JP2002351524A - Process scheduler system - Google Patents

Process scheduler system

Info

Publication number
JP2002351524A
JP2002351524A JP2001155253A JP2001155253A JP2002351524A JP 2002351524 A JP2002351524 A JP 2002351524A JP 2001155253 A JP2001155253 A JP 2001155253A JP 2001155253 A JP2001155253 A JP 2001155253A JP 2002351524 A JP2002351524 A JP 2002351524A
Authority
JP
Japan
Prior art keywords
schedule
production
procurement
ordering
scheduler system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001155253A
Other languages
Japanese (ja)
Inventor
Tetsuo Aino
哲男 相野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Solution Innovators Ltd
Original Assignee
NEC Solution Innovators Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEC Solution Innovators Ltd filed Critical NEC Solution Innovators Ltd
Priority to JP2001155253A priority Critical patent/JP2002351524A/en
Publication of JP2002351524A publication Critical patent/JP2002351524A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a technology on a process scheduler system, that can reduce a stock of subcontracted parts and a stock in process by performing smooth process control time sequentially by integrating the date of delivery of subcontracted key parts into production process control, reducing manhour needing manual imputing and performing delivery control from a subcontractor. SOLUTION: As shown in Figure 1, this process scheduler system generally comprises a process scheduling device (process scheduling means, computer and data processor) 100, an input processing part 105 and an output processing part (output processing means) 51.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、製品を生産する上
で作業工程、設備及び外部調達品納期を含む生産スケジ
ュールを自動生成する工程スケジュラーシステムに関す
る技術に属する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technology relating to a process scheduler system for automatically generating a production schedule including a work process, equipment, and a delivery date of an externally procured product in producing a product.

【0002】[0002]

【従来の技術】従来、各種製品の製造工場における各製
造工程の工程管理システムとしてスケジューリングシス
テムが知られている。従来技術のスケジューリングシス
テムは、工場などの日程計画を検討する際に用いられて
おり、スケジューラーとシミュレータとから構成されて
いる。ここで、「スケジューラー」とは、日程を計画す
るシステムであり、所定の作業の開始から当該作業の終
了に至る迄の時系列的な一連の工程計画に基づき、自動
又は手動で日程計画を行うためのものである。また、
「シミュレータ」とは、工場の設備能力等、当該シミュ
レータでのデータ処理の基礎となるデータをデータベー
スと登録しており、スケジューラーで計画した日程を時
間軸で考慮しながら模擬することができるようにしたも
のである。
2. Description of the Related Art Conventionally, a scheduling system has been known as a process management system for each manufacturing process in a manufacturing factory of various products. 2. Description of the Related Art A conventional scheduling system is used when examining a schedule of a factory or the like, and includes a scheduler and a simulator. Here, the “scheduler” is a system for planning a schedule, and automatically or manually schedules a schedule based on a series of time-series process plans from the start of a predetermined work to the end of the work. It is for. Also,
A "simulator" is a database in which data that is the basis for data processing in the simulator, such as the equipment capacity of a factory, is registered in a database. The schedule can be simulated while considering the schedule planned by the scheduler on a time axis. It was done.

【0003】また、従来技術のスケジューリングシステ
ムは、スケジューラーで計画した日程を忠実にシミュレ
ーションを行うことで、計画した日程の妥当性を検証す
る目的で用いられている。
The prior art scheduling system is used to verify the validity of the planned schedule by faithfully simulating the schedule scheduled by the scheduler.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、従来技
術には以下に掲げる問題点があった。
However, the prior art has the following problems.

【0005】従来のスケジューリングシステムは、スケ
ジューラーで計画した日程を忠実にシミュレーションを
行うことで、計画した日程の妥当性を検証する目的で用
いられている。従って、外部調達品が納入されてから作
業を行う関係について連携がとられていないため、実体
と異なる日程計画になってしまう。即ち、従来技術のス
ケジューリングシステムでは、通常業務としての部材発
注システムと遊離しているため、外部調達品の納期と連
動した作業工程のスケジュールができていない。また、
連動することができても再度部材発注データを手入力す
る必要があり、手間がかかるという問題点があった。
The conventional scheduling system is used for verifying the validity of the planned schedule by faithfully simulating the schedule scheduled by the scheduler. Therefore, there is no coordination between the externally procured products and the work performed after the delivery, so that the schedule is different from the actual one. That is, in the scheduling system of the related art, since it is separated from the component ordering system as a normal business, the schedule of the work process linked to the delivery date of the externally procured product cannot be made. Also,
Even if they can be linked, it is necessary to manually input the member order data again, which is troublesome.

【0006】本発明は斯かる問題点を鑑みてなされたも
のであり、その目的とするところは、外部発注されるキ
ー部品の納入時期を生産での工程管理に組入れることで
時系列的に円滑な工程管理を行い、手入力を必要とする
工数の削減と外注先からの納入コントロールとを行い、
外注部品の在庫や仕掛在庫の削減を可能とする工程スケ
ジュラーシステムに関する技術を提供することを目的と
する。
The present invention has been made in view of such a problem, and an object of the present invention is to incorporate a delivery time of a key part to be ordered externally into a process control in production, so that a time series can be smoothly controlled. Process management, reduce man-hours requiring manual input, and control delivery from subcontractors.
It is an object of the present invention to provide a technology relating to a process scheduler system capable of reducing the stock of outsourced parts and the work-in-process stock.

【0007】[0007]

【課題を解決するための手段】請求項1記載の本発明の
要旨は、生産スケジュールを自動生成するための工程ス
ケジュラーシステムであって、自社工場外に対するキー
部品発注データの取込みを行う部材発注情報取込手段
と、生産に関する工程展開を行う日程展開処理手段とを
備え、該日程展開処理手段は、前記キー部品発注データ
に対応するキー部品の発注から納品までの外部調達品工
程と相関する工程に対して、前記外部調達品工程を最優
先に割付ける優先工程割付処理部と、生産計画における
自社工場の負荷オーバ時など外注先に対して前記キー部
品発注データに該当する生産工程の新規委託や既に委託
した生産工程の変更を含む外注先委託変更の設定を行う
日程調整設定部とを有することを特徴とする工程スケジ
ュラーシステムに存する。請求項2記載の本発明の要旨
は、前記部材発注情報取込手段は、外部の部材発注シス
テムに接続されて、該部材発注システムにおける発注情
報に連動した前記キー部品発注データを取込み、前記日
程展開処理手段は、取込まれた前記キー部品発注データ
に基づく前記外部調達品工程を優先工程として工程展開
することを特徴とする請求項1に記載の工程スケジュラ
ーシステムに存する。請求項3記載の本発明の要旨は、
前記日程展開処理手段は、工程展開された各工程のプロ
ットデータを生成し、該プロットデータを印字装置やデ
ィスプレイ表示装置などの出力処理手段に送ることを特
徴とする請求項1又は2に記載の工程スケジュラーシス
テムに存する。請求項4記載の本発明の要旨は、前記日
程展開処理手段は、各々の工程の優先順位を決定するた
めの依存関係テーブルを有し、該依存関係テーブルは、
工程毎に設定された前工程と並行して開始できるか、前
工程の終了後に開始できるかを判断するための識別子が
予め設定され、前記外部調達品工程の前記識別子は、前
記外部調達品工程の前工程と並行して開始できる設定が
されることを特徴とする請求項1乃至3のいずれかに記
載の工程スケジュラーシステムに存する。請求項5記載
の本発明の要旨は、前記日程展開処理手段は、製品生産
における一連の工程において、自社工場の生産工程と、
前記外部調達品工程に対応する前記自社工場外の前記キ
ー部品の生産工程とを管理して工程展開することを特徴
とする請求項1乃至4のいずれかに記載の工程スケジュ
ラーシステムに存する。請求項6記載の本発明の要旨
は、請求項1乃至5のいずれかに記載の工程スケジュラ
ーシステムを利用したマニュアル日程調整方法であっ
て、キー部品発注に相当する自社工場外への生産工程の
新規委託や既に委託した生産工程の変更を含む外注先委
託変更の設定を行う日程調整設定部にて、前記日程展開
処理手段による工程展開後、外部調達品工程の後工程に
おける発注されたキー部品の手待ち在庫を抑えるため、
前記キー部品の納入日の調整をし、納入コントロールを
行う日程調整ができることを特徴とするマニュアル日程
調整方法に存する。請求項7記載の本発明の要旨は、請
求項1乃至5のいずれかに記載の工程スケジュラーシス
テムを利用した日程計画表示方法であって、キー部品発
注に相当する外部調達品工程や該外部調達品工程に関す
る外部調達品の納期に該当する出力手段の表示部分に、
操作者が判別しやすい赤色など所定の色を設定すること
を特徴とする日程計画表示方法に存する。請求項8記載
の本発明の要旨は、請求項1乃至5のいずれかに記載の
工程スケジュラーシステムを利用した原材料調達方法で
あって、生産計画における自社工場の負荷オーバ時など
外注先に対して、負荷に関係するキー部品を含む原材料
の発注を行い、前記日程展開処理手段による工程展開
後、外部調達品工程の後工程において、発注された前記
原材料の手持ち在庫を抑えるため、前記原材料の納入日
を調整し、調整された納入日に基づき、前記外注先に対
して、前記原材料の生産、又は、前記外注先での調達を
指示して、前記自社工場における前記原材料の調達をコ
ントロールすることを特徴とする原材料調達方法に存す
る。
The gist of the present invention described in claim 1 is a process scheduler system for automatically generating a production schedule, wherein member ordering information for taking in key part ordering data outside of a company's own factory. And a schedule development processing means for performing a process development relating to production, wherein the schedule development processing means correlates with an external procurement process from ordering to delivery of a key part corresponding to the key part order data. A priority process allocation processing unit that allocates the externally procured product process with the highest priority, and a new outsourcing of the production process corresponding to the key part order data to a subcontractor such as when the load of the factory in the production plan is over And a schedule adjustment setting unit for setting outsourced outsourced changes including changes in production processes already outsourced. That. The gist of the present invention according to claim 2 is that the member order information acquiring means is connected to an external member ordering system and fetches the key part order data linked to the order information in the member ordering system. 2. The process scheduler system according to claim 1, wherein the expansion processing means expands the process with the external procurement process based on the taken key part order data as a priority process. The gist of the present invention described in claim 3 is that
3. The schedule development processing unit according to claim 1, wherein the schedule development processing unit generates plot data of each of the developed processes, and sends the plot data to an output processing unit such as a printing device or a display device. It exists in the process scheduler system. The gist of the present invention according to claim 4 is that the schedule development processing means has a dependency table for determining the priority of each step, and the dependency table includes:
An identifier for determining whether the process can be started in parallel with the previous process set for each process or can be started after the end of the previous process is set in advance, and the identifier of the external procurement process is the external procurement process. The process scheduler system according to any one of claims 1 to 3, wherein settings are made so that the process can be started in parallel with the previous process. The gist of the present invention according to claim 5 is that the schedule development processing means includes:
The process scheduler system according to any one of claims 1 to 4, wherein a process of managing the key component production process outside the company factory corresponding to the external procurement process is managed and developed. The gist of the present invention according to claim 6 is a manual schedule adjusting method using the process scheduler system according to any one of claims 1 to 5, wherein the production schedule outside the company factory corresponding to the ordering of key parts is provided. In the schedule adjustment setting section for setting outsourced outsourced changes including new outsourced and outsourced production process changes, after the process development by the schedule development processing means, the key components ordered in the post-process of the external procurement process In order to reduce the backlog of
The present invention resides in a manual schedule adjusting method, wherein a delivery date of the key component is adjusted, and a schedule for controlling the delivery can be adjusted. According to a seventh aspect of the present invention, there is provided a method for displaying a schedule using the process scheduler system according to any one of the first to fifth aspects, wherein the externally procured product process corresponding to a key part order and the external procurement process are provided. In the display part of the output means corresponding to the delivery date of the external procured product related to the product process,
The present invention resides in a method of displaying a schedule, wherein a predetermined color such as red, which is easy for an operator to distinguish, is set. The gist of the present invention described in claim 8 is a method for procuring raw materials using the process scheduler system according to any one of claims 1 to 5, wherein the method is applied to a subcontractor such as when the load of its own factory in a production plan is over. After ordering the raw materials including the key parts related to the load, and after the process development by the schedule development processing means, in the post-process of the external procurement process, the delivery of the raw materials to suppress the stock on hand of the ordered raw materials is performed. Adjusting the date and instructing the subcontractor to produce the raw material or procurement at the subcontractor based on the adjusted delivery date to control the procurement of the raw material at the own factory. Raw material procurement method characterized by the following.

【0008】[0008]

【発明の実施の形態】以下、本発明の実施の形態を図面
に基づいて詳細に説明する。
Embodiments of the present invention will be described below in detail with reference to the drawings.

【0009】図1は、本実施の形態に係る工程スケジュ
ラーシステムの構成を示すブロック図である。
FIG. 1 is a block diagram showing a configuration of a process scheduler system according to the present embodiment.

【0010】図1に示すように、本実施の形態に係る工
程スケジュラーシステムは、工程スケジューリング装置
(工程スケジューリング手段、コンピュータ、データ処
理装置)100と、入力処理部105と、出力処理部
(出力処理手段)51とで概略構成される。
As shown in FIG. 1, a process scheduler system according to the present embodiment comprises a process scheduling device (process scheduling means, computer, data processing device) 100, an input processing unit 105, and an output processing unit (output processing unit). (Means) 51.

【0011】入力処理部105は、部材発注情報取込部
(部材発注情報取込手段)101と、作業割付方式入力
部102と、日程調整入力部103と、作業実績入力部
104とを備える。
The input processing unit 105 includes a member order information acquisition unit (member order information acquisition unit) 101, a work allocation method input unit 102, a schedule adjustment input unit 103, and a work result input unit 104.

【0012】部材発注情報取込部101は、通常別シス
テムである部材発注システム(発注システム、MRP)
200と連動し、キー部品発注データの取込み機能を有
する。
A member order information taking-in unit 101 is a member ordering system (ordering system, MRP) which is usually a separate system.
It has a function of taking in key part ordering data in conjunction with 200.

【0013】作業割付方式入力部102では、作業能力
設定や工程依存関係設定等に用いられるデータが入力さ
れる。
The work allocation method input unit 102 receives data used for setting work capacity and setting process dependency.

【0014】日程調整入力部103では、設備能力変更
や外注委託変更等に用いられるデータが入力される。
The schedule adjustment input unit 103 inputs data used for a change in equipment capacity or a change in outsourcing.

【0015】作業実績入力部104では、対象JOBの
削除、仕掛かり・製品在庫更新及び不良率の再設定処理
に用いられるデータが入力される。
In the work result input unit 104, data used for deleting the target job, updating the in-process / product inventory, and resetting the defect rate is input.

【0016】工程スケジューリング装置100は、日程
展開処理部110と、外部調達品納期設定部(外部調達
品工程関連設定部)11と、作業割付方式設定部12と
を備える。
The process scheduling apparatus 100 includes a schedule development processing unit 110, an external procurement item delivery date setting unit (external procurement item process-related setting unit) 11, and a work allocation method setting unit 12.

【0017】外部調達品納期設定部11は、部材発注情
報取込部101で取込まれたキー部品発注データに基づ
き、発注される部材に関係する工程に対する優先工程と
してキー部品TBL(キー部品テーブル)に格納したT
BLデータ(テーブルデータ)を参照し、納期日をプロ
ットする。これにより、外部調達品の納期の設定を行
う。
Based on the key part order data taken in by the part order information take-in section 101, the externally procured item delivery date setting section 11 sets a key part TBL (key part table) as a priority step for a step related to a part to be ordered. T) stored in
The delivery date is plotted with reference to the BL data (table data). Thereby, the delivery date of the externally procured product is set.

【0018】作業割付方式設定部12は、作業割付方式
入力部102で入力されたデータに基づき、作業能力設
定と工程依存関係設定等を行う。
The work allocation method setting unit 12 performs work capacity setting and process dependency setting based on the data input by the work allocation method input unit 102.

【0019】日程展開処理部(日程展開処理手段)11
0は、優先工程割付処理部120と、日程調整設定部
(日程調整部)13と、作業実績管理処理部14とを備
える。
Schedule development processing unit (schedule development processing means) 11
0 includes a priority process allocation processing unit 120, a schedule adjustment setting unit (schedule adjustment unit) 13, and a work result management processing unit 14.

【0020】日程調整設定部13は、日程調整入力部1
03で入力されたデータに基づき、設備数の増減による
設備能力変更や、残業・休日出勤等の稼働時間の増減、
生産工程における自社工場の負荷オーバ時など必要に応
じて外注先に対して、キー部品発注に相当する生産工程
の新規委託や委託した生産工程の変更を含む外注先委託
変更などの設定を行う。
The schedule adjustment setting unit 13 includes a schedule adjustment input unit 1
Based on the data entered in 03, change in equipment capacity due to increase / decrease in the number of facilities, increase / decrease in operating hours such as overtime and work on holidays,
If necessary, such as when the load of the factory in the production process is over, the subcontractor is set up such as new consignment of the production process corresponding to the key part ordering or change of the subcontractor outsourced change including the change of the outsourced production process.

【0021】作業実績管理処理部14は作業実績入力部
104で入力されたデータに基づき、対象JOBの削
除、仕掛かり・製品在庫更新及び不良率の再設定処理を
行う。
The work result management processing unit 14 performs a process of deleting the target job, updating the work-in-process / product inventory, and resetting the defect rate based on the data input by the work result input unit 104.

【0022】優先工程割付処理部120は、展開対象J
OB取得21と、優先工程割付処理22と、依存関係割
付処理23と、設備と要因と時間とに関する資源・不良
率割付処理24とを行う。
The priority step allocation processing unit 120 determines the
An OB acquisition 21, a priority process assignment process 22, a dependency assignment process 23, and a resource / defective rate assignment process 24 relating to equipment, factors, and time are performed.

【0023】出力処理部51は、日程展開された日程計
画結果を、ガントチャートなどの形式で印字出力やディ
スプレイ表示を行う。
The output processing section 51 prints out the displayed schedule planning result in the form of a Gantt chart or displays it on a display.

【0024】図2は、図1における動作と発注システム
(MRP)200との関係を示す図である。
FIG. 2 is a diagram showing the relationship between the operation in FIG. 1 and the ordering system (MRP) 200.

【0025】既に確立された発注システム200と連動
し、キー部品の発注データ取込みを行い、キー部品登録
データを作成する(ステップA01)。
In conjunction with the already established ordering system 200, key part order data is taken in and key part registration data is created (step A01).

【0026】作成されたキー部品登録データと製品生産
に関するデータベース210とに基づき、作業項目(工
程)自動作成を行う(ステップA02)。
Based on the created key part registration data and the database 210 concerning product production, work items (processes) are automatically created (step A02).

【0027】次に、キー部品の納入時期を最優先にして
スケジュールを立案するため、キー部品納期をプロット
する(ステップA03)。
Next, the key component delivery date is plotted in order to formulate a schedule with the delivery priority of the key component as the highest priority (step A03).

【0028】キー部品との関係を含む日程計画展開を行
う(ステップA04)。
Schedule development including the relationship with key parts is performed (step A04).

【0029】出力処理部51にて日程計画表示し、操作
者による調整を行う(ステップA05)。
The output processing section 51 displays a schedule and displays an adjustment by the operator (step A05).

【0030】この操作者による調整(A05X)におい
て、作業工程の負荷・納期変更を行い(ステップA0
6)、ステップA04に戻る。
In the adjustment (A05X) by the operator, the load and delivery date of the work process are changed (step A0).
6) Return to step A04.

【0031】また、調整(A05X)において、外部委
託、キー部品の納期変更を行い(ステップA07)、ス
テップA01に戻る。
In the adjustment (A05X), the outsourcing and the change of the delivery date of the key part are performed (step A07), and the process returns to step A01.

【0032】更に、調整(A05X)において、調整O
Kの場合(ステップA08)、確定し(ステップA0
9)、外部調達変更依頼を行い(ステップA10)、発
注システム200の処理を行う。
Further, in the adjustment (A05X), the adjustment O
In the case of K (step A08), it is determined (step A0
9), a change request for external procurement is made (step A10), and the processing of the ordering system 200 is performed.

【0033】以上の流れを達成するため、作業要素を有
する事象の開始からその終了に至る迄の時系列的な一連
の計画をたてるスケジューラーと、工場の設備能力等、
スケジューラーが計画したスケジュールを模擬するため
に必要な基礎となるデータをデータベースが必要とな
る。また、スケジューラーで計画した作業日程等の事象
を時間軸を考慮しながらシミュレート計算を行ってスケ
ジュールを模擬する。
In order to achieve the above-mentioned flow, a scheduler for making a series of time-series plans from the start of an event having a work element to the end thereof, and equipment capacity of a factory, etc.
A database is needed for the underlying data needed to simulate the schedule planned by the scheduler. In addition, a schedule is simulated by performing a simulation calculation of an event such as a work schedule planned by the scheduler while considering a time axis.

【0034】図3は、図1の動作の流れを示すフローチ
ャートである。
FIG. 3 is a flowchart showing the flow of the operation of FIG.

【0035】まず、指示された対象JOBを抽出して納
期順に取得する(展開対象JOB取得)(ステップS
1)。ここで、同一納期の場合は受注TRN(受注トラ
ンザクション、オーダー)の優先順位で決定する。
First, the designated target job is extracted and acquired in the order of delivery date (development target job acquisition) (step S).
1). Here, in the case of the same delivery date, the order is determined by the priority of the order TRN (order transaction, order).

【0036】次に、図1の外部調達品納期設定部11に
おける部品の所要量計算等により外部調達品の発注情報
を取込み、一つの工程に対する優先工程としてキー部品
TBLに格納したTBLデータを参照し納期日をプロッ
トする(外部調達品の納期の取得)(ステップS2)。
Next, the externally procured product delivery date setting unit 11 shown in FIG. 1 fetches the order information of the externally procured product by calculating the required quantity of the component, and refers to the TBL data stored in the key component TBL as a priority process for one process. Then, the delivery date is plotted (acquisition of the delivery date of the externally procured product) (step S2).

【0037】更に、依存関係TBL(工程依存TBL、
依存関係テーブル)における終了(調達部品の納入日)
と開始との関係を示す識別子であるFS(終了−開始)
に基づき、外部調達品の納期と関係する工程の判定を行
う。
Further, a dependency relationship TBL (process dependent TBL,
End (dependency table) (delivery date of procured parts)
FS (End-Start), which is an identifier indicating the relationship between “Start” and “Start”
Based on the above, the process related to the delivery date of the externally procured product is determined.

【0038】また、外部調達品と関係しない一般の工程
は依存関係TBLにおける識別子であるSS(開始―開
始)、FS(終了―開始)に基づき、先行工程開始、又
は、先行工程終了の何時間後に該当する工程開始を行う
かを判定して、工程展開を行う(ステップS3)。
A general process not related to an external procurement item is based on the identifiers SS (start-start) and FS (end-start) in the dependency relationship TBL, and indicates the number of hours before the start of the preceding process or the end of the preceding process. It is determined whether or not to start the corresponding process later, and the process is developed (step S3).

【0039】次に、以下の内容で工程別生産数を求める
(工程別生産数の決定)(ステップS4)。 (イ)客先への納入予定TRN(納入予定トランザクシ
ョン)の生産数に基づき、工程依存TBLにおける工程
別不良率から工程単位の生産数を求める。 (ロ)外注TRN(外注トランザクション)に該当する
工程の依頼数が設定されている場合は、(イ)で求めた
生産数−依頼数が社内生産数となる。
Next, the number of productions per process is determined according to the following contents (determination of the number of productions per process) (step S4). (B) Based on the number of TRNs (transactions to be delivered) to be delivered to the customer, the number of productions for each process is obtained from the defect rate for each process in the process-dependent TBL. (B) When the number of requests for the process corresponding to the outsourcing TRN (outsourcing transaction) is set, the production number minus the number of requests obtained in (a) is the in-house production number.

【0040】以下の内容で設備負荷判定を行う(ステッ
プS5)。 (ハ)稼働時間TBL(稼働時間テーブル)と能力TB
L(能力テーブル)とを参照して、工程別に割当てる機
械を判定する。 (ニ)能力TBLを図番、工程で抽出して優先順位順に
読込む。但し、機械TRN(機械トランザクション)に
該当図番、工程の機械が設定されている場合は、機械T
RNの使用、又は、未使用を考慮して対象機械を判定す
る。 (ホ)該当工程の生産時間を求める。(生産数÷能力T
BLの時間当り生産能力=生産時間) (ヘ)対象機械の稼働時間を稼働時間TBLより取得す
る。 (ト)計画実績TRN(計画実績トランザクション)又
は展開シミュレーションTRN(展開シミュレーション
トランザクション)を過去から順に参照して、空きのあ
る機械を検索する。
An equipment load determination is made in the following manner (step S5). (C) Operating time TBL (operating time table) and capacity TB
With reference to L (capacity table), a machine to be assigned for each process is determined. (D) Capability TBL is extracted by drawing number and process, and is read in order of priority. However, if the corresponding drawing number and the machine of the process are set in the machine TRN (machine transaction), the machine T
The target machine is determined in consideration of whether the RN is used or not used. (E) Obtain the production time of the process. (Production quantity / capacity T
(Production capacity per time of BL = production time) (f) Obtain the operation time of the target machine from the operation time TBL. (G) A plan machine TRN (plan plan transaction) or a deployment simulation TRN (development simulation transaction) is sequentially referred to from the past to search for a vacant machine.

【0041】ここで、休日TRN(休日トランザクショ
ン)に設定されている稼働時間変更内容を考慮する。
Here, the change in the operating time set for the holiday TRN (holiday transaction) is considered.

【0042】JOB別・設備別にガントチャートによっ
て日程計画を表示する(日程表示)(ステップS6)。
The schedule is displayed on the Gantt chart for each job and for each facility (schedule display) (step S6).

【0043】表示された日程計画を参照して、日程調整
を行うかどうか判断する(ステップS7)。
With reference to the displayed schedule plan, it is determined whether or not schedule adjustment is performed (step S7).

【0044】日程調整を行う場合(図中、Yes)、設
備数の増減と、残業・休日出勤等の稼働時間の増減と、
生産工程における負荷オーバ時など必要に応じて外注先
に工程を委託する外注先委託変更とを指示し(日程展開
調整)(ステップS8)、ステップS1に戻る。
When the schedule is adjusted (Yes in the figure), an increase or decrease in the number of facilities and an increase or decrease in operating hours such as overtime and work on holidays are performed.
An instruction is issued to change the subcontractor to outsource the process to a subcontractor as necessary, such as when the load in the production process is over (schedule development adjustment) (step S8), and the process returns to step S1.

【0045】なお、前回の日程計画のシミュレーション
は展開シミュレーションTBL(展開シミュレーション
テーブル)に保存されており、変更前の日程計画を参照
したい場合は、展開シミュレーションTBLから表示す
る。
Note that the simulation of the previous schedule plan is stored in the development simulation TBL (development simulation table), and when it is desired to refer to the schedule plan before the change, it is displayed from the development simulation TBL.

【0046】図4は、工程依存TBL150と外部調達
品TBL160とスケジュール割付結果例170とを示
す図である。
FIG. 4 is a diagram showing a process-dependent TBL 150, an externally procured product TBL 160, and a schedule allocation result example 170.

【0047】図4を参照して本実施の形態に係る工程ス
ケジュラーシステムの具体的な動作の流れの説明をす
る。
The specific operation flow of the process scheduler system according to the present embodiment will be described with reference to FIG.

【0048】生産工程のスケジューリングは、設備能
力、カレンダ、稼働時間、不良率、生産量等を考慮して
日程展開されるが、外部調達品の内容を有する外部調達
品TBL(外部調達品テーブル)160と工程依存TB
L(依存関係TBL)150とに基づく展開を行う。
The scheduling of the production process is developed in consideration of the equipment capacity, the calendar, the operation time, the defect rate, the production amount, and the like. The external procured product TBL (external procured product table) having the contents of the external procured product 160 and process dependent TB
L (dependency TBL) 150 is developed.

【0049】図4に示すように、工程依存TBL150
において、JOBCD152のJOB1Aには、工程1
〜5が対応する。
As shown in FIG. 4, the process-dependent TBL 150
In JOB1A of JOBCD152, step 1
~ 5 correspond.

【0050】また、前工程依存関係10Kの「SS」は
前工程と並行して開始できる「開始−開始」を意味し、
「FS」は前工程終了後工程開始の「終了−開始」を意
味する。
The “SS” in the preceding process dependency 10K means “start-start” that can be started in parallel with the preceding process.
“FS” means “end-start” at the start of the process after the end of the previous process.

【0051】日程展開の例は、最初に処理される工程1
の処理後、外部調達品TBL160を工程2の如く優先
し、発注日10H、納入予定日10Nをプロットし、そ
の後工程順位及び工程依存関係に従って、工程展開を実
施する。
The example of the schedule development is the first processing step 1
, The externally procured product TBL160 is prioritized as in Step 2, the order date 10H and the scheduled delivery date 10N are plotted, and then the process is developed according to the process order and process dependency.

【0052】その結果、スケジュール割付結果例170
に示すように工程1〜5が表示される。
As a result, a schedule allocation result example 170
Steps 1 to 5 are displayed as shown in FIG.

【0053】実施の形態に係る工程スケジュラーシステ
ムは上記の如く構成されているので、以下に掲げる効果
を奏する。
Since the process scheduler system according to the embodiment is configured as described above, the following effects can be obtained.

【0054】作業方式入力と日程調整入力とにより工程
展開されるので何度でも実体にあった日程計画が展開で
きる。
Since the process is developed by the input of the operation method and the input of the schedule adjustment, the actual schedule can be developed any number of times.

【0055】また、予め別システムである部材発注シス
テムから発注情報の取込処理をすることにより、発注情
報を再度手入力する必要がない。
Further, since the order information is fetched from the member ordering system which is another system in advance, it is not necessary to manually input the order information again.

【0056】また、外部調達品納期と連動した日程計画
展開を行い、負荷限界オーバに対する対策として外注先
への委託変更が組込まれることで容易な日程調整が可能
となる。
Further, the schedule is developed in conjunction with the delivery date of the externally procured product, and the schedule change can be easily adjusted by incorporating a change to a subcontractor as a countermeasure against overload limit.

【0057】なお、本実施の形態においては、本発明は
それに限定されず、本発明を適用する上で好適な工程ス
ケジュラーシステムに関する技術に適用することができ
る。
In the present embodiment, the present invention is not limited to this, and can be applied to a technique relating to a process scheduler system suitable for applying the present invention.

【0058】また、上記構成部材の数、位置、形状等は
上記実施の形態に限定されず、本発明を実施する上で好
適な数、位置、形状等にすることができる。
The number, position, shape, and the like of the above-mentioned constituent members are not limited to the above-described embodiment, but can be set to a number, position, shape, and the like suitable for carrying out the present invention.

【0059】なお、各図において、同一構成要素には同
一符号を付している。
In the respective drawings, the same components are denoted by the same reference numerals.

【0060】[0060]

【発明の効果】本発明は以上のように構成されているの
で、以下に掲げる効果を奏する。
Since the present invention is configured as described above, the following effects can be obtained.

【0061】第1の効果は、日程計画のシミュレートが
高速で行え、日程計画立案の効率化ができることにあ
る。その理由は、工程情報、依存関係情報、設備情報、
カレンダ、能力情報等に基づき、コンピュータによって
工程展開とスケジュールの割付けが高速にできるためで
ある。
The first effect is that the schedule can be simulated at a high speed, and the efficiency of the schedule can be improved. The reasons are process information, dependency information, equipment information,
This is because the process development and schedule assignment can be performed at high speed by the computer based on the calendar, the capability information, and the like.

【0062】第2の効果は、外部調達品の納入管理によ
る自社の生産日程への影響をシミュレートすることで、
手作業となる工程や手待ちの工程を低減できることにあ
る。その理由は、外部調達品を最優先に工程展開し、そ
の後、全ての工程を展開するため、どの期間が待ちにな
るかを容易に判断できる。また、この判断用のデータを
視覚で理解できるように表示することで、日程調整、納
入の督促などの対策が可能であるためである。
The second effect is to simulate the influence on the production schedule of the company due to the delivery management of the externally procured products.
That is, it is possible to reduce the number of manual processes and manual waiting processes. The reason is that the externally procured products are developed with the highest priority, and then all the processes are developed, so that it is easy to determine which period will be waiting. In addition, by displaying the data for this determination so that it can be visually understood, it is possible to take measures such as schedule adjustment and demand for delivery.

【0063】第3の効果は、納入コントロールによる仕
掛かり在庫の削減ができることにある。その理由は、各
工程間で手待ち時間が多くなると工程毎に部材や仕掛か
り在庫が滞納して増大する。手待ち作業の工程を制御す
るために納入時期の変更等により手待ち時間を削減する
ことで、仕掛かり在庫を削減できる。
The third effect is that the in-process inventory can be reduced by the delivery control. The reason is that if the waiting time increases between the processes, the members and the in-process stock are delayed for each process and increase. In-process stock can be reduced by reducing the hand waiting time by changing the delivery time or the like in order to control the process of the hand waiting work.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態に係る工程スケジュラーシ
ステムの構成を示すブロック図である。
FIG. 1 is a block diagram showing a configuration of a process scheduler system according to an embodiment of the present invention.

【図2】図1における動作と発注システムとの関係を示
す図である。
FIG. 2 is a diagram showing the relationship between the operation in FIG. 1 and an ordering system.

【図3】図1の動作の流れを示すフローチャートであ
る。
FIG. 3 is a flowchart showing a flow of the operation of FIG. 1;

【図4】図1の工程スケジューリング装置の処理におけ
る工程依存TBLと外部調達品TBLとスケジュール割
付結果例とを示す図である。
FIG. 4 is a diagram showing a process-dependent TBL, an externally procured product TBL, and an example of a schedule assignment result in the process of the process scheduling apparatus in FIG. 1;

【符号の説明】 1〜5 工程 1A JOB 10H 発注日 10K 前工程依存関係 10N 納入予定日 11 外部調達品納期設定部(外部調達品工程関連設定
部) 12 作業割付方式設定部 13 日程調整設定部(日程調整部) 14 作業実績管理処理部 21 展開対象JOB取得 22 優先工程割付処理 23 依存関係割付処理 24 資源・不良率割付処理 51 出力処理部(出力処理手段) 100 工程スケジューリング装置(工程スケジューリ
ング手段、コンピュータ、データ処理装置) 101 部材発注情報取込部(部材発注情報取込手段) 102 作業割付方式入力部 103 日程調整入力部 104 作業実績入力部 105 入力処理部 110 日程展開処理部(日程展開処理手段) 120 優先工程割付処理部 150 工程依存TBL(依存関係TBL) 152 JOBCD 160 外部調達品TBL(外部調達品テーブル) 170 スケジュール割付結果例 200 部材発注システム(発注システム、MRP) 210 データベース
[Description of Signs] 1-5 Process 1A JOB 10H Ordering date 10K Dependency on previous process 10N Scheduled delivery date 11 Externally procured product delivery date setting section (Externally procured product process related setting section) 12 Work allocation method setting section 13 Schedule adjustment setting section (Schedule adjustment unit) 14 Work result management processing unit 21 Acquisition of job to be expanded 22 Priority process allocation process 23 Dependency allocation process 24 Resource / defective rate allocation process 51 Output processing unit (output processing unit) 100 Process scheduling device (process scheduling unit) , Computer, data processing device) 101 member order information acquisition unit (member order information acquisition means) 102 work allocation method input unit 103 schedule adjustment input unit 104 work performance input unit 105 input processing unit 110 schedule development processing unit (schedule development) Processing means) 120 priority process allocation processing unit 150 process dependent TBL (dependency) TBL) 152 JOBCD 160 Externally procured item TBL (Externally procured item table) 170 Schedule allocation result example 200 Material ordering system (ordering system, MRP) 210 Database

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 生産スケジュールを自動生成するための
工程スケジュラーシステムであって、 自社工場外に対するキー部品発注データの取込みを行う
部材発注情報取込手段と、 生産に関する工程展開を行う日程展開処理手段とを備
え、 該日程展開処理手段は、前記キー部品発注データに対応
するキー部品の発注から納品までの外部調達品工程と相
関する工程に対して、前記外部調達品工程を最優先に割
付ける優先工程割付処理部と、生産計画における自社工
場の負荷オーバ時など外注先に対して前記キー部品発注
データに該当する生産工程の新規委託や既に委託した生
産工程の変更を含む外注先委託変更の設定を行う日程調
整設定部とを有することを特徴とする工程スケジュラー
システム。
1. A process scheduler system for automatically generating a production schedule, comprising: a member ordering information fetching means for fetching key part ordering data outside a company's own factory; and a schedule development processing means for developing a production-related process. Wherein the schedule development processing means assigns the externally procured product process to the process correlated with the externally procured product process from ordering to delivery of the key component corresponding to the key component order data with the highest priority. The priority process allocation processing unit and the outsourcing contract change including the new consignment of the production process corresponding to the key part order data or the change of the production process already consigned to the subcontractor such as when the load of the factory in the production plan is over. A process scheduler system comprising a schedule adjustment setting unit for setting.
【請求項2】 前記部材発注情報取込手段は、外部の部
材発注システムに接続されて、該部材発注システムにお
ける発注情報に連動した前記キー部品発注データを取込
み、 前記日程展開処理手段は、取込まれた前記キー部品発注
データに基づく前記外部調達品工程を優先工程として工
程展開することを特徴とする請求項1に記載の工程スケ
ジュラーシステム。
2. The member order information taking-in means is connected to an external member ordering system and takes in the key part ordering data in conjunction with ordering information in the member ordering system. The process scheduler system according to claim 1, wherein the externally procured product process based on the inserted key part order data is developed as a priority process.
【請求項3】 前記日程展開処理手段は、工程展開され
た各工程のプロットデータを生成し、該プロットデータ
を印字装置やディスプレイ表示装置などの出力処理手段
に送ることを特徴とする請求項1又は2に記載の工程ス
ケジュラーシステム。
3. The process according to claim 1, wherein the schedule development processing means generates plot data of each of the developed processes, and sends the plot data to an output processing means such as a printing device or a display device. Or the process scheduler system according to 2.
【請求項4】 前記日程展開処理手段は、各々の工程の
優先順位を決定するための依存関係テーブルを有し、 該依存関係テーブルは、工程毎に設定された前工程と並
行して開始できるか、前工程の終了後に開始できるかを
判断するための識別子が予め設定され、 前記外部調達品工程の前記識別子は、前記外部調達品工
程の前工程と並行して開始できる設定がされることを特
徴とする請求項1乃至3のいずれかに記載の工程スケジ
ュラーシステム。
4. The schedule development processing means has a dependency table for determining a priority of each process, and the dependency table can be started in parallel with a previous process set for each process. Or an identifier for determining whether the process can be started after the end of the previous process is set in advance, and the identifier of the external procured product process is set so that it can be started in parallel with the previous process of the external procured product process. The process scheduler system according to any one of claims 1 to 3, wherein:
【請求項5】 前記日程展開処理手段は、製品生産にお
ける一連の工程において、自社工場の生産工程と、前記
外部調達品工程に対応する前記自社工場外の前記キー部
品の生産工程とを管理して工程展開することを特徴とす
る請求項1乃至4のいずれかに記載の工程スケジュラー
システム。
5. The schedule development processing means manages, in a series of steps in product production, a production process of the own factory and a production process of the key part outside the own factory corresponding to the external procurement process. The process scheduler system according to any one of claims 1 to 4, wherein the process is developed by a process.
【請求項6】 請求項1乃至5のいずれかに記載の工程
スケジュラーシステムを利用したマニュアル日程調整方
法であって、 キー部品発注に相当する自社工場外への生産工程の新規
委託や既に委託した生産工程の変更を含む外注先委託変
更の設定を行う日程調整設定部にて、前記日程展開処理
手段による工程展開後、外部調達品工程の後工程におけ
る発注されたキー部品の手待ち在庫を抑えるため、前記
キー部品の納入日を調整し、納入コントロールを行う日
程調整ができることを特徴とするマニュアル日程調整方
法。
6. A manual schedule adjusting method using the process scheduler system according to claim 1, wherein a new production process is outsourced to an outside of a factory corresponding to a key part order. In the schedule adjustment setting part for setting outsourced outsourced change including the change of the production process, after the process is developed by the schedule development processing means, the hand-held inventory of the ordered key parts in the subsequent process of the external procurement process is suppressed. Therefore, the delivery date of the key part is adjusted, and the schedule for controlling the delivery can be adjusted.
【請求項7】 請求項1乃至5のいずれかに記載の工程
スケジュラーシステムを利用した日程計画表示方法であ
って、 キー部品発注に相当する外部調達品工程や該外部調達品
工程に関する外部調達品の納期に該当する出力手段の表
示部分に、操作者が判別しやすい赤色など所定の色を設
定することを特徴とする日程計画表示方法。
7. A schedule plan display method using the process scheduler system according to claim 1, wherein an external procurement process corresponding to a key part order and an external procurement product relating to the external procurement process. A predetermined color, such as red, which is easy for the operator to discriminate, on a display portion of the output means corresponding to the delivery date.
【請求項8】 請求項1乃至5のいずれかに記載の工程
スケジュラーシステムを利用した原材料調達方法であっ
て、 生産計画における自社工場の負荷オーバ時など外注先に
対して、負荷に関係するキー部品を含む原材料の発注を
行い、 前記日程展開処理手段による工程展開後、外部調達品工
程の後工程において、発注された前記原材料の手持ち在
庫を抑えるため、前記原材料の納入日を調整し、 調整された納入日に基づき、前記外注先に対して、前記
原材料の生産、又は、前記外注先での調達を指示して、
前記自社工場における前記原材料の調達をコントロール
することを特徴とする原材料調達方法。
8. A raw material procurement method using the process scheduler system according to any one of claims 1 to 5, wherein a key related to load is supplied to a subcontractor in a production plan such as when the load of an own factory is overloaded. After ordering raw materials including parts, after the process development by the schedule development processing means, in the subsequent process of the external procurement process, adjust the delivery date of the raw materials in order to reduce the stock on hand of the ordered raw materials, and adjust Based on the delivery date, to the subcontractor, instruct the production of the raw materials, or procurement at the subcontractor,
A raw material procurement method comprising controlling the procurement of the raw material at the in-house factory.
JP2001155253A 2001-05-24 2001-05-24 Process scheduler system Pending JP2002351524A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001155253A JP2002351524A (en) 2001-05-24 2001-05-24 Process scheduler system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001155253A JP2002351524A (en) 2001-05-24 2001-05-24 Process scheduler system

Publications (1)

Publication Number Publication Date
JP2002351524A true JP2002351524A (en) 2002-12-06

Family

ID=18999481

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001155253A Pending JP2002351524A (en) 2001-05-24 2001-05-24 Process scheduler system

Country Status (1)

Country Link
JP (1) JP2002351524A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005216074A (en) * 2004-01-30 2005-08-11 Jfe Steel Kk Production plan preparation system, production plan preparation method and program
JP2019211803A (en) * 2018-05-31 2019-12-12 株式会社神戸製鋼所 Production schedule creation device, production schedule creation method and program

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005216074A (en) * 2004-01-30 2005-08-11 Jfe Steel Kk Production plan preparation system, production plan preparation method and program
JP4525093B2 (en) * 2004-01-30 2010-08-18 Jfeスチール株式会社 Production plan creation system, production plan creation method and program
JP2019211803A (en) * 2018-05-31 2019-12-12 株式会社神戸製鋼所 Production schedule creation device, production schedule creation method and program
JP7223511B2 (en) 2018-05-31 2023-02-16 株式会社神戸製鋼所 PRODUCTION SCHEDULE CREATION DEVICE, PRODUCTION SCHEDULE CREATION METHOD AND PROGRAM

Similar Documents

Publication Publication Date Title
US6876895B2 (en) Order assembly production system and method
US20060212323A1 (en) Production management system
US7099726B2 (en) Production planning system
US7039481B2 (en) Production planning system
JP2008299762A (en) Production management program
JPH06214996A (en) Production management method
JP2004310290A (en) Production managing method for plurality of production lines
JPH08314526A (en) Manufacture management system
JP2002351524A (en) Process scheduler system
JPH1080842A (en) Production plan preparing device
JP2796409B2 (en) Schedule management method and device
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
JP3491558B2 (en) Alternative lot determination system
JP2000210845A (en) Production control device and method
US20110046769A1 (en) Manufacturing instruction equipment, program, manufacturing instruction system, and manufacturing instruction method
Pritsker et al. Production scheduling using FACTOR
JPH09212556A (en) Operating instruction method in process schedule
JPH07271864A (en) Production control method
US20050065833A1 (en) Production scheduling management method and production scheduling management program
JP4239767B2 (en) Design change support system, design change method, design change support program, and recording medium recording the same
JPH1011502A (en) Production plan evaluation system
TWI784311B (en) Management device, management system, and management program
JPH086997A (en) Preparing method for arrow diagram master classified by types
Saratov Synchronizing the operation of workshops in custom production
JP2002312018A (en) Process control system

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040830

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040907

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050104