JP2003313862A - Method for installing cast-in-place steel base column and steel column - Google Patents
Method for installing cast-in-place steel base column and steel columnInfo
- Publication number
- JP2003313862A JP2003313862A JP2002122303A JP2002122303A JP2003313862A JP 2003313862 A JP2003313862 A JP 2003313862A JP 2002122303 A JP2002122303 A JP 2002122303A JP 2002122303 A JP2002122303 A JP 2002122303A JP 2003313862 A JP2003313862 A JP 2003313862A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- column
- true
- steel
- retarder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は場所打ち構真台柱及
び構真柱の施工方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a cast-in-place column and a method of constructing the column.
【0002】[0002]
【従来の技術】建築物の逆打ち工法では、地下構造体が
完成するまでの間の建物荷重や作業荷重を支持するため
に構真柱(鉄骨)及び構真台柱(コンクリート)が用い
られる(例えば、特許第284744号参照)。2. Description of the Related Art In a method of building a building upside down, structure columns (steel frames) and structure columns (concrete) are used to support building loads and work loads until the underground structure is completed ( See, for example, Japanese Patent No. 284744).
【0003】構真柱根入れ部の設計は鉄骨とコンクリー
トとの付着力を主体として行われるが、高耐力な構真柱
を設計する場合、必要な耐力に応じて根入れ長さを長く
する必要がある。ところが、付着力は根入れ部の全長に
わたって発揮されず、変位に応じて根入れ部の上方から
部分的にしか発揮されないため、根入れ長さを長くして
も期待した程の付着力を得ることはできない。また、根
入れ長さを確保するためだけに構真台柱の長さを長くす
ることは現実的でなく、現状においてはこの様な方法で
高耐力な構真柱を施工することは困難である。The design of the root of the true column is carried out mainly by the adhesive force between the steel frame and the concrete, but when designing the true column having a high bearing capacity, the rooting length is lengthened according to the required bearing strength. There is a need. However, since the adhesive force is not exerted over the entire length of the rooting part and is only partially exerted from above the rooting part according to the displacement, even if the rooting length is increased, the expected adhesive force is obtained. It is not possible. In addition, it is not realistic to increase the length of the gantry column in order to secure the rooting length, and it is difficult to construct a high-bearing gantry column by such a method at present. .
【0004】一方、鉄骨先端の支圧抵抗を設計に考慮出
来れば、同じ根入れ長さでもより高耐力な構真柱を設計
できる可能性がある。この様な観点からH型鋼のフラン
ジ外面に凸部を設けたり、H型鋼に補強リブを設けて掘
削孔内にセメントミルクにより定着させる構真柱の定着
方法が提案されている(特開2001−27134
7)。また、鋼材の定着部分に、軸力の作用方向に略平
行な配置でコンクリート等の付着面積を増大する補強プ
レートを付設するとともに、軸力の作用方向と略直角な
方向にスタッドジベル等の支圧補強板を突設し、これら
を鋼材とともにコンクリート等の固化材料の中に埋め込
んで定着するという、鋼材をコンクリート等の固化材料
へ定着する荷重伝達機構が提案されている(特許第27
64648号)。On the other hand, if bearing resistance at the tip of the steel frame can be taken into consideration in the design, there is a possibility that it is possible to design a false column having a higher yield strength even with the same insertion length. From such a point of view, a method of fixing a true column in which a convex portion is provided on the outer surface of the flange of the H-shaped steel or a reinforcing rib is provided on the H-shaped steel and fixed in the excavation hole with cement milk is proposed (Japanese Patent Laid-Open No. 2001-2001) 27134
7). In addition, a reinforcing plate that increases the adhesion area of concrete, etc. is installed in the fixing part of the steel material in a direction substantially parallel to the acting direction of the axial force, and a stud dowel etc. is supported in a direction substantially perpendicular to the acting direction of the axial force. A load transfer mechanism has been proposed in which a pressure-reinforcing plate is projected and embedded together with a steel material in a solidified material such as concrete to fix the steel material to the solidified material such as concrete (Patent No. 27).
64648).
【0005】しかし、鉄骨先端以深のコンクリートが長
い構真台柱は、コンクリートの硬化に伴うブリージング
によるブリージング水により鉄骨先端部に空隙等が生
じ、従って、構真柱の構造的な変更による支圧抵抗の向
上が見込まれても実際は充分な支圧抵抗が発揮されない
可能性がある。[0005] However, in the case of the truss column with a long concrete depth beyond the steel frame tip, the breathing water caused by the hardening of the concrete causes voids and the like in the steel frame tip portion, and therefore the bearing resistance due to the structural change of the truss column. However, in reality, there is a possibility that sufficient bearing resistance will not be exerted even if the improvement of is expected.
【0006】[0006]
【発明が解決しようとする課題】本発明は上記した点に
鑑みなされたもので、簡単な手順により形成できるとと
もに、ブリージングから生じる不都合を回避して高鉛直
荷重支持を行うことができる高耐力な場所打ち構真台柱
及び構真柱の施工方法を提案するものである。SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned points, and can be formed by a simple procedure and has a high yield strength capable of supporting a high vertical load while avoiding the disadvantage caused by breathing. It proposes a cast-in-place structure pillar and a construction method of the structure pillar.
【0007】[0007]
【課題を解決するための手段】本発明は上記課題を解決
するため、コンクリート硬化の初期にブリージング水の
ほとんどが発生し、しかもコンクリートの打設量に比例
する如く空隙等の弊害が生じ易いことに着目し、コンク
リートの打設後適当な時間をおくことで鉄骨先端深度以
深のコンクリートに予めブリージングを発生させること
で鉄骨先端部分に発生するブリージング水を大幅に減少
できることを見いだしたものである。In order to solve the above-mentioned problems, the present invention is such that most breathing water is generated in the early stage of hardening of concrete, and moreover, harmful effects such as voids tend to occur in proportion to the amount of concrete placed. Focusing on the above, it was found that breathing water generated at the tip of the steel frame can be significantly reduced by preliminarily causing breathing in the concrete deeper than the depth of the steel frame by placing an appropriate time after placing the concrete.
【0008】即ち、本請求項1発明の施工方法は、掘削
孔内に建込んだ構真柱の建込み位置下方に於いて、所定
レベルまで一次コンクリートを打設した後、該コンクリ
ート上に所定レベルまで遅延剤入りコンクリートを順次
打設し、次いで所定時間放置してブリージングを発生さ
せた後、遅延剤入りコンクリートが硬化する前にその上
方の構真柱の建込み部分に二次コンクリートを打設して
構真柱を定着させることを特徴とする場所打ち構真台柱
及び構真柱の施工方法として構成した。That is, in the construction method of the present invention, the primary concrete is poured to a predetermined level below the erected position of the true column built in the excavation hole, and then the predetermined concrete is placed on the concrete. After pouring the concrete containing the retarder to the level, and then allowing it to stand for a certain period of time to generate breathing, pour the secondary concrete on the built-up portion of the structure column above it before the concrete containing the retarder hardens. It was constructed as a construction method for cast-in-place and stand-up columns, which is characterized by installing and fixing the true columns.
【0009】また、請求項2発明の施工方法は、上記構
真柱が、定着部分に於ける外表面に横断面T字状の支圧
補強板を周方向複数突設した構真柱である請求項1記載
の構真台柱及び構真柱の施工方法として構成した。According to a second aspect of the present invention, the true column is a true column in which a plurality of bearing reinforcing plates having a T-shaped cross section are circumferentially projected on the outer surface of the fixing portion. It is configured as a structure-supporting pillar and a method of constructing a structure-supporting pillar according to claim 1.
【0010】また、請求項3発明の施工方法は、掘削孔
内の構真柱の建込み予定位置下方所定レベルまでコンク
リートを打設した後、該コンクリート上の構真柱建込み
予定位置の所定レベルまで遅延剤入りコンクリートを打
設し、次いで所定時間放置してブリージングを発生させ
た後、遅延剤入りコンクリートが硬化する前に、遅延剤
入りコンクリート内に構真柱の建込みを行って構真柱を
定着させることを特徴とする場所打ち構真台柱及び構真
柱の施工方法として構成した。According to the third aspect of the present invention, after placing concrete up to a predetermined level below the planned construction position of the concrete pillar in the excavation hole, the predetermined position of the concrete pillar to be built on the concrete is determined. After pouring the concrete containing the retarder to the level and then allowing it to stand for a predetermined time to cause breathing, before the concrete containing the retarder hardens, the concrete columns are erected in the concrete containing the retarder. It was constructed as a cast-in-place column and a method of constructing the column in which the column is fixed.
【0011】また、請求項4発明の施工方法は、上記構
真柱が、定着部分に於ける外表面に横断面T字状の支圧
補強板を周方向複数突設した構真柱である請求項3記載
の構真台柱及び構真柱の施工方法として構成した。According to a fourth aspect of the present invention, the true column is a true column in which a plurality of bearing reinforcing plates having a T-shaped cross section are circumferentially projected on the outer surface of the fixing portion. It is configured as the structure-supporting pillar and the method for constructing the structure-supporting pillar according to claim 3.
【0012】[0012]
【発明の実施の形態】以下、本発明の実施の形態を図面
を参照して説明する。BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings.
【0013】本発明に於ける構真台柱及び構真柱の施工
方法は、構真柱の先建て、後建てに拘わらず用いること
が可能である。In the present invention, the structure-supporting columns and the method of constructing the structure-supporting columns can be used regardless of whether the structure-supporting columns are pre-built or rear-built.
【0014】構真柱の先建ての場合には、例えば、図1
に示す如き以下の工程を経る。
(a) 地盤の掘削
(b) 鉄骨の建込み
(c) 一次コンクリートの打設
(d) 遅延剤入りコンクリートの打設
(e) ブリージング水の発生
(f) 二次コンクリートの打設In the case of a pre-built concrete pillar, for example, FIG.
The following steps are performed as shown in FIG. (a) Excavation of the ground (b) Construction of steel frame (c) Placing of primary concrete (d) Placing of concrete with retarder (e) Generation of breathing water (f) Placing of secondary concrete
【0015】まず、既存の装置、例えば、アースドリル
工法を用いて地盤1に所定深さの掘削孔2を穿設し(図
1(a) )、次いで、掘削孔2内に所定の下部空間をあけ
て構真柱3を建込む(図1(b) )。First, an existing device, for example, an earth drill method is used to form a drill hole 2 of a predetermined depth in the ground 1 (FIG. 1 (a)), and then a predetermined lower space is formed in the drill hole 2. Open the structure and build the true pillar 3 (Fig. 1 (b)).
【0016】次いで、掘削孔2内の構真柱3の建込み位
置下方に於いて所定レベルaまでの一次コンクリート4f
をトレミー管5を介する等の公知方法により打設し(図
1(c) )、次いで一次コンクリート4f上に所定レベルb
まで遅延剤入りコンクリート4rを打設する(図1(d)
)。ここで使用される遅延剤は、セメントやコンクリ
ートの凝結を遅らせるための混和剤として従来から使用
されているものが使用でき、その量は打設コンクリート
の量などの種々の要因を考慮して適宜選択する。Next, below the erected position of the structural column 3 in the excavation hole 2, the primary concrete 4f up to a predetermined level a.
Is placed by a known method such as through the tremie pipe 5 (Fig. 1 (c)), and then a predetermined level b on the primary concrete 4f.
Placing concrete 4r containing retarder until (Fig. 1 (d)
). The retarder used here can be the one that has been conventionally used as an admixture for delaying the setting of cement or concrete, and the amount thereof is appropriately determined in consideration of various factors such as the amount of cast concrete. select.
【0017】一次コンクリート4fを打設する所定レベル
aは、その上部の構真柱3下端との間に遅延剤入りコン
クリート4rを打設できる空間をあけたレベルを指す。ま
た、遅延剤入りコンクリート4rは、一次コンクリートと
二次コンクリートとの打継ぎ部分の品質維持を図ること
を主目的とするため、打継ぎ可能な量があれば良く、一
次コンクリート4fと比較してその量は少なくて良い。The predetermined level "a" at which the primary concrete 4f is poured refers to a level at which a space for placing the retarder-containing concrete 4r is provided between the upper part of the predetermined level "a" and the lower end of the false column 3. Further, since the retarder-containing concrete 4r is mainly intended to maintain the quality of the splicing portion between the primary concrete and the secondary concrete, it only needs to have a splicable amount, and compared with the primary concrete 4f. The amount may be small.
【0018】そして、この状態で所定時間放置して一次
コンクリート4f及び遅延剤入りコンクリート4rに於いて
ブリージング水を発生させ、一部のブリージング水6を
上面にわきあがらせる(図1(e) )。ここでの放置時間
は打設したコンクリートの量,組成,遅延剤入りコンク
リート4rの硬化時間,その他の要因により適宜選択すれ
ば良く、4〜6時間程度が目安として考えられるが、当
然これに限られない。特に、遅延剤入りコンクリートが
硬化すれば二次コンクリート4sとの打継ぎ部分の品質低
下を来すため、その硬化の前に二次コンクリートを打設
する必要があり、放置時間にはその点の要件は充分考慮
する必要がある。構真柱3下端以深の一次コンクリート
4fに於けるブリージング水の殆どはこの時点で発生す
る。Then, in this state, it is left for a predetermined time to generate breathing water in the primary concrete 4f and the retarder-containing concrete 4r, and a part of the breathing water 6 is agitated on the upper surface (FIG. 1 (e)). . The leaving time here may be appropriately selected depending on the amount of the placed concrete, the composition, the hardening time of the concrete 4r containing the retarder, and other factors, and about 4 to 6 hours can be considered as a guide, but naturally it is not limited to this. I can't. In particular, if the retarder-containing concrete hardens, the quality of the jointing part with the secondary concrete 4s will deteriorate, so it is necessary to pour the secondary concrete before hardening, and it is necessary to set the The requirements need to be carefully considered. Primary concrete 3 Primary concrete deeper than the lower end
Most of the breathing water in 4f occurs at this point.
【0019】最後に、遅延剤入りコンクリート4rが硬化
する前に、構真柱3の建込み部分に二次コンクリート4s
を打設して構真柱3を定着させる(図1(f) )。この
際、二次コンクリート4sに於いてもブリージング水は発
生し、生じたブリージング水6は二次コンクリート4s表
面に上昇するが、構真柱3下方の一次コンクリート4f部
分で殆どブリージングの発生は終了しているため、構真
柱下部に於けるブリージング水の影響は少なく、支圧抵
抗を発生する上では問題とならない。また、遅延剤入り
コンクリート4rを用いることで、一次コンクリート4fの
打設後に時間をおくことに起因するコンクリート硬化に
よる施工性の低下や打継ぎ部分の品質の低下を防止し
て、良好な施工性及び品質を確保できる。Finally, before the concrete 4r containing the retarder is hardened, the secondary concrete 4s is added to the built-in portion of the structure column 3.
To mount the structure pillar 3 (Fig. 1 (f)). At this time, breathing water is generated also in the secondary concrete 4s, and the generated breathing water 6 rises to the surface of the secondary concrete 4s, but the occurrence of breathing is almost completed in the primary concrete 4f portion below the structure column 3. Therefore, there is little influence of breathing water in the lower part of the structure column, and there is no problem in generating bearing resistance. In addition, by using the retarder-containing concrete 4r, it is possible to prevent deterioration of the workability due to concrete hardening and deterioration of the quality of the joints due to the time elapse after the primary concrete 4f has been poured, and good workability And quality can be secured.
【0020】本発明で使用される構真柱3としては、従
来から使用されているものであれば使用でき、例えば、
H型鋼,クロスH型鋼、その他種々の形態のものが使用
できるが、より好ましい形態として、ベースプレートを
使用せずに、特にブリージング水に起因する不都合が鉄
骨先端部分に溜まることを防ぐとともに、多大な支圧抵
抗を期待できる構真柱を使用する。この様な構真柱とし
て、定着部分に於ける外表面に横断面T字状の支圧補強
板8を周方向複数突設したものが使用できる。As the structure post 3 used in the present invention, any conventional one can be used, for example,
H-shaped steel, cross-H-shaped steel, and various other forms can be used, but as a more preferable form, it is possible to prevent the inconvenience due to breathing water from accumulating at the steel frame tip part without using the base plate, and Use a true column that can be expected to bear pressure. As such a true column, it is possible to use a structure in which a plurality of bearing support plates 8 having a T-shaped cross section are circumferentially projected on the outer surface of the fixing portion.
【0021】その具体例として、図2及び図3に示す如
く、クロスH型鋼の下端部のフランジ7外面に四枚の横
断面T字状をなす支圧補強板8を突設したものが挙げら
れる。この支圧補強板8は、例えば鋼材と同材質で、溶
接,接着等の適宜固定方法により鋼材に固定したものが
使用でき、鋼材とその一側縁を連結する第1板部8aと、
該第1板部8a他側縁を一面中央部に連結した第2板部8b
とで構成している。この場合にはその量を減らす目的
で、第1板部8aは上面を外方へ下る傾斜面とした四角形
に、第2板部8bはその両側面を外方へ下る傾斜面とした
台形状にそれぞれ形成しているが、これに限られず、例
えばそれぞれ長方形状であっても良い。As a specific example thereof, as shown in FIG. 2 and FIG. 3, one in which four pressure bearing reinforcing plates 8 having a T-shaped cross section are provided on the outer surface of the flange 7 at the lower end of the cross H-shaped steel so as to project. To be The bearing reinforcement plate 8 can be made of the same material as steel, for example, and can be fixed to steel by an appropriate fixing method such as welding or bonding. The first plate 8a for connecting the steel to one side edge thereof,
The second plate portion 8b in which the other side edge of the first plate portion 8a is connected to the central portion of one surface
It consists of and. In this case, for the purpose of reducing the amount, the first plate portion 8a is a quadrangle whose upper surface is an inclined surface which is inclined outward, and the second plate portion 8b is a trapezoid whose both side surfaces are inclined surfaces which are outwardly inclined. However, the present invention is not limited to this, and may be rectangular, for example.
【0022】また、上記と同様の構真柱として、定着部
分に於ける外表面に長手方向に沿って板状の支圧補強板
8を複数段突設したものが使用できる。この場合に支圧
補強板8は横断面T字状のものに限らず、単なる板状の
ものであっても良い。図4及び図5はクロスH型鋼の下
端部のフランジ7外面にそれぞれ二段各四枚の板状をな
す支圧補強板8を突設した例を示す。図示例では同様に
材量を減らすべく、上面を下方へ下る傾斜面とした三角
板状に各支圧補強板8を形成している。Further, as the above-described true-structured column, it is possible to use one in which a plurality of plate-shaped pressure-bearing reinforcing plates 8 are provided so as to project along the longitudinal direction on the outer surface of the fixing portion. In this case, the bearing pressure reinforcing plate 8 is not limited to the T-shaped cross section, but may be a simple plate-shaped member. FIG. 4 and FIG. 5 show an example in which a pressure-bearing reinforcing plate 8 in the form of four plates in two steps is provided on the outer surface of the flange 7 at the lower end of the cross H-section steel. In the illustrated example, similarly, in order to reduce the amount of material, each bearing reinforcing plate 8 is formed in the shape of a triangular plate whose upper surface is an inclined surface that descends downward.
【0023】図6及び図7は、定着部分に於ける外表面
に横断面T字状をなす支圧補強板8を複数段突設した例
を示す。尚、上記各実施例に於いて鋼材としてクロスH
型鋼に代わりにH型鋼の外表面に同様の支圧補強板を固
定したものを使用することも出来る。これらの構真柱は
後述する後建ての場合にも当然採用される。6 and 7 show an example in which a plurality of pressure bearing reinforcing plates 8 having a T-shaped cross section are provided on the outer surface of the fixing portion so as to project. In addition, in each of the above-mentioned examples, the cloth H is used as the steel material.
Instead of the shaped steel, it is also possible to use an H-shaped steel having an outer surface to which a similar bearing reinforcing plate is fixed. Naturally, these true pillars are also adopted in the case of a later-constructed building which will be described later.
【0024】構真柱の後建ての場合には、例えば、図8
に示す如き以下の工程を経る。
(a) 地盤の掘削
(b) コンクリートの打設
(c) 遅延剤入りコンクリートの打設
(d) ブリージング水の発生
(e) 構真柱の建込みIn the case of the post-construction of the true pillar, for example, as shown in FIG.
The following steps are performed as shown in FIG. (a) Ground excavation (b) Concrete placement (c) Concrete containing retarder (d) Breathing water generation (e) Construction of true columns
【0025】まず、図1の場合と同様に所定深さの掘削
孔2を穿設し(図8(a) )、次いで掘削孔2内の構真柱
3の建込み予定位置下方に所定レベルcまでのコンクリ
ート4を打設し、次いで、該コンクリート4上に所定レ
ベルdまでの遅延剤入りコンクリート4rを打設(図8
(c) )する。コンクリート4を打設する所定レベルc
は、上記した如く、その上に構真柱3を建込み出来る空
間をあけたレベルを指す。First, as in the case of FIG. 1, the excavation hole 2 having a predetermined depth is bored (FIG. 8 (a)), and then a predetermined level is provided in the excavation hole 2 below the planned position of the construction column 3. Concrete 4 up to c is cast, and then concrete 4r containing retarder up to a predetermined level d is cast on the concrete 4 (see FIG. 8).
(c)) Predetermined level c for placing concrete 4
Indicates a level with a space on which the true pillar 3 can be built, as described above.
【0026】そして、この状態で所定時間放置してコン
クリート4及び遅延剤入りコンクリート4rに於いてブリ
ージング水を発生させ(図8(d) )一部のブリージング
水6を上面にわき上がらせる。ここでの放置時間も図1
の場合と同様に選択すれば良く、4〜6時間程度が目安
となり、当然これに限られない。コンクリート4に於け
るブリージング水の殆どはこの時点で発生し、遅延剤入
りコンクリート4rに於けるブリージング水もかなりのパ
ーセンテージでこの時点で発生する。Then, in this state, it is left for a predetermined time to generate breathing water in the concrete 4 and the retarder-containing concrete 4r (FIG. 8 (d)), and part of the breathing water 6 is raised to the upper surface. The time left here is also shown in Figure 1.
It may be selected in the same manner as in the above case, and the guideline is about 4 to 6 hours, and is not limited to this. Most of the breathing water in concrete 4 is generated at this time, and the breathing water in retarder-containing concrete 4r is also generated at a considerable percentage at this time.
【0027】次いで、遅延剤入りコンクリート4rが硬化
する前に、該遅延剤入りコンクリート4r内に構真柱3の
建て込みを行って構真柱を定着させる。Next, before the concrete 4r containing the retarder is hardened, the concrete columns 3 are built in the concrete 4r containing the retarder to fix the true columns.
【0028】この場合、先建て工法の場合と同様、鉄骨
先端部下方のコンクリート4に於けるブリージング水は
殆ど発生を終了しているため、鉄骨先端部に空隙等の不
都合が生じることは殆どない。また、時間をおいた後鉄
骨を挿入するため、コンクリートの硬化に伴う施工性の
低下や鉄骨とコンクリートの付着力の減少が予想される
が、遅延剤入りコンクリートを用いることで施工性及び
品質が確保できる。In this case, as in the case of the pre-construction method, almost no breathing water has been generated in the concrete 4 below the steel frame tip, so there is almost no inconvenience such as voids at the steel frame tip. . In addition, since the steel frame is inserted after a while, it is expected that the workability will decrease with hardening of the concrete and the adhesive force between the steel frame and the concrete will decrease. Can be secured.
【0029】[0029]
【発明の効果】以上説明した如く、本発明の場所打ち構
真台柱及び構真柱の施工方法は、既述構成としたことに
より、ブリージングによる構真柱への影響を極力排除し
てより高品質な構真台柱の形成が可能であり、従来方法
では実現困難な高耐力の構真台柱を実現できる。また、
同じ耐力の構真台柱を設計する場合に、従来方法に比較
して構真柱の根入れ長さを短くでき、コストの低減が可
能である。As has been described above, the cast-in-place true column and the method of constructing the true column of the present invention are configured as described above, so that the influence of breathing on the true column is eliminated as much as possible. It is possible to form a high-quality rearrangement column, and it is possible to realize a high-bearing rearrangement column that is difficult to achieve by the conventional method. Also,
In the case of designing a true-standing post with the same strength, the rooting length of the true-post can be shortened as compared with the conventional method, and the cost can be reduced.
【0030】また、定着部分に於ける外表面に横断面T
字状の支圧補強板を周方向複数突設してなる構真柱を使
用したものにあっては、ブリージングによって生じるブ
リージング水が下端面を容易に回避して上昇し、構真柱
下部に空隙が生じる等の不都合を更に良好に防止でき、
その結果、高強度構真台柱を形成できるとともに、支圧
抵抗が大きくより高耐力な構真台柱を実現できる。A cross section T is formed on the outer surface of the fixing portion.
In the case of using a true column with a plurality of letter-shaped bearing support plates protruding in the circumferential direction, the breathing water generated by breathing easily avoids the lower end surface and rises to the bottom of the true column. It is possible to prevent problems such as voids even better.
As a result, it is possible to form a high-strength structure-supporting column and to realize a structure-supporting column having a large bearing resistance and a higher yield strength.
【図1】本発明の施工方法の一例を説明する説明図であ
る。FIG. 1 is an explanatory diagram illustrating an example of a construction method of the present invention.
【図2】本発明に使用する構真柱の一例を示す要部側面
図である。FIG. 2 is a side view of an essential part showing an example of a false column used in the present invention.
【図3】図3の構真柱の横断面図である。FIG. 3 is a cross-sectional view of the true column of FIG.
【図4】本発明に使用する構真柱の他の一例を示す要部
側面図である。FIG. 4 is a side view of an essential part showing another example of the false column used in the present invention.
【図5】図4の構真注の横断面図である。5 is a transverse cross-sectional view of the structure injection of FIG. 4. FIG.
【図6】本発明に使用する構真注の更に他の一例を示す
要部側面図である。FIG. 6 is a side view of a main part showing still another example of a structural injection used in the present invention.
【図7】図6の構真柱の横断面図である。7 is a cross-sectional view of the true column of FIG.
【図8】本発明の施工方法の他の一例を説明する説明図
である。FIG. 8 is an explanatory diagram illustrating another example of the construction method of the present invention.
1…地盤,2…掘削孔,3…構真柱,4…コンクリー
ト,4f…一次コンクリート,4s…二次コンクリート,4r
…遅延剤入りコンクリート,5…トレミー管,6…ブリ
ージング水,7…フランジ,8…支圧補強板,8a…第1
板部,8b…第2板部1 ... Ground, 2 ... Drilled hole, 3 ... Structural column, 4 ... Concrete, 4f ... Primary concrete, 4s ... Secondary concrete, 4r
… Concrete with retarder, 5… Tremy tube, 6… Breathing water, 7… Flange, 8… Bearing reinforcement plate, 8a… 1st
Plate part, 8b ... Second plate part
───────────────────────────────────────────────────── フロントページの続き (72)発明者 青木 雅路 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 (72)発明者 武田 力 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 Fターム(参考) 2D041 AA01 BA04 CB05 DA03 EA04 EB02 2D050 AA13 CA04 CB03 EE10 EE18 ─────────────────────────────────────────────────── ─── Continued front page (72) Inventor Masaji Aoki Chiba Prefecture Inzai City 1-5 Otsuka 1 Stock Association Takenaka Corporation Technical Research Institute (72) Inventor Riki Takeda Chiba Prefecture Inzai City 1-5 Otsuka 1 Stock Association Takenaka Corporation Technical Research Institute F-term (reference) 2D041 AA01 BA04 CB05 DA03 EA04 EB02 2D050 AA13 CA04 CB03 EE10 EE18
Claims (4)
方に於いて、所定レベルまで一次コンクリートを打設し
た後、該コンクリート上に所定レベルまで遅延剤入りコ
ンクリートを順次打設し、次いで所定時間放置してブリ
ージングを発生させた後、遅延剤入りコンクリートが硬
化する前にその上方の構真柱の建込み部分に二次コンク
リートを打設して構真柱を定着させることを特徴とする
場所打ち構真台柱及び構真柱の施工方法。1. A primary concrete is poured to a predetermined level below the construction position of a true column built in an excavation hole, and then a concrete containing a retarder is sequentially cast to the predetermined level on the concrete. Then, after leaving for a predetermined time to cause breathing, before the concrete containing the retarder hardens, the secondary concrete is placed in the built-up portion of the structure column above it to fix the structure column. A cast-in-place column and a construction method for the column.
横断面T字状の支圧補強板を周方向複数突設した構真柱
である請求項1記載の構真台柱及び構真柱の施工方法。2. The true post of claim 1, wherein the true post is a true post in which a plurality of bearing reinforcing plates having a T-shaped cross section are provided on the outer surface of the fixing portion so as to project in the circumferential direction. Construction method of structure pillar.
定レベルまでコンクリートを打設した後、該コンクリー
ト上の構真柱建込み予定位置の所定レベルまで遅延剤入
りコンクリートを打設し、次いで所定時間放置してブリ
ージングを発生させた後、遅延剤入りコンクリートが硬
化する前に、遅延剤入りコンクリート内に構真柱の建込
みを行って構真柱を定着させることを特徴とする場所打
ち構真台柱及び構真柱の施工方法。3. After pouring concrete to a predetermined level below the planned construction position of the structural column in the excavation hole, concrete with a retarder is poured to a predetermined level at the planned construction position of the structural column on the concrete. Then, after allowing to stand for a predetermined time to cause breathing, before the concrete containing the retardant is hardened, the structure column is installed in the concrete containing the retardant to fix the structure column. Cast-in-place structure pillar and construction method of structure pillar.
横断面T字状の支圧補強板を周方向複数突設した構真柱
である請求項3記載の構真台柱及び構真柱の施工方法。4. The false-post column according to claim 3, wherein the false-post column is a false-post column in which a plurality of bearing reinforcing plates having a T-shaped cross section are provided in a protruding manner in the circumferential direction on the outer surface of the fixing portion. Construction method of structure pillar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002122303A JP3699056B2 (en) | 2002-04-24 | 2002-04-24 | Cast-in-place column and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002122303A JP3699056B2 (en) | 2002-04-24 | 2002-04-24 | Cast-in-place column and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003313862A true JP2003313862A (en) | 2003-11-06 |
JP3699056B2 JP3699056B2 (en) | 2005-09-28 |
Family
ID=29537955
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002122303A Expired - Fee Related JP3699056B2 (en) | 2002-04-24 | 2002-04-24 | Cast-in-place column and construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3699056B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107476287A (en) * | 2017-08-04 | 2017-12-15 | 广州市建筑科学研究院新技术开发中心有限公司 | A kind of deformed steel for SMW engineering methods and its construction method using the deformed steel |
-
2002
- 2002-04-24 JP JP2002122303A patent/JP3699056B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107476287A (en) * | 2017-08-04 | 2017-12-15 | 广州市建筑科学研究院新技术开发中心有限公司 | A kind of deformed steel for SMW engineering methods and its construction method using the deformed steel |
Also Published As
Publication number | Publication date |
---|---|
JP3699056B2 (en) | 2005-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2008240410A (en) | Bridge construction method, steel structure, and bridge | |
JP2006104747A (en) | Pier stud connection structure and pier stud connecting method | |
KR101606439B1 (en) | Spacer for fixing between truss girder and deck plate combine | |
JP4185870B2 (en) | Pile head joint structure and pile construction method | |
JP2006328666A (en) | Construction method for integrating pile with column | |
JP2010261270A (en) | Composite structure and method for constructing composite structure building | |
JP4844926B2 (en) | Column base joint structure and construction method | |
JP2000064305A (en) | Foundation structure of steel tower and construction thereof | |
JP2005105531A (en) | Foundation structure of building and its construction method | |
KR20090109678A (en) | System and method for underground downward construction using concrete filled tube | |
JP2003313862A (en) | Method for installing cast-in-place steel base column and steel column | |
JP2002030672A (en) | Structure of joining foundation pile to pier base and method of constructing the structure | |
JP2007218086A (en) | Steel tower foundation structure | |
JP2002322652A (en) | Joining construction method for pile head part to building frame and its joint part structure | |
JP6860381B2 (en) | Reinforcement method and structure of steel pipe pile using multiple fine crack type fiber reinforced cement composite material | |
JP2001271499A (en) | Temporary bearing construction method for existing building by steel batter brace member | |
JP2020070589A (en) | Reinforcement structure for column base part of steel column | |
JP2006188862A (en) | Construction method of structure, and foundation structure used for the same | |
JP3196412B2 (en) | Cast-in-place steel pipe concrete pile-column structure and its construction method | |
JP4298628B2 (en) | Construction method of viaduct beam using steel pipe column joint element | |
JP2000273880A (en) | Pile head connecting method | |
JPH1113067A (en) | Burying construction method for supplementary stud in reverse concreting construction method | |
JP2001254519A (en) | Reinforcing construction and reinforcing method using steel plate with joint bar | |
JP2006214195A (en) | Column structure for steel-frame structure and its constructing method | |
JP2004316278A (en) | Structure of steel pipe plinth part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Effective date: 20040802 Free format text: JAPANESE INTERMEDIATE CODE: A971007 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050222 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050414 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050705 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050706 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090715 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100715 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 6 Free format text: PAYMENT UNTIL: 20110715 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 6 Free format text: PAYMENT UNTIL: 20110715 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120715 Year of fee payment: 7 |
|
LAPS | Cancellation because of no payment of annual fees |