JP2003239680A - Method for connecting shield new pipe to existing pipe under ground - Google Patents
Method for connecting shield new pipe to existing pipe under groundInfo
- Publication number
- JP2003239680A JP2003239680A JP2002075165A JP2002075165A JP2003239680A JP 2003239680 A JP2003239680 A JP 2003239680A JP 2002075165 A JP2002075165 A JP 2002075165A JP 2002075165 A JP2002075165 A JP 2002075165A JP 2003239680 A JP2003239680 A JP 2003239680A
- Authority
- JP
- Japan
- Prior art keywords
- existing pipe
- pipe
- shield
- new pipe
- joining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明が属する技術分野】本発明は、シールド施工の新
設管を既設管に地中接合する方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of underground joining a new pipe for shield construction to an existing pipe.
【0002】[0002]
【従来の技術】従来、シールド施工の新設管を既設管に
地中接合する技術として、シールドの先端が既設管との
接合位置に到達した段階で、シールド機の先端部外側に
予め装備したスライドフードをジヤッキで押し出して既
設管に接合する、いわゆるスライドフード工法が知られ
ているが、この従来工法は、接合作業中に切羽が開放さ
れない利点がある反面、使用するシールド機が特製品で
あるため、その製造コストが割高であり、また、スライ
ドフードの装備でシールド機が長くなるため、新設管が
曲率半径の小さい曲線部を含む場合に適用できないとい
う不利点がある。2. Description of the Related Art Conventionally, as a technique for underground joining a new pipe for shield construction to an existing pipe, when the tip of the shield reaches the joining position with the existing pipe, a slide that is pre-installed on the outside of the tip of the shield machine A so-called slide hood construction method is known in which the hood is pushed out with a jack and joined to the existing pipe, but this conventional construction method has the advantage that the face is not opened during the joining work, but the shield machine used is a special product. Therefore, the manufacturing cost thereof is high, and the shield machine is long due to the equipment of the slide hood. Therefore, there is a disadvantage that it cannot be applied when the new pipe includes a curved portion having a small radius of curvature.
【0003】[0003]
【発明が解決しようとする課題】本発明が解決しようと
する課題(本発明の目的)は、前述のスライドフード工
法が適用できない、新設管が曲率半径の小さい曲線部を
含む場合にも適用できるシールド施工の新設管と既設管
の地中接合方法を提供することにある。The problem to be solved by the present invention (object of the present invention) can be applied to a case where the above-mentioned slide hood construction method cannot be applied and the new pipe includes a curved portion having a small radius of curvature. It is to provide a method of connecting a new pipe for shield construction and an existing pipe underground.
【0004】[0004]
【課題を解決するための手段】前記課題を解決するため
に、本発明のシールド施工の新設管と既設管の地中接合
方法(以下、本発明の方法という)では、シールド施工
の新設管を既設管に地中接合するに当たり、予め、接合
部周辺の地盤を適宜工法で地盤改良し、シールド機の先
端が接合地点に到達した段階で、シールド機内の諸設備
類を全て撤去した後、残されたシールド外殻の先端部内
でシールド外殻と既設管とを結ぶ刃口構造の覆工体をセ
グメント仕様で形成し、この覆工体をその後方に設置し
た推進ジヤッキで推進して、その先端を既設管に当接
し、接合するようにしている。In order to solve the above-mentioned problems, in the underground joining method for a shielded new pipe and an existing pipe of the present invention (hereinafter referred to as the method of the present invention), a new shielded pipe is used. Before joining the underground pipe to the existing pipe, the ground around the joint should be improved in advance by an appropriate construction method, and at the stage where the tip of the shield machine reached the joint point, all the equipment inside the shield machine was removed and left. A lining body with a blade structure that connects the shield outer shell and the existing pipe is formed in the tip portion of the shield outer shell with segment specifications, and this lining body is propelled by a propulsion jack installed behind it, and The tip is brought into contact with the existing pipe and joined.
【0005】なお、本発明の方法では、接合作業の開始
前に、接合作業中に必要に応じて適用することができる
ように圧気工法の準備をするのが好ましい。In the method of the present invention, it is preferable to prepare the pneumatic construction method before the start of the joining work so that it can be applied as needed during the joining work.
【0006】[0006]
【発明の実施の形態】本発明の工法の一実施態様の説明
図である図1において、1はシールド外殻、2はシール
ド外殻1の後方に連なる新設管、3は新設管2が接合さ
れる既設管、4は接合部周辺の地盤改良部であり、地盤
改良部4の施工は接合作業の開始前に行うが、これをど
のようにして行うかは任意であり、例えば、既設管3か
ら薬液注入工法を施すという態様で行ってもよい。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS In FIG. 1, which is an explanatory view of an embodiment of a construction method of the present invention, 1 is a shield outer shell, 2 is a new pipe connected to the rear of the shield outer shell 1, and 3 is a new pipe 2 joined. The existing pipes 4 to be provided are ground improvement portions around the joints, and the ground improvement portions 4 are constructed before the start of the joint work, but how to perform this is arbitrary. Alternatively, the chemical solution injection method may be performed from step 3.
【0007】新設管2と既設管3を接合する作業は、新
設管2を施工するシールド機の先端(シールド外殻1の
先端)が既設管3に当接する位置に達した段階で開始
し、先ず、シールド機内の諸設備類の全て、すなわち、
面板等の山留め設備、ずり出し装置、シールド推進用ジ
ヤッキ、エレクタ等の全てを撤去する。The operation of joining the new pipe 2 and the existing pipe 3 is started when the tip of the shield machine for constructing the new pipe 2 (the tip of the shield outer shell 1) reaches the position where it abuts on the existing pipe 3, First, all of the various equipment inside the shield machine, that is,
We will remove all of the clasping equipment such as face plates, slipping device, jack for shield propulsion, and erector.
【0008】次いで、残されたシールド外殻1の先端部
内で、シールド外殻1と既設管3とを結ぶ刃口構造の覆
工体5をセグメント仕様で形成し、この覆工体5をその
後方に設置した推進ジヤッキ6で矢印方向に推進して、
その先端を既設管3のセグメントに溶接して固定する
(図1には推進前と推進後の覆工体5をそれぞれ点線と
実線で示している)。Then, a lining body 5 having a blade edge structure for connecting the shield outer shell 1 and the existing pipe 3 is formed in a segment specification in the tip portion of the remaining shield outer shell 1, and this lining body 5 is thereafter formed. Propel in the direction of the arrow with the propulsion jack 6 installed on one side,
The tip is welded and fixed to the segment of the existing pipe 3 (in FIG. 1, the lining body 5 before and after propulsion is shown by a dotted line and a solid line, respectively).
【0009】なお、前述の覆工体5は、工場で、新設管
2のセグメント覆工と同様の仕様で所定の形状と大きさ
に形成した後、これを人力で取り扱える程度の複数個の
ブロックに分割してシールド外殻1内の所定位置に搬入
し、ここで元どおりに組み立てればよい。The above-mentioned lining body 5 is formed into a predetermined shape and size in the factory with the same specifications as the segment lining of the new pipe 2, and then a plurality of blocks which can be handled manually. It may be divided into two parts, carried in to a predetermined position in the shield outer shell 1, and assembled there as before.
【0010】本発明の方法では、接合作業中、切羽が開
放されているため、その間に切羽からの地下水の湧出や
土砂の流出が発生して接合作業に支障が生じることがな
いように、地盤改良部4の施工を入念に行うことが肝要
であるが、地盤改良だけでは作業の安全性が確保できな
いと思われる場合には、接合作業中に必要に応じて圧気
工法を適用することができるように、接合作業の開始前
に例えば、図示のように新設管2内に隔壁7,7を設置
する等して圧気工法のための準備をしておくのが好まし
い。According to the method of the present invention, since the cutting face is opened during the joining work, the ground work is prevented so that the spouting of groundwater and the outflow of earth and sand from the cutting face do not hinder the joining work. It is important to carefully perform the construction of the improvement part 4, but if it is considered that the work safety cannot be ensured only by ground improvement, the pneumatic method can be applied as necessary during the joining work. As described above, it is preferable to prepare for the pneumatic construction method, for example, by installing the partition walls 7, 7 in the new pipe 2 as shown in the figure before starting the joining work.
【0011】なお、前述のようにして覆工体5の先端を
既設管3に接合した後、推進ジヤッキ6や隔壁7を撤去
するとともに、シールド躯体1の内側に配筋の上、コン
クリートを打設して、鉄筋コンクリート層を形成し、こ
の鉄筋コンクリート層を介して新設管2と覆工体5を接
続する。After the tip of the lining body 5 is joined to the existing pipe 3 as described above, the propulsion jack 6 and the partition wall 7 are removed, and the inside of the shield skeleton 1 is reinforced and concrete is struck. Then, the reinforced concrete layer is formed, and the new pipe 2 and the lining body 5 are connected via this reinforced concrete layer.
【0012】[0012]
【発明の効果】本発明の方法は以上のようなものである
から、前記目的の達成という効果以外に、スライドフー
ド工法の場合と比較して使用するシールド機が特製品で
ないのでその製造コストが低く、また、予め、シールド
外殻内で形成した覆工体を推進して既設管に接合するの
で施工能率がよい、等の効果が期待できる。Since the method of the present invention is as described above, in addition to the effect of achieving the above-mentioned object, the shield machine used is not a special product as compared with the slide hood construction method, so that the manufacturing cost thereof is low. It is low, and since the lining body formed in advance in the shield outer shell is propelled and joined to the existing pipe, effects such as good construction efficiency can be expected.
【図1】本発明の方法の一実施態様説明用の断面図てあ
る。FIG. 1 is a sectional view for explaining an embodiment of a method of the present invention.
1:シールド外殻、2:新設管、3:既設管、4:地盤
改良部、5:覆工体、6:推進ジヤッキ、7:隔壁。1: shield outer shell, 2: new pipe, 3: existing pipe, 4: ground improvement part, 5: lining body, 6: propulsion jack, 7: bulkhead.
Claims (2)
合するに当たり、予め、接合部周辺の地盤を適宜工法で
地盤改良し、シールド機の先端が接合地点に到達した段
階で、シールド機内の諸設備類を全て撤去した後、残さ
れたシールド外殻の先端部内でシールド外殻と既設管と
を結ぶ刃口構造の覆工体をセグメント仕様で形成し、こ
の覆工体をその後方に設置した推進ジヤッキで推進し
て、その先端を既設管に当接し、接合することを特徴と
するシールド施工の新設管と既設管の地中接合方法。1. When a new pipe for shield construction is underground-joined to an existing pipe, the ground around the joint is improved in advance by an appropriate construction method before the tip of the shield machine reaches the joint point. After removing all of the various equipments, the lining body with a blade structure that connects the shield outer shell and the existing pipe is formed with segment specifications in the tip of the remaining shield outer shell, and this lining body is placed behind it. A method of underground joining of a new pipe and an existing pipe for shield construction, characterized by propelling with a propulsion jack installed in the above, abutting the tip of the jack to the existing pipe, and joining.
に応じて適用することができるように圧気工法の準備を
する請求項1記載のシールド施工の新設管と既設管の地
中接合方法。2. The underground joining of a shielded new pipe and an existing pipe according to claim 1, wherein the pneumatic construction method is prepared before the joining work is started so that it can be applied as needed during the joining work. Method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002075165A JP2003239680A (en) | 2002-02-13 | 2002-02-13 | Method for connecting shield new pipe to existing pipe under ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002075165A JP2003239680A (en) | 2002-02-13 | 2002-02-13 | Method for connecting shield new pipe to existing pipe under ground |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2003239680A true JP2003239680A (en) | 2003-08-27 |
Family
ID=27785183
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002075165A Pending JP2003239680A (en) | 2002-02-13 | 2002-02-13 | Method for connecting shield new pipe to existing pipe under ground |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2003239680A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013072201A (en) * | 2011-09-27 | 2013-04-22 | Taisei Corp | Adit and adit construction method |
JP2014122512A (en) * | 2012-12-21 | 2014-07-03 | Kumagai Gumi Co Ltd | Pipe installation method |
-
2002
- 2002-02-13 JP JP2002075165A patent/JP2003239680A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013072201A (en) * | 2011-09-27 | 2013-04-22 | Taisei Corp | Adit and adit construction method |
JP2014122512A (en) * | 2012-12-21 | 2014-07-03 | Kumagai Gumi Co Ltd | Pipe installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2003239680A (en) | Method for connecting shield new pipe to existing pipe under ground | |
JP4731308B2 (en) | Cutter plate for tunnel excavator | |
JPH1122367A (en) | Connecting method of tunnel by use of different diameter-shielding excavator | |
JPH0489992A (en) | Existing pipe duct enlarging method and shield excavation device used with the method | |
JPH04106293A (en) | Underground connection method of shield tunnel | |
JP2742026B2 (en) | Underground tunnel joining method and segment | |
JP4160681B2 (en) | Propulsion steel pipe joint structure | |
JP2006037595A (en) | Excavator for jacking method and jacking method | |
JP3616898B2 (en) | Method for joining underground structures using propulsion device | |
JP2009235719A (en) | Shield machine and tunnel construction method | |
JP3640805B2 (en) | Pipe propulsion machine | |
JP3911062B2 (en) | Cutting edge device for joining existing structure and method for joining propulsion pipe | |
JP4142828B2 (en) | Shield machine | |
JP3713094B2 (en) | Connection method of existing underground pipe and new pipe by shield method | |
JPH066865B2 (en) | Shield tunnel underground docking method | |
JP4549585B2 (en) | Shield machine start mechanism and start method | |
JP3093437B2 (en) | Shield machine | |
JP2554540B2 (en) | Method and device for reaching shield tunnel | |
JP4879131B2 (en) | Underground joining method of shield excavator | |
JPH0455594A (en) | Underground connection of shield tunnels of defferent diameter | |
JPH08121075A (en) | Advancing method of shielding and excavating machine from existing tunnel | |
JP3188152B2 (en) | Small diameter pipe thruster | |
JPH09170397A (en) | Shield machine and recovery method thereof | |
JP2005290797A (en) | Combined method of propulsion and shielding | |
JPH102187A (en) | Adapter ring used for pipe jacking method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A625 | Written request for application examination (by other person) |
Effective date: 20041130 Free format text: JAPANESE INTERMEDIATE CODE: A625 |
|
A131 | Notification of reasons for refusal |
Effective date: 20061121 Free format text: JAPANESE INTERMEDIATE CODE: A131 |
|
A02 | Decision of refusal |
Effective date: 20071106 Free format text: JAPANESE INTERMEDIATE CODE: A02 |