JP2003013621A - Power plant constructing method - Google Patents
Power plant constructing methodInfo
- Publication number
- JP2003013621A JP2003013621A JP2001200141A JP2001200141A JP2003013621A JP 2003013621 A JP2003013621 A JP 2003013621A JP 2001200141 A JP2001200141 A JP 2001200141A JP 2001200141 A JP2001200141 A JP 2001200141A JP 2003013621 A JP2003013621 A JP 2003013621A
- Authority
- JP
- Japan
- Prior art keywords
- building
- steel
- concrete
- module structure
- power plant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、鉄骨コンクリート
構造を含む発電プラントの建屋を建設する工法に係り、
特に鉄骨コンクリート構造部位に、鉄骨材および建屋内
機器等を一体化したモジュール構造物を適用する発電プ
ラント建設工法の改良に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for constructing a building of a power plant including a steel concrete structure,
Particularly, the present invention relates to improvement of a power plant construction method in which a modular structure in which a steel aggregate and building equipment are integrated is applied to a steel concrete structure part.
【0002】[0002]
【従来の技術】従来、原子力発電プラントの建屋、例え
ば原子炉建屋あるいはタービン建屋については、鉄筋コ
ンクリート構造、または本設もしくは仮設鉄骨を内蔵し
た鉄骨鉄筋コンクリート構造となっている。このような
従来構造の建屋を建設する場合には、例えば本設または
仮設の鉄骨を据付けた後に配筋および型枠工事を行な
い、または直接配筋および型枠工事を行なった後にコン
クリートを打設し、所定のコンクリート強度が得られた
後に型枠撤去を行なう等の工程をもって、建屋の床、
壁、天井の順序で最下階より順次上階へと建屋工事を進
めている。2. Description of the Related Art Conventionally, a building of a nuclear power plant, for example, a reactor building or a turbine building, has a reinforced concrete structure or a reinforced concrete structure with built-in permanent or temporary steel. When constructing a building with such a conventional structure, for example, rebar and formwork work is performed after installing main or temporary steel frames, or concrete is placed after direct rebar and formwork work. Then, with the steps such as removing the formwork after the specified concrete strength is obtained, the floor of the building,
Building construction is proceeding from the bottom floor to the upper floor in the order of walls and ceiling.
【0003】また、建築工事の床、柱、壁等のコンクリ
ート打設が終わり、コンクリートの必要強度が得られた
段階で、一旦機電側にエリアが引き渡され、建屋内に設
置される配管、機器、支持構造物等のプラントを構成す
る建屋内機器設備の工事が行なわれる。引き渡されたエ
リアにおいて、機電側が機器、配管操作架台等の部材ま
たはプレハブ構造物等の先入れ搬入を行なった後は、再
びエリアを建築側に天井工事を行なう為に引き渡す。建
築側は天井部にデッキ受けビーム、デッキプレート等の
設置を行ない天井コンクリートを打設する。そして、コ
ンクリートの必要強度が得られた段階で再び機電側にエ
リアが引き渡され、機電側は機器、配管、操作架台、支
持構造物等の据付を行なう。[0003] Further, at the stage where the concrete, such as floors, pillars, walls, etc., of the construction work is completed and the required strength of the concrete is obtained, the area is once handed over to the mechanical side, and the pipes and equipment installed in the building. The construction of equipment such as supporting structures and other equipment that constitutes the plant will be performed. In the handed over area, after the mechatronics side has carried in equipment, members such as a pipe operation stand or prefabricated structures in advance, the area is handed over to the building side again for ceiling construction. On the building side, deck receiving beams, deck plates, etc. will be installed on the ceiling, and ceiling concrete will be placed. Then, when the required strength of the concrete is obtained, the area is handed over to the machine side again, and the machine side installs the equipment, pipes, operation platform, support structure and the like.
【0004】機電側工事の操作架台や支持構造物等の取
付については、床、柱、梁、壁、天井等に予め埋設設置
された埋め込み金物を使用して建築部材と接合される。
図9は従来工法を例示したものである。この図9に示し
たように、建屋基礎1等の上に鉄骨柱2が搭載され、鉄
骨柱2上に鉄骨梁3が連結されている。鉄骨柱2および
鉄骨梁3の周囲に鉄筋4が配設され、コンクリート5が
打設されている。このような鉄骨鉄筋コンクリート構造
の建屋構造において、内側に複数本の杆状の支持部材6
が縦横に配置され、この支持部材6によって配管等の建
屋内機器7が支持されている。各支持部材6の端部は、
埋込金物8を介してコンクリート5に埋設支持されてい
る。[0004] For the mounting of the operation pedestal and the supporting structure for the mechanics side work, embedded metal fittings preliminarily embedded in the floor, pillars, beams, walls, ceiling, etc. are used to join the building members.
FIG. 9 illustrates the conventional method. As shown in FIG. 9, the steel frame columns 2 are mounted on the building foundation 1 and the like, and the steel frame beams 3 are connected to the steel frame columns 2. Reinforcing bars 4 are arranged around the steel columns 2 and the steel beams 3, and concrete 5 is placed therein. In such a building structure of a steel-framed reinforced concrete structure, a plurality of rod-shaped support members 6 are provided inside.
Are vertically and horizontally arranged, and the supporting member 6 supports the building equipment 7 such as piping. The end of each support member 6 is
It is embedded in and supported by the concrete 5 via the embedded hardware 8.
【0005】このような構成について、従来では建屋の
コンクリート打設が終了し、型枠撤去後の完成した建屋
またはエリアにおいて、柱、梁(天井)、床コンクリー
ト等に型枠内面と接し、表面がコンクリート面に現れる
ように埋設された埋込金物8に支持部材6を接続し、プ
ラント構成用の建屋内機器7を据付けていた。機電側は
完成した建屋またはエリアの引渡を受けた後、工事を開
始していた。With such a construction, conventionally, in the completed building or area after completion of the concrete pouring of the building, the pillars, beams (ceiling), floor concrete, etc. come into contact with the inner surface of the form, The support member 6 was connected to the embedded metal article 8 that was buried so that would appear on the concrete surface, and the building equipment 7 for plant construction was installed. After receiving the delivery of the completed building or area, the electric machinery side started construction.
【0006】したがって、従来の原子力発電プラント建
設工法においては、同一エリアの建設工事を建築工事、
機電工事が交互に乗込んで行なっており、このことによ
り工事期間の冗長化を招いていた。Therefore, in the conventional nuclear power plant construction method, construction work in the same area is
Mechanical and electrical work was alternately carried in, which caused redundancy in the construction period.
【0007】このような従来の工法のもとで、工期短縮
方法としては、大型仮設揚重機の採用等により、建築工
事において鉄筋のプレハブ化、鉄骨のプレハブ化等、建
築部材を大型化し、据付け場所での工事物量の削減によ
って対応してきた。同様に、機電工事においても配管の
長尺化、配管と支持部材とを一体としたプレハブ化等の
方法による据付部材の大型化を図り、据付け場所での工
事物量の削減により対応してきた。Based on the conventional construction method, as a method for shortening the construction period, by adopting a large-scale temporary lifting machine, etc., the construction members are made larger by installing prefabricated reinforcing bars, prefabricated steel frames, etc. This has been dealt with by reducing the amount of construction work at the site. Similarly, in mechanical and electrical work as well, efforts have been made to increase the size of the installation members by lengthening the pipes, prefabricating the pipes and supporting members into one body, and reducing the amount of work at the installation site.
【0008】最近の計画プラントにおいては、ますます
工期短縮要求が強まり、新たな建設工法の開発が必要と
なってきた。このような要求を解決し、さらに工期を短
縮する方法として、建築部材とプラント構成機器とを一
体化するモジュール工法が知られている(特開平10−
266602号公報等)。この工法によれば、プラント
建屋の建設個所に設置される鉄骨柱、天井梁、建設個所
に装備される建屋内機器および建設個所の側壁の壁面材
とを一体化して、モジュール構造物として構成し、この
モジュール構造物を工場組立てした後に現地に搬送して
据付ける工法を採用することによって工期短縮を達成し
ようとしている。In recent planned plants, the demand for shortening the construction period has become stronger, and it has become necessary to develop a new construction method. As a method of solving such a requirement and further shortening the construction period, a module construction method in which a building member and a plant constituent device are integrated is known (Japanese Patent Laid-Open No. 10-
266602). According to this construction method, the steel pillars installed at the construction site of the plant building, the ceiling beams, the interior equipment installed at the construction site and the wall material of the side wall of the construction site are integrated to form a modular structure. We are trying to shorten the construction period by adopting a construction method in which this modular structure is assembled in a factory and then transported to the site and installed.
【0009】[0009]
【発明が解決しようとする課題】しかし、上述した従来
のモジュール構造物を利用した工法においては、工期短
縮を目指して発電プラントの大型モジュール工法を考え
た場合、その大きさに比して壁面材による強度不足が考
えられ、また壁面材の鉄板厚さが薄いため壁面で支えら
れる荷重が小さく、壁面を利用して大荷重の機器設備や
支持構造物等を予めモジュール構造物として取り付ける
ことが困難と考えられる。However, in the construction method using the conventional module structure described above, when considering a large-scale module construction method of a power plant aiming at shortening the construction period, the wall material is larger than the size. Insufficient strength is expected due to the wall material, and the load on the wall surface is small due to the thin iron plate of the wall material, making it difficult to preliminarily mount large-load equipment and supporting structures as a module structure using the wall surface. it is conceivable that.
【0010】また、予め壁面をモジュール構成要素とし
ているため、用途が制限され、柱配置等の変更に容易に
対応することが困難である。Further, since the wall surface is used as a module constituent element in advance, its use is limited, and it is difficult to easily deal with the change of the column arrangement and the like.
【0011】さらに、天井部分のみにおいて建屋内機器
を支持する構成であるため、配管、ケーブルトレイ、ダ
クト等の天井部分に設置される限られた範囲の機器設備
しか据付けることができず、またモジュール構造物の大
型化、多量の機器設備をモジュール構造物に一体化する
場合の大重量化への対応が困難であり、大幅な工期短縮
を妨げることとなる可能性がある。Further, since the construction equipment is supported only on the ceiling portion, only a limited range of equipment facilities such as piping, cable trays and ducts which can be installed on the ceiling portion can be installed. It is difficult to cope with an increase in the size of the module structure and an increase in the weight when a large amount of equipment is integrated into the module structure, which may prevent a significant reduction in the construction period.
【0012】本発明はこのような事情に鑑みてなされた
ものであり、モジュール構造物の強度向上が図れるとと
もに、大型化および多量の機器設備を一体化する場合の
モジュール大重量化への対応が容易となり、さらに壁の
有無等の各種建屋構造に対応して種々の形態で実施でき
るうえ、各種上下配置の機器設備を多量にモジュール化
できるとともに、建屋への組込みおよびコンクリート打
設等の作業性も大幅に改善でき、完成した建屋強度の信
頼性向上も図れる発電プラント建設工法を提供すること
を目的とする。The present invention has been made in view of the above circumstances, and it is possible to improve the strength of the module structure and to cope with the increase in the size of the module and the increase in the weight of the module when a large amount of equipment is integrated. In addition to being easy, it can be implemented in various forms corresponding to various building structures such as with or without walls, and it is possible to modularize a large number of vertically arranged equipment and equipment, and workability such as assembling into the building and concrete placement It is an object of the present invention to provide a power plant construction method that can significantly improve the reliability of the strength of the completed building.
【0013】[0013]
【課題を解決するための手段】前記の目的を達成するた
め、請求項1に係る発明では、発電プラントにおける建
屋の少なくとも一部に鉄骨柱、鉄骨梁およびデッキプレ
ートを用いた鉄骨コンクリート構造を有する発電プラン
ト建設工法において、前記鉄骨柱と、前記鉄骨梁と、前
記デッキプレートを支持するためのデッキ受けビーム
と、前記建屋内に設置される建屋内機器と、前記建屋内
機器を支持する支持部材を有し、モジュール構造物を前
記建屋の基礎もしくは下階床上に搭載した後に、前記モ
ジュール構造物の鉄骨柱の周囲にコンクリートを打設す
ることを特徴とする発電プラントの建設工法を提供す
る。In order to achieve the above-mentioned object, in the invention according to claim 1, at least a part of the building in the power plant has a steel concrete structure using steel columns, steel beams and deck plates. In the power plant construction method, the steel frame column, the steel frame beam, a deck receiving beam for supporting the deck plate, a building device installed in the building, and a supporting member supporting the building device. The present invention provides a construction method for a power plant, which comprises placing a module structure on a foundation or a lower floor of the building and then placing concrete around the steel column of the module structure.
【0014】請求項2に係る発明では、支持部材と前記
鉄骨柱、前記鉄骨梁または他の支持部材と接合部のうち
少なくとも一部の前記コンクリート内に埋設させること
を特徴とする請求項1記載の発電プラントの建設工法を
提供する。The invention according to claim 2 is characterized in that at least a part of a support member and the steel frame column, the steel beam or another support member and a joint is embedded in the concrete. Providing construction method for power plant.
【0015】請求項3に係る発明では、前記モジュール
構造物の支持部材のうち、前記鉄骨コンクリート柱その
他の部位のコンクリート内に埋設される端部に、当該コ
ンクリートと空隙なく結合し得るアンカー部材を予め連
結しておき、このアンカー部材の全体もしくは一部分を
前記コンクリート内に埋設させることを特徴とする請求
項2記載の発電プラント建設工法を提供する。In the invention according to claim 3, among the supporting members of the module structure, an anchor member that can be joined to the concrete without a void is provided at an end portion of the steel concrete column or the other part which is embedded in the concrete. 3. The method for constructing a power plant according to claim 2, wherein the anchor members are connected in advance and the whole or a part of the anchor member is embedded in the concrete.
【0016】請求項4に係る発明では、前記モジュール
構造物の鉄骨柱または鉄骨梁に、コンクリート補強鉄筋
を前記モジュール構造物の据付前に、予め取付けておく
ことを特徴とする請求項1から3までのいずれかに記載
の発電プラント建設工法を提供する。The invention according to claim 4 is characterized in that concrete reinforced reinforcing bars are preliminarily attached to the steel column or steel beam of the module structure before installation of the module structure. The power generation plant construction method described in any of the above is provided.
【0017】請求項5に係る発明では、前記モジュール
構造物は複数の階層を有することを特徴とする請求項1
から4までのいずれかに記載の発電プラント建設工法を
提供する。In the invention according to claim 5, the module structure has a plurality of layers.
A power plant construction method according to any one of 1 to 4 is provided.
【0018】請求項6に係る発明では、複数の階層にお
いて荷重を分散して負担する支持手段として、各階層の
鉄骨梁、デッキ受けプレートもしくは支持部材を上下い
ずれかの方向から支持する押上部材または吊下部材を適
用することを特徴とする請求項5記載の発電プラント建
設工法を提供する。In the invention according to claim 6, as a supporting means for distributing and bearing the load in a plurality of layers, a push-up member for supporting the steel beam, the deck receiving plate or the supporting member of each layer from either the upper or lower direction or The construction method of a power plant according to claim 5, wherein a hanging member is applied.
【0019】請求項7に係る発明では、前記モジュール
構造物の少なくとも一部の前記建屋内機器の荷重を前記
建屋内機器より下方の前記鉄骨梁または前記デッキ受け
プレートに支持させることを特徴とする請求項1から5
までのいずれかに記載の発電プラント建設工法を提供す
る。The invention according to claim 7 is characterized in that the load of the building equipment of at least a part of the module structure is supported by the steel beam or the deck receiving plate below the building equipment. Claims 1 to 5
The power generation plant construction method described in any of the above is provided.
【0020】[0020]
【発明の実施の形態】以下、本発明に係る発電プラント
建設工法の実施形態について、図1〜図8を参照して説
明する。まず、図1〜図5により基本構成例を説明す
る。図1は本実施形態で適用されるモジュール構造物を
示す斜視図であり、図2は据付け状態を示す側面図であ
る。図3は建屋の柱および壁部分のコンクリート打設の
状態を説明するための断面図であり、図4および図5は
建屋内機器の支持部材の連結構造等を示す断面図であ
る。BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of a power plant construction method according to the present invention will be described below with reference to FIGS. First, a basic configuration example will be described with reference to FIGS. FIG. 1 is a perspective view showing a module structure applied in this embodiment, and FIG. 2 is a side view showing an installed state. FIG. 3 is a cross-sectional view for explaining a concrete pouring state of a pillar and a wall portion of a building, and FIGS. 4 and 5 are cross-sectional views showing a connecting structure of supporting members of building equipment and the like.
【0021】図1および図2に示したモジュール構造物
11は、発電プラントにおける建屋、例えばタービン建
屋の一部に適用されるものであり、図1および図2にお
いては基本構成例として、平面視で長方形の各隅各部に
4本の鉄骨柱12を配置した単層階のモジュール構造を
示している(なお、以下の説明では便宜的に、図1を基
準として左手前側の面を前面といい、これに対向する右
奥側の面を背面といい、右手前側の面を右側面といい、
これと対向する左奥側の面を左側面という。図2には前
面視の状態が示されている)。The module structure 11 shown in FIGS. 1 and 2 is applied to a part of a building in a power plant, for example, a turbine building. In FIGS. 1 and 2, as a basic configuration example, a plan view is shown. Shows a module structure of a single-story floor in which four steel columns 12 are arranged at each corner of each rectangle (for convenience, the surface on the left front side is referred to as the front surface with reference to FIG. 1 in the following description). The surface on the right back side opposite to this is called the back surface, and the surface on the right front side is called the right side surface.
The surface on the left back side facing this is called the left side surface. FIG. 2 shows a front view state).
【0022】これらの図1および図2に示すように、各
鉄骨柱12は例えばH型鋼からなっており、これらの各
鉄骨柱12は前後面の対向方向にウェブを向け、左右側
面の対向方向にフランジを向けている。各鉄骨柱12の
頂部間には例えばI型鋼からなる鉄骨梁13が溶接によ
りそれぞれ連結され、これらの鉄骨梁13によってモジ
ュール構造物11が各側面視において門型とされてい
る。As shown in FIGS. 1 and 2, each of the steel frame columns 12 is made of, for example, H-shaped steel, and each of the steel frame columns 12 faces the web in the front-back direction and the left-right side direction. Is facing the flange. Steel beams 13 made of, for example, I-shaped steel are connected between the tops of the steel columns 12 by welding, and the module structures 11 are gate-shaped in each side view by these steel beams 13.
【0023】左右側面に配置された鉄骨梁13(13
c,13d)の内側面には、それぞれ平行にI型鋼から
なる左右のデッキ受けビーム14が配置され、これら左
右の各デッキ受けビーム14の端部がそれぞれ前後配置
の鉄骨梁13(13a,13b)に溶接によって接合さ
れている。また、左右のデッキ受けビーム14間には、
これらと直交する複数の交差型デッキ受けビーム15が
前後方向に間隔的に溶接によって連結されている。そし
て、これらの各デッキ受けビーム15の上面が平坦面に
配置され、これらの上にデッキプレート16が配置され
ている。なお、モジュール構造物11は工場またはプラ
ント建屋近傍の搬入用揚重機吊り込み能力範囲内等にお
いて組立てられるが、その際には図示しない定盤または
仮設基礎上に鉄骨柱12および鉄骨梁13等に対し、プ
ラント構成機器の吊り込み作業に支障の無い範囲におい
てデッキ受けビーム14,15が組立てられ、基本的な
建屋部材を構成する。デッキプレート16は通常、工場
製作時等およびモジュール構造物11の搬送段階等にお
いては未設置であり、モジュール構造物11を所定の据
付位置に定置した後に設置される。Steel frame beams 13 (13) arranged on the left and right sides
c, 13d), the left and right deck receiving beams 14 made of I-shaped steel are arranged parallel to each other, and the end portions of the left and right deck receiving beams 14 are respectively arranged in the front and rear steel beams 13 (13a, 13b). ) Are welded together. Also, between the left and right deck receiving beams 14,
A plurality of intersecting deck receiving beams 15 orthogonal to these are connected by welding in the front-rear direction at intervals. The upper surface of each deck receiving beam 15 is arranged on a flat surface, and the deck plate 16 is arranged thereon. In addition, the module structure 11 is assembled within the range of lifting capacity of the lifting machine for loading near the factory or the plant building, but at that time, the steel columns 12 and the steel beams 13 are mounted on the surface plate or the temporary foundation not shown. On the other hand, the deck receiving beams 14 and 15 are assembled in a range where there is no hindrance to the work of suspending the plant component equipment to form a basic building member. The deck plate 16 is usually not installed at the time of manufacturing the factory or at the stage of transporting the module structure 11, and is installed after the module structure 11 is placed at a predetermined installation position.
【0024】そして、本実施形態のモジュール構造物1
1は、鉄骨柱12、鉄骨梁13およびデッキ受けビーム
14,15以外に、鉄骨柱12、鉄骨梁13およびデッ
キ受けビーム14,15の少なくともいずれかに連結さ
れてこれらを補強し、かつプラント構成用建屋内機器の
荷重を支持する複数の支持部材17,18,19,2
0,21,22を有している。すなわち、モジュール構
造物11の各鉄骨柱12間に、各鉄骨梁13の一定距離
下方位置にI型鋼からなる比較的大型の枠型の支持部材
(第1支持部材)17が図1において前後、左右の位置
で各鉄骨梁13と平行に配置され、各端部が鉄骨柱12
にそれぞれ溶接により接合されている。Then, the module structure 1 of the present embodiment
1 is connected to at least one of the steel column 12, the steel beam 13 and the deck receiving beams 14 and 15 in addition to the steel column 12, the steel beam 13 and the deck receiving beams 14 and 15 to reinforce them, and a plant configuration Supporting members 17, 18, 19, 2 for supporting the load of equipment for indoor building
It has 0, 21, 22. That is, a relatively large frame-shaped support member (first support member) 17 made of I-shaped steel is provided between the steel columns 12 of the module structure 11 at a position below each steel beam 13 by a predetermined distance. It is arranged in parallel with each steel beam 13 at the left and right positions, and each end is made up of steel columns 12.
Are joined to each other by welding.
【0025】これらの第1支持部材17は、その上方に
配置する鉄骨梁13に所要本数の垂直な細いボックス断
面形状の縦長な支持部材(第2支持部材)18を、それ
ぞれ溶接によって連結している。また、例えば左右の第
2支持部材18同士の間には水平な細いボックス断面形
状の支持部材(第3支持部材)19が溶接により連結さ
れている。The first support members 17 are formed by connecting the required number of vertical support members (second support members) 18 each having a vertical thin box cross-section to the steel beam 13 arranged above them by welding. There is. Further, for example, a horizontal thin box-shaped support member (third support member) 19 is connected between the left and right second support members 18 by welding.
【0026】なお、この第3支持部材19の端部と第1
支持部材17とは、据付け後に打設される壁コンクリー
ト等に埋設される部分となっている。そこで、この第3
支持部材19の端部には、鉄骨コンクリート柱その他の
部位のコンクリート内に埋設される端部に、当該コンク
リートと空隙なく結合し得るI型鋼等からなるアンカー
部材23が連結されている。このアンカー部材23につ
いては、後に図4および図5を参照して詳細に説明す
る。The end of the third support member 19 and the first
The support member 17 is a portion that is embedded in wall concrete or the like that is placed after installation. Therefore, this third
At the end of the support member 19, an anchor member 23 made of I-type steel or the like, which can be joined to the concrete without a void, is connected to the end of the steel concrete column or the like that is embedded in the concrete. The anchor member 23 will be described later in detail with reference to FIGS. 4 and 5.
【0027】さらに、モジュール構造物11の前面中央
位置に配置された縦長な第2支持部材18とその左方で
対向する鉄骨柱12との間には水平な支持部材(第4支
持部材)20が溶接により接合され、この第4支持部材
20の中間部にはその上方に配置された鉄骨梁13との
間に縦長な支持部材(第5支持部材)21が溶接により
接合されている。また、モジュール構造物11の内部略
中央に配置されている水平な第3支持部材19にはその
上方に配置されたデッキ受けビーム15との間に縦長な
支持部材(第6支持部材)22が溶接により接合され、
この第6支持部材22には図示しないが例えばモジュー
ル構造部物11の前面の第4支持部材20と同一高さで
平行な支持部材が設けられている。Further, a horizontal support member (fourth support member) 20 is provided between the vertically long second support member 18 arranged at the center position of the front surface of the module structure 11 and the steel frame column 12 opposed to the left side thereof. Are joined by welding, and a vertically long support member (fifth support member) 21 is joined by welding to the intermediate portion of the fourth support member 20 between the fourth support member 20 and the steel beam 13 arranged above the fourth support member 20. Further, a vertically long support member (sixth support member) 22 is provided between the horizontal third support member 19 arranged substantially in the center of the module structure 11 and the deck receiving beam 15 arranged above the horizontal third support member 19. Joined by welding,
Although not shown, the sixth support member 22 is provided with, for example, a support member which is parallel to the fourth support member 20 on the front surface of the module structure part 11 at the same height.
【0028】このような支持部材17〜22により、モ
ジュール構造物11が補強されて各方向の荷重に対して
剛性向上が図られる。また、水平な第1支持部材17、
第2支持部材18、第4支持部材19等には、プラント
構成用の建屋内機器24、例えば各種配管24a、ケー
ブルトレイ24b等が支持されている。これにより、鉄
骨柱12と、鉄骨梁13と、デッキプレート16を支持
するためのデッキ受けビーム14,15と、鉄骨柱12
や鉄骨梁13およびデッキ受けビーム14,15等の少
なくともいずれかに連結されてこれらを補強し、かつ各
種配管24a、ケーブルトレイ24b等の建屋内機器2
4の荷重を支持する支持部材17〜22と、これらの支
持部材17〜22に支持された建屋内機器とを予め一体
化したモジュール構造物11が構成されている。The supporting members 17 to 22 reinforce the module structure 11 to improve the rigidity against loads in each direction. In addition, the horizontal first support member 17,
The second supporting member 18, the fourth supporting member 19, and the like support building equipment 24 for plant configuration, such as various pipes 24a and cable trays 24b. Thereby, the steel frame column 12, the steel frame beam 13, the deck receiving beams 14 and 15 for supporting the deck plate 16, and the steel frame column 12
Building equipment 2 such as various pipes 24a, cable trays 24b, and the like, which are connected to at least one of the steel frame beam 13 and the deck beams 14 and 15 to reinforce them.
The module structure 11 in which the supporting members 17 to 22 supporting the load of No. 4 and the building equipment supported by these supporting members 17 to 22 are integrated in advance is configured.
【0029】なお、モジュール構造物11の強度要求上
または建屋内機器24の配置設計上の要求により、鉄骨
梁13と第1支持部材17とを接続する第2支持部材1
8を設けた建屋構造として構成することにより、建屋内
への搬入を考慮することなく建屋内機器の構造設計を行
うことができるため、建屋内機器24の構造設計を容易
にすることができるとともに、モジュール構造物11の
全体の強度を高めることが可能となり、モジュール構造
物の吊込み時の変形を防止する補強機能が得られる。The second support member 1 for connecting the steel beam 13 and the first support member 17 is required depending on the strength requirement of the module structure 11 or the layout design of the building equipment 24.
By configuring as a building structure provided with 8, the structural design of the building equipment can be performed without considering the carry-in into the building, and thus the structural design of the building equipment 24 can be facilitated. As a result, the strength of the entire module structure 11 can be increased, and a reinforcing function for preventing the module structure from being deformed when suspended can be obtained.
【0030】なお、建屋内機器24の据付作業の大半が
終了した後には、建屋内機器24の吊込み作業のために
取付けていなかった残りのデッキ受けビーム14,15
の取付等を行ない、さらにデッキ受けビーム14,15
と支持部材等とを接続することにより、モジュール構造
物11としての建屋内機器24の据付作業が完了する。
そして、建屋内機器24の据付作業が完了した後、デッ
キプレート16を取り付け、モジュール構造物11が完
成する。Incidentally, after most of the installation work of the building equipment 24 is completed, the remaining deck receiving beams 14 and 15 which have not been installed for suspending the building equipment 24 are installed.
And the deck receiving beams 14 and 15
The installation work of the building equipment 24 as the module structure 11 is completed by connecting the and the support member and the like.
Then, after the installation work of the building equipment 24 is completed, the deck plate 16 is attached and the module structure 11 is completed.
【0031】デッキプレート16または建屋内機器24
の一部は、モジュール構造物11の重量を軽減し、揚重
機能力範囲内に収めるためにモジュール構造物11より
削減することも可能である。また、揚重機能力に余裕が
ある場合には、後述する補強鉄筋や図示しないコンクリ
ート型枠等を鉄骨柱12または鉄骨梁13に取付けるこ
とも可能である。このようにして完成したモジュール構
造物11は、仮設揚重機にてプラント建屋の建設個所に
吊り込み、据付を行なう。Deck plate 16 or building equipment 24
It is possible to reduce the weight of the module structure 11 and to reduce the weight of the module structure 11 more than that of the module structure 11 so that the module structure 11 is within the lifting capacity range. In addition, when there is a margin in lifting capacity, it is possible to attach a reinforcing bar to be described later, a concrete formwork or the like not shown to the steel column 12 or the steel beam 13. The module structure 11 thus completed is hung by a temporary lifting machine at the construction site of the plant building and installed.
【0032】図3および図4は、モジュール構造物11
を建屋の基礎もしくは下階床25上に搭載後、モジュー
ル構造物11の鉄骨柱12の周囲に鉄筋26を配置する
とともに、コンクリート27を打設して、鉄骨鉄筋コン
クリート柱28と、柱間に鉄筋を配置し、コンクリート
27を打設して鉄筋コンクリート壁29を形成した状態
を示す図である。3 and 4 show the modular structure 11
After mounting on the foundation of the building or on the lower floor 25, the reinforcing bars 26 are arranged around the steel columns 12 of the module structure 11, and concrete 27 is placed to reinforce the steel reinforced concrete columns 28 and the reinforcing bars between the columns. FIG. 6 is a view showing a state in which the reinforced concrete wall 29 is formed by arranging and placing concrete 27.
【0033】ここで、図3は、前述した第3支持部材1
9にアンカー部材23を設けない場合の鉄筋コンクリー
ト壁29を示している。この図3に示すように、第3支
持部材19の鉄骨材料にボックス型鋼管等の中空管を適
用して直接、I型鋼からなる第1支持部材に接合した場
合には、コンクリート壁29に埋設される第3支持部材
19の内部にコンクリートが入らないため空洞部30が
生じ、コンクリート壁29の必要強度が得られなくなる
可能性がある。Here, FIG. 3 shows the third support member 1 described above.
9 shows the reinforced concrete wall 29 when the anchor member 23 is not provided. As shown in FIG. 3, when a hollow pipe such as a box-type steel pipe is applied to the steel material of the third support member 19 and directly joined to the first support member made of I-shaped steel, the concrete wall 29 is Since concrete does not enter the inside of the buried third support member 19, a hollow portion 30 is generated, and the required strength of the concrete wall 29 may not be obtained.
【0034】これに対し、図4は例えばI型鋼等からな
るアンカー部材23をボックス状断面の第3支持部材1
9の先端に設け、このアンカー部材23の仕口を第1支
持部材17の側面に合致させるとともに、このアンカー
部材23の長さをコンクリート29の外壁面よりも外面
側に配置する長さとしたものである。このような構成と
した場合には、コンクリート29と空隙なく結合し得る
アンカー部材23を予め連結したことにより、第3支持
部材19と第1支持部材17との接合部に空洞部が生じ
ることを防止でき、コンクリート29の必要強度が得る
ことができるようになる。なお、アンカー部材23とし
ては、I型鋼に限らず、H型鋼、U型鋼またはコンクリ
ートの空洞部が生じないように形成したアンカー部材で
あればよい。On the other hand, in FIG. 4, an anchor member 23 made of, for example, I-shaped steel is used as a third support member 1 having a box-shaped cross section.
9 is provided at the tip of the anchor member 23 so that the joint of the anchor member 23 is matched with the side surface of the first support member 17 and the length of the anchor member 23 is set to the length of the outer surface side of the outer wall surface of the concrete 29. Is. In the case of such a configuration, by connecting the concrete member 29 and the anchor member 23, which can be joined without a void, in advance, it is possible to form a cavity at the joint between the third supporting member 19 and the first supporting member 17. Therefore, the required strength of the concrete 29 can be obtained. The anchor member 23 is not limited to the I-shaped steel, but may be any H-shaped steel, U-shaped steel, or an anchor member formed so that a hollow portion of concrete does not occur.
【0035】図5(a),(b),(c)は、アンカー
部材23の異なる取付形態を示す模式図である。コンク
リート29の強度計算の範囲は一般的に、鉄筋26の内
側寸法で規定されるため、アンカー部材23が図5
(a)に示すように、鉄筋26外のふかしコンクリート
29a内に収納される構成、あるいは図5(b)に示す
ように、ふかしコンクリート29a外表面まで突出する
構成、さらに図5(c)に示すように、ふかしコンクリ
ート29a外方まで突出する構成のいずれか取り付け形
態を有する構造を採用することができる。これらの構成
の採用により、空洞部によるコンクリートの強度の低下
を防止することが可能である。5 (a), 5 (b) and 5 (c) are schematic views showing different attachment forms of the anchor member 23. As shown in FIG. The strength calculation range of the concrete 29 is generally defined by the inner dimension of the reinforcing bar 26, so that the anchor member 23 is shown in FIG.
As shown in (a), the structure is stored in the puffed concrete 29a outside the reinforcing bar 26, or as shown in FIG. 5 (b), the structure is such that it projects to the outer surface of the puffed concrete 29a, and further in FIG. 5 (c). As shown in the figure, it is possible to employ a structure having any one of the mounting configurations of projecting to the outside of the puffed concrete 29a. By adopting these configurations, it is possible to prevent a decrease in the strength of the concrete due to the hollow portion.
【0036】次に、図6〜図8によって応用例について
説明する。Next, application examples will be described with reference to FIGS.
【0037】まず、図6は応用例として、図1に示した
基本構成を上下方向には2層階として高階化するととも
に、横方向には、図1に示した基本構成を3倍して3室
連続した形状のモジュール構造としたものである。な
お、この図6に示したモジュール構造物も、発電プラン
トにおける建屋、例えばタービン建屋の一部に適用され
るものであり、図1の機能を拡大したものであるから、
図6の図1に対応する同一部位に、図1と同一の符号を
付して構成説明を省略する。この図6に示した構成によ
れば、大型建屋構成への適用において優れた効果が奏さ
れる。First, as an application example, FIG. 6 shows the basic structure shown in FIG. 1 as a two-story floor in the vertical direction, and the horizontal structure is tripled from the basic structure shown in FIG. This is a modular structure with three continuous chambers. The module structure shown in FIG. 6 is also applied to a building in a power plant, for example, a part of a turbine building, and is an expanded version of the function shown in FIG.
The same reference numerals as those in FIG. 1 are given to the same portions in FIG. 6 corresponding to FIG. 1, and the description of the configuration is omitted. According to the configuration shown in FIG. 6, an excellent effect is exerted in application to a large building configuration.
【0038】次に、図7および図8によって荷重分担の
方法について説明する。本実施形態では、モジュール構
造物11が複数の階層を有するものとして形成してお
き、その各階層において建屋内機器24の荷重または打
設コンクリート29の荷重を分散して負担させるもので
ある。そして、この場合、複数の階層において荷重を分
散して負担する支持手段として、各階層の鉄骨梁、デッ
キ受けビームもしくは支持部材を上下いずれかの方向か
ら支持する押上部材または吊下部材を適用するものであ
る。Next, a load sharing method will be described with reference to FIGS. In the present embodiment, the module structure 11 is formed as having a plurality of layers, and the load of the building equipment 24 or the load of the cast concrete 29 is dispersed and applied in each layer. Then, in this case, as the supporting means for distributing and bearing the load in the plurality of layers, a push-up member or a suspension member for supporting the steel beam, the deck receiving beam or the supporting member of each layer from either the upper or lower direction is applied. It is a thing.
【0039】すなわち、図7(a)および図7(b)
は、3層構造を有するモジュール構造物の建屋内機器2
4の荷重を分散させる概念図である。図7(a)に示し
た構成は、各階層の建屋内機器24,24,24の各荷
重31,31,31を各階層の天井部分の鉄骨梁13ま
たはデッキ受けビーム15,15,15に受け持たせる
構成としたものである。この場合には、上向き矢印31
で示すように、吊下部材を適用した構成となり、特定の
階層への荷重の集中を防止することが可能である。That is, FIGS. 7 (a) and 7 (b)
Is a building device 2 of a modular structure having a three-layer structure
It is a conceptual diagram which distributes the load of FIG. In the configuration shown in FIG. 7A, the loads 31, 31, 31 of the building equipment 24, 24, 24 of each floor are applied to the steel beam 13 or the deck receiving beams 15, 15, 15 of the ceiling portion of each floor. It is configured to handle it. In this case, the upward arrow 31
As shown in, the suspension member is applied, and it is possible to prevent the concentration of the load on a specific floor.
【0040】また、図7(b)は、モジュール構造物1
1をプラント建屋の建設個所に据付けた後でなされるコ
ンクリート29の打設時の荷重に対し、鉄骨梁13また
はデッキ受けビーム15が耐えられない場合を想定した
ものである。この場合には、建屋内機器24の荷重31
を鉄骨梁またはデッキ受けビーム15に受け持たせるこ
とにより、上向き矢印31で示すように、吊下部材を適
用した構成となり、特定の階層への荷重の集中を防止す
ることが可能である。FIG. 7B shows the module structure 1
This is based on the assumption that the steel beam 13 or the deck receiving beam 15 cannot withstand the load when the concrete 29 is placed after the installation of No. 1 at the construction site of the plant building. In this case, the load 31 of the building equipment 24
By supporting the steel beams or the deck receiving beam 15 with each other, a suspension member is applied as shown by the upward arrow 31, and it is possible to prevent the load from being concentrated on a specific floor.
【0041】さらに、図8は、図7(a),(b)にお
ける荷重分散によっても特定の階層への荷重の集中が避
けられない場合に、上向きの太線矢印で示した如く、押
上部材32を適用する構成として、建屋内機器24の荷
重を分散させる概念図である。例えば鉄骨梁13または
デッキ受けビーム15に対して建屋内機器24の荷重3
1とコンクリート11の打設荷重とが加わる場合、押上
部材32等を設置することにより鉄骨梁13またはデッ
キ受けビーム15に対する荷重を各階層のデッキ受けビ
ーム15あるいは図示しない建屋マット等への荷重の分
散を行なうことが可能である。Further, in FIG. 8, when the concentration of the load on a specific floor cannot be avoided even by the load distribution in FIGS. 7A and 7B, as shown by the upward thick line arrow, the push-up member 32 is shown. It is a conceptual diagram which distributes the load of the building equipment 24 as a structure to which is applied. For example, the load 3 of the building equipment 24 against the steel beam 13 or the deck receiving beam 15
1 and the placing load of the concrete 11 are applied, the load on the steel beam 13 or the deck receiving beam 15 can be changed by installing the push-up member 32 or the like on the deck receiving beam 15 of each floor or the building mat not shown. It is possible to perform dispersion.
【0042】以上のように、本実施形態は、プラント建
屋の建設個所に設置される鉄骨柱12と鉄骨柱12に接
合されて床面を構成する鉄骨梁13と鉄骨柱12の相互
間を任意の高さで接合する支持部材17〜22と鉄骨梁
13に接続されるデッキ受けビーム14,15とからな
る建屋を構成する建屋部材と建設個所に設置される配
管、機器、支持構造物等プラントを構成する建屋内機器
24とを一体としたモジュール構造物11を構成し、建
屋マット部25またはモジュール構造物11の下層建屋
が完成した後にモジュール構造物11を建設個所に吊り
込み、建屋マット部25またはモジュール構造物11の
下層建屋と接合し、しかる後に鉄筋工事、コンクリート
型枠工事、コンクリート打設工事を行うものである。ま
た、支持部材17〜22相互、または鉄骨柱12または
鉄骨梁13に接合された支持部材17〜22をモジュー
ル構造物11の補強部材とするものである。このような
方法によれば、モジュール構造物11の支持構造物17
〜22が変形防止の補強材として活用でき、このモジュ
ール構造物の大型化および大重量化が可能となり、モジ
ュール構造物の搬入回数が削減され工期短縮上有利とな
る。As described above, according to the present embodiment, the steel columns 12 installed at the construction site of the plant building and the steel beams 13 and the steel columns 12 which are joined to the steel columns 12 to form the floor surface are arbitrarily arranged. , Which is a building comprising a support member 17 to 22 joined at the height of the building and deck receiving beams 14 and 15 connected to the steel beam 13, and piping, equipment, support structures and the like installed at a construction site The module structure 11 that is integrated with the building equipment 24 that constitutes the module structure 11 is constructed, and after the building mat part 25 or the lower-layer building of the module structure 11 is completed, the module structure 11 is hung at the construction site, and the building mat part is formed. No. 25 or the module structure 11 is joined to the lower building, and then the reinforcing bar work, the concrete formwork work, and the concrete placing work are performed. Further, the supporting members 17 to 22 mutually or the supporting members 17 to 22 joined to the steel column 12 or the steel beam 13 are used as the reinforcing members of the module structure 11. According to such a method, the support structure 17 for the module structure 11
22 to 22 can be used as a reinforcing material for preventing deformation, the module structure can be made large and heavy, and the number of times the module structure is carried in is reduced, which is advantageous in shortening the construction period.
【0043】また、鉄骨柱12または鉄骨梁13に接合
された支持部材17〜22の接合部分の全部または一部
がモジュール構造物11を建設個所に吊り込んだ後に打
設されるコンクリート29内に埋設されるようにしたも
のである。また、鉄骨柱12または鉄骨梁13に接合さ
れたアンカー部材23を介して支持部材の接合を行な
い、アンカー部材23の全部または一部がモジュール構
造物11を建設個所に吊り込んだ後に打設されるコンク
リート29内に埋設されるようにするものである。この
ような方法によれば、モジュール構造物11の設計にお
いて支持構造物17〜22の取付位置の制約が大幅に解
消され、適切な位置に支持構造物を配置したモジュール
構造物の強度を大きくすることができるため、モジュー
ル構造物11の大型化、大重量化が可能となり、工期短
縮上有利となる。また、コンクリート建屋に予め埋設さ
れる埋込金物の設置数量を削減することができ、工事上
有利となる。Further, all or part of the joint portions of the support members 17 to 22 joined to the steel column 12 or the steel beam 13 are placed in the concrete 29 which is cast after the module structure 11 is suspended at the construction site. It is intended to be buried. Further, the support member is joined via the anchor member 23 joined to the steel column 12 or the steel beam 13, and all or part of the anchor member 23 is laid after suspending the module structure 11 at a construction site. It is to be embedded in the concrete 29. According to such a method, restrictions on the mounting positions of the support structures 17 to 22 in the design of the module structure 11 are largely eliminated, and the strength of the module structure in which the support structures are arranged at appropriate positions is increased. Therefore, the module structure 11 can be increased in size and weight, which is advantageous in shortening the construction period. In addition, it is possible to reduce the number of embedded metal objects to be embedded in the concrete building in advance, which is advantageous in construction.
【0044】また、本実施形態では、モジュール構造物
11を構成する鉄骨柱12、鉄骨梁13にコンクリート
補強鉄筋26、またはコンクリート補強鉄筋26と型枠
とを取付ける。このような方法によれば、モジュール構
造物11搬入後の鉄筋、型枠作業期間が不要となり、工
期短縮上有利となる。Further, in this embodiment, the concrete reinforcing bars 26, or the concrete reinforcing bars 26 and the formwork are attached to the steel columns 12 and the steel beams 13 constituting the module structure 11. According to such a method, the work period of the reinforcing bar and the formwork after carrying in the module structure 11 is unnecessary, which is advantageous in shortening the construction period.
【0045】さらに本実施形態は、モジュール構造物1
1が複数階層を有することによりモジュール構造物の大
型化、大重量化が可能となり、工期短縮上有利となる。
さらにプラントを構成する建屋内機器24の荷重を複数
の階層に分散して負担させることにより、モジュール構
造物に予め設置する建屋内機器設備を多くすることがで
き、工期短縮上有利となる。さらに、モジュール構造物
11が複数階層を有し、プラントを構成する建屋内機器
24の荷重を押上または吊下部材によって複数の階層に
分散して負担させることにより、建屋部材寸法の増大を
防止し、工事上有利となる。Further, this embodiment is based on the module structure 1
Since 1 has a plurality of layers, the module structure can be increased in size and weight, which is advantageous in shortening the construction period.
Further, by distributing the load of the building equipment 24 constituting the plant to a plurality of layers to bear the load, it is possible to increase the quantity of building equipment installed in advance in the module structure, which is advantageous in shortening the construction period. Further, the module structure 11 has a plurality of layers, and the load of the building equipment 24 constituting the plant is distributed to the plurality of layers by the lifting members or the hanging members to bear the load, thereby preventing an increase in the size of the building members. , Will be advantageous in construction.
【0046】[0046]
【発明の効果】以上のように、本発明によれば、モジュ
ール構造物の強度向上が図れるとともに、大型化および
多量の機器設備を一体化する場合のモジュール大重量化
への対応が容易となり、発電プラントの建設工期短縮を
図ることができる発電プラント建設工法を提供すること
ができる。As described above, according to the present invention, the strength of the module structure can be improved, and it becomes easy to cope with the increase in size and weight of the module when a large amount of equipment is integrated. A power plant construction method capable of shortening the construction period of a power plant can be provided.
【図1】前記実施形態による図1に対応する前面からの
側面図。FIG. 1 is a side view from the front corresponding to FIG. 1 according to the embodiment.
【図2】前記実施形態による建築部材と支持構造物の接
合構造例を示す断面図。FIG. 2 is a cross-sectional view showing a joint structure example of a building member and a support structure according to the embodiment.
【図3】前記実施形態による建築部材と支持構造物の接
合構造例を示す断面図。FIG. 3 is a cross-sectional view showing a joint structure example of a building member and a support structure according to the embodiment.
【図4】前記実施形態によるアンカー部材を用いた建築
部材と支持構造物の接合構造例を示す断面図。FIG. 4 is a cross-sectional view showing a joint structure example of a building member and a support structure using the anchor member according to the embodiment.
【図5】(a),(b),(c)はそれぞれ前記実施形
態によるアンカー部材の接合構造例を示す断面図。5A, 5B, and 5C are cross-sectional views showing an example of the joint structure of the anchor member according to the embodiment.
【図6】本発明による多層構造を有するモジュール構造
物の応用例を示す斜視図。FIG. 6 is a perspective view showing an application example of a module structure having a multilayer structure according to the present invention.
【図7】(a),(b)は多層構造を有するモジュール
構造物の機器設備の荷重を分散させる場合の説明図。7 (a) and 7 (b) are explanatory views in the case of distributing the load of the equipment of the module structure having the multilayer structure.
【図8】本発明による多層構造を有するモジュール構造
物の機器設備の荷重を分散させる場合の説明図。FIG. 8 is an explanatory view of the case where the load of the equipment of the module structure having the multilayer structure according to the present invention is dispersed.
【図9】従来工法による埋め込み金物と支持構造物との
接合構造例を示す断面図。FIG. 9 is a cross-sectional view showing an example of a joint structure between an embedded metal article and a support structure by a conventional method.
11 モジュール構造物 12 鉄骨柱 13,13a,13b,13c,13d 鉄骨梁 14,15 デッキ受けビーム 16 デッキプレート 17 第1支持部材 18 第2支持部材 19 第3支持部材 20 第4支持部材 21 第5支持部材 22 第6支持部材 23 アンカー部材 24 建屋内機器 24a 配管 24b ケーブルトレイ 25 下階床 26 鉄筋 27 コンクリート 28 鉄骨鉄筋コンクリート柱 29 鉄筋コンクリート壁 30 空洞部 31 荷重 32 押上部材 11 Module structure 12 Steel columns 13, 13a, 13b, 13c, 13d Steel beam 14,15 deck receiving beam 16 deck plate 17 First support member 18 Second support member 19 Third support member 20 4th support member 21 Fifth support member 22 6th support member 23 Anchor member 24 Building equipment 24a piping 24b cable tray 25 Lower floor 26 Rebar 27 concrete 28 Steel reinforced concrete columns 29 Reinforced concrete wall 30 cavity 31 load 32 Push-up member
フロントページの続き (51)Int.Cl.7 識別記号 FI テーマコート゛(参考) G21C 13/00 Q (71)出願人 390014568 東芝プラント建設株式会社 東京都大田区蒲田五丁目37番1号 (72)発明者 渡辺 幸一 神奈川県横浜市磯子区新杉田町8番地 株 式会社東芝横浜事業所内 (72)発明者 村上 正孝 神奈川県横浜市磯子区新杉田町8番地 株 式会社東芝横浜事業所内 (72)発明者 曽利 慎二 神奈川県横浜市磯子区新杉田町8番地 株 式会社東芝横浜事業所内 (72)発明者 湯原 耕造 東京都港区芝浦一丁目1番1号 株式会社 東芝本社事務所内 (72)発明者 新名 孝行 東京都港区芝浦一丁目1番1号 株式会社 東芝本社事務所内 (72)発明者 阿津地 武宏 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 村上 宏 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 三浦 宣明 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 光井 滋也 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 井上 聡 神奈川県川崎市幸区堀川町66番2号 東芝 エンジニアリング株式会社内 (72)発明者 鈴木 雄一郎 神奈川県川崎市幸区堀川町66番2号 東芝 エンジニアリング株式会社内 (72)発明者 眞喜志 康智 東京都大田区蒲田五丁目37番1号 東芝プ ラント建設株式会社内 (72)発明者 武田 信一 東京都大田区蒲田五丁目37番1号 東芝プ ラント建設株式会社内 Fターム(参考) 2E174 AA01 AA03 BA03 DA01 Continuation of front page (51) Int.Cl. 7 identification code FI theme code (reference) G21C 13/00 Q (71) Applicant 390014568 Toshiba Plant Construction Co., Ltd. 5-37-1 Kamata, Ota-ku, Tokyo (72) Inventor Koichi Watanabe 8 Shinsita-cho, Isogo-ku, Yokohama-shi, Kanagawa Incorporated company Toshiba Yokohama Works (72) Inventor Masataka Murakami 8 Shinsugita-cho, Isogo-ku, Yokohama-shi, Kanagawa Incorporated Company Toshiba Yokohama (72) Inventor Shinji Sori, 8 Shinsita-cho, Isogo-ku, Yokohama-shi, Kanagawa, Ltd. Incorporated company Toshiba Yokohama Office (72) Inventor Kozo Yubara 1-1-1, Shibaura, Minato-ku, Tokyo Toshiba Headquarters Office Co., Ltd. (72) Inventor New Takayuki Makoto 1-1-1, Shibaura, Minato-ku, Tokyo Inside the Toshiba Head Office (72) Inventor Takehiro Atsuji 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Hiroshi Murakami Tokyo 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Invention Nobuaki Miura 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Shigeya Mitsui 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Satoshi Inoue Kanagawa 66-2 Horikawa-cho, Saiwai-ku, Kawasaki-shi, Japan (72) Inventor Yuichiro Suzuki 66-2, Horikawa-cho, Saiwai-ku, Kawasaki-shi, Kanagawa Toshiba Engineering Co., Ltd. (72) Inventor Machishi Yasuchi Tokyo 5-37-3 Kamata, Ota-ku, Toshiba Plant Construction Co., Ltd. (72) Inventor Shinichi Takeda 5-37-3 Kamata, Ota-ku, Tokyo F-Term, Toshiba Plant Construction Co., Ltd. (reference) 2E174 AA01 AA03 BA03 DA01
Claims (7)
一部に鉄骨柱、鉄骨梁およびデッキプレートを用いた鉄
骨コンクリート構造を有する発電プラント建設工法にお
いて、前記鉄骨柱と、前記鉄骨梁と、前記デッキプレー
トを支持するためのデッキ受けビームと、前記建屋内に
設置される建屋内機器と、前記建屋内機器を支持する支
持部材を有し、モジュール構造物を前記建屋の基礎もし
くは下階床上に搭載した後に、前記モジュール構造物の
鉄骨柱の周囲にコンクリートを打設することを特徴とす
る発電プラントの建設工法。1. A power plant construction method having a steel-framed concrete structure using a steel frame column, a steel beam and a deck plate in at least a part of a building in the power plant, wherein the steel column, the steel beam and the deck plate are provided. After having a deck receiving beam for supporting, a building device installed in the building, and a supporting member for supporting the building device, after mounting a module structure on the foundation or the lower floor of the building. A construction method for a power plant, wherein concrete is placed around a steel column of the module structure.
は他の支持部材と接合部のうち少なくとも一部の前記コ
ンクリート内に埋設させることを特徴とする請求項1記
載の発電プラントの建設工法。2. The construction method for a power plant according to claim 1, wherein at least a part of a supporting member and the steel column, the steel beam, or another supporting member and a joint portion is embedded in the concrete. .
ち、前記鉄骨コンクリート柱その他の部位のコンクリー
ト内に埋設される端部に、当該コンクリートと空隙なく
結合し得るアンカー部材を予め連結しておき、このアン
カー部材の全体もしくは一部分を前記コンクリート内に
埋設させることを特徴とする請求項2記載の発電プラン
ト建設工法。3. An anchor member, which can be joined to the concrete without any voids, is previously connected to an end of the supporting member of the module structure which is embedded in the concrete of the steel-framed concrete column or other parts, The power plant construction method according to claim 2, wherein the anchor member is wholly or partially embedded in the concrete.
骨梁に、コンクリート補強鉄筋を前記モジュール構造物
の据付前に、予め取付けておくことを特徴とする請求項
1から3までのいずれかに記載の発電プラント建設工
法。4. A concrete reinforcing bar is attached to a steel frame column or a steel beam of the module structure before the module structure is installed, according to any one of claims 1 to 3. Power plant construction method.
することを特徴とする請求項1から4までのいずれかに
記載の発電プラント建設工法。5. The power plant construction method according to claim 1, wherein the module structure has a plurality of layers.
する支持手段として、各階層の鉄骨梁、デッキ受けプレ
ートもしくは支持部材を上下いずれかの方向から支持す
る押上部材または吊下部材を適用することを特徴とする
請求項5記載の発電プラント建設工法。6. A push-up member or a suspension member for supporting the steel beam, the deck receiving plate or the supporting member of each layer from above or below is applied as the supporting means for distributing and bearing the load in the plurality of layers. The power plant construction method according to claim 5, wherein
の前記建屋内機器の荷重を前記建屋内機器より下方の前
記鉄骨梁または前記デッキ受けプレートに支持させるこ
とを特徴とする請求項1から6までのいずれかに記載の
発電プラント建設工法。7. The load of at least a part of the building equipment of the module structure is supported by the steel beam or the deck receiving plate below the building equipment. The construction method for a power plant according to any one of 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001200141A JP4316161B2 (en) | 2001-06-29 | 2001-06-29 | Power plant construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001200141A JP4316161B2 (en) | 2001-06-29 | 2001-06-29 | Power plant construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003013621A true JP2003013621A (en) | 2003-01-15 |
JP4316161B2 JP4316161B2 (en) | 2009-08-19 |
Family
ID=19037314
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001200141A Expired - Lifetime JP4316161B2 (en) | 2001-06-29 | 2001-06-29 | Power plant construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4316161B2 (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006525499A (en) * | 2003-05-05 | 2006-11-09 | フラマトム・エイエヌピー・ゲゼルシャフト・ミット・ベシュレンクテル・ハフツング | Engineering facilities, especially nuclear facilities |
JP2008280165A (en) * | 2007-05-14 | 2008-11-20 | Mitsuhashi Seisakusho:Kk | Lifting structure of heavy article |
JP2009052393A (en) * | 2007-07-31 | 2009-03-12 | Hitachi Ltd | Module structure |
JP2010275782A (en) * | 2009-05-29 | 2010-12-09 | Hitachi Plant Technologies Ltd | Module structure and plant construction method |
US8091311B2 (en) | 2006-07-27 | 2012-01-10 | Hitachi, Ltd. | Composite integrated module and method for constructing a building |
WO2012132161A1 (en) | 2011-03-29 | 2012-10-04 | 株式会社日立プラントテクノロジー | Module structure, and module construction method |
CN103835512A (en) * | 2014-02-28 | 2014-06-04 | 中天建设集团有限公司 | Shaped splicable protective shed mounting method |
CN103835511A (en) * | 2014-02-28 | 2014-06-04 | 中天建设集团有限公司 | Integral lifting method for ultra-long light thin giant steel tube truss |
CN104234436A (en) * | 2014-08-28 | 2014-12-24 | 中广核工程有限公司 | Modular building method of nuclear power plant stainless steel cladding surface |
JP2017048747A (en) * | 2015-09-03 | 2017-03-09 | 三菱日立パワーシステムズ株式会社 | Steam turbine equipment and carrying-in method of feed water heater in steam turbine equipment |
KR102074098B1 (en) * | 2019-05-13 | 2020-02-05 | 이성권 | Factory Frame Module Construction Structure and Method |
WO2021029051A1 (en) * | 2019-08-14 | 2021-02-18 | 日揮グローバル株式会社 | Plant facility manufacturing method |
JP2022553520A (en) * | 2020-05-11 | 2022-12-23 | 上海森松製薬設備工程有限公司 | Modular factory building |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103184763B (en) * | 2011-12-29 | 2014-10-29 | 苏州中材建设有限公司 | Method for installing kiln tail steel structure framework on large-sized cement clinker production line |
-
2001
- 2001-06-29 JP JP2001200141A patent/JP4316161B2/en not_active Expired - Lifetime
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006525499A (en) * | 2003-05-05 | 2006-11-09 | フラマトム・エイエヌピー・ゲゼルシャフト・ミット・ベシュレンクテル・ハフツング | Engineering facilities, especially nuclear facilities |
US7822167B2 (en) | 2003-05-05 | 2010-10-26 | Areva Np Gmbh | Nuclear facility and method for operating a nuclear facility |
US8091311B2 (en) | 2006-07-27 | 2012-01-10 | Hitachi, Ltd. | Composite integrated module and method for constructing a building |
JP2008280165A (en) * | 2007-05-14 | 2008-11-20 | Mitsuhashi Seisakusho:Kk | Lifting structure of heavy article |
JP2009052393A (en) * | 2007-07-31 | 2009-03-12 | Hitachi Ltd | Module structure |
JP2010275782A (en) * | 2009-05-29 | 2010-12-09 | Hitachi Plant Technologies Ltd | Module structure and plant construction method |
WO2012132161A1 (en) | 2011-03-29 | 2012-10-04 | 株式会社日立プラントテクノロジー | Module structure, and module construction method |
CN103835511A (en) * | 2014-02-28 | 2014-06-04 | 中天建设集团有限公司 | Integral lifting method for ultra-long light thin giant steel tube truss |
CN103835512A (en) * | 2014-02-28 | 2014-06-04 | 中天建设集团有限公司 | Shaped splicable protective shed mounting method |
CN104234436A (en) * | 2014-08-28 | 2014-12-24 | 中广核工程有限公司 | Modular building method of nuclear power plant stainless steel cladding surface |
JP2017048747A (en) * | 2015-09-03 | 2017-03-09 | 三菱日立パワーシステムズ株式会社 | Steam turbine equipment and carrying-in method of feed water heater in steam turbine equipment |
KR102074098B1 (en) * | 2019-05-13 | 2020-02-05 | 이성권 | Factory Frame Module Construction Structure and Method |
WO2021029051A1 (en) * | 2019-08-14 | 2021-02-18 | 日揮グローバル株式会社 | Plant facility manufacturing method |
JPWO2021029051A1 (en) * | 2019-08-14 | 2021-11-18 | 日揮グローバル株式会社 | Manufacturing method of plant equipment |
JP7016452B2 (en) | 2019-08-14 | 2022-02-04 | 日揮グローバル株式会社 | Manufacturing method of plant equipment |
US11732963B2 (en) | 2019-08-14 | 2023-08-22 | Jgc Corporation | Fabrication method of a plant facility |
JP2022553520A (en) * | 2020-05-11 | 2022-12-23 | 上海森松製薬設備工程有限公司 | Modular factory building |
JP7350167B2 (en) | 2020-05-11 | 2023-09-25 | 上海森松製薬設備工程有限公司 | Modular factory building |
Also Published As
Publication number | Publication date |
---|---|
JP4316161B2 (en) | 2009-08-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5523179B2 (en) | Building construction method and room module | |
JP2003013621A (en) | Power plant constructing method | |
JPH102018A (en) | Building unit, unit building, and its constructing method | |
CN108005410B (en) | Assembled steel-concrete combined structure residential system and construction method thereof | |
KR20210038684A (en) | Precast building construction system | |
CN104234436A (en) | Modular building method of nuclear power plant stainless steel cladding surface | |
KR19980080404A (en) | Method of construction of plant buildings and modular structures used in the construction thereof | |
JP4567857B2 (en) | Unit building | |
JP4700178B2 (en) | Unit building | |
JP7368671B2 (en) | Slab base structure before concrete pouring, reinforced concrete slab structure, construction method for slab base structure before concrete pouring, and construction method for reinforced concrete slab structure | |
JP2003293506A (en) | Reinforced concrete floor structure | |
JP2023016370A (en) | Construction method of structure | |
JP3207276B2 (en) | How to build a unit building | |
JP2004061443A (en) | Building of nuclear power plant and method for constructing it | |
JPH102017A (en) | Building unit and its constructing method | |
JPH06299718A (en) | Construction of wall, floor in atomic power plant and wall slab thereof | |
JP2661302B2 (en) | Grating floor construction method | |
JPH05140993A (en) | Structure of medium/high multistorey building | |
JP2002097716A (en) | Short support slab supporting structure | |
CN115613707A (en) | Assembled building wall, beam, vertical horizontal bearing member's of board combination node | |
JP2003041661A (en) | Building construction method and building | |
JP2022159938A (en) | Unit-type building | |
JP2504658B2 (en) | Foundation structure in middle-high-rise buildings | |
JP2003213953A (en) | Plant building constructing method | |
JP3045836B2 (en) | Unit building and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A712 Effective date: 20040319 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070216 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080806 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080819 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081017 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20081209 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090203 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090421 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090520 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 4316161 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120529 Year of fee payment: 3 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120529 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120529 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130529 Year of fee payment: 4 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130529 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130529 Year of fee payment: 4 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130529 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130529 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140529 Year of fee payment: 5 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
EXPY | Cancellation because of completion of term |