JP2003027415A - PCa GIRDER CONNECTING METHOD AND BRIDGE FALL PREVENTING METHOD - Google Patents
PCa GIRDER CONNECTING METHOD AND BRIDGE FALL PREVENTING METHODInfo
- Publication number
- JP2003027415A JP2003027415A JP2001213684A JP2001213684A JP2003027415A JP 2003027415 A JP2003027415 A JP 2003027415A JP 2001213684 A JP2001213684 A JP 2001213684A JP 2001213684 A JP2001213684 A JP 2001213684A JP 2003027415 A JP2003027415 A JP 2003027415A
- Authority
- JP
- Japan
- Prior art keywords
- pca
- girders
- girder
- tension
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、PCa(プレキャ
ストコンクリート)桁の連結方法及び落橋防止方法に関
する。本発明においてPCa桁とは、プレキャスト鉄筋
コンクリート桁、プレキャストプレストレストコンクリ
ート桁を含む。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for connecting PCa (precast concrete) girders and a method for preventing bridge collapse. In the present invention, the PCa girder includes a precast reinforced concrete girder and a precast prestressed concrete girder.
【0002】[0002]
【従来の技術】コンクリート構造物の桟橋などにおける
連結部では、PCa桁を受梁に剛結する技術として、受
梁から突出した鉄筋と桁端部から突出した鉄筋を現場で
組合せ、その連結部にコンクリートを打設することによ
り、鉄筋コンクリート構造とするものがある。このよう
な場合では、PCa桁端部から突出した鉄筋は、太径で
かつその配置間隔も密なものであり、連結部の鉄筋組み
の作業スペースがあまり無いために、大変な労力を要す
るという問題がある。2. Description of the Related Art As a technique for rigidly connecting a PCa girder to a receiving beam at a connecting portion of a pier or the like of a concrete structure, a reinforcing bar protruding from the receiving beam and a reinforcing bar protruding from the end of the girder are combined on site and the connecting portion is There is a reinforced concrete structure in which concrete is poured into. In such a case, the reinforcing bars protruding from the end of the PCa girder have a large diameter and are closely arranged, and there is not much working space for the reinforcing bar assembly at the connecting portion, which requires a great deal of labor. There's a problem.
【0003】[0003]
【発明が解決しようとする課題】PCa桁を連結するた
めに、上述のような技術があるが、鉄筋が輻輳している
ことから、労力を要し、作業性に劣る。従ってPCa桁
を容易にしかも確実に連結する技術が望まれている。There are the above-mentioned techniques for connecting PCa girders, but since the reinforcing bars are congested, it requires labor and is inferior in workability. Therefore, a technique for easily and surely connecting PCa digits is desired.
【0004】本発明は、上記問題を解決することを目的
とし、PC鋼材をPCa桁の連結部に配置することによ
って、連結を容易に、しかも確実にしたPCa桁の連結
方法及び落橋防止方法を提供する。また本発明は、PC
鋼材を複数スパンの上部工全体に亘って配置し、連結部
の結合を容易にかつ確実にし、さらに連結部が損傷する
ような異常時においてもPCa桁が受梁から落橋するこ
とがないようにすることを目的とする。An object of the present invention is to solve the above problems by providing a PCa girder connecting method and a bridge preventing method by arranging a PC steel material at a PCa girder connecting portion so that the connection is easy and reliable. provide. In addition, the present invention is a PC
By arranging steel materials over the entire superstructure of multiple spans, the connection of the connecting parts can be made easy and reliable, and the PCa girder will not fall from the receiving beam even in the case of an abnormality such as damage to the connecting parts. The purpose is to do.
【0005】[0005]
【課題を解決するための手段】本発明は、上記問題を解
決するためになされたものであって、PCa桁を容易に
連結するための方法であり、第1の発明は、連続したP
C床版工の支承部上で、PCa桁相互間及び/又は間詰
め相互間にPC鋼材を緊張又は非緊張で配置したことを
特徴とするPCa桁の連結方法である。間詰めとは、橋
幅方向に隣接する桁同士を一体化させるために桁の間に
充填した縦目地コンクリートを言う。桁相互又は間詰め
相互とは、支承部上で橋軸方向に隣接する桁又は間詰め
相互を言う。The present invention has been made to solve the above problems, and is a method for easily connecting PCa digits, and the first invention is a continuous P method.
A method for connecting PCa girders, characterized in that PC steel girders are arranged in a tensioned or non-tensioned manner between the PCa girders and / or between the PCa girders on the bearing of the C floor slab. Space-filling refers to vertical joint concrete filled between girders in order to integrate girders that are adjacent in the bridge width direction. The mutual girders or the mutual packings are the girders or the packing mutuals that are adjacent to each other in the bridge axial direction on the support portion.
【0006】次に本発明の第2の発明は、PC鋼材を複
数の上部工を貫通して使用することを特徴とする方法で
あって、床版工の複数スパンに亘るPCa桁中及び/又
は間詰め中に、PC鋼材を連続的に緊張又は非緊張で配
置したことを特徴とするPCa桁の連結方法である。Next, a second invention of the present invention is a method characterized in that a PC steel material is used by penetrating a plurality of superstructures, and in a PCa girder spanning a plurality of spans of a floor slab and / or Alternatively, the PCa girder connecting method is characterized in that the PC steel materials are continuously arranged in a tensioned state or a non-tensed state during the filling.
【0007】さらに、本発明の第3の発明は、地震等の
異常時においてもPCa桁が落橋をしないようにするた
めの方法であり、連続した床版工の支承部上で、PCa
桁相互間及び/又は間詰め相互間にPC鋼材を緊張又は
非緊張で配置し、PCa桁が支承部から落橋するのを防
止することを特徴とする落橋防止方法である。また本発
明の第4の発明は、床版工の複数スパンに亘るPCa桁
中及び/又は間詰め中に、PC鋼材を連続的に緊張又は
非緊張で配置し、PCa桁が支承部から落橋するのを防
止することを特徴とする落橋防止方法を提供する。Further, a third aspect of the present invention is a method for preventing the PCa girder from falling over even in the event of an abnormality such as an earthquake.
A method of preventing a bridge from falling down, characterized in that PC steel members are arranged with tension or non-tension between the girders and / or between the girders to prevent the PCa girder from falling from the support portion. A fourth invention of the present invention is to arrange PC steel material continuously or without tension during PCa girder and / or padding over a plurality of spans of a floor slab, and the PCa girder is bridged from the bearing portion. There is provided a method of preventing a bridge from falling, which is characterized by preventing the bridge from falling.
【0008】なお、本発明において、上記第1、第2の
発明を同時に施工してもよく、また上記第3、第4の発
明を同時に施工してもよい。In the present invention, the first and second inventions may be applied simultaneously, and the third and fourth inventions may be applied simultaneously.
【0009】[0009]
【発明の実施の形態】以下、図面を参照して本発明の実
施の形態を説明する。図2は従来のPCa桁1の端部の
断面図であり、図5は従来の支承部5上における桁1の
連結を示す縦断面図である。桁1はプレテンション方式
のPC鋼材7を内蔵したPCa桁である。支承部5上に
おいて、図2、5に示されるように、桁1の連結部には
桁同士及び間詰め同士間に太径の多数の鉄筋2が密に配
置され、現場打ちコンクリート6が打設されている。BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings. FIG. 2 is a sectional view of an end portion of a conventional PCa girder 1, and FIG. 5 is a vertical sectional view showing the connection of the girder 1 on the conventional bearing 5. The girder 1 is a PCa girder containing a pre-tensioned PC steel material 7. As shown in FIGS. 2 and 5, on the support portion 5, a large number of large-diameter reinforcing bars 2 are densely arranged between the girders and the gaps between the girders 1 as shown in FIGS. It is set up.
【0010】図1は本発明の実施例を示すPCa桁端部
の断面図、図3、図4は本発明の実施例の支承部上にお
ける桁の連結を示す縦断面図で、図3は図1のA矢視断
面図、図4は図1のB矢視断面図である。本発明による
と、図1に示すように、PCa桁1の断面あるいは桁1
相互間の間詰め4にPC鋼材3を配置する。従って、P
Ca桁1の端部に配置される鉄筋2の本数は減少し、そ
の径も従来のものよりは細くすることができ、場合によ
っては、鉄筋2は不要となる。図3は本発明におけるP
Ca桁1が支承部5上で現場コンクリート6を打設して
接続部分にPC鋼材3を配置した例である。このPC鋼
材3は両方の桁1にそれぞれ定着部8を有し、緊張定着
されるか又は非緊張で配設される。図4はPC鋼材3が
間詰め4中に配置された状態を示すものである。PC鋼
材3はもちろん、PCa桁1同士及び間詰め4同士の両
方に配置してもよい。本発明の図1では従来の図2に比
べ、鉄筋を大幅に減少させることができる。FIG. 1 is a sectional view of a PCa girder end portion showing an embodiment of the present invention, and FIGS. 3 and 4 are vertical sectional views showing connection of girders on a bearing portion of the embodiment of the present invention. 1 is a sectional view taken along the arrow A in FIG. 1, and FIG. 4 is a sectional view taken along the arrow B in FIG. According to the present invention, as shown in FIG. 1, the cross section of the PCa girder 1 or the girder 1
The PC steel material 3 is arranged in the space 4 between the two. Therefore, P
The number of the reinforcing bars 2 arranged at the end of the Ca girder 1 is reduced, and the diameter thereof can be made smaller than that of the conventional one. In some cases, the reinforcing bars 2 are unnecessary. FIG. 3 shows P in the present invention.
The Ca girder 1 is an example in which on-site concrete 6 is cast on the support portion 5 and the PC steel material 3 is arranged at the connecting portion. The PC steel material 3 has fixing portions 8 on both the girders 1 and is either tension-fixed or non-tensioned. FIG. 4 shows a state in which the PC steel material 3 is arranged in the padding 4. Not only the PC steel material 3 but also the PCa girders 1 and the paddings 4 may be arranged. In FIG. 1 of the present invention, the reinforcing bars can be significantly reduced as compared with the conventional FIG.
【0011】なお、図1、図3、図4に示すPC鋼材3
は、緊張して設置してもよく、非緊張のままとしておい
てもよい。この構造は落橋防止方法として有効に作用す
る。The PC steel material 3 shown in FIGS. 1, 3 and 4 is used.
May be placed under tension or may remain untensed. This structure works effectively as a method for preventing bridge collapse.
【0012】次に本発明の別の実施例を示す縦断面を図
6に示した。図7は図6に対応する従来の桁の連結を示
す縦断面図である。従来は受梁5上で鉄筋2を配置とし
て隣接する桁同士を連結していた。本発明では、基礎杭
9上に受梁5を備えた複数スパンの桁1からなる橋梁の
上部工全体に、PC鋼材3を連続的に配置したので、P
Ca桁1にあらかじめ配置されるPC鋼材も減少させる
ことができる。また、図6に示すように、PC鋼材3を
複数スパンの桁1に対して、連続的に緊張又は非緊張で
配置し、PCa桁が支承部5から落橋するのを防止する
ことができる。Next, FIG. 6 shows a vertical cross section showing another embodiment of the present invention. FIG. 7 is a vertical cross-sectional view showing connection of a conventional girder corresponding to FIG. Conventionally, the reinforcing bars 2 are arranged on the receiving beam 5 to connect adjacent girders. In the present invention, since the PC steel material 3 is continuously arranged over the entire superstructure of the bridge composed of the girders 1 having a plurality of spans and provided with the receiving beam 5 on the foundation pile 9,
It is also possible to reduce the PC steel material that is previously arranged on the Ca girder 1. Further, as shown in FIG. 6, the PC steel material 3 can be continuously arranged in tension or non-tension with respect to the girder 1 having a plurality of spans to prevent the PCa girder from falling from the support portion 5.
【0013】[0013]
【発明の効果】本発明によれば、PCa桁の橋軸方向の
連結を簡単にかつ確実に行うことができる。また、地震
等の異常時においても、落橋を確実に防止することがで
きるというすぐれた効果を奏する。According to the present invention, PCa girders can be easily and reliably connected in the bridge axis direction. In addition, it has an excellent effect that it is possible to surely prevent a fall bridge even in the case of an abnormality such as an earthquake.
【図1】実施例の桁の横断面図である。FIG. 1 is a cross-sectional view of a girder according to an embodiment.
【図2】従来の桁の横断面図である。FIG. 2 is a cross-sectional view of a conventional girder.
【図3】実施例の桁の縦断面図(図1のA矢視図)であ
る。FIG. 3 is a vertical cross-sectional view of the girder of the embodiment (a view as seen from an arrow A in FIG. 1).
【図4】実施例の桁の縦断面図(図1のB矢視図)であ
る。FIG. 4 is a vertical cross-sectional view of the girder of the embodiment (a view from the arrow B in FIG. 1).
【図5】従来の桁の縦断面図である。FIG. 5 is a vertical cross-sectional view of a conventional girder.
【図6】実施例の桁の縦断面図である。FIG. 6 is a vertical cross-sectional view of the girder of the embodiment.
【図7】従来の桁の縦断面図である。FIG. 7 is a vertical cross-sectional view of a conventional girder.
1 PCa桁 2 鉄筋 3 PC鋼材 4 間詰め 5 受梁 6 現場打コンクリート 7 PC鋼材 8 定着部 9 基礎杭 1 PCa digit 2 rebar 3 PC steel 4 stuffing 5 Receiving beam 6 cast-in-place concrete 7 PC steel 8 fixing section 9 foundation piles
─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───
【手続補正書】[Procedure amendment]
【提出日】平成14年7月24日(2002.7.2
4)[Submission date] July 24, 2002 (2002.7.2)
4)
【手続補正1】[Procedure Amendment 1]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】0012[Correction target item name] 0012
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【0012】次に本発明の別の実施例を示す縦断面を図
6に示した。図7は図6に対応する従来の桁の連結を示
す縦断面図である。従来は受梁5上で鉄筋2を配置して
隣接する桁同士を連結していた。本発明では、基礎杭9
上に受梁5を備えた複数スパンの桁1からなる橋梁の上
部工全体に、PC鋼材3を連続的に配置したので、PC
a桁1にあらかじめ配置されるPC鋼材も減少させるこ
とができる。また、図6に示すように、PC鋼材3を複
数スパンの桁1に対して、連続的に緊張又は非緊張で配
置し、PCa桁が支承部5から落橋するのを防止するこ
とができる。Next, FIG. 6 shows a vertical cross section showing another embodiment of the present invention. FIG. 7 is a vertical cross-sectional view showing connection of a conventional girder corresponding to FIG. Conventionally, not consolidate digits that are adjacent to place the reinforcing bars 2 on the receiving beam 5. In the present invention, the foundation pile 9
Since the PC steel material 3 was continuously arranged over the entire superstructure of the bridge composed of the girders 1 having a plurality of spans with the receiving beam 5 above,
It is also possible to reduce the PC steel material pre-arranged on the a-digit 1. Further, as shown in FIG. 6, the PC steel material 3 can be arranged continuously or tautly with respect to the girder 1 having a plurality of spans to prevent the PCa girder from falling from the support portion 5.
【手続補正2】[Procedure Amendment 2]
【補正対象書類名】明細書[Document name to be amended] Statement
【補正対象項目名】符号の説明[Correction target item name] Explanation of code
【補正方法】変更[Correction method] Change
【補正内容】[Correction content]
【符号の説明】 1 PCa桁 2 鉄筋 3 PC鋼材 4 間詰め 5 支承部(受梁) 6 現場打コンクリート 7 PC鋼材 8 定着部 9 基礎杭[Explanation of symbols] 1 PCa girder 2 Reinforcing bar 3 PC steel 4 Packing 5 Support part (support beam) 6 Cast concrete 7 PC steel 8 Anchorage 9 Foundation pile
───────────────────────────────────────────────────── フロントページの続き (72)発明者 石田 邦洋 東京都千代田区丸の内3丁目4番1号 株 式会社ピー・エス内 Fターム(参考) 2D059 AA03 AA05 AA14 BB35 BB37 BB39 GG01 GG05 GG30 GG55 ─────────────────────────────────────────────────── ─── Continued front page (72) Inventor Kunihiro Ishida Marunouchi 3-4-1 shares, Chiyoda-ku, Tokyo Ceremony Company PS F term (reference) 2D059 AA03 AA05 AA14 BB35 BB37 BB39 GG01 GG05 GG30 GG55
Claims (4)
相互間及び/又は間詰め相互間にPC鋼材を緊張又は非
緊張で配置したことを特徴とするPCa桁の連結方法。1. A method for connecting PCa girders, characterized in that PC steel members are arranged with tension or no tension between PCa girders and / or between packed PCa girders on a continuous bearing part of a floor slab.
び/又は間詰め中に、PC鋼材を連続的に緊張又は非緊
張で配置したことを特徴とするPCa桁の連結方法。2. A method for connecting PCa girders, characterized in that PC steel materials are continuously arranged in a tensioned state or a non-tensed state in PCa girders spanning a plurality of spans of a floor slab and / or during packing.
相互間及び/又は間詰め相互間にPC鋼材を緊張又は非
緊張で配置し、PCa桁が支承部から落橋するのを防止
することを特徴とする落橋防止方法。3. A PC steel girder is arranged with tension or non-tension between PCa girders and / or between stuffed PCa girders on a continuous floor slab bearing to prevent the PCa girder from falling from the bearing. A method of preventing a fall of a bridge characterized by:
び/又は間詰め中に、PC鋼材を連続的に緊張又は非緊
張で配置し、PCa桁が支承部から落橋するのを防止す
ることを特徴とする落橋防止方法。4. A PC steel girder is continuously tensioned or non-tensioned during PCa girder spanning multiple spans and / or padding of a floor slab to prevent the PCa girder from falling from the bearing. A method of preventing a bridge from falling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001213684A JP2003027415A (en) | 2001-07-13 | 2001-07-13 | PCa GIRDER CONNECTING METHOD AND BRIDGE FALL PREVENTING METHOD |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001213684A JP2003027415A (en) | 2001-07-13 | 2001-07-13 | PCa GIRDER CONNECTING METHOD AND BRIDGE FALL PREVENTING METHOD |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2003027415A true JP2003027415A (en) | 2003-01-29 |
Family
ID=19048621
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001213684A Pending JP2003027415A (en) | 2001-07-13 | 2001-07-13 | PCa GIRDER CONNECTING METHOD AND BRIDGE FALL PREVENTING METHOD |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2003027415A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007032212A (en) * | 2005-07-29 | 2007-02-08 | Taisei Corp | Ribbed floor slab and on-water structure |
JP2008014083A (en) * | 2006-07-07 | 2008-01-24 | Nippon Ps:Kk | Construction method of pier |
JP2009079428A (en) * | 2007-09-26 | 2009-04-16 | Kajima Corp | Joint method of concrete members and manufacturing method of floor slab for prestressed concrete bridge |
JP5291843B1 (en) * | 2013-02-26 | 2013-09-18 | 朝日エンヂニヤリング株式会社 | Girder bridge reinforcement structure |
JP2014062403A (en) * | 2012-09-21 | 2014-04-10 | Kitagawa Kogyo Co Ltd | Bridge girder and construction method of bridge girder |
JP2016194223A (en) * | 2015-04-01 | 2016-11-17 | 鹿島建設株式会社 | Method for introducing pre-stress to cast-in-place concrete |
WO2019038989A1 (en) * | 2017-08-25 | 2019-02-28 | 住友電工スチールワイヤー株式会社 | Concrete structure and method for manufacturing same |
CN109610315A (en) * | 2018-12-26 | 2019-04-12 | 北京工业大学 | The dry joint connecting structure of prefabrication and assembly construction floorings and implementation method |
JP2021063378A (en) * | 2019-10-15 | 2021-04-22 | 三井住友建設株式会社 | Concrete floor slab and concrete floor slab forming method |
-
2001
- 2001-07-13 JP JP2001213684A patent/JP2003027415A/en active Pending
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007032212A (en) * | 2005-07-29 | 2007-02-08 | Taisei Corp | Ribbed floor slab and on-water structure |
JP2008014083A (en) * | 2006-07-07 | 2008-01-24 | Nippon Ps:Kk | Construction method of pier |
JP4597921B2 (en) * | 2006-07-07 | 2010-12-15 | 株式会社日本ピーエス | How to build a pier |
JP2009079428A (en) * | 2007-09-26 | 2009-04-16 | Kajima Corp | Joint method of concrete members and manufacturing method of floor slab for prestressed concrete bridge |
JP2014062403A (en) * | 2012-09-21 | 2014-04-10 | Kitagawa Kogyo Co Ltd | Bridge girder and construction method of bridge girder |
JP5291843B1 (en) * | 2013-02-26 | 2013-09-18 | 朝日エンヂニヤリング株式会社 | Girder bridge reinforcement structure |
JP2016194223A (en) * | 2015-04-01 | 2016-11-17 | 鹿島建設株式会社 | Method for introducing pre-stress to cast-in-place concrete |
WO2019038989A1 (en) * | 2017-08-25 | 2019-02-28 | 住友電工スチールワイヤー株式会社 | Concrete structure and method for manufacturing same |
JPWO2019038989A1 (en) * | 2017-08-25 | 2020-08-06 | 住友電気工業株式会社 | Concrete structure and method for manufacturing the same |
US11028587B2 (en) | 2017-08-25 | 2021-06-08 | Sumitomo Electric Industries, Ltd. | Concrete structure body and manufacturing method thereof |
JP7040528B2 (en) | 2017-08-25 | 2022-03-23 | 住友電気工業株式会社 | Concrete structure and its manufacturing method |
CN109610315A (en) * | 2018-12-26 | 2019-04-12 | 北京工业大学 | The dry joint connecting structure of prefabrication and assembly construction floorings and implementation method |
JP2021063378A (en) * | 2019-10-15 | 2021-04-22 | 三井住友建設株式会社 | Concrete floor slab and concrete floor slab forming method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100889273B1 (en) | Construction method for rhamen bridge | |
KR20050064049A (en) | Method for connecting continuously p.s.c-ibeam by steel bracket and its structure | |
KR100349864B1 (en) | The Structural Continuity Method for Prestreseed Concrete Bridge of Composite I-Beam | |
JP2003027415A (en) | PCa GIRDER CONNECTING METHOD AND BRIDGE FALL PREVENTING METHOD | |
KR100554408B1 (en) | Composite Girder for Bridge and Construction Method | |
JP2003253621A (en) | Continuous beam structure for continuing existing simple beam bridge | |
JP3396610B2 (en) | Hollow slab bridge and method of construction | |
JP3660647B2 (en) | Girder construction method using concrete receiving beams | |
KR101232329B1 (en) | Integral bridge and construction method using arched and concrete-filled tube | |
JP2000064222A (en) | Elevated bridge | |
JP2622013B2 (en) | Reinforced concrete shear wall structure | |
JP2831934B2 (en) | How to build substructure | |
JP2002070154A (en) | Fixing structure for structural steel product and joint structure | |
KR100393132B1 (en) | Construction method of composite steel-box bridge using prestress | |
KR100458046B1 (en) | Struture for continuing intermediate support of compositive girder bridge | |
JP3684213B2 (en) | Construction method of PC composite structure | |
JP3676442B2 (en) | Filled coated steel pipe concrete structure | |
JP4493245B2 (en) | Suspended floor slab bridge and method for reinforcing suspended floor slab | |
JP2002275833A (en) | Continuing method of simple beam of existing bridge and continuous beam structure | |
JP2005060964A (en) | Construction method for girder bridge | |
JPH0542553B2 (en) | ||
JP3455115B2 (en) | Hollow section bridge and method of constructing the same | |
KR102512912B1 (en) | PSC Block-type Arch Structure and its Construction Method | |
JP3877018B2 (en) | Barring prevention structure of steel reinforced concrete column / beam joint | |
KR102574831B1 (en) | Compoisite phc pile and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040817 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040907 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20050111 |