CN109024624A - Slab muscle pre-embedded construction method between a kind of slope stake - Google Patents

Slab muscle pre-embedded construction method between a kind of slope stake Download PDF

Info

Publication number
CN109024624A
CN109024624A CN201810828407.1A CN201810828407A CN109024624A CN 109024624 A CN109024624 A CN 109024624A CN 201810828407 A CN201810828407 A CN 201810828407A CN 109024624 A CN109024624 A CN 109024624A
Authority
CN
China
Prior art keywords
stake
friction pile
embedded
muscle
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810828407.1A
Other languages
Chinese (zh)
Inventor
高蕤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201810828407.1A priority Critical patent/CN109024624A/en
Publication of CN109024624A publication Critical patent/CN109024624A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses slab muscle pre-embedded construction methods between a kind of slope stake, belong to civil construction technical field, comprising: drill through drilling according to plate plate muscle position level between stake using drill on friction pile the friction pile armlet of pore-forming;Friction pile main reinforcement and stirrup are installed;Place embedded bar;Embedded bar blocked at friction pile armlet with mortar closely knit;Pour concrete piles.Bar planting depth of the present invention can satisfy anchoring and require, and can guarantee the stabilization and safety of side slope;The pre-buried problem of plate plate muscle between very good solution of the present invention slope retaining friction pile stake, it is ensured that slab muscle construction quality between stake, and this method is simple to operation, has good economy and society to be worth.

Description

Slab muscle pre-embedded construction method between a kind of slope stake
Technical field
The invention belongs to civil construction technical field, it is specifically related to slab muscle pre-embedded construction method between a kind of slope stake.
Background technique
This engineering is located at Guiyang City, Guizhou Province, belongs to karst landform, engineering construction needs a large amount of excavation massifs, in order to subtract Few excavated volume, portion need vertical cut supporting.The supporting of this engineering massif is constructed using plate between friction pile and stake Method for protecting support first excavates friction pile according to design position, excavates plate between massif and construction stake, plate muscle after antiskid pile driving construction is complete again The method for generalling use rear plant anchor, because of massif distance limitation when bar planting, it is difficult to ensure that rebar-planting quality, it is therefore necessary to right Plate plate muscle anchoring research counter-measure between stake.
Slab muscle anchoring construction is there are hidden danger of quality between carrying out stake with bar planting method after routine, due between stake when plate bar planting it is another Massif is close in side to make troubles to bar planting, and bar planting depth is difficult to meet anchoring requirement, not can guarantee the stabilization and peace of side slope Entirely.
The present invention is invented aiming at plate Bar Anchorage between similar stake.By changing sequence of construction and method, in advance It is pre-buried to reach Bar Anchorage requirement.
Summary of the invention
It, being capable of plate between the slope stake of preposition construction the technical problems to be solved by the present invention are: it is simple to provide a kind of operation Reinforcing bar pre-embedded construction method.
In order to solve the above-mentioned technical problem, inventor obtains technical solution of the present invention by practice and summary, the present invention Disclose slab muscle pre-embedded construction method between a kind of slope stake, comprising the following steps:
Step 1: it is bored using drill according to plate plate muscle position level between stake on friction pile the friction pile armlet of pore-forming Take drilling;
Step 2: installation friction pile main reinforcement and stirrup;
Step 3: embedded bar is placed;
Step 4: embedded bar blocked at friction pile armlet with mortar closely knit;
Step 5: concrete piles are poured.
The depth to drill in step 1 is determined according to the lap of splice of reinforcing bar, and drilling is cleaned out.
Anchoring requirement should be met for embedding section of embedded bar in step 3.
The pre-buried depth of embedded bar is determined according to pile shaft concrete strength and bar diameter is poured.
The embedded bar diameter is 450mm.
Compared with prior art, the present invention can obtain following technical effect:
1. plate plate muscle pre-buried problem between very good solution of the present invention slope retaining friction pile stake, it is ensured that slab muscle is applied between stake Working medium amount, and this method is simple to operation, has good economy and society to be worth.
2. bar planting depth of the present invention can satisfy anchoring and require, it can guarantee the stabilization and safety of side slope.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, those of ordinary skill in the art are come It says, without creative efforts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is the pre-buried sectional view of slab muscle between stake;
Fig. 2 is the pre-buried plan view of slab muscle between stake.
In figure: 1. friction piles, 2. armlets, plate between 3., 4. embedded bars, 5. drillings, 6. mortars, 7. main reinforcements, 8. stirrups.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
With reference to the accompanying drawing and specific embodiment is further described application principle of the invention.
Embodiment 1
It is as shown in Figs. 1-2:.
Slab muscle pre-embedded construction method between a kind of slope stake, comprising the following steps:
Step 1: using drill according to 3 plate muscle position water of plate between stake on friction pile 1 the friction pile armlet 2 of pore-forming Flat drill takes drilling 5;
Step 2: installation friction pile main reinforcement 7 and stirrup 8;
Step 3: embedded bar 4 is placed;
Step 4: embedded bar 4 is blocked at friction pile armlet 2 with mortar 6 closely knit;
Step 5: concrete piles are poured.
The depth of drilling 5 is determined according to the lap of splice of reinforcing bar in step 1, and drilling is cleaned out.
Anchoring requirement should be met for 4 embedding sections of embedded bar in step 3.
The pre-buried depth of the embedded bar 4 is determined according to pile shaft concrete strength and bar diameter is poured.
4 diameter of embedded bar is 450mm.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (5)

1. slab muscle pre-embedded construction method between a kind of slope stake, it is characterised in that: the following steps are included:
Step 1: using drill according to plate between stake (3) plate muscle position on friction pile (1) the friction pile armlet (2) of pore-forming Level drills through drilling (5);
Step 2: installation friction pile main reinforcement (7) and stirrup (8);
Step 3: it places embedded bar (4);
Step 4: embedded bar (4) is blocked at friction pile armlet (2) with mortar (6) closely knit;
Step 5: concrete piles are poured.
2. slab muscle pre-embedded construction method between a kind of slope stake according to claim 1, it is characterised in that: bored in step 1 The depth in hole (5) is determined according to the lap of splice of reinforcing bar, and drilling is cleaned out.
3. slab muscle pre-embedded construction method between a kind of slope stake according to claim 1, it is characterised in that: pre- in step 3 Anchoring requirement should be met by burying embedding section of reinforcing bar (4).
4. slab muscle pre-embedded construction method between a kind of slope stake according to claim 1, it is characterised in that: the pre-buried steel Muscle (4) pre-buried depth is determined according to pile shaft concrete strength and bar diameter is poured.
5. slab muscle pre-embedded construction method between a kind of slope stake according to claim 1, it is characterised in that: the pre-buried steel Muscle (4) diameter is 450mm.
CN201810828407.1A 2018-07-25 2018-07-25 Slab muscle pre-embedded construction method between a kind of slope stake Pending CN109024624A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810828407.1A CN109024624A (en) 2018-07-25 2018-07-25 Slab muscle pre-embedded construction method between a kind of slope stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810828407.1A CN109024624A (en) 2018-07-25 2018-07-25 Slab muscle pre-embedded construction method between a kind of slope stake

Publications (1)

Publication Number Publication Date
CN109024624A true CN109024624A (en) 2018-12-18

Family

ID=64646198

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810828407.1A Pending CN109024624A (en) 2018-07-25 2018-07-25 Slab muscle pre-embedded construction method between a kind of slope stake

Country Status (1)

Country Link
CN (1) CN109024624A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201581411U (en) * 2009-12-31 2010-09-15 中铁二院昆明勘察设计研究院有限责任公司 Inclined inserting sheet pile wall
KR20140078395A (en) * 2012-12-17 2014-06-25 한국철도기술연구원 Anchored retaining wall of gravity block type, and constructing method for the same
CN108265733A (en) * 2018-04-11 2018-07-10 王凯 Build-in soil body restricted type pile slab supporting structure and construction method before stake

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201581411U (en) * 2009-12-31 2010-09-15 中铁二院昆明勘察设计研究院有限责任公司 Inclined inserting sheet pile wall
KR20140078395A (en) * 2012-12-17 2014-06-25 한국철도기술연구원 Anchored retaining wall of gravity block type, and constructing method for the same
CN108265733A (en) * 2018-04-11 2018-07-10 王凯 Build-in soil body restricted type pile slab supporting structure and construction method before stake

Similar Documents

Publication Publication Date Title
KR100964796B1 (en) Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction
CN104631438B (en) Long auger guncreting uplift pile construction method
KR20140078395A (en) Anchored retaining wall of gravity block type, and constructing method for the same
KR20100068597A (en) A shoring method using arch plate pile and h-pile
JP2008057184A (en) Method of constructing underground wall by using h-shaped pc pile
CN107100160A (en) A kind of construction technology for lower storage reservoir check dam vibro-replacement stone column
KR20100065521A (en) A shoring method using arch plate pile and h-pile
KR20090116452A (en) Composite wall using angled channel
CN109989407A (en) Railway increases two wires platform way of escape foundation pile pipe curtain supporting construction newly
KR100534603B1 (en) Apparatus for Retaining Wall Using a Ground Anchor And the Method Using the Same
JP2007046343A (en) Liquefaction preventive construction method of ground just under existing building
CN109024624A (en) Slab muscle pre-embedded construction method between a kind of slope stake
JP4485006B2 (en) Construction method for underground structures
CN102434718A (en) Method for reinforcing originating end of push bench
JP3760343B2 (en) Drilling bottom stabilization method and construction method of underground building
CN104727305B (en) Boring high-pressure slip-casting uplift pile construction method
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
KR101437882B1 (en) Tunnel excavating method having various cross sectional shapes
JP2000110171A (en) Settling method for underground construction
CN100591861C (en) Mixing pile foundation pit supporting structure
JP4623577B2 (en) How to build cast-in-place piles
JP2005090015A (en) Ground excavating method
KR101649210B1 (en) Steel pipe wall temporary construction
KR102625776B1 (en) Construction method of CIP retaining wall with improved water protection and ground subsidence prevention function
JP5670595B2 (en) Vertical shaft construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181218

RJ01 Rejection of invention patent application after publication