JP2002199466A - Transmission terminal - Google Patents

Transmission terminal

Info

Publication number
JP2002199466A
JP2002199466A JP2001377538A JP2001377538A JP2002199466A JP 2002199466 A JP2002199466 A JP 2002199466A JP 2001377538 A JP2001377538 A JP 2001377538A JP 2001377538 A JP2001377538 A JP 2001377538A JP 2002199466 A JP2002199466 A JP 2002199466A
Authority
JP
Japan
Prior art keywords
phase
calculation
power
monitored
transmission terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001377538A
Other languages
Japanese (ja)
Inventor
直大 ▲高▼鴨
Naohiro Takakamo
Satoko Gotou
聡子 後藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to JP12380395A priority Critical patent/JP3634893B2/en
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2001377538A priority patent/JP2002199466A/en
Publication of JP2002199466A publication Critical patent/JP2002199466A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a transmission terminal that can easily measure each electric power of the respective branches of a distribution system. SOLUTION: The transmission terminal 1 installed at an installation site of an electric line to be monitored consists of a selector 17, that selects the current signal of two or more electric lines to be monitored in prescribed timing, an analog/digital converter 19 that converts the selected current signal into a digital quantity, a storage means 26 that stores the digital quantity converted from the current signal, a rated value setting section 22 that sets a rated value corresponding to each of the electric lines to be monitored, a central processing unit 8 that makes arithmetic operations of the stored contents, on the basis of the contents set by the rated value setting section 22, a transmission section 24 that communicates as for the arithmetic operation results with a host device and an enclosure that integrally accommodates the terminal components.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は配電系統の諸電気量を現
場で計測して中央設置の上位装置に伝送する伝送端末装
置に係り、特に、配電系統の分岐(フィーダ)毎の電気
量を計測し上位装置に伝送するのに好適な伝送端末装置
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a transmission terminal device for measuring various electric quantities of a distribution system on site and transmitting the measured electric quantities to a centrally installed higher-level device. The present invention relates to a transmission terminal device suitable for measuring and transmitting to a higher-level device.

【0002】[0002]

【従来の技術】工場やビル等における受配電系統の諸電
気量の計測・監視は、電源の安定供給や、負荷状況把握
に必要である。例えば、特開昭60−186007号公
報には、変圧器の監視を行う従来技術が記載されてお
り、実開昭61−14854号公報には、最大需要電力
(デマンド)を監視する従来技術が記載されている。
2. Description of the Related Art Measurement and monitoring of various amounts of electricity in a power distribution system in a factory or a building are necessary for stable supply of power and for grasping load conditions. For example, Japanese Patent Application Laid-Open No. 60-186007 describes a conventional technique for monitoring a transformer, and Japanese Utility Model Application Laid-Open No. 61-14854 discloses a conventional technique for monitoring the maximum power demand. Has been described.

【0003】このような受配電系統の計測・監視を行う
設備や装置は、投資費用が高いため、上記従来技術の如
く、計測・監視対象が重要な場所に限られる。例えば、
配電系統の分岐部分を計測・監視する場合、分岐電路が
5本あったとしたら、その5本全部の各々について計測
・監視するのではなく、そのうちの重要な分岐電路のみ
を計測・監視するようにしている。何故ならば、各分岐
電路毎に電気量が異なるため、分岐電路に取り付ける計
器用変成器(CT)や計器用変圧器(VT),信号変換
用のトランスジューサは取付箇所に合わせた定格のもの
を使用せざるを得ないという問題があるからである。
[0003] Such equipment and devices for measuring and monitoring the power receiving and distribution system have high investment costs, and therefore are limited to places where the objects to be measured and monitored are important, as in the prior art. For example,
When measuring and monitoring the distribution system branch section, if there are five branch circuits, measure and monitor only the important branch circuits among them, instead of measuring and monitoring all five of them. ing. Because the amount of electricity differs for each branch circuit, the meter transformer (CT), the meter transformer (VT), and the transducer for signal conversion attached to the branch circuit must be rated for the mounting location. This is because there is a problem that it must be used.

【0004】また、計測したデータから電気量を演算し
て求める場合、計測器の定格に合わせた演算が必要とな
るため、多数箇所から夫々定格の異なる計器により取り
込んだデータを中央の計算機で一括して演算するのは容
易でないという問題がある。そこで従来は、例えば5本
の分岐電路のうち重要な2本の分岐電路について電気量
を計測・監視する場合、各分岐電路毎に当該分岐電路専
用の計測・監視装置(コントローラ)を設置している。
[0004] Further, when calculating the quantity of electricity from the measured data, it is necessary to perform calculation in accordance with the rating of the measuring instrument. Therefore, data taken in from different locations by instruments having different ratings are collectively collected by a central computer. There is a problem that it is not easy to perform calculations. Conventionally, for example, when measuring and monitoring the amount of electricity for two important branch circuits out of five branch circuits, a dedicated measurement / monitoring device (controller) is installed for each branch circuit. I have.

【0005】[0005]

【発明が解決しようとする課題】近年では、ますます省
エネルギーが要求され、きめ細かな計測や監視が要求さ
れてきている。つまり、上記例でいえば、5本の分岐が
あった場合、5本全部の分岐電路の計測・監視を行う必
要が生じてきている。しかし、このようなきめ細かな計
測・監視を行う場合、従来の考え方の延長で計測・監視
を行うと、各分岐電路毎にトランスジューサやコントロ
ーラを設置する必要が生じ、設備費用が膨大となって現
実的でないという問題がある。即ち、 1)分岐毎のCTあるいはVTの定格に合わせてトラン
スデューサを選定する必要があり、仕様決めが容易でな
い。
In recent years, more and more energy saving has been required, and fine measurement and monitoring have been required. That is, in the above example, if there are five branches, it is necessary to measure and monitor all five branch electric circuits. However, when performing such detailed measurement and monitoring, if measurement and monitoring are performed by extending the conventional concept, it becomes necessary to install a transducer and controller for each branch circuit, and equipment costs become enormous. There is a problem that is not the target. That is: 1) It is necessary to select a transducer according to the rating of CT or VT for each branch, and it is not easy to determine the specifications.

【0006】2)分岐毎のCTに合わせてコントローラ
もしくは中央装置は計算処理を行う必要があり複雑であ
る。
2) The controller or the central unit needs to perform calculation processing in accordance with the CT for each branch, which is complicated.

【0007】3)CTの仕様が変わると、トランスデュ
ーサの変更や、コントローラもしくは中央装置の計算処
理を変更する必要がある。
[0007] 3) When the specifications of the CT change, it is necessary to change the transducer and the calculation process of the controller or the central unit.

【0008】4)トランスデューサ、A/D変換部等の
配線作業工数が多い。
[0010] 4) The number of man-hours for wiring the transducer, A / D converter, etc., is large.

【0009】5)トランスデューサ等を寄せ集めると据
付面積が大きい。
5) The installation area is large when the transducers and the like are gathered.

【0010】6)投資費用が大である。6) The investment cost is large.

【0011】という問題がある。There is a problem that

【0012】本発明の目的は、上記した問題点を全て解
決し、配電系統の分岐部分のきめ細かな計測・監視を容
易に行うことのできる伝送端末装置、即ち、分岐部分で
必要性の最も高い分岐毎の“電流”の計測を主体として
“電圧”,“電力”,“電力量”の計測を小形の1台の
装置で実現できる伝送端末装置を提供することにある。
SUMMARY OF THE INVENTION An object of the present invention is to solve all of the above-mentioned problems and to make it possible to easily perform detailed measurement and monitoring of a branch portion of a power distribution system, that is, a transmission terminal device which is most required in a branch portion. It is an object of the present invention to provide a transmission terminal device capable of realizing measurement of “voltage”, “power”, and “power amount” with one small device mainly by measuring “current” for each branch.

【0013】[0013]

【課題を解決するための手段】上記目的は、被監視電路
の設置現場に設置される伝送端末装置を、2組以上の被
監視電路の電流信号と被監視電路の電圧信号を所定のタ
イミングで選択する選択手段と、該選択した前記電流信
号及び電圧信号をディジタル量に変換するアナログ/デ
ィジタル変換手段と、該変換したディジタル量を記憶す
る記憶手段と、前記被監視電路の電圧及び電流に対応し
た定格値を設定する定格値設定手段と、前記記憶したデ
ィジタル量について前記定格値設定手段により設定され
た定格値に基づいて被監視電路の電気量を演算する中央
処理装置と、上位装置との間で前記演算の結果を通信す
る伝送手段と、を一体に収納する構成にしたことで達成
される。
SUMMARY OF THE INVENTION It is an object of the present invention to provide a transmission terminal device installed at a site where a monitored circuit is installed by transmitting a current signal of at least two sets of monitored circuits and a voltage signal of the monitored circuit at a predetermined timing. Selecting means for selecting, analog / digital converting means for converting the selected current signal and voltage signal into digital quantity, storing means for storing the converted digital quantity, and corresponding to the voltage and current of the monitored circuit. Rating value setting means for setting the rated value, a central processing unit for calculating the electric quantity of the monitored electric circuit based on the rated value set by the rating value setting means for the stored digital quantity, and a higher-level device. This is achieved by a configuration in which transmission means for communicating the result of the calculation between them are housed integrally.

【0014】[0014]

【作用】分岐電路全ての電流値等を上記構成の1台の伝
送端末装置に取り込み、中央処理装置は、各電流値等の
定格に合わせた諸電気量を演算し、その演算結果を、上
位装置に伝送する。これにより、1つの1つの分岐電路
に異なる定格のトランスジューサを設置する必要がなく
なり、また、各定格に基づく諸電気量の演算は現場設置
の伝送端末装置で行い、中央設置の上位装置は諸電気量
の演算を行う必要はなくなる。
The current values and the like of all the branch circuits are taken into one transmission terminal device having the above configuration, and the central processing unit calculates various amounts of electricity in accordance with the ratings of the respective current values and the like, and the calculation results are superordinated. Transmit to device. This eliminates the need to install transducers of different ratings on one branch circuit, calculates various quantities based on each rating by the transmission terminal equipment installed on site, and the upper-level equipment installed in the center uses various electrical equipment. There is no need to perform quantity calculations.

【0015】[0015]

【実施例】以下、本発明の一実施例を図面を参照して説
明する。図1は、本発明の第1実施例に係る伝送端末装
置のブロック構成図である。伝送端末装置1は、以下に
説明する部品,装置を1つの筐体内に備え一体ものとし
て構成される。この伝送端末装置1において、2は電圧
入力部、2a,2b,2cは伝送端末装置1に電源を供
給する端子、3は供給された電源を以下に説明する各部
に適した電圧に変換して各部に供給するための電源部で
あり、入力電圧85V〜264に対応するものである。
4は信号用変圧器、5は交流信号を所定の矩形波の直流
信号に変える比較器、16は波形を整形するICであ
る。7は上記整形された矩形波信号を伝える信号線で周
波数検出信号線である。
An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a block diagram of a transmission terminal apparatus according to a first embodiment of the present invention. The transmission terminal device 1 includes components and devices described below in a single housing and is configured as an integral unit. In the transmission terminal device 1, reference numeral 2 denotes a voltage input unit, reference numerals 2a, 2b, and 2c denote terminals for supplying power to the transmission terminal device 1, and reference numeral 3 denotes a unit that converts the supplied power to a voltage suitable for each unit described below. It is a power supply unit for supplying to each unit, and corresponds to an input voltage of 85 V to 264.
4 is a signal transformer, 5 is a comparator for converting an AC signal into a DC signal of a predetermined rectangular wave, and 16 is an IC for shaping the waveform. Reference numeral 7 denotes a signal line for transmitting the shaped rectangular wave signal, which is a frequency detection signal line.

【0016】8は、マイコン等の中央処理装置(以下、
CPUと称す。)であり、2組以上の被監視電路の電流
信号の演算処理を主要目的として、各部を統括制御す
る。9は上記の演算処理や統括制御の手順を記憶するR
OM(リードオンメモリ)、10は演算結果や途中経過
を記憶するRAM(ランダムアクセスメモリ)であり、
これらのROM9,RAM10は、CPU8に内蔵され
ている。
Reference numeral 8 denotes a central processing unit (hereinafter referred to as a microcomputer).
Called CPU. ), And each unit is collectively controlled with a main purpose of calculating current signals of two or more sets of monitored electric circuits. Reference numeral 9 denotes an R which stores the above-described arithmetic processing and overall control procedures.
OM (read-on memory), 10 is a RAM (random access memory) for storing the calculation results and the progress of the operation,
These ROM 9 and RAM 10 are built in the CPU 8.

【0017】11a,11b,…,11nは、各々1組
の被監視電路からの電流信号を取込む電流入力部で、1
2a,12b,12c,12dの4つの端子と、内部変
流器13、増幅器14およびサンプルホールド(保持)
回路15で構成されている。6はサンプルホールド回路
15に指示を与える保持指令信号線、17は上記複数の
入力部からの信号を所定のタイミングで択一的に選択を
行う選択部(マルチプレクサ)であり、このタイミング
や選択場所は制御線18により指示される。
Each of 11a, 11b,..., 11n is a current input section for receiving a current signal from one set of monitored electric circuits.
4 terminals 2a, 12b, 12c, 12d, internal current transformer 13, amplifier 14, and sample hold (hold)
It is composed of a circuit 15. Reference numeral 6 denotes a holding command signal line for giving an instruction to the sample and hold circuit 15, and reference numeral 17 denotes a selection unit (multiplexer) for selectively selecting signals from the plurality of input units at a predetermined timing. Is indicated by the control line 18.

【0018】19は、上記選択部17により選択された
信号(アナログ信号)をディジタル量(値)に変換する
A/D変換部(A/Dコンバータ)である。20,21
はA/D変換部19に変換指示を与えたり、変換終了を
検出するなどの制御線である。22b,22c,…,2
2nは、CT105a,…に対応して設けた設定部で、
CTの一次定格を設定するものである。また、22a
は、VTの一次定格を設定する設定部である。
Reference numeral 19 denotes an A / D converter (A / D converter) for converting the signal (analog signal) selected by the selector 17 into a digital value (value). 20, 21
Is a control line for giving a conversion instruction to the A / D converter 19 and detecting the end of conversion. 22b, 22c, ..., 2
2n is a setting unit provided corresponding to the CT 105a,.
This is to set the primary rating of CT. Also, 22a
Is a setting unit for setting the primary rating of the VT.

【0019】23は、伝送端末装置1の固有番地を設定
するアドレス設定部で、中央制御室等に設置されている
上位装置との間で通信を行う際に、この上位装置に接続
される複数の伝送端末装置の各々を番地付けするもので
ある。24は、上位装置と通信を行う伝送部で、端子2
5により後述する伝送線により上位装置と接続される。
27は、上記した増幅器14と同種の増幅器で、電圧信
号増幅用である。
Reference numeral 23 denotes an address setting unit for setting a unique address of the transmission terminal device 1. When performing communication with a higher-level device installed in a central control room or the like, a plurality of addresses 23 are connected to the higher-level device. Is assigned to each of the transmission terminal devices. Reference numeral 24 denotes a transmission unit that communicates with a higher-level device.
5 connects to a higher-level device via a transmission line described later.
Reference numeral 27 denotes an amplifier of the same type as the amplifier 14 described above, for amplifying a voltage signal.

【0020】図2は、図1に示す伝送端末装置1を配電
系統に適用したシステムの構成図である。102は変圧
器(TR)、103はヒューズ(F)104は計器用変
圧器(VT)105a〜105eは計器用変流器(C
T)である。106は二次変電所などの変圧器(T
R)、107a〜107eはCTである。108は、電
動機,照明機器,コンピュータ,空調機など各種の負荷
である。
FIG. 2 is a configuration diagram of a system in which the transmission terminal device 1 shown in FIG. 1 is applied to a distribution system. 102 is a transformer (TR), 103 is a fuse (F) 104 is an instrument transformer (VT) 105a to 105e are instrument current transformers (C
T). 106 is a transformer (T) such as a secondary substation.
R), 107a to 107e are CTs. Reference numeral 108 denotes various loads such as a motor, a lighting device, a computer, and an air conditioner.

【0021】100は中央装置で、各現場に設置された
複数の伝送端末装置1が計測し演算した結果を集計して
監視するための計算機(汎用パソコン等)である。10
1は、各伝送端末装置1と中央装置100とを接続する
伝送線である。
Reference numeral 100 denotes a central unit, which is a computer (general-purpose personal computer or the like) for totalizing and monitoring the results measured and calculated by a plurality of transmission terminal devices 1 installed at each site. 10
Reference numeral 1 denotes a transmission line that connects each transmission terminal device 1 and the central device 100.

【0022】図3は、図1の単線図で示した配電系統の
被監視電路と伝送端末装置1の詳細な実体結線図であ
る。図3の実体結線図は、各種相線式のうち三相3線式
を示したもので、配電系統では最も一般的なものであ
る。図中のR,S,Tは配電線の相を示すもので、理解
し易いように、RはR相,SはS相,TはT相を示して
いる。従って、このような相線式での電流の計測・監視
は、1つの分岐に対し少なくとも2ヶ所必要であり、図
中ではCTを105aR,105aTなどと示してい
る。尚、単相3線式も同様である。
FIG. 3 is a detailed actual connection diagram of the monitored circuit of the distribution system and the transmission terminal device 1 shown in the single line diagram of FIG. The solid connection diagram of FIG. 3 shows a three-phase three-wire system among various phase-wire systems, and is the most general one in a distribution system. In the figure, R, S, and T indicate phases of the distribution line. For easy understanding, R indicates the R phase, S indicates the S phase, and T indicates the T phase. Therefore, such a phase-wire type current measurement / monitoring requires at least two locations for one branch, and CTs are shown as 105aR, 105aT, etc. in the figure. The same applies to the single-phase three-wire system.

【0023】図4は、図1における設定部22a及び2
2b〜22nの詳細回路と、VT,CTの一次定格に対
する設定部の対応を示している。220,221は電位
を確立させるための抵抗である。
FIG. 4 shows the setting sections 22a and 22 in FIG.
The detailed circuit of 2b-22n and the correspondence of the setting part to the primary rating of VT and CT are shown. 220 and 221 are resistors for establishing a potential.

【0024】図5は、伝送端末装置1の正面図である。
符号で示す部品は、図1に対応している。なお、端子2
a〜2c,12a〜12d,25や各設定部は、カバー
223,224で覆うことができる。
FIG. 5 is a front view of the transmission terminal device 1.
Parts indicated by reference numerals correspond to FIG. Terminal 2
a to 2c, 12a to 12d, 25 and each setting unit can be covered with covers 223, 224.

【0025】次に、上述した伝送端末装置1の動作を説
明する。図6は、交流信号を所定のタイミングでサンプ
リング(抽出)して計測値を求める基本的な方法を示し
たもので、本実施例では、交流の1周期を12回サンプ
リングしている。
Next, the operation of the transmission terminal device 1 will be described. FIG. 6 shows a basic method of obtaining a measurement value by sampling (extracting) an AC signal at a predetermined timing, and in this embodiment, one cycle of AC is sampled 12 times.

【0026】電流の実行値Iは、図に示す計算式のよう
に、各サンプリング値(i1〜i12)を2乗して1周期
分を加算してからサンプリング数n(12)で除し、根
をとれば算出できる。電圧も同様である。また、本実施
例では、サンプリングの後の1周期で計算結果を求めて
いる。
The execution value I of the current is calculated by squaring each sampling value (i1 to i12), adding one cycle, and dividing by the number of samplings n (12), as shown in the formula shown in FIG. It can be calculated by taking the root. The same applies to the voltage. In this embodiment, the calculation result is obtained in one cycle after the sampling.

【0027】以下、分岐部分の分岐数が“8”の例につ
いて説明する。図7は、電源投入時処理手順を示すフロ
ーチャートである。まずS1で、内部の初期処理を行
う。S2では、図1の周波数検出信号線7の矩形波チェ
ックを行い、50Hzか60Hzであるかを判定し、判
定結果によりサンプリング間隔を決定する。即ち、50
Hzでは1周期が1/50秒であるためサンプリング間
隔は1/(50×12)秒であり、60Hzでは1/
(60×12)秒となる。
An example in which the number of branches in the branch portion is "8" will be described below. FIG. 7 is a flowchart illustrating a power-on processing procedure. First, in S1, internal initial processing is performed. In S2, a rectangular wave check of the frequency detection signal line 7 in FIG. 1 is performed to determine whether the frequency is 50 Hz or 60 Hz, and a sampling interval is determined based on the determination result. That is, 50
In Hz, one cycle is 1/50 second, so the sampling interval is 1 / (50 × 12) seconds.
(60 × 12) seconds.

【0028】次のS3は、図6に示した計算処理が早く
終了した場合等を考慮したもので、次回のサンプリング
開始タイミング(例えば上記矩形波の立上り)をチェッ
クする。そしてS4で上記サンプリング間隔をCPU8
の内部タイマにセットし、所定のタイミングで割込処理
ができるようにする。次のS5では、上記割込処理が可
能なようにタイマ割込解除を行い、割込待ちとなる。
The next step S3 is to take into consideration the case where the calculation processing shown in FIG. 6 has been completed earlier, and checks the next sampling start timing (for example, the rising edge of the rectangular wave). Then, in S4, the CPU 8 sets the sampling interval to
The internal timer is set so that interrupt processing can be performed at a predetermined timing. In the next step S5, the timer interrupt is released so that the above-described interrupt processing can be performed, and the process waits for an interrupt.

【0029】図8は、タイマ割込処理手順を示すフロー
チャートである。この割込間隔の時間は、上記したサン
プリング間隔の時間である。まずS6で、前記した保持
指令信号線6を介してホールド(保持)指令を行ってか
らS7に処理が移る。S7では、まずS7aで選択部1
7の第1チャンネルを選択し(この場合被監視電路のR
相−S相間の電圧に相当)、次にS7bでA/D変換部
19に対し変換指令を行う。次にS7cで変換が終了し
たか否かを判断し、終了していなければ終了を待ち、終
了していればS7に移り変換されたディジタル量(値)
を読出してRAM10に記憶する。なお、記憶場所につ
いては図11で後述する。
FIG. 8 is a flowchart showing a timer interrupt processing procedure. The time of the interruption interval is the time of the sampling interval described above. First, in S6, a hold (hold) command is issued via the hold command signal line 6, and the process proceeds to S7. In S7, first, in S7a, the selection unit 1
7 is selected (in this case, R
Next, in S7b, a conversion command is issued to the A / D conversion unit 19. Next, in S7c, it is determined whether or not the conversion has been completed. If the conversion has not been completed, the process waits for the completion.
Is read and stored in the RAM 10. The storage location will be described later with reference to FIG.

【0030】次にS8では選択部17の第2チャンネル
を選択し(この場合被監視電路のS相−T相間の電圧に
相当)、上記S7と同様の処理を行う。次のS9では選
択部17の第3チャンネルを選択し(この場合被監視電
路のCTのR相に相当)、上記S7と同様の処理を行
う。S10では選択部17の第4チャンネルを選択し
(この場合被監視電路のCTのT相に相当)、上記S7
と同様の処理を行う。以下、同様にして他の分岐部分の
被監視電路のCTに対応する第18チャンネルまで処理
を次々に行う。この一連の処理が、図6に示すv1,i1
の位置に相当するタイミングである。
Next, in S8, the second channel of the selector 17 is selected (corresponding to the voltage between the S phase and the T phase of the monitored electric circuit in this case), and the same processing as in S7 is performed. In the next S9, the third channel of the selector 17 is selected (corresponding to the R phase of the CT of the monitored electric circuit in this case), and the same processing as the above S7 is performed. In S10, the fourth channel of the selection unit 17 is selected (in this case, it corresponds to the T phase of CT of the monitored circuit), and
The same processing is performed. Hereinafter, similarly, the processing is successively performed up to the 18th channel corresponding to the CT of the monitored electric circuit of the other branch portion. This series of processing is performed by v1, i1 shown in FIG.
Is the timing corresponding to the position.

【0031】S12では、上記で説明した交流の1周期
分のサンプリング回数即ち本実施例例では12回が終了
したか否かをチェックし、終了していなければS13に
移り記憶場所を更新してS14で後述する受信割込みを
解除し、次のサンプリングタイミング(即ち図6のv
2,i2の位置)で割込みが発生するのを待つ。
In S12, it is checked whether or not the number of samplings for one cycle of the AC described above, that is, in this embodiment, whether or not twelve has been completed. If not, the flow proceeds to S13 to update the storage location. In S14, the reception interrupt described later is released, and the next sampling timing (ie, v in FIG. 6)
Wait for an interrupt at (2, i2).

【0032】このようにして1周期12回の一連の処理
が終了すると、S15に移りタイマ割込を禁止(即ちサ
ンプリング処理)し、S16では受信割込を解除し計算
処理S17に移る。計算処理は図10で後述する。次に
計算処理が終了するとS18に移り、S3と同様タイミ
ングチェックを行い、S19でタイマ割込を解除し、待
機状態即ち割込み待ち状態となる。
When a series of processes of 12 times in one cycle is completed in this way, the process proceeds to S15 to inhibit the timer interrupt (that is, the sampling process). In S16, the reception interrupt is released, and the process proceeds to S17. The calculation process will be described later with reference to FIG. Next, when the calculation process is completed, the process proceeds to S18, where a timing check is performed in the same manner as in S3, the timer interrupt is released in S19, and a standby state, that is, an interrupt wait state is set.

【0033】図9は、受信割込み処理手順を示すフロー
チャートである。この処理は、上位装置100との間で
通信を行うための処理である。受信割込みは、図8で説
明したタイマ割込み処理より優先度は低く、受信割込み
が解除されているところで処理が行われる。
FIG. 9 is a flowchart showing a reception interrupt processing procedure. This process is a process for performing communication with the host device 100. The reception interrupt has a lower priority than the timer interrupt process described with reference to FIG. 8, and the process is performed when the reception interrupt is released.

【0034】まず、S40で受信した内容について通信
上の障害有無のチェックを行い、次にS41で送信する
データ(図12に示す計算結果)の先頭アドレスをセッ
トし、S42で送信可能状態にあるかチェックし、送信
可能状態でなければ待ち、送信可能であればS43で上
記アドレスで示した場所のデータを読出しS44で送信
を行う。次のS45では、上記データのすべてが送信終
わったかをチェックし、終わってなければS46でデー
タアドレスの更新を行いS42に戻る。また、全データ
の送信が終了した場合は、元の処理すなわち、待機状態
の場所に戻る。あるいは、S17の演算処理の途中に戻
り処理を継続する。
First, the content received in S40 is checked for a communication failure, then the head address of the data to be transmitted (the calculation result shown in FIG. 12) is set in S41, and the transmission is possible in S42. If it is possible to transmit, data is read from the location indicated by the above address in S43 and transmitted in S44. In the next S45, it is checked whether or not all the data has been transmitted. If not, the data address is updated in S46 and the process returns to S42. When the transmission of all data is completed, the process returns to the original processing, that is, the place in the standby state. Alternatively, the process returns to the middle of the calculation process in S17 and continues.

【0035】図10は、三相3線式,単相3線式におけ
る計算処理手順を示すフローチャートである。図11
は、図6及び図8で説明したところの所定のタイミング
でサンプリングを行い、A/Dコンバータ17でディジ
タル量に変換し、読み書き可能なRAM10に記憶した
ところを示す図である。また図12は、図10で示した
計算処理の結果を記憶した例を示す図である。
FIG. 10 is a flowchart showing the calculation processing procedure in the three-phase three-wire system and the single-phase three-wire system. FIG.
FIG. 9 is a diagram showing that sampling is performed at the predetermined timing described in FIGS. 6 and 8, converted into a digital amount by the A / D converter 17, and stored in the readable / writable RAM 10. FIG. 12 is a diagram illustrating an example in which the result of the calculation process illustrated in FIG. 10 is stored.

【0036】まず、図11に示すサンプリングしたデー
タからS30でR相・S相間の線間電圧について計算を
行うが、計算の基本は図6に示した通りである。次にS
31でS相・T相間の線間電圧を同様に求め、S32で
はT相・R相間の線間電圧を計算する。尚、三相3線式
及び単相3線式におけるT相・R相間の線間電圧は、0
から減算すれば得られることは公知である。
First, the line voltage between the R phase and the S phase is calculated in S30 from the sampled data shown in FIG. 11, and the calculation is basically performed as shown in FIG. Then S
At S31, the line voltage between the S phase and the T phase is similarly obtained, and at S32, the line voltage between the T phase and the R phase is calculated. The line voltage between the T phase and the R phase in the three-phase three-wire system and the single-phase three-wire system is 0.
It is known that it can be obtained by subtracting from.

【0037】次にS33では、図1に示した入力部11
aに対応する電流について計算を行う。即ち、R相の電
流をS33aで、T相の電流をS33bで計算し、S相
は上記電圧と同様に、S33cに示すように、0から減
じれば結果が得られる。S34では、図1に示した入力
部11bに対応する電流について計算を行うが、これは
S33と同様である。
Next, in S33, the input unit 11 shown in FIG.
Calculation is performed on the current corresponding to a. That is, the current of the R phase is calculated by S33a, the current of the T phase is calculated by S33b, and the result is obtained by subtracting the S phase from 0 as shown in S33c, similarly to the above voltage. In S34, the calculation is performed on the current corresponding to the input unit 11b shown in FIG. 1, but this is the same as S33.

【0038】以上のようにして、次々と電流計算を行な
い、本実施例では、8組分の電流について計算し、結果
を、図12に示すように、RAM10の各記憶領域に記
憶する。
As described above, the current is calculated one after another. In the present embodiment, the current is calculated for eight sets, and the result is stored in each storage area of the RAM 10 as shown in FIG.

【0039】尚、上記実施例では1組の電圧の計算処理
も含めて説明したが、この計算処理を省略することは可
能である。また、図10で示したフローチャートでは、
図4に示すVT,CTの一次定格に対する換算計算及
び、図1に示す増幅器14,27,A/Dコンバータの
分解能に関する詳細説明を省略したが、各々の根を求め
る計算の後でまとめて計算することができるのは明白で
ある。
Although the above embodiment has been described including the calculation of one set of voltages, this calculation can be omitted. Also, in the flowchart shown in FIG.
Although the conversion calculation for the primary ratings of VT and CT shown in FIG. 4 and the detailed description of the resolution of the amplifiers 14 and 27 and the A / D converter shown in FIG. 1 are omitted, the calculation is collectively performed after the calculation for obtaining the respective roots. Obviously you can.

【0040】以上の実施例によれば、三相3線式及び単
相3線式における分岐部分の複数の電流と電圧について
計測・監視が行なえる。
According to the above-described embodiment, measurement and monitoring can be performed on a plurality of currents and voltages at branch portions in the three-phase three-wire system and the single-phase three-wire system.

【0041】次に、本発明の応用実施例について図13
〜図15を参照して説明する。図13は、単相2線式の
システムに上述した伝送端末装置1を接続した図であ
る。本実施例では、電源端子2bと2cは端子部で短絡
したもので、前記で説明したS相・T相間の電圧は
“0”になる。図14は単相2線式の計算フローチャー
トを示し、図11で示したサンプリングデータを基に計
算する。図14での計算処理において、前述した第1実
施例と異なる点は、電圧計算が1相分(R・S間)、電
流計算のS相分が無い点である。また図15に計算結果
の記憶例を示す。
Next, an application example of the present invention will be described with reference to FIG.
This will be described with reference to FIGS. FIG. 13 is a diagram in which the above-described transmission terminal device 1 is connected to a single-phase two-wire system. In this embodiment, the power supply terminals 2b and 2c are short-circuited at the terminals, and the voltage between the S phase and the T phase described above becomes "0". FIG. 14 shows a calculation flowchart of the single-phase two-wire system, and the calculation is performed based on the sampling data shown in FIG. The calculation processing in FIG. 14 differs from the above-described first embodiment in that the voltage calculation is for one phase (between R and S) and the current calculation is not for the S phase. FIG. 15 shows a storage example of the calculation result.

【0042】すなわち、本実施例では、三相3線式及び
単相3線式から余分な計算を省いているが、逆の発想か
らすれば、第1実施例の計算処理をそのまま用いても何
ら支障がないことを示すものである。
That is, in this embodiment, extra calculations are omitted from the three-phase three-wire system and the single-phase three-wire system. However, from the opposite viewpoint, the calculation process of the first embodiment can be used as it is. This indicates that there is no problem.

【0043】第1実施例では、三相3線式及び単相3線
式の分岐数8の電流計測を示したが、本実施例では、応
用の仕方によって、単相2線式の分岐数16の電流計測
が可能なことを意味しているわけである。
In the first embodiment, the current measurement with the number of branches of eight in the three-phase three-wire system and the single-phase three-wire system has been described. In the present embodiment, the number of branches in the single-phase two-wire system depends on the application. This means that 16 current measurements are possible.

【0044】次に、本発明の第2実施例について、図1
6〜図18を参照して説明する。第2実施例の目的とす
るところは、分岐部分の2組以上の被監視電路の電流
と、電力及び電力量の計測を可能とするところにある。
三相3線式及び単相3線式の電流計測については上記第
1実施例について説明したので省略し、以下電力及び電
力量の計測について説明する。
Next, a second embodiment of the present invention will be described with reference to FIG.
This will be described with reference to FIGS. An object of the second embodiment is to enable the measurement of the current, the electric power, and the electric energy of two or more sets of monitored electric circuits in the branch portion.
The description of the three-phase three-wire current measurement and the single-phase three-wire current measurement is omitted because it has been described in the first embodiment, and the measurement of electric power and electric energy will be described below.

【0045】図16は、単相分の電力を表現したもの
で、交流の1周期の電流と電圧の積を平均したもの(図
の△P)が電力と定義されていることは公知の通りであ
る。従って、図6において説明した所定のタイミング毎
のサンプリングした電流iと電圧vの積を1周期分加算
し、サンプリング回数で除したものが電力となる。また
電力量は、電力に時間を乗じたものであり、図中に示す
△Pと△tを乗じ、結果を累積したものが積算電力量と
なる。
FIG. 16 shows the power for a single phase, and it is known that the average of the product of the current and the voltage in one AC cycle (ΔP in the figure) is defined as the power. It is. Therefore, the product obtained by adding the product of the sampled current i and voltage v at each predetermined timing described in FIG. 6 for one cycle and dividing by the number of times of sampling is the power. The electric energy is obtained by multiplying electric power by time, multiplying ΔP and Δt shown in the figure, and accumulating the result to be an integrated electric energy.

【0046】次に、図17を用いて、計算の手順を説明
する。まず、図11で説明した電圧と電流のサンプリン
グデータをもとに、S60で入力部11aに対応した部
分の電力の計算を行うが、S60aではR相・S相間の
電力を求める。次にS60bで、S相・T相間の電力を
求める。次の60cでは、二電力計法により1分岐分の
電力を求める。同様にして他の電流入力部11b,…,
11n(本例では8分岐分)に対応して、S61,S6
2の順で計算を行う。
Next, the calculation procedure will be described with reference to FIG. First, based on the voltage and current sampling data described with reference to FIG. 11, the power of the portion corresponding to the input unit 11a is calculated in S60. In S60a, the power between the R phase and the S phase is obtained. Next, in S60b, the power between the S phase and the T phase is obtained. In the next 60c, the power for one branch is obtained by the two-power meter method. Similarly, the other current input units 11b,.
11n (in this example, for eight branches), S61 and S6
Calculation is performed in the order of 2.

【0047】S63では、電力量を計算するが、図6で
説明したように、計算処理を次の周期で専有するので、
“2”を乗じ累積,結果を記憶する。このような処理を
S64,S65と次々に行い、結果を、図19に示すよ
うにRAM10に記憶する。この後で、図10に示した
電流計算を行う。図18は、上記電力及び電力量の計算
結果を記憶した例を示す図である。図中(△PRS),
(△PST)は各線間の電力を示す。
In S63, the electric energy is calculated. However, as described with reference to FIG. 6, since the calculation processing is exclusively used in the next cycle,
Multiply by "2" and accumulate and store the result. Such processing is sequentially performed in S64 and S65, and the result is stored in the RAM 10 as shown in FIG. Thereafter, the current calculation shown in FIG. 10 is performed. FIG. 18 is a diagram illustrating an example in which the calculation results of the power and the power amount are stored. In the figure (△ PRS),
(△ PST) indicates the power between the lines.

【0048】なお、本実施例では、電力量の計算を全部
の電力の計算後に行ったが、各部分の電力計算直後に計
算しても良いことは当然である。また、図6で示した計
算処理の時間は1周期分で示したが、計算処理時間が長
く必要であれば次の周期まで延長して3倍すれば良いこ
とは言うまでもない。
In this embodiment, the calculation of the electric energy is performed after the calculation of all the electric powers. However, it is obvious that the calculation may be performed immediately after the electric power of each part is calculated. In addition, although the calculation processing time shown in FIG. 6 is shown for one cycle, it goes without saying that if the calculation processing time is long, it may be extended to the next cycle and tripled.

【0049】次に、第2実施例の応用例について、図1
9,図20を参照して説明する。図19は、単相2線式
における電力・電力量の計算フローチャートを示すもの
で、S70とS71は、図13に示す105aR,10
5aTに相当する電力の計算を行うステップであり、S
60aは図17と同じである。S71(60b’)は、
図17に示すS60bと少し異なり、電圧のサンプリン
グデータが、S60aと同じR・S間の電圧とT相の電
流の積になる点が異なるが、後は同じである。同様にし
て、S72,S73,S74の順に16点分の電力計算
を行う。そして、S75で電力量の計算を行い、S7
6,S77と順次16点分の電力量計算を行う。
Next, an application example of the second embodiment will be described with reference to FIG.
This will be described with reference to FIG. FIG. 19 is a flowchart showing calculation of electric power and electric energy in the single-phase two-wire system. S70 and S71 correspond to 105aR, 10A shown in FIG.
This is the step of calculating the power corresponding to 5 aT,
60a is the same as FIG. S71 (60b ')
Slightly different from S60b shown in FIG. 17, the voltage sampling data is different from S60a in that it is the same product of the voltage between R and S and the T-phase current as in S60a. Similarly, power calculation for 16 points is performed in the order of S72, S73, and S74. Then, the power amount is calculated in S75, and in S7
The calculation of the electric energy for 16 points is sequentially performed in steps S6 and S77.

【0050】また、これら計算した結果は、図20で示
すようにRAM10の所定位置に記憶する。ここで図中
の“−”は空きを示すが、図18と対比してみれば、こ
の意味は理解できるはずである。すなわち、三相3線式
及び単相3線式の考え方との思想統一である。しかしな
がら、計算処理手順においては、上記説明した通り電圧
について異なるため、処理手順を記憶するROM9は異
なる。
The results of these calculations are stored at predetermined positions in the RAM 10 as shown in FIG. Here, "-" in the figure indicates an empty space, but this meaning should be understood by comparing with FIG. That is, the concept is unified with the three-phase three-wire system and the single-phase three-wire system. However, in the calculation processing procedure, since the voltage is different as described above, the ROM 9 storing the processing procedure is different.

【0051】図1の説明では、停電検出部28及び負不
揮発性記憶部26の説明を省いたので、以下これを説明
する。停電検出部28は、波形整形回路6の出力を受け
て動作をする。即ち、停電を検出し、これを停電検出信
号線29を介してCPU8にいち早く伝え、電力量の計
算結果を不揮発性記憶部26に記憶させる。
In the description of FIG. 1, the description of the power failure detection unit 28 and the negative nonvolatile storage unit 26 is omitted, and the description will be made below. The power failure detection unit 28 operates upon receiving the output of the waveform shaping circuit 6. That is, the power failure is detected, the power failure is immediately transmitted to the CPU 8 via the power failure detection signal line 29, and the calculation result of the electric energy is stored in the nonvolatile storage unit 26.

【0052】不揮発性記憶部26は、例えばEEPRO
M(Electrical・Erasable・Pro
grammable・Read・Only・Memmo
ry)で構成される。この素子は、電気的消去可能で書
き変え可能なメモリ素子であり、永久的に記憶ができ
る。
The nonvolatile storage unit 26 stores, for example, EEPRO
M (Electrical / Erasable / Pro)
Grammable, Read, Only, Memmo
ry). This element is an electrically erasable and rewritable memory element that can be permanently stored.

【0053】復電した場合は、図7に示す電源投入時フ
ローチャートの初期処理で上記不揮発性記憶部26の内
容をRAM10の電力量計算結果の位置に転送し、これ
により継続して計算結果を累積することが可能となる。
When the power is restored, the contents of the non-volatile storage unit 26 are transferred to the position of the power amount calculation result in the RAM 10 in the initial processing of the power-on flowchart shown in FIG. It is possible to accumulate.

【0054】次に、本発明の第3実施例について、図4
及び図21を用いて説明する。上述した第2実施例で
は、三相3線式及び単相3線式と単相2線式とで電力計
算処理が異なるためROM9を各々専用としたが、製品
の標準化の見知で考えると好ましくない。そこで本実施
例では、これを解決するために、図21に示す相線式判
断処理を行う。
Next, a third embodiment of the present invention will be described with reference to FIG.
This will be described with reference to FIG. In the above-described second embodiment, the ROM 9 is dedicated to each of the three-phase three-wire system, the single-phase three-wire system, and the single-phase two-wire system because the power calculation processing is different. However, considering the standardization of products, Not preferred. Therefore, in the present embodiment, in order to solve this, a phase line type determination process shown in FIG. 21 is performed.

【0055】そこで、図4に示すVT一次定格設定部2
2aのビットNo.4(222)を利用してCPUが相線
式を判断し、図21に示すフローチャートの計算処理を
行う。すなわち、計算処理に先立ち、S47で、単相2
線式(上記VT一次定格設定部のビットNo.4がオン)
か否かを判断し、単相2線式でなければS48で三相3
線式(単相3線式も同じ)の電力・電力量計算を行い、
S49でさらに電圧・電流の計算を行う。単相2線式で
あればS47からS50に進み、単相2線式の電力・電
力量計算を行った後、単相2線式の電圧・電流計算を行
う。計算処理の内容は、第1実施例,第2実施例で説明
した通りである。また、計算処理の手順は、ROM9に
記憶する。
Therefore, the VT primary rating setting section 2 shown in FIG.
Using the bit No. 4 (222) of 2a, the CPU determines the phase line type and performs the calculation processing of the flowchart shown in FIG. That is, prior to the calculation processing, in S47, the single-phase 2
Wire type (bit No. 4 of the VT primary rating setting section is on)
It is determined whether or not it is not a single-phase two-wire system.
Calculate the electric power and electric energy of the wire system (same for the single-phase three-wire system)
In S49, calculation of voltage and current is further performed. If it is a single-phase two-wire system, the process proceeds from S47 to S50, where a single-phase two-wire power / power amount calculation is performed, and then a single-phase two-wire voltage / current calculation is performed. The contents of the calculation processing are as described in the first embodiment and the second embodiment. The calculation procedure is stored in the ROM 9.

【0056】以上のように、相線式の判断を行うことに
より、分岐部分の相線式に合わせて伝送端末装置1を用
いることができる。従って、製品の標準化がはかれ、ま
た、使用者は機種選定の煩わしさがなくなる。
As described above, the transmission terminal apparatus 1 can be used in accordance with the phase line type of the branching part by performing the phase line type determination. Therefore, the product is standardized, and the user does not have to select a model.

【0057】ところで、上記第2実施例及び第3実施例
での電気量計測は、電圧・電流,電力・電力量であった
が、電圧・電流のサンプリングデータがあれば、無効電
力,無効電力量を算出することができる。詳細説明は省
略するが、無効電力は位相差90°の電圧と電流の積で
求められることは公知の事実である。また、電力(有効
電力)と無効電力が得られると、力率を計算できること
は勿論である。
Although the electric quantity measurement in the second embodiment and the third embodiment is voltage / current and power / power amount, if there is sampling data of voltage / current, reactive power and reactive power The amount can be calculated. Although detailed description is omitted, it is a known fact that the reactive power is obtained by the product of the voltage and the current having a phase difference of 90 °. When the power (active power) and the reactive power are obtained, the power factor can of course be calculated.

【0058】[0058]

【発明の効果】本発明によれば、受配電系統における分
岐部分毎のCT一次定格や、VTの一次定格を気にする
ことなく仕様決めが1台の装置で容易に計測でき、中央
装置で集中した監視が可能となる。また、伝送端末装置
自身で各々の計算を行い上位装置に伝送するので、中央
装置の負担が軽減され、更に、CTやVTの変更があっ
ても伝送端末装置で対応できるのため、中央装置の計算
処理を変更する必要がないという効果もある。
According to the present invention, the specification can be easily measured by one device without worrying about the CT primary rating and the VT primary rating for each branch portion in the power distribution system. Centralized monitoring becomes possible. In addition, since the transmission terminal device itself performs each calculation and transmits it to the higher-level device, the burden on the central device is reduced. Further, even if there is a change in CT or VT, the transmission terminal device can cope with the change. There is also an effect that there is no need to change the calculation process.

【0059】また、配線作業工数の低減,設置面積の低
減など効果は大である。さらに、分岐部分の各分岐毎の
電力,電力量の計測を可能としたことは、負荷毎のきめ
細かなエネルギー使用状態を把握でき、省エネルギーの
施策に役立つ。更にまた、相線式を判断できることによ
り、配電系統の相線式に合わせた計測が1台で行える大
きな効果があり、投資費用の大きな低減と、配電系統の
安定した供給に絶大な効果をもたらす。
The effects of reducing the number of man-hours for wiring work and reducing the installation area are great. Further, the fact that the power and the amount of power for each branch of the branch portion can be measured enables detailed energy use state for each load to be grasped, which is useful for energy saving measures. Furthermore, since the phase line type can be determined, there is a great effect that the measurement according to the phase line type of the distribution system can be performed by one unit, which greatly reduces the investment cost and has a great effect on the stable supply of the distribution system. .

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例に係る伝送端末装置のブロッ
ク構成図である。
FIG. 1 is a block diagram of a transmission terminal apparatus according to an embodiment of the present invention.

【図2】図1に示す伝送端末装置を配電系統に配置した
システム構成図である。
FIG. 2 is a system configuration diagram in which the transmission terminal device shown in FIG. 1 is arranged in a distribution system.

【図3】三相3線式(単相3線式も同様)における実体
結線図である。
FIG. 3 is a substantial connection diagram in a three-phase three-wire system (the same applies to a single-phase three-wire system).

【図4】CT,VTの一次定格を設定する設定部の詳細
図と一次定格に対する設定部の設定対応内容を示す図で
ある。
FIG. 4 is a detailed diagram of a setting unit for setting a primary rating of CT and VT, and a diagram showing contents of setting of the setting unit for the primary rating.

【図5】伝送端末装置の正面図である。FIG. 5 is a front view of the transmission terminal device.

【図6】サンプリングと電流・電圧計算式を説明する図
である。
FIG. 6 is a diagram illustrating sampling and current / voltage calculation formulas.

【図7】電源投入時の処理手順を示すフローチャートで
ある。
FIG. 7 is a flowchart illustrating a processing procedure when power is turned on.

【図8】タイマ割り込み処理手順を示すフローチャート
である。
FIG. 8 is a flowchart illustrating a timer interrupt processing procedure.

【図9】受信割り込み処理手順を示すフローチャートで
ある。
FIG. 9 is a flowchart illustrating a reception interrupt processing procedure.

【図10】三相3線式・単相3線式計算処理手順を示す
フローチャートである。
FIG. 10 is a flowchart illustrating a three-phase three-wire / single-phase three-wire calculation processing procedure;

【図11】サンプリングデータの記憶例を示す図であ
る。
FIG. 11 is a diagram illustrating a storage example of sampling data.

【図12】三相3線式・単相3線式計算結果の記憶例を
示す図である。
FIG. 12 is a diagram illustrating a storage example of a calculation result of a three-phase three-wire system / single-phase three-wire system.

【図13】単相2線式の実体結線図である。FIG. 13 is a schematic diagram of a single-phase two-wire system.

【図14】単相2線式における電流計算フローチャート
である。
FIG. 14 is a current calculation flowchart in a single-phase two-wire system.

【図15】単相2線式の計算結果の記憶例を示す図であ
る。
FIG. 15 is a diagram illustrating a storage example of a single-phase two-wire calculation result.

【図16】電力計算を説明する図である。FIG. 16 is a diagram illustrating power calculation.

【図17】三相3線式(単相3線式も同じ)の電力・電
力量の計算フローチャートである。
FIG. 17 is a calculation flowchart of electric power and electric energy of a three-phase three-wire system (the same applies to a single-phase three-wire system).

【図18】電力・電力量計算結果の記憶例を示す図であ
る。
FIG. 18 is a diagram illustrating a storage example of power / power amount calculation results.

【図19】単相2線式の電力・電力量の計算フローチャ
ートである。
FIG. 19 is a calculation flowchart of electric power and electric energy of a single-phase two-wire system.

【図20】図19の結果の記憶例を示す図である。20 is a diagram illustrating a storage example of the result of FIG. 19;

【図21】相線式を判断して処理を行うフローチャート
である。
FIG. 21 is a flowchart for performing processing by determining a phase line type.

【符号の説明】[Explanation of symbols]

1;伝送端末装置、2;電源端子、11a,11b,
…,11n;電流信号入力部、17;選択部、19;A
/D変換部、8;中央処理装置、22a;VT一次定格
設定部、22b,22c,…,22n;CT一次定格設
定部、24;伝送部、222;相線式判断ビット。
1, transmission terminal device, 2: power supply terminal, 11a, 11b,
..., 11n; current signal input section, 17; selection section, 19;
/ D conversion unit, 8; central processing unit, 22a; VT primary rating setting unit, 22b, 22c, ..., 22n; CT primary rating setting unit, 24; transmission unit, 222;

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 2組以上の被監視電路の電流信号と被監
視電路の電圧信号を所定のタイミングで選択する選択手
段と、 該選択した前記電流信号及び電圧信号をディジタル量に
変換するアナログ/ディジタル変換手段と、 該変換したディジタル量を記憶する記憶手段と、 前記被監視電路の電圧及び電流に対応した定格値を設定
する定格値設定手段と、 前記記憶したディジタル量について前記定格値設定手段
により設定された定格値に基づいて被監視電路の電気量
を演算する中央処理装置と、 上位装置との間で前記演算の結果を通信する伝送手段
と、 を一体に収納することを特徴とする伝送端末装置。
1. A selecting means for selecting, at a predetermined timing, current signals of two or more sets of monitored circuits and voltage signals of monitored circuits, and an analog / digital converter for converting the selected current signals and voltage signals into digital quantities. Digital conversion means; storage means for storing the converted digital quantity; rated value setting means for setting a rated value corresponding to the voltage and current of the monitored circuit; and rated value setting means for the stored digital quantity. A central processing unit that calculates the electric quantity of the monitored electric circuit based on the rated value set by the above, and a transmission unit that communicates the result of the calculation between the host device and the host device. Transmission terminal equipment.
JP2001377538A 1995-05-23 2001-12-11 Transmission terminal Pending JP2002199466A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP12380395A JP3634893B2 (en) 1995-05-23 1995-05-23 Transmission terminal device
JP2001377538A JP2002199466A (en) 1995-05-23 2001-12-11 Transmission terminal

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP12380395A JP3634893B2 (en) 1995-05-23 1995-05-23 Transmission terminal device
JP2001377538A JP2002199466A (en) 1995-05-23 2001-12-11 Transmission terminal

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP12380395A Division JP3634893B2 (en) 1995-05-23 1995-05-23 Transmission terminal device

Publications (1)

Publication Number Publication Date
JP2002199466A true JP2002199466A (en) 2002-07-12

Family

ID=61558555

Family Applications (2)

Application Number Title Priority Date Filing Date
JP12380395A Expired - Fee Related JP3634893B2 (en) 1995-05-23 1995-05-23 Transmission terminal device
JP2001377538A Pending JP2002199466A (en) 1995-05-23 2001-12-11 Transmission terminal

Family Applications Before (1)

Application Number Title Priority Date Filing Date
JP12380395A Expired - Fee Related JP3634893B2 (en) 1995-05-23 1995-05-23 Transmission terminal device

Country Status (1)

Country Link
JP (2) JP3634893B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013122424A (en) * 2011-12-12 2013-06-20 Hioki Ee Corp Voltage measuring instrument, current measuring instrument and power measuring instrument

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE517963C2 (en) * 2000-05-31 2002-08-06 Abb Ab Mains protection system for the protection of the integrity of a total electrical power system, electric power system including a network protection, system protection procedure, system protection terminal and computer software product
SE517714C2 (en) * 2000-05-31 2002-07-09 Abb Ab Mains protection system for protecting the integrity of a total electrical power system against slightly damped power fluctuations, electric power system including a network protection, system protection system procedure, system protection terminal, computer program product and computer readable medium
JP5355047B2 (en) * 2008-11-17 2013-11-27 中国電力株式会社 Power factor improvement promotion system
KR101717661B1 (en) * 2016-02-02 2017-03-17 엘에스산전 주식회사 Temperature rising test apparatus of deverged circuit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013122424A (en) * 2011-12-12 2013-06-20 Hioki Ee Corp Voltage measuring instrument, current measuring instrument and power measuring instrument

Also Published As

Publication number Publication date
JPH08317476A (en) 1996-11-29
JP3634893B2 (en) 2005-03-30

Similar Documents

Publication Publication Date Title
KR100840042B1 (en) Monitor apparatus
US5247454A (en) Reconfigurable circuit monitoring system
US7006934B2 (en) Revenue meter with power quality features
US6185508B1 (en) Power meter for determining parameters of multi-phase power lines
US6611772B1 (en) Electronic electricity meter configurable to operate in a plurality of meter forms and ratings
US20100121586A1 (en) unbalance power of an electrical facility or system, along with the device for its calibration
JP2003222645A (en) Multicircuit power measuring device
JP2002199466A (en) Transmission terminal
JP3686878B2 (en) Backpack unit communicating with PC computer system to monitor power consumption
JP2866615B2 (en) Power saving measurement device
JP2004184346A (en) Insulation state measuring apparatus
AU695365B2 (en) Electrical apparatus with wide dynamic range for monitoring and protecting electric power systems
KR100538018B1 (en) A new measurement equipment for the shieth currents of grounding power cables
CN116223871A (en) Metering device and metering method for replacing electric energy meter without power outage
JP2000249723A (en) Measuring terminal device
JP2001133496A (en) Multi power-measuring instrument
JP2001298877A (en) Device for monitoring power of a plurality of loads
JP2005233879A (en) Single-phase three-wire system watt-hour meter equipped with line current monitoring function, and line current managing system thereof
JP2000241461A (en) Measuring device and circuit breaker using the same
JP3493520B2 (en) Load management system
KR100490143B1 (en) System for measuring the harmonics of electric power in using internet
JP2004007921A (en) Inspection test device of digital form protection relay system
JP3027212B2 (en) Harmonic observation equipment
JPH1164401A (en) Convenient power monitor
JPH0610818U (en) Digital measurement / monitoring control device