JP2003030393A - Operation process controlling method - Google Patents

Operation process controlling method

Info

Publication number
JP2003030393A
JP2003030393A JP2001212916A JP2001212916A JP2003030393A JP 2003030393 A JP2003030393 A JP 2003030393A JP 2001212916 A JP2001212916 A JP 2001212916A JP 2001212916 A JP2001212916 A JP 2001212916A JP 2003030393 A JP2003030393 A JP 2003030393A
Authority
JP
Japan
Prior art keywords
work
product
management control
lot number
instruction sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2001212916A
Other languages
Japanese (ja)
Inventor
Takanobu Ito
貴延 伊東
Hideyuki Ishii
秀幸 石井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nitta DuPont Inc
Original Assignee
Rodel Nitta Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rodel Nitta Inc filed Critical Rodel Nitta Inc
Priority to JP2001212916A priority Critical patent/JP2003030393A/en
Publication of JP2003030393A publication Critical patent/JP2003030393A/en
Withdrawn legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To perform progress control over manufacturing stages and to contribute to the improvement of productivity, etc. SOLUTION: Information regarding operation stages needed to manufacture respective products is inputted to a management control part 10 which manages the operation stages needed to manufacture the products together with the lot numbers of the respective manufactured products while given the lot numbers by the products. The management control part 10 creates an operation instruction document where the information regarding the operation stages inputted to the management control part 10 and the lot numbers of the products are represented as linear and two-dimensional codes. When the operation instruction document is supplied to the respective operation stages and specific operations are performed for components, etc., the codes regarding the operations of the operation instruction document and the codes regarding the lot numbers are read by a code read means 17 and inputted to the management control part 10.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、各種製品を製造す
る際に実施される各作業工程における作業を管理する方
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of managing work in each work process performed when manufacturing various products.

【0002】[0002]

【従来の技術】各種製品は、通常、複数の製造工程を経
て製造される。製品の製造ラインでは、製品を製造する
ために必要な作業を順番に実施することによって、製品
とされる。この場合、各作業工程における作業を管理す
るために、各製品にロット番号がそれぞれ付与されて、
各製品毎に、必要とする作業工程が記載された作業指示
書が作成されて、所定の作業が実施される部品等ととも
に作業指示書が、各作業工程に供給される。作業者は、
その作業指示書に基づいて、各作業工程において所定の
作業を実施する。そして、作業が終了すると、作業指示
書における必要な項目をチェックした後に、所定の作業
が終了した部品等とともに、作業指示書が次の作業工程
に供給される。
2. Description of the Related Art Various products are usually manufactured through a plurality of manufacturing processes. In a product manufacturing line, a product is obtained by sequentially performing the operations required to manufacture the product. In this case, in order to manage the work in each work process, each product is assigned a lot number,
A work instruction sheet in which necessary work steps are described is created for each product, and the work instruction sheet is supplied to each work step together with parts and the like for performing a predetermined work. The worker
Based on the work instruction sheet, a predetermined work is performed in each work process. When the work is completed, the necessary items in the work instruction sheet are checked, and then the work instruction sheet is supplied to the next work process together with the parts and the like for which the predetermined work has been completed.

【0003】[0003]

【発明が解決しようとする課題】各作業工程において
は、作業指示書に対して、製品毎に付与されたロット番
号、実施した作業内容、その作業を実施した日付等を、
作業者が記入する必要がある。しかしながら、製品毎に
付与されたロット番号、作業内容等の記入は煩わしく、
また、それらを正確に記入することは容易でないという
問題がある。しかも、作業者が、作業指示書に必要な事
項を記入することにより、各作業工程において作業効率
が低下するおそれもある。
In each work process, the lot number assigned to each product, the work performed, the date when the work was performed, etc., were recorded in the work instruction sheet.
Must be filled by the operator. However, it is troublesome to enter the lot number, work content, etc. assigned to each product,
There is also a problem that it is not easy to fill them in accurately. In addition, the worker may fill in necessary items in the work instruction sheet, which may reduce work efficiency in each work process.

【0004】また、作業指示書は、部品等とともに各作
業工程に供給されるために、全ての作業が終了するまで
は、作業指示書によって指示された作業が、いつ、実施
されたかは把握することができず、また、1つの製品に
関しても、どの段階まで作業が実施されたかを把握する
ことができないという問題もある。さらには、各作業工
程における作業の実績は、作業指示書を回収した後に集
計しなければならず、製造ラインにおける各作業工程を
確実に管理することができないという問題もある。
Further, since the work instruction sheet is supplied to each work process together with parts and the like, it is possible to grasp when the work instructed by the work instruction sheet has been carried out until all the work is completed. There is also a problem that it is impossible to grasp the level to which the work has been carried out for one product. Furthermore, the work performance in each work process must be totaled after collecting the work instructions, and there is a problem that each work process in the manufacturing line cannot be reliably managed.

【0005】本発明は、このような問題を解決するもの
であり、その目的は、製造工程における進捗管理が可能
であり、また、生産性の向上等に貢献することができる
作業工程管理方法を提供することにある。
The present invention solves such a problem, and an object thereof is to provide a work process management method capable of managing the progress in the manufacturing process and contributing to the improvement of productivity. To provide.

【0006】[0006]

【課題を解決するための手段】本発明の作業工程管理方
法は、製品を製造するために必要な作業工程を、製造さ
れる各製品のロット番号とともに管理する管理制御部に
対して、各製品を製造するために必要な作業工程に関す
る情報を各製品毎にロット番号を付与してそれぞれ入力
する工程と、管理制御部に入力された作業工程に関する
情報および製品のロット番号を、1次元または2次元コ
ードとして表示された作業指示書を作成する工程と、作
業工程において所定の作業が実施されることにより、作
業指示書におけるその作業に関するコードおよびロット
番号に関するコードを、コード読取り手段にて読み取る
ことにより、前記管理制御部に入力する工程と、を包含
することを特徴とする。
A work process management method according to the present invention relates to a management control unit that manages work processes required for manufacturing a product together with a lot number of each product to be manufactured. The process of inputting the information on the work process necessary for manufacturing the product by assigning a lot number to each product, and the information on the work process and the product lot number input to the management control unit are one-dimensional or two-dimensional. By a process of creating a work instruction sheet displayed as a dimension code and performing a predetermined work in the work step, the code relating to the work and the code relating to the lot number in the work instruction sheet are read by the code reading means. And a step of inputting to the management control unit.

【0007】前記管理制御部は、前記コード読取り手段
によって読み取られた作業工程に関する情報を、その情
報が読み取られた日付とともに管理する。
The management control unit manages the information about the work process read by the code reading means together with the date when the information was read.

【0008】[0008]

【発明の実施の形態】以下、本発明の実施の形態を図面
に基づいて説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings.

【0009】図1は、本発明の作業工程管理方法の実施
に使用される作業管理システムの一例を示す概略構成図
である。この作業管理システムは、例えば、半導体ウエ
ハを研磨する際に使用する研磨パッドの製造ラインに使
用される。研磨パッドは、支持層上に表面層が積層され
て構成されており、表面層は、多孔性のウレタン樹脂ま
たはポリウレタン樹脂に、ウレタン樹脂を、多孔性を維
持しつつ含浸させることにより形成されている。支持層
は、比較的曲げやすいが、伸縮性が小さい材料によって
構成されている。
FIG. 1 is a schematic configuration diagram showing an example of a work management system used for implementing the work process management method of the present invention. This work management system is used, for example, in a production line of a polishing pad used when polishing a semiconductor wafer. The polishing pad is configured by laminating a surface layer on a support layer, and the surface layer is formed by impregnating a porous urethane resin or polyurethane resin with the urethane resin while maintaining the porosity. There is. The support layer is made of a material that is relatively bendable but has low elasticity.

【0010】この作業管理システムには、CPU(中央
処理装置)11と、プログラム、データ等が記憶された
RAM12およびROM13と、各種情報を入力するキ
ーボード等の入力手段15と、各種情報を表示する表示
手段14と、各種情報を記録紙にプリントするプリンタ
16とを有する管理制御部10が設けられている。この
管理制御部10は、通常のコンピュータシステムによっ
て構成されている。また、管理制御部10のCPU11
には、複数のバーコード読取り手段17が接続されてい
る。各バーコード読取り手段17は、製造ラインにおけ
る各作業工程が実施される作業所にそれぞれ配置されて
いる。
This work management system displays a CPU (central processing unit) 11, a RAM 12 and a ROM 13 in which programs, data and the like are stored, an input means 15 such as a keyboard for inputting various information, and various information. A management control unit 10 having a display unit 14 and a printer 16 for printing various kinds of information on recording paper is provided. The management control unit 10 is composed of a normal computer system. Further, the CPU 11 of the management control unit 10
A plurality of bar code reading means 17 is connected to. Each bar code reading means 17 is arranged at a work place where each work process is performed in the manufacturing line.

【0011】管理制御部10のCPU11は、入力手段
15にて入力される各種情報に基づいて、作業指示書を
作成する。
The CPU 11 of the management control unit 10 creates a work instruction sheet based on various information input by the input means 15.

【0012】CPU11には、製品である研磨パッドの
仕様が記載された受注伝票に基づいて、製造に必要な作
業に関する情報が入力される。この場合、まず、受注伝
票に記載された研磨パッドの仕様に基づいて、製造され
る各研磨パッドのロット番号が、製造される各製品毎に
それぞれ設定されて、入力手段15によってそれぞれC
PU11に入力される。そして、受注伝票に基づいて、
各ロット番号がそれぞれ設定された製品である各研磨パ
ッド毎に、必要な各作業工程がそれぞれ設定されて、設
定された各作業工程に関する情報が、入力手段15によ
ってCPU11に入力される。
Information on work required for manufacturing is input to the CPU 11 based on an order receipt in which specifications of a polishing pad, which is a product, are described. In this case, first, the lot number of each polishing pad to be manufactured is set for each product to be manufactured based on the specifications of the polishing pad described in the order receipt, and C is input by the input means 15 respectively.
It is input to PU11. And based on the order receipt,
The necessary work steps are set for each polishing pad, which is a product for which each lot number is set, and the information about each set work step is input to the CPU 11 by the input means 15.

【0013】研磨パッドの製造に際して必要とされる各
作業工程としては、例えば、支持層の切り出し工程と、
切り出された支持層に表面層を貼り付ける貼り付け工程
と、支持層に貼り付けられた表面層を加工する加工工程
とがあり、これらの各作業工程が、ロット番号が付与さ
れた製品毎にそれぞれ設定される。そして、製造された
製品を出荷する出荷工程も、作業工程として各製品毎に
設定される。
The working steps required for manufacturing the polishing pad include, for example, a step of cutting the support layer,
There is a sticking step of sticking the surface layer to the cut support layer, and a processing step of processing the surface layer stuck to the support layer, and each of these working steps is performed for each product to which a lot number is given. Each is set. The shipping process for shipping the manufactured product is also set for each product as a work process.

【0014】この場合、各製品毎に指定される各作業工
程の情報は、9桁の数字によって設定され、1つの製品
に対して設定される各作業工程が連続した番号とされ
る。この場合、各作業工程毎に、各作業を実施する予定
の日付である計画日付と、その計画日付において各作業
工程での作業処理する予定の部品の個数である計画数量
とが、それぞれ、設定されて、入力手段15によってC
PU11に入力される。
In this case, the information of each work process designated for each product is set by a 9-digit number, and each work process set for one product is a continuous number. In this case, for each work process, the planned date, which is the date on which each work is scheduled to be performed, and the planned quantity, which is the number of parts to be processed in each work process on that planned date, are set. Then, by the input means 15, C
It is input to PU11.

【0015】図2は、このようにして設定される作業計
画を示す作業計画表である。作業計画表には、図2に示
すように、各作業工程毎に、それぞれの作業工程を示す
番号と、その作業工程を実施する計画日付と、その計画
日付において処理する部品数である計画数量とがそれぞ
れ入力される欄が設けられている。なお、この作業計画
表には、各作業工程毎に、実際に作業が実施された日付
および数量の実績を示す欄も設けられている。
FIG. 2 is a work plan table showing the work plan set in this way. In the work plan table, as shown in FIG. 2, for each work process, a number indicating each work process, a planned date for implementing the work process, and a planned quantity that is the number of parts to be processed on the planned date. There are fields for entering and respectively. The work plan table also has columns for each work process, which indicate the actual date of work and the actual quantity.

【0016】図2に示す例では、切り出し工程を実施す
る予定の計画日付として5月15日、その切り出し工程
を実施する予定の計画数量として100個が設定されて
いる。また、貼り付け工程を実施する予定の計画日付が
5月15日、その貼り付け工程を実施する予定の計画数
量として95個が設定されている。同様に、加工工程を
実施する予定の計画日付として5月20日、その加工工
程を実施する予定の計画数量として90個が設定され、
さらに、出荷工程を実施する予定の計画日付として5月
21日、その出荷工程を実施する予定の計画数量として
90個が設定されている。
In the example shown in FIG. 2, May 15 is set as the planned date for carrying out the cutting process, and 100 pieces are set as the planned quantity for carrying out the cutting process. Further, the planned date for carrying out the attaching process is May 15, and 95 pieces are set as the planned quantity for carrying out the attaching process. Similarly, May 20 is set as the planned date for carrying out the machining process, and 90 pieces are set as the planned quantity for carrying out the machining process.
Further, May 21 is set as the planned date for carrying out the shipping process, and 90 pieces are set as the planned quantity for carrying out the shipping process.

【0017】このようにして、各作業工程毎の計画が設
定されると、設定された各作業工程、計画日付、計画数
量が、ROM13に記憶されるとともに、各製品毎に、
作業指示書がそれぞれ作成されてプリントアウトされ
る。
When the plan for each work process is set in this manner, the set work process, the planned date, and the planned quantity are stored in the ROM 13 and also for each product.
Work instructions are created and printed out.

【0018】図3は、この場合に作成される作業指示書
の一例を示している。作成される作業指示書20には、
各製品固有のロット番号を、バーコード21にて表示さ
れている。そして、その製品に対して必要とされる各作
業工程における情報を示す番号も、それぞれバーコード
22〜25にて表示される。この場合、ロット番号が付
与された製品に対する各作業工程に関する情報の番号
は、連番になっている。
FIG. 3 shows an example of the work instruction document created in this case. The created work instruction sheet 20 includes
The lot number unique to each product is displayed by the barcode 21. Then, the numbers indicating the information in each work process required for the product are also displayed by the barcodes 22 to 25, respectively. In this case, the information numbers related to the respective work processes for the products to which the lot numbers are given are serial numbers.

【0019】このようにして、各製品毎に、ロット番号
が付与された作業指示書が作成されてプリントアウトさ
れると、プリントアウトされた作業指示書は、製品とさ
れる部品とともに、所定の製造ラインに供給され、製造
ラインにおいて、作業指示書の指示にしたがって、各作
業工程が実施される。
In this way, when a work instruction sheet to which a lot number has been added is created and printed out for each product, the printed work instruction sheet, together with the parts to be the products, has a predetermined size. It is supplied to the production line, and each work process is carried out in the production line according to the instructions in the work instruction sheet.

【0020】製造ラインにおいては、各作業工程毎に、
バーコード読取り手段17が設けられており、部品およ
び作業指示書20が供給されることにより、作業指示書
に記載された所定の作業が実施される。
In the production line, for each work process,
The bar code reading means 17 is provided, and by supplying the parts and the work instruction sheet 20, the predetermined work described in the work instruction sheet is performed.

【0021】研磨パッドの製造ラインにおいては、ま
ず、支持層の切り出し作業が実施される。そして、切り
出し作業によって所定の支持層が切り出されると、作業
指示書20における製品のロット番号を表示するバーコ
ード21を、バーコード読取り手段17によって読み取
るとともに、実施された切り出し作業に関するバーコー
ド22をバーコード読取り手段17にて読み取る。そし
て、切り出された支持層とともに作業指示書20が次の
作業工程に供給される。
In the polishing pad production line, first, the work of cutting out the support layer is carried out. Then, when the predetermined support layer is cut out by the cutting out work, the bar code 21 indicating the lot number of the product in the work instruction sheet 20 is read by the bar code reading means 17, and the bar code 22 concerning the executed cutting out work is read. It is read by the bar code reading means 17. Then, the work instruction sheet 20 is supplied to the next work process together with the cut support layer.

【0022】次の作業工程では、支持層に対して表面層
が貼り付けられる。この作業が終了すると、作業指示書
20における製品のロット番号を表示するバーコード2
1を、バーコード読取り手段17によって読み取るとと
もに、実施された貼り付け作業に関するバーコード23
をバーコード読取り手段17にて読み取る。そして、表
面層が貼り付けられた支持層とともに作業指示書20が
次の作業工程に供給される。
In the next working step, the surface layer is attached to the support layer. When this work is completed, the bar code 2 displaying the lot number of the product in the work instruction sheet 20.
1 is read by the bar code reading means 17, and the bar code 23 relating to the pasting work performed is performed.
Is read by the barcode reading means 17. Then, the work instruction sheet 20 is supplied to the next work step together with the support layer to which the surface layer is attached.

【0023】次の作業工程では、支持層に貼り付けられ
た表面層が加工されて研磨パッドとされる。この作業が
終了すると、作業指示書20における製品のロット番号
を表示するバーコード21を、バーコード読取り手段1
7によって読み取るとともに、実施された加工作業に関
するバーコード24をバーコード読取り手段17にて読
み取る。そして、製造された研磨パッドが、作業指示書
20が次の作業工程に供給される。
In the next working step, the surface layer attached to the support layer is processed into a polishing pad. When this work is completed, the bar code 21 indicating the lot number of the product in the work instruction sheet 20 is replaced with the bar code reading means 1.
The bar code 24 is read by the bar code reading means 17 as well as the bar code 24 related to the processing operation performed. Then, the work instruction sheet 20 of the manufactured polishing pad is supplied to the next work process.

【0024】最後に、製造された研磨パッドが、出荷さ
れる。出荷作業が終了すると、作業指示書20における
製品のロット番号を表示するバーコード21を、バーコ
ード読取り手段17によって読み取るとともに、出荷作
業に関するバーコード25をバーコード読取り手段17
にて読み取る。
Finally, the manufactured polishing pad is shipped. When the shipping work is completed, the bar code 21 indicating the lot number of the product in the work instruction sheet 20 is read by the bar code reading means 17, and the bar code 25 relating to the shipping work is read by the bar code reading means 17.
Read at.

【0025】このようにして、バーコード読取り手段1
7にて、作業指示書20における製品のロット番号を表
示するバーコード21と、各作業工程における作業に関
するバーコード22〜25とがそれぞれ読み取られる
と、CPU11は、各バーコード21〜25が読み取ら
れた日付とともに、その日付における各作業工程におい
てそれぞれ所定の作業が実施された部品の数量を集計し
て、図2に示す計画表の実績欄に入力する。
In this way, the bar code reading means 1
7, the bar code 21 for displaying the lot number of the product in the work instruction sheet 20 and the bar codes 22 to 25 related to the work in each work process are read, and the CPU 11 reads the bar codes 21 to 25. Along with the date, the quantity of the parts on which the predetermined work has been performed in each work process on that date is totaled and input into the actual result column of the plan table shown in FIG.

【0026】このように、各製品毎に作成された作業指
示書20には、ロット番号および各作業工程において実
施される作業内容を、バーコード21〜25にて表示し
ているために、各作業工程において、ロット番号および
作業内容を、バーコード読取り手段17にて読み取るだ
けで、ロット番号および各作業工程における作業内容を
管理することができる。従って、各作業工程における作
業の進捗状況を容易に把握することができる。
As described above, since the work instruction sheet 20 prepared for each product displays the lot number and the work content to be executed in each work step by the bar codes 21 to 25, In the work process, the lot number and the work content in each work process can be managed only by reading the lot number and the work content with the barcode reading means 17. Therefore, it is possible to easily grasp the progress status of the work in each work process.

【0027】また、バーコード読取り手段17によって
読取られた情報が、作業計画表の実績欄に入力されるた
めに、各作業行程における作業の実績が、逐次、集計さ
れる。従って、各作業工程における作業実績を、リアル
タイムで把握することができ、各作業工程における歩留
まり、生産能力等を容易に改善することができる。
Further, since the information read by the bar code reading means 17 is input to the actual result column of the work plan table, the actual results of the work in each work process are sequentially added up. Therefore, the work record in each work process can be grasped in real time, and the yield, the production capacity, etc. in each work process can be easily improved.

【0028】さらには、出荷された製品のロット番号に
基づいて、製造時の各作業工程に関するデータを取得す
ることができる。
Further, based on the lot number of the shipped product, it is possible to acquire data regarding each work process at the time of manufacturing.

【0029】[0029]

【発明の効果】本発明の作業工程管理方法は、このよう
に、各製品毎に実施される作業工程を、容易に、しか
も、確実に管理することができる。
As described above, the work process management method of the present invention can easily and reliably manage the work process performed for each product.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の作業工程管理方法の実施に使用される
管理システムの一例を示す概略構成図である。
FIG. 1 is a schematic configuration diagram showing an example of a management system used for implementing a work process management method of the present invention.

【図2】その管理システムの管理制御部に設定される計
画表である。
FIG. 2 is a plan table set in a management control unit of the management system.

【図3】管理制御部によって作成される作業指示書であ
る。
FIG. 3 is a work instruction document created by a management control unit.

【符号の説明】[Explanation of symbols]

10 管理制御部 11 CPU 12 RAM 13 ROM 14 表示手段 15 入力手段 16 プリンタ 17 バーコード読取り手段 20 作業指示書 21〜25 バーコード 10 Management control unit 11 CPU 12 RAM 13 ROM 14 Display means 15 Input means 16 Printer 17 Bar code reading means 20 work instructions 21-25 barcode

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 製品を製造するために必要な作業工程
を、製造される各製品のロット番号とともに管理する管
理制御部に対して、各製品を製造するために必要な作業
工程に関する情報を各製品毎にロット番号を付与してそ
れぞれ入力する工程と、 管理制御部に入力された作業工程に関する情報および製
品のロット番号を、1次元または2次元コードとして表
示された作業指示書を作成する工程と、 作業工程において所定の作業が実施されることにより、
作業指示書におけるその作業に関するコードおよびロッ
ト番号に関するコードを、コード読取り手段にて読み取
ることにより、前記管理制御部に入力する工程と、 を包含することを特徴とする作業工程管理方法。
1. A management control unit that manages the work process required to manufacture a product together with the lot number of each product to be manufactured, and provides information about the work process necessary to manufacture each product to a management control unit. A process of assigning a lot number to each product and inputting it, and a process of creating a work instruction sheet in which the information about the work process input to the management control unit and the lot number of the product are displayed as a one-dimensional or two-dimensional code. And by performing a predetermined work in the work process,
A step of inputting the code relating to the work and the code relating to the lot number in the work instruction sheet to the management control section by reading the code with a code reading means.
【請求項2】 前記管理制御部は、前記コード読取り手
段によって読み取られた作業工程に関する情報を、その
情報が読み取られた日付とともに管理する請求項1に記
載の作業管理方法。
2. The work management method according to claim 1, wherein the management control unit manages the information about the work process read by the code reading unit together with the date when the information was read.
JP2001212916A 2001-07-12 2001-07-12 Operation process controlling method Withdrawn JP2003030393A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001212916A JP2003030393A (en) 2001-07-12 2001-07-12 Operation process controlling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001212916A JP2003030393A (en) 2001-07-12 2001-07-12 Operation process controlling method

Publications (1)

Publication Number Publication Date
JP2003030393A true JP2003030393A (en) 2003-01-31

Family

ID=19047988

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001212916A Withdrawn JP2003030393A (en) 2001-07-12 2001-07-12 Operation process controlling method

Country Status (1)

Country Link
JP (1) JP2003030393A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008250792A (en) * 2007-03-30 2008-10-16 Hitachi Ltd Work process management system
KR101935849B1 (en) * 2018-07-30 2019-04-03 채민석 Method for controlling textile machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008250792A (en) * 2007-03-30 2008-10-16 Hitachi Ltd Work process management system
KR101935849B1 (en) * 2018-07-30 2019-04-03 채민석 Method for controlling textile machine

Similar Documents

Publication Publication Date Title
US7857221B2 (en) RFID tag system
CA2361778A1 (en) Quilt making automatic scheduling system and method
JP5018641B2 (en) Production management system and production management method
JP2006039903A (en) System for using work instruction with ic tag
JP2003030393A (en) Operation process controlling method
EP3392810A1 (en) Method for elaborating work orders to be executed by a mes/mom system
JPH05323875A (en) Label for management of form for concrete
JP3208096B2 (en) Automatic machining system by bar code
KR101215597B1 (en) Method for production of spool
JP2001315920A (en) Control tag, control system and controlling method
JP3090612B2 (en) production management system
JP2006113903A (en) Manufacturing system
JPH1166157A (en) Production process control system
JP5212221B2 (en) Planning device, planning method and planning program
JPH02278308A (en) Product arrangement controller
JPH04275667A (en) Metal die managing method, metal die, metal die using device and metal die managing system
JP4794744B2 (en) Material processing management system
JPH07334569A (en) Process control method and device therefor
WO2023204090A1 (en) Location management device, location management system, and location management method
JP4724292B2 (en) Unit staircase processing system and method
JP3002718B2 (en) Work progress management method
JP2674333B2 (en) Semiconductor device manufacturing history collection system
JP4551812B2 (en) External setup device for parts supply equipment
JP2017126228A (en) Production plan creation method considering divertability of intermediate item
JP2004195615A (en) Work indication system

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20081007