JP2002356996A - Method of lifting building construction device, and intermediate frame - Google Patents

Method of lifting building construction device, and intermediate frame

Info

Publication number
JP2002356996A
JP2002356996A JP2001165738A JP2001165738A JP2002356996A JP 2002356996 A JP2002356996 A JP 2002356996A JP 2001165738 A JP2001165738 A JP 2001165738A JP 2001165738 A JP2001165738 A JP 2001165738A JP 2002356996 A JP2002356996 A JP 2002356996A
Authority
JP
Japan
Prior art keywords
building
intermediate frame
construction
construction device
horizontal member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001165738A
Other languages
Japanese (ja)
Other versions
JP3707009B2 (en
Inventor
Koji Kondo
弘司 近藤
Atsushi Nishimura
淳 西村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2001165738A priority Critical patent/JP3707009B2/en
Publication of JP2002356996A publication Critical patent/JP2002356996A/en
Application granted granted Critical
Publication of JP3707009B2 publication Critical patent/JP3707009B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Jib Cranes (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an efficient and versatile method of lifting a building construction device, and an intermediate frame for use in the lifting method. SOLUTION: The construction device 3 is positioned to cover the outer periphery of a building 1 and intermediate frames 12 are positioned on the outer sides of the building 1. The construction device 3 stands still during construction work while supporting an upper bolt 4 and a lower bolt 5 respectively against a horizontal member 2a and a horizontal member 2b of the building 1. The construction device 3 is lifted like a looper by use of the intermediate frames 12 and the building 1; when it reaches the upper end of each intermediate frame 12, the intermediate frame 12 is raised and these operations are repeated whereby the construction device is located above the building 1 under construction.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、効率的、かつ汎用
性の高い建築物の施工装置の上昇方法、及び上昇方法を
実施する上で使用する中間フレームに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an efficient and highly versatile method of assembling a building construction apparatus, and to an intermediate frame used in carrying out the method.

【0002】[0002]

【従来の技術】従来より、建築物の施工に際し、天候の
影響を受けることなく、安全な作業環境の確保と生産性
を向上する施工の一手段として、施工中の建築物の上部
に配置され、漸次上昇していく本体フレームと、該本体
フレームを上昇させるクライミング機構と、該本体フレ
ームに搭載されて資材を揚重し搬送する搬送機構と、を
備えた建築物の施工装置を用いた施工方法が採用されて
いる。図6、図7に示すように、該施工装置3は、施工
の対象となる建築物1にその高さ方向に所定間隔をあけ
て設けられた複数の水平部材2、2a、2bに対して、
上部カンヌキ4及び下部カンヌキ5を介して荷重を預け
て、油圧ジャッキ7を備えた前記クライミング機構6に
より尺取り虫状に上昇下降する装置である。
2. Description of the Related Art Conventionally, when constructing a building, it has been placed above a building under construction as a means of ensuring a safe working environment and improving productivity without being affected by the weather. Construction using a building construction apparatus including a gradually rising body frame, a climbing mechanism for raising the body frame, and a transport mechanism mounted on the body frame for lifting and transporting materials. The method has been adopted. As shown in FIG. 6 and FIG. 7, the construction device 3 is used for a plurality of horizontal members 2, 2 a, and 2 b provided at predetermined intervals in the height direction of a building 1 to be constructed. ,
This is a device which receives a load via the upper cannula 4 and the lower cannula 5 and ascends and descends like a scale by the climbing mechanism 6 provided with the hydraulic jack 7.

【0003】該建築物の施工装置3は、通常の施工作業
時において前記下部カンヌキ5を突出させて前記建築物
1の水平部材2bに連結支持されるとともに、前記上部
カンヌキ4を突出させて前記水平部材2bより一段高い
位置に取り付けられた水平部材2aに連結支持されるこ
とによって、前記建築物1の上部に固定されている(図
7(a)参照)。
[0003] The building construction apparatus 3 projects and supports the lower kanuki 5 and the horizontal member 2b of the building 1 during normal construction work. It is fixed to the upper part of the building 1 by being connected and supported by a horizontal member 2a attached at a position one step higher than the horizontal member 2b (see FIG. 7A).

【0004】このような施工装置3の上昇方法は、前記
上部カンヌキ4を引き込み前記水平部材2aより取り離
し、前記油圧ジャッキ7を伸長させて、上部カンヌキ4
が前記水平部材2aより一段高い位置に取り付けられた
水平部材2に達した時点で、上部カンヌキ4を突出させ
て該水平部材2に連結支持する(図7(b)参照)。次
に、前記下部カンヌキ5を前記水平部材2bより引き込
み、前記油圧ジャッキ7を短縮して前記下部カンヌキ5
が前記水平部材2bより一段高い位置に取り付けられた
水平部材2aに達した時点で、該水平部材2aに前記下
部カンヌキ5を突出させて該水平部材2aに支持する
(図7(c)参照)。これらの動作を繰り返すことによ
り、前記施工装置3は前記建築物1を上昇していくこと
となる。
[0004] Such an ascending method of the construction device 3 is as follows. The upper cannula 4 is pulled in, separated from the horizontal member 2a, and the hydraulic jack 7 is extended.
Reaches the horizontal member 2 attached at a position one step higher than the horizontal member 2a, the upper cannula 4 is projected and connected to and supported by the horizontal member 2 (see FIG. 7B). Next, the lower cannus 5 are retracted from the horizontal member 2b, and the hydraulic jack 7 is shortened to reduce the lower cannus 5.
Reaches the horizontal member 2a attached at a position one step higher than the horizontal member 2b, the lower cannula 5 projects from the horizontal member 2a and is supported by the horizontal member 2a (see FIG. 7 (c)). . By repeating these operations, the construction device 3 moves up the building 1.

【0005】したがって、前記クライミング機構6のス
トロークは、建築物1の水平部材2、2a、2bの各々
の配置間隔L4の2倍以上の長さが必要となる。
Accordingly, the stroke of the climbing mechanism 6, the horizontal members 2,2a building 1, each of at least twice the length of the arrangement interval L 4 and 2b are required.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、建築物
1の水平部材2、2a、2bの各々の配置間隔L4の2
倍長さが、前記クライミング機構6のストロークの標準
値よりも長い場合には、建築物1に前記施工装置3を用
いた施工方法を実施する際に、対象となる建築物1の設
計変更を行うか(建築物1の水平部材2、2a、2bの
各々の配置間隔L 4を前記施工装置3のストローク限界
に合わせる)、クライミング機構6のストロークを長く
するよう、製作し直す等の対策が必要となるため、汎用
性が乏しく不経済となっていた。
SUMMARY OF THE INVENTION However, buildings
1 horizontal member 2, 2a, 2b, the arrangement interval LFour2
Double length is the standard of the stroke of the climbing mechanism 6.
If it is longer than the value, use the construction device 3 for the building 1.
Of the target building 1
Do you change total (of horizontal member 2, 2a, 2b of building 1)
Each arrangement interval L FourThe stroke limit of the construction device 3
The stroke of the climbing mechanism 6
It is necessary to take countermeasures such as re-production so that
It was poor and uneconomical.

【0007】上記事情に鑑み、本発明は効率的、かつ汎
用性の高い建築物の施工装置の上昇方法、及び上昇方法
に用いる中間フレームを提供することを目的としてい
る。
In view of the above circumstances, an object of the present invention is to provide an efficient and highly versatile method of assembling a building construction apparatus, and an intermediate frame used in the ascending method.

【0008】[0008]

【課題を解決するための手段】請求項1記載の発明は、
施工中の建築物の上部に配置されて、資材を揚重し搬送
する搬送機構を有するとともに、作業空間を提供する建
築物の施工装置を、建築物の上部構築に伴い、該建築物
の施工装置に設けたクライミング機構により建築物から
反力をとりながら上昇させる建築物の施工装置の上昇方
法において、前記建築物と前記建築物の施工装置との間
に中間フレームを介在させ、該中間フレームを建築物に
係止させ、該中間フレームより反力をとって建築物の施
工装置を上昇させるとともに、建築物の施工装置の上昇
に伴い該中間フレームも上昇させることを特徴としてい
る。
According to the first aspect of the present invention,
The building construction equipment which is arranged at the top of the building under construction, has a transport mechanism for lifting and transporting materials, and provides a work space. In a method for assembling a building construction apparatus for raising while taking a reaction force from a building by a climbing mechanism provided in the apparatus, an intermediate frame is interposed between the building and the construction apparatus for the building, and the intermediate frame is provided. Is locked to a building, a reaction force is taken from the intermediate frame to raise the building construction device, and the intermediate frame is also raised with the rise of the building construction device.

【0009】請求項2記載の発明は、該中間フレーム
は、建築物の高さ方向に所定間隔をあけて設けられると
ともに、建築物の隣り合う水平部材の間隔よりも部材長
が長く設定された縦部材と、該縦部材の長さ方向に複数
設けられ、建築物の水平部材と係止可能とされた係止部
と、前記縦部材にその長さ方向に沿ってかつ隣り合う水
平部材の中間部に設けられ、かつ建築物の施工装置を支
持しうる複数の施工装置支持部と、を備えることを特徴
としている。
According to a second aspect of the present invention, the intermediate frames are provided at predetermined intervals in the height direction of the building, and the length of the intermediate frames is set longer than the interval between adjacent horizontal members of the building. A vertical member, a plurality of locking members provided in the length direction of the vertical member and capable of locking with the horizontal member of the building, and a horizontal member adjacent to the vertical member along the length direction thereof. And a plurality of construction device support portions that are provided at the intermediate portion and that can support the construction device of the building.

【0010】[0010]

【発明の実施の形態】以下、本発明に係る建築物の施工
装置の上昇方法及び中間フレームの実施形態について、
図1〜図5を用いて説明する。図1の平面図、図2の斜
視図に示すように、建築物1を構成する複数の水平部材
2には、取合ブラケット16aを介して中間フレーム1
2が各々支持されている。また、該中間フレーム12と
建築物1を覆うように配置された施工装置3は、該施工
装置3に備えられる上部カンヌキ4及び下部カンヌキ5
を介して建築物1を構成する水平部材2、2a、2b、
もしくは前記中間フレーム12により突出して設けられ
たブラケット17に設置されている。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of a method for assembling a building construction apparatus and an intermediate frame according to the present invention will be described.
This will be described with reference to FIGS. As shown in the plan view of FIG. 1 and the perspective view of FIG. 2, the plurality of horizontal members 2 constituting the building 1 are connected to the intermediate frame 1 via the connecting bracket 16a.
2 are each supported. Further, the construction device 3 arranged so as to cover the intermediate frame 12 and the building 1 includes an upper kanuki 4 and a lower kanuki 5 provided in the construction device 3.
Horizontal members 2, 2a, 2b constituting the building 1 through
Alternatively, it is installed on a bracket 17 protruding from the intermediate frame 12.

【0011】前記施工装置3は、従来より用いられてい
るものであり、図2に示すように建築物1の施工済み部
分の上部に設置されて、漸次上昇していく本体フレーム
8と、その本体フレーム8を建築物1に対して上昇させ
るために複数個設けられたクライミング機構6と、複数
の該クライミング機構6の上部を連結するように設けら
れた上部フレーム9と、前記本体フレーム8に搭載され
て資材を揚重し搬送する搬送機構(図示しない)と、を
備えている。
The construction device 3 has been conventionally used. The construction device 3 is installed above the constructed portion of the building 1 as shown in FIG. A plurality of climbing mechanisms 6 are provided to raise the main body frame 8 with respect to the building 1, an upper frame 9 provided to connect the upper portions of the plurality of climbing mechanisms 6, and And a transport mechanism (not shown) that is mounted and lifts and transports the material.

【0012】前記本体フレーム8は、建築物1を囲うよ
うに設けられた図示しない鋼材が縦横に組まれたフレー
ム状の構造体であって、クライミング機構6により常に
建築物の施工済み部分の上部に設置されて施工進捗に伴
い、漸次上昇していって上部に盛り替えられていくもの
である。また、本体フレーム8の下面側には搬送機構
(図示しない)が備えられている。該搬送機構は、資材
を揚重(垂直搬送)し、かつ水平搬送するトロリーホイ
ストとその走行レールとなる横行ビーム、昇降ビームか
らなるものである。
The main body frame 8 is a frame-like structure in which steel materials (not shown) provided so as to surround the building 1 are assembled vertically and horizontally. And gradually rises as the construction progresses, and is replaced at the top. A transport mechanism (not shown) is provided on the lower surface side of the main body frame 8. The transport mechanism is composed of a trolley hoist that lifts (vertical transports) materials and transports the materials horizontally, and a traverse beam and a lifting beam serving as a traveling rail.

【0013】また、前記クライミング機構6は、建築物
1の施工済み部分の水平部材2、2a、2bから反力を
取って前記本体フレーム8を上昇させるもので、油圧ジ
ャッキ7と、前記本体フレーム8に備えられた下部カン
ヌキ5と、上部フレーム9に備えられた前記上部カンヌ
キ4と、を備えるものである。
The climbing mechanism 6 raises the main body frame 8 by taking a reaction force from the horizontal members 2, 2a, 2b of the constructed portion of the building 1, and includes a hydraulic jack 7, and the main body frame. 8, and the upper cannula 4 provided on the upper frame 9.

【0014】該油圧ジャッキ7を構成するロッド10の
先端は、前記本体フレーム8の上面に対して垂直に直接
取り付けられているとともに、前記油圧ジャッキ7を構
成するヘッド11の先端近傍には、上部フレーム9が取
り付けられている。該上部フレーム9は、前記本体フレ
ーム8と同様に、建築物1を囲うように設けられた図示
しない鋼材が縦横に組まれたフレーム状の構造体であ
る。
The tip of the rod 10 constituting the hydraulic jack 7 is directly mounted perpendicularly to the upper surface of the main body frame 8, and the top of the head 11 constituting the hydraulic jack 7 is located near the tip. A frame 9 is attached. The upper frame 9 is, like the main body frame 8, a frame-like structure in which steel materials (not shown) provided so as to surround the building 1 are assembled vertically and horizontally.

【0015】なお、本発明の実施形態において、前記ク
ライミング機構6を構成する前記油圧ジャッキ7は上方
にヘッド11、下方にロッド10を有するように鉛直軸
方向に取り付けたが、これに限ることなく下方にヘッド
11、上方にロッド10を有するように鉛直軸方向に取
り付けてもよい。
In the embodiment of the present invention, the hydraulic jack 7 constituting the climbing mechanism 6 is mounted in the vertical axis direction so as to have the head 11 on the upper side and the rod 10 on the lower side. It may be mounted in the vertical axis direction so as to have the head 11 below and the rod 10 above.

【0016】このような前記クライミング機構6を構成
する複数の前記油圧ジャッキ7は、そのロッド10を前
記本体フレーム8に連結固定されるとともに、ヘッド1
1を前記上部フレーム9に連結固定されて、2点支持と
されることにより、常に鉛直軸方向が保持されるもので
ある。本実施の形態において、これら複数の前記油圧ジ
ャッキ7は、前記本体フレーム8の1辺の中央にそれぞ
れ1機づつ備えられているものとしたが、設置位置や設
置個数はこれに限るものではない。また、前記クライミ
ング機構6には油圧ジャッキ7を用いたが、同様の機能
を作用させるものであればこれに限るものではない。
The plurality of hydraulic jacks 7 constituting the climbing mechanism 6 have their rods 10 connected and fixed to the main body frame 8 and the head 1
1 is connected and fixed to the upper frame 9 and is supported at two points, so that the vertical axis direction is always maintained. In the present embodiment, the plurality of hydraulic jacks 7 are provided one by one at the center of one side of the main body frame 8, however, the installation positions and the number of installations are not limited thereto. . In addition, although the hydraulic jack 7 is used for the climbing mechanism 6, it is not limited to this as long as the same function is operated.

【0017】これらクライミング機構6を備える前記施
工装置3は、前記上部カンヌキ4、及び下部カンヌキ5
を介して施工済みの建築物1に支持され、該建築物1か
ら反力を取って前記油圧ジャッキ7の伸縮運動により上
昇することとなる。前記上部カンヌキ4は、前記上部フ
レーム9の内側面で、前記施工装置3の内側に向かって
突出可能なように取り付けられている。また、下部カン
ヌキ5は、前記本体フレーム8の内側面で、かつ上部カ
ンヌキ4の設置位置と鉛直方向に同軸状で、前記施工装
置3の内側に突出可能なように固定されている(図1、
図2参照)。これら前記上部カンヌキ4、及び下部カン
ヌキ5は、前記本体フレーム8の1辺に対して、端部近
傍に対をなすように2機づつ備えられているが、設置位
置や設置個数はこれに限るものではない。
The construction apparatus 3 having the climbing mechanism 6 includes the upper kanuki 4 and the lower kanki 5
Is supported by the constructed building 1 via the construction, and takes a reaction force from the building 1 to rise by the expansion and contraction movement of the hydraulic jack 7. The upper cannula 4 is attached to the inner surface of the upper frame 9 so as to be able to protrude toward the inside of the construction device 3. The lower kanuki 5 is fixed on the inner surface of the main body frame 8 and coaxially in the vertical direction with the installation position of the upper kanuki 4 so as to be able to protrude inside the construction device 3 (FIG. 1). ,
(See FIG. 2). The upper canker 4 and the lower canker 5 are provided two by two so as to form a pair near one end with respect to one side of the main body frame 8, but the installation position and the number of installation are not limited thereto. Not something.

【0018】一方、建築物1を構成する水平部材2と、
該水平部材2より一段低い位置に取り付けられた水平部
材2aには、取合ブラケット16aを介して前記中間フ
レーム12が支持されている(図3参照)。該中間フレ
ーム12は、建築物1の高さ方向に所定間隔を空けて配
置された対をなす縦部材13と、これらを連結するよう
に梯子状に取り付けられた連結梁14a、14bと、中
間連結梁15a、15bと、より構成されている。
On the other hand, a horizontal member 2 constituting the building 1
The intermediate frame 12 is supported by a horizontal member 2a mounted at a position one step lower than the horizontal member 2 via a mounting bracket 16a (see FIG. 3). The intermediate frame 12 includes a pair of vertical members 13 arranged at predetermined intervals in the height direction of the building 1, connecting beams 14 a and 14 b attached in a ladder shape so as to connect them, and an intermediate frame 12. It is composed of connecting beams 15a and 15b.

【0019】前記縦部材13は、前記施工装置3の荷重
が作用した際にも変形しないような鋼材等の剛性部材よ
りなる角形棒材で、前記水平部材2、2a、2bの部材
長さL1より狭く、かつ前記施工装置3の上部カンヌキ
4、及び下部カンヌキ5の取付幅内に収まる程度の間隔
2を持って並行に配置されている。また、部材長L3
前記水平部材2の配置間隔L4よりも長く、水平部材2
の配置間隔L4の2倍より短い程度の長さを有するもの
である。
The vertical member 13 is a rectangular rod made of a rigid member such as steel which does not deform even when the load of the construction device 3 is applied, and the length L of the horizontal members 2, 2a and 2b is L. They are arranged in parallel with a distance L 2 that is smaller than 1 and that is within the mounting width of the upper kanuki 4 and the lower kanki 5 of the construction device 3. Further, the member length L 3 is longer than the arrangement interval L 4 of the horizontal members 2,
The degree less than twice the arrangement interval L 4 of those having a length.

【0020】この対をなす該縦部材13の前記建築物1
と対向する側面13bには各々、前記建築物1を構成す
る水平部材2、2aと同じ配置間隔L4の位置に、該水
平部材2、2aに係止可能とされた係止部である取合ブ
ラケット16a、16aが適宜固定手段により固定され
ている。また、該取合ブラケット16a、16aとの中
間部の近傍位置、及びこの位置から間隔L4だけ下方の
近傍位置にも同じように、該縦部材13の前記建築物1
と対向する側面13bに取合ブラケット16b、16b
が適宜固定手段により固定されている。
The building 1 of the pair of vertical members 13
Each on a side surface 13b which faces and, in the position of the same arrangement interval L 4 and horizontal members 2,2a constituting the building 1, taken on the horizontal member 2,2a is lockable and has been engaging portion The brackets 16a, 16a are appropriately fixed by fixing means. Further, it said mounting engagement bracket 16a, a position near the intermediate part of the 16a, and also in the same way in the vicinity of the downwardly from this position by a distance L 4, the building of the vertical member 13 1
Mounting brackets 16b, 16b
Are appropriately fixed by fixing means.

【0021】また、対をなす該縦部材13には、これら
を連結するように前記取合ブラケット16a、16aと
同様の高さ位置に前記連結梁14a、14bと、前記取
合ブラケット16b、16bと同じ程度で約上部の高さ
位置に中間連結梁15a、15bが適宜固定手段を用い
て、梯子状に締結されている。該連結梁14a、14b
と、中間連結梁15a、15bは、前記縦部材13と同
様に、施工装置3の荷重が作用した際にも変形しないよ
うな鋼材等の剛性部材よりなる角形棒材である。該中間
フレーム12が、建築物1の水平部材2、2aに前記取
合ブラケット16a、16aを介して支持されている状
態では、連結梁14a、14bは水平部材2、2aと同
様の高さに位置し、前記対をなす該縦部材13の向かい
合う側面13a同士を連結するように取り付けられてい
る。
The pair of vertical members 13 are connected to the connecting beams 14a, 14b and the connecting brackets 16b, 16b at the same height as the connecting brackets 16a, 16a so as to connect them. The intermediate connecting beams 15a and 15b are fastened in a ladder-like manner at approximately the same height as the above by using fixing means as appropriate. The connecting beams 14a, 14b
The intermediate connecting beams 15a and 15b are, similarly to the vertical members 13, rectangular bars made of a rigid member such as a steel material so as not to be deformed even when a load of the construction device 3 is applied. When the intermediate frame 12 is supported by the horizontal members 2 and 2a of the building 1 via the connecting brackets 16a and 16a, the connecting beams 14a and 14b have the same height as the horizontal members 2 and 2a. It is attached so as to connect the side surfaces 13a of the pair of vertical members 13 facing each other.

【0022】一方、該中間フレーム12が、建築物1の
水平部材2、2aに前記取合ブラケット16a、16a
を介して支持されている状態では、中間連結梁15a、
15bは、水平部材2、2aの中間部程度の高さ、およ
び水平部材2aと該水平部材2aより一段低い位置の水
平部材2bとの中間部程度の高さに位置しており、前記
対をなす該縦部材13の前記建築物1と対向する側面1
3bに、それぞれ固定手段により固定されている。ま
た、これらの部材長L5は前記縦部材13の設置間隔L2
とほぼ同程度で、その両端には対をなす該縦部材13よ
り外方へ張り出すように、前記施工装置3の上部カンヌ
キ4及び下部カンヌキ5を受けることにより前記施工装
置3を支持する施工装置支持部であるブラケット17が
備えられている。
On the other hand, the intermediate frame 12 is attached to the horizontal members 2, 2a of the building 1 by the connecting brackets 16a, 16a.
In the state supported through the intermediate connecting beam 15a,
15b is located at a height of about the middle of the horizontal members 2 and 2a, and at a height of about the middle of the horizontal member 2a and the horizontal member 2b at a position one step lower than the horizontal member 2a. The side surface 1 of the vertical member 13 facing the building 1
3b are respectively fixed by fixing means. Further, installation interval L 2 of these members length L 5 represents the longitudinal member 13
And supporting the construction device 3 by receiving the upper kanuki 4 and the lower kanuki 5 of the construction device 3 at both ends thereof so as to protrude outward from the pair of longitudinal members 13. A bracket 17 as a device support is provided.

【0023】該ブラケット17は、前記中間連結梁15
a、15b内に格納自在となっており、施工装置3が中
間フレーム12を利用して上昇する際には外方へ張り出
しているが、該中間フレーム12自身を上昇させる際に
は、格納した状態としておくものである。なお、本実施
の形態において、該ブラケット17は、前記中間連結梁
15a、15b内に格納自在としたが、該中間フレーム
12内に収納でき、かつ前記施工装置3を支持する強度
を備えていればこのような構造に限るものではない。
The bracket 17 is connected to the intermediate connecting beam 15.
a, 15b, which can be stored freely, and extends outward when the construction apparatus 3 ascends using the intermediate frame 12, but is stored when the intermediate frame 12 itself is raised. It is a state to keep. In the present embodiment, the bracket 17 is storable in the intermediate connecting beams 15a and 15b. However, the bracket 17 can be stored in the intermediate frame 12 and has sufficient strength to support the construction device 3. It is not limited to such a structure.

【0024】上述するような構成による前記中間フレー
ム12は、前記建築物1の外側面毎に各々配置されるこ
ととなる。さらに、これら前記建築物1に支持された中
間フレーム12の外周を覆うように、前記施工装置3が
配置されている。また、これら施工装置3は、施工作業
時には前記建築物1の水平部材2aに上部カンヌキ4を
連結支持されるとともに、前記水平部材2bに下部カン
ヌキ5を連結支持された状態で静止しており(図4−A
参照)、上昇する際には該施工装置3は、前記中間フレ
ーム12、及び前記建築物1の水平部材2、2a、2b
を利用して尺取り虫状に上昇することとなる。
The intermediate frames 12 having the above-described configuration are arranged on each outer side of the building 1. Further, the construction device 3 is arranged so as to cover the outer periphery of the intermediate frame 12 supported by the building 1. In addition, these construction devices 3 are stationary at the time of construction work, with the upper kanuki 4 being connected and supported by the horizontal member 2a of the building 1 and the lower kanuki 5 being connected and supported by the horizontal member 2b ( FIG. 4-A
), When ascending, the construction device 3 moves the intermediate frame 12 and the horizontal members 2, 2a, 2b of the building 1.
It will rise in the shape of a scale insect by using.

【0025】次に、本発明の中間フレーム12を用いた
前記施工装置3の上昇方法を以下に示す。前記施工装置
3は、通常の施工作業時において前記下部カンヌキ5を
突出させて前記建築物1の水平部材2bに支持されると
ともに、前記上部カンヌキ4を突出させて前記水平部材
2bより一段高い位置に配置された水平部材2aに支持
されることによって、前記建築物1に固定されている
(図4−A参照)。
Next, a method of lifting the construction apparatus 3 using the intermediate frame 12 of the present invention will be described below. The construction device 3 is supported by the horizontal member 2b of the building 1 by protruding the lower kanuki 5 during normal construction work, and is protruded by the upper kanuki 4 to a position one step higher than the horizontal member 2b. Is fixed to the building 1 by being supported by the horizontal member 2a disposed at the same position (see FIG. 4-A).

【0026】この状態において、前記建築物1を上方に
延長するような工程が終了した後、前記施工装置3は、
前記下部カンヌキ5を引込み前記水平部材2bから取り
離すとともに(図4−B参照)、前記油圧ジャッキ7を
短縮させて、前記下部カンヌキ5が前記中間フレーム1
2の下方に配置された前記中間連結梁15b位置に達し
た時点で(図4−C参照)、先ほど引込めた下部カンヌ
キ5を再度突出させることにより、該中間連結梁15b
より突出したブラケット17に連結支持される(図4−
D参照)。
In this state, after the process of extending the building 1 upward is completed, the construction device 3
The lower cannus 5 are retracted and separated from the horizontal member 2b (see FIG. 4B), and the hydraulic jacks 7 are shortened so that the lower cannus 5 are connected to the intermediate frame 1.
When the intermediate connecting beam 15b is located below the second connecting beam 15b (see FIG. 4C), the lower cannus 5, which has been retracted earlier, is again protruded to thereby provide the intermediate connecting beam 15b.
It is connected and supported by the bracket 17 which protrudes more (FIG. 4-
D).

【0027】この後、前記上部カンヌキ4を引き込み前
記水平部材2aより取り離し(図4−E参照)、前記油
圧ジャッキ7を伸長させて、上部カンヌキ4が前記中間
フレーム12の上方に配置された前記中間連結梁15a
の位置に達した時点で(図4−F参照)、先ほど引込め
た上部カンヌキ4を再度突出させて、該中間連結梁15
aより突出したブラケット17に連結支持される(図4
−G参照)。これらの動作を繰り返すことにより、前記
施工装置3は、前記建築物1を上昇していくものであ
る。前記施工装置3の上部カンヌキ4が、建築物1の水
平部材2に達した後、今度は中間フレーム12を建築物
1に対して上昇させる。
Thereafter, the upper canker 4 is pulled in and separated from the horizontal member 2a (see FIG. 4E), and the hydraulic jack 7 is extended, so that the upper canker 4 is disposed above the intermediate frame 12. The intermediate connecting beam 15a
(See FIG. 4F), the upper cannus 4 retracted earlier are again projected, and the intermediate connecting beams 15
4A is connected to and supported by a bracket 17 protruding from FIG.
-G). By repeating these operations, the construction device 3 moves up the building 1. After the upper canker 4 of the construction device 3 reaches the horizontal member 2 of the building 1, the intermediate frame 12 is raised with respect to the building 1 this time.

【0028】次に、前記中間フレーム12の上昇方法を
以下に示す。前記施工装置3は、先に述べたように前記
下部カンヌキ5を突出させて前記建築物1の水平部材2
bに連結支持されるとともに、前記上部カンヌキ4を突
出させてを前記水平部材2bより一段高い位置に取り付
けられた水平部材2aに連結支持されている(図5−A
参照)。なお、図5−Aは、前記施工装置3が図3−G
の状態から前記建築物1の施工済み部分の上部にまで達
した後、新たに前記施工装置3より上部に建築物1の施
工が終了した状態を示している。
Next, the method of raising the intermediate frame 12 will be described below. As described above, the construction device 3 projects the lower cannus 5 to project the horizontal member 2 of the building 1.
b and connected to and supported by a horizontal member 2a mounted at a position one step higher than the horizontal member 2b with the upper cannula 4 protruding (FIG. 5-A).
reference). In addition, FIG.
After reaching the upper part of the completed portion of the building 1 from the state of the above, the construction of the building 1 is newly completed above the construction device 3.

【0029】また、前記中間フレーム12を上昇させる
際には、中間連結梁15a、15bより突出したブラケ
ット17をあらかじめ該中間連結梁15a、15bに格
納しておく。
When the intermediate frame 12 is raised, the brackets 17 protruding from the intermediate connecting beams 15a and 15b are stored in advance in the intermediate connecting beams 15a and 15b.

【0030】この状態において、前記上部カンヌキ4が
前記水平部材2aに連結支持された状態のまま、前記下
部カンヌキ5を前記水平部材2bより取り離し、中間フ
レーム12の下方に配置された前記連結梁14bと同じ
高さ位置の前記縦部材13の外側面、もしくは同高さの
取り合いブラケット16aにボルト等の締結手段を介し
て連結し、施工装置3と中間フレーム12を一体化する
(図5−B参照)。さらに、前記油圧ジャッキ7を短縮
させて、前記下部カンヌキ5と一体となって上昇する中
間フレーム12の前記中間連結梁15aが、前記建築物
1の水平部材2aの位置に達した時点で(図5−C参
照)、該中間連結梁15a、15bの約下部に設けられ
た取合ブラケット16bを水平部材2a、2bに支持さ
せる(図5−D参照)。これにより、前記水平部材2a
には前記施工装置3の前記上部カンヌキ4と、中間フレ
ーム12の該取合ブラケット16bが連結支持された状
態となっている。
In this state, the lower cannula 5 is separated from the horizontal member 2b while the upper cannula 4 is connected and supported by the horizontal member 2a, and the connecting beam disposed below the intermediate frame 12 is removed. The outer surface of the vertical member 13 at the same height as 14b, or the mounting bracket 16a at the same height is connected via a fastening means such as a bolt to integrate the construction device 3 and the intermediate frame 12 (FIG. 5). B). Further, when the hydraulic jack 7 is shortened and the intermediate connecting beam 15a of the intermediate frame 12, which rises integrally with the lower cannula 5, reaches the position of the horizontal member 2a of the building 1 (see FIG. 5C), and the horizontal members 2a and 2b support the connecting bracket 16b provided at a lower portion of the intermediate connecting beams 15a and 15b (see FIG. 5D). Thereby, the horizontal member 2a
The upper bracket 4b of the construction device 3 and the coupling bracket 16b of the intermediate frame 12 are connected and supported.

【0031】この状態で、前記連結梁14bより取り離
した後、前記下部カンヌキ5を引き込み(図5−E参
照)、前記油圧ジャッキ7を下方に伸長させる。下部カ
ンヌキ5が中間フレーム12の下方に配置された前記中
間連結梁15b高さに達した時点で、下部カンヌキ5を
前記中間連結梁15bと同じ高さ位置の前記縦部材13
の外側面、もしくは同高さの取り合いブラケット16a
にボルト等の締結手段を介して連結し、再度施工装置3
と中間フレーム12を一体化させる(図5−F参照)。
再度、前記クライミング機構6を短縮させて下部カンヌ
キ5と一体となった中間フレーム12を上昇させ、中間
フレーム12の上方に配置された前記連結梁14aが前
記建築物1の水平部材2に達した時点で、中間フレーム
12の連結梁14a、14bに設けられた取合ブラケッ
ト16aをそれぞれ前記建築物の水平部材2、2aに連
結支持する(図5−G参照)。
In this state, after detaching from the connecting beam 14b, the lower cannula 5 is pulled in (see FIG. 5E), and the hydraulic jack 7 is extended downward. When the lower cannus 5 reach the height of the intermediate connecting beams 15b disposed below the intermediate frame 12, the lower cannus 5 are moved to the vertical members 13 at the same height position as the intermediate connecting beams 15b.
Outer surface or the same height of the bracket 16a
To the construction device 3 again by fastening means such as bolts.
And the intermediate frame 12 (see FIG. 5-F).
Again, the climbing mechanism 6 is shortened to raise the intermediate frame 12 integrated with the lower cannula 5, and the connecting beam 14a disposed above the intermediate frame 12 reaches the horizontal member 2 of the building 1. At this point, the connecting brackets 16a provided on the connecting beams 14a, 14b of the intermediate frame 12 are connected and supported on the horizontal members 2, 2a of the building, respectively (see FIG. 5-G).

【0032】このように、前記施工装置3は前記中間フ
レーム12を用いて前記建築物1を上昇し、中間フレー
ム12の上端に達した時点で中間フレーム12を上昇さ
せることを繰り返すことにより、順次施工済みの建築物
1の上方に位置するものである。
As described above, the construction apparatus 3 raises the building 1 using the intermediate frame 12, and repeatedly raises the intermediate frame 12 when the building 1 reaches the upper end of the intermediate frame 12. It is located above the constructed building 1.

【0033】なお、本発明の実施の形態において、前記
中間フレーム12に配置された前記中間連結梁15a、
15bは、建築物1の水平部材2、2a、2bの配置間
隔L 4 を2分割する高さ位置に設けたが、これに限る
ことはなく、該水平部材2、2a、2bの配置間隔L
4 が大きい場合には、配置間隔L4 を複数分割するよ
うな高さ位置に前記中間連結梁15a、15bを複数本
固定しても良い。
Note that, in the embodiment of the present invention,
The intermediate connecting beam 15a disposed on the intermediate frame 12,
15b is between the arrangement of the horizontal members 2, 2a, 2b of the building 1.
Interval L FourIs provided at the height position where it is divided into two, but is not limited to this.
The arrangement interval L of the horizontal members 2, 2a, 2b
FourIs large, the arrangement interval LFour Will be divided into multiple
A plurality of the intermediate connection beams 15a and 15b
It may be fixed.

【0034】また、本発明は上記実施形態にとらわれる
ことなく、各部の構成や施工手順の細部は、施工すべき
建築物の形態や規模等に応じて適宜の設計的変更が可能
であることは言うまでもない。
Further, the present invention is not limited to the above-described embodiment, and the details of the configuration of each part and the construction procedure can be appropriately changed according to the form and scale of the building to be constructed. Needless to say.

【0035】上述の構成によれば、前記施工装置3の上
昇は、建築物1及び中間フレーム12より反力を得て行
われるため、中間フレーム12の前記中間連結梁15
a、15bの配置間隔を適宜対応させることにより、前
記クライミング機構6のストロークは、施工する建築物
1に配置された水平部材2、2a、2bの配置間隔L4
に影響されることが無くなるため、前記施工装置3を汎
用的に用いることが可能となる。
According to the above-described structure, the construction apparatus 3 is lifted by receiving a reaction force from the building 1 and the intermediate frame 12.
a, by associating appropriate arrangement interval 15b, the stroke of the climbing mechanism 6, the construction is building 1 arranged horizontal member 2, 2a, 2b arrangement interval L 4 of
The construction apparatus 3 can be used for general purposes because the construction apparatus 3 is not affected by the above.

【0036】また、施工する建築物1に配置された水平
部材2、2a、2bの配置間隔L4により、前記施工装
置3の前記クライミング機構6を製作し直す必要がない
ため、大幅なコスト縮減に寄与することが可能となる。
Further, the construction is building 1 arranged horizontal member 2, 2a, the arrangement interval L 4 of 2b, since there is no need to re-manufacture the climbing mechanism 6 of the working device 3, significant cost reduction It is possible to contribute to.

【0037】さらに、前記施工装置3の上昇に用いる中
間フレーム12は、構成部材に山留鋼材を転用すること
が可能であるため、さらにコスト縮減に寄与することが
可能となるとともに、資源の有効活用を図ることも可能
となる。
Further, since the intermediate frame 12 used for raising the construction apparatus 3 can use diverted steel materials for the constituent members, it can contribute to further cost reduction and use resources efficiently. It will also be possible to utilize it.

【0038】[0038]

【発明の効果】請求項1記載の発明は、施工中の建築物
の上部に配置されて、資材を揚重し搬送する搬送機構を
有するとともに、作業空間を提供する建築物の施工装置
を、建築物の上部構築に伴い、該建築物の施工装置に設
けたクライミング機構により建築物から反力をとりなが
ら上昇させる建築物の施工装置の上昇方法において、前
記建築物と前記建築物の施工装置との間に中間フレーム
を介在させ、該中間フレームを建築物に係止させ、該中
間フレームより反力をとって建築物の施工装置を上昇さ
せるとともに、建築物の施工装置の上昇に伴い該中間フ
レームも上昇させることから、中間フレームの中間連結
梁の配置間隔を適宜対応させることにより、前記クライ
ミング機構のストロークは、施工する建築物に配置され
た水平部材の配置間隔L4に影響されることが無くなる
ため、施工装置を汎用的に用いることが可能となる。ま
た、施工する建築物に配置された水平部材の配置間隔L
4により、施工装置のクライミング機構を製作し直す必
要がないため、大幅なコスト縮減に寄与することが可能
となる。
According to the first aspect of the present invention, there is provided a building construction apparatus which is disposed above a building under construction, has a transport mechanism for lifting and transporting materials, and provides a work space. In a method for assembling a building construction device in which a climbing mechanism provided in the construction device of the building rises while taking a reaction force from the building along with the upper construction of the building, the building and the construction device of the building An intermediate frame is interposed between the intermediate frame and the intermediate frame, the intermediate frame is locked to the building, and a reaction force is taken from the intermediate frame to raise the construction equipment of the building. Since the intermediate frame is also raised, the stroke of the climbing mechanism can be adjusted by appropriately setting the arrangement interval of the intermediate connecting beams of the intermediate frame, thereby disposing the horizontal members arranged on the building to be constructed. Since it is no longer is influenced by the interval L 4, it is possible to use a construction device universally. In addition, the arrangement interval L of the horizontal members arranged in the building to be constructed
According to 4 , it is not necessary to remanufacture the climbing mechanism of the construction apparatus, and it is possible to greatly contribute to cost reduction.

【0039】請求項2記載の発明は、該中間フレーム
は、建築物の高さ方向に所定間隔をあけて設けられると
ともに、建築物の隣り合う水平部材の間隔よりも部材長
が長く設定された縦部材と、該縦部材の長さ方向に複数
設けられ、建築物の水平部材と係止可能とされた係止部
と、前記縦部材にその長さ方向に沿ってかつ隣り合う水
平部材の中間部に設けられ、かつ建築物の施工装置を支
持しうる複数の施工装置支持部と、を備えることから、
構造が簡略で製作が容易であるとともに、中間フレーム
を構成する部材に、山留鋼材を転用することが可能であ
るため、さらにコスト縮減に寄与することが可能となる
とともに、資源の有効活用を図ることも可能となる。
According to a second aspect of the present invention, the intermediate frames are provided at predetermined intervals in the height direction of the building, and the length of the intermediate frames is set longer than the interval between adjacent horizontal members of the building. A vertical member, a plurality of locking members provided in the length direction of the vertical member and capable of locking with the horizontal member of the building, and a horizontal member adjacent to the vertical member along the length direction thereof. With a plurality of construction device support parts that are provided in the middle part and that can support the construction device of the building,
The structure is simple and easy to manufacture.Besides, it is possible to divert the buckle steel material to the members that constitute the intermediate frame, which can contribute to further cost reduction and effective use of resources. It is also possible to plan.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明に係る施工装置と中間フレームの配置
状況を示す平面図である。
FIG. 1 is a plan view showing an arrangement state of a construction apparatus and an intermediate frame according to the present invention.

【図2】 本発明に係る施工装置と中間フレームの配置
状況を示す斜視図である。
FIG. 2 is a perspective view showing an arrangement state of a construction apparatus and an intermediate frame according to the present invention.

【図3】 本発明に係る中間フレームの詳細を示す図で
ある。
FIG. 3 is a diagram showing details of an intermediate frame according to the present invention.

【図4】 本発明に係る施工装置の上昇方法を示す図で
ある。
FIG. 4 is a view showing a method of lifting the construction apparatus according to the present invention.

【図5】 本発明に係る中間フレームの上昇方法を示す
図である。
FIG. 5 is a diagram illustrating a method of raising an intermediate frame according to the present invention.

【図6】 従来の施工装置の配置状況を示す平面図であ
る。
FIG. 6 is a plan view showing an arrangement state of a conventional construction apparatus.

【図7】 従来の施工装置の上昇方法を示す図である。FIG. 7 is a view showing a method of lifting a conventional construction apparatus.

【符号の説明】[Explanation of symbols]

1 建築物 2 水平部材 2a 水平部材 2b 水平部材 3 施工装置 4 上部カンヌキ 5 下部カンヌキ 6 クライミング機構 7 油圧ジャッキ 8 本体フレーム 9 上部フレーム 10 ロッド 11 ヘッド 12 中間フレーム 13 縦部材 14a 連結梁 14b 連結梁 15a 中間連結梁 15b 中間連結梁 16a 取合ブラケット(係止部) 16b 取合ブラケット(係止部) 17 ブラケット(施工装置支持部) DESCRIPTION OF SYMBOLS 1 Building 2 Horizontal member 2a Horizontal member 2b Horizontal member 3 Construction apparatus 4 Upper kanuki 5 Lower kanuki 6 Climbing mechanism 7 Hydraulic jack 8 Main frame 9 Upper frame 10 Rod 11 Head 12 Intermediate frame 13 Vertical member 14a Connecting beam 14b Connecting beam 15a Intermediate connecting beam 15b Intermediate connecting beam 16a Connection bracket (locking portion) 16b Connection bracket (locking portion) 17 Bracket (construction device support portion)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 施工中の建築物の上部に配置されて、資
材を揚重し搬送する搬送機構を有するとともに、作業空
間を提供する建築物の施工装置を、建築物の上部構築に
伴い、該建築物の施工装置に設けたクライミング機構に
より建築物から反力をとりながら上昇させる建築物の施
工装置の上昇方法において、 前記建築物と前記建築物の施工装置との間に中間フレー
ムを介在させ、該中間フレームを建築物に係止させ、該
中間フレームより反力をとって建築物の施工装置を上昇
させるとともに、建築物の施工装置の上昇に伴い該中間
フレームも上昇させることを特徴とする建築物の施工装
置の上昇方法。
Claims: 1. A building construction device which is arranged above a building under construction, lifts and transports materials, and provides a work space. In a method of assembling a building construction apparatus for raising while taking a reaction force from a building by a climbing mechanism provided in the building construction apparatus, an intermediate frame is interposed between the building and the building construction apparatus. The intermediate frame is locked to a building, and a reaction force is taken from the intermediate frame to raise the building construction device, and the intermediate frame is also raised with the rise of the building construction device. Method of raising construction equipment for buildings.
【請求項2】 請求項1記載の建築物の施工装置の上昇
方法を実施する上で使用する中間フレームであって、 該中間フレームは、建築物の高さ方向に所定間隔をあけ
て設けられるとともに、建築物の隣り合う水平部材の間
隔よりも部材長が長く設定された縦部材と、該縦部材の
長さ方向に複数設けられ、建築物の水平部材と係止可能
とされた係止部と、前記縦部材にその長さ方向に沿って
かつ隣り合う水平部材の中間部に設けられ、かつ建築物
の施工装置を支持しうる複数の施工装置支持部と、を備
えることを特徴とした中間フレーム。
2. An intermediate frame used for carrying out the method for lifting a building construction apparatus according to claim 1, wherein the intermediate frames are provided at predetermined intervals in a height direction of the building. In addition, a vertical member having a member length set longer than an interval between adjacent horizontal members of a building, and a plurality of locking members provided in the length direction of the vertical member so as to be lockable with the horizontal member of the building And a plurality of construction device support portions that are provided along the length direction of the vertical member and at an intermediate portion between adjacent horizontal members, and that can support a construction device of a building, Intermediate frame.
JP2001165738A 2001-05-31 2001-05-31 Method of ascending building construction apparatus and intermediate frame Expired - Fee Related JP3707009B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001165738A JP3707009B2 (en) 2001-05-31 2001-05-31 Method of ascending building construction apparatus and intermediate frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001165738A JP3707009B2 (en) 2001-05-31 2001-05-31 Method of ascending building construction apparatus and intermediate frame

Publications (2)

Publication Number Publication Date
JP2002356996A true JP2002356996A (en) 2002-12-13
JP3707009B2 JP3707009B2 (en) 2005-10-19

Family

ID=19008371

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001165738A Expired - Fee Related JP3707009B2 (en) 2001-05-31 2001-05-31 Method of ascending building construction apparatus and intermediate frame

Country Status (1)

Country Link
JP (1) JP3707009B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014005592A (en) * 2012-06-21 2014-01-16 Taihei Dengyo Kaisha Ltd Mobile heavy object lifting device
CN114988252A (en) * 2022-05-30 2022-09-02 浙江崇德建设有限公司 Lift for construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014005592A (en) * 2012-06-21 2014-01-16 Taihei Dengyo Kaisha Ltd Mobile heavy object lifting device
CN114988252A (en) * 2022-05-30 2022-09-02 浙江崇德建设有限公司 Lift for construction
CN114988252B (en) * 2022-05-30 2023-08-01 浙江崇德建设有限公司 Elevator for construction

Also Published As

Publication number Publication date
JP3707009B2 (en) 2005-10-19

Similar Documents

Publication Publication Date Title
JP6893188B2 (en) Demolition system and demolition method of existing structures
JP5914203B2 (en) Disassembly method, disassembly assistance device
JP5421143B2 (en) Overhead crane installation equipment
JP2909413B2 (en) Suspension device for building exterior walls
JP2002356996A (en) Method of lifting building construction device, and intermediate frame
JP2019015151A (en) Demolition system of existing structure
JPH0812262A (en) Installing method for overhead traveller and its device
JP2002046951A (en) Scaffold apparatus for maintenance of elevator
JPH06212803A (en) Composite jack device for push-up and pull-up
JP6967383B2 (en) How to dismantle an existing structure
JP2890341B2 (en) Method and apparatus for lifting up top-level frame for structure construction
JP2008063873A (en) Transfer mechanism of ceiling and execution method
JP2000191270A (en) Elevating mechanism and construction machine
JP6956651B2 (en) Lifting method of escalator truss
JP3179814B2 (en) Column and beam construction method and apparatus
JP6893136B2 (en) Demolition system for existing structures
JP4296547B2 (en) Full PC column lifting method and lifting jig
JP2592980B2 (en) Construction method of steel frame material for high-rise structure
JP2985537B2 (en) Building construction platform
JP3553370B2 (en) Work stage device for steel tower construction and steel tower construction method
JP2791749B2 (en) Method and apparatus for lifting up top-level frame for structure construction
JP2738276B2 (en) Sliding formwork device
JP2781671B2 (en) Building erection method and building elevating device
JP2020186548A (en) Method for installing elevating type scaffold
JPH06280396A (en) Jack up building constructing apparatus

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050617

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050628

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050720

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees