JP2003013428A - Method for executing concrete placing works in dam construction, etc., and attachment for forklift for use in the concrete placing works - Google Patents

Method for executing concrete placing works in dam construction, etc., and attachment for forklift for use in the concrete placing works

Info

Publication number
JP2003013428A
JP2003013428A JP2001198350A JP2001198350A JP2003013428A JP 2003013428 A JP2003013428 A JP 2003013428A JP 2001198350 A JP2001198350 A JP 2001198350A JP 2001198350 A JP2001198350 A JP 2001198350A JP 2003013428 A JP2003013428 A JP 2003013428A
Authority
JP
Japan
Prior art keywords
concrete
concrete formwork
forklift
attachment
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001198350A
Other languages
Japanese (ja)
Inventor
Takashi Nikaido
隆 二階堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Komatsu Forklift KK
Original Assignee
Komatsu Forklift KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Komatsu Forklift KK filed Critical Komatsu Forklift KK
Priority to JP2001198350A priority Critical patent/JP2003013428A/en
Publication of JP2003013428A publication Critical patent/JP2003013428A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Forklifts And Lifting Vehicles (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method for smoothly executing concrete placing works in dam construction, etc. SOLUTION: The method for executing the concrete placing works in the dam construction, etc., is carried out by setting a concrete form 30 and pouring concrete inside the concrete form 30. According to the method, an attachment for rockably hanging the concrete form 30 is detachably attached to a fork claw 6 of a side-shifting-type forklift. Therefore, the concrete form 30 is hung by using the attachment attached to the forklift, and set at a predetermined location.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、ダム建設や河川の
護岸建設等において、コンクリートを打設する打設工事
方法及びこのコンクリート打設工事に用いるフォークリ
フト用アタッチメントに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pouring method for pouring concrete in dam construction, revetment construction of rivers, and the like, and a forklift attachment used for the concrete pouring construction.

【0002】[0002]

【従来の技術】従来、ダム建設にあっては、コンクリー
ト型枠を設置して、このコンクリート型枠の内側にコン
クリートを流し込んで、コンクリートを打設する打設工
事を行い、これを上方に向かって段階的に行うことで、
ダムのコンクリートを構築するようにしていた。このダ
ム建設におけるコンクリート打設工事では、コンクリー
ト型枠を搬送し所定の場所に設置するため、作業車両を
使用していたが、この作業車両としては、フォークリフ
トを改良した専用のコンクリート打設工事用の作業車両
であった。
2. Description of the Related Art Conventionally, in the construction of dams, a concrete formwork is installed, concrete is poured into the inside of the concrete formwork, and a concrete placing work is performed. By doing it step by step,
I was trying to build concrete for the dam. In the concrete pouring work in this dam construction, a work vehicle was used to transport the concrete formwork and install it at a predetermined place, but this work vehicle was a dedicated concrete pouring work with an improved forklift. It was a working vehicle.

【0003】このコンクリート打設工事用の作業車両
は、図8に示すように、車体41の前部にサイドシフト
シリンダ42により左右移動自在となる上下に向かう左
右一対のマスト43を備え、このマスト43に沿ってリ
フトシリンダ44により上下動する昇降体45を備え、
この昇降体45にはその下部に前方に向かう左右一対の
レール部46を形成している。そして、この昇降体45
のレール部46に沿ってリーチシリンダ47により前後
移動自在となる上下に向かう左右一対のマスト48を備
え、このマスト48はティルトシリンダ49により前後
にも傾動自在となる。また、昇降体45のレール部46
にはアウトリガー50も備える。そして、このマスト4
8に沿ってリフトシリンダ51により上下動する先端昇
降体52を備え、この先端昇降体52には回転機構部5
3を有すると共に、下方に向かうアームブラケット54
を介して先端下部にコンクリート型枠30のクランプ用
の把手36を挟持するクランプ55を備える。
As shown in FIG. 8, this work vehicle for concrete pouring work is provided with a pair of left and right masts 43 that are vertically movable by a side shift cylinder 42 in the front part of a vehicle body 41. 43 is provided with a lifting body 45 that moves up and down by a lift cylinder 44,
A pair of left and right rail portions 46 facing forward are formed on the lower portion of the lifting body 45. And this lifting body 45
A pair of up and down left and right masts 48 that are movable back and forth by a reach cylinder 47 along the rail portion 46 of the mast 48 are tilted forward and backward by a tilt cylinder 49. In addition, the rail portion 46 of the lifting body 45
It also has an outrigger 50. And this mast 4
8 is provided with a tip lifting / lowering body 52 which is vertically moved by a lift cylinder 51.
3 and has a downward arm bracket 54
A clamp 55 for holding a grip 36 for clamping the concrete formwork 30 is provided at the lower end of the end of the clamp 55.

【0004】一方、コンクリート型枠30は、図9に示
すように、板状となる金属板31の片面略全面にわたっ
て格子状のリブ32を形成すると共に、その上部にクラ
ンプ用の棒状となる把手36を複数設ける。また、この
下部に下方に向かって伸びる棒状となる設置固定用の取
り付け用ブラケット33を等間隔に複数設ける。さら
に、このコンクリート型枠30には、図示していない
が、コンクリート型枠30を設置固定する際の作業者が
乗る枠体状となる作業台を設ける。
On the other hand, as shown in FIG. 9, the concrete formwork 30 has a grid-shaped rib 32 formed on substantially the entire one surface of a plate-shaped metal plate 31, and a clamp-shaped handle for gripping the rib 32. A plurality of 36 are provided. Further, a plurality of rod-shaped mounting brackets 33 for installation and fixing extending downward are provided at equal intervals on the lower portion. Further, although not shown, the concrete formwork 30 is provided with a workbench in the form of a frame on which an operator rides when installing and fixing the concrete formwork 30.

【0005】このようになるコンクリート打設工事用の
作業車両及びコンクリート型枠30を用いたダム建設に
おけるコンクリート打設工事にあっては、作業車両の車
体41を構築中のダムのコンクリート上の端部近傍に停
止させ、ここでアウトリガー50を作動させて車体41
を固定する。また、先端のクランプ55でコンクリート
型枠30のクランプ用の把手36を挟持し、コンクリー
ト型枠30を固定した状態で保持する。そして、クラン
プ55により固定した状態で保持したコンクリート型枠
30を所定の角度及び所定の位置に、すなわちダムのコ
ンクリートの側面にあわせて、例えばダム上流側の垂直
面ではコンクリート型枠30を垂直に、またダム下流側
の斜面ではコンクリート型枠30も同じ斜めの角度にし
て、所定の位置に設置し、コンクリート型枠30の取り
付け用ブラケット33をボルトによりダムのコンクリー
トの側面である垂直面や斜面に固定する。このコンクリ
ート型枠30の設置を横に向かって多数行う。そして、
この設置した多数のコンクリート型枠30の内側にコン
クリートを流し込んで、コンクリートを打設する打設工
事を行う。この打設工事を上方に向かって段階的に行う
ことで、ダムのコンクリートを構築する。
In the concrete pouring work in the dam construction using the work vehicle and the concrete formwork 30 for the concrete pouring work as described above, in the concrete end of the dam under construction of the body 41 of the work vehicle. The vehicle is stopped near the vehicle part, and the outrigger 50 is operated there to operate the vehicle body 41.
To fix. Further, the clamp 55 for clamping the concrete formwork 30 is clamped by the clamp 55 at the tip, and the concrete formwork 30 is held in a fixed state. Then, the concrete formwork 30 held in a fixed state by the clamp 55 is placed at a predetermined angle and a predetermined position, that is, in conformity with the concrete side surface of the dam. Also, on the slope on the downstream side of the dam, the concrete formwork 30 is also installed at a predetermined position with the same oblique angle, and the mounting bracket 33 of the concrete formwork 30 is bolted to the vertical or sloped surface of the concrete of the dam. Fixed to. A large number of this concrete formwork 30 are installed horizontally. And
Concrete is poured into the plurality of installed concrete formwork 30 to perform a concrete placing work. The concrete for the dam will be constructed by gradually performing this pouring work upward.

【0006】[0006]

【発明が解決しようとする課題】従来のコンクリート打
設工事において、専用のコンクリート打設工事用の作業
車両にあっては、先端のクランプでコンクリート型枠を
固定した状態で保持するようにしていたため、例えば、
ダム下流側の斜面にあわせてコンクリート型枠を斜めに
保持した場合、保持したコンクリート型枠が前方下部に
斜めに向かうようになり、車体前方に大きな荷重が作用
するおそれがあった。そこで、車体前方への転倒を防止
するため、車体を大型化する必要があり、このため、車
体が非常に大型かつ高価になるといった問題があった。
In the conventional concrete pouring work, in the case of a dedicated work vehicle for concrete pouring work, the concrete formwork is held fixed by the clamp at the tip. , For example,
When the concrete formwork was held diagonally in accordance with the slope on the downstream side of the dam, the held concrete formwork came to be directed diagonally downward to the front, and a large load might be applied to the front of the vehicle body. Therefore, it is necessary to increase the size of the vehicle body in order to prevent the vehicle body from falling forward, which causes a problem that the vehicle body becomes very large and expensive.

【0007】また、先端のクランプによってコンクリー
ト型枠を固定した状態で保持するようにしていたため、
コンクリート型枠を設置場所に設置する際の位置決めに
おいて、自由度が全くなく、昇降体の上下動、マストの
前後動、先端昇降体の昇降動や回転によって位置決めを
行うため、その位置決め作業が極めて難しいものとなっ
ていた。
Further, since the concrete formwork is held in a fixed state by the clamp at the tip,
There is no degree of freedom in positioning the concrete formwork at the installation site, and the positioning work is extremely difficult because the vertical movement of the lifting body, the vertical movement of the mast, and the vertical movement and rotation of the tip lifting body are used for positioning. It was difficult.

【0008】さらに、専用のコンクリート打設工事用の
作業車両にあっては、マストに沿って上下動する昇降
体、昇降体のレール部に沿って前後動するマスト、ある
いはこのマストに沿って上下動する回転機構部を有する
先端昇降体といった各種の機構を備えていたため、構造
が非常に複雑で、かつ重量が非常に重くなるといった問
題もあった。
Further, in a dedicated work vehicle for concrete pouring work, an elevating body that moves up and down along a mast, a mast that moves back and forth along a rail portion of the elevating body, or up and down along this mast. Since various mechanisms such as a tip lifting body having a moving rotation mechanism section were provided, there was a problem that the structure was very complicated and the weight became very heavy.

【0009】しかも、産業車両はフォークリフトをコン
クリート打設工事用として専用に改良したものであり、
このため、産業車両を通常の荷役作業といった他の作業
に用いることが難しく、汎用性が極めて低いといった問
題もあった。
Moreover, the industrial vehicle is a specially improved forklift for concrete placing work.
Therefore, it is difficult to use the industrial vehicle for other work such as normal cargo handling work, and there is a problem that the versatility is extremely low.

【0010】本発明は、これらの問題を解消し、ダム建
設等におけるコンクリート打設工事を良好に行うことの
できるコンクリート打設工事方法及びこのコンクリート
打設工事に用いるフォークリフト用のアタッチメントを
提供することを、その課題とする。
The present invention solves these problems and provides a concrete placing method which can favorably perform concrete placing work in dam construction and the like, and an attachment for a forklift used for this concrete placing work. Is the task.

【0011】[0011]

【課題を解決するための手段】第一の発明は、コンクリ
ート型枠を設置して、このコンクリート型枠の内側にコ
ンクリートを流し込んで、ダム等におけるコンクリート
を打設するダム建設等におけるコンクリート打設工事方
法において、サイドシフト式のフォークリフトのフォー
ク爪にコンクリート型枠を揺動自在に吊り下げるアタッ
チメントを着脱自在に装着し、このフォークリフトに装
着したアタッチメントを用いてコンクリート型枠を吊り
下げて搬送し、コンクリート型枠を所定の場所に設置す
るようにしたダム建設等におけるコンクリート打設工事
方法である。
[Means for Solving the Problems] The first invention is to install a concrete formwork, pour concrete into the concrete formwork, and place concrete in a dam or the like. In the construction method, an attachment for swingably suspending the concrete formwork is detachably attached to the fork claws of a side shift type forklift, and the concrete formwork is suspended and transported using the attachment attached to this forklift, It is a concrete pouring construction method in dam construction etc. in which a concrete formwork is installed at a predetermined place.

【0012】第二の発明は、設置したコンクリート型枠
の内側にコンクリートを流し込んで、ダム等におけるコ
ンクリートを打設するダム建設等におけるコンクリート
打設工事に用いるフォークリフト用のアタッチメントで
あって、サイドシフト式のフォークリフトのフォーク爪
を差し込み可能とする嵌合部を備えると共に、先端にコ
ンクリート型枠の吊り輪を引っ掛ける吊りフックを備え
て、この吊りフックでコンクリート型枠の吊り輪を引っ
掛けることにより、コンクリート型枠を揺動自在に吊り
下げて搬送し所定の場所に設置するようにしたコンクリ
ート打設工事に用いるフォークリフト用のアタッチメン
トである。
A second aspect of the present invention is an attachment for a forklift used for concrete placing work in dam construction or the like, in which concrete is poured into the installed concrete formwork and the concrete is placed in a dam or the like. In addition to having a fitting part that allows the fork claws of a forklift truck of the type to be inserted, a hook for hooking the suspension ring of the concrete formwork is provided at the tip, and by using this suspension hook to hook the suspension ring of the concrete formwork, concrete It is an attachment for a forklift used for concrete placing work, in which the form frame is oscillatedly suspended and conveyed so as to be installed at a predetermined place.

【0013】[0013]

【作 用】第一の発明によれば、コンクリート型枠を揺
動自在に吊り下げることにより、車体前方に大きな荷重
が作用するのを大幅に低減することができ、車体前方へ
の転倒のおそれを無くすことができる。しかも、コンク
リート型枠を所定の場所に設置する際、吊り下げたコン
クリート型枠を前後あるいは左右に若干揺動して微調整
を行うことができる。
[Operation] According to the first invention, by suspending the concrete formwork swingably, it is possible to significantly reduce a large load applied to the front of the vehicle body, and it is possible that the concrete vehicle will fall forward of the vehicle body. Can be eliminated. Moreover, when the concrete formwork is installed at a predetermined place, the suspended concrete formwork can be slightly swung back and forth or left and right to perform fine adjustment.

【0014】第二の発明によれば、アタッチメントにあ
っては、フォークリフトのフォーク爪を差し込み可能と
する嵌合部を備えると共に、先端にコンクリート型枠の
吊り輪を引っ掛ける吊りフックを備えただけの単純な構
造にすることができる。
According to the second aspect of the invention, the attachment is provided with a fitting portion into which a fork claw of a forklift can be inserted, and a suspension hook for hooking a suspension ring of a concrete formwork at its tip. It can have a simple structure.

【0015】[0015]

【発明の実施の形態】本発明によるダム建設等における
コンクリート打設工事方法及びこのコンクリート打設工
事に用いるフォークリフト用のアタッチメントの一実施
形態について説明する。
BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of a method for placing concrete in dam construction or the like according to the present invention and an attachment for a forklift used in this concrete placing work will be described.

【0016】まず、作業車両としては、通常のサイドシ
フト式のフォークリフトを使用する。このサイドシフト
式のフォークリフトは、図1に示すように、車体1の前
部に備えたマスト2に沿ってリフトシリンダ3により上
下動する昇降体4にサイドシフトシリンダ5を横に向け
て備えて、このサイドシフトシリンダ5によりフォーク
爪6を左右移動自在にしたものである。
First, a normal side-shift type forklift is used as the work vehicle. As shown in FIG. 1, this side-shift type forklift truck is provided with a side-shift cylinder 5 sideways on an elevating body 4 which is vertically moved by a lift cylinder 3 along a mast 2 provided on a front portion of a vehicle body 1. The side shift cylinder 5 allows the fork claw 6 to move left and right.

【0017】そして、コンクリート打設工事に用いるフ
ォークリフト用のアタッチメントとしては、図2、図3
及び図4に示すように、サイドシフト式のフォークリフ
トのフォーク爪6を差し込み可能とする左右一対のさや
状の嵌合部11を備え、この嵌合部11は前部に設ける
ボルト12と後端に設けるロックピン13によりフォー
クリフトのフォーク爪6に固定することで、フォーク爪
6に対して着脱自在にしている。そして、この左右の嵌
合部11にフレーム14を取り付けて、このフレーム1
4は左右に向かう横板材15と前後に向かう縦板材16
とを固着してこれらの上部にリブ17を設けたものであ
る。そして、フレーム14の前部に左右に向かうベース
板18を取り付けて、このベース板18の下部にコンク
リート型枠30の吊り輪35を引っ掛ける吊りフック1
9を複数、例えば3個備える。この吊りフック19は上
部に形成したボルト部20を、ベース板18に形成した
穴21に挿入し、その上部をナット22で固定して取り
付ける構造である。なお、ベース板18に形成する穴2
1を多数にすることで、吊りフック19の取り付け位置
を変更可能として、吊りフック19を所望の位置に配置
することで、仕様の異なるコンクリート型枠30にも対
応可能にするようにしても良い。
As an attachment for a forklift used in concrete placing work, as shown in FIGS.
Also, as shown in FIG. 4, a pair of left and right pod-like fitting portions 11 into which the fork claws 6 of the side-shift type forklift can be inserted are provided, and the fitting portions 11 include a bolt 12 provided at the front portion and a rear end. By being fixed to the fork pawls 6 of the forklift by the lock pin 13 provided on the forklift trucks, the fork pawls 6 can be attached and detached freely. Then, the frame 14 is attached to the left and right fitting portions 11, and the frame 1
4 is a horizontal plate member 15 directed to the left and right and a vertical plate member 16 directed to the front and rear
And are fixed to each other, and ribs 17 are provided on the upper portions thereof. Then, a hanging hook 1 for attaching a base plate 18 directed to the left and right to the front part of the frame 14 and hooking a hanging ring 35 of a concrete formwork 30 under the base plate 18
A plurality of 9, for example, 3 are provided. The suspension hook 19 has a structure in which a bolt portion 20 formed on the upper portion is inserted into a hole 21 formed on the base plate 18, and the upper portion is fixed by a nut 22 to be attached. The holes 2 formed in the base plate 18
It is possible to change the mounting position of the hanging hook 19 by increasing the number of 1 and arrange the hanging hook 19 at a desired position so that it can be applied to concrete formwork 30 having different specifications. .

【0018】一方、コンクリート型枠30は、図5に示
すように、板状となる金属板31の片面略全面にわたっ
て格子状のリブ32を形成する。また、この下部に下方
に向かって伸びる棒状となる設置固定用の取り付け用ブ
ラケット33を等間隔に複数設け、この取り付け用ブラ
ケット33にボルト貫通用の穴34を複数形成する。さ
らに、このコンクリート型枠30には、図示していない
が、コンクリート型枠30を設置固定する際の作業者が
乗る枠体状となる作業台を設ける。そして、このコンク
リート型枠30の上部にはU字状の吊り輪35を3個備
え、この吊り輪35を吊りフック19で引っ掛けるよう
にする。
On the other hand, as shown in FIG. 5, the concrete formwork 30 has grid-shaped ribs 32 formed on substantially the entire one surface of a plate-shaped metal plate 31. Further, a plurality of rod-shaped mounting brackets 33 for installation and fixing extending downward are provided at equal intervals in the lower portion, and a plurality of holes 34 for bolt penetration are formed in the mounting bracket 33. Further, although not shown, the concrete formwork 30 is provided with a workbench in the form of a frame on which an operator rides when installing and fixing the concrete formwork 30. Further, three U-shaped suspension rings 35 are provided on the upper portion of the concrete formwork 30, and the suspension rings 35 are hooked by the suspension hooks 19.

【0019】このようにコンクリート打設工事に用いる
フォークリフト用のアタッチメントにあっては、フォー
クリフトのフォーク爪6を差し込み可能とする嵌合部1
1を備えると共に、先端にコンクリート型枠30の吊り
輪35を引っ掛ける吊りフック19を備えただけの構造
にすることにより、従来のクランプ55でコンクリート
型枠30を保持するものと比べて、その構造を極めて単
純にしている。
As described above, in the attachment for a forklift used for concrete placing work, the fitting portion 1 into which the fork pawl 6 of the forklift can be inserted.
1 and the structure in which the hanging hook 19 for hooking the hanging ring 35 of the concrete formwork 30 is only provided at the tip end, the structure is compared with the conventional clamp 55 holding the concrete formwork 30. Is extremely simple.

【0020】次に、ダム建設等におけるコンクリート打
設工事方法について述べると、最初にサイドシフト式の
フォークリフトのフォーク爪6に前述のアタッチメント
を装着する。
Next, a concrete pouring method for dam construction will be described. First, the attachment is attached to the fork claw 6 of a side shift type forklift.

【0021】そして、ダム上流側の垂直面での作業にお
いては、フォーク爪6に装着したアタッチメントの吊り
フック19をコンクリート型枠30の吊り輪35に引っ
掛けて、コンクリート型枠30を揺動自在に吊り下げ
る。そして、図6(a)に示すように、フォークリフト
の車体1を前進してコンクリート型枠30を吊り下げた
状態で搬送し、構築中のダムのコンクリート上の端部近
傍に停止する。そして、図6(b)に示すように、吊り
下げたコンクリート型枠30を所定の高さまで下降させ
る。この時、必要に応じてサイドシリンダ5によりフォ
ーク爪6を左右に移動することで、コンクリート型枠3
0を移動して、位置を合わせる。次に、フォークリフト
の車体1を若干後進して、コンクリート型枠30の取り
付け用ブラケット33がコンクリートの垂直面に当接し
たら、フォークリフトの車体1の後進を停止する。な
お、必要に応じて吊り下げたコンクリート型枠30を前
後あるいは左右に若干揺動して微調整を行って位置決め
する。そして、図6(c)に示すように、コンクリート
型枠30の取り付け用ブラケット33をボルトによりコ
ンクリートの垂直面に固定することで、コンクリート型
枠30を所定の場所に設置する。設置後、アタッチメン
トの吊りフック19をコンクリート型枠30の吊り輪3
5より取り外す。このコンクリート型枠30の設置を横
に向かって多数行う。そして、この設置した多数のコン
クリート型枠30の内側にコンクリートを流し込んで、
コンクリートを打設する打設工事を行う。この打設工事
を上方に向かって段階的に行うことで、ダムのコンクリ
ートを構築する。
Then, in the work on the vertical surface on the upstream side of the dam, the suspension hook 19 of the attachment attached to the fork claw 6 is hooked on the suspension ring 35 of the concrete formwork 30 so that the concrete formwork 30 can swing. Be suspended. Then, as shown in FIG. 6 (a), the vehicle body 1 of the forklift is moved forward and conveyed with the concrete formwork 30 suspended, and stopped near the concrete end of the dam being constructed. Then, as shown in FIG. 6B, the suspended concrete formwork 30 is lowered to a predetermined height. At this time, by moving the fork claws 6 left and right by the side cylinders 5 as needed, the concrete formwork 3
Move 0 to align. Next, the vehicle body 1 of the forklift is slightly moved backward, and when the mounting bracket 33 of the concrete formwork 30 comes into contact with the vertical surface of the concrete, the backward movement of the vehicle body 1 of the forklift is stopped. If necessary, the suspended concrete form 30 is slightly rocked back and forth or left and right to perform fine adjustment for positioning. Then, as shown in FIG. 6C, the mounting bracket 33 of the concrete formwork 30 is fixed to the vertical surface of the concrete with bolts, whereby the concrete formwork 30 is installed at a predetermined place. After installation, attach the attachment hook 19 to the suspension ring 3 of the concrete formwork 30.
Remove from 5. A large number of this concrete formwork 30 are installed horizontally. Then, the concrete is poured into the inside of the plurality of installed concrete formwork 30,
Pour construction to pour concrete. The concrete for the dam will be constructed by gradually performing this pouring work upward.

【0022】また、コンクリート型枠30の内側にコン
クリートを流し込み、流し込んだコンクリートが硬化し
た後は、フォークリフトの車体1を前進して、ダムのコ
ンクリート上の端部近傍に停止し、停止後、アタッチメ
ントの吊りフック19をコンクリート型枠30の吊り輪
35に引っ掛ける。そして、今度はコンクリートの垂直
面に固定しているコンクリート型枠30の取り付け用ブ
ラケット33のボルトを外して、コンクリート型枠30
を吊りフック19により吊り下げる。そして、コンクリ
ート型枠30をコンクリートの上面より上方まで上昇さ
せ、上昇後、フォークリフトの車体1を後進して、コン
クリート型枠30を搬送する。
Further, after the concrete is poured into the concrete formwork 30 and the poured concrete is hardened, the body 1 of the forklift is advanced and stopped near the concrete end of the dam, and after the attachment, the attachment is stopped. The hanging hook 19 of 1 is hooked on the hanging ring 35 of the concrete formwork 30. Then, this time, the bolt of the mounting bracket 33 of the concrete formwork 30 fixed to the vertical surface of the concrete is removed, and the concrete formwork 30 is removed.
Is hung by the hanging hook 19. Then, the concrete formwork 30 is raised above the upper surface of the concrete, and after the rise, the vehicle body 1 of the forklift is moved backward to convey the concrete formwork 30.

【0023】また、下方側で使用したコンクリート型枠
30を続けて上方側で使用する場合は、コンクリート型
枠30の取り付け用ブラケット33のボルトを外して、
コンクリート型枠30を吊りフック19により吊り下げ
た後、コンクリート型枠30を所定の高さまで上昇させ
て、位置を合わせる。なお、必要に応じて吊り下げたコ
ンクリート型枠30を前後あるいは左右に若干揺動して
微調整を行って位置決めする。そして、コンクリート型
枠30の取り付け用ブラケット33をボルトによりコン
クリートの垂直面に固定することで、再びコンクリート
型枠30を所定の場所に設置する。
When the concrete formwork 30 used on the lower side is continuously used on the upper side, the bolts of the bracket 33 for mounting the concrete formwork 30 are removed,
After suspending the concrete formwork 30 with the suspension hooks 19, the concrete formwork 30 is lifted to a predetermined height to align the positions. If necessary, the suspended concrete form 30 is slightly rocked back and forth or left and right to perform fine adjustment for positioning. Then, the mounting bracket 33 of the concrete formwork 30 is fixed to the vertical surface of the concrete with bolts, whereby the concrete formwork 30 is installed again at a predetermined place.

【0024】一方、ダム下流側の斜面での作業において
は、基本的にダム上流側の垂直面での作業と略同様であ
るが、以下のとおりである。フォーク爪6に装着したア
タッチメントの吊りフック19をコンクリート型枠30
の吊り輪に引っ掛けて、コンクリート型枠30を揺動自
在に吊り下げる。そして、図7(a)に示すように、フ
ォークリフトの車体1を前進してコンクリート型枠30
を吊り下げた状態で搬送し、構築中のダムのコンクリー
ト上の端部近傍に停止する。そして、吊り下げたコンク
リート型枠30を所定の高さまで下降させる。この時、
必要に応じてサイドシリンダ5によりフォーク爪6を左
右に移動することで、コンクリート型枠30を移動し
て、位置を合わせる。そして、図7(b)に示すよう
に、コンクリート型枠30を下降させて、コンクリート
型枠30の下端である取り付け用ブラケット33をコン
クリートの斜面に当接させる。次に、フォークリフトの
車体1を後進して、コンクリート型枠30を徐々に倒
し、コンクリート型枠30が斜面と略平行となったら、
フォークリフトの車体1の後進を停止する。なお、必要
に応じて吊り下げたコンクリート型枠30を前後あるい
は左右に若干揺動して微調整を行って位置決めする。そ
して、図7(c)に示すように、コンクリート型枠30
の取り付け用ブラケット33をボルトによりコンクリー
トの斜面に固定することで、コンクリート型枠30を所
定の場所に設置する。設置後、アタッチメントの吊りフ
ック19をコンクリート型枠30の吊り輪35より取り
外す。このコンクリート型枠30の設置を横に向かって
多数行う。そして、この設置した多数のコンクリート型
枠30の内側にコンクリートを流し込んで、コンクリー
トを打設する打設工事を行う。この打設工事を上方に向
かって段階的に行うことで、ダムのコンクリートを構築
する。
On the other hand, the work on the slope on the downstream side of the dam is basically the same as the work on the vertical surface on the upstream side of the dam, but is as follows. Attach the attachment hook 19 attached to the fork claw 6 to the concrete formwork 30.
To suspend the concrete formwork 30 so that the concrete formwork 30 can swing freely. Then, as shown in FIG. 7A, the vehicle body 1 of the forklift is moved forward to advance the concrete formwork 30.
Is transported in a suspended state and stopped near the concrete end of the dam being constructed. Then, the suspended concrete formwork 30 is lowered to a predetermined height. This time,
The side cylinder 5 moves the fork claws 6 to the left or right as needed, thereby moving the concrete formwork 30 and aligning the positions. Then, as shown in FIG. 7B, the concrete formwork 30 is lowered to bring the mounting bracket 33, which is the lower end of the concrete formwork 30, into contact with the slope of the concrete. Next, the vehicle body 1 of the forklift is moved backward, the concrete formwork 30 is gradually tilted down, and when the concrete formwork 30 becomes substantially parallel to the slope,
Stop the reverse movement of the forklift body 1. If necessary, the suspended concrete form 30 is slightly rocked back and forth or left and right to perform fine adjustment for positioning. Then, as shown in FIG. 7C, the concrete formwork 30
The concrete formwork 30 is installed at a predetermined place by fixing the mounting bracket 33 of 1 to the slope of the concrete with bolts. After installation, the attachment hook 19 of the attachment is removed from the suspension ring 35 of the concrete formwork 30. A large number of this concrete formwork 30 are installed horizontally. Then, the concrete is poured into the plurality of the installed concrete formwork 30 to perform the placing work for placing the concrete. The concrete of the dam will be constructed by gradually performing this casting work upward.

【0025】また、コンクリート型枠30の内側にコン
クリートを流し込み、流し込んだコンクリートが硬化し
た後は、フォークリフトの車体1を前進して、ダムのコ
ンクリート上の端部近傍に停止し、停止後、アタッチメ
ントの吊りフック19をコンクリート型枠30の吊り輪
35に引っ掛ける。そして、今度はコンクリートの斜面
に固定しているコンクリート型枠30の取り付け用ブラ
ケット33のボルトを外して、コンクリート型枠30を
吊りフック19により吊り下げる。次に、フォークリフ
トの車体1を前進して、コンクリート型枠30を徐々に
起こし、コンクリート型枠30が垂下したら、フォーク
リフトの車体1の前進を停止する。そして、コンクリー
ト型枠30をコンクリートの上面より上方まで上昇さ
せ、上昇後、フォークリフトの車体1を後進して、コン
クリート型枠30を搬送する。
Further, after the concrete is poured into the concrete formwork 30 and the poured concrete is hardened, the body 1 of the forklift is moved forward and stopped near the concrete end of the dam, and after the attachment, the attachment is made. The hanging hook 19 of 1 is hooked on the hanging ring 35 of the concrete formwork 30. Then, this time, the bolt of the mounting bracket 33 of the concrete formwork 30 fixed to the slope of the concrete is removed, and the concrete formwork 30 is suspended by the suspension hook 19. Next, the vehicle body 1 of the forklift is advanced to gradually raise the concrete formwork 30, and when the concrete formwork 30 hangs down, the advancement of the vehicle body 1 of the forklift is stopped. Then, the concrete formwork 30 is raised above the upper surface of the concrete, and after the rise, the vehicle body 1 of the forklift is moved backward to convey the concrete formwork 30.

【0026】また、下方側で使用したコンクリート型枠
30を続けて上方側で使用する場合は、コンクリート型
枠30の取り付け用ブラケット33のボルトを外して、
コンクリート型枠30を吊りフック19により吊り下げ
た後、一旦、フォークリフトの車体1を前進して、コン
クリート型枠30を徐々に起こして垂下させる。そし
て、コンクリート型枠30を所定の高さまで上昇して、
位置を合わせる。次に、フォークリフトの車体1を後進
して、コンクリート型枠30を徐々に倒し、コンクリー
ト型枠30が斜面と略平行となったら、フォークリフト
の車体1の後進を停止する。なお、必要に応じて吊り下
げたコンクリート型枠30を前後あるいは左右に若干揺
動して微調整を行って位置決めする。そして、コンクリ
ート型枠30の取り付け用ブラケット33をボルトによ
りコンクリートの斜面に固定することで、再びコンクリ
ート型枠30を所定の場所に設置する。
When the concrete formwork 30 used on the lower side is continuously used on the upper side, the bolts of the mounting bracket 33 of the concrete formwork 30 are removed,
After suspending the concrete formwork 30 with the suspension hooks 19, the vehicle body 1 of the forklift is once moved forward, and the concrete formwork 30 is gradually raised and hung down. Then, raise the concrete formwork 30 to a predetermined height,
Adjust the position. Next, the vehicle body 1 of the forklift is moved backward, the concrete formwork 30 is gradually tilted down, and when the concrete formwork 30 becomes substantially parallel to the slope, the backward movement of the bodywork 1 of the forklift is stopped. If necessary, the suspended concrete form 30 is slightly rocked back and forth or left and right to perform fine adjustment for positioning. Then, the mounting bracket 33 of the concrete formwork 30 is fixed to the slope of the concrete with bolts, whereby the concrete formwork 30 is installed again at a predetermined place.

【0027】以上のようにダム建設等におけるコンクリ
ート打設工事方法にあっては、サイドシフト式のフォー
クリフトのフォーク爪6にコンクリート型枠30を揺動
自在に吊り下げるアタッチメントを着脱自在に装着し、
このフォークリフトに装着したアタッチメントを用いて
コンクリート型枠30を吊り下げて搬送し、コンクリー
ト型枠30を所定の場所に設置するようにしたことによ
り、従来のクランプ55でコンクリート型枠30を固定
した状態で保持するものと比べて、コンクリート型枠3
0を揺動自在に吊り下げることで、車体1前方に大きな
荷重が作用するのを大幅に低減することができ、車体1
前方への転倒のおそれを無くすようにしている。
As described above, in the concrete pouring construction method in dam construction, etc., the attachment for suspending the concrete formwork 30 swingably is detachably attached to the fork claw 6 of the side shift type forklift.
A state in which the concrete formwork 30 is fixed by the conventional clamp 55 by suspending and transporting the concrete formwork 30 using the attachment attached to this forklift and installing the concrete formwork 30 at a predetermined place. Concrete formwork 3 compared to what is held in
By suspending 0 in a swingable manner, it is possible to significantly reduce a large load applied to the front of the vehicle body 1.
I try to eliminate the risk of falling forward.

【0028】また、コンクリート型枠30を所定の場所
に設置する際、アタッチメントによってコンクリート型
枠30を揺動自在に吊り下げることにより、吊り下げた
コンクリート型枠30を前後あるいは左右に若干揺動し
て微調整を行うようにして、コンクリート型枠30の位
置決めを容易にしている。
When the concrete formwork 30 is installed at a predetermined place, the concrete formwork 30 is oscillated by an attachment so that the hung concrete formwork 30 is slightly swung back and forth or left and right. The concrete form 30 is easily positioned by fine adjustment.

【0029】また、フォークリフトにあっては、アタッ
チメントを装着することにより、コンクリート打設工事
用とすることができると共に、アタッチメントを取り外
すことにより、通常の荷役作業といった他の作業を行え
るようにしている。
Further, in the forklift, the attachment can be mounted for concrete pouring work, and the attachment can be removed to perform other work such as normal cargo handling work. .

【0030】なお、前述したコンクリート打設工事方法
にあっては、ダム建設における工事方法として説明した
が、これに限定されるものではなく、河川の護岸建設や
その他の建設等に適用することも可能である。
Although the concrete pouring construction method described above has been described as a construction method for dam construction, the construction method is not limited to this and may be applied to river bank construction and other construction. It is possible.

【0031】[0031]

【発明の効果】本発明によれば、コンクリート型枠を揺
動自在に吊り下げて搬送し、コンクリート型枠を所定の
場所に設置するようにしたことにより、車体前方に大き
な荷重が作用するのを大幅に低減し、車体前方への転倒
のおそれを無くすことで、車体の大型化を抑えて、車体
の小型化を図ることができ、これを安価に提供すること
ができる。しかも、コンクリート型枠を所定の場所に設
置する際、吊り下げたコンクリート型枠を前後あるいは
左右に若干揺動して微調整を行うことができ、その位置
決め作業を極めて容易に行うことができる。
According to the present invention, since a concrete formwork is oscillatedly suspended and conveyed, and the concrete formwork is installed at a predetermined place, a large load acts on the front of the vehicle body. It is possible to suppress the increase in size of the vehicle body and to reduce the size of the vehicle body by significantly reducing the risk of falling to the front of the vehicle body, and to provide the vehicle body at a low cost. Moreover, when the concrete formwork is installed at a predetermined place, the suspended concrete formwork can be slightly rocked back and forth or left and right to perform fine adjustment, and the positioning work can be performed extremely easily.

【0032】また、アタッチメントにあっては、フォー
クリフトのフォーク爪を差し込み可能とする嵌合部を備
えると共に、先端にコンクリート型枠の吊り輪を引っ掛
ける吊りフックを備えただけの構造にすることにより、
その構造を極めて単純にかつ重量も非常に軽くすること
ができる。
Further, the attachment is provided with a fitting portion into which a fork claw of a forklift can be inserted, and a structure in which a hanging hook for hooking a hanging ring of a concrete formwork is simply provided at a tip thereof.
The structure can be extremely simple and very light in weight.

【0033】しかも、フォークリフトにあっては、この
アタッチメントを装着することにより、コンクリート打
設工事用とすることができると共に、アタッチメントを
取り外すことにより、通常の荷役作業といった他の作業
を行うことができ、各種の作業に極めて良好に対応する
ことができ、汎用性の高いものにすることができる。
In addition, the forklift can be used for concrete placing work by mounting this attachment, and by removing the attachment, other work such as normal cargo handling work can be performed. It is possible to cope with various kinds of work extremely well and to make it highly versatile.

【図面の簡単な説明】[Brief description of drawings]

【図1】サイドシフト式のフォークリフトの説明図であ
る。
FIG. 1 is an explanatory diagram of a side shift type forklift.

【図2】本発明によるフォークリフト用のアタッチメン
トの平面図である。
FIG. 2 is a plan view of an attachment for a forklift according to the present invention.

【図3】本発明によるフォークリフト用のアタッチメン
トの側面図である。
FIG. 3 is a side view of an attachment for a forklift according to the present invention.

【図4】本発明によるフォークリフト用のアタッチメン
トの斜視図である。
FIG. 4 is a perspective view of an attachment for a forklift according to the present invention.

【図5】本発明によるコンクリート型枠の正面図であ
る。
FIG. 5 is a front view of a concrete formwork according to the present invention.

【図6】(a)本発明によるコンクリート打設工事方法
の作業状態説明図である。 (b)本発明によるコンクリート打設工事方法の作業状
態説明図である。 (c)本発明によるコンクリート打設工事方法の作業状
態説明図である。
FIG. 6 (a) is a work state explanatory view of the concrete pouring construction method according to the present invention. (B) It is a work state explanatory drawing of the concrete pouring construction method by this invention. (C) It is a working state explanatory drawing of the concrete pouring construction method by this invention.

【図7】(a)本発明によるコンクリート打設工事方法
の作業状態説明図である。 (b)本発明によるコンクリート打設工事方法の作業状
態説明図である。 (c)本発明によるコンクリート打設工事方法の作業状
態説明図である。
FIG. 7 (a) is a work state explanatory view of the concrete pouring construction method according to the present invention. (B) It is a work state explanatory drawing of the concrete pouring construction method by this invention. (C) It is a working state explanatory drawing of the concrete pouring construction method by this invention.

【図8】従来のコンクリート打設工事用の作業車両の説
明図である。
FIG. 8 is an explanatory view of a conventional work vehicle for concrete placing work.

【図9】従来のコンクリート型枠の正面図である。FIG. 9 is a front view of a conventional concrete formwork.

【符号の説明】[Explanation of symbols]

1…車体、2…マスト、3…リフトシリンダ、4…昇降
体、5…サイドシフトシリンダ、6…フォーク爪、11
…嵌合部、12…ボルト、13…ロックピン、14…フ
レーム、15…横板材、16…縦板材、17…リブ、1
8…ベース板、19…吊りフック、20…ボルト部、2
1…穴、22…ナット、30…コンクリート型枠、31
…金属板、32…リブ、33…取り付け用ブラケット、
34…穴、35…吊り輪、36…把手、41…車体、4
2…サイドシフトシリンダ、43…マスト、44…リフ
トシリンダ、45…昇降体、46…レール部、47…リ
ーチシリンダ、48…マスト、49…ティルトシリン
ダ、50…アウトリガー、51…リフトシリンダ、52
…先端昇降体、53…回転機構部、54…アームブラケ
ット、55…クランプ。
DESCRIPTION OF SYMBOLS 1 ... Car body, 2 ... Mast, 3 ... Lift cylinder, 4 ... Lifting body, 5 ... Side shift cylinder, 6 ... Fork claw, 11
... Fitting part, 12 ... Bolt, 13 ... Lock pin, 14 ... Frame, 15 ... Horizontal plate material, 16 ... Vertical plate material, 17 ... Rib, 1
8 ... Base plate, 19 ... Hanging hook, 20 ... Bolt part, 2
1 ... Hole, 22 ... Nut, 30 ... Concrete formwork, 31
... metal plate, 32 ... rib, 33 ... mounting bracket,
34 ... Hole, 35 ... Suspension ring, 36 ... Handle, 41 ... Car body, 4
2 ... Side shift cylinder, 43 ... Mast, 44 ... Lift cylinder, 45 ... Lifting body, 46 ... Rail part, 47 ... Reach cylinder, 48 ... Mast, 49 ... Tilt cylinder, 50 ... Outrigger, 51 ... Lift cylinder, 52
... Tip elevating body, 53 ... Rotation mechanism part, 54 ... Arm bracket, 55 ... Clamp.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート型枠30を設置して、この
コンクリート型枠30の内側にコンクリートを流し込ん
で、ダム等におけるコンクリートを打設するダム建設等
におけるコンクリート打設工事方法において、 サイドシフト式のフォークリフトのフォーク爪6にコン
クリート型枠30を揺動自在に吊り下げるアタッチメン
トを着脱自在に装着し、このフォークリフトに装着した
アタッチメントを用いてコンクリート型枠30を吊り下
げて搬送し、コンクリート型枠30を所定の場所に設置
するようにしたことを特徴とするダム建設等におけるコ
ンクリート打設工事方法。
1. A method for placing concrete in a dam, etc., in which concrete formwork 30 is installed, and concrete is poured into the inside of the concrete formwork 30 to place concrete in a dam, etc. An attachment that removably suspends the concrete formwork 30 is detachably attached to the fork claws 6 of the forklift, and the concrete formwork 30 is hung and conveyed using the attachment attached to this forklift, and the concrete formwork 30 is A concrete pouring construction method in dam construction, etc., characterized by being installed at a predetermined place.
【請求項2】 設置したコンクリート型枠30の内側に
コンクリートを流し込んで、ダム等におけるコンクリー
トを打設するダム建設等におけるコンクリート打設工事
に用いるフォークリフト用のアタッチメントであって、 サイドシフト式のフォークリフトのフォーク爪6を差し
込み可能とする嵌合部11を備えると共に、先端にコン
クリート型枠30の吊り輪35を引っ掛ける吊りフック
19を備えて、この吊りフック19でコンクリート型枠
30の吊り輪35を引っ掛けることにより、コンクリー
ト型枠30を揺動自在に吊り下げて搬送し所定の場所に
設置するようにしたことを特徴とするコンクリート打設
工事に用いるフォークリフト用のアタッチメント。
2. A side-shift type forklift attachment for a forklift used for concrete placing work in a dam construction or the like, in which concrete is poured into the installed concrete formwork 30 and the concrete is placed in the dam or the like. In addition to the fitting portion 11 into which the fork claw 6 of FIG. 3 can be inserted, a suspension hook 19 for hooking the suspension ring 35 of the concrete formwork 30 is provided at the tip, and the suspension ring 35 of the concrete formwork 30 is attached by the suspension hook 19. An attachment for a forklift used in a concrete placing work, characterized in that the concrete formwork 30 is oscillatedly hung so that it can be hung and conveyed to be installed at a predetermined place.
JP2001198350A 2001-06-29 2001-06-29 Method for executing concrete placing works in dam construction, etc., and attachment for forklift for use in the concrete placing works Pending JP2003013428A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001198350A JP2003013428A (en) 2001-06-29 2001-06-29 Method for executing concrete placing works in dam construction, etc., and attachment for forklift for use in the concrete placing works

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001198350A JP2003013428A (en) 2001-06-29 2001-06-29 Method for executing concrete placing works in dam construction, etc., and attachment for forklift for use in the concrete placing works

Publications (1)

Publication Number Publication Date
JP2003013428A true JP2003013428A (en) 2003-01-15

Family

ID=19035815

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001198350A Pending JP2003013428A (en) 2001-06-29 2001-06-29 Method for executing concrete placing works in dam construction, etc., and attachment for forklift for use in the concrete placing works

Country Status (1)

Country Link
JP (1) JP2003013428A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220031235A (en) * 2020-09-04 2022-03-11 (주)에이치에스비 Hanger type extraction device for cargo loaded in container

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220031235A (en) * 2020-09-04 2022-03-11 (주)에이치에스비 Hanger type extraction device for cargo loaded in container
KR102450233B1 (en) * 2020-09-04 2022-10-04 (주)에이치에스비 Hanger type extraction device for cargo loaded in container

Similar Documents

Publication Publication Date Title
US20200399099A1 (en) Crane
JP2003013428A (en) Method for executing concrete placing works in dam construction, etc., and attachment for forklift for use in the concrete placing works
CN113481972B (en) Steel reinforcement cage material loading transportation and lower cage device
CN112660993B (en) Box girder falling-prevention stop block mounting system and construction method
JP2004034933A (en) Fuel gas cylinder mounting device for industrial vehicle
JPH08197233A (en) Device for attaching/detaching ladle cover and ladle cover fitting mechanism
JP2562475Y2 (en) Counterweight attachment / detachment device for construction machinery
CN217201769U (en) Special hoisting sling
CN210594932U (en) T beam mold board hoist
CN219860128U (en) Plate overturning lifting appliance
CN213356748U (en) Lifting device capable of adjusting angle of suspension arm
JPH0614193U (en) Cargo handling vehicle
JP3038292B2 (en) Formwork lifting attachment and formwork lifting vehicle
JP3075513B2 (en) Work vehicle for mounting reinforcement
JPH11335065A (en) Iron plate grip device
JPH08143277A (en) Fitting structure of weight at movement type construction machine
KR101008167B1 (en) An apparstus for supplying the dart in converter
JP2000351576A (en) Tower crane and removal method thereof
JP4127828B2 (en) Continuous casting equipment
KR20220168007A (en) Construction mold moving and installation device for fork lift and braket therof
JPH04135578U (en) Hanging device with hook release prevention mechanism
JP2512649Y2 (en) U-shaped groove suspender
JPH08133657A (en) Suspension frame device in crane ship
JPH09110366A (en) Lifting gear of building materials
JPH10175711A (en) Lifting gear for ditch cover