JP2003096769A - Method for embedding ready-made pile with little earth removal - Google Patents

Method for embedding ready-made pile with little earth removal

Info

Publication number
JP2003096769A
JP2003096769A JP2001287289A JP2001287289A JP2003096769A JP 2003096769 A JP2003096769 A JP 2003096769A JP 2001287289 A JP2001287289 A JP 2001287289A JP 2001287289 A JP2001287289 A JP 2001287289A JP 2003096769 A JP2003096769 A JP 2003096769A
Authority
JP
Japan
Prior art keywords
pile
ready
hole
tip
diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001287289A
Other languages
Japanese (ja)
Inventor
Shinichi Yamato
真一 大和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Corp
Original Assignee
Asahi Kasei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Kasei Corp filed Critical Asahi Kasei Corp
Priority to JP2001287289A priority Critical patent/JP2003096769A/en
Publication of JP2003096769A publication Critical patent/JP2003096769A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a method for embedding a ready-made pile capable of reducing a volume of excavated soil to be removed and safely and surely transferring upper load to the ground. SOLUTION: The method for embedding the ready-make pile is so constituted that a hole having a diameter less than an outside diameter of a spiral vane is excavated until the predetermined depth after dry excavation is made in the vicinity of the surface of the earth by a pre-auger method, the neighboring front end of the excavated hole is enlargingly excavated and, at the same time, that the pile having a plurality of spiral vanes around the front end of the pile into the excavated hole is rotationally pressed in after a cement milk is injected to make it in a soil cement state.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】この発明は、既製杭とソイル
セメントとの複合構造体の埋設工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for burying a composite structure of ready-made piles and soil cement.

【0002】[0002]

【従来の技術】従来、既製杭の埋込み杭工法では杭先端
部を拡大掘削し、この部分にセメントミルクを注入して
杭先端部に拡大球根を造成するプレボーリング拡大根固
め工法が多く実施されてきた(図3)。しかし、杭先端
部の支持力は打込み工法の場合より小さく不十分なため
杭先端のみを太径とするST杭や杭先端部周辺に凸部を
有する節付き杭とし、杭先端部付近の周面摩擦力をも加
えて、支持力を高める方法(図4)、更には特開昭60
-238515のように杭先端部にらせん翼を設けて杭
先端支持力を増強する方法も考案されていた。
2. Description of the Related Art Conventionally, in the pre-built embedded pile method of prefabricated piles, a pre-boring expansion root consolidation method has been often carried out in which the pile tip is enlarged and excavated and cement milk is injected into this portion to form an enlarged bulb at the pile tip. Came (Fig. 3). However, since the bearing capacity of the pile tip is smaller than that of the driving method and is insufficient, we have made ST piles with only the pile tip a large diameter and knotted piles with protrusions around the pile tip, A method of increasing the supporting force by adding a surface friction force (FIG. 4), and further, JP-A-60
There has also been devised a method of increasing the pile tip supporting force by providing a spiral wing at the tip of the pile as in -238515.

【0003】しかし、この方法では杭外径は凸部やらせ
ん翼等の太径部があるため埋込杭工法で杭沈設するには
杭全長にわたり掘削孔を杭の太径部径以上の径で掘削す
る必要があった。その結果、掘削時及び杭埋設時に排出
される土砂は多くこれらは産業廃棄物となるので環境面
からも多くの問題点を有していた。従来の凸部やらせん
翼等を有する太径部を有する杭の埋込み工法では太径部
を大きくすると杭沈設のための掘削孔も大きくなり、そ
のための掘削残土も多くなり、更には施工機械も大きく
なるという欠点があった。
However, in this method, since the pile outer diameter has a large diameter portion such as a convex portion or a spiral wing, in order to bury the pile by the buried pile construction method, the excavation hole should have a diameter larger than the diameter of the large diameter portion of the pile over the entire length of the pile. Had to drill in. As a result, a large amount of earth and sand is discharged during excavation and burying of piles, and these are industrial wastes, which poses many environmental problems. In the conventional embedding method for piles with large diameter parts that have convex parts and spiral wings, etc., if the large diameter part is enlarged, the excavation holes for sunk the piles also increase, and the amount of excavated soil for that purpose also increases, and also the construction machinery. It had the drawback of becoming large.

【0004】[0004]

【発明が解決しようとする課題】本発明は、掘削土砂が
少なく、掘削孔拡底部の信頼性を向上させ、上部荷重を
安全確実に地盤に伝達しうる既製杭とソイルセメントと
の複合構造体の埋設工法の提供を目的とする。
SUMMARY OF THE INVENTION The present invention is a composite structure of ready-made piles and soil cement which has less excavated soil, improves the reliability of the bottom of the excavation hole, and can transmit the upper load safely and reliably to the ground. The purpose is to provide the buried construction method.

【0005】[0005]

【課題を解決するための手段】本発明者は、上部プレオ
ーガー孔径を杭外径(すなわち、らせん翼径)より小さ
くし、らせん翼の回転沈設機能と支持力発現のための一
体化機能を巧みに利用することに着目し、本発明に到達
した。すなわち、本発明は、下記の通り。 (1)地表部ではオーガーにて空掘り掘削し、次いで所
定深度まで既製杭のらせん翼外径以下の径の孔を水もし
くはセメントミルクを使用して掘削し、且つ先端付近を
拡大掘削するとともにセメントミルクを注入して先端付
近をソイルセメント状とした後、該掘削孔内に杭先端部
にらせん翼を有する既製杭を回転圧入して埋設すること
を特徴とする排土の少ない既製杭の埋設方法。
The present inventor has made the upper pre-auger hole diameter smaller than the pile outer diameter (that is, the diameter of the spiral blade), and has been skillful in the rotation sinking function of the spiral blade and the integrated function for expressing the supporting force. The present invention has been reached, focusing on the utilization of That is, the present invention is as follows. (1) At the surface, excavate with an auger, then drill a hole with a diameter less than or equal to the outer diameter of the spiral blade of a ready-made pile to a predetermined depth using water or cement milk. After injecting cement milk to make the vicinity of the soil cement-like, a ready-made pile with small soil discharge characterized by rotatingly press-fitting and embedding a ready-made pile having a spiral blade at the pile tip in the excavation hole Buried method.

【0006】(2)オーガーにて所定深度まで既製杭の
らせん翼外径以下の径の孔を空掘り掘削し、次いで先端
付近を拡大掘削するとともにセメントミルクを注入して
先端付近をソイルセメント状とした後、該掘削孔内に杭
先端部にらせん翼を有する既製杭を回転圧入して埋設す
ることを特徴とする排土の少ない既製杭の埋設方法。
(2) With an auger, a hole having a diameter equal to or smaller than the outer diameter of the spiral blade of the ready-made pile is dug to a predetermined depth, and then the vicinity of the tip is enlarged and at the same time cement milk is injected to make a soil cement shape near the tip. After that, the method for burying a ready-made pile with a small amount of soil discharge is characterized in that the ready-made pile having a spiral blade at the tip of the pile is rotatively press-fitted and buried in the excavation hole.

【0007】[0007]

【発明の実施の形態】以下図面を用いて本発明を詳細に
説明する。図1及び図2に実施態様の概要を示す。図に
示す1は杭本体であり、3は杭本体に固着された約1回
転のらせん翼である。2はらせん翼外径以下の径の上部
プレオーガー孔であり、5はらせん翼径より大きい下部
プレオーガー孔である。また6は地表部の空掘り部分で
ある。
DETAILED DESCRIPTION OF THE INVENTION The present invention will be described in detail below with reference to the drawings. 1 and 2 show the outline of the embodiment. Reference numeral 1 shown in the drawing is a pile main body, and 3 is a spiral blade fixed to the pile main body and having about one rotation. Reference numeral 2 is an upper pre-auger hole having a diameter equal to or smaller than the outer diameter of the spiral blade, and 5 is a lower pre-auger hole larger than the diameter of the spiral blade. In addition, 6 is a hollow portion of the ground surface.

【0008】下部プレオーガー孔内にはソイルセメント
が充填されており、杭と一体化して複合構造となってい
る。この構造体の施工に用いる掘削装置は最下部がオー
ガービットであり、上部は曲がりがなく、剛性の高いロ
ッドである。先端のオーガービットは、拡大掘削刃を有
するものであればどのような形状でも良く、拡大掘削刃
が油圧式で機械的に開閉するものでも、また、逆回転に
よって周辺土との抵抗によって開閉する方式のものでも
よい。ビットの先端はノズルを有し、掘削液やセメント
ミルクを吐出できる構造を有することが好ましい。
Soil cement is filled in the lower pre-auger hole and is integrated with the pile to form a composite structure. The bottom of the excavator used for constructing this structure is an auger bit, and the top is a rod having no bending and high rigidity. The auger bit at the tip may have any shape as long as it has an enlarged digging blade, even if the enlarged digging blade is hydraulically opened and closed mechanically, or it is opened and closed by resistance to the surrounding soil by reverse rotation. A system may be used. It is preferable that the tip of the bit has a nozzle and has a structure capable of discharging the drilling liquid and the cement milk.

【0009】このような掘削装置を用いて、らせん翼外
径以下の径の上部プレオーガー孔を所定深度まで設け
る。上部プレオーガー孔の掘削を開始するにあたり地表
部付近では水やセメントミルクを排出せずに空掘りを行
う。空掘りする長さは、長いほど排出土砂が少なくなっ
て効果的であるので、杭径程度以上が望ましい。上部プ
レオーガー区間では図1に示すように空掘り区間を除い
て地盤状況に応じ水やセメントミルクを注入しながら掘
削しても良いし、地盤が軟らかい場合は図2に示すよう
に空掘りを続行しても良い。上部プレオーガー孔の掘削
に続いて拡大掘削刃を拡げて先端拡底部を掘削し、ビッ
ト先端部のノズルなどを介して先端拡底部内にセメント
ミルクを注入する。掘削装置を引き抜いた後、掘削孔内
に杭先端部外周面に複数のらせん翼を有する既製杭を回
転により下降させて既製杭の下端部を掘削孔拡底部に定
着させる。
By using such an excavating device, an upper pre-auger hole having a diameter equal to or smaller than the outer diameter of the spiral blade is provided up to a predetermined depth. Before starting the excavation of the upper pre-auger hole, empty digging will be performed near the surface without discharging water or cement milk. The longer the length of hollow digging is, the less soil and sand is discharged, which is more effective. In the upper pre-auger section, as shown in Fig. 1, except for the blank digging section, it may be possible to dig while injecting water or cement milk depending on the ground condition, or if the ground is soft, continue digging as shown in Fig. 2. You may. Subsequent to the excavation of the upper pre-auger hole, the expansion drilling blade is expanded to excavate the tip bottom expanding part, and cement milk is injected into the tip bottom expanding part through a nozzle or the like at the bit tip. After pulling out the excavator, the ready-made pile having a plurality of spiral blades on the outer peripheral surface of the pile tip in the drill hole is lowered by rotation to fix the lower end of the ready-made pile to the bottom of the drill hole.

【0010】上部プレオーガー孔の径は地盤の硬さに応
じて選定すれば良い。杭先端部に複数枚の独立したらせ
ん翼を設ければ、掘削孔がらせん翼外径より小さくても
らせん翼により杭の回転沈設が可能である。拡大掘削孔
の長さは地盤の種別及び必要な支持力に応じて選択すれ
ば良い。らせん翼径の3倍くらいあれば良いが、5倍以
上あれば十分である。また拡大掘削孔径は羽根径程度あ
れば良いが地盤が硬い場合には羽根径より多少小さくて
もよい。
The diameter of the upper pre-auger hole may be selected according to the hardness of the ground. If multiple independent spiral blades are provided at the tip of the pile, the pile can be rotationally sunk by the spiral blade even if the drill hole is smaller than the outer diameter of the spiral blade. The length of the enlarged excavation hole may be selected according to the type of ground and the required bearing capacity. About 3 times the spiral blade diameter is enough, but 5 times or more is sufficient. The diameter of the enlarged excavation hole may be about the diameter of the blade, but it may be slightly smaller than the diameter of the blade when the ground is hard.

【0011】また、地盤が軟らかく大きな拡大掘削が可
能な場合は羽根径より大きくすることが望ましい。羽根
から拡大球根への荷重を十分伝達させるには拡大球根径
は羽根径の1.1〜1.5倍程度あれば十分である。使
用する杭は鋼管杭、既製コンクリート杭、鋼管コンクリ
ート杭、H型鋼杭等いずれの杭も可能である。既製コン
クリートの場合はらせん翼を杭外周面に取り付けるため
の工夫を施す必要がある。コンクリート杭製造時に複数
の短い鋼管を予め型枠内に設置しておきコンクリート硬
化後鋼管部分にらせん翼を溶接にて固着すれば良い。
Further, when the ground is soft and large expansion excavation is possible, it is desirable to make it larger than the blade diameter. In order to sufficiently transmit the load from the blade to the expanded bulb, it is sufficient that the expanded bulb diameter is about 1.1 to 1.5 times the blade diameter. The piles to be used can be steel pipe piles, ready-made concrete piles, steel pipe concrete piles, H-shaped steel piles and the like. In the case of ready-made concrete, it is necessary to take measures to attach the spiral blade to the outer peripheral surface of the pile. A plurality of short steel pipes may be installed in the formwork in advance during the production of concrete piles, and after the concrete is hardened, the spiral blade may be fixed to the steel pipe portion by welding.

【0012】杭先端部に取り付ける複数のらせん翼は、
各らせん翼がほぼ一回転のものが好ましい。各らせん翼
はほぼ等間隔に設置することが好ましい。らせん翼の径
は杭外径の1.5〜3倍程度が好ましい。荷重の分散効
果の点で1.5倍以上が、また羽根の分担力を過大にし
ない観点から3倍以下が好ましい。羽根の間隔は杭外径
にもよるが杭径の2倍から10倍程度の間隔で設置する
と効果的である。
The plurality of spiral blades attached to the tip of the pile are
It is preferable that each spiral blade has almost one rotation. It is preferable that the spiral blades are installed at substantially equal intervals. The diameter of the spiral blade is preferably about 1.5 to 3 times the outer diameter of the pile. It is preferably 1.5 times or more from the viewpoint of the effect of dispersing the load, and is preferably 3 times or less from the viewpoint of not unduly increasing the blade sharing force. It is effective to install the blades at intervals of about 2 to 10 times the pile diameter, depending on the outer diameter of the pile.

【0013】[0013]

【実施例】図面に基づきこの発明の実施例を説明する。
図5に示されるように掘削径D1=380mmで地上よ
り18m深さまで掘削し、その後、拡底部掘削径D0=
1000mmで、さらに、L=6.5m掘削し、全長L
0=23.5mの掘削孔を設けた。この拡底部掘削孔内
に水セメント比が60%のセメントミルクを注入し、杭
先端部LB=約6mの範囲に1500mmピッチで5枚
のらせん翼が杭外周に接合された本体部の外径D=40
0mmの外殻鋼管付コンクリート杭を埋設した。杭先端
部付近の標準貫入試験によるN値の平均値は、30程度
であった。
Embodiments of the present invention will be described with reference to the drawings.
As shown in FIG. 5, the excavation diameter D 1 = 380 mm is excavated to a depth of 18 m from the ground, and then the bottom excavation diameter D 0 =
At 1000 mm, L = 6.5 m was excavated, and the total length was L.
A drilling hole of 0 = 23.5 m was provided. Cement milk with a water-cement ratio of 60% was injected into the drilled hole in the bottom part, and the outer diameter of the main body in which five spiral blades were joined to the outer periphery of the pile at a pitch of 1500 mm in the range of the tip LB of the pile = about 6 m. D = 40
A concrete pile with a 0 mm outer shell steel pipe was buried. The average N value in the standard penetration test near the tip of the pile was about 30.

【0014】[0014]

【比較例】実施例と同じ敷地内に図6に示されるように
従来工法である掘削径D1=450mmで地上より全長
LO=23.5mの掘削孔を設けたのち先端部をD0=6
50、LB=2.0mの拡大削孔を造成し、この拡大掘
削孔内に水セメント比が60%のセメントミルクを注入
し、実施例と同じ外径(D=400mm)の既製コンク
リート杭を埋設した。
[Comparative Example] As shown in FIG. 6, a drilling diameter D 1 = 450 mm and a total length L o = 23.5 m from the ground, which is a conventional method, are provided in the same site as in the embodiment, and then the tip is D 0 = 6.
50, LB = 2.0 m expanded drilling hole was created, cement milk with a water cement ratio of 60% was injected into this expanded drilling hole, and a ready-made concrete pile with the same outer diameter (D = 400 mm) as in the example. Buried.

【0015】セメントミルクが硬化した後、実施例、比
較例で埋設した既製杭の再試験を実施した。最大荷重は
実施例では4100kNであったのに対して、比較例で
は高々1300kNであった。
After the cement milk was hardened, the ready-made piles buried in Examples and Comparative Examples were retested. The maximum load was 4100 kN in the example, whereas it was at most 1300 kN in the comparative example.

【0016】[0016]

【発明の効果】従来の既製杭を用いるプレボーリング先
端拡大根固め工法では杭を所定深度まで沈設させるため
に丁寧に掘削する必要があったので多くの水やセメント
ミルクが使用された。そのため地上へ排出する掘削土砂
は極めて多く作業廃棄物となって問題であった。本発明
では杭先端部に複数のらせん翼を設けているので大きな
掘削孔は必要とせず水やセメントミルクを少なくしても
杭を回転埋設すればらせん翼の推進力で所定深度まで埋
設できる。そのため地表部付近は水やセメントミルクを
一切使用しない空掘り施工が可能であり、空掘り区間が
掘削孔の蓋となってプレオーガー掘削時のみならず杭埋
設時も地表部への土砂の排出が抑制される効果を有して
いる。
EFFECTS OF THE INVENTION In the conventional pre-boring tip widening consolidation method using ready-made piles, a lot of water and cement milk were used because it was necessary to carefully excavate the piles in order to submerge them to a predetermined depth. Therefore, the excavated soil discharged to the ground was extremely large and became a work waste, which was a problem. In the present invention, since a plurality of spiral blades are provided at the tip of the pile, a large excavation hole is not required, and even if the amount of water and cement milk is reduced, the pile can be buried to a predetermined depth by rotationally burying it by the thrust of the spiral blade. For this reason, it is possible to perform hollow digging without using water or cement milk near the surface, and the empty digging section serves as a cover for the drilling hole, so that the earth and sand are discharged to the surface not only during pre-auger digging but also during pile burial. Has the effect of being suppressed.

【0017】また、節付き杭の施工では杭を所定深度ま
で沈設させるには杭全長にわたり節径以上の径で地盤を
掘削する必要があった。そのため節部を杭本体外径より
大幅に大きくすることは不経済となり大きくできない。
そのため、拡大球根を杭先端部に造成しても拡大径と節
径には大きな差があり十分な支持力伝達ができない問題
点を有していた。本発明では杭本体外径より大きいらせ
ん翼を取り付けても掘削孔はらせん翼径以下で良く、ま
たらせん翼を大きくしておけば拡大掘削孔と杭とを十分
一体化させる事ができるので杭の荷重伝達が良好とな
る。
Further, in the construction of the knotted pile, it was necessary to excavate the ground with a diameter equal to or larger than the knot diameter over the entire length of the pile in order to sink the pile to a predetermined depth. Therefore, it is uneconomical to make the joints much larger than the outer diameter of the pile body, and it is not possible to make them larger.
Therefore, there is a problem that even if an enlarged bulb is formed at the tip of the pile, there is a large difference between the enlarged diameter and the node diameter, and sufficient bearing force cannot be transmitted. In the present invention, even if a spiral blade larger than the outer diameter of the pile main body is attached, the excavation hole may be smaller than the spiral blade diameter, and if the spiral blade is made large, the enlarged excavation hole and the pile can be sufficiently integrated. The load transmission of is good.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一態様を示す概要説明図である。FIG. 1 is a schematic explanatory diagram illustrating one embodiment of the present invention.

【図2】本発明の別の態様を示す概要説明図である。FIG. 2 is a schematic explanatory view showing another aspect of the present invention.

【図3】従来工法の例を示す概要説明図である。FIG. 3 is a schematic explanatory diagram showing an example of a conventional method.

【図4】杭先端部に節付き杭を用いた従来工法の例を示
す概要説明図である。
FIG. 4 is a schematic explanatory view showing an example of a conventional construction method in which a knotted pile is used at the tip of the pile.

【図5】本発明の実施例を示す説明図である。FIG. 5 is an explanatory diagram showing an example of the present invention.

【図6】比較例を示す説明図である。FIG. 6 is an explanatory diagram showing a comparative example.

【符号の説明】[Explanation of symbols]

1 杭本体 2 上部プレオーガー孔 3 らせん翼 4 ソイルセメント硬化体 5 下部プレオーガー孔 6 空掘り部分 D 既製杭 D0 拡底部掘削径 D1 掘削径 L 拡底部掘削長 LB 既製杭の先端部 L0 掘削孔全長1 Pile Main Body 2 Upper Pre-Auger Hole 3 Helical Wing 4 Soil Cement Hardened Body 5 Lower Pre-Auger Hole 6 Empty Dug D D Ready-made Pile D0 Expanded Bottom Excavation Diameter D 1 Excavated Diameter L Expanded Excavation Length LB Pre-existing Pile Tip L0 Excavation Hole Total Length

─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成13年9月20日(2001.9.2
0)
[Submission date] September 20, 2001 (2001.9.2)
0)

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0014[Correction target item name] 0014

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【0014】[0014]

【比較例】実施例と同じ敷地内に図6に示されるよう
従来工法である掘削径D1=450mmで地上より
全長L0=23.5mの掘削孔を設けたのち先端部を
D0=650mm、LB=2.0mの拡大削孔を造成
し、この拡大削孔内に水セメント比が60%のセメント
ミルクを注入し、実施例と同じ外径(D=400mm)
の既製コンクリート杭を埋設した。
[Comparative Example] As shown in FIG. 6 in the same site as in Example, after having a borehole of the full-length L0 = 23.5m from the ground by drilling diameter D 1 = 450 mm, which is a conventional method, the tip D0 = 650 mm , LB = 2.0 m enlarged drilling hole was created, and cement milk having a water-cement ratio of 60% was injected into this enlarged drilling hole, and the same outer diameter (D = 400 mm) as in the example.
The prefabricated concrete pile was buried.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 地表部ではオーガーにて空掘り掘削し、
次いで所定深度まで既製杭のらせん翼外径以下の径の孔
を水もしくはセメントミルクを使用して掘削し、且つ先
端付近を拡大掘削するとともにセメントミルクを注入し
て先端付近をソイルセメント状とした後、該掘削孔内に
杭先端部にらせん翼を有する既製杭を回転圧入して埋設
することを特徴とする排土の少ない既製杭の埋設方法。
1. The surface of the ground is dug by an auger,
Next, drill a hole with a diameter less than or equal to the spiral blade outer diameter of the prefabricated pile to a predetermined depth using water or cement milk, and expand the vicinity of the tip and inject cement milk to make the soil cement near the tip. After that, a method for burying a ready-made pile with little soil discharge is characterized in that the ready-made pile having a spiral blade at the tip of the pile is rotationally press-fitted and buried in the excavation hole.
【請求項2】 オーガーにて所定深度まで既製杭のらせ
ん翼外径以下の径の孔を空掘り掘削し、次いで先端付近
を拡大掘削するとともにセメントミルクを注入して先端
付近をソイルセメント状とした後、該掘削孔内に杭先端
部にらせん翼を有する既製杭を回転圧入して埋設するこ
とを特徴とする排土の少ない既製杭の埋設方法。
2. A hole is drilled by an auger to a predetermined depth up to the outer diameter of the spiral blade of the ready-made pile, and then the vicinity of the tip is expanded and cement milk is injected to make the vicinity of the soil cement-like. After that, the method for burying a ready-made pile with a small amount of soil discharge is characterized in that the ready-made pile having a spiral wing at the tip of the pile is rotatively press-fitted and buried in the excavated hole.
JP2001287289A 2001-09-20 2001-09-20 Method for embedding ready-made pile with little earth removal Pending JP2003096769A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001287289A JP2003096769A (en) 2001-09-20 2001-09-20 Method for embedding ready-made pile with little earth removal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001287289A JP2003096769A (en) 2001-09-20 2001-09-20 Method for embedding ready-made pile with little earth removal

Publications (1)

Publication Number Publication Date
JP2003096769A true JP2003096769A (en) 2003-04-03

Family

ID=19110128

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001287289A Pending JP2003096769A (en) 2001-09-20 2001-09-20 Method for embedding ready-made pile with little earth removal

Country Status (1)

Country Link
JP (1) JP2003096769A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61117323A (en) * 1984-11-13 1986-06-04 Asahi Chem Ind Co Ltd Method of burying ready-made pile
JPS63122821A (en) * 1986-11-10 1988-05-26 Nippon Chikou Kk Foundation of self-supporting column
JPH06316927A (en) * 1993-05-06 1994-11-15 Kawasaki Steel Corp Installation of open section pile in large diameter
JPH08319616A (en) * 1995-05-23 1996-12-03 Kokudo Kiso:Kk Burying method of pile
JP2000352048A (en) * 1999-06-09 2000-12-19 Kokudo Kiso:Kk Steel pipe pile and method of burying the same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61117323A (en) * 1984-11-13 1986-06-04 Asahi Chem Ind Co Ltd Method of burying ready-made pile
JPS63122821A (en) * 1986-11-10 1988-05-26 Nippon Chikou Kk Foundation of self-supporting column
JPH06316927A (en) * 1993-05-06 1994-11-15 Kawasaki Steel Corp Installation of open section pile in large diameter
JPH08319616A (en) * 1995-05-23 1996-12-03 Kokudo Kiso:Kk Burying method of pile
JP2000352048A (en) * 1999-06-09 2000-12-19 Kokudo Kiso:Kk Steel pipe pile and method of burying the same

Similar Documents

Publication Publication Date Title
JP5265500B2 (en) Pile digging method, foundation pile structure
JP5677728B2 (en) Tunnel reinforcement method, tunnel reinforcement structure
CN105064336A (en) Hole forming construction method for three-section type pedestal pile
JP2008057184A (en) Method of constructing underground wall by using h-shaped pc pile
CN103061341B (en) Middle pick pile sinking construction method
JP2001336149A (en) Taper pile for civil engineering and building work foundation construction, foundation construction equipment therefor, and embedding method therefor
JP4724879B2 (en) Foundation pile structure
JP5024692B2 (en) Construction method of foundation pile, ready-made pile, pile hole drilling rod
KR100411662B1 (en) Construction Method of Prestressed spun High strength Concrete Pile
JPS62253817A (en) Burying work of custom-made concrete pile with expanded head
JP2003096769A (en) Method for embedding ready-made pile with little earth removal
JP2002054135A (en) Composite structure
JP2001271347A (en) Drop method for ready-made pile
JP4166191B2 (en) Hollow pile embedding method and excavator used therefor
JP2003096771A (en) Precast soil-cement pile having composite blades
JP2004027610A (en) Burying method for prefabricated pile
JP2003147767A (en) Rotational burying method for ready-made pile
JP2003147768A (en) Ready-made pile burying method for reducing removal earth
JP4156313B2 (en) Rotating method for ready-made piles
JP2005240395A (en) Rotary embedding method for pile
JP2005002635A (en) Foundation pile and manufacturing method therefor
JP2002180462A (en) Method for embedding existing pile
JPH0325121A (en) Sinking of pile in inner drilling pile method
JP2006183233A (en) Method for rotatively burying pile with concrete spiral protrusion
KR100420493B1 (en) A steel conduit post for ground-making

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080901

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100825

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100831

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20110105