁の腹板
8S 横桁の腹板
10 橋脚
12 主筋
13 鉄筋の突出部分
14 剪断補強筋
16 鉄骨
18A 鉄骨の上端部
18B 調整用部材の上端部
18C 調整用部材及び仕口部材により延長された鉄骨の最上端部
20 調整用部材
21 仕口部材
22 一次施工用コンクリート
24 二次施工用コンクリート
26 スタッドジベル
28 底板
30 高力ボルト
32 天板
34 剛結部
38 円形鋼管
L 定着長[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a structure in which a steel concrete pier and a steel girder supported on the pier are integrated and connected.
[0002]
[Prior art]
Conventionally, in a joint structure between a pier and a girder such as a road bridge, a reinforced concrete pier is constructed, a steel girder is supported on the pier, and the pier and the girder are connected to each other (for example, See Patent Document 1).
An example of a conventional connection structure between a pier and a girder will be described with reference to FIGS. As shown in FIG. 8, a
[0003]
The
The
[0004]
The aggregate of the
[0005]
Furthermore, a large number of
Then, the portion of the
[0006]
[Patent Document 1]
JP-A-4-92007 (Pages 1 to 4, FIGS. 1 to 15)
[0007]
[Problems to be solved by the invention]
However, in the conventional connection structure between the
[0008]
In addition, if there are many interference locations between the
Further, the
[0009]
In addition, since the connection between the
The present invention has been made in order to eliminate the above-mentioned problems of the conventional technology, and an object of the present invention is to enable a firm connection between a girder and a pier, construct a pier, and connect the girder. Provide a pier-to-girder joint structure that can simplify the necessary reinforcing work and improve workability, and secure a strong connection between the pier and the girder even when the girder height is low. It is to be.
[0010]
[Means for Solving the Problems]
The present invention has the following configuration to solve the problem. The invention according to claim 1 is a joint structure between a steel concrete pier and a steel girder supported on the pier, wherein an upper end portion of a steel frame protruding from an upper portion of the pier and the girder are joined. In addition, a bridge pier and a girder are filled with a hardening material between the protruding portion and the girder.
[0011]
According to the invention of claim 1, the pier and the girder are connected by the connection between the upper end portion of the steel frame and the girder of the protruding portion of the pier and the connection between the protruding portion and the girder via the hardening material. ing. Since the steel frame and the girder are joined, the reinforcing bar as the main bar is unnecessary. Therefore, it is possible to omit the arrangement of the reinforcing bars in the rigid connection portion, and the work of filling the hardening material between the projecting portion and the girder becomes easy. Also, even when the height of the girder is low, since the steel frame is connected to the girder, it is possible to prevent the anchorage length L between the pier and the girder from being insufficient and the connection between the pier and the girder to be weakened. .
[0012]
According to a second aspect of the present invention, there is provided the joint structure between the pier and the girder according to the first aspect, wherein an upper end portion of the steel frame and a lower surface of the girder are welded and / or fastened by a fastener. It is a joint structure between a pier and a girder that are joined by using.
According to the invention of
[0013]
According to a third aspect of the present invention, there is provided a joint structure between the pier and the girder according to the first or second aspect, wherein the pier and the girder are formed of steel.
According to the third aspect of the present invention, since the steel frame of the pier is formed by the shape steel, the bending strength of the pier is secured, and the strength of the pier is improved. In addition, H-shaped steel, angle iron, grooved steel, T-shaped steel, I-shaped steel, etc. can be mentioned as a shape steel.
[0014]
According to a fourth aspect of the present invention, there is provided a joint structure between the pier and the spar according to the first or second aspect, wherein the pier and the spar are formed by using the steel frame as a steel pipe.
According to the invention of
According to a fifth aspect of the present invention, there is provided a connecting structure between the pier and the girder according to any one of the first to fourth aspects, wherein an upper end portion of the steel frame and the girder are connected via a steel plate connected to the girder. It is a connection structure between a pier and a girder.
[0015]
According to the invention of claim 5, the steel frame of the pier is joined to the steel plate below the girder, and since this steel plate is joined to the girder, the pier and the girder are firmly integrated. Further, since the steel frame is connected to the girder via the steel plate, the girder can be connected to the steel frame even when there is no upper end portion of the steel frame directly below the girder.
[0016]
BEST MODE FOR CARRYING OUT THE INVENTION
A first embodiment of the present invention will be described with reference to the drawings.
First, the configuration of the present embodiment will be described with reference to FIGS. FIG. 1 is a side view of a bridge according to the present embodiment, FIG. 2 is a vertical sectional view taken along line AA of FIG. 1, FIG. 3 is a front view of a pier according to the present embodiment, and FIG. FIG. 5 is a cross-sectional view taken along line BB of FIG. 3, FIG. 5 is a cross-sectional view taken along line CC of FIG. 3, and FIG. In FIG. 3 and FIG. 5, illustration of the concrete for primary construction or the concrete for secondary construction is partially omitted.
[0017]
As shown in FIGS. 1 and 2, the bridge 1 includes a
As shown in FIGS. 3 and 4, the
[0018]
In the
[0019]
As shown in FIGS. 3 and 6, an adjusting
[0020]
The concrete filled in the
Further, as shown in FIG. 6, a
[0021]
As shown in FIG. 3, the lower sides of the cross beams 4Sa and 4Sb are placed on the steel frames 16 forming the upper and lower sides of the steel frames 16 forming the mouth shape in FIG. The lower surface of the flange 6SL rests. As shown in FIG. 3, the main girders 4Ma and 4Mb are located outside and above the steel frames 16 forming the left and right sides of the steel frames 16 forming the mouth shape in FIG. The lower flanges 6ML of the main girders 4Ma, 4Mb are located at a height lower than the
[0022]
The edge of the
[0023]
Further, as shown in FIG. 5, two
[0024]
As shown in FIGS. 3 and 5, the portion from the upper end to the
[0025]
The
This embodiment is configured as described above, and its operation will be described next.
The
[0026]
In addition, since the adjusting
[0027]
Further, the
[0028]
Moreover, since the concrete 24 for secondary construction is cast in the part surrounded by the main girder 4Ma, 4Mb and the horizontal girder 4Sa, 4Sb above the
[0029]
In addition, the
Further, even when the length of the
[0030]
Further, in the present embodiment, the
[0031]
Further, in the present embodiment, the
In addition, in the present embodiment, the
[0032]
【The invention's effect】
Since the present invention has the joint structure between the pier and the girder as described above, the girder and the pier can be firmly joined to each other, and the reinforcing work required for constructing the pier and joining with the girder can be simplified. Therefore, there is an effect that it is possible to provide a joint structure between the pier and the girder which can secure a strong connection between the pier and the girder even when the height of the girder is low.
[Brief description of the drawings]
FIG. 1 is a side view of a bridge according to an embodiment.
FIG. 2 is a vertical sectional view taken along line AA of FIG.
FIG. 3 is a front view of the pier according to the present embodiment.
FIG. 4 is a cross-sectional view taken along the line BB of FIG. 3;
5 is a cross-sectional view taken along the line CC of FIG. 3 and omitting illustration of a part of concrete for secondary construction and illustration of a part of a bottom plate.
FIG. 6 is a configuration diagram of a joint portion between a steel frame and a girder according to the present embodiment.
FIG. 7 is a cross-sectional view of a pier according to a modification of the present embodiment.
FIG. 8 is a configuration diagram of a conventional joint portion between a pier and a girder.
FIG. 9 is a configuration diagram of a main reinforcing bar and a shear reinforcing bar of a conventional pier.
[Explanation of symbols]
1
Claims (5)
前記橋脚上部から突出させた鉄骨の上端部と前記桁とを結合し、
この突出部分と前記桁との間に硬化材を充填したことを特徴とする橋脚と桁との結合構造。A joint structure of a steel concrete pier and a steel girder supported on the pier,
Combine the upper end of the steel frame protruding from the pier upper part and the girder,
A joint structure between a pier and a girder, wherein a hardening material is filled between the projecting portion and the girder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003093067A JP4232508B2 (en) | 2003-03-31 | 2003-03-31 | Connecting structure of pier and girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003093067A JP4232508B2 (en) | 2003-03-31 | 2003-03-31 | Connecting structure of pier and girder |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004300698A true JP2004300698A (en) | 2004-10-28 |
JP4232508B2 JP4232508B2 (en) | 2009-03-04 |
Family
ID=33405946
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003093067A Expired - Lifetime JP4232508B2 (en) | 2003-03-31 | 2003-03-31 | Connecting structure of pier and girder |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4232508B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007107339A (en) * | 2005-10-17 | 2007-04-26 | Mitsui Eng & Shipbuild Co Ltd | Structure and its construction method for steel concrete compound rigid frame bridge |
-
2003
- 2003-03-31 JP JP2003093067A patent/JP4232508B2/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007107339A (en) * | 2005-10-17 | 2007-04-26 | Mitsui Eng & Shipbuild Co Ltd | Structure and its construction method for steel concrete compound rigid frame bridge |
Also Published As
Publication number | Publication date |
---|---|
JP4232508B2 (en) | 2009-03-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101186062B1 (en) | Connection of concrete filled steel tube column and H-shaped steel beam and constructing method of the same | |
KR20130012898A (en) | Joint of steel column | |
JP5977904B1 (en) | Construction method of simple temporary bridge | |
KR20180058962A (en) | Seismic retrofit structure | |
JP2742994B2 (en) | Bridge pier reinforcement method | |
KR101346679B1 (en) | Steel Assembly for Composite Beam and Composite Beam Using the same | |
KR101962788B1 (en) | Temporary bridge construction method using steel girder and composite deck-plate and temporary bridge therewith | |
JPH11148110A (en) | Continuous girder bridge | |
KR20140058226A (en) | Slim floor system using built-up type steel beam made of plate and box-pipe | |
KR200383309Y1 (en) | Form system for construction of underground slab | |
JP2004300698A (en) | Joint structural of pier and girder | |
JP2004225290A (en) | Composite floor-slab girder | |
KR20130000775U (en) | Construction structure for joining steel or reinforced steel concrete column and beam with reinforcing end part | |
KR20170139873A (en) | Coupling structure of double type for girder and column capable of reducing girder height | |
JPH04254646A (en) | Steel framed reinforced concrete beam | |
JP2009161905A (en) | Composite hollow structure of column head part or girder end part of bridge | |
JP2001172916A (en) | Corrugated synthetic floor slab | |
JP2004238801A (en) | Aseismic reinforcement structure | |
JP3437785B2 (en) | Corrugated steel web girder | |
JP3232517U (en) | Seismic retrofitting structure | |
JP2003213622A (en) | Steel girder bridge using concrete cross beam | |
KR101327916B1 (en) | Diaphragm frame for spc wall girder, spc wall girder using diaphragm frame and construction method trerewith | |
JP2013181334A (en) | Earthquake strengthening method of building | |
JP6630776B2 (en) | Construction method of slab structure | |
JP6850578B2 (en) | Structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060310 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20071220 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080205 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080407 |
|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A712 Effective date: 20080428 |
|
RD03 | Notification of appointment of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7423 Effective date: 20080501 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080902 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081021 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20081118 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20081201 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111219 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4232508 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111219 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121219 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121219 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131219 Year of fee payment: 5 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
EXPY | Cancellation because of completion of term |