JP2003274564A - Method and device for controlling operation of private power generation system - Google Patents

Method and device for controlling operation of private power generation system

Info

Publication number
JP2003274564A
JP2003274564A JP2002072631A JP2002072631A JP2003274564A JP 2003274564 A JP2003274564 A JP 2003274564A JP 2002072631 A JP2002072631 A JP 2002072631A JP 2002072631 A JP2002072631 A JP 2002072631A JP 2003274564 A JP2003274564 A JP 2003274564A
Authority
JP
Japan
Prior art keywords
power
generators
load
power generation
generation system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002072631A
Other languages
Japanese (ja)
Inventor
Kazuhiko Kato
一彦 加藤
Koji Ito
康志 伊藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2002072631A priority Critical patent/JP2003274564A/en
Publication of JP2003274564A publication Critical patent/JP2003274564A/en
Pending legal-status Critical Current

Links

Abstract

<P>PROBLEM TO BE SOLVED: To realize an operation control method for a private power generation system, which enables minimum cost operation by considering the unit cost of the purchased power and the estimated unit cost of generated power. <P>SOLUTION: In this operation control method for a private power generation system which has a plurality of generators 4, when the load becomes two small if the number of generators, for example, is increased from one or the loads is two small for the two units of generators now in operation, the unit cost of the purchased power at that time is compared with the estimated unit cost of the generated power; if the unit cost of the purchased power is lower than the other, the quantity of power to be purchased is increased, and the number of generators in operation is kept to one or the two units in operation area reduced into one (chain 1). Power, the day demand is inputted in advance. And, in the case that to small a load is forecast, the quantity of power to be purchased is increased, and the number of generators is reduced before that. Likewise, when sudden drop in power load is predicted, the quantity of power to be purchased is increased to a quantity not to cause a reverse current, and the number of generators is reduced (chain 3). <P>COPYRIGHT: (C)2003,JPO

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は自家用発電システム
の運転制御方法および運転制御装置に関し、例えば液体
燃料もしくは気体燃料を燃焼させ発生させた軸動力で発
電機を駆動し電力を発生させる常用自家用発電機や、排
熱を利用するコージェネレーションシステム等について
の運転制御方法および運転制御装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an operation control method and an operation control apparatus for a private power generation system, for example, a private private power generation system in which a generator is driven by an axial power generated by burning liquid fuel or gas fuel to generate electric power. The present invention relates to an operation control method and an operation control device for a machine, a cogeneration system that uses exhaust heat, and the like.

【0002】[0002]

【従来の技術】自家用発電システムの一例であるディー
ゼルコージェネレーションシステムを図8〜図10に示
す。図8は基本的な構成例を示す建屋正面縦断面図、図
9は基本的な構成例を示す建屋側面縦断面図、図10は
排熱、電力等の基本的な流れを示すフロー図である。
2. Description of the Related Art A diesel cogeneration system, which is an example of a private power generation system, is shown in FIGS. FIG. 8 is a vertical cross-sectional view of a building front view showing a basic configuration example, FIG. 9 is a vertical cross-sectional view of a building side view showing a basic configuration example, and FIG. 10 is a flow chart showing a basic flow of waste heat, electric power, etc. is there.

【0003】図8に示す主燃料タンク1より小分けされ
た燃料は燃料小出槽2に一時保管され、燃料供給装置
(図示せず)によりエンジン3に供給される。エンジン
3で発生する軸動力は発電機4に伝達され発電が行われ
る。
The fuel subdivided from the main fuel tank 1 shown in FIG. 8 is temporarily stored in the fuel dispensing tank 2 and supplied to the engine 3 by a fuel supply device (not shown). The shaft power generated by the engine 3 is transmitted to the generator 4 to generate power.

【0004】この時、図10に示すように一次冷却水5
はエンジン3を冷却し温水となる。この温水は熱交換器
6に送られ、ここで熱の移動が行われて温水7が発生す
る。温水7は、プロセスに使用されるほか、図9、図1
0に示す蒸気排ガスボイラー8に通され蒸気9となる。
これによりエンジン3から出る排熱は有効に利用され
る。
At this time, as shown in FIG. 10, the primary cooling water 5
Turns the engine 3 into hot water. This hot water is sent to the heat exchanger 6, where heat is transferred to generate hot water 7. The hot water 7 is used in the process and also in FIGS.
The steam exhaust gas boiler 8 shown in FIG.
As a result, the exhaust heat emitted from the engine 3 is effectively used.

【0005】排ガスは図9に示す消音器10を通り煙突
11より排出される。排熱回収されない場合、排熱は他
の熱交換器12を経由して冷却塔13により放熱され
る。また、以上の制御は制御ユニット14に設けられた
運転制御装置(図1参照)により行われている。
The exhaust gas passes through the silencer 10 shown in FIG. 9 and is discharged from the chimney 11. When the exhaust heat is not recovered, the exhaust heat is radiated by the cooling tower 13 via the other heat exchanger 12. The above control is performed by the operation control device (see FIG. 1) provided in the control unit 14.

【0006】次に、上記自家用発電システムの運転制御
装置で行われる運転制御について説明する。
Next, the operation control performed by the operation control device of the private power generation system will be described.

【0007】通常は、電力会社受電系統に対して常時系
統連系運転を行い、所内電力用として使用する。不足電
力分は電力会社より受電する。電力会社と逆潮流有りで
契約している場合は、余剰電力を電力会社へ逆送電する
ケースもある。逆潮流無しの場合、大別すれば、従来の
運転制御は下記のケース1〜3に分けられる。なお、図
11において15は発電状況、16は受電状況を示す。
Normally, the power receiving system of the electric power company is always connected to the grid and used for power supply in the office. The power shortage will be received from the power company. If there is a reverse flow contract with an electric power company, surplus power may be reversely transmitted to the electric power company. When there is no reverse power flow, the operation control of the related art can be roughly divided into the following cases 1 to 3. In addition, in FIG. 11, reference numeral 15 indicates a power generation status, and 16 indicates a power reception status.

【0008】ケース1.図11(A)のように電力負荷
がほぼ一定の場合、自家用発電システムの容量は100
%出力運転となる大きさとされ、24時問運転を行う。
Case 1. When the power load is almost constant as shown in FIG. 11A, the capacity of the private power generation system is 100.
The size is such that% output operation is performed, and 24-hour operation is performed.

【0009】ケース2.図11(B)のように山形の電
力負荷の場合、山の頂のみ運転を行う(ピークカッ
ト)。
Case 2. In the case of a mountain-shaped power load as shown in FIG. 11 (B), only the top of the mountain is operated (peak cut).

【0010】ケース3.電力単価を勘案する場合、図1
1(C)に示すように電力単価の高い昼間は自家用発電
システムを出来る限り100%出力で運転し、電力単価
の安い夜間は自家用発電システムを止めるか、契約電力
を超える分について最低限の運転を行う。
Case 3. When considering the unit price of electricity, see Figure 1.
As shown in 1 (C), the private power generation system is operated at 100% output as much as possible during the day when the power unit price is high, and the private power generation system is stopped at night when the power unit price is low, or the minimum operation for the amount exceeding the contracted power. I do.

【0011】ここで、上記ケース1の場合及び、電力会
社との逆潮流有りで契約している場合、自家用発電シス
テムは100%出力で運転する。しかし、上記ケース2
又はケース3の場合、現在の電力負荷状況により、自家
用発電システムの発電量を制御する。
Here, in case 1 above and when a contract is made with a power company with reverse power flow, the private power generation system operates at 100% output. However, case 2 above
Alternatively, in case 3, the power generation amount of the private power generation system is controlled according to the current power load condition.

【0012】具体的には、ケース2の場合、契約電力を
超える前に自家用発電システムを起動し、契約電力を超
える分を自家用発電システムで賄い、基本料金の削減と
従量料金の削減を行う。
[0012] Specifically, in case 2, the private power generation system is started before the contract power is exceeded, and the private power generation system is used to cover the excess of the contract power to reduce the basic charge and the usage-based charge.

【0013】また、ケース3で季時別契約を実施した場
合、夜間の安い電力料金の場合は、出来るだけ自家用発
電システムを止め、契約電力を超える場合のみ発電し、
一方、昼間は電力料金が高いため、出来る限り自家用発
電システムを運転し、基本料金の削減分と従量料金の削
減分でメリットを出すようにする。
In case 3, when a seasonal contract is carried out and the electric power charge is low at night, the private power generation system is stopped as much as possible, and power is generated only when the contracted power is exceeded.
On the other hand, during the daytime, electricity charges are high, so the private power generation system should be operated as much as possible, and the reduction in basic charges and the reduction in pay-as-you-go charges should bring benefits.

【0014】ただ、実際の電力負荷は変動があり、この
変動に自家用発電システムが瞬時に反応できずタイムラ
グがある。また、エンジン性能により最低動作容量が決
まっている。このため、実際の運転制御は余裕がある状
態で行われている。
However, the actual electric power load fluctuates, and the private power generation system cannot instantaneously react to this fluctuation, which causes a time lag. Also, the minimum operating capacity is determined by the engine performance. Therefore, the actual operation control is performed with a margin.

【0015】今、発電機2台の自家用発電システムで、
仮に電力負荷0の状態より電力負荷が増え、或いは電力
負荷が減少していく場合について述べる。各発電機の発
電状況の例を図12に、電力負荷が増加する場合(後述
1)〜4))の処理手順例を図13に、減少する場合
(後述5)〜6))の処理手順例を図14に示す。図1
2において、17は電力負荷を0より増大させ3000
kWまで増加させた後減少させたときの電力負荷状況
を、18、19は事例として1000kWの発電機2台
としたときの、l台目、2台目の発電状況をそれぞれ示
す。
Now, in a private power generation system with two generators,
A case where the power load increases or the power load decreases from the state where the power load is 0 will be described. An example of the power generation status of each generator is shown in FIG. 12, an example of a processing procedure when the electric power load increases (1) to 4) described below is shown in FIG. 13, and a processing procedure when the electric load decreases (5) to 6) described later). An example is shown in FIG. Figure 1
In 2, 17 increases the power load from 0 to 3000
The power load states when the power load is increased to kW and then decreased, and 18 and 19 respectively show the power generation states of the first and second units when two 1000 kW generators are used as an example.

【0016】具体的には、 1)電力負荷が増え(図13のステップS101YE
S)、予測発電単価の方が買電単価より安い場合(ステ
ップS102YES)、自家用発電システムを起動する。
但しこの場合、電力負荷が、最低受電一定値にエンジン
の最低動作容量と余裕分とを和した値を超えた時から1
台目の発電を開始する(ステップS103YES→ステッ
プS104)。
Specifically, 1) the power load increases (step S101YE in FIG. 13).
S) If the predicted power generation unit price is lower than the power purchase unit price (YES in step S102), the private power generation system is activated.
However, in this case, the power load exceeds 1 from the time when the minimum power receiving constant value exceeds the minimum operating capacity of the engine and the margin.
Power generation for the second stage is started (step S103 YES → step S104).

【0017】2)更に電力負荷が増え(ステップS10
7YES)複数台運転をする場合は、現在運転中の発電機
が100%出力運転となる前に余裕を持って次号機の運
転を開始する(ステップS)。一般的には80%程度で
次号機の運転を開始するため(ステップS109YES→
ステップS110)、2台運転の場合、40%の低負荷
運転となる。
2) The power load is further increased (step S10).
7YES) When operating a plurality of units, start the operation of the next unit with a margin before the generator currently in operation becomes 100% output operation (step S). Generally, the operation of the next unit is started at about 80% (step S109 YES →
(Step S110) In the case of two-unit operation, 40% low load operation is performed.

【0018】3)更に電力負荷が増えると(ステップS
111YES)、2台共100%運転するまで発電量を増
加させていき(ステップS112→ステップS113NO
→ステップS111YES→ステップS112の繰り返
し)、それ以降は買電量を増やすことにより電力負荷を
まかなう事となる(ステップS113YES→ステップS
114)。
3) When the power load further increases (step S
111YES) Increase the amount of power generation until both units operate 100% (step S112 → step S113NO)
→ Step S111 YES → Step S112 is repeated), and thereafter, the power load is covered by increasing the power purchase amount (Step S113 YES → Step S113).
114).

【0019】4)なお、買電単価が予測発電単価より高
い場合(ステップS102NO)、電力負荷が、契約電力
量から最低受電一定値とエンジンの最低動作容量と余裕
分とを差し引いた値を超えた時より1台目の発電を開始
する(ステップS106YES→ステップS104)。
4) When the unit price of power purchase is higher than the estimated unit price of power generation (NO in step S102), the power load exceeds the value obtained by subtracting the minimum constant power reception value, the minimum operating capacity of the engine, and the margin from the contract power amount. Then, the power generation of the first unit is started (YES in step S106 → step S104).

【0020】5)電力負荷が減り(図14ステップS2
01YES〜ステップS205)、自家用発電システムを
停止する場合は、電力負荷の変動を考慮し、低負荷状態
になってから、具体的には単機発電量が40%程度にな
ってから停止させる(ステップS205YES→ステップ
S206)。この結果、2台運転していて2台目が停止
され1台での運転になった場合、80%運転となる。
5) The power load is reduced (step S2 in FIG. 14).
01YES-step S205), when stopping the private power generation system, in consideration of the fluctuation of the power load, after the low load state, specifically, when the single-unit power generation amount reaches about 40%, stop the power generation system (step S205 YES → step S206). As a result, if two units are in operation and the second unit is stopped and only one unit is in operation, the operation will be 80%.

【0021】6)更に電力負荷が減り(ステップS20
7〜ステップS210)、残り1台の発電機を停止する
場合は、電力負荷の変動を考慮し、低負荷状態になって
から具体的には単機発電量が40%程度になってから停
止させる(ステップS210YES→ステップS21
1)。
6) The power load is further reduced (step S20).
7 to step S210), when stopping the remaining one generator, in consideration of the fluctuation of the electric power load, after the low load state, specifically, stop the generator after the single-unit power generation amount reaches about 40%. (Step S210 YES → Step S21
1).

【0022】[0022]

【発明が解決しようとする課題】上記のような運転制御
をした場合、以下に述べるような課題があった。
When the above operation control is performed, there are the following problems.

【0023】すなわち、現状の電力負荷に応じて自家用
発電システムの発電台数を決定するが、電力負荷の変動
(増加・減少)を見ていない分、余裕を見て発電台数の
増加・減少をさせる必要があり、その分、低負荷運転、
即ち効率の悪い運転になる。
That is, the number of power generations of the private power generation system is determined according to the current power load, but since the fluctuation (increase / decrease) of the power load is not observed, the number of power generations is increased / decreased with a margin. It is necessary, the low load operation,
That is, the operation becomes inefficient.

【0024】また、電力会社と逆潮流なしの契約をして
いる場合、最大容量の設備が停止した場合でも逆潮流を
しないよう受電一定電力を設定し、その分は電力会社よ
り受電するが、この場合、電力負荷が発電機容量+受電
一定電力より少ない場合は100%運転が出来ず、燃費
の悪い低負荷での運転をすることとなる。
In addition, when a contract is made with a power company without reverse power flow, even if the equipment with the maximum capacity is stopped, a certain amount of power is set so that the reverse power flow is not received, and that amount is received from the power company. In this case, when the electric power load is less than the generator capacity + constant electric power received, 100% operation cannot be performed, and operation is performed at a low load with poor fuel economy.

【0025】さらに、昼休み等で一斉に設備が停止され
電力負荷が激減する場合、自家用発電システムが迫従で
きず逆潮流に至る場合がある。そのため最低受電一定値
を大きく取る必要があり、経済的な運転ができない。
Further, when the facilities are stopped all at once such as during lunch break and the electric power load is drastically reduced, the private power generation system may not be able to follow and a reverse flow may occur. Therefore, it is necessary to take a large constant value for minimum power reception, and economical operation cannot be performed.

【0026】本発明は上記事情に鑑みてなされたもので
あり、その目的は、上記従来技術の欠点を解消し、買電
単価と予測発電単価とを勘案したコストミニマムな運転
を可能とする自家用発電システムの運転制御方法および
運転制御装置を提供することにある。
The present invention has been made in view of the above circumstances, and an object thereof is to solve the above-mentioned drawbacks of the prior art and to enable a cost-minimum operation in consideration of the purchase price of electricity and the estimated electricity generation rate. An object is to provide an operation control method and an operation control device for a power generation system.

【0027】また、負荷変動にも柔軟に対応し、しかも
コストミニマムな運転を可能にする自家用発電システム
の運転制御方法および運転制御装置を提供することにあ
る。
It is another object of the present invention to provide an operation control method and an operation control device for a private power generation system that flexibly copes with load fluctuations and enables cost-minimum operation.

【0028】また、昼休みなどの急激な負荷変動にも逆
潮流を起こさずに柔軟に対応し、しかもコストミニマム
な運転を可能にする自家用発電システムの運転制御方法
及び運転制御装置を提供することにある。
Further, it is an object of the present invention to provide an operation control method and an operation control device for a private power generation system that flexibly responds to a sudden load change such as lunch break without causing a reverse power flow, and that enables a cost-minimum operation. is there.

【0029】[0029]

【課題を解決するための手段】上記目的達成のため請求
項1の発明では、複数の発電機を有する自家用発電シス
テムの運転制御方法において、発電機台数を増加させる
と低負荷になる場合又は現在発電している各発電機が低
負荷になった場合に、そのときの買電単価を予測発電単
価と比較し、買電単価の方が安価であるときは、買電す
る量を増加させると共に発電機台数を少ないまま維持す
るか又は発電機台数を削減する。
In order to achieve the above object, according to the invention of claim 1, in the operation control method of a private power generation system having a plurality of generators, when the number of generators increases, the load becomes low, or at present. When each generator that is generating electricity has a low load, compare the unit power purchase price at that time with the predicted power generation unit price, and if the power purchase unit price is cheaper, increase the amount of power purchased and Either keep the number of generators low or reduce the number of generators.

【0030】また、請求項2の発明では、複数の発電機
を有する自家用発電システムの運転制御方法において、
電力日負荷を予め入力しておき、該電力日負荷に基づく
電力負荷予測で該電力負荷の低下が予測された場合に、
該予測された電力負荷の低下以前に買電する量を増加さ
せると共に前記発電機の運転台数を減少させる。
Further, in the invention of claim 2, in the operation control method of the private power generation system having a plurality of generators,
If the power daily load is input in advance and a decrease in the power load is predicted by the power load prediction based on the power daily load,
Before the predicted reduction of the electric power load, the amount of power purchased is increased and the number of operating generators is decreased.

【0031】また、請求項3の発明では、複数の発電機
を有する自家用発電システムの運転制御方法において、
電力日負荷を予め入力しておき、該電力日負荷に基づく
電力負荷予測で該電力負荷の急激な低下が予測された場
合に、該予測された電力負荷の急激な低下以前に、該電
力負荷の急激な低下によっても逆潮流が起きないところ
まで買電する量を増加させると共に前記発電機の運転台
数を減少させ、且つ通常は最低受電量を低下させてお
く。
According to a third aspect of the invention, in the operation control method of the private power generation system having a plurality of generators,
If the power daily load is input in advance and a sharp decrease in the power load is predicted by the power load prediction based on the power daily load, the power load is calculated before the predicted sharp decrease in the power load. Is increased, the amount of power purchased is increased to the point where the reverse flow does not occur, the operating number of the generators is decreased, and the minimum amount of power received is normally decreased.

【0032】また、請求項4の発明では、複数の発電機
を有する自家用発電システムの運転制御装置において、
電力負荷および発電機の運転台数を監視する監視手段
と、発電機台数を増加させると低負荷になる場合又は現
在発電している各発電機が低負荷になった場合に、その
ときにおける商用電力の買電単価と前記発電機の予測発
電単価とを比較する電力単価比較手段と、比較の結果、
買電単価の方が安価である場合には、買電量を増加させ
ると共に発電機台数を少ないまま維持するか又は発電機
台数を削減するかいずれかの台数制御を行う制御手段と
を備えている。
According to a fourth aspect of the invention, in the operation control device of the private power generation system having a plurality of generators,
Monitoring means for monitoring the power load and the number of generators in operation, and commercial power at that time when the number of generators increases and the load becomes low, or when each generator currently generating electricity becomes low load Power unit price comparing means for comparing the power purchase unit price of the above with the predicted power generation unit price of the generator, and the result of the comparison,
When the unit price of electric power purchase is cheaper, it is provided with a control means for controlling the number of electric power sources by increasing the amount of electric power purchase and keeping the number of generators small or reducing the number of generators. .

【0033】また、請求項5の発明では、複数の発電機
を有する自家用発電システムの運転制御装置において、
予め入力された電力日負荷に基づいて電力負荷を予測す
る予測手段と、予測の結果、該電力負荷の低下が予測さ
れた場合に、該予測された電力負荷の低下以前に買電す
る量を増加させると共に前記発電機の運転台数を減少さ
せる台数制御を行う制御手段とを備えている。
According to the invention of claim 5, in the operation control device of the private power generation system having a plurality of generators,
A predicting unit that predicts a power load based on a previously input power daily load, and, as a result of the prediction, when a decrease in the power load is predicted, an amount to be purchased before the predicted decrease in the power load is set. And a control means for controlling the number of the generators that increases and decreases the number of operating generators.

【0034】さらに、請求項6の発明では、複数の発電
機を有する自家用発電システムの運転制御装置におい
て、予め入力された電力日負荷に基づいて電力負荷を予
測する予測手段と、予測の結果、該電力負荷の急激な低
下が予測された場合に、該予測された電力負荷の急激な
低下以前に、該電力負荷の急激な低下によっても逆潮流
が起きないところまで買電する量を増加させると共に前
記発電機の運転台数を減少させる台数制御を行う制御手
段とを備えている。
Further, according to the invention of claim 6, in the operation control device of the private power generation system having a plurality of generators, a prediction means for predicting the power load based on the power daily load inputted in advance, and the prediction result, When the sudden decrease of the power load is predicted, before the predicted sudden decrease of the power load, the amount of power purchase is increased to the point where the reverse flow does not occur due to the sudden decrease of the power load. In addition, a control unit that controls the number of operating generators is provided.

【0035】[0035]

【発明の実施の形態】図1は以下に説明する各実施形態
で使用される自家用発電システム(コージェネレーショ
ンシステム)を含む電力系統図である。
1 is a power system diagram including a private power generation system (cogeneration system) used in each embodiment described below.

【0036】同図に示すように、このシステムでは、商
用系統50からの商用電力と自家発電システム(コージ
ェネレーションシステム)51からの発明電力とを最適
に組み合わせて電力コストの低減を図りつつ、複数の負
荷52、重要負荷53に電力を供給する。このシステム
は運転制御装置54により制御されている。
As shown in the figure, in this system, the commercial power from the commercial grid 50 and the inventive power from the private power generation system (cogeneration system) 51 are optimally combined to reduce the power cost, The electric power is supplied to the load 52 and the important load 53. This system is controlled by the operation controller 54.

【0037】この運転制御装置54は、前記制御ユニッ
ト14内に設けられており、その機能としては、電力負
荷および発電機の運転台数を監視する監視手段と、所定
の条件が成立した場合に、商用電力の買電単価と発電機
の予測発電単価とを比較する電力単価比較手段と、予め
入力された電力日負荷に基づいて電力負荷を予測する予
測手段と、電力単価の比較の結果、または電力負荷の予
測の結果に基づいて買電量の増加・低減、および発電機
の運転台数の制御を行う制御手段とを備えている。この
運転制御装置54における処理手順は、以下の第1の実
施形態乃至第3の実施形態で詳述する。
The operation control device 54 is provided in the control unit 14, and its functions are to monitor the power load and the number of generators in operation, and when a predetermined condition is satisfied, A power unit price comparison means for comparing the purchased power unit price of commercial power with the predicted power generation unit price of the generator, a prediction means for predicting the power load based on the previously input power daily load, the result of the power unit price comparison, or It is provided with control means for increasing / decreasing the amount of power purchased and controlling the number of operating generators based on the result of the prediction of the power load. The processing procedure in this operation control device 54 will be described in detail in the following first to third embodiments.

【0038】〈第1の実施形態〉図2は、図1に示した
運転制御装置で実行される第1の実施形態の処理手順を
示すフローチャートである。この実施形態は、電力負荷
が増加して行く場面で、買電量の増加、発電機台数の増
加をする場合の処理手順を示している。
<First Embodiment> FIG. 2 is a flowchart showing the processing procedure of the first embodiment executed by the operation control device shown in FIG. This embodiment shows a processing procedure in the case of increasing the power purchase amount and the number of generators in a situation where the power load increases.

【0039】この第1の実施形態の動作を説明すると、
電力負荷が増加して来て、発電機台数を増加させると仮
定したときに、その時点の電力負荷では発電機の増加で
各発電機が低負荷になってしまう場合に(ステップS
1)、先ず買電単価と予測発電単価と比較する(ステッ
プS2)。このとき、買電単価の方が高かった場合は
(ステップS2NO)、買電量を増やすと却ってコストが
高くなる。そこで、この場合、発電機が低負荷でもその
侭の状態を続ける(ステップS2NO→ステップS1)。
The operation of the first embodiment will be described below.
When it is assumed that the power load increases and the number of generators increases, when the power load at that time causes each generator to become a low load due to the increase in the number of generators (step S
1) First, the power purchase unit price is compared with the predicted power generation unit price (step S2). At this time, if the unit price of power purchase is higher (NO in step S2), increasing the amount of power purchase will rather increase the cost. Therefore, in this case, even if the generator has a low load, the state of the windshield is continued (step S2NO → step S1).

【0040】一方、買電単価の方が安かった場合(ステ
ップS2YES)、買電量を増やした方がコストは低くな
る。そこで、この場合、買電量を増やす(ステップS
3)。次いで、その買電量と余裕とを足した分が契約電
力を超えていないかを確認する(ステップS4)。超え
ていないときは(ステップS4NO)、その買電量が維持
できる。
On the other hand, when the unit price of power purchase is cheaper (YES in step S2), the cost is lower when the amount of power purchase is increased. Therefore, in this case, the power purchase amount is increased (step S
3). Next, it is confirmed whether or not the amount obtained by adding the power purchase amount and the margin exceeds the contract power (step S4). When it does not exceed (NO in step S4), the power purchase amount can be maintained.

【0041】そしてこの場合、電力負荷が増加していて
も発電機の運転台数は少ないままを維持する(ステップ
S6)。このように発電機の運転台数を少ないままに維
持すると、発電機は高出力運転が維持され、効率が高く
なって予測発電単価が下がる。この予測発電単価が下が
ること、また、前述したように単価の低い買電の方の割
合が増えることで、ここでの総合電力単価はミニマムと
なる。
In this case, the number of operating generators remains small even if the electric power load increases (step S6). In this way, if the number of generators to be operated is kept small, the generators maintain high output operation, the efficiency is increased, and the predicted unit price of power generation is decreased. The estimated unit price of power generation will decrease, and the percentage of power purchasers with lower unit prices will increase, as described above, so the total unit price of power generation here will be a minimum.

【0042】なお、運転台数を少ないままに維持するこ
とで、運転時間を減らすことができ、メンテナンス費等
を削減することができる。この点も予測発電単価に反映
される。
By keeping the number of operating units small, the operating time can be reduced and the maintenance cost can be reduced. This point is also reflected in the predicted unit price of power generation.

【0043】但し、買電量を増やした結果、その買電量
と余裕とを足した分が契約電力を超えるときは(ステッ
プS4YES)、それ以上買電量を増やすことは出来な
い。この場合、それ以上の電力負荷の増加に備え、発電
機台数を増加させる(ステップS5)。
However, as a result of increasing the power purchase amount, if the power purchase amount plus the margin exceeds the contracted power (step S4 YES), the power purchase amount cannot be further increased. In this case, the number of generators is increased in preparation for a further increase in power load (step S5).

【0044】図3に比較例を示す。この比較例は、1,
000kW発電機2台の自家用発電システムにおいて、
電力負荷が増加して行く場面で、従来の方法を適用した
場合(同図左側)と、この第1の実施形態の方法を適用
した場合(同図右側)の、発電状況の違いを示すもので
ある。
FIG. 3 shows a comparative example. This comparative example is 1,
In a private power generation system with two 000kW generators,
In the scene where the electric power load increases, it shows the difference in power generation status between when the conventional method is applied (left side in the figure) and when the method of the first embodiment is applied (right side in the figure). Is.

【0045】具体的には、同図に示すように最低受電電
力量が500kWの場合、従来では、電力負荷が増大し
1台より2台運転となる時は、発電量400kW2台分
を和した1300kWであるのに対し、この第1の実施
形態によるときは、電力負荷が1300kWの場合でも
1台運転となり、その後も買電量を増やして1台運転を
継続し(1600kWの例参照)、電力負荷が1900
kWになってはじめて2台運転とすることにより総合電
力単価を下げることができる。
Specifically, as shown in the figure, when the minimum received power amount is 500 kW, in the conventional case, when the power load increases and two units are operated from one unit, the power generation amount of two units of 400 kW is summed. In contrast to 1300 kW, in the case of the first embodiment, even when the power load is 1300 kW, one unit is in operation, and thereafter, the power purchase amount is increased and one unit is continuously operated (see an example of 1600 kW). Load is 1900
It is possible to reduce the total unit price of electric power by operating two units only after reaching kW.

【0046】なお、電力負荷が減少して行く場合も、同
じ処理が行われる。同じ図3の比較例を引用して説明す
れば、電力負荷が例えば1900kW未満になったら、
買電量が増やされ、それまで2台運転だったものが1台
運転にされ、例えば、1600kWの電力負荷の場合も
買電量の増加で対応がなされる。
The same processing is performed when the power load is decreasing. Explaining with reference to the same comparative example of FIG. 3, when the power load becomes less than 1900 kW,
The power purchase amount is increased, and the operation that used to operate two units until then is changed to one device operation. For example, even in the case of a power load of 1600 kW, the increase in the power purchase amount can be dealt with.

【0047】〈第2の実施形態〉次に第2の実施形態に
ついて説明する。なお、システム全体構成は図1と同様
であるため、図示は省略し、処理手順のみを説明する。
図4は、上述した運転制御装置で実行される第2の実施
形態の処理手順を示すフローチャートである。
<Second Embodiment> Next, a second embodiment will be described. Since the overall system configuration is the same as in FIG. 1, the illustration is omitted and only the processing procedure will be described.
FIG. 4 is a flowchart showing a processing procedure of the second embodiment executed by the operation control device described above.

【0048】この第2の実施形態では、日負荷を予め入
力しておき、これに基づいて将来予測を行う。このとき
電力負荷の低下が予測される場合は、買電を増やすこと
により予め運転台数を減らす。それによって低負荷運転
を避け、コストミニマムの運転状態とする。
In the second embodiment, the daily load is input in advance, and future prediction is performed based on the input daily load. At this time, if a decrease in the power load is predicted, the number of operating vehicles is reduced in advance by increasing the power purchase. By doing so, low-load operation is avoided, and the operating state is at a minimum cost.

【0049】この第2の実施形態の動作を説明すると、
予め入力されている電力日負荷に基づき先ず電力負荷の
将来予測を行う(ステップS11)。ここで、電力負荷
の減少が予測されない場合(ステップS12NO)、新た
に処理をする必要はない。ステップS11に戻る。一
方、電力負荷の減少が予測された場合(ステップS12
YES)には、買電単価が予想発電単価よりも低いことを
条件に、買電量を増やす(ステップS13YES→ステッ
プS14)。次いで、その買電量と余裕とを足した分が
契約電力を超えていないかを確認する(ステップS1
5)。超えていないときは(ステップS15NO)、その
買電量が維持できる。そしてこの場合、発電機の運転台
数を削減する(ステップS17)。
The operation of the second embodiment will be described below.
First, the future of the electric power load is predicted based on the electric power daily load input in advance (step S11). Here, when the decrease of the power load is not predicted (NO in step S12), it is not necessary to perform new processing. It returns to step S11. On the other hand, when a decrease in power load is predicted (step S12)
YES), the power purchase amount is increased on condition that the power purchase unit price is lower than the expected power generation unit price (YES in step S13 → step S14). Next, it is confirmed whether or not the amount obtained by adding the power purchase amount and the surplus does not exceed the contracted power (step S1).
5). When it does not exceed (NO in step S15), the power purchase amount can be maintained. In this case, the number of operating generators is reduced (step S17).

【0050】このように予め発電機の運転台数を少なく
しておくと、そのあと電力負荷が低下した場合も、発電
機は高出力運転が維持されて効率が高くなり予測発電単
価が下がる。なお、運転台数を少なくすることで、運転
時間を減らすことができ、メンテナンス費等を削減する
ことができる。この点も予測発電単価に反映される。
By thus reducing the number of generators in operation in advance, even if the electric power load subsequently decreases, the generators maintain high output operation, the efficiency increases, and the predicted power generation unit price decreases. By reducing the number of operating units, the operating time can be reduced and the maintenance cost can be reduced. This point is also reflected in the predicted unit price of power generation.

【0051】但し、買電量を増やした結果、その買電量
と余裕とを足した分が契約電力を超えるときは(ステッ
プS15YES)、それ以上買電量を増やすことが出来な
い。この場合は発電機台数を維持する(ステップS1
6)。
However, as a result of increasing the power purchase amount, if the amount obtained by adding the power purchase amount and the surplus exceeds the contracted power (step S15 YES), the power purchase amount cannot be further increased. In this case, the number of generators is maintained (step S1
6).

【0052】図5に比較例を示す。この比較例は、1,
000kW発電機2台の自家用発電システムにおいて電
力負荷の減少が予測される場面で、従来の方法を適用し
た場合(同図左側)と、この第2の実施形態の方法を適
用した場合(同図右側)の、発電状況の違いを示すもの
である。具体的には、同図に示すように、例えば190
0kWの電力負荷の状態で、電力負荷の低下が予測され
た場合に、予め買電量を増やすと共に発電機の運転台数
を削減しておく。こうすると、例えば1600kWに電
力負荷が減少した場合も、従来であれば、受電一定電力
500kWに発電量が各550kWとなったのに対し、
本実施形態によれば、買電が600kW、発電が100
0kWと、高効率で発電単価が低い状態が維持される。
FIG. 5 shows a comparative example. This comparative example is 1,
When a conventional method is applied (on the left side of the figure) and a method of the second embodiment is applied (a figure on the same figure) in a scene where a decrease in power load is predicted in a private power generation system with two 000 kW generators. The right side) shows the difference in power generation status. Specifically, as shown in FIG.
When a decrease in the electric power load is predicted in the state of the electric power load of 0 kW, the amount of power purchased is increased and the number of operating generators is reduced in advance. By doing this, for example, even when the power load is reduced to 1600 kW, in the conventional case, the amount of power generation is 550 kW for the constant received power of 500 kW, whereas
According to this embodiment, power purchase is 600 kW and power generation is 100
A high efficiency of 0 kW and a low unit price of power generation are maintained.

【0053】〈第3の実施形態〉次に第3の実施形態に
ついて説明する。なお、システム全体構成は図1と同様
であるため、図示は省略し、処理手順のみを説明する。
図6は、上述した運転制御装置で実行される第3の実施
形態の処理手順を示すフローチャートである。この実施
形態は、日負荷を予め入力しておいて、これを基に将来
予測を行い、電力負荷が急激に下がることが予測される
場合は予め受電量を増やし、逆潮流を避けるとともに、
通常は最低受電量を下げておくことで低負荷運転を避
け、コストミニマムの運転状態とする。
<Third Embodiment> Next, a third embodiment will be described. Since the overall system configuration is the same as in FIG. 1, the illustration is omitted and only the processing procedure will be described.
FIG. 6 is a flowchart showing a processing procedure of the third embodiment executed by the operation control device described above. In this embodiment, the daily load is input in advance, and future prediction is performed based on this input. If it is predicted that the power load will suddenly decrease, the amount of power received is increased in advance to avoid reverse power flow,
Normally, the minimum amount of power received should be lowered to avoid low load operation, and the operating state should be at the cost minimum.

【0054】この第3の実施形態の動作を説明すると、
予め入力されている電力日負荷に基づき先ず電力負荷の
将来予測を行う(ステップS21)。ここで、電力負荷
の減少が予測されない場合(ステップS22NO)、新た
に処理をする必要はない。ステップS21に戻る。一
方、電力負荷の急激な減少が予測された場合(ステップ
S22YES)、そこで買電量を増やす(ステップS2
3)。次いで、その買電量と余裕とを足した分が契約電
力を超えていないかを確認する(ステップS24)。超
えていないときは(ステップS24NO)、その買電量が
維持できる。そしてこの場合、発電機の運転台数を削減
する(ステップS26)。
The operation of the third embodiment will be described below.
First, the future of the power load is predicted based on the power daily load that has been input in advance (step S21). Here, when the decrease in the power load is not predicted (NO in step S22), it is not necessary to perform new processing. It returns to step S21. On the other hand, when a sharp decrease in the power load is predicted (step S22 YES), the power purchase amount is increased (step S2).
3). Next, it is confirmed whether or not the sum of the power purchase amount and the surplus exceeds the contract power (step S24). When it does not exceed (NO in step S24), the power purchase amount can be maintained. In this case, the number of operating generators is reduced (step S26).

【0055】このように予め発電機の運転台数を少なく
しておくと、そのあと電力負荷が急激に低下した場合
も、逆潮流が生ずることはなく、しかも発電機は高出力
運転が維持されて効率が高くなり予測発電単価が下が
る。なお、運転台数を少なくすることで、運転時間を減
らすことができ、メンテナンス費等を削減することがで
きる。この点も予測発電単価に反映される。
By thus reducing the number of generators in operation in advance, even if the power load sharply decreases thereafter, reverse power flow does not occur, and the generators maintain high output operation. The efficiency will be higher and the forecasted power generation cost will be lower. By reducing the number of operating units, the operating time can be reduced and the maintenance cost can be reduced. This point is also reflected in the predicted unit price of power generation.

【0056】但し、買電量を増やした結果、その買電量
と余裕とを足した分が契約電力を超えるときは(ステッ
プS24YES)、それ以上買電量を増やすことが出来な
い。この場合は発電機台数を維持する(ステップS2
5)。
However, as a result of increasing the power purchase amount, if the power purchase amount plus the margin exceeds the contracted power (step S24 YES), the power purchase amount cannot be increased any more. In this case, the number of generators is maintained (step S2
5).

【0057】図7に比較例を示す。この比較例は、1,
000kW発電機2台の自家用発電システムにおいて、
電力負荷の急激な減少が予測される場面で、従来の方法
を適用した場合(同図左側)と、この第3の実施形態の
方法を適用した場合(同図右側)の、発電状況の違いを
示すものである。
FIG. 7 shows a comparative example. This comparative example is 1,
In a private power generation system with two 000kW generators,
Differences in power generation status between when the conventional method is applied (on the left side of the figure) and when the method of the third embodiment is applied (on the right side of the figure) in a scene where a rapid decrease in the power load is predicted. Is shown.

【0058】具体的には、従来の場合、例えば受電一定
電力値500kW、発電量各700kWで電力負荷19
00kWの状態より、昼休みに入る等で一斉に設備が停
止され電力負荷が激減した場合、発電をタイムリーに減
少させることができず、逆潮流になるか(同図符号2
0)、保護継電器により自家用発電システムが停止に至
る。
Specifically, in the conventional case, for example, a constant power reception value of 500 kW, a power generation amount of 700 kW, and a power load 19
If the equipment is shut down all at once such as during lunch break from the state of 00 kW and the power load is drastically reduced, it will not be possible to reduce the power generation in a timely manner and it will be a reverse power flow (symbol 2 in the same figure).
0), the protective relay causes the private power generation system to stop.

【0059】一方、本実施形態の場合、日負荷が予め入
力されているため、同じ昼休みで電力負荷の激減が予測
される場合には、昼前に予め受電量を増やし(符号2
1)、昼休みに入って電力激減後も逆潮流しないように
できる(符号22。なお図では昼休みを昼と表示。)。
また、このとき以外の、午前中及び午後は、受電一定電
力を少なくすることで(符号23、24)、発電台数の
削滅、高効率での運転ができ、これによって総合電力単
価を下げることが出来る。
On the other hand, in the case of the present embodiment, since the daily load is input in advance, if a drastic decrease in the power load is predicted in the same lunch break, the power reception amount is increased in advance before lunch (reference numeral 2).
1) It is possible to prevent reverse power flow even after entering the lunch break and after the power is sharply reduced (reference numeral 22. Note that the lunch break is indicated as daytime in the figure).
In the mornings and afternoons other than this time, by reducing the constant power received (reference numerals 23 and 24), it is possible to reduce the number of power generators and operate with high efficiency, thereby lowering the total power unit price. Can be done.

【0060】なお、各実施形態の発電機台数は2台であ
ったが、本発明は発電機台数3台以上についても同様に
実施出来る。
Although the number of generators in each embodiment was two, the present invention can be similarly applied to the case where the number of generators is three or more.

【0061】[0061]

【発明の効果】以上説明したように、請求項1、4の発
明によれば、電力負荷が増加或いは減少する場合に、そ
のときの買電単価と予測発電単価の違いを反映した上で
の買電量の増加、及び運転台数の現状維持或いは減少処
理が行われる。これにより総合電力単価ミニマムの運転
状態を実現することができる。
As described above, according to the first and fourth aspects of the invention, when the power load increases or decreases, the difference between the power purchase unit price and the predicted power generation unit price at that time is reflected. The amount of power purchased is increased and the number of operating vehicles is maintained or reduced. As a result, it is possible to realize the minimum operating condition of the total power unit price.

【0062】また、請求項2、5の発明によれば、将来
予測で電力負荷が下がることが判明した場合に、予め買
電量を増やす一方で運転台数が減らされる。これにより
低負荷運転を避けることができ、総合電力単価ミニマム
の運転状態を実現することが出来る。
According to the second and fifth aspects of the present invention, when it is found in the future that the power load will decrease, the power purchase amount is increased in advance while the operating number is decreased. As a result, low load operation can be avoided, and the operation state of the minimum unit price of total power can be realized.

【0063】さらに、請求項3、6の発明によれば、将
来予測を行い電力負荷が急激に下がることが予測された
場合に、受電量を増やして逆潮流を避け、また、通常は
最低受電量が下げた状態におかれる。これにより総合電
力単価ミニマムの運転状態を実現することが出来る。
Further, according to the inventions of claims 3 and 6, when a future prediction is made and it is predicted that the power load sharply decreases, the amount of received power is increased to avoid reverse power flow, and normally the minimum received power is received. The quantity is lowered. As a result, it is possible to realize the operation state of the minimum total power unit price.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施形態の構成を示す説明図である。FIG. 1 is an explanatory diagram showing a configuration of an embodiment of the present invention.

【図2】本発明の第1の実施形態の処理手順を示すフロ
ーチャートである。
FIG. 2 is a flowchart showing a processing procedure of the first embodiment of the present invention.

【図3】1,000kW発電機2台の自家用発電システ
ムに対し、本発明の第1の実施形態の運転制御方法を適
用した場合(右側)と従来の運転制御方法を適用した場
合(左側)の各発電状況を対比して示す説明図である。
FIG. 3 is a case where the operation control method of the first embodiment of the present invention is applied to a private power generation system with two 1,000 kW generators (right side) and a case where a conventional operation control method is applied (left side). FIG. 3 is an explanatory diagram showing the respective power generation states of FIG.

【図4】本発明の第2の実施形態の処理手順を示すフロ
ー図である。
FIG. 4 is a flowchart showing a processing procedure according to a second embodiment of the present invention.

【図5】1,000kW発電機2台の自家用発電システ
ムに対し、本発明の第2の実施形態の運転制御方法を適
用した場合(右側)と従来の運転制御方法を適用した場
合(左側)の各発電状況を対比して示す説明図である。
FIG. 5 shows a case where the operation control method according to the second embodiment of the present invention is applied to a private power generation system with two 1,000 kW generators (right side) and a case where a conventional operation control method is applied (left side). FIG. 3 is an explanatory diagram showing the respective power generation states of FIG.

【図6】本発明の第3の実施形態の処理手順を示すフロ
ーチャートである。
FIG. 6 is a flowchart showing a processing procedure of a third embodiment of the present invention.

【図7】1,000kW発電機2台の自家用発電システ
ムに対し、本発明の第3の実施形態の運転制御方法を適
用した場合(右側)と従来の運転制御方法を適用した場
合(左側)の各発電状況を対比して示す説明図である。
FIG. 7 shows a case where the operation control method of the third embodiment of the present invention is applied (right side) and a case where a conventional operation control method is applied (left side) to a private power generation system with two 1,000 kW generators. FIG. 3 is an explanatory diagram showing the respective power generation states of FIG.

【図8】ディーゼルコージェネレーションシステムの基
本的な構成例を示す建屋正面縦断面図である。
FIG. 8 is a building front vertical cross-sectional view showing a basic configuration example of a diesel cogeneration system.

【図9】ディーゼルコージェネレーションシステムの基
本的な構成例を示す建屋側面縦断面図である。
FIG. 9 is a side elevational sectional view of a building showing a basic configuration example of a diesel cogeneration system.

【図10】ディーゼルコージエネレーションシステムの
排熱、電力等の基本的な流れを示すフローチャートであ
る。
FIG. 10 is a flowchart showing a basic flow of exhaust heat, electric power, etc. of the diesel cogeneration system.

【図11】従来の自家用発電システムの基本的な発電・
買電状況の例を示し、(A)は電力負荷が一定の場合、
(B)は山形の電力負荷の場合、(C)は季時別契約を
実施した場合の発電・買電状況の例を示す説明図であ
る。
[Fig. 11] Basic power generation of a conventional private power generation system
An example of the power purchase situation is shown, (A) shows the case where the power load is constant,
FIG. 7B is an explanatory diagram showing an example of the power generation / power purchase status in the case of a Yamagata power load, and FIG.

【図12】従来の自家用発電システムの運転制御方法に
おける各発電機の発電状況の例を示す説明図である。
FIG. 12 is an explanatory diagram showing an example of a power generation state of each generator in a conventional operation control method for a private power generation system.

【図13】従来の自家用発電システムの買電上昇時の処
理手順を示すフローチャートである。
FIG. 13 is a flowchart showing a processing procedure when the conventional power generation system for electric power generation rises.

【図14】従来の自家用発電システムの買電減少時の処
理手順を示すフローチャートである。
FIG. 14 is a flowchart showing a processing procedure when the power purchase for the conventional private power generation system is reduced.

【符号の説明】[Explanation of symbols]

1 主燃料タンク 2 燃料小出槽 3 エンジン 4 発電機 5 一次冷却水 6 熱交換器 7 温水 8 蒸気排ガスボイラー 9 蒸気 10 消音器 11 煙突 12 他の熱交換器 13 冷却塔 14 運転制御ユニット 15 発電状況 16 買電状況 17 電力負荷 18 1台目運転状況 19 2台目運転状況 20 従来の昼休みの発電状況の例 21 第3の実施形態での昼前の発電状況の例 22 第3の実施形態での昼休みの発電状況の例 23 第3の実施形態での午前の発電状況の例 24 第3の実施形態での午後の発電状況の例 54 運転制御装置 1 Main fuel tank 2 small fuel tank 3 engine 4 generator 5 Primary cooling water 6 heat exchanger 7 hot water 8 Steam exhaust gas boiler 9 steam 10 silencer 11 chimney 12 Other heat exchangers 13 Cooling tower 14 Operation control unit 15 Power generation status 16 Power Purchase Status 17 Power load 18 1st unit operation status 19 Operation status of the second unit 20 Example of conventional power generation during lunch break 21 Example of power generation status before noon in the third embodiment 22 Example of power generation status during lunch break in the third embodiment 23 Example of power generation status in the morning in the third embodiment 24 Example of afternoon power generation status in the third embodiment 54 Operation control device

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 複数の発電機を有する自家用発電システ
ムの運転制御方法において、 発電機台数を増加させると低負荷になる場合又は現在発
電している各発電機が低負荷になった場合に、そのとき
の買電単価を予測発電単価と比較し、 買電単価の方が安価であるときは、買電する量を増加さ
せると共に発電機台数を少ないまま維持するか又は発電
機台数を削減する、 ことを特徴とする自家用発電システムの運転制御方法。
1. An operation control method for an in-house power generation system having a plurality of generators, wherein increasing the number of generators results in a low load, or when each generator currently generating electricity becomes a low load. Compare the unit electricity purchase price at that time with the estimated electricity generation unit price, and if the electricity purchase unit price is cheaper, increase the amount of electricity purchased and either keep the number of generators small or reduce the number of generators. An operation control method for a private power generation system, which is characterized by:
【請求項2】 複数の発電機を有する自家用発電システ
ムの運転制御方法において、 電力日負荷を予め入力しておき、 該電力日負荷に基づく電力負荷予測で該電力負荷の低下
が予測された場合に、該予測された電力負荷の低下以前
に買電する量を増加させると共に前記発電機の運転台数
を減少させる、ことを特徴とする自家用発電システムの
運転制御方法。
2. An operation control method for a private power generation system having a plurality of generators, wherein a daily power load is input in advance, and a decrease in the power load is predicted by a power load prediction based on the daily power load. In addition, the operation control method of the private power generation system, comprising increasing the amount of power purchased before the predicted reduction of the electric power load and decreasing the number of operating generators.
【請求項3】 複数の発電機を有する自家用発電システ
ムの運転制御方法において、 電力日負荷を予め入力しておき、 該電力日負荷に基づく電力負荷予測で該電力負荷の急激
な低下が予測された場合に、該予測された電力負荷の急
激な低下以前に、該電力負荷の急激な低下によっても逆
潮流が起きないところまで買電する量を増加させると共
に前記発電機の運転台数を減少させ、 且つ通常は最低受電量を低下させておく、 ことを特徴とする自家用発電システムの運転制御方法。
3. An operation control method for a private power generation system having a plurality of generators, wherein an electric power daily load is input in advance, and a sudden decrease of the electric power load is predicted by an electric power load prediction based on the electric power daily load. In the case of the above, the amount of electric power to be purchased is increased and the number of operating generators is decreased before the predicted abrupt decrease of the electric power load even if the reverse power flow does not occur due to the abrupt decrease of the electric power load. And, usually, the minimum amount of power received is lowered, and the operation control method of the private power generation system is characterized.
【請求項4】 複数の発電機を有する自家用発電システ
ムの運転制御装置において、 電力負荷および発電機の運転台数を監視する監視手段
と、 発電機台数を増加させると低負荷になる場合又は現在発
電している各発電機が低負荷になった場合に、そのとき
における商用電力の買電単価と前記発電機の予測発電単
価とを比較する電力単価比較手段と、 比較の結果、買電単価の方が安価である場合には、買電
量を増加させると共に発電機台数を少ないまま維持する
か又は発電機台数を削減するかいずれかの台数制御を行
う制御手段と、 を備えたことを特徴とする自家用発電システムの運転制
御装置。
4. An operation control device for a private power generation system having a plurality of generators, a monitoring means for monitoring an electric power load and the number of generators operating, and a case where the number of generators is reduced to a low load or present power generation. When the load on each generator is low, the unit price comparison means for comparing the unit purchase price of commercial power and the predicted unit price of the generator at that time, and the comparison result shows that If it is cheaper, it is equipped with a control means for controlling the number of generators, either by increasing the power purchase amount and keeping the number of generators small or reducing the number of generators. Operation control device for private power generation system.
【請求項5】 複数の発電機を有する自家用発電システ
ムの運転制御装置において、 予め入力された電力日負荷に基づいて電力負荷を予測す
る予測手段と、 予測の結果、該電力負荷の低下が予測された場合に、該
予測された電力負荷の低下以前に買電する量を増加させ
ると共に前記発電機の運転台数を減少させる台数制御を
行う制御手段と、 を備えたことを特徴とする自家用発電システムの運転制
御装置。
5. In an operation control device of a private power generation system having a plurality of generators, a prediction means for predicting an electric power load based on a previously input daily electric power load, and a result of the prediction that a decrease in the electric power load is predicted. Control unit that controls the number of electric generators that increase the amount of power purchased before the predicted decrease in the electric power load and decreases the number of operating generators when the electric power generation is predicted. System operation control device.
【請求項6】 複数の発電機を有する自家用発電システ
ムの運転制御装置において、 予め入力された電力日負荷に基づいて電力負荷を予測す
る予測手段と、 予測の結果、該電力負荷の急激な低下が予測された場合
に、該予測された電力負荷の急激な低下以前に、該電力
負荷の急激な低下によっても逆潮流が起きないところま
で買電する量を増加させると共に前記発電機の運転台数
を減少させる台数制御を行う制御手段と、 を備えたことを特徴とする自家発電システムの運転制御
装置。
6. An operation control device for a private power generation system having a plurality of generators, a predicting means for predicting an electric power load based on a pre-input daily electric power load, and a result of the prediction, a rapid decrease in the electric power load. When the predicted power load is decreased, the amount of power purchased is increased to the point where a reverse power flow does not occur due to the sudden decrease in the power load, and the number of operating generators is increased. An operation control device for an in-house power generation system, comprising:
JP2002072631A 2002-03-15 2002-03-15 Method and device for controlling operation of private power generation system Pending JP2003274564A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002072631A JP2003274564A (en) 2002-03-15 2002-03-15 Method and device for controlling operation of private power generation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002072631A JP2003274564A (en) 2002-03-15 2002-03-15 Method and device for controlling operation of private power generation system

Publications (1)

Publication Number Publication Date
JP2003274564A true JP2003274564A (en) 2003-09-26

Family

ID=29202576

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002072631A Pending JP2003274564A (en) 2002-03-15 2002-03-15 Method and device for controlling operation of private power generation system

Country Status (1)

Country Link
JP (1) JP2003274564A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163624A (en) * 2003-12-02 2005-06-23 Hitachi Ltd Engine cogeneration system
CN104701890A (en) * 2015-03-21 2015-06-10 南京理工大学 Wind power integrated power system spinning reserve optimizing method taking wind power overflow into consideration

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005163624A (en) * 2003-12-02 2005-06-23 Hitachi Ltd Engine cogeneration system
CN104701890A (en) * 2015-03-21 2015-06-10 南京理工大学 Wind power integrated power system spinning reserve optimizing method taking wind power overflow into consideration

Similar Documents

Publication Publication Date Title
JP4864809B2 (en) Device control apparatus, device control system, and device control method
JP6420912B2 (en) Management server, management method and management system
JP6145670B2 (en) Power flow control system, management device, program
JP2007129873A (en) Device and method for managing energy demand
JP2010098793A (en) Power demand and supply system
JP2008141926A (en) Home power storage device, on-vehicle power storage device, power supply/storage system and power storage control method
JPH0686463A (en) Energy supply system
JP2007006595A (en) Operation method of private power generator set with power storage means
JP6034211B2 (en) Operation control device, operation control method, and operation control program
JP2007104775A (en) Energy demanding/supplying method in combined power supply, and energy demanding/supplying apparatus
JP2014155286A (en) Facility operation scheduling method
JP2005026010A (en) Fuel cell power generating equipment
JP6754880B2 (en) Power supply system
JP6903531B2 (en) Distributed power control device, distributed power control system and distributed power control method
JP7386028B2 (en) power supply system
CN109687504B (en) Micro-grid energy optimization distribution method based on source-load balance
JP2003274564A (en) Method and device for controlling operation of private power generation system
JP2002298887A (en) Power management device
JP2017127148A (en) Generator control system and generator control method
JP2017050903A (en) Energy management system, energy management apparatus, and energy management method
JP7386029B2 (en) power supply system
AU2021206016B2 (en) Method and system for controlling an electrical installation
JP2003173808A (en) System coordination system of distributed power generating facility
KR20220156061A (en) Method and related device for control of energy system
JP2004349082A (en) Cogeneration system