JP2002147190A - Tunnel constructing method - Google Patents
Tunnel constructing methodInfo
- Publication number
- JP2002147190A JP2002147190A JP2000341726A JP2000341726A JP2002147190A JP 2002147190 A JP2002147190 A JP 2002147190A JP 2000341726 A JP2000341726 A JP 2000341726A JP 2000341726 A JP2000341726 A JP 2000341726A JP 2002147190 A JP2002147190 A JP 2002147190A
- Authority
- JP
- Japan
- Prior art keywords
- partition wall
- tunnel
- end surface
- support members
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、トンネル内に仕切
壁を据え付ける工程を有するトンネルの施工方法に関す
るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunnel construction method including a step of installing a partition wall in a tunnel.
【0002】[0002]
【従来の技術】従来より、図4に示すような、内部に仕
切壁40を有するトンネル41がある。この仕切壁40
は、トンネル41内に配設される電力線等の各種ケーブ
ル42とガス管等の配管43との配設位置を仕切ること
によって安全性を向上させるものである。従来におい
て、仕切壁40は、施工現場にてコンクリートを打設す
ることによって形成されたり、あるいは、図4に示すよ
うに複数のブロック40aを組み立てることによって形
成されていた。2. Description of the Related Art Conventionally, there is a tunnel 41 having a partition wall 40 therein as shown in FIG. This partition wall 40
Is to improve the safety by partitioning the arrangement positions of various cables 42 such as power lines arranged in the tunnel 41 and pipes 43 such as gas pipes. Conventionally, the partition wall 40 has been formed by casting concrete at a construction site, or has been formed by assembling a plurality of blocks 40a as shown in FIG.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、コンク
リートを打設することによって仕切壁40を形成する方
法では、トンネル41内にコンクリート打設用の型枠を
搬入し、搬入した型枠を組み立てた後、型枠にコンクリ
ートを打設するといったように、多くの作業工程を必要
とする。同様に、複数のブロック40aを組み立てる方
法も、ブロック40aの搬入や搬入されたブロック40
aを組み立てるといった多くの作業工程を必要とする。
このように、従来の方法においては、多くの作業工程を
必要とし、これに伴って工期も長期化するので、コスト
上昇の原因となる。However, in the method of forming the partition wall 40 by casting concrete, the concrete casting formwork is loaded into the tunnel 41 and the loaded formwork is assembled. In addition, many work steps are required, such as placing concrete in a formwork. Similarly, the method of assembling the plurality of blocks 40a is based on the loading of the block 40a or the loaded block 40a.
It requires many working steps such as assembling a.
As described above, in the conventional method, many work steps are required, and accordingly, the construction period is prolonged, which causes an increase in cost.
【0004】本発明は、このような事情に鑑みてなされ
たもので、トンネル内に、効率良く短期間のうちに仕切
壁を据え付けることができるトンネルの施工方法を提供
することを目的とする。The present invention has been made in view of such circumstances, and an object of the present invention is to provide a tunnel construction method capable of efficiently installing a partition wall in a tunnel in a short period of time.
【0005】[0005]
【課題を解決するための手段】上記の課題を解決するた
め、本発明のトンネルの施工方法は、トンネル内に仕切
壁を据え付ける工程を有するトンネルの施工方法におい
て、仕切壁の下端面をその長手方向中央部から端部に向
かってテーパ状に予め形成しておくとともに、仕切壁の
下端面と、仕切壁のトンネル内での据え付け位置に相当
する床面との間に下端面の長手方向に沿って2つの支持
部材を配置し、2つの支持部材のそれぞれを仕切壁の下
端面の長手方向に移動させることによって、仕切壁を上
方に持ち上げて仕切壁の上端面とトンネルの内面とを当
接させ、仕切壁をトンネル内に据え付けることを特徴と
する。In order to solve the above-mentioned problems, a tunnel construction method according to the present invention is directed to a tunnel construction method including a step of installing a partition wall in a tunnel. In the longitudinal direction of the lower end surface between the lower end surface of the partition wall and the floor surface corresponding to the installation position of the partition wall in the tunnel while being formed in advance in a tapered shape from the direction center portion to the end portion. The partition wall is lifted upward by moving the two support members along the longitudinal direction of the lower end surface of the partition wall so that the upper end surface of the partition wall contacts the inner surface of the tunnel. And the partition wall is installed in the tunnel.
【0006】本発明によれば、仕切壁の下端面をその長
手方向中央部から端部に向かってテーパ状に予め形成し
ておくとともに、このテーパ状に形成された下端面を2
つの支持部材によって支持し、これら支持部材を下端面
の長手方向に移動することによって、仕切壁を上昇・下
降することができる。そして、仕切壁をトンネルに据え
付ける際、仕切壁をトンネルに対して位置決めするため
に、仕切壁を上方に持ち上げて仕切壁の上端面とトンネ
ルの内面とを当接する必要があるが、下端面と据え付け
位置に相当する床面との間に支持部材を配置してこれら
支持部材を移動することにより、仕切壁を容易に上方に
持ち上げることができる。したがって、トンネルに対す
る仕切壁の位置決めを効率良く行うことができ、全体の
据え付け作業効率も向上することができるので、低コス
ト化を実現することができる。According to the present invention, the lower end surface of the partition wall is formed in advance in a tapered shape from the center in the longitudinal direction to the end portion, and the tapered lower end surface is formed in two.
The partition wall can be raised and lowered by being supported by two support members and moving these support members in the longitudinal direction of the lower end surface. Then, when installing the partition wall in the tunnel, in order to position the partition wall with respect to the tunnel, it is necessary to lift the partition wall upward and abut the upper end surface of the partition wall and the inner surface of the tunnel. By disposing the support members between the floor surface corresponding to the installation position and moving these support members, the partition wall can be easily lifted upward. Therefore, the positioning of the partition wall with respect to the tunnel can be performed efficiently, and the overall installation work efficiency can be improved, so that cost reduction can be realized.
【0007】このとき、支持部材のそれぞれに雌ねじ溝
を形成するとともに、雌ねじ溝のそれぞれを棒状雄ねじ
部材で連結し、雄ねじ部材を回転させることによって支
持部材のそれぞれを容易に簡単な構成で移動させること
ができる。At this time, a female screw groove is formed in each of the support members, each of the female screw grooves is connected by a bar-shaped male screw member, and each of the support members is easily moved with a simple structure by rotating the male screw member. be able to.
【0008】支持部材の仕切壁を支持する支持面にガイ
ド溝を形成しておくことにより、仕切壁の下端面の長手
方向への支持部材の移動を安定して実現することができ
る。By forming guide grooves on the support surface of the support member that supports the partition wall, the movement of the support member in the longitudinal direction of the lower end surface of the partition wall can be stably realized.
【0009】また、支持部材の仕切壁を支持する支持面
に低摩擦抵抗部材を設けておくことによっても、支持部
材を安定して移動させることができる。Further, by providing the low frictional resistance member on the support surface of the support member that supports the partition wall, the support member can be moved stably.
【0010】[0010]
【発明の実施の形態】以下、本発明のトンネルの施工方
法の一実施形態について図1を参照しながら説明する。
図1は本発明のトンネルの施工方法を説明するための図
であって、図1(a)はトンネルの側方断面図であり、
図1(b)は支持部材と仕切壁との当接面(支持面)近
傍の拡大断面図である。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of a tunnel construction method according to the present invention will be described below with reference to FIG.
FIG. 1 is a view for explaining a tunnel construction method of the present invention, and FIG. 1 (a) is a side sectional view of the tunnel;
FIG. 1B is an enlarged cross-sectional view near the contact surface (support surface) between the support member and the partition wall.
【0011】図1(a)において、トンネルTは、この
トンネルTの内部を2つの空間に仕切る仕切壁2を有し
ている。仕切壁2はトンネルTの内部において起立状態
で据え付けられている。この仕切壁2は、図1(a)に
示すように、トンネルTの軸線L方向に沿って分割され
た複数枚の仕切壁2を接続したものである。起立状態の
仕切壁2の上端はボルト(固定部材)3によってトンネ
ルTの天井面(内面)1aに固定されている。In FIG. 1A, a tunnel T has a partition wall 2 for dividing the inside of the tunnel T into two spaces. The partition wall 2 is installed upright inside the tunnel T. As shown in FIG. 1A, the partition wall 2 is formed by connecting a plurality of partition walls 2 divided along the direction of the axis L of the tunnel T. The upper end of the partition wall 2 in the upright state is fixed to the ceiling surface (inner surface) 1a of the tunnel T by a bolt (fixing member) 3.
【0012】以上説明したような構成を有するトンネル
Tを施工する方法について説明する。まず、シールド掘
削機やボーリングマシンによって穴を掘削し、セグメン
ト1によって履工する。A method of constructing the tunnel T having the above-described configuration will be described. First, a hole is excavated by a shield excavator or a boring machine, and work is performed by segment 1.
【0013】次いで、仕切壁2をトンネルTの入口から
トンネルT内部に搬入する。ここで、仕切壁2を搬送す
る際には、例えば、仕切壁2を不図示の台車に搭載し、
この仕切壁2を搭載した台車を、予め敷設されているレ
ールに沿って仕切壁2の後側(トンネルTの入口側)か
ら押すように搬送する。Next, the partition wall 2 is carried into the tunnel T from the entrance of the tunnel T. Here, when transporting the partition wall 2, for example, the partition wall 2 is mounted on a trolley (not shown),
The trolley on which the partition wall 2 is mounted is transported along a rail laid in advance from the rear side of the partition wall 2 (the entrance side of the tunnel T).
【0014】そして、仕切壁2をトンネルTの入口から
トンネルT内部に起立させた状態のままで搬入する。こ
の仕切壁2は、例えば工場などトンネルTの施工現場以
外において予め形成されたものである。この仕切壁2の
大きさ(高さ)はトンネルTの大きさ(径)に応じて設
定されている。つまり、仕切壁2の高さは、トンネルT
内に起立した状態のままで搬送可能な程度に、上端面2
c及び下端面2dとトンネルTの内面1aとの間に僅か
な隙間が形成される程度に設定されている。Then, the partition wall 2 is carried in from the entrance of the tunnel T with the partition wall 2 standing inside the tunnel T. The partition wall 2 is formed in advance at a place other than the construction site of the tunnel T, such as a factory. The size (height) of the partition wall 2 is set according to the size (diameter) of the tunnel T. That is, the height of the partition wall 2 is
The upper end face 2 is large enough to be transported while standing inside.
c and the lower end surface 2d and the inner surface 1a of the tunnel T are set to such an extent that a slight gap is formed.
【0015】図1(a)及び図2に示すように、仕切壁
2のそれぞれの下端面2dは、その長手方向(軸線L方
向)の中央部から側端面2a、2b側に向かって上昇す
るようにテーパ状に形成されている。一方、仕切壁2の
据え付け位置に相当するトンネルT内の床面1cには、
2つの支持部材4、4が配置されている。これら2つの
支持部材4は、仕切壁2の長手方向(軸線L方向)に沿
って、仕切壁2の下端面2dの2つのテーパ部をそれぞ
れ支持するように配置されている。そして、トンネルT
内に搬入した仕切壁2を、据え付け位置に相当する位置
に配置されている支持部材4、4に載せる。As shown in FIGS. 1 (a) and 2, each lower end surface 2d of the partition wall 2 rises from the center in the longitudinal direction (the direction of the axis L) toward the side end surfaces 2a, 2b. Is formed in a tapered shape as described above. On the other hand, on the floor 1c in the tunnel T corresponding to the installation position of the partition wall 2,
Two support members 4, 4 are arranged. These two support members 4 are arranged along the longitudinal direction (the direction of the axis L) of the partition wall 2 so as to support the two tapered portions of the lower end surface 2d of the partition wall 2 respectively. And the tunnel T
The partition wall 2 carried into the inside is placed on the support members 4, 4 arranged at positions corresponding to the installation positions.
【0016】支持部材4の仕切壁2を支持する支持面
は、図1(a)に示すように、下端面2dのテーパ形状
に応じて側面視傾斜して形成されている。さらに、図1
(b)に示すように、支持部材4の仕切壁2を支持する
支持面には断面視V字状のガイド溝4aが形成されてお
り、仕切壁2の下端面2dも断面視V字状に形成されて
いる。As shown in FIG. 1 (a), the support surface of the support member 4 supporting the partition wall 2 is formed to be inclined in side view in accordance with the tapered shape of the lower end surface 2d. Further, FIG.
As shown in (b), a guide groove 4a having a V-shaped cross section is formed on the support surface of the support member 4 supporting the partition wall 2, and a lower end surface 2d of the partition wall 2 is also V-shaped when viewed in cross section. Is formed.
【0017】支持部材4はそれぞれ軸線Lに平行な貫通
穴5を有しており、この貫通穴5には雌ねじ溝5aが形
成されている。そして、これら貫通穴5は棒状の雄ねじ
部材6によって連結されており、雄ねじ部材6の雄ねじ
溝と貫通穴5の雌ねじ溝5aとはそれぞれ螺合してい
る。Each of the support members 4 has a through hole 5 parallel to the axis L, and a female screw groove 5a is formed in the through hole 5. The through holes 5 are connected by a rod-shaped male screw member 6, and the male screw groove of the male screw member 6 and the female screw groove 5 a of the through hole 5 are screwed respectively.
【0018】そして、仕切壁2を支持している支持部材
4の雌ねじ溝5aに螺合している雄ねじ部材4を回転さ
せる。すると、この雄ねじ部材6の回転に伴って、この
雄ねじ部材6に螺合する雌ねじ溝5aを有している支持
部材4、4は、図2の破線で示すように互いに接近する
ように移動する。この支持部材4、4の接近に伴い、テ
ーパ状に形成されている下端面5を有する仕切壁2は上
方に持ち上げられる。Then, the male screw member 4 screwed into the female screw groove 5a of the support member 4 supporting the partition wall 2 is rotated. Then, with the rotation of the male screw member 6, the support members 4, 4 having the female screw grooves 5a screwed to the male screw member 6 move so as to approach each other as shown by the broken line in FIG. . As the support members 4 approach, the partition wall 2 having the tapered lower end surface 5 is lifted upward.
【0019】支持部材4、4の互いの接近に伴って上方
に持ち上げられた仕切壁2は上端面2cをトンネルTの
天井面1aに当接させる。こうして、仕切壁2はトンネ
ルT(セグメント1)に対して位置決めされる。そし
て、仕切壁2の上端面2cをトンネルTの天井面1aに
当接させたらボルト(固定部材)3によってトンネルT
(セグメント1)と仕切壁2とを固定するとともに、仕
切壁2と支持部材4ともボルト8で固定する。図3
(a)に示すように、仕切壁2の上端面2cには鉄板な
どのカバー部材10が設けられているとともに、側面か
ら上端面2cに向かう貫通穴11が形成されている。ボ
ルト3はこの貫通穴11を通ってセグメント1に連結さ
れる。また、仕切壁2の下端面2d側にも貫通穴11と
同様の構成を有する貫通穴が形成されておりボルト8は
この貫通穴を通される。そして、仕切壁2どうしを連結
具14によって連結する。The partition wall 2 lifted upward as the support members 4, 4 approach each other brings the upper end surface 2c into contact with the ceiling surface 1a of the tunnel T. Thus, the partition wall 2 is positioned with respect to the tunnel T (segment 1). When the upper end surface 2c of the partition wall 2 is brought into contact with the ceiling surface 1a of the tunnel T, the tunnel T
The (segment 1) and the partition wall 2 are fixed, and the partition wall 2 and the support member 4 are also fixed with bolts 8. FIG.
As shown in (a), a cover member 10 such as an iron plate is provided on the upper end surface 2c of the partition wall 2, and a through hole 11 is formed from the side surface to the upper end surface 2c. The bolt 3 is connected to the segment 1 through the through hole 11. A through hole having the same configuration as the through hole 11 is also formed on the lower end surface 2d side of the partition wall 2, and the bolt 8 is passed through the through hole. Then, the partition walls 2 are connected to each other by the connecting tool 14.
【0020】こうして、仕切壁2をトンネルT内の据え
付け位置に据え付けたら、次の仕切壁2を上記示した手
順と同様の手順で据え付ける。そして、全ての仕切壁2
を据え付け終えたら、トンネルTの下部にインバートコ
ンクリートを打設して床部(不図示)を形成する。コン
クリートが打設されることにより、仕切壁2の下端面2
dとトンネルTの床面1cとの間に形成されている隙間
にもコンクリートが満たされるため、仕切壁2は安定し
て据え付けられる。After the partition wall 2 has been installed at the installation position in the tunnel T, the next partition wall 2 is installed in the same procedure as described above. And all the partitions 2
After the installation is completed, invert concrete is poured into the lower part of the tunnel T to form a floor (not shown). When the concrete is cast, the lower end surface 2 of the partition wall 2 is formed.
Since the gap formed between d and the floor 1c of the tunnel T is also filled with concrete, the partition wall 2 is stably installed.
【0021】以上説明したように、仕切壁2の下端面2
dをその長手方向中央部から端部(側端面2a、2b)
に向かってテーパ状に予め形成しておくとともに、この
テーパ状に形成された下端面2dを2つの支持部材4、
4によって支持し、これら支持部材4、4を下端面2d
の長手方向に移動することによって、仕切壁2を上昇・
下降することができる。そして、仕切壁2をトンネルT
に据え付ける際、仕切壁2をトンネルTに対して位置決
めするために上方に持ち上げて上端面2cとトンネルT
の天井面1aとを当接する必要があるが、下端面2d
と、据え付け位置に相当する床面1cとの間に支持部材
4を配置してこれら支持部材4を下端面2dの長手方向
に移動することにより、仕切壁2を容易に上方に持ち上
げることができる。したがって、トンネルTに対する仕
切壁2の位置決めを効率良く行うことができ、全体の据
え付け作業効率も向上することができるので、低コスト
化を実現することができる。As described above, the lower end surface 2 of the partition wall 2
d from the center in the longitudinal direction to the end (side end surfaces 2a, 2b)
And the lower end surface 2d formed in a tapered shape is formed into two support members 4,
4 to support the support members 4 and 4 at the lower end surface 2d.
The partition wall 2 is raised by moving in the longitudinal direction of
Can descend. Then, partition wall 2 is placed in tunnel T
In order to position the partition wall 2 with respect to the tunnel T, the partition wall 2 is lifted upward and
It is necessary to make contact with the ceiling surface 1a, but the lower end surface 2d
By disposing the support members 4 between the support member 4 and the floor surface 1c corresponding to the installation position and moving these support members 4 in the longitudinal direction of the lower end surface 2d, the partition wall 2 can be easily lifted upward. . Therefore, the positioning of the partition wall 2 with respect to the tunnel T can be performed efficiently, and the entire installation work efficiency can be improved, so that cost reduction can be realized.
【0022】このとき、支持部材4のそれぞれに雌ねじ
溝5aを形成するとともに、雌ねじ溝5aのそれぞれを
1本の棒状雄ねじ部材6で連結し、雄ねじ部材6を回転
させることによって、支持部材4のそれぞれを容易に簡
単な構成で移動させることができる。At this time, a female screw groove 5a is formed in each of the support members 4, and each of the female screw grooves 5a is connected by a single bar-shaped male screw member 6, and the male screw member 6 is rotated to thereby form the support member 4. Each can be easily moved with a simple configuration.
【0023】支持部材4の仕切壁2を支持する支持面に
ガイド溝4aを形成しておくことにより、仕切壁2の下
端面2dと支持部材4との摺動を安定して実現すること
ができる。By forming guide grooves 4a on the support surface of the support member 4 supporting the partition wall 2, the sliding between the lower end surface 2d of the partition wall 2 and the support member 4 can be stably realized. it can.
【0024】なお、仕切壁2の下端面2dと支持部材4
との間に、テフロン(登録商標)などの低摩擦抵抗部材
を貼り付けたり、あるいは塗布することによって、仕切
壁2の下端面2dと支持部材4との摺動をさらに安定し
て実現することができる。The lower end face 2d of the partition wall 2 and the support member 4
Between the lower end surface 2d of the partition wall 2 and the support member 4 by applying or applying a low friction resistance member such as Teflon (registered trademark). Can be.
【0025】なお、図3(b)に示すように、仕切壁2
の上端面2cとカバー部材10との間にゴムなどの弾性
部材(可撓性部材)12を介在させてもよい。弾性部材
を12を設けることによって、仕切壁2の上端面2cを
トンネルTの天井面1aに当接させる際の損傷を防止す
ることができる。Note that, as shown in FIG.
An elastic member (flexible member) 12 such as rubber may be interposed between the upper end surface 2c of the cover member 10 and the cover member 10. By providing the elastic member 12, it is possible to prevent damage when the upper end surface 2c of the partition wall 2 is brought into contact with the ceiling surface 1a of the tunnel T.
【0026】上記実施形態において、仕切壁2を上昇さ
せた際、仕切壁2の位置決めが望みどおりに行われなか
ったら、支持部材4、4を離間させる方向に雄ねじ部材
6を回転することにより、仕切壁2は下降する。そし
て、位置決め動作を再度行えばよい。In the above embodiment, when the partition wall 2 is raised and the positioning of the partition wall 2 is not performed as desired, the male screw member 6 is rotated in a direction in which the support members 4 and 4 are separated from each other. The partition wall 2 descends. Then, the positioning operation may be performed again.
【0027】上記実施形態において、仕切壁2の下端面
2dのテーパ形状は中央部から端部(側端面2a、2
b)に向かって上昇するような形状であるが、中央部か
ら端部に向かって下降するような形状であってもよい。
この場合、2つの支持部材4、4を離すことによって仕
切壁2は上昇し、一方、支持部材4、4を接近させるこ
とによって仕切壁2は下降する。In the above embodiment, the tapered shape of the lower end face 2d of the partition wall 2 is changed from the center to the end (side end faces 2a, 2d).
The shape is such that it rises toward b), but it may be a shape that descends from the center to the end.
In this case, the partition wall 2 is raised by separating the two support members 4, 4, while the partition wall 2 is lowered by bringing the support members 4, 4 closer.
【0028】[0028]
【発明の効果】本発明のトンネルの施工方法によれば、
仕切壁の下端面をその長手方向中央部から端部に向かっ
てテーパ状に予め形成しておくとともに、このテーパ状
に形成された下端面を2つの支持部材によって支持し、
これら支持部材を下端面の長手方向に移動することによ
って、仕切壁を上昇・下降することができる。そして、
仕切壁をトンネルに据え付ける際、仕切壁をトンネルに
対して位置決めするために、仕切壁を上方に持ち上げて
仕切壁の上端面とトンネルの内面とを当接する必要があ
るが、下端面と据え付け位置に相当する床面との間に支
持部材を配置してこれら支持部材を移動することによ
り、仕切壁を容易に上方に持ち上げることができる。し
たがって、トンネルに対する仕切壁の位置決めを効率良
く行うことができ、全体の据え付け作業効率も向上する
ことができるので、低コスト化を実現することができ
る。According to the tunnel construction method of the present invention,
The lower end surface of the partition wall is formed in advance in a tapered shape from the longitudinal center portion to the end portion, and the tapered lower end surface is supported by two support members,
By moving these support members in the longitudinal direction of the lower end surface, the partition wall can be moved up and down. And
When the partition wall is installed on the tunnel, it is necessary to lift the partition wall upward and contact the upper end surface of the partition wall and the inner surface of the tunnel in order to position the partition wall with respect to the tunnel. By disposing the support members between the floor surface and the support member and moving these support members, the partition wall can be easily lifted upward. Therefore, the positioning of the partition wall with respect to the tunnel can be performed efficiently, and the overall installation work efficiency can be improved, so that cost reduction can be realized.
【図1】本発明のトンネルの施工方法の一実施形態を説
明するための図である。FIG. 1 is a view for explaining one embodiment of a tunnel construction method of the present invention.
【図2】仕切壁が持ち上げられる様子を説明するための
図である。FIG. 2 is a diagram for explaining how a partition wall is lifted.
【図3】仕切壁を説明するための図である。FIG. 3 is a diagram for explaining a partition wall.
【図4】従来のトンネルの施工方法の課題を説明するた
めの図である。FIG. 4 is a view for explaining a problem of a conventional tunnel construction method.
1 セグメント 1a 天井面(内面) 1c 床面(内面) 2 仕切壁 2a 側端面 2b 側端面 2c 上端面 2d 下端面 3 ボルト(固定部材) 4 支持部材 5 貫通穴 5a 雌ねじ溝 6 雄ねじ部材 12 弾性部材 L (トンネル)軸線 T トンネル DESCRIPTION OF SYMBOLS 1 segment 1a Ceiling surface (inner surface) 1c Floor surface (inner surface) 2 Partition wall 2a Side end surface 2b Side end surface 2c Upper end surface 2d Lower end surface 3 Bolt (fixing member) 4 Support member 5 Through hole 5a Female thread groove 6 Male screw member 12 Elastic member L (tunnel) axis T tunnel
Claims (4)
有するトンネルの施工方法において、 前記仕切壁の下端面をその長手方向中央部から端部に向
かってテーパ状に予め形成しておくとともに、前記仕切
壁の下端面と、前記仕切壁のトンネル内での据え付け位
置に相当する床面との間に前記下端面の長手方向に沿っ
て2つの支持部材を配置し、該2つの支持部材のそれぞ
れを前記仕切壁の下端面の長手方向に移動させることに
よって、前記仕切壁を上方に持ち上げて該仕切壁の上端
面と前記トンネルの内面とを当接させ、該仕切壁をトン
ネル内に据え付けることを特徴とするとするトンネルの
施工方法。1. A tunnel construction method having a step of installing a partition wall in a tunnel, wherein a lower end surface of the partition wall is formed in advance in a tapered shape from a longitudinal center to an end thereof, and Two support members are arranged along the longitudinal direction of the lower end surface between a lower end surface of the partition wall and a floor surface corresponding to an installation position of the partition wall in the tunnel, and each of the two support members is disposed. Is moved in the longitudinal direction of the lower end surface of the partition wall, thereby lifting the partition wall upward to bring the upper end surface of the partition wall into contact with the inner surface of the tunnel, and installing the partition wall in the tunnel. A tunnel construction method characterized by the following.
おいて、 前記支持部材のそれぞれに雌ねじ溝を形成するととも
に、該雌ねじ溝のそれぞれを棒状雄ねじ部材で連結し、
前記雄ねじ部材を回転させることによって前記支持部材
のそれぞれを移動させることを特徴とするトンネルの施
工方法。2. The tunnel construction method according to claim 1, wherein a female screw groove is formed in each of the support members, and each of the female screw grooves is connected with a bar-shaped male screw member.
A tunnel construction method, wherein each of the support members is moved by rotating the male screw member.
方法において、 前記支持部材の前記仕切壁を支持する支持面にガイド溝
を形成することを特徴とするトンネルの施工方法。3. The tunnel construction method according to claim 1, wherein a guide groove is formed on a support surface of the support member that supports the partition wall.
ルの施工方法において、 前記支持部材の前記仕切壁を支持する支持面に低摩擦抵
抗部材を設けたことを特徴とするトンネルの施工方法。4. The tunnel construction method according to claim 1, wherein a low frictional resistance member is provided on a support surface of the support member that supports the partition wall. Method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000341726A JP2002147190A (en) | 2000-11-09 | 2000-11-09 | Tunnel constructing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000341726A JP2002147190A (en) | 2000-11-09 | 2000-11-09 | Tunnel constructing method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2002147190A true JP2002147190A (en) | 2002-05-22 |
Family
ID=18816426
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000341726A Withdrawn JP2002147190A (en) | 2000-11-09 | 2000-11-09 | Tunnel constructing method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2002147190A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112502751A (en) * | 2020-11-27 | 2021-03-16 | 成都城投建筑工程有限公司 | Two-way highway tunnel separates fender supporting construction |
-
2000
- 2000-11-09 JP JP2000341726A patent/JP2002147190A/en not_active Withdrawn
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112502751A (en) * | 2020-11-27 | 2021-03-16 | 成都城投建筑工程有限公司 | Two-way highway tunnel separates fender supporting construction |
CN112502751B (en) * | 2020-11-27 | 2022-11-08 | 成都城投建筑工程有限公司 | Two-way highway tunnel separates fender supporting construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101363224A (en) | Movable foundation pit support system and construction method | |
JP2002147190A (en) | Tunnel constructing method | |
JP2016050425A (en) | Pile removal method | |
JP3299042B2 (en) | Tunnel lining method | |
JP2011032684A (en) | Lining structure and lining method | |
JP2006283497A (en) | Vertical wall assembling device and vertical wall construction method | |
JPH11141740A (en) | Method for transferring existing piping in cut and cover tunnel making work | |
KR101192265B1 (en) | Phc long pile construction machine and method thereof | |
CN114718064A (en) | Horizontal pushing device for prefabricated underground continuous wall and wall forming method thereof | |
JP2022128939A (en) | Floor slab installation method | |
KR100297929B1 (en) | Slip form for excavation molding in vertical tunnel | |
KR20240017727A (en) | Mainframe rotation mechanism and rotation method for excavation apparatus | |
JP2011089346A (en) | Construction method of structure | |
CN111560982A (en) | Installation method of cable prefabricated well | |
JP2005090175A (en) | Concrete lining form device of shaft sinking wall surface and concrete lining method | |
JP2009091112A (en) | Heavy load lifting adjustment tool | |
JP2000027447A (en) | Method for providing horizontal recess part in periphery of concrete columnar body | |
CN217128311U (en) | A prefabricated lining cutting structure of left and right sides piecemeal for open cut tunnel | |
JPH08135396A (en) | Base rock holding method of crain guarder | |
JP6211303B2 (en) | Seismic isolation method for existing buildings and temporary structure under construction | |
CN220166886U (en) | Positioning device for bridge pile foundation reinforcement cage | |
CN213297844U (en) | Counter weight structure of full-slewing drilling machine | |
CN219826367U (en) | Assembled integral precast concrete earthquake-resistant wall | |
CN212535122U (en) | Material platform is dismantled in quick ann of type of encorbelmenting of building engineering | |
JPH03233098A (en) | Method and device for installation of precast concrete plate for tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20080205 |