JP2003056012A - Levelness detector for construction machinery - Google Patents

Levelness detector for construction machinery

Info

Publication number
JP2003056012A
JP2003056012A JP2001245339A JP2001245339A JP2003056012A JP 2003056012 A JP2003056012 A JP 2003056012A JP 2001245339 A JP2001245339 A JP 2001245339A JP 2001245339 A JP2001245339 A JP 2001245339A JP 2003056012 A JP2003056012 A JP 2003056012A
Authority
JP
Japan
Prior art keywords
plate
level
levelness
construction machine
detector
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001245339A
Other languages
Japanese (ja)
Inventor
Nozomi Tanaka
望 田中
Takayoshi Murahashi
高嘉 村橋
Takahiro Kawakami
孝浩 川上
Hideo Sorada
英男 空田
Tatsuji Tanaka
竜次 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Construction Machinery Co Ltd
Original Assignee
Hitachi Construction Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Construction Machinery Co Ltd filed Critical Hitachi Construction Machinery Co Ltd
Priority to JP2001245339A priority Critical patent/JP2003056012A/en
Publication of JP2003056012A publication Critical patent/JP2003056012A/en
Pending legal-status Critical Current

Links

Landscapes

  • Component Parts Of Construction Machinery (AREA)

Abstract

PROBLEM TO BE SOLVED: To make levelness adjustment easier for a level in back and forth direction and a level in right and left direction of the construction machinery. SOLUTION: A levelness detector 10 provided in a driver's cab 4 of the construction machinery is equipped with a first level 13 for detecting the levelness in back and forth direction of the construction machinery and a second level 14 for detecting the levelness in right to left direction of the construction machinery. The first level 13 is placed on the first plate 12, and the second level 14 is placed on the second plate 15. The levelness of the first level 13 is adjusted by utilizing a slot 12E of the first plate 12, and the levelness of the second level 14 is adjusted by utilizing the slot 15D of the second plate 15.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、油圧ショベル等の
建設機械に用いられる水平度検出器に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a levelness detector used for construction machines such as hydraulic excavators.

【0002】[0002]

【従来の技術】建設機械、例えば油圧ショベルでは下部
走行体上に上部旋回体が旋回可能に設けられ、その上部
旋回体に運転室が設けられている。オペレータは運転室
内で操作レバー等を操作することにより、走行、旋回、
フロント装置の動作等を制御して掘削作業等を行う。
2. Description of the Related Art In a construction machine such as a hydraulic excavator, an upper revolving structure is rotatably provided on a lower traveling structure, and a driver's cab is provided on the upper revolving structure. An operator operates a control lever etc. in the driver's cab to run, turn,
Excavation work is performed by controlling the operation of the front equipment.

【0003】このとき、作業現場の作業面に凸凹があっ
たり作業面が傾斜していると油圧ショベル自体が前後左
右方向に傾き、このように傾いた姿勢で作業を行うこと
になる。しかし、作業の安全性や作業効率の観点から、
作業現場を水平にならすなどして油圧ショベルの姿勢を
水平に保ちつつ作業を行うのが好ましい。なお、左右方
向および前後方向とは運転席に着座したオペレータから
見た方向であり、以下の説明でも同様とする。
At this time, if the work surface at the work site is uneven or the work surface is inclined, the hydraulic excavator itself tilts in the front-rear, left-right directions, and the work is performed in such a tilted posture. However, from the viewpoint of work safety and work efficiency,
It is preferable to work while keeping the posture of the hydraulic excavator horizontal by leveling the work site. The left-right direction and the front-back direction are the directions viewed from the operator sitting in the driver's seat, and the same applies to the following description.

【0004】そこで、従来、たとえば特開2000−3
8746号公報においてこの種の、建設機械の水平度検
出器が開示されている。この水平度検出器は、建設機械
の運転席の側面窓に車両前後方向に延設された2本のロ
ッドに取り付けられている。水平度検出器は、側面窓と
平行に延在する取付板と、この取付板に垂直に取り付け
られる略L字状の載置台とを有する。載置台は側面窓と
直行する水平面を有し、この水平面に建設機械左右方向
の水平度を検出する水準器および建設機械前後方向の水
平度を検出する水準器が載置されている。
Therefore, conventionally, for example, Japanese Unexamined Patent Publication No. 2000-3 is used.
Japanese Patent No. 8746 discloses such a levelness detector for a construction machine. This levelness detector is attached to two rods extending in the vehicle front-rear direction on the side window of the driver's seat of the construction machine. The horizontality detector has a mounting plate extending parallel to the side window, and a substantially L-shaped mounting table mounted vertically to the mounting plate. The mounting table has a horizontal surface orthogonal to the side window, and on this horizontal surface, a spirit level that detects the horizontalness of the horizontal direction of the construction machine and a spirit level that detects the horizontalness of the front and rear direction of the construction machine are mounted.

【0005】[0005]

【発明が解決しようとする課題】ところで、上述した従
来の水平度検出器は、初期の段階で2つの水準器が水平
となるように調整するいわゆる水平位置合わせを行う必
要がある。前後方向の水準器の水平位置合わせは、取付
板に取り付ける2本のボルトを利用して載置台を揺動さ
せて行う。左右方向の水準器の水平位置合わせは、載置
台の水平面と水準器の両端取付部との間に介在させるシ
ムの枚数を調整して行われる。このため、水平度が正し
く設定されるまで、シムの枚数を変えて水平度を調整す
る作業を繰り返さなければならない。
By the way, in the above-mentioned conventional levelness detector, it is necessary to perform so-called horizontal alignment in which the two spirit levels are adjusted to be horizontal at the initial stage. Horizontal alignment of the level in the front-back direction is performed by swinging the mounting table using two bolts attached to the mounting plate. Horizontal alignment of the level in the left-right direction is performed by adjusting the number of shims to be interposed between the horizontal surface of the mounting table and the mounting portions at both ends of the level. Therefore, it is necessary to repeat the work of adjusting the level by changing the number of shims until the level is correctly set.

【0006】本発明の目的は、前後方向の水準器のみな
らず、左右方向の水準器も容易に水平となるように調整
することができる水平度検出器を提供することである。
It is an object of the present invention to provide a levelness detector capable of easily adjusting not only the level in the front-back direction but also the level in the left-right direction to be horizontal.

【0007】[0007]

【課題を解決するための手段】発明の実施の形態を示す
図3に対応付けて説明する。請求項1の発明は、建設機
械の運転室4内に設けられ、建設機械の前後方向および
左右方向の水平度を検出する水平度検出器10に適用さ
れる。そして、建設機械の前後方向の水平度を検出する
第1水準器13と、建設機械の左右方向の水平度を検出
する第2水準器14と、第1水準器13が設置される載
置台12Bと運転室4の固定部6に固定するための取付
部12Aとを有する第1プレート12と、第2水準器1
4が設置される載置台12Bと第1プレート12に固定
するための取付部とを有する第2プレート15と、第1
プレート12をその取付部12Aを介して運転席の固定
部6に水平度を調整しつつ取り付ける第1固定手段12
D,12E,50,60と、第2プレート15をその取
付部15Aを介して第1プレート12に水平度を調整し
つつ取り付ける第2固定手段15C,15D,51,6
1とを備えることにより、上述の目的を達成する。第1
水準器13の水平度は、第1プレート12を運転席の固
定部6に取り付け際に、第1固定手段12D,12E,
50,60によって調整する。第2水準器14の水平度
は、第2プレート15を第1プレート12に取り付け際
に第2固定手段15C,15D,51,61によって調
整する。
An embodiment of the invention will be described with reference to FIG. The invention of claim 1 is applied to a levelness detector 10 provided in the operator's cab 4 of a construction machine and detecting the levelness of the construction machine in the front-rear direction and the left-right direction. Then, a first level 13 for detecting the horizontalness of the construction machine in the front-rear direction, a second level 14 for detecting the horizontalness of the construction machine in the left-right direction, and a mounting table 12B on which the first level 13 is installed. And a first plate 12 having a mounting portion 12A for fixing to the fixing portion 6 of the cab 4, and a second spirit level 1
A second plate 15 having a mounting table 12B on which the No. 4 is installed and a mounting portion for fixing to the first plate 12;
First fixing means 12 for attaching the plate 12 to the fixing portion 6 of the driver's seat through the attachment portion 12A while adjusting the levelness.
D, 12E, 50, 60 and second fixing means 15C, 15D, 51, 6 for attaching the second plate 15 to the first plate 12 via its attachment portion 15A while adjusting the horizontal degree.
The above-mentioned object is achieved by including 1 and. First
When the first plate 12 is attached to the fixed portion 6 of the driver's seat, the level of the level 13 is determined by the first fixing means 12D, 12E,
Adjust by 50, 60. The levelness of the second level 14 is adjusted by the second fixing means 15C, 15D, 51, 61 when the second plate 15 is attached to the first plate 12.

【0008】なお、本発明の構成を説明する上記課題を
解決するための手段の項では、本発明を分かり易くする
ために発明の実施の形態の図を用いたが、これにより本
発明が発明の実施の形態に限定されるものではない。
Incidentally, in the section of the means for solving the above-mentioned problems for explaining the constitution of the present invention, the drawings of the embodiments of the invention are used for the purpose of making the present invention easy to understand. However, the present invention is not limited to the embodiment.

【0009】[0009]

【発明の実施の形態】−第1の実施の形態− 以下、図1〜図5を参照して本発明の実施の形態を説明
する。図1は油圧ショベルの斜視図、図2は運転室の後
方斜視図である。図1に示すように、油圧ショベルは下
部走行体1を備えており、下部走行体1の上方には旋回
フレーム3が旋回可能に設けられている。旋回フレーム
3の上には、運転室4が設けられており、オペレータ
は、運転室4内に設けられた図示しない運転席に着座し
て油圧ショベルの運転操作を行う。
BEST MODE FOR CARRYING OUT THE INVENTION First Embodiment Hereinafter, an embodiment of the present invention will be described with reference to FIGS. 1 is a perspective view of a hydraulic excavator, and FIG. 2 is a rear perspective view of a driver's cab. As shown in FIG. 1, the hydraulic excavator includes a lower traveling body 1, and a revolving frame 3 is rotatably provided above the lower traveling body 1. A driver's cab 4 is provided on the revolving frame 3, and an operator sits on a driver's seat (not shown) provided in the driver's cab 4 to operate the hydraulic excavator.

【0010】図2に示すように、運転室4の側面窓5に
は側面窓5を保護するためのガード6が設けられてい
る。ガード6は、図示しないキャブ本体の構造体に両端
が保持されている4本のロッドで構成されている。
As shown in FIG. 2, the side window 5 of the cab 4 is provided with a guard 6 for protecting the side window 5. The guard 6 is composed of four rods whose both ends are held by a cab body structure (not shown).

【0011】図3は側面窓5のガード6に設けられた水
平度検出器10を運転席側から見た図、図4(a)は水
平度検出器10を上方から見た平面図、(b)は水平度
検出器10を運転室前方から見た正面図である。図4
(a)において、100は側面の窓ガラスである。
FIG. 3 is a view of the horizontality detector 10 provided on the guard 6 of the side window 5 as seen from the driver's seat side, and FIG. 4A is a plan view of the horizontality detector 10 seen from above, b) is a front view of the levelness detector 10 as viewed from the front of the cab. Figure 4
In (a), 100 is a side window glass.

【0012】図4(a)において、水平度検出器10
は、取付板11と第1プレート12を用いてロッド6
A,6Bに取り付けられる。取付板11は、上方凹部1
1A、中央平坦部11B、および下方凹部11Cを備え
ている。上方凹部11Aおよび下方凹部11Cには、そ
れぞれロッド6A,6Bが嵌め込まれる。また、中央平
坦部11Bの高さは、ロッド6A,6Bの間の距離とほ
ぼ同じ高さとされており、上下方向に離間して図示しな
い2つのボルト孔が形成されている。ボルト孔にはナッ
ト50が同心状に溶接されている。
In FIG. 4A, the horizontality detector 10
Is the rod 6 using the mounting plate 11 and the first plate 12.
It is attached to A and 6B. The mounting plate 11 has an upper recess 1
1A, a central flat portion 11B, and a lower concave portion 11C. Rods 6A and 6B are fitted in the upper recess 11A and the lower recess 11C, respectively. Further, the height of the central flat portion 11B is substantially the same as the distance between the rods 6A and 6B, and two bolt holes (not shown) are formed apart from each other in the vertical direction. A nut 50 is concentrically welded to the bolt hole.

【0013】第1プレート12は、取付板11に取り付
けるための取付部12A、建設機械前後方向水平度検出
用の第1水準器13を載置する載置台12B、および第
2プレート15を取り付けるためのフランジ部12Cを
備えて一体成形されている。図3に示すように、取付部
12Aには、ボルト孔12Dと建設機械前後方向に伸び
る長孔12Eとが上下方向に離間して形成されている。
取付板11と第1プレート12との間にロッド6A,6
Bを挟持し、ボルト60をナット50に螺合して水平度
検出器10が運転席に設置される。
The first plate 12 has a mounting portion 12A for mounting it on the mounting plate 11, a mounting table 12B for mounting a first level 13 for detecting the horizontal direction of the construction machine, and a second plate 15. Is integrally molded with the flange portion 12C. As shown in FIG. 3, a bolt hole 12D and a long hole 12E extending in the front-rear direction of the construction machine are formed in the mounting portion 12A so as to be separated from each other in the vertical direction.
Between the mounting plate 11 and the first plate 12, rods 6A, 6
The horizontality detector 10 is installed in the driver's seat by sandwiching B and screwing the bolt 60 into the nut 50.

【0014】載置台12Bは取付部12Aに直交する水
平面を有し、この水平面に第1水準器13がビス16に
よって固定されている。第1水準器13は細長い形状を
なしており、その長手方向が油圧ショベル前後方向を向
くように載置されている。
The mounting table 12B has a horizontal plane orthogonal to the mounting portion 12A, and the first level 13 is fixed to the horizontal plane by screws 16. The first spirit level 13 has an elongated shape, and is mounted so that the longitudinal direction thereof faces the front and rear direction of the hydraulic excavator.

【0015】載置台12Bの油圧ショベル前側部には、
載置台水平面から下方に垂直に延在するフランジ部12
Cが形成されている。フランジ部12Cには、建設機械
幅方向の両端に所定の間隔をあけて設けられた一対のボ
ルト孔12Dが形成されている。ボルト孔12Dにはナ
ット51が同心状に溶接されている。
On the front side of the hydraulic excavator of the mounting table 12B,
Flange portion 12 vertically extending downward from the horizontal surface of the mounting table
C is formed. The flange portion 12C is formed with a pair of bolt holes 12D provided at both ends in the width direction of the construction machine at predetermined intervals. A nut 51 is concentrically welded to the bolt hole 12D.

【0016】フランジ部12Cには、第2プレート15
が取り付けられる。第2プレート15は、第1プレート
12のフランジ部12Cに取り付けられる取付部15A
および第2水準器14を載置する載置台15Bを備えて
一体成形されている。載置台15Bは取付部15Aに対
しておよそ120度の角度をなして形成されている。
The second plate 15 is provided on the flange portion 12C.
Is attached. The second plate 15 has a mounting portion 15A that is mounted on the flange portion 12C of the first plate 12.
And the mounting table 15B on which the second level 14 is mounted is provided and integrally molded. The mounting table 15B is formed at an angle of about 120 degrees with respect to the mounting portion 15A.

【0017】取付部15Aには、建設機械幅方向一端部
にボルト孔15Cが、他端部には,建設機械上下方向に
延設される長孔15Dが形成されている。第1プレート
12のフランジ部12Cに第2プレート15の取付部1
5Aを当接させてボルト61,ナット51により、第1
プレート12に対して第2プレート15が接続されて固
定される。載置台15Bの傾斜面には、第2水準器14
がビス16で固定されている。
A bolt hole 15C is formed at one end of the mounting portion 15A in the width direction of the construction machine, and an elongated hole 15D extending vertically in the construction machine is formed at the other end. The mounting portion 1 of the second plate 15 is attached to the flange portion 12C of the first plate 12.
5A is brought into contact with the bolt 61 and the nut 51, and the first
The second plate 15 is connected and fixed to the plate 12. The second level 14 is provided on the inclined surface of the mounting table 15B.
Are fixed with screws 16.

【0018】図5は第1水準器13の詳細を示す図であ
り、(a)は第1水準器13の縦断面図、(b)は
(a)をA方向から見た平面図、(c)は(a)のB−
B’断面図、(d),(e)は第1水準器13が左右方
向に傾いた場合の平面図である。第1水準器13は、僅
かな気体(気泡)13Aを残して液体13Bを封入した
気泡管13Cをケース13D内に収納したものである。
ケース13Dには覗き窓(開口)13Eが形成されてい
て、この覗き窓13Eから気泡管13C内の気泡13A
の位置を視認することにより第1水準器13の前後方向
の水平度、すなわち油圧ショベルの前後方向の水平度を
検出する。第2水準器14も同様に構成され、油圧ショ
ベルの左右方向の水平度を検出する。図5(d)および
(e)は油圧ショベルの前後方向水平度が調整されてい
ない状態における水準器13の気泡13Aの基準ライン
13Fに対する位置を示す。
5A and 5B are diagrams showing the details of the first spirit level 13, wherein FIG. 5A is a vertical sectional view of the first spirit level 13, FIG. 5B is a plan view of FIG. c) is B- of (a)
B'sectional view, (d), (e) is a top view when the 1st level 13 inclines to the left-right direction. The first level 13 has a bubble tube 13C in which a liquid 13B is sealed while leaving a slight amount of gas (bubbles) 13A in a case 13D.
A viewing window (opening) 13E is formed in the case 13D, and a bubble 13A inside the bubble tube 13C is formed through the viewing window 13E.
By visually recognizing the position of, the levelness of the first level 13 in the front-rear direction, that is, the levelness of the hydraulic shovel in the front-rear direction is detected. The second spirit level 14 is also configured similarly and detects the horizontalness of the hydraulic excavator in the left-right direction. FIGS. 5D and 5E show the position of the bubble 13A of the level 13 with respect to the reference line 13F in the state where the front-rear horizontality of the hydraulic excavator is not adjusted.

【0019】以上の構成を有する水平度検出器10を運
転室4に取り付ける際に行う初期の水平位置合わせの手
順について説明する。まず、取付板11の上方凹部11
Aおよび下方凹部11Cのそれぞれを運転室4における
ガード6のロッド6A,6Bにそれぞれ嵌め込む。取付
板11に第1プレート12を取り付ける前に、第1水準
器13は第1プレート12の載置台12Bにビス16に
よってあらかじめ固定しておく。同様に、第2水準器1
4は、第2プレート15の載置台15Bに対してビス1
6によって固定しておく。
An initial horizontal alignment procedure performed when the horizontality detector 10 having the above structure is attached to the cab 4 will be described. First, the upper recess 11 of the mounting plate 11
The A and the lower recess 11C are fitted into the rods 6A and 6B of the guard 6 in the cab 4, respectively. Before attaching the first plate 12 to the mounting plate 11, the first level 13 is fixed to the mounting table 12B of the first plate 12 in advance with screws 16. Similarly, the second level 1
4 is a screw 1 with respect to the mounting table 15B of the second plate 15.
Fix with 6.

【0020】次に、取付板11におけるガード6を挟ん
だ反対側から、取付板11に対して第1プレート12を
ボルト60,ナット50によって取り付ける。このと
き、第1水準器13の水平位置合わせも行う。まず円形
のボルト孔12Dおよび取付板11のボルト孔にボルト
60を貫通させ、取付板11の裏側のナット50にボル
ト60を仮締めする。ボルト60を長孔12Eに挿入し
てナット50に仮締めする。ここで、第1プレート12
を前後方向におおよそ水平となるように支えながら、第
1水準器13の気泡管13Cにおける気泡13Aを覗き
窓13Eから覗き込み、気泡13Aが中心位置にあるか
否かを確認する。そして、気泡13Aが中心位置からず
れていた場合には、第1プレート12における円形のボ
ルト孔12Dに挿入されたボルト60を中心として、第
1プレート12をわずかに揺動させて、第1水準器13
の水平位置合わせを行う。
Next, the first plate 12 is attached to the attachment plate 11 from the opposite side of the attachment plate 11 with the guard 6 sandwiched between them by bolts 60 and nuts 50. At this time, horizontal alignment of the first level 13 is also performed. First, the bolt 60 is passed through the circular bolt hole 12D and the bolt hole of the mounting plate 11, and the bolt 60 is temporarily tightened to the nut 50 on the back side of the mounting plate 11. The bolt 60 is inserted into the long hole 12E and temporarily fastened to the nut 50. Here, the first plate 12
While supporting so as to be approximately horizontal in the front-rear direction, the bubble 13A in the bubble tube 13C of the first spirit level 13 is looked into through the viewing window 13E, and it is confirmed whether or not the bubble 13A is at the center position. When the bubble 13A is displaced from the center position, the first plate 12 is slightly swung about the bolt 60 inserted in the circular bolt hole 12D of the first plate 12, and the first level is reached. Bowl 13
Horizontal alignment of.

【0021】この作業を適宜繰り返し行い、気泡13A
が中心に位置するように水平位置合わせを行う。水平位
置合わせ状態で、ボルト60を長孔12Eに挿入し、取
付板11の裏側のナット50にボルト60を螺合して締
め付けることにより、取付板11に対して第1プレート
12が固定される。こうして、第1プレート12が取付
板11に取り付けられるとともに、第1水準器13の初
期の位置合わせが完了する。
This operation is appropriately repeated to form the bubbles 13A.
Horizontal alignment is done so that is centered. The first plate 12 is fixed to the mounting plate 11 by inserting the bolt 60 into the elongated hole 12E and screwing and tightening the bolt 60 into the nut 50 on the back side of the mounting plate 11 in the horizontal alignment state. . Thus, the first plate 12 is attached to the attachment plate 11, and the initial alignment of the first spirit level 13 is completed.

【0022】次に、第1プレート12のフランジ部12
Cに第2プレート15を取り付けるとともに、第2水準
器14の初期の水平位置合わせを行う。まず、第1プレ
ート12のフランジ部12Cに第2プレート15の取付
部15Aを当接させる。第2プレート15のボルト孔1
5Cとフランジ部12Cのボルト孔にボルト61を挿通
し、フランジ部12Cのナット51に螺合して仮締めす
る。長孔15Dとフランジ部12Cのボルト孔にボルト
61を挿通し、フランジ部12Cのナット50に螺合し
て仮締めする。
Next, the flange portion 12 of the first plate 12
The second plate 15 is attached to C and the initial horizontal alignment of the second level 14 is performed. First, the mounting portion 15A of the second plate 15 is brought into contact with the flange portion 12C of the first plate 12. Bolt hole 1 of the second plate 15
The bolt 61 is inserted through the bolt holes of 5C and the flange portion 12C, screwed into the nut 51 of the flange portion 12C, and temporarily tightened. The bolt 61 is inserted through the long hole 15D and the bolt hole of the flange portion 12C, and screwed into the nut 50 of the flange portion 12C to temporarily tighten it.

【0023】ここで、第2プレート15を左右方向にお
およそ水平になるように支持しながら、第2水準器14
の気泡管14Cにおける気泡14Aを覗き窓14Eから
覗き込み、気泡14Aが中心位置にあるか否かを確認す
る。そして、気泡14Aが中心位置からずれていた場合
には、第2プレート15における円形のボルト孔15C
に挿入されたボルト61を中心として、第2プレート1
5をわずかに揺動させて、水平位置合わせを行う。
Here, while supporting the second plate 15 so as to be approximately horizontal in the left-right direction, the second level 14
The bubble 14A in the bubble tube 14C is viewed through the viewing window 14E, and it is confirmed whether or not the bubble 14A is at the center position. When the bubble 14A is displaced from the center position, the circular bolt hole 15C in the second plate 15 is formed.
Centering around the bolt 61 inserted in the second plate 1
5 is rocked slightly to perform horizontal alignment.

【0024】この作業を適宜繰り返し、気泡14Aが中
心に位置するように水平位置合わせを行う。その位置で
ボルト61をフランジ部12Cの裏側のナット51に堅
締する。これにより、第1プレート12に対して第2プ
レート15が固定される。こうして、第2プレート15
が第1プレート12に取り付けられるとともに、第2水
準器14の初期の位置合わせが完了する。
By repeating this operation as appropriate, horizontal alignment is performed so that the bubble 14A is located at the center. At that position, the bolt 61 is tightly fastened to the nut 51 on the back side of the flange portion 12C. As a result, the second plate 15 is fixed to the first plate 12. Thus, the second plate 15
Is attached to the first plate 12, and the initial alignment of the second spirit level 14 is completed.

【0025】このように、本実施の形態に係る水平度検
出器10では、油圧ショベル前後の水平度を検出する第
1水準器13が第1プレート12に載置され、油圧ショ
ベル左右の水平度を検出する第2水準器14が第2プレ
ート15に載置されている。そして、第1プレート12
をロッド6に取り付ける際に、長孔12Eを利用して第
1プレート12を揺動させるだけで、第1水準器13の
水平位置合わせを行うことができる。また、第2プレー
ト15を第1プレート12に取り付ける際に、長孔15
Dを利用して第2プレート15を揺動させるだけで、第
2水準器14の水平位置合わせを行うことができる。し
たがって、従来のシムを用いた水平位置合わせのよう
に、第2水準器14の取付・取り外しを何回も行うこと
なく、簡単にその水平位置合わせを行うことができる。
As described above, in the levelness detector 10 according to this embodiment, the first level 13 for detecting the levelness before and after the hydraulic excavator is placed on the first plate 12, and the levelness of the left and right sides of the hydraulic excavator is set. The second level 14 for detecting the is mounted on the second plate 15. Then, the first plate 12
The horizontal position of the first spirit level 13 can be adjusted only by swinging the first plate 12 using the elongated hole 12E when attaching the first level 12 to the rod 6. When attaching the second plate 15 to the first plate 12, the long hole 15
The horizontal position of the second electronic level 14 can be aligned simply by swinging the second plate 15 using D. Therefore, unlike the conventional horizontal alignment using a shim, the horizontal alignment can be easily performed without repeatedly attaching and detaching the second spirit level 14.

【0026】−第2の実施形態− 次に、本発明の第2の実施形態について説明する。図6
は、本実施形態に係る水平度検出器を車両前方から見た
図である。第1の実施の形態と異なるのは、第1プレー
ト112に対する第2プレート115の取り付け方式で
ある。
-Second Embodiment- Next, a second embodiment of the present invention will be described. Figure 6
FIG. 3 is a diagram of the horizontality detector according to the present embodiment as seen from the front of the vehicle. The difference from the first embodiment is the method of attaching the second plate 115 to the first plate 112.

【0027】すなわち、第2プレート115は第1プレ
ート112に1本のボルト160で取り付けられてい
る。第1水準器13の初期の位置合わせが完了したら、
第2水準器14が予め取り付けられている第2プレート
115を第1プレート112のフランジ部112Cにボ
ルト60をナット(不図示)に螺合して仮止めする。第
2プレート115を左右方向におおよそ水平になるよう
に支持しながら、第2水準器14の気泡14Aが中心位
置にあるか否かを確認する。そして、気泡14Aが中心
位置からずれていた場合には、ボルト161を中心とし
て第2プレート115をわずかに揺動させて、水平位置
合わせを行う。
That is, the second plate 115 is attached to the first plate 112 with one bolt 160. When the initial alignment of the first spirit level 13 is completed,
The second plate 115 to which the second level 14 is attached in advance is temporarily fixed to the flange portion 112C of the first plate 112 by screwing a bolt 60 into a nut (not shown). While supporting the second plate 115 so as to be approximately horizontal in the left-right direction, it is confirmed whether or not the bubble 14A of the second level 14 is at the center position. Then, when the bubble 14A is displaced from the center position, the second plate 115 is slightly swung about the bolt 161 to perform horizontal alignment.

【0028】この作業を適宜繰り返し、気泡14Aが中
心に位置するように水平位置合わせを行い、その位置で
ボルト161をナットに堅締させて第1プレート112
に対して第2プレート115が固定される。このように
して、第2水準器14の初期の位置合わせが完了する。
By repeating this operation as appropriate, horizontal alignment is performed so that the bubble 14A is located at the center, and at that position, the bolt 161 is tightly fastened to the nut and the first plate 112 is fixed.
On the other hand, the second plate 115 is fixed. In this way, the initial alignment of the second spirit level 14 is completed.

【0029】本実施形態では、第1の実施形態と比べ
て、第2プレート32を取り付ける作業並びに第2水準
器14の水平度調整作業をさらに簡易化することができ
る。
In this embodiment, the work of attaching the second plate 32 and the work of adjusting the levelness of the second level 14 can be further simplified as compared with the first embodiment.

【0030】なお、上述した実施の形態では、水平度検
出器を運転室4のガード6に設けたが、これに限らず、
例えば運転席前方の計器板部分に設けても良い。また、
本実施の形態は、図7に示すようなローリングショベル
の水平度検出器にも適用することができる。図7はロー
リングショベルの正面図(フロント装置は省略して示し
た)であって、旋回体102は不図示の旋回駆動機構に
より走行体101に旋回自在に設置されるとともに、ロ
ーリング機構103により図7の左右方向に傾斜自在に
設けられている。図7のローリング機構103では、走
行体101のトラックフレーム101aがセンタピン1
01bを介して上部旋回体102の下部フレーム102
aに連結され、センタピン101bの左右に油圧シリン
ダ103A,103Bが設けられている。油圧シリンダ
103A,103Bのボトム側は下部走行体101にピ
ストンロッド先端は上部旋回体102に接続されてお
り、図7のように作業現場に傾斜や凸凹があった場合、
オペレータが運転室104内に設けられた水平度検出器
で水平度を確認しながら油圧シリンダ103A,103
Bを伸縮して上部旋回体102の水平状態を保持する。
In the above embodiment, the levelness detector is provided in the guard 6 of the operator's cab 4, but the invention is not limited to this.
For example, it may be provided on the instrument panel portion in front of the driver's seat. Also,
This embodiment can also be applied to a horizontality detector of a rolling shovel as shown in FIG. 7. FIG. 7 is a front view of a rolling excavator (a front device is omitted), in which the revolving structure 102 is rotatably installed on the traveling structure 101 by a revolving drive mechanism (not shown), and the revolving structure 103 is provided by It is provided so as to be tiltable in the left-right direction of 7. In the rolling mechanism 103 shown in FIG. 7, the track frame 101a of the traveling body 101 has the center pin 1
The lower frame 102 of the upper swing body 102 via 01b
Hydraulic cylinders 103A and 103B are provided on the left and right of the center pin 101b, which are connected to a. The bottom side of each of the hydraulic cylinders 103A and 103B is connected to the lower traveling body 101, and the tip of the piston rod is connected to the upper revolving body 102. If there is an inclination or unevenness at the work site as shown in FIG.
While the operator confirms the levelness with the levelness detector provided in the cab 104, the hydraulic cylinders 103A, 103
B is expanded and contracted to maintain the upper swing body 102 in a horizontal state.

【0031】以上の実施の形態では、第1および第2固
定手段として、長孔12Eや15Dにボルト60,61
を挿通して第1および第2のプレート12および15を
それぞれ揺動させるようにしたが、これ以外の種々の方
式でもよい。また、以上では油圧ショベルについて説明
したが、それ以外の建設機械にも本発明を適用できる。
In the above embodiment, the bolts 60 and 61 are provided in the long holes 12E and 15D as the first and second fixing means.
Although the first and second plates 12 and 15 are oscillated by inserting through the above, various methods other than this may be used. Although the hydraulic excavator has been described above, the present invention can be applied to other construction machines.

【0032】[0032]

【発明の効果】以上説明したように、本発明によれば、
建設機械の前後方向の水平度を検出する第1水準器と、
建設機械の左右方向の水平度を検出する第2水準器の双
方を、それぞれ第1および第2の固定手段で固定する際
にそれぞれの水平度を調整可能としたので、水準器の水
平度調整が容易になる。しかも、シムを用いる必要が無
いので、シムを紛失する心配がなくなり、また細かな部
品の管理が不要であるので、組立性も向上する。
As described above, according to the present invention,
A first level that detects the horizontalness of the construction machine in the front-rear direction,
Since the horizontal level of each of the second levelers for detecting the horizontal level of the construction machine is fixed by the first and second fixing means, the levelness of the level level can be adjusted. Will be easier. Moreover, since it is not necessary to use a shim, there is no fear of losing the shim, and since it is not necessary to manage fine parts, the assemblability is improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】油圧ショベルの斜視図。FIG. 1 is a perspective view of a hydraulic excavator.

【図2】運転室の後方斜視図。FIG. 2 is a rear perspective view of the cab.

【図3】側面窓のガードに設けられた水平度検出器を運
転席側から見た図。
FIG. 3 is a view of a horizontality detector provided on a guard of a side window as seen from a driver's seat side.

【図4】(a)は図3のIVA方向から見た水平度検出器
の平面図、(b)は図3のIVB方向から見た水平度検出
器の正面図。
4A is a plan view of the horizontality detector seen from the IVA direction in FIG. 3, and FIG. 4B is a front view of the horizontality detector seen from the IVB direction in FIG.

【図5】図1に示す水準器の詳細を示す図であり、
(a)は水準器の縦断面図、(b)は(a)をA方向か
ら見た平面図、(c)は(a)のB−B’断面図、
(d),(e)は水準器が左右方向に傾いた場合の平面
図。
5 is a diagram showing details of the electronic level shown in FIG. 1,
(A) is a vertical cross-sectional view of the electronic level, (b) is a plan view of (a) seen from the direction A, (c) is a cross-sectional view taken along the line BB 'of (a),
(D), (e) is a plan view when the spirit level is tilted in the left-right direction.

【図6】第2の実施形態に係る水平度検出器を運転席前
方から見た正面図。
FIG. 6 is a front view of the horizontality detector according to the second embodiment as seen from the front of a driver's seat.

【図7】ローリングショベルの正面図。FIG. 7 is a front view of a rolling shovel.

【符号の説明】[Explanation of symbols]

6 ガード 6A〜6D ロッド 10 水平度検出器 11 取付板 12 第2プレート 13 第1水準器 14 第2水準器 15 第2プレート 50 ナット 60 ボルト 6 Guard 6A-6D Rod 10 Horizontality detector 11 Mounting plate 12 2nd plate 13 1st level 14 Second level 15 Second plate 50 nuts 60 bolts

───────────────────────────────────────────────────── フロントページの続き (72)発明者 川上 孝浩 茨城県水戸市川又町25−12 (72)発明者 空田 英男 茨城県新治郡千代田町新治1828日立建機千 代田寮2−317 (72)発明者 田中 竜次 茨城県稲敷郡阿見町荒川本郷1374−5 Fターム(参考) 2D015 HA01 HB04    ─────────────────────────────────────────────────── ─── Continued front page    (72) Inventor Takahiro Kawakami             25-12 Kawamata Town, Mito City, Ibaraki Prefecture (72) Inventor Hideo Sora             1828 Shinji, Chiyoda-cho, Shinji-gun, Ibaraki Prefecture Hitachi Construction Machinery Sen             2-317 Shirota Dormitory (72) Inventor Ryuji Tanaka             1374-5 Arakawa Hongo, Ami Town, Inashiki District, Ibaraki Prefecture F-term (reference) 2D015 HA01 HB04

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】建設機械の運転室内に設けられ、前記建設
機械の前後方向および左右方向の水平度を検出する水平
度検出器において、 前記建設機械の前後方向の水平度を検出する第1水準器
と、 前記建設機械の左右方向の水平度を検出する第2水準器
と、 前記第1水準器が設置される載置台と運転室の固定部に
固定するための取付部とを有する第1プレートと、 前記第2水準器が設置される載置台と前記第1プレート
に固定するための取付部とを有する第2プレートと、 前記第1プレートをその取付部を介して運転室の固定部
に水平度を調整しつつ取り付ける第1固定手段と、 前記第2プレートをその取付部を介して前記第1プレー
トに水平度を調整しつつ取り付ける第2固定手段とを備
えることを特徴とする建設機械の水平度検出器。
1. A leveling detector provided in a driver's cab of a construction machine for detecting the horizontalness of the construction machine in the front-rear direction and the left-right direction, the first level detecting the levelness of the construction machine in the front-rear direction. A first level having a level, a second level that detects the horizontalness of the construction machine in the left-right direction, and a mounting table on which the first level is installed and a fixed part in a cab A second plate having a plate, a mounting table on which the second spirit level is installed, and an attachment portion for fixing the first plate to the first plate; and a fixing portion of the cab through the attachment portion of the first plate. And a second fixing means for mounting the second plate on the first plate via the mounting portion while adjusting the levelness thereof. Machine levelness detector.
【請求項2】請求項1に記載の建設機械の水平度検出器
において、 前記第1固定手段は、前記第1プレートの前記取付部に
おいて建設機械前後方向の一端側に形成されたボルト孔
および他端側に設けられ建設機械前後方向に延設された
長孔と、これらボルト孔および長孔に挿通されるボルト
とを含み、 前記ボルト孔を支点として前記第1プレートを揺動可能
としたことを特徴とする建設機械の水平度検出器。
2. The levelness detector for a construction machine according to claim 1, wherein the first fixing means is a bolt hole formed at one end side in the front-rear direction of the construction machine in the mounting portion of the first plate, and A long hole provided on the other end side and extending in the front-rear direction of the construction machine, and a bolt hole and a bolt inserted into the long hole are included, and the first plate can be swung with the bolt hole as a fulcrum. A horizontality detector for construction machinery.
【請求項3】請求項2に記載の建設機械の水平度検出器
において、 前記第2固定手段は、前記第2プレートの前記取付部に
おいて建設機械左右方向の一端側に形成されたボルト孔
および他端側に設けられ長孔と、これらボルト孔および
長孔に挿通されるボルトとを含み、 前記ボルト孔を支点として前記第2プレートを揺動可能
としたことを特徴とする建設機械の水平度検出器。
3. The levelness detector for a construction machine according to claim 2, wherein the second fixing means is a bolt hole formed at one end side in the left-right direction of the construction machine in the mounting portion of the second plate, A horizontal construction machine, characterized in that the second plate includes an elongated hole provided on the other end side and a bolt hole and a bolt inserted into the elongated hole, and the second plate is swingable with the bolt hole as a fulcrum. Degree detector.
JP2001245339A 2001-08-13 2001-08-13 Levelness detector for construction machinery Pending JP2003056012A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001245339A JP2003056012A (en) 2001-08-13 2001-08-13 Levelness detector for construction machinery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001245339A JP2003056012A (en) 2001-08-13 2001-08-13 Levelness detector for construction machinery

Publications (1)

Publication Number Publication Date
JP2003056012A true JP2003056012A (en) 2003-02-26

Family

ID=19075109

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001245339A Pending JP2003056012A (en) 2001-08-13 2001-08-13 Levelness detector for construction machinery

Country Status (1)

Country Link
JP (1) JP2003056012A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000038746A (en) * 1998-07-21 2000-02-08 Hitachi Constr Mach Co Ltd Horizontality detector for construction equipment

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000038746A (en) * 1998-07-21 2000-02-08 Hitachi Constr Mach Co Ltd Horizontality detector for construction equipment

Similar Documents

Publication Publication Date Title
US7665801B2 (en) Structure of upper frame for supporting cabin of construction machinery
US8978812B2 (en) Construction machine
JP5278509B2 (en) Device mounting method and apparatus for construction machinery
US20050194155A1 (en) Blade pitch control structure for bulldozer
JP4387893B2 (en) Construction machinery cab
JP2003205754A (en) On-vehicle mount structure for fuel container
JP2003056012A (en) Levelness detector for construction machinery
JP2011202357A (en) Construction machine
JPH0622058U (en) Seat mounting structure
JP4254354B2 (en) Seat-mounted drive robot
JPH10331657A (en) Circular construction machine
JP3227342B2 (en) Cabin floor structure
JP4199173B2 (en) Swivel construction machine
JP5507041B2 (en) Swivel work vehicle
JP4188799B2 (en) Construction machinery
JP2002146834A (en) Revolving working machine
JP2005014642A (en) Construction machine
JPH08270016A (en) Fitting structure of counter weight
JP2006027316A (en) Working vehicle
JP5252951B2 (en) Side mirror device for turning work vehicle
JPH10204921A (en) Rolling shovel
JP2001032328A (en) Counterweight supporting structure of construction machine
JP2010070939A (en) Construction machinery
JP2005319865A (en) Motorcycle
JPH08310437A (en) Sub-frame installed part structure for vehicle

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080212

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20091221

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100105

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20100629