JP2004229081A - Method for witnessing engineering work test - Google Patents

Method for witnessing engineering work test Download PDF

Info

Publication number
JP2004229081A
JP2004229081A JP2003016217A JP2003016217A JP2004229081A JP 2004229081 A JP2004229081 A JP 2004229081A JP 2003016217 A JP2003016217 A JP 2003016217A JP 2003016217 A JP2003016217 A JP 2003016217A JP 2004229081 A JP2004229081 A JP 2004229081A
Authority
JP
Japan
Prior art keywords
test
construction
specimen
supervisor
status
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2003016217A
Other languages
Japanese (ja)
Inventor
Rikuta Murakami
陸太 村上
Yasuhiko Yamashita
靖彦 山下
Yasukazu Fujimoto
康和 藤本
Yoshinori Matsubara
由典 松原
Akira Sumi
彰 角
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2003016217A priority Critical patent/JP2004229081A/en
Publication of JP2004229081A publication Critical patent/JP2004229081A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
  • Closed-Circuit Television Systems (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To decrease time burdens of individual persons attending to witness an engineering work test. <P>SOLUTION: A method for witnessing the test of an engineering work where a test work preparer 1, a testing operator 2, and a test administrator 3 for administrating the engineering work test attend together to test the engineering work when the testing operator 2 tests the engineering work 7 prepared by the test work preparer 1. At least the testing operator 2 and the test administrator 3 are connected each other to be able to freely transmit information through a communication network N. During the engineering work test, the testing operator 2 transmits the test administrator 3 an engineering work testing state in real time, and the test administrator 3 transmits the testing operator 2 an electronic signature confirming a engineering work test condition. The engineering test condition and an electronic signature are recorded in a server Cs as a transmission record. <P>COPYRIGHT: (C)2004,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は、試験体作成者が作成した工事試験体を対象にして、試験実施者が該当工事試験を実施するに当たり、前記試験体作成者と、前記試験実施者と、該当工事試験を監理する試験監理者とが立ち会って行う工事試験立会い方法に関する。
【0002】
【従来の技術】
工事試験とは、例えば、建築工事においては、材料の強度試験(構造体コンクリートの圧縮試験や、鉄筋の圧接継手の引張試験)等が例として挙げられる。
例えば、コンクリート強度の試験の場合は、予め決められた配合によって練られたコンクリートの供試体(工事試験体に相当)を造り、その供試体を所定の養生期間を経て圧縮試験にかけるという流れで実施される。その圧縮試験の際には、供試体を作成した試験体作成者(例えば、建築施工会社)、圧縮試験を実行する試験実施者(例えば、試験機関)、該当工事試験を監理する試験監理者(例えば、施主)がそれぞれ一同に会して工事試験が行われるのが一般的であった。
従来、この種の工事試験立会い方法としては、まず、試験体作成者が、試験監理者の立会いの下で供試体を作成する。そして、その供試体の養生後に工事試験の日程を設定して前記試験監理者に連絡し、その工事試験日程に基づいて、工事試験装置が備えられた箇所(例えば、試験機関)に供試体を持ち込んで、試験体作成者、試験実施者、試験監理者が集まって、一同が確認できる試験環境で工事試験を実施するといったものであった。
尚、この様な従来技術に関しては、先行技術調査を行うまでもなく、当業者の間で広く知られているものであることから、先行技術文献は示していない。
【0003】
【発明が解決しようとする課題】
上述した従来の工事試験立会い方法によれば、工事試験の実施場所まで、試験体作成者、試験実施者、試験監理者のそれぞれが出向く必要があり、それに伴っては、工事試験を行う時間に加えて、その場所に移動するための時間がそれぞれに必要となり、各自の時間負担が大きい問題点があった。更には、工事試験に向けた各自の時間調整にも手間が掛かると言った問題点があった。
【0004】
従って、本発明の目的は、上記問題点を解消し、工事試験立会い者各自の時間負担を軽減し易い工事試験立会い方法を提供するところにある。
【0005】
【課題を解決するための手段】
請求項1の発明の特徴構成は、試験体作成者が作成した工事試験体を対象にして、試験実施者が該当工事試験を実施するに当たり、前記試験体作成者と、前記試験実施者と、該当工事試験を監理する試験監理者とが立ち会って行う工事試験立会い方法において、予め、少なくとも試験実施者と試験監理者とを、互いに通信ネットワークを介して情報伝達自在な状態に接続しておき、工事試験の実施に伴って、前記試験実施者から前記試験監理者に工事試験状況をリアルタイムで送信すると共に、前記試験監理者から前記試験実施者に工事試験状況を確認した電子署名をリアルタイムで送信し、これらの送信記録として、前記工事試験状況と、前記電子署名とをサーバに記録しておくところにある。
【0006】
請求項1の発明の特徴構成によれば、少なくとも試験実施者と試験監理者とを、互いに通信ネットワークを介して情報伝達自在な状態に接続しておき、工事試験の実施に伴って、前記試験実施者から前記試験監理者に工事試験状況をリアルタイムで送信すると共に、前記試験監理者から前記試験実施者に工事試験状況を確認した電子署名をリアルタイムで送信し、これらの送信記録として、前記工事試験状況と、前記電子署名とをサーバに記録しておくから、試験監理者は、工事試験の実施場所まで出向かずに、工事試験の状況を、リアルタイムで且つありのままの状態で確認することができる。従って、通信ネットワークが繋がる環境であれば、試験実施者と試験監理者との居場所は全く自由で、工事試験の実施場所に移動するための時間を省略することが可能となる他、他の作業と並行させた状態での工事試験監理を実施することが可能となり、工事試験参加者各自の時間負担を軽減することが可能となる。
また、このような工事試験の状況や、試験監理者が工事試験を確認した証としての電子署名がサーバに記録してあることで、該当工事試験の正当性、信憑性の維持を図ることが可能となる。更には、記録されたデータは、前記供試体作成者、前記試験実施者、前記試験監理者のそれぞれが、後日、当該工事試験の情報として利用することが可能となる。
【0007】
請求項2の発明の特徴構成は、前記通信ネットワークを介して前記工事試験の立ち会いに参加している参加者のアクセス状況は、各参加者にリアルタイムで公開されているところにある。
【0008】
請求項2の発明の特徴構成によれば、請求項1の発明による作用効果を叶えることができるのに加えて、工事試験に関わる参加者どうしのアクセス状況を、それぞれの参加者がリアルタイムで認識することが可能となり、該当工事試験の正当性や信憑性の維持を、より好ましい状態で図ることが可能となる。
【0009】
請求項3の発明の特徴構成は、前記工事試験状況は、少なくとも工事試験の状況をカメラで撮影した映像情報として送信され、前記カメラは、前記試験監理者側から遠隔操作自在に構成してあるところにある。
【0010】
請求項3の発明の特徴構成によれば、請求項1又は2の発明による作用効果を叶えることができるのに加えて、試験監理者側からカメラを遠隔操作して、試験監理を実施し易い状態で工事試験を確認することが可能となり、よりきめの細かい試験監理を効率よく実現することが可能となる。更には、試験監理者の遠隔操作の内容の通りに、試験監理者側のモニターの表示画面が変化する様を確認することができ、前記表示画面が作り物でないことの証として確認することができる。
【0011】
請求項4の発明の特徴構成は、前記工事試験体には、その試験体を特定するラベルを予め設けておくところにある。
【0012】
請求項4の発明の特徴構成によれば、請求項1〜3の何れかの発明による作用効果を叶えることができるのに加えて、試験体を取り違えて工事試験を実施してしまうことを防止でき、より正確な状態での工事試験が可能となる。
尚、このラベルは、試験監理者側のモニターでも確認することができるから、工事試験者が目視によってラベル確認すると共に、試験監理者もモニター上で試験体を確認することができる。
【0013】
【発明の実施の形態】
以下に本発明の実施の形態を図面に基づいて説明する。
【0014】
図1は、本発明による工事試験立会い方法の一つの実施形態を実施する上で使用する工事試験立会い設備Sを示してあり、この工事試験立会い設備Sによって、『ネット上工事試験立会い』が実現している。
【0015】
前記工事試験立会い設備Sは、試験体作成者1、試験実施者2、試験監理者3の存在位置のそれぞれに設置したコンピュータC1,C2,C3を設け、試験実施者2の位置を工事試験の実施場所4とし、この実施場所4には、工事試験の状況を撮影して映像情報として送信自在なカメラ5を設けて構成してある。また、前記試験実施者2のもとには、工事試験装置6が設置されていることは勿論のことである。
前記各コンピュータC1,C2,C3は、通信ネットワークNによって連結してあり、それぞれ情報送受信自在な状態に構成してある。
また、前記試験体作成者1が使用しているコンピュータC1は、サーバコンピュータCsとしての機能をも備えており、前記通信ネットワークNを使用した工事試験に関わる各種情報を、読み書き自在な状態で記録している。
各種情報とは、当該通信ネットワークNを通した工事試験関連の情報であり、具体的には、ネット上工事試験立会いへの参加者のアクセス状況を示す情報(例えば、名前やIDナンバー)や、前記カメラ5の撮影データ情報、前記工事試験装置6による試験中・後の計測値、カメラの遠隔操作用情報、工事試験状況を承認した試験監理者のコンピュータC3から発信された電子署名情報、各情報に対応させた記録時間等である。
【0016】
前記試験体作成者1は、工事試験体(ここでは、コンクリート供試体)7を作成する者を言い、具体的には、材料提供業者や工事施工業者であったり、該当工事の施工管理を行う工事管理業者、又は、それらの一部の組み合わせや、全てで構成されることがある。
前記試験実施者2は、工事試験体7を対象として、例えば、圧縮試験や引張り試験等の工事試験を実施する者を言い、具体的には、工事試験専門機関や、上述の試験体作成者1内で工事試験装置6を備えた者で構成されることがある。
前記試験監理者3は、当該工事の施工監理の一環として、工事試験の監理を行う者を言い、具体的には、工事監理専門機関や、施主等で構成されることがある。
【0017】
前記工事試験装置6は、該当する工事試験によって異なるが、当該実施形態では、コンクリート供試体の圧縮試験を実施する例を挙げているため、工事試験装置6としては、圧縮試験装置が該当する。
【0018】
次に、具体的な『ネット上工事試験立会い』の手順について、図2を用いて説明する。
[1] 『ネット上工事試験立会い』に先立って、工事試験体(ここでは、コンクリート供試体)7を、前記試験体作成者1、及び、前記試験監理者3(及び、試験実施者2も参加することもある)立会いの下に形成し、その工事試験体7であることを、後の『ネット上工事試験立会い』実施時に確認することができるようにするために、IDナンバーを記載したラベル8を工事試験体7に確認自在な状態に接着しておく(図1参照)。前記ラベルは、紙に、IDナンバーを印刷したものである。
[2] 所定の期間の養生を経た工事試験体7は、試験実施者2のもとに持ち込まれる。
[3] 試験実施者2と、試験体作成者1、試験監理者3との間で工事試験体実施日程が調整され、実施日時が決定される。
[4] 決定した工事試験日程に基づいて、試験体作成者1、試験実施者2、試験監理者3それぞれは、前記通信ネットワークNにログインする。
ログイン情報や、工事試験状況等は、ログインユーザに対して公開される。また、この時点からのアクセス履歴や、前記各種情報は、サーバコンピュータCs(C1)に記録される。尚、通信ネットワークNとして、第三者にも繋がるおそれのあるものを使用する場合には、ログイン時に、セキュリティーチェックが実施され、当該工事試験に関係する者のみが『ネット上工事試験立会い』に参加できるように構成されている。
[5] 工事試験を開始する。
試験実施者2は、前記工事試験装置6を使用して該当工事試験を実施する。その際、試験状況は、一部始終、カメラ5によって撮影され、その映像情報は前記通信ネットワークNに提供される。そして、工事試験装置6による工事試験体7への荷重・歪み状況の情報も通信ネットワークNに提供される。また、試験監理者3のコンピュータC3からは、前記カメラ5の撮影方向の変更操作や、ズーム操作等を遠隔操作することができる。
[6] 試験体作成者1、試験実施者2、試験監理者3は、工事試験の状況を確認すると、承認の意味で、電子署名をそれぞれ通信ネットワークNからサーバコンピュータC1に送信することができる。各電子署名は、記録日時を添えて、サーバコンピュータC1に記録され、上述の各プロセスデータと共に、事後に読み出すことができるように構成されている。
【0019】
このように、本実施形態の『ネット上工事試験立会い方法』によれば、試験体作成者1、試験監理者3が、工事試験の実施場所4まで出向かずに、工事試験の状況を、リアルタイムで且つありのままの状態で確認することができ、工事試験の実施場所に移動するための時間を省略することが可能となる他、通信ネットワークNに繋げる手段さえあれば、遠隔地どうしでも立ち会いが可能で、且つ、他の作業と並行させた状態での『ネット上工事試験立会い』を実施することも可能となり、工事試験参加者各自の時間負担を軽減することが可能となる。
また、セキュリティーを確保した中での各自の電子署名を残すことによって、該当工事試験の正当性、信憑性の維持を図ることが可能となる。
更には、記録されたデータは、前記供試体作成者1、前記試験実施者2、前記試験監理者3のそれぞれが、後日、当該工事試験の情報として利用することが可能となる。
また、工事試験の実施場所4に設置されたカメラ5は、前記試験監理者側から遠隔操作することができるので、試験監理者3は、確認しやすい状態に前記カメラ5を遠隔操作して、より詳細な工事試験状況を確認することが可能となる他、遠隔操作ができること自体が、映像情報の改竄が無いことの証となり、工事試験としての正当性・信憑性を更に向上させている。
【0020】
〔別実施形態〕
以下に他の実施の形態を説明する。
【0021】
〈1〉 試験体作成者1は、先の実施形態で説明した材料提供業者や工事施工業者、該当工事の施工管理を行う工事管理業者、又は、それらの一部の組み合わせや、全てで構成されるものに限るものではなく、例えば、試験実施者2や試験監理者3が兼ねることもあり、要するに、工事試験体7を作成する者であればよく、それらを含めて試験体作成者と総称する。
〈2〉 試験実施者2は、先の実施形態で説明したように工事試験専門機関や、上述の試験体作成者1内で構成することができ、要するに、該当工事試験を実施する者であればよく、それらを含めて試験実施者と総称する。
〈3〉 試験監理者3は、先の実施形態で説明した工事監理専門機関や、施主に限るものではなく、例えば、試験体作成者1や試験実施者2で有りながらも、公に工事監理を実施できる組織であれば、試験監理者3を兼ねることも可能である。要するに、該当工事の施工監理の一環として、工事試験の監理を行う者であればよく、それらを含めて試験監理者と総称する。
〈4〉 工事試験は、先の実施形態で説明したコンクリート供試体を対象とした圧縮試験に限るものではなく、例えば、鉄筋の圧接継手の引張試験や、耐火試験、各種の材料試験(鋼材など)等であってもよく、それらを含めて工事試験と総称する。
従って、工事試験体7そのものは、対象となる工事試験に応じて適切な状態に形成される必要があり、コンクリート供試体に限るものではない。更には、工事試験装置6も、対象となる工事試験を実施できうるものが必要である。
〈5〉 前記カメラ5で撮影した映像情報は、静止画情報や動画情報の何れであってもよい。
〈6〉 サーバコンピュータCsは、先の実施形態で説明した試験体作成者1が使用しているコンピュータC1に限るものではなく、例えば、試験実施者2が使用しているコンピュータC2や、試験監理者3の使用しているコンピュータC3であってもよく、更には、それらとは別に設けたコンピュータであってもよい。
〈7〉 前記ラベルは、先の実施形態で説明したように紙にIDナンバーを印刷したもに限るものではなく、例えば、素材は、紙以外に、合成樹脂や金属や布等の単体や、組み合わせ、更には、ラミネートを設けてあってもよい。また、印刷内容に関しては、IDナンバーに替えて、説明文字や、バーコードであってもよい。更には、ラベルそのものが、ICタグで構成してあってもよい。要するに、工事試験体7を特定することができるものであればよく、それらを総称してラベルと言う。
【0022】
尚、上述のように、図面との対照を便利にするために符号を記したが、該記入により本発明は添付図面の構成に限定されるものではない。
【図面の簡単な説明】
【図1】工事試験立会い設備を示す概念図
【図2】工事試験を示すフロー図
【符号の説明】
1 試験体作成者
2 試験実施者
3 試験監理者
Cs サーバ
5 カメラ
7 工事試験体
8 ラベル
N 通信ネットワーク
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention supervises the specimen creator, the test executor, and the applicable construction test when the tester performs the applicable construction test on the construction specimen created by the specimen creator. The present invention relates to a construction test witness method performed in the presence of a test supervisor.
[0002]
[Prior art]
Examples of the construction test include, for example, a strength test of a material (a compression test of a structural concrete and a tensile test of a pressure-welded joint of a reinforcing bar) in a building construction.
For example, in the case of a test for concrete strength, a concrete specimen (equivalent to a construction specimen) kneaded according to a predetermined composition is prepared, and the specimen is subjected to a compression test after a predetermined curing period. Will be implemented. At the time of the compression test, the creator of the specimen (for example, a building construction company) that created the specimen, a test executor that performs the compression test (for example, a testing organization), and a test supervisor (for example) that supervises the relevant construction test For example, it was common for the owners to meet together and conduct a construction test.
Conventionally, as this kind of construction test witness method, first, a test specimen creator prepares a test specimen in the presence of a test supervisor. Then, after curing the specimen, a schedule for the construction test is set and the test supervisor is contacted. Based on the construction test schedule, the specimen is placed at a location (for example, a testing organization) provided with the construction test device. A test creator, a test executor, and a test supervisor gathered to carry out a construction test in a test environment in which all of them could confirm.
Since such prior art is widely known among those skilled in the art without conducting a prior art search, no prior art document is shown.
[0003]
[Problems to be solved by the invention]
According to the conventional construction test witness method described above, it is necessary for the specimen creator, the test executor, and the test supervisor to go to the place where the construction test is to be performed. In addition, there is a problem that time for moving to the place is required for each person, and each person has a large time burden. Furthermore, there is a problem that it takes time to adjust the time for each person for the construction test.
[0004]
Accordingly, it is an object of the present invention to provide a construction test witness method which can solve the above-mentioned problems and can easily reduce the time burden on each of the construction test witnesses.
[0005]
[Means for Solving the Problems]
The feature configuration of the invention of claim 1 is that, when a test implementer performs a corresponding construction test on a construction specimen created by a specimen creator, the specimen creator, the test implementer, In a construction test witness method performed by a test supervisor who supervises the applicable construction test, in advance, at least the test executor and the test supervisor are connected to each other in a state where information can be freely transmitted via a communication network, Along with the execution of the construction test, the test performer transmits the construction test status to the test supervisor in real time, and the test supervisor transmits the electronic signature confirming the construction test status to the test supervisor in real time. Then, as the transmission records, the construction test status and the electronic signature are recorded in a server.
[0006]
According to the characteristic configuration of the invention of claim 1, at least the test executor and the test supervisor are connected to each other in a state in which information can be freely transmitted through a communication network, and the test is performed along with the execution of the construction test. The implementer transmits the construction test status in real time to the test supervisor, and the test supervisor transmits the electronic signature confirming the construction test status to the test implementer in real time. Since the test status and the electronic signature are recorded on the server, the test supervisor can check the status of the construction test in real time and as it is without going to the place where the construction test is performed. . Therefore, as long as the environment where the communication network is connected, the location of the test executor and the test supervisor is completely free, so that it is possible to omit the time required to move to the site where the construction test is to be performed, and to perform other tasks. It is possible to carry out construction test supervision in a state parallel to the above, and it is possible to reduce the time burden of each construction test participant.
In addition, since the status of such construction tests and an electronic signature as a proof that the supervisor has confirmed the construction tests are recorded on the server, the legitimacy and credibility of the relevant construction tests can be maintained. It becomes possible. Further, the recorded data can be used by the specimen creator, the test executor, and the test supervisor as information of the construction test at a later date.
[0007]
A feature of the invention according to claim 2 is that the access status of the participants participating in the witness of the construction test via the communication network is disclosed to each participant in real time.
[0008]
According to the characteristic configuration of the second aspect of the invention, in addition to the effect of the first aspect of the invention, each participant can recognize the access status of the participants involved in the construction test in real time. It is possible to maintain the legitimacy and credibility of the relevant construction test in a more preferable state.
[0009]
According to a feature of the invention of claim 3, the construction test status is transmitted as video information obtained by photographing at least the construction test status with a camera, and the camera is configured to be remotely controllable from the test supervisor side. There.
[0010]
According to the characteristic configuration of the third aspect of the present invention, in addition to the effect of the first or second aspect of the present invention, the test supervisor can easily perform the test supervision by remotely operating the camera from the test supervisor. It is possible to confirm the construction test in the state, and it is possible to efficiently realize more detailed test management. Furthermore, it is possible to confirm that the display screen of the monitor of the test supervisor changes as in the content of the remote control of the test supervisor, and to confirm that the display screen is not a fake. .
[0011]
A feature of the invention according to claim 4 is that the construction test specimen is provided with a label for specifying the test specimen in advance.
[0012]
According to the characteristic configuration of the invention of claim 4, in addition to being able to achieve the effect of any of the inventions of claims 1 to 3, it is also possible to prevent a construction test from being performed by changing the test body. The construction test can be performed in a more accurate state.
In addition, since this label can also be confirmed on the monitor of the test supervisor, the construction supervisor can visually check the label, and the supervisor can also confirm the specimen on the monitor.
[0013]
BEST MODE FOR CARRYING OUT THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings.
[0014]
FIG. 1 shows a construction test witness facility S used in carrying out one embodiment of a construction test witness method according to the present invention. are doing.
[0015]
The construction test witness equipment S is provided with computers C1, C2, and C3 installed at the locations of the specimen creator 1, the test executor 2, and the test supervisor 3, respectively. An implementation location 4 is provided with a camera 5 which is capable of photographing the state of the construction test and transmitting it as video information. In addition, it goes without saying that the construction test apparatus 6 is installed under the test performer 2.
The computers C1, C2, and C3 are connected by a communication network N, and are configured to be capable of transmitting and receiving information.
The computer C1 used by the specimen creator 1 also has a function as a server computer Cs, and records various information related to a construction test using the communication network N in a readable / writable state. are doing.
The various information is information related to the construction test through the communication network N, and specifically, information (for example, a name or an ID number) indicating a participant's access status to the witness on the construction test on the net, The photographing data information of the camera 5, the measured value during and after the test by the construction test device 6, the information for remote control of the camera, the electronic signature information transmitted from the computer C3 of the test supervisor who approved the construction test status, The recording time corresponds to the information.
[0016]
The specimen creator 1 refers to a person who prepares a construction specimen (here, a concrete specimen) 7. Specifically, the specimen creator 1 is a material provider or a construction contractor, or performs construction management of the corresponding construction. It may be composed of a construction management company, a combination of some of them, or all of them.
The test performer 2 refers to a person who performs a construction test such as a compression test or a tensile test on the construction test object 7. 1 may be constituted by a person equipped with the construction test device 6.
The test supervisor 3 refers to a person who supervises a construction test as a part of the construction supervision of the construction, and may be specifically composed of a construction supervising organization, a client, or the like.
[0017]
Although the construction test device 6 differs depending on the construction test concerned, in this embodiment, an example in which a compression test of a concrete specimen is performed is given, and thus the construction test device 6 corresponds to a compression test device.
[0018]
Next, a specific procedure of “witnessing on-line construction test” will be described with reference to FIG.
[1] Prior to “witnessing on-line construction test”, a construction specimen (here, a concrete specimen) 7 was prepared by combining the specimen creator 1 and the test supervisor 3 (and also the test performer 2). It is formed under the witness, and the ID number is written in order to be able to confirm that it is the construction test body 7 at the time of the "on-net construction test witness" later. The label 8 is adhered to the construction test specimen 7 in a state where it can be checked (see FIG. 1). The label is obtained by printing an ID number on paper.
[2] The construction specimen 7 that has been cured for a predetermined period is brought to the test executor 2.
[3] The work schedule of the construction specimen is adjusted between the test performer 2, the specimen creator 1, and the test supervisor 3, and the implementation date and time are determined.
[4] The test specimen creator 1, the test executor 2, and the test supervisor 3 log in to the communication network N based on the determined construction test schedule.
Login information, construction test status, and the like are disclosed to the login user. The access history from this point and the various information are recorded in the server computer Cs (C1). If a communication network N that could be connected to a third party is used, a security check will be performed at the time of login, and only those who are involved in the construction test will be able to participate in the It is configured to participate.
[5] Start the construction test.
The test executor 2 performs the relevant construction test using the construction test device 6. At this time, the test situation is photographed by the camera 5 throughout, and the video information is provided to the communication network N. Then, information on the load / strain status of the construction test body 7 by the construction test device 6 is also provided to the communication network N. Further, the computer C3 of the test supervisor 3 can remotely control the operation of changing the shooting direction of the camera 5 and the zoom operation.
[6] When the test body creator 1, the test executor 2, and the test supervisor 3 confirm the status of the construction test, they can transmit an electronic signature from the communication network N to the server computer C1 in the sense of approval. . Each digital signature is recorded on the server computer C1 with the recording date and time, and is configured to be read out later together with the above-described process data.
[0019]
As described above, according to the “working on-line construction test witness method” of the present embodiment, the specimen creator 1 and the test supervisor 3 can view the status of the construction test in real time without visiting the construction test location 4. In addition, it is possible to check the status as it is, and it is possible to omit the time required to move to the place where the construction test is carried out, and if there is only a means to connect to the communication network N, it is possible to witness remote places In addition, it is also possible to carry out the “work on-line construction test witness” in parallel with other work, and it is possible to reduce the time burden on each of the construction test participants.
In addition, by leaving their own electronic signatures while ensuring security, it is possible to maintain the legitimacy and credibility of the relevant construction test.
Further, the recorded data can be used by the specimen creator 1, the test executor 2, and the test supervisor 3 as information on the construction test at a later date.
Further, since the camera 5 installed at the construction test site 4 can be remotely operated from the test supervisor, the test supervisor 3 remotely operates the camera 5 in a state where it is easy to confirm. In addition to being able to check the status of the construction test in more detail, the fact that remote operation is possible proves that the video information has not been tampered with, further improving the legitimacy and credibility of the construction test.
[0020]
[Another embodiment]
Hereinafter, other embodiments will be described.
[0021]
<1> The specimen creator 1 is composed of the material provider and the construction contractor described in the above embodiment, the construction management company that performs the construction management of the relevant construction, or a combination of some or all of them. The tester 2 and the test supervisor 3 may also be used, for example, and may be a person who creates the construction specimen 7. I do.
<2> The test executor 2 can be constituted by a construction test specialized institution as described in the previous embodiment or the above-described specimen creator 1, and in short, it is a person who performs the relevant construction test. It is better to collectively refer to them as testers.
<3> The test supervisor 3 is not limited to the construction supervising organization and the owner described in the above embodiment. For example, the test supervisor 3 may be the specimen creator 1 or the test performer 2 but may be publicly supervised. If the organization can perform the above, it can also serve as the test supervisor 3. In short, any person who supervises the construction test as a part of the supervision of the construction of the relevant work may be sufficient, and is collectively referred to as a test supervisor including those.
<4> The construction test is not limited to the compression test for the concrete specimen described in the above embodiment, but may be, for example, a tensile test of a pressure-welded joint of a reinforcing bar, a fire resistance test, or various material tests (such as steel materials). ), Etc., and these are collectively referred to as construction tests.
Therefore, the construction specimen 7 itself needs to be formed in an appropriate state according to the construction test to be performed, and is not limited to the concrete specimen. Furthermore, the construction test device 6 must also be capable of performing the construction test of interest.
<5> The video information captured by the camera 5 may be any of still image information and moving image information.
<6> The server computer Cs is not limited to the computer C1 used by the test specimen creator 1 described in the above embodiment. For example, the computer C2 used by the test operator 2 and the test management The computer C3 used by the person 3 may be used, or a computer provided separately from the computer C3 may be used.
<7> The label is not limited to the one in which the ID number is printed on paper as described in the above embodiment. For example, in addition to paper, the material is a simple substance such as synthetic resin, metal, cloth, or the like, Combinations and further laminates may be provided. Further, as for the print content, an explanatory character or a bar code may be used instead of the ID number. Further, the label itself may be constituted by an IC tag. In short, what is necessary is just to be able to specify the construction test specimen 7, and they are collectively called a label.
[0022]
Note that, as described above, reference numerals are provided for convenience of comparison with the drawings, but the present invention is not limited to the configuration of the attached drawings by the entry.
[Brief description of the drawings]
FIG. 1 is a conceptual diagram showing a construction test attending facility. FIG. 2 is a flowchart showing a construction test.
1 Test Creator 2 Test Performer 3 Test Supervisor Cs Server 5 Camera 7 Construction Specimen 8 Label N Communication Network

Claims (4)

試験体作成者が作成した工事試験体を対象にして、試験実施者が該当工事試験を実施するに当たり、前記試験体作成者と、前記試験実施者と、該当工事試験を監理する試験監理者とが立ち会って行う工事試験立会い方法であって、
予め、少なくとも試験実施者と試験監理者とを、互いに通信ネットワークを介して情報伝達自在な状態に接続しておき、工事試験の実施に伴って、前記試験実施者から前記試験監理者に工事試験状況をリアルタイムで送信すると共に、前記試験監理者から前記試験実施者に工事試験状況を確認した電子署名をリアルタイムで送信し、これらの送信記録として、前記工事試験状況と、前記電子署名とをサーバに記録しておく工事試験立会い方法。
Targeting the construction specimen created by the specimen creator, when the test implementer performs the applicable construction test, the specimen creator, the test performer, and a test supervisor who supervises the applicable construction test Is a method of witnessing a construction test
In advance, at least the test executor and the test supervisor are connected to each other in a state in which information can be freely transmitted via a communication network, and the construction test is performed by the test executor to the test supervisor. Along with transmitting the status in real time, an electronic signature confirming the construction test status is transmitted from the test supervisor to the test implementer in real time, and the transmission test status and the electronic signature are stored in a server as a transmission record thereof. Witness method of construction test to record.
前記通信ネットワークを介して前記工事試験の立ち会いに参加している参加者のアクセス状況は、各参加者にリアルタイムで公開されている請求項1に記載の工事試験立会い方法。The construction test witness method according to claim 1, wherein the access status of the participant participating in the witness of the construction test via the communication network is disclosed to each participant in real time. 前記工事試験状況は、少なくとも工事試験の状況をカメラで撮影した映像情報として送信され、前記カメラは、前記試験監理者側から遠隔操作自在に構成してある請求項1又は2に記載の工事試験立会い方法。The construction test according to claim 1, wherein the construction test status is transmitted as video information obtained by photographing at least the construction test status with a camera, and the camera is configured to be remotely operable from the test supervisor. Witness method. 前記工事試験体には、その試験体を特定するラベルを予め設けておく請求項1〜3の何れか一項に記載の工事試験立会い方法。The construction test witness method according to any one of claims 1 to 3, wherein the construction specimen is provided in advance with a label for specifying the specimen.
JP2003016217A 2003-01-24 2003-01-24 Method for witnessing engineering work test Pending JP2004229081A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003016217A JP2004229081A (en) 2003-01-24 2003-01-24 Method for witnessing engineering work test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003016217A JP2004229081A (en) 2003-01-24 2003-01-24 Method for witnessing engineering work test

Publications (1)

Publication Number Publication Date
JP2004229081A true JP2004229081A (en) 2004-08-12

Family

ID=32903746

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003016217A Pending JP2004229081A (en) 2003-01-24 2003-01-24 Method for witnessing engineering work test

Country Status (1)

Country Link
JP (1) JP2004229081A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006118964A (en) * 2004-10-21 2006-05-11 Nidec-Shimpo Corp Load testing machine
KR101018711B1 (en) * 2008-08-13 2011-03-04 한국전기연구원 Remote admission test system using network of public use
CN104458416A (en) * 2014-11-24 2015-03-25 武汉钢铁(集团)公司 Tensile test data processing method
CN105352817A (en) * 2015-10-22 2016-02-24 武汉钢铁(集团)公司 Bending test data processing system for steel products
KR20190028772A (en) 2017-03-31 2019-03-19 미츠비시 쥬고교 가부시키가이샤 Virtual enrollment method and virtual enrollment system
CN106815779B (en) * 2017-03-27 2024-03-01 绍兴市标点电子技术有限公司 System and method for preventing false sample in construction engineering quality detection

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006118964A (en) * 2004-10-21 2006-05-11 Nidec-Shimpo Corp Load testing machine
KR101018711B1 (en) * 2008-08-13 2011-03-04 한국전기연구원 Remote admission test system using network of public use
CN104458416A (en) * 2014-11-24 2015-03-25 武汉钢铁(集团)公司 Tensile test data processing method
CN105352817A (en) * 2015-10-22 2016-02-24 武汉钢铁(集团)公司 Bending test data processing system for steel products
CN106815779B (en) * 2017-03-27 2024-03-01 绍兴市标点电子技术有限公司 System and method for preventing false sample in construction engineering quality detection
KR20190028772A (en) 2017-03-31 2019-03-19 미츠비시 쥬고교 가부시키가이샤 Virtual enrollment method and virtual enrollment system

Similar Documents

Publication Publication Date Title
JP4620030B2 (en) Equipment inspection support system, equipment inspection support method and program thereof
US11605257B2 (en) Information processing apparatus, control program of communication terminal, and entrance and exit management method
CN109447676A (en) A kind of advertising media&#39;s monitoring system and method
JP2009151610A (en) Ground information transfer device and ground information transfer program
JP2004229081A (en) Method for witnessing engineering work test
CN105719186A (en) Traffic accident investigation and management method and system
JP2019193062A (en) Pile construction site monitoring system by video
JP6462080B1 (en) Inspection device, inspection system, inspection method, and inspection program
JP7467846B2 (en) Information processing device, method, and program
JP2008146107A (en) Quality management system by construction inspection, and quality management program and its recording medium
Pollitt Report on digital evidence
JP2009276950A (en) Individual confirmation method in e-learning learning utilizing biometrics
KR20210115701A (en) Building pre-check system and method using smart check list
CN116523364A (en) Power operation site violation evidence obtaining method and device, storage medium and electronic equipment
JP7354623B2 (en) Test result reporting method and test result reporting system
JP2002004580A (en) Construction quality inspecting system
TWI603281B (en) Computer-assisted examination monitoring application (app) system and method for using the same
JP2007179464A (en) Monitoring log management system
JP2022174570A (en) Land boundary confirmation system, method for confirming land boundary, land boundary confirmation device, land boundary confirmation system program, and recording medium
CN115809863B (en) Work management method and system based on block chain
KR20140069578A (en) Method for providing online certificaiton service and server thereof
CN116038913A (en) Automatic consumption monitoring method for concrete raw materials, laboratory and mixing station production system
KR20240106807A (en) Radiographic test approval system and method
CN106845649A (en) A kind of thermal power plant repair quality movement management-control method based on internet
DE102015109607A1 (en) Method and apparatus for personalized electronic signing of a document and computer program product

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20041209

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041216

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050414