JP2003286725A - Immersion method of caisson - Google Patents
Immersion method of caissonInfo
- Publication number
- JP2003286725A JP2003286725A JP2002091065A JP2002091065A JP2003286725A JP 2003286725 A JP2003286725 A JP 2003286725A JP 2002091065 A JP2002091065 A JP 2002091065A JP 2002091065 A JP2002091065 A JP 2002091065A JP 2003286725 A JP2003286725 A JP 2003286725A
- Authority
- JP
- Japan
- Prior art keywords
- caisson
- ground
- smw
- construction
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【発明の詳細な説明】
【0001】
【発明の属する技術分野】本発明は、支持地盤が軟弱地
盤等のように不安定な場合であっても確実に施工できる
ケーソンの沈設方法に関する。
【0002】
【従来の技術】ケーソンの沈設方法は、図2に示す概要
図のように、地上において予め構築したケーソン1を支
持地盤2上に設置して、その下部3を掘削しながら支持
力4を減じながら、その自重もしくは荷重によって地中
に沈下させて行くものであることから、ケーソン1の沈
下は、支持地盤2の状況に大きく影響を受けている。
【0003】特に、支持地盤2が軟弱地盤の場合には、
支持力4の不足から施工不可能に至るケースや工事中の
過沈下による事故が発生する場合もあることから、これ
らの事故を未然に防ぐために、事前にボーリング調査を
行うことで所望の工事計画を立てているのが一般的であ
る。
【0004】しかしながら、このような工事計画に依っ
ても、支持地盤2を構成している地質の分布状況を完全
に把握することはできないことから、計画上の支持力が
得られないこともある。そして、仮に計画通りであった
としても、沈設中に地質の変化に伴って支持力が様々に
変化することに変わりは無いものであり、結果として高
い施工管理能力を求められているのが現状である。
【0005】
【発明が解決しようとする課題】本発明は、以上のよう
な現状に鑑みて提案するものであり、支持地盤が軟弱地
盤であってもケーソンの施工を可能にして、ケーソンの
過沈下も阻止することが出来るケーソンの沈設方法を提
供している。
【0006】
【課題を解決するための手段】本発明によるケーソンの
沈設方法は、ケーソンの刃口下部に該当する範囲に無芯
材で所定強度のソイルセメント連続壁(以下、SMWと
称する)を必要本数設置し、しかる後にSMWの上にケ
ーソンを設定して地盤及びSMWを掘削することで支持
力を低下させており、これによって、支持地盤が軟弱地
盤であってもケーソンの施工を可能にし、一定の支持力
を常に確保することで過沈下を防止することによって、
沈設作業の安定化を図ると共に、工期管理を容易にして
いる。
【0007】
【発明の実施の形態】本発明によるケーソンの沈設方法
は、最初に、沈設するケーソンの刃口下部に該当してい
る範囲に、無芯材で所定強度のSMWを必要な本数だけ
設置して置くものであり、しかる後に、このSMWの上
にケーソンを設定すると同時に、従来と同様な手法によ
って支持地盤及び設置したSMWを掘削することによっ
てケーソンの支持力を低下させるものであり、これによ
って、恒常的に安定した沈設作業可能にすると共に、施
工状態の安定化で確保される施工期間の特定によって総
工期の管理を容易にしている。
【0008】以下に、本発明によるケーソンの沈設方法
の実施形態を図面に基づいて詳細に説明する。尚、本発
明の理解を容易にするために、従来と同様の部位につい
ては同一の符号で表示している。
【0009】図1は、本発明によるケーソンの沈設方法
の実施形態を示しており、SMWの配列状態を示す平面
図(a)と図1(a)を(b)−(b)矢視した断面図
(b)で表現している。
【0010】本実施の形態では、躯体を構築するため
に、地上においてケーソン1を構築して支持地盤2上に
設置するものであるが、図1(a)に示すように沈設す
るケーソン1の刃口下部が設置される位置に該当する範
囲5に、SMW6を予め構築するものであり、ケーソン
1の荷重支持体として設置されている。
【0011】SMW6は、H鋼のような心材を用いずに
構成されると共に、ソイルセメントは、ケーソン1の刃
口下部で掘削する際の障害にならないような強度以下に
調合されている。
【0012】SMW6の本数は、上記のSMW6を用い
ることでケーソン1の躯体重量に合わせて決定されるも
のであり、必要な支持力に合わせて必要な本数を所定の
間隔で施工している。
【0013】ケーソン1は、SMW6が設置された後
に、このSMW6の群上に載置するように設置されるも
のであり、これによって、その全荷重若しくはその一部
はSMW6によって支持される。
【0014】従って、ケーソン1は、支持地盤2が例え
軟弱地盤であっても安定化された状態で支持地盤2上に
設置されることになる。
【0015】図1(b)は、ケーソン1をSMW6で支
持している状態を示している。本実施の形態では、支持
地盤2が軟弱地盤であっても、ケーソン1は、SMW
6、6の群上に載置されているので、支持力7が充分に
確保されており、支持力不足を生じることなく恒常的に
支持されている。
【0016】従って、ケーソン1を沈設させる時には、
従来と同様に掘削を行いながら重機を用いることによっ
て刃口下部のSMW6及び支持地盤2を崩して支持力を
低減させることが継続的に可能であり、ケーソン1の沈
設作業は、何らの支障を受けることなく順調に推進でき
る。
【0017】以上のように、本発明によるケーソンの沈
設方法は、実施の形態のように構成されているので、ケ
ーソンを沈設させる施工が不可能になる懸念は全く無く
なっており、工事中の過沈下による事故も発生すること
が無いから、これらの事故を未然に防ぐために事前のボ
ーリング調査を行う必要が無く、加えて、仮に沈設中に
地質の変化に伴なう支持力の変化が発生しても何らの支
障も生じないものであり、結果として施工管理を確実か
つ容易にしている。
【0018】以上、本発明によるケーソンの沈設方法
を、上記実施の形態に基づいて詳細に説明したが、本発
明は、これらの実施の形態に何ら限定されるものでな
く、発明の主旨を逸脱しない範囲において各種の変更が
可能であることは当然のことである。
【0019】
【発明の効果】本発明によるケーソンの沈設方法は、ケ
ーソンの刃口下部に該当する範囲に無芯材で所定強度の
SMWを必要本数設置し、しかる後にSMWの上にケー
ソンを設定して地盤及びSMWを掘削することで支持力
を低下させることで、支持地盤が軟弱地盤であってもケ
ーソンの施工を可能にし、一定の支持力を常に確保する
ことで過沈下を防止することによって、沈設作業の安定
化を図ると共に、工期管理を容易にする効果を奏してい
る。Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for laying a caisson that can be carried out reliably even when the supporting ground is unstable such as a soft ground. 2. Description of the Related Art As shown in a schematic diagram of FIG. 2, a caisson is laid down by placing a caisson 1 previously constructed on the ground on a supporting ground 2 and excavating a lower portion 3 of the caisson. 4, the sinking of the caisson 1 is greatly affected by the condition of the supporting ground 2 because the sinking of the caisson 1 is caused by sinking into the ground by its own weight or load while reducing the number of the ground. [0003] In particular, when the supporting ground 2 is soft ground,
In some cases, construction may not be possible due to lack of bearing capacity 4, and accidents due to excessive subsidence during construction may occur. It is common to set up. [0004] However, even with such a construction plan, the distribution of the geology constituting the supporting ground 2 cannot be completely grasped, so that the planned supporting capacity may not be obtained. . And even if it was as planned, the bearing capacity will change variously with the change of geology during subsidence, and as a result, high construction management capability is required at present. It is. SUMMARY OF THE INVENTION The present invention has been made in view of the above situation, and enables the construction of a caisson even if the supporting ground is soft ground, and allows the caisson to be installed. It provides a caisson squatting method that can also prevent subsidence. A caisson laying method according to the present invention comprises a step of forming a continuous wall (hereinafter, referred to as SMW) of a cement-free material having a predetermined strength in a region corresponding to a lower portion of a cutting edge of a caisson. The required number is installed, and after that, the caisson is set on the SMW and the ground and the SMW are excavated to reduce the supporting force, thereby making it possible to construct the caisson even if the supporting ground is soft ground. , By maintaining a constant bearing capacity to prevent oversinking,
It stabilizes the laying work and facilitates construction period management. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A caisson squatting method according to the present invention is as follows. First, in a range corresponding to a lower portion of a blade of a caisson to be sunk, a required number of coreless SMWs having a predetermined strength are provided. The caisson is set on this SMW, and at the same time, the supporting ground of the caisson is lowered by excavating the supporting ground and the installed SMW by the same method as before, As a result, it is possible to constantly and stably perform the laying work, and the management of the total construction period is facilitated by specifying the construction period secured by stabilizing the construction state. An embodiment of a caisson laying method according to the present invention will be described below in detail with reference to the drawings. In order to facilitate understanding of the present invention, the same parts as those in the related art are denoted by the same reference numerals. FIG. 1 shows an embodiment of a caisson laying method according to the present invention. FIG. 1 (a) is a plan view showing an arrangement state of SMWs and FIG. 1 (a) is viewed from arrows (b)-(b). This is represented by a sectional view (b). In this embodiment, a caisson 1 is constructed on the ground and installed on the supporting ground 2 in order to construct a skeleton. However, as shown in FIG. The SMW 6 is constructed in advance in a range 5 corresponding to the position where the lower part of the blade is installed, and is installed as a load support for the caisson 1. [0011] The SMW 6 is constructed without using a core material such as H steel, and the soil cement is formulated to have a strength or less so as not to hinder the excavation below the cutting edge of the caisson 1. The number of SMWs 6 is determined in accordance with the weight of the caisson 1 by using the above-described SMW 6, and the required number of SMWs 6 are installed at predetermined intervals in accordance with the required supporting force. The caisson 1 is installed so as to be mounted on the group of the SMW 6 after the SMW 6 is installed, so that the entire load or a part thereof is supported by the SMW 6. Therefore, the caisson 1 is installed on the supporting ground 2 in a stabilized state even if the supporting ground 2 is soft ground. FIG. 1B shows a state in which the caisson 1 is supported by the SMW 6. In the present embodiment, even if the supporting ground 2 is soft ground, the caisson 1
Since they are placed on the groups 6 and 6, the supporting force 7 is sufficiently ensured, and they are constantly supported without causing insufficient supporting force. Therefore, when the caisson 1 is laid down,
By using a heavy machine while excavating in the same manner as before, it is possible to continuously reduce the supporting force by breaking the SMW 6 and the supporting ground 2 below the cutting edge, and the work of submerging the caisson 1 does not hinder any kind. We can proceed smoothly without receiving it. As described above, the caisson laying method according to the present invention is configured as in the embodiment, so that there is no concern that the caisson laying work cannot be performed, and Since there is no accident due to subsidence, there is no need to conduct a drilling survey in advance to prevent these accidents, and in addition, if the bearing capacity changes due to geological changes during subsidence, This does not cause any trouble, and as a result, the construction management is made reliable and easy. As described above, the caisson squatting method according to the present invention has been described in detail based on the above embodiments. However, the present invention is not limited to these embodiments at all and departs from the gist of the invention. It goes without saying that various changes are possible within a range not to be performed. According to the method of laying a caisson according to the present invention, a required number of coreless SMWs having a predetermined strength are installed in the area corresponding to the lower part of the blade of the caisson, and then the caisson is set on the SMW. To reduce the bearing capacity by excavating the ground and SMW, thereby enabling caisson construction even when the supporting ground is soft ground, and preventing over-subsidence by constantly securing a constant bearing force This has the effect of stabilizing the laying work and facilitating construction period management.
【図面の簡単な説明】
【 図1】本発明によるケーソンの沈設方法の実施形態
図
【 図2】従来におけるケーソンの沈設方法の概要図
【符号の説明】
1 ケーソン、 2 支持地盤、 3 ケーソンの下
部、 4、7 支持力、5 刃口下部の範囲、 6 S
MW、BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an embodiment of a caisson laying method according to the present invention. FIG. 2 is a schematic diagram of a conventional caisson laying method. [Description of symbols] 1 caisson, 2 supporting ground, 3 caisson Lower part, 4, 7 Supporting force, 5 Range of lower part of cutting edge, 6 S
MW,
Claims (1)
芯材で所定強度のソイルセメント連続壁を必要本数設置
し、しかる後に該ソイルセメント連続壁の上にケーソン
を設定して地盤及びソイルセメント連続壁を掘削するこ
とで支持力を低下させるケーソンの沈設方法。Claims: 1. A required number of soil-cement continuous walls made of a coreless material having a predetermined strength are installed in an area corresponding to a lower portion of a blade of a caisson, and thereafter, a caisson is placed on the soil-cement continuous wall. A caisson laying method that lowers the bearing capacity by excavating the ground and soil cement continuous wall by setting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002091065A JP2003286725A (en) | 2002-03-28 | 2002-03-28 | Immersion method of caisson |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002091065A JP2003286725A (en) | 2002-03-28 | 2002-03-28 | Immersion method of caisson |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2003286725A true JP2003286725A (en) | 2003-10-10 |
Family
ID=29236242
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002091065A Pending JP2003286725A (en) | 2002-03-28 | 2002-03-28 | Immersion method of caisson |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2003286725A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015110871A (en) * | 2013-12-06 | 2015-06-18 | 鹿島建設株式会社 | Caisson immersion method and underground column body group |
CN111827264A (en) * | 2020-07-21 | 2020-10-27 | 重鑫岩土技术(上海)有限公司 | Method for constructing steel reinforced concrete underground continuous wall by using steel caisson technology |
-
2002
- 2002-03-28 JP JP2002091065A patent/JP2003286725A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015110871A (en) * | 2013-12-06 | 2015-06-18 | 鹿島建設株式会社 | Caisson immersion method and underground column body group |
CN111827264A (en) * | 2020-07-21 | 2020-10-27 | 重鑫岩土技术(上海)有限公司 | Method for constructing steel reinforced concrete underground continuous wall by using steel caisson technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2008013926A (en) | Existing building foundation reinforcing method | |
JPS62288218A (en) | Settlement caisson | |
JP2003286725A (en) | Immersion method of caisson | |
JP6645098B2 (en) | Removal method of existing pile | |
JP2001303883A (en) | Excavation method using earth retaining structure composed of ring beam, inverted lining wall and rock bolt | |
CN208396651U (en) | Rectangle pile foundation drilling construction equipment | |
JP3702435B2 (en) | How to build the foundation | |
JPS60184128A (en) | Sinking method for caisson | |
CN206887984U (en) | A kind of photovoltaic generation support steel bar concrete reinforcement steel pipe pile foundation | |
KR200316588Y1 (en) | Apparatus for belling out deep foundation | |
JP2000178966A (en) | Structure of diaphragm wall | |
JPS5843532B2 (en) | Caisson sinking method | |
JP2015187344A (en) | Buried structure of prefabricated pile and burying method of prefabricated pile | |
JP4146250B2 (en) | Open caisson bottom plate construction method | |
KR100491428B1 (en) | Reinforced in situ concrete pier on slope | |
JPH03250117A (en) | Construction method of bottom enlarged continuous wall | |
JP2794069B2 (en) | Anchor construction method | |
CN106284411A (en) | The excavation method of sunk type subway station | |
JP2515038B2 (en) | Construction method of underground wall with variable cross section | |
JPS6229625A (en) | Settling construction for open caisson | |
JPH11158891A (en) | Construction of basement for residence | |
CN109024624A (en) | Slab muscle pre-embedded construction method between a kind of slope stake | |
JPH10121465A (en) | Continuos underground wall engineering method | |
JP2015183374A (en) | Pile construction method | |
JPH1121909A (en) | Whole rotational type caisson and immersion method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Effective date: 20040129 Free format text: JAPANESE INTERMEDIATE CODE: A621 |
|
RD02 | Notification of acceptance of power of attorney |
Effective date: 20040712 Free format text: JAPANESE INTERMEDIATE CODE: A7422 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060206 |
|
A131 | Notification of reasons for refusal |
Effective date: 20060214 Free format text: JAPANESE INTERMEDIATE CODE: A131 |
|
A02 | Decision of refusal |
Effective date: 20060613 Free format text: JAPANESE INTERMEDIATE CODE: A02 |