JP2004038538A - Device, and method for managing progress, and computer program - Google Patents
Device, and method for managing progress, and computer program Download PDFInfo
- Publication number
- JP2004038538A JP2004038538A JP2002194393A JP2002194393A JP2004038538A JP 2004038538 A JP2004038538 A JP 2004038538A JP 2002194393 A JP2002194393 A JP 2002194393A JP 2002194393 A JP2002194393 A JP 2002194393A JP 2004038538 A JP2004038538 A JP 2004038538A
- Authority
- JP
- Japan
- Prior art keywords
- progress
- information
- worker
- work
- well
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000000034 method Methods 0.000 title claims abstract description 44
- 238000004590 computer program Methods 0.000 title claims description 15
- 230000010365 information processing Effects 0.000 claims abstract description 48
- 230000008569 process Effects 0.000 claims abstract description 39
- 238000012545 processing Methods 0.000 claims abstract description 37
- 238000007726 management method Methods 0.000 claims description 17
- 230000003111 delayed effect Effects 0.000 claims description 6
- 230000007246 mechanism Effects 0.000 abstract description 3
- 238000010276 construction Methods 0.000 description 43
- 230000004044 response Effects 0.000 description 8
- 230000000737 periodic effect Effects 0.000 description 7
- 230000005540 biological transmission Effects 0.000 description 6
- 238000012937 correction Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 238000011084 recovery Methods 0.000 description 3
- 238000012360 testing method Methods 0.000 description 3
- 238000004891 communication Methods 0.000 description 2
- 230000006870 function Effects 0.000 description 2
- 230000003213 activating effect Effects 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 239000003086 colorant Substances 0.000 description 1
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、作業者の作業の進捗状況を管理するための技術であって、特に同じ工程の作業を複数の場所で並行して行う際の進捗状況の管理に好適な技術に関する。
【0002】
【従来の技術】
従来から、例えば、金融機関の複数の支店で、同時に現金自動取引端末などの工事を行う際、端末が設置されている各支店にそれぞれ作業員を派遣して作業を進めていた。
そして、各支店での作業の進捗状況は、派遣された各作業者が直接センタに電話して進捗状況の報告を行い、電話を受けたセンタの管理者がこの報告に基づいて手作業で紙や所定のボードに進捗状況を書き込むなどして管理していた。
【0003】
【発明が解決しようとする課題】
しかし、従来の電話による進捗状況の管理では、作業者からかかってくる電話に対応するためのセンタ側にオペレーターを何人も待機させておく必要があり管理コストが非常に高く、効率が悪かった。
特に、各支店で同じ工程の作業を並行して行っている場合には、各作業の完了報告が一時期に集中してしまうためセンタ側で対応できないばかりか、作業者としても報告が集中すると電話がなかなか繋がらず、作業報告が効率的にできないという問題があった。
【0004】
また、各作業者からの進捗報告により個々の現場の作業状況は把握できても、全支店での作業の進捗状況を把握することが難しかった。
そのため、例えば、金融機関端末などの工事では、全ての支店の作業進捗状況をある一定の状態にしてから一斉にテストを行いたい場合(例えば、あるプログラムをインストールしてからテストをする場合)などには、どの支店がどこまで作業が進んでいるのか全体を把握する必要があるが、従来の電話による進捗管理では、個々の作業を把握することはできても、全体の進捗状況として取りまとめることが困難であるという問題があった。
【0005】
本発明は、上述の問題点等に鑑みてなされたものであって、作業者の作業の進捗状況を効率的に把握できる仕組みであって、特に、同じ工程からなる作業を複数の作業者が異なる場所で並行して行う場合に好適な仕組みを提供することを目的とする。
【0006】
【課題を解決するための手段】
上記課題を解決するため、本発明の一の観点にかかる進捗状況管理装置は、作業者が作業を行う際の進捗状況を管理するための装置であって、上記作業者が保持する移動端末から通知された作業の進捗状況を表す進捗情報を受付ける受付手段と、進捗状況を管理する管理者に対して、受付けた各作業者の進捗情報を一覧表示して提供する進捗情報処理手段とを有することを特徴とする。
【0007】
上記進捗情報処理手段は、作業者の進捗状況をグラフ化して一覧表示するようにしてもよい。
【0008】
また、上記進捗情報処理手段は、作業が完了した部分と、作業が完了していない部分とを異なる態様でグラフ化して表示するようにしてもよい。
【0009】
また、上記進捗情報処理手段は、同じ作業の工程毎に、作業者の進捗度合いを並べて表示するようにしてもよい。
【0010】
作業者の移動端末に対して一定時間間隔で進捗情報の報告を要求するメッセージを通知する報告処理手段を更に有するようにしてもよい。
【0011】
また、上記進捗情報には、完了した作業に関する情報又は遅延が見込まれる作業に関する情報のうちの少なくとも一の情報を含んでもよい。
【0012】
作業者に対する周知情報と、周知を行う対象となる作業者の指定入力を受付ける周知情報処理手段と、受付けた周知情報を所定のWebページに掲載するWeb処理手段とを更に有し、上記周知情報処理手段は、Webページ処理手段により掲載されたWebページのアドレス情報を上記指定された作業者の移動端末へ送信するようにしてもよい。
【0013】
また、上記移動端末はインターネットに接続可能に構成されており、上記受信手段は、所定のWebページ上で進捗状況の登録を受付けるようにしてもよい。
【0014】
本発明の一の観点にかかる進捗情報管理方法は、コンピュータにより、作業者が作業を行う際の進捗状況を管理するための方法であって、上記作業者が保持する移動端末から送信された作業の進捗状況を表す進捗情報を受信する処理と、進捗状況を管理する管理者に対して、受信した各作業者の進捗情報を一覧表示して提供する処理と、を有することを特徴とする。
【0015】
本発明の一の観点にかかるコンピュータプログラムは、コンピュータを作業者が作業を行う際の進捗状況を管理するための装置として機能させるためのコンピュータプログラムであって、コンピュータに対して、上記作業者が保持する移動端末から送信された作業の進捗状況を表す進捗情報を受信する処理と、進捗状況を管理する管理者に対して、受信した各作業者の進捗情報を一覧表示して提供する処理とを実行させることを特徴とする。
【0016】
【発明の実施の形態】
以下、図面を参照して、本発明にかかる進捗情報管理装置及びコンピュータプログラムを、一例として複数の金融機関の支店で端末の工事を行う作業者の進捗状況を管理するためのシステムに適用した実施形態について説明する。
図1に本実施形態にかかるシステムの全体構成図を示す。
図1において、本実施形態のシステムは、サーバ1と、このサーバ1とインターネット2を介して接続可能に構成された管理センタ装置3、及び携帯電話センタ4と、この携帯電話センタ4と携帯電話網を通じて接続可能に構成された携帯電話端末5から構成されている。
【0017】
管理センタ装置3は、作業者の進捗情報を管理する管理者が使用するコンピュータである。
この管理センタ装置3は、所定のブラウザなどによりインターネットに接続可能に構成されており、所定のWebページにアクセスできるようになっている。
【0018】
携帯電話センタ4は携帯電話事業者のセンタである。この携帯電話センタ4は、また管理センタ装置3には、ディスプレイ、キーボードなどの入力手段が接続されることにより、情報の入出力が可能となっている。コンピュータ1により構成される携帯電話網を管理するとともに、携帯電話端末5をインターネット2に接続させることができるようになっている。
【0019】
携帯電話端末5は、金融機関の各支店において作業を行う作業者が保持する端末である。この携帯電話端末5は、携帯電話センタ4が提供する携帯電話網を介して管理センタの管理者と通話を行ったり、また携帯電話網及びインターネット2を介してサーバ1が提供するWebページにアクセスできるように構成されている。
なお、本実施形態では、携帯電話端末5としたが、これに代えて、作業者が保持する端末として、例えば、PDA(Personal Digital Assistance)、携帯可能ないわゆるパソコンなどを用いてもよい。
【0020】
サーバ1は、作業者の作業の進捗状況を管理するサーバであり、本発明にかかる進捗状況管理装置を構成する。
このサーバ1は、コンピュータにより構成され、CPU(Central Processing Unit)、CPUが実行するコンピュータプログラム、コンピュータプログラム等を記憶するためのRAM、ROMなどの内部メモリ及びハードディスクドライブなどの外部記憶装置により、図1に示した機能ブロックを構成する。
図1に示した機能ブロックは、工事基本情報テーブル101、トラブルテーブル102、作業者情報記憶部103、周知情報記憶部104、管理者情報記憶部105、Web情報作成部106、受付処理部107、進捗情報処理部108、報告処理部109、周知情報処理部110から構成されている。
【0021】
工事基本情報テーブル101は、管理対象となる工事に関する情報を記憶する記憶部である。
この工事基本情報テーブル101には、工事の基本情報と、各基本情報に対応する工程毎の項目情報が記憶できるようになっている。
基本情報としては、例えば、図2に示すように、工事コード、工事名、拠点コード、拠点名、実施日が含まれる。工事コードは、一つの工事毎に付与され、各工事を識別するための識別情報であり、工事名は各工事の名称である。また、拠点コードは工事の拠点を表す識別情報であり、拠点名は当該拠点の名称を表している。また、実施日は工事を実施する年月日を表している。
また、項目情報としては、例えば、図2に示すように、項目番号(No.)、作業項目名、計画時刻、計画台数、遅延見込、遅延見込台数、作業フラグが含まれる。項目番号は、各項目を識別するための番号であり、作業項目名は、作業の内容を表す名称である。また、計画時刻は当該作業を行う予定時刻であり、計画台数は、当該作業の対象予定となっている金融機関の端末等の台数を表している。遅延見込は、作業者から当該作業が遅延しそうか否かに関する見込情報を表し、見込み台数は作業の遅延が見込まれている端末の台数を表している。また作業フラグは、各作業項目が完了したか否かを示すフラグである。
【0022】
トラブルテーブル102は、工事で発生したトラブル情報を記憶するための記憶部である。
このトラブルテーブル102には、図3に示すように、各トラブル情報を識別するためのID、工事コード、拠点コード、作業を表す作業コード、発生時間、回復時間、対応済みか否かを表す対応情報、装置名、対応作業者、トラブル状況、トラブルの原因を表す原因情報、トラブル区分、回復見込時間、回復時間が記憶できるようになっている。
【0023】
作業者情報記憶部103は、実際に現場で作業を行う作業者に関する情報を記憶するための記憶部である。
この作業者情報記憶部103には、図4に示すように、作業者を識別するための作業者コード、工事コード、作業者が属するグループを表すグループコード、作業者の携帯電話端末5への電話番号及びメールアドレスなどが記憶できるようになっている。
【0024】
周知情報記憶部104は、管理者から作業者へ周知するための情報を記憶する記憶部である。
この周知情報記憶部104には、周知情報を識別するためのIDと、周知対象となる工事の工事コード、店舗コード、店舗名、周知対象となった作業者の作業者コード、作成日時、作業者が周知条項を見たか否かを表すステータス情報、周知文書ファイルが記憶できるようになっている。
【0025】
管理者情報記憶部105は、管理者に関する情報を記憶した記憶部である。この管理者情報記憶部105には、管理者の識別情報、氏名、管理者を認証するためのパスワードなどが記憶できるようになっている。
【0026】
Web情報作成部106は、所定のWebページを作成する処理を行う。
このWeb情報作成部106は、例えば、所定のWebページのフォームに従って、工事の進捗情報をHTML変換し、Webページ上で進捗状況情報を提供することができる。
また、Web情報作成部106は、例えば、Webページ上に作業者が進捗状況などを入力するための入力フォームをWebページ上で提供することができる。
【0027】
受付処理部107は、作業者から進捗情報の入力を受付け、これを工事基本情報テーブル101に記憶する処理などを行う。
また、受付処理部107は、管理者からトラブル情報の登録を受付け、受付けたトラブル情報をトラブルテーブル102に記憶する処理を行う。
【0028】
進捗情報処理部108は、受信した各作業者の進捗情報を管理者用のWebページ上で一覧表示して提供する処理を行う。
作業者の進捗情報の表示は、進捗情報処理部108が各作業者の進捗状況をグラフ化して一覧表示すると共に、作業が完了した部分と作業が完了していない部分、遅延見込みがある部分などを異なる態様でグラフ化して管理者用のWebページ上に表示することができる。この異なる態様とは、例えば、色を異ならせてもよいし、また形状などをことならせてもよい。
また、進捗情報処理部108は、同じ工程の作業を行っている作業者の進捗状況を、各工程毎に応じて並べて表示することができる。
【0029】
報告処理部109は、作業者の携帯電話端末5に対して定期的に進捗状況の報告を要求するメッセージを通知する。この通知は、例えば、報告処理部109が電子メールにより作業進捗状況を報告するよう要求するメッセージを通知し、作業者が進捗情報を登録する旨の回答をしたときに、所定のWebページ上の入力画面にアクセスさせて進捗情報の入力をさせるようにしてもよい。
【0030】
周知情報処理部110は、管理者から作業者に対する周知情報の登録を受付け、これを携帯電話端末5に電子メール等で通知することができる。
この周知情報を通知する場合、周知情報処理部110は、管理者が周知を行う作業者を指定できるようにし、指定された作業者にのみ周知情報を通知するようにしてもよい。
また、周知情報を通知する際、周知情報処理部110が直接周知情報を電子メールで送信するだけでなく、周知情報が掲載されたWebページのアドレス情報(URL)を通知するようにしてもよい。
【0031】
次に、本発明にかかる進捗状況管理方法の一実施形態について説明する。
なお、本実施形態では、予め管理センタの管理者により、各工事及び拠点毎に行う工事の基本情報及び項目情報が工事基本情報テーブル101に登録されているものとする。
まず、作業者側からの要求により進捗情報の登録を行う際の処理について図5を参照して説明する。
図5において、作業者が携帯電話端末5を使用して、サーバ1にアクセスすると、受付処理部107は、ログイン画面を表示して工事コード、拠点コードの入力を要求する(S101)。
作業者が要求に応じて工事コード、拠点コードを入力すると、受付処理部107がこれを受付け、工事基本情報テーブル101を参照して、入力された工事コード、拠点コードが正しいか判別する(S102)。
判別の結果、誤っている場合には、その旨のメッセージを作業者に通知するなどして処理を終了する。
【0032】
また、判別の結果正しい場合には、受付処理部107は、工事基本情報テーブル101を参照して、図6に示すように当該工事コード及び拠点コードに対応付けて登録されている作業項目を表示し、これらの中から作業者が作業完了等の情報登録を行う作業項目の選択を要求する(S103)。
【0033】
要求に応じて作業者が作業項目を選択すると、進捗情報処理部108は、図7に示すように入力フォームを表示させ、作業者に進捗情報の入力を要求する(S104)。
このとき入力する進捗情報としては、例えば、報告時刻、報告台数などを入力させてもよいし、作業が遅延する見込みがある時は、遅延見込み数、遅延見込み時間などを入力させるようにしてもよい。
作業者が要求に応じて入力を完了し作業完了のボタンを押すと、進捗情報処理部108は作業完了情報などの登録情報を受付け、受付けた情報をもとに工事基本情報テーブル101の進捗状況などを更新して(S105)、処理を終了する。
【0034】
次に、サーバ1から定期的に作業者に対して報告を要求する際の処理について図8を参照して説明する。
図8において、報告処理部109は、所定のタイミングで図9に示すような、定期報告要求メッセージを電子メールなどにより作業者の携帯電話端末5に送信し(S201)、作業者がこの要求に基づいて定期報告を行う旨の回答をしたか否か判別する(S202)。
判別の結果、作業者が図9の「いいえ」を選択し定期報告を行わない旨の回答をすると、報告処理部109は処理を終了し、次の定期報告時間まで待機する。
【0035】
また、この要求に応じて作業者が図9の「はい」を選択すると、進捗情報処理部108は、図10に示すように現在完了台数及び遅延見込時間の入力を要求する(S203)。
要求に応じて作業者が現在完了台数と、必要に応じて遅延見込時間を入力して台数報告ボタンを押すと、進捗情報処理部108は、入力された進捗情報を受付け、受付けた進捗情報をもとに工事基本情報テーブル101の進捗状況などを更新して(S204)、処理を終了する。
【0036】
次に、管理者が工事の進捗状況を確認する際のサーバ1の処理について図11を参照して説明する。
図11において、管理者が管理センタ装置3を使用して進捗状況を管理するためのWebページにアクセスすると、受付処理部107は、管理者が進捗状況を表示する工事の工事コードと、管理者のパスワードの入力を要求する(S301)。
要求に基づいて管理者が工事コード及びパスワードを入力すると、受付処理部107は管理者情報記憶部105を参照して、入力されたパスワードが正しいか否か判別する(S302)。
判別の結果パスワードが正しくない場合には、その旨のメッセージを表示するなどして処理を終了する。
【0037】
また判別の結果パスワードが正しい場合には、進捗情報処理部108が、工事基本情報テーブル101及びトラブルテーブル102を参照して、指定された工事コードに対応する進捗状況情報及びトラブル情報を取得する(S303)。
そして、進捗情報処理部108が、取得したこれらの情報に基づいてこれをグラフに変換して(S304)、Webページ情報作成部106がこれをHTML形式に変換することにより管理者用のWebページに表示する(S305)。
この際、図12に示すように、進捗情報処理部108は、各作業者の進捗状況を棒グラフ化して一覧表示すると共に、作業が完了した工程(例えば、図中の1001a、1006aなど)を青色、作業が完了していないか或いはトラブルが発生している工程(例えば、図中の1006b)は赤色、遅延見込みが報告されている場合(例えば、図中の1001b、1005)には紫色などのように、それぞれ異なる態様でグラフ化して表示する。また、進捗情報処理部108は、同じ工程の作業を行っている作業者の進捗状況を、入店報告、機器搬入完了などの各工程毎に対応させて表示することにより、全体及び各作業者の進捗度合いを並べて表示することができる。
【0038】
また、この状態で進捗情報処理部108は、管理者から数値データ表示(図中の進捗状況2)のボタン又はログオフボタンが押されたか否か判別する(S306)。
判別の結果、管理者がログオフボタンを押した場合には進捗情報処理部108は、処理を終了する。
【0039】
また、判別の結果管理者が数値表示を選択した場合には、進捗情報処理部108は、図13に示すように進捗状況を数値化したデータで表示し(S307)、この状態で管理者からログオフのボタンが押されることにより処理を終了する。
【0040】
次に、管理者から作業者に対して周知情報を通知する際の処理について図14を参照して説明する。
図14において、まず管理者から周知情報の登録が要求されると、周知情報処理部110は、図15に示すように、周知情報登録画面を表示させ、周知情報の登録又は選択を要求する(S401)。
周知情報の登録は、図15に示すように、新規周知文登録エリア2001から新規に周知文書の登録を受付けてもよいし、また周知情報記憶部104に記憶されている登録済み周知文一覧2002の中から所望の文書を選択するようにしてもよい。
【0041】
管理者により周知文書の登録又は選択がされると、周知情報処理部110は、図16に示すように周知内容を表示すると共に、送信先の選択を要求する(S402)。
送信先のチェックは、例えば、図16に示したように、周知情報処理部110が、工事コードごと、拠点コードごとに送信先の店舗名、アドレス、作業者がメッセージを確認したか否かを表す状態を表示し、その中から送信チェックボックス2003にチェックを行うことで選択できるようにしてもよい。
【0042】
送信先の選択が完了し一斉送信ボタン2004が押されると、Web情報作成部106が当該周知情報をHTML変換し、当該周知情報を所定のWebページ上に掲載する(S403)。
また、周知情報処理部110は、図17に示すように、指定された作業者に対して電子メールにより周知情報がある旨のメッセージと、そのメッセージが掲載されているWebページのURLを周知対象となっている作業者に通知する(S404)。
そして、周知情報を通知された作業者が指定されたURLにアクセスすることにより周知情報を見ることができ、作業者からWebページアクセスされた時点で周知情報処理部110が周知情報記憶部104のステータス(状態)を既読に変更して(S405)、処理を終了する。
【0043】
次に、トラブル情報の受付について図18を参照して説明する。
図18において、作業者のところで何らかのトラブルが発生し、作業者が電話又はFAXなどにより管理センタの管理者に連絡をする。
これにより、管理者がサーバ1に対してトラブル情報の登録を要求すると、進捗情報処理部108が、図19に示す画面を表示してトラブル情報の登録を受付ける(S501)。
【0044】
管理者が作業者から報告されたトラブル内容を入力画面に従って入力すると、進捗情報処理部108は、入力された情報をトラブルテーブル102に記憶する(S502)。
また、登録が完了した状態で管理者からトラブル情報の照会が要求されると、進捗情報処理部108は、トラブルテーブル102を参照して、図20に示すトラブル情報の一覧画面を表示する(S503)。
そして、管理者がトラブル状況の修正を行う場合には、この状態で表示されている項番をダブルクリックすることにより、進捗情報処理部108は、図21に示すようなトラブル修正登録画面を表示して修正情報の入力を受付ける(S504)。
修正情報の入力が完了すると、進捗情報処理部108は、工事基本情報テーブル101及びトラブルテーブル102の進捗状況などを更新して(S505)、処理を終了する。
【0045】
このように、上述の実施形態によれば、受付処理部107が、各作業者の作業者携帯端末5から送信された進捗情報を受信し、進捗情報処理部108が、Webサーバ2を介して進捗状況を管理する管理センタ装置3に対して、受信した各作業者の進捗情報をWebページ上に一覧表示して提供するようにしたことから、管理者はWebページを見れば進捗状況を簡単に把握することができる。これにより、管理センタ側で、管理者を何人も待機させておく必要はなく、人件費が軽減できる。
また、携帯端末から登録させることにより、各作業の完了報告が一時期に集中しても、登録可能となり、センタ側で情報で効率良く進捗情報の取得ができる。
【0046】
また、進捗情報処理部108が、各作業者の進捗状況をグラフ化して一覧表示するようにしたことから管理者は視覚的に各作業者の進捗度合いを確認することができる。
【0047】
また、進捗情報処理部108が、作業が完了した部分と、作業が完了していない部分とを異なる色で表示するようにしたことから、管理者は一目で作業者の作業が完了しているか否かを把握することができる。
【0048】
また、進捗情報処理部108が、同じ工程から構成される作業の工程毎に応じて、各作業者の進捗度合いを表示するようにしたことから、複数の場所に分かれて同じ工程の工事などを行う場合でも、簡単に各現場の進捗状況を把握することができる。特に、例えば、金融機関などの端末の場合、全ての支店の作業進捗状況をある一定の状態にしてから一斉にテストを行いたい場合などであっても、全支店の進捗状況として取りまとめて把握することができるから、簡単に作業を行うことができる。
【0049】
また、報告処理部109により、作業者携帯端末5に対して一定時間間隔で進捗状況の報告を要求するメッセージを通知するようにしたことから、作業者が報告を忘れることなく、定期的に進捗状況の報告を得ることができる。また、作業者からの報告時間をセンタ側でコントロールすることができ、報告が一時期に集中することを防止できる。
また作業者としても、報告要求があったときに所定の入力フォームを使って進捗情報を連絡すればよいから、従来のように電話が繋がらなかったり、連絡を忘れてしまうことがなく、簡単に進捗情報を管理者側に通知できる。
【0050】
また、進捗状況情報に、完了した作業に関する情報及び/又は作業の遅延が見込まれる時間の少なくともいずれかを含むようにすれば、管理者は作業の進み具合を把握、予測することができる。
【0051】
また、周知情報処理部110により、作業者に対する周知情報と、周知を行う対象となる作業者の指定を受付け、受付けた周知情報を所定のWebページに掲載するようにし、作業者には、当該Webページのアドレス情報を通知するようにしたことから、作業者に送信する際のデータ量がWebページのアドレス情報だけであるため少なくて済むし、また作業者としても時間が空いている時にWebページにアクセスして周知情報を見ればよく、電話などで直接通知するよりも効率的に周知情報を提供できる。
【0052】
上述の実施形態は、サーバ1を複数の金融機関の支店で、同じ工程に従って金融機関の端末の工事を行う作業者の作業状況を管理する際に適用した例について説明したが、本発明はこれに限定されるものではなく、複数の作業者の進捗状況を管理するシステムであれば種々のシステムに適用可能である。
【0053】
本実施形態にかかるサーバ1は、専用装置であってもよいし、また、汎用のコンピュータとコンピュータプログラムを用いて実現してもよい。汎用のコンピュータを利用して実現する場合には、例えば、汎用のコンピュータに対して上述の動作を実行するためのコンピュータプログラムやこれを格納したコンピュータ読み取り可能な媒体(FD、CD−ROM等)からコンピュータプログラムをインストールすることにより上述の処理を実行する各装置を構成するようにしてもよい。なお、上述の機能をOS(Operating System)が分担又はOSとアプリケーションプログラムの共同により実現する場合等には、OS以外の部分のみをコンピュータプログラムとして、またこのコンピュータプログラムをコンピュータ読み取り可能な媒体に格納してもよい。
【0054】
また、サーバ1用の各コンピュータプログラムを搬送波に重畳し、通信ネットワークを介して配信することも可能である。例えば、通信ネットワークの掲示板(BBS)に当該プログラムを掲示し、これをネットワークを介して配信するようにしてもよい。そして、このコンピュータプログラムを起動し、OS制御下で他のアプリケーションプログラムと同様に実行させることにより上述の処理を実行させるようにしてもよい。
【0055】
【発明の効果】
本発明によれば、作業者の作業の進捗状況を効率的に把握できる。
【図面の簡単な説明】
【図1】本発明にかかる一実施形態の全体構成の概略を示した図。
【図2】本実施形態にかかる工事基本情報テーブルに記憶されるデータの一例を示した図。
【図3】本実施形態にかかるトラブルテーブルに記憶されるデータの一例を示した図。
【図4】本実施形態にかかる作業者情報データベースに記憶されるデータの一例を示した図。
【図5】本実施形態にかかる作業者が進捗情報を登録する際のWebサーバの処理を示した図。
【図6】本実施形態にかかる作業者が進捗情報を登録する際の作業広告を表示した画面の一例した図。
【図7】本実施形態にかかる作業者が進捗情報を登録する際の画面の一例した図。
【図8】本実施形態にかかる作業者に対して定期報告要求を行う際のWebサーバの処理を示した図。
【図9】本実施形態にかかる定時報告要求メッセージを表示した画面の一例した図。
【図10】本実施形態にかかる作業者が定時報告行う際の画面の一例した図。
【図11】本実施形態にかかる管理者に対して進捗情報を提供する際のWebサーバの処理を示した図。
【図12】本実施形態にかかる進捗状況情報を表示した際の画面の一例を示した図。
【図13】本実施形態にかかる進捗状況情報を表示した際の画面の別の例を示した図。
【図14】本実施形態にかかる作業者に周知情報を通知する際のWebサーバの処理を示した図。
【図15】本実施形態にかかる周知情報の登録画面の一例を示した図。
【図16】本実施形態にかかる周知情報の送信先選択画面の一例を示した図。
【図17】本実施形態にかかる周知情報が通知された際の作業者携帯端末の画面の一例を示した図。
【図18】本実施形態にかかるトラブル情報を登録する際のWebサーバの処理を示した図。
【図19】本実施形態にかかるトラブル情報の登録画面の一例を示した図。
【図20】本実施形態にかかるトラブル情報の一覧表示画面の例を示した図。
【図21】本実施形態にかかるトラブル情報の修正登録画面の一例を示した図。
【符号の説明】
1 サーバ
3 管理センタ装置
5 携帯電話端末
101 工事基本情報テーブル
102 トラブルテーブル
107 受付処理部
108 進捗情報処理部
109 報告処理部
110 周知情報処理部[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a technique for managing the progress of a worker's work, and more particularly to a technique suitable for managing the progress of a task performed in the same process at a plurality of locations in parallel.
[0002]
[Prior art]
2. Description of the Related Art Conventionally, for example, when a plurality of branches of a financial institution perform construction of an automatic teller machine at the same time, a worker has been dispatched to each branch where the terminal is installed to carry out the work.
The progress of the work at each branch is reported by each dispatched worker directly to the center to report the progress, and the center manager who receives the call manually makes a paper report based on this report. Or by writing the progress on a predetermined board.
[0003]
[Problems to be solved by the invention]
However, in the conventional management of the progress status by telephone, it is necessary to keep a number of operators on the center side for responding to a telephone call from an operator, so that the management cost is extremely high and the efficiency is low.
In particular, when the same process is performed at each branch in parallel, the completion report of each work is concentrated at a certain time, so that not only can the center respond, but also the report is concentrated as a worker. However, there was a problem that the work report could not be efficiently made.
[0004]
In addition, it is difficult to grasp the progress of work at all branches, even if the progress of work from each worker can be grasped by the progress report from each worker.
Therefore, for example, in the construction of a terminal of a financial institution, etc., when it is desired to perform a test at once after keeping the work progress status of all branches to a certain state (for example, when performing a test after installing a certain program), etc. Needs to keep track of which branches are working and how far they are going.However, with conventional telephone progress management, it is possible to keep track of There was a problem that it was difficult.
[0005]
The present invention has been made in view of the above-described problems and the like, and is a mechanism capable of efficiently grasping the progress of work performed by a worker. It is an object of the present invention to provide a mechanism suitable for performing at different places in parallel.
[0006]
[Means for Solving the Problems]
In order to solve the above problems, a progress management device according to an aspect of the present invention is a device for managing a progress when an operator performs a task, and includes a mobile terminal held by the operator. A receiving unit for receiving progress information indicating a progress status of the notified work; and a progress information processing unit for displaying a list of the received progress information of each worker and providing the received progress information to a manager managing the progress status. It is characterized by the following.
[0007]
The progress information processing means may graph the progress of the worker and display the progress.
[0008]
In addition, the progress information processing means may display a portion where the work is completed and a portion where the work is not completed in a different manner as a graph.
[0009]
Further, the progress information processing means may display the degree of progress of the worker side by side for each process of the same work.
[0010]
Report processing means for notifying the worker's mobile terminal of a message requesting a report of progress information at regular time intervals may be further provided.
[0011]
The progress information may include at least one of information on a completed task or information on a task that is expected to be delayed.
[0012]
Well-known information to the worker, well-known information processing means for receiving a designation input of the worker to be well-known, and web processing means for posting the received well-known information on a predetermined Web page. The processing means may transmit the address information of the Web page posted by the Web page processing means to the mobile terminal of the designated worker.
[0013]
Further, the mobile terminal may be configured to be connectable to the Internet, and the receiving unit may receive registration of the progress on a predetermined Web page.
[0014]
A progress information management method according to one aspect of the present invention is a method for managing, by a computer, a progress status when an operator performs an operation, the operation transmitted from a mobile terminal held by the operator. And a process of displaying a list of the received progress information of each worker to the manager who manages the progress status, and providing the list to the manager who manages the progress status.
[0015]
A computer program according to one aspect of the present invention is a computer program for causing a computer to function as an apparatus for managing the progress of a task performed by an operator. A process of receiving progress information indicating the progress of the work transmitted from the mobile terminal to be held, and a process of listing and providing the received progress information of each worker to an administrator who manages the progress. Is executed.
[0016]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, with reference to the drawings, an embodiment in which a progress information management device and a computer program according to the present invention are applied to a system for managing the progress of workers who work on terminals at branches of a plurality of financial institutions as an example. The form will be described.
FIG. 1 shows an overall configuration diagram of a system according to the present embodiment.
In FIG. 1, a system according to the present embodiment includes a
[0017]
The
The
[0018]
The mobile phone center 4 is a center of a mobile phone carrier. The mobile phone center 4 is connected to input means such as a display and a keyboard so that information can be input and output to and from the
[0019]
The mobile phone terminal 5 is a terminal held by a worker who works at each branch of the financial institution. The mobile phone terminal 5 communicates with a manager of the management center via a mobile phone network provided by the mobile phone center 4 and accesses a Web page provided by the
In the present embodiment, the mobile phone terminal 5 is used. Alternatively, for example, a PDA (Personal Digital Assistance) or a portable personal computer may be used as a terminal held by the worker.
[0020]
The
The
The functional blocks shown in FIG. 1 include a construction basic information table 101, a trouble table 102, a worker
[0021]
The construction basic information table 101 is a storage unit that stores information related to construction to be managed.
The construction basic information table 101 can store basic construction information and item information for each process corresponding to each piece of basic information.
The basic information includes, for example, a construction code, a construction name, a base code, a base name, and an implementation date, as shown in FIG. The construction code is assigned to each construction, is identification information for identifying each construction, and the construction name is the name of each construction. The base code is identification information indicating the base of the construction, and the base name indicates the name of the base. The implementation date indicates the date of the construction.
The item information includes, for example, an item number (No.), a work item name, a planned time, a planned number, a delay estimate, a delay estimate number, and a work flag, as shown in FIG. The item number is a number for identifying each item, and the work item name is a name representing the content of the work. The planned time is the scheduled time for performing the work, and the planned number indicates the number of terminals of the financial institution that is the target of the work. The expected delay indicates expected information on whether or not the work is likely to be delayed from the operator, and the expected number indicates the number of terminals expected to be delayed. The work flag is a flag indicating whether each work item has been completed.
[0022]
The trouble table 102 is a storage unit for storing trouble information generated during construction.
In the trouble table 102, as shown in FIG. 3, an ID for identifying each trouble information, a construction code, a base code, a work code representing the work, an occurrence time, a recovery time, and a response indicating whether or not the trouble has been dealt with. Information, a device name, a corresponding operator, a trouble situation, cause information indicating a cause of the trouble, a trouble classification, a recovery expected time, and a recovery time can be stored.
[0023]
The worker
As shown in FIG. 4, the worker
[0024]
The well-known information storage unit 104 is a storage unit that stores information to be widely known from the manager to the worker.
The well-known information storage unit 104 stores an ID for identifying well-known information, a construction code of a work to be well-known, a store code, a store name, a worker code of a worker to be well-known, a creation date and time, Status information indicating whether or not the user has viewed the well-known clause, and a well-known document file can be stored.
[0025]
The administrator
[0026]
The Web
The Web
In addition, the Web
[0027]
The
Further, the
[0028]
The progress
The progress information of the worker is displayed by the progress
In addition, the progress
[0029]
The
[0030]
The well-known
When notifying the well-known information, the well-known
When notifying the well-known information, the well-known
[0031]
Next, an embodiment of a progress management method according to the present invention will be described.
In the present embodiment, it is assumed that basic information and item information of each construction and the construction performed for each base are registered in the construction basic information table 101 by an administrator of the management center in advance.
First, processing for registering progress information in response to a request from the worker will be described with reference to FIG.
In FIG. 5, when the worker accesses the
When the worker inputs the construction code and the base code in response to the request, the
If the result of the determination is incorrect, a message to that effect is sent to the operator and the process is terminated.
[0032]
If the result of the determination is correct, the
[0033]
When the worker selects a work item in response to the request, the progress
As the progress information to be input at this time, for example, the report time, the number of reports, or the like may be input, or when the work is expected to be delayed, the expected delay number, the expected delay time, or the like may be input. Good.
When the operator completes the input in response to the request and presses the work completion button, the progress
[0034]
Next, a process when the
In FIG. 8, the
As a result of the determination, when the operator selects “No” in FIG. 9 and replies that the periodic report is not to be performed, the
[0035]
When the operator selects “Yes” in FIG. 9 in response to this request, the progress
When the operator inputs the currently completed number and the expected delay time as needed and presses the number report button in response to the request, the progress
[0036]
Next, processing of the
In FIG. 11, when the administrator accesses a Web page for managing the progress using the
When the administrator inputs the construction code and the password based on the request, the
If the result of the determination is that the password is incorrect, a message to that effect is displayed and the process is terminated.
[0037]
If the password is correct as a result of the determination, the progress
Then, the progress
At this time, as shown in FIG. 12, the progress
[0038]
In this state, the progress
If the result of determination is that the administrator has pressed the logoff button, the progress
[0039]
If the administrator selects the numerical display as a result of the determination, the progress
[0040]
Next, a process when the administrator notifies the worker of the well-known information will be described with reference to FIG.
In FIG. 14, when the registration of the well-known information is first requested by the administrator, the well-known
For registration of the well-known information, as shown in FIG. 15, registration of a newly-known document may be accepted from a new well-known
[0041]
When a well-known document is registered or selected by the administrator, the well-known
For example, as shown in FIG. 16, the well-known
[0042]
When the selection of the transmission destination is completed and the
As shown in FIG. 17, the well-known
The worker who has been notified of the well-known information can view the well-known information by accessing the designated URL. When the worker accesses the Web page, the well-known
[0043]
Next, reception of trouble information will be described with reference to FIG.
In FIG. 18, some trouble occurs at the worker, and the worker contacts the manager of the management center by telephone or facsimile.
Thus, when the administrator requests the
[0044]
When the administrator inputs the details of the trouble reported from the operator according to the input screen, the progress
In addition, when the administrator requests the inquiry of the trouble information in the state where the registration is completed, the progress
When the administrator corrects the trouble situation, by double-clicking the item number displayed in this state, the progress
When the input of the correction information is completed, the progress
[0045]
As described above, according to the above-described embodiment, the
Further, by registering from the portable terminal, even if the completion reports of each work are concentrated at one time, the registration is possible, and the progress information can be efficiently acquired on the center side with the information.
[0046]
In addition, since the progress
[0047]
In addition, since the progress
[0048]
In addition, since the progress
[0049]
In addition, the
Also, as a worker, when there is a report request, it is only necessary to notify the progress information using a predetermined input form, so that the telephone is not connected or the contact is not forgotten as in the past, so it is easy Progress information can be notified to the administrator.
[0050]
In addition, when the progress status information includes at least one of the information on the completed work and / or the time in which the work is expected to be delayed, the manager can grasp and predict the progress of the work.
[0051]
Also, the well-known
[0052]
In the above-described embodiment, an example has been described in which the
[0053]
The
[0054]
In addition, each computer program for the
[0055]
【The invention's effect】
ADVANTAGE OF THE INVENTION According to this invention, a worker's work progress can be grasped efficiently.
[Brief description of the drawings]
FIG. 1 is a diagram schematically illustrating an entire configuration of an embodiment according to the present invention.
FIG. 2 is a diagram showing an example of data stored in a construction basic information table according to the embodiment.
FIG. 3 is an exemplary view showing an example of data stored in a trouble table according to the embodiment;
FIG. 4 is a diagram showing an example of data stored in a worker information database according to the embodiment.
FIG. 5 is an exemplary view showing processing of a Web server when an operator according to the embodiment registers progress information.
FIG. 6 is an exemplary view showing an example of a screen displaying a work advertisement when the worker registers progress information according to the embodiment;
FIG. 7 is a view showing an example of a screen when the worker according to the embodiment registers progress information.
FIG. 8 is an exemplary view showing processing of a Web server when making a periodic report request to an operator according to the embodiment;
FIG. 9 is an exemplary view showing a screen displaying a periodic report request message according to the embodiment;
FIG. 10 is a view showing an example of a screen when the worker according to the embodiment makes a periodic report.
FIG. 11 is an exemplary view showing processing of a Web server when providing progress information to an administrator according to the embodiment;
FIG. 12 is an exemplary view showing an example of a screen when progress information is displayed according to the embodiment;
FIG. 13 is an exemplary view showing another example of the screen when the progress information is displayed according to the embodiment;
FIG. 14 is an exemplary view showing a process of the Web server when notifying the worker of known information according to the embodiment;
FIG. 15 is an exemplary view showing an example of a registration screen of well-known information according to the embodiment.
FIG. 16 is an exemplary view showing an example of a transmission destination selection screen of well-known information according to the embodiment.
FIG. 17 is an exemplary view showing an example of a screen of the worker portable terminal when the well-known information according to the embodiment is notified.
FIG. 18 is an exemplary view showing processing of a Web server when registering trouble information according to the embodiment;
FIG. 19 is an exemplary view showing an example of a trouble information registration screen according to the embodiment;
FIG. 20 is an exemplary view showing an example of a trouble information list display screen according to the embodiment;
FIG. 21 is an exemplary view showing an example of a trouble information correction registration screen according to the embodiment.
[Explanation of symbols]
1 server
3 Management center device
5 mobile phone terminals
101 Basic construction information table
102 Trouble Table
107 reception processing unit
108 Progress Information Processing Unit
109 Report processing unit
110 Well-known information processing unit
Claims (10)
上記作業者が保持する移動端末から通知された作業の進捗状況を表す進捗情報を受付ける受付手段と、
進捗状況を管理する管理者に対して、受付けた作業者の進捗情報を一覧表示して提供する進捗情報処理手段と、
を有することを特徴とする進捗状況管理装置。An apparatus for managing the progress of an operation performed by an operator,
Receiving means for receiving progress information indicating the progress of the work notified from the mobile terminal held by the worker,
Progress information processing means for displaying and providing a list of received progress information of the worker to an administrator who manages the progress,
A progress management device comprising:
請求項1記載の進捗状況管理装置。The progress information processing means graphs and displays the progress of the worker,
The progress management device according to claim 1.
請求項2記載の進捗状況管理装置。3. The progress management apparatus according to claim 2, wherein the progress information processing unit displays a graph of the part where the work is completed and a part where the work is not completed in a different manner.
請求項1〜3のいずれかの項に記載の進捗状況管理装置。The progress information processing means displays the degree of progress of each worker side by side for each process of the work including the same process,
The progress management device according to claim 1.
請求項1〜4のいずれかの項に記載の進捗状況管理装置。Further comprising a report processing means for notifying a message requesting the progress information report to the worker's mobile terminal at regular time intervals,
The progress management device according to claim 1.
請求項1〜5のいずれかの項に記載の進捗状況管理装置。The progress information includes at least one of information on completed work or information on work expected to be delayed,
The progress management device according to claim 1.
受付けた周知情報を所定のWebページに掲載するWeb処理手段とを更に有し、
上記周知情報処理手段は、Webページ処理手段により掲載されたWebページのアドレス情報を、上記指定された作業者の移動端末へ送信する、
請求項1〜6のいずれかの項に記載の進捗状況管理装置。Well-known information to the worker, well-known information processing means for receiving designation of the worker to be notified,
Web processing means for posting the received well-known information on a predetermined Web page,
The well-known information processing means transmits address information of a Web page posted by the Web page processing means to a mobile terminal of the designated worker.
The progress management device according to claim 1.
上記受信手段は、所定のWebページ上で進捗状況の登録を受付ける、
請求項1〜7のいずれかの項に記載の進捗状況管理装置。The mobile terminal is configured to be connectable to the Internet,
The receiving means receives registration of a progress status on a predetermined Web page;
The progress management device according to claim 1.
上記作業者が保持する移動端末から送信された作業の進捗状況を表す進捗情報を受信する処理と、
進捗状況を管理する管理者に対して、受信した上記作業者の進捗情報を一覧表示して提供する処理と、
を有することを特徴とする進捗状況管理方法。A method for managing, by a computer, the progress of an operation performed by an operator,
A process of receiving progress information indicating the progress of the work transmitted from the mobile terminal held by the worker,
A process of displaying a list of the received progress information of the worker and providing the received progress information to an administrator who manages the progress status;
The progress management method characterized by having.
コンピュータに対して、
各作業者が保持する移動端末から送信された作業の進捗状況を表す進捗情報を受信する処理と、
進捗状況を管理する管理者に対して、受信した各作業者の進捗情報を一覧表示して提供する処理と、
を実行させるコンピュータプログラム。A computer program for causing a computer to function as a device for managing the progress when a plurality of workers perform work,
Against the computer
A process of receiving progress information indicating the progress of the work transmitted from the mobile terminal held by each worker;
A process of displaying and providing the received progress information of each worker to the manager who manages the progress,
A computer program that executes
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002194393A JP2004038538A (en) | 2002-07-03 | 2002-07-03 | Device, and method for managing progress, and computer program |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002194393A JP2004038538A (en) | 2002-07-03 | 2002-07-03 | Device, and method for managing progress, and computer program |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004038538A true JP2004038538A (en) | 2004-02-05 |
Family
ID=31703103
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002194393A Withdrawn JP2004038538A (en) | 2002-07-03 | 2002-07-03 | Device, and method for managing progress, and computer program |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004038538A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006331021A (en) * | 2005-05-25 | 2006-12-07 | Kandenko Co Ltd | Construction progress management method using internet |
JP2007087111A (en) * | 2005-09-22 | 2007-04-05 | Fujitsu Support & Service Kk | Progress management system, method of managing progress, progress management apparatus, and progress management program |
JP2009294696A (en) * | 2008-06-02 | 2009-12-17 | Hitachi Ltd | Client apparatus introduction management system, client apparatus introduction management method, information processor and program |
WO2016002462A1 (en) * | 2014-06-30 | 2016-01-07 | 株式会社日立ソリューションズ | Work management system |
JP2021089645A (en) * | 2019-12-05 | 2021-06-10 | Necフィールディング株式会社 | Maintenance work management device, system, method, and program |
WO2023084618A1 (en) * | 2021-11-09 | 2023-05-19 | 株式会社 Lozi | Logistics management system, logistics management method, and computer program |
-
2002
- 2002-07-03 JP JP2002194393A patent/JP2004038538A/en not_active Withdrawn
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006331021A (en) * | 2005-05-25 | 2006-12-07 | Kandenko Co Ltd | Construction progress management method using internet |
JP2007087111A (en) * | 2005-09-22 | 2007-04-05 | Fujitsu Support & Service Kk | Progress management system, method of managing progress, progress management apparatus, and progress management program |
JP2009294696A (en) * | 2008-06-02 | 2009-12-17 | Hitachi Ltd | Client apparatus introduction management system, client apparatus introduction management method, information processor and program |
WO2016002462A1 (en) * | 2014-06-30 | 2016-01-07 | 株式会社日立ソリューションズ | Work management system |
JP2016012243A (en) * | 2014-06-30 | 2016-01-21 | 株式会社日立ソリューションズ | Work management system |
JP2021089645A (en) * | 2019-12-05 | 2021-06-10 | Necフィールディング株式会社 | Maintenance work management device, system, method, and program |
JP7067797B2 (en) | 2019-12-05 | 2022-05-16 | Necフィールディング株式会社 | Maintenance work management equipment, systems, methods, and programs |
WO2023084618A1 (en) * | 2021-11-09 | 2023-05-19 | 株式会社 Lozi | Logistics management system, logistics management method, and computer program |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7499869B2 (en) | System and method for scheduling employee shifts | |
US11256559B2 (en) | Error display system, error display method, and information processing apparatus | |
JP4591247B2 (en) | Information display method | |
CN110750222A (en) | Printing method, printing device, computer equipment and storage medium | |
CN109657899B (en) | Item processing method, device, equipment and readable storage medium | |
US20160314543A1 (en) | System and method for improved inspection techniques | |
CN104050525A (en) | Information processing device and processing execution method | |
CN102103475A (en) | Print job management apparatus, system, and method | |
JP2004038538A (en) | Device, and method for managing progress, and computer program | |
CN114416769A (en) | To-do task query method and device and electronic equipment | |
CN110648105B (en) | Recommendation method and device based on data processing, electronic equipment and storage medium | |
JP2015197791A (en) | Advertisement distribution device, advertisement distribution method, and program | |
JP3582881B2 (en) | Electronic questionnaire system | |
JP2007004768A (en) | Newspaper sale management system | |
KR20000024120A (en) | Apparatus and method for processing a cyber civil appeals | |
JP2008123191A (en) | Operation management server, operation management method and computer program | |
CN110032703A (en) | A kind of enterprise web site trustship method and system | |
JP2005293491A (en) | Server system | |
JP2008293454A (en) | Appointment inquiry system | |
JP2015043132A (en) | Terminal device, collection server, and management method | |
US11445075B2 (en) | Display system, display device, terminal device, and data management method with notification function of receiving communication data | |
JP2012123434A (en) | Facility management system | |
JP2002117099A (en) | Method and server for managing progress of construction work | |
KR20010063419A (en) | Wireless electric bulletin board managing system and method | |
KR20220167928A (en) | Method Of Servicing A National Research and Development Information By Using A Calendar |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Application deemed to be withdrawn because no request for examination was validly filed |