JP2002121710A - Method and device for launching erection girder - Google Patents

Method and device for launching erection girder

Info

Publication number
JP2002121710A
JP2002121710A JP2000315134A JP2000315134A JP2002121710A JP 2002121710 A JP2002121710 A JP 2002121710A JP 2000315134 A JP2000315134 A JP 2000315134A JP 2000315134 A JP2000315134 A JP 2000315134A JP 2002121710 A JP2002121710 A JP 2002121710A
Authority
JP
Japan
Prior art keywords
girder
erection
hand
bridge
driving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000315134A
Other languages
Japanese (ja)
Inventor
Yoshihiko Hatsugawa
芳彦 秡川
Katsuhide Mitsune
克秀 三根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yokogawa Construction Co Ltd
Original Assignee
Yokogawa Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yokogawa Construction Co Ltd filed Critical Yokogawa Construction Co Ltd
Priority to JP2000315134A priority Critical patent/JP2002121710A/en
Publication of JP2002121710A publication Critical patent/JP2002121710A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an erection girder launching method capable of relatively reducing the weight of the erection girders or launching erection girders to be used for bridge girder construction, and capable of reducing weight of a device for moving the girders and simplifying the structure thereof, and capable of reducing the man-hours and cost. SOLUTION: In the bridge girder construction on bridge piers, when launching at least one erection girder stretched between bridge piers so as to provide the bridge girder with a progress of the construction of the bridge girder, an erection girder and a launching erection girder are stretched between the bridge piers in parallel with each other, and an erection girder driving means and a launching erection girder driving means are arranged between the erection girder and the launching erection girder. The erection girder and the launching erection girder are relatively displaced from each other in a progressing direction of the bridge girder construction by the erection girder driving means and the launching erection girder driving means so as to carry the erection girder.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、高架橋などの橋桁
を設置する際に用いる架設桁を、工事の進行に伴って前
進させるための送り出し方法および、送り出し装置に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a delivery method and a delivery device for advancing an installation girder used for installing a bridge girder such as a viaduct with the progress of construction work.

【0002】[0002]

【従来の技術】図1は、従来の送り出し方法による橋桁
の設置工事を示すものであり、図1(a)は側面図、図1
(b)は平面図である。
2. Description of the Related Art FIG. 1 shows the construction work of a bridge girder by a conventional delivery method. FIG. 1 (a) is a side view, and FIG.
(b) is a plan view.

【0003】図においては、既設の橋脚1A〜1E上に、平
行に配置した二本の架設桁2,2が設置され、架設桁
2,2前端には手延桁(手延機)3,3が取り付けられ
ている。なお、図では紙面の左から右に向かって工事が
進行するものとしている。また、図示の架設桁2,2
は、橋脚1A〜1C上では、例えばローラ4A〜4Cによって移
動可能に支持されているものとする。
In the figure, two erection girders 2, 2 arranged in parallel are installed on existing piers 1A to 1E, and a hand girder (hand rolling machine) 3, 3 is attached. In the drawing, the construction proceeds from left to right on the page. In addition, the illustrated construction girders 2 and 2
Is movably supported on the piers 1A to 1C by, for example, rollers 4A to 4C.

【0004】橋脚1E上には、架設桁2の駆動装置5が設
置されている。駆動装置5はウィンチ6とワイヤ7から
なり、ウィンチ6によって架設桁2と接続したワイヤ7
を巻き上げることにより、架設桁2を前進させる。一
方、架設桁2の後端には惜しみ装置8が接続している。
惜しみ装置8は、ウィンチ9とワイヤロープ10とを具
え、架設桁2と接続したワイヤロープ10を引っ張り、そ
れによって架設桁2を後方、すなわち架設桁2が進行す
る方向とは反対方向に牽引することで、架設桁2の行き
過ぎ(逸走)を防ぐ。なお、ここでは、架設桁2,2そ
れぞれに対応して駆動装置5および惜しみ装置8が2台
づつ設置されているものとする。
[0004] On the pier 1E, a driving device 5 for the erection girder 2 is installed. The driving device 5 includes a winch 6 and a wire 7, and the wire 7 connected to the bridge 2 by the winch 6.
, The erection girder 2 is advanced. On the other hand, a rescue device 8 is connected to the rear end of the bridge 2.
The regret device 8 includes a winch 9 and a wire rope 10 and pulls the wire rope 10 connected to the erection girder 2, thereby pulling the erection girder backward, that is, in the direction opposite to the direction in which the erection girder 2 advances. In this way, the bridge girder 2 is prevented from going too far (runaway). Here, it is assumed that two drive devices 5 and two spare devices 8 are installed in correspondence with the installation girders 2 and 2, respectively.

【0005】ここで、図示の場合における架設桁2,2
の送り出しおよび橋桁の設置は以下のような手順で行わ
れる。先ず、駆動装置のウィンチ6によってワイヤロー
プ7を巻き取ることにより、架設桁2(および手延桁
3)を前進させる。次いで架設桁2,2上を、橋桁ブロ
ック11,12を吊り下げた橋形クレーン13,14を移動させ
つつ、橋桁ブロック11,12を組み立て、橋桁15,16を順
次形成する。その後、さらに架設桁2,2を前進させ
て、橋脚間に橋桁を新たに設置する。なお、架設桁2,
2を前進させる際には、前述したように、惜しみ装置8
により架設桁2,2の逸走を防いでいる。
[0005] Here, the construction girders 2 and 2 in the case shown in the figure.
And the installation of the bridge girder are performed in the following procedure. First, the erection girder 2 (and the hand girder 3) is advanced by winding the wire rope 7 by the winch 6 of the driving device. Next, the bridge girder blocks 11, 12 are assembled while moving the bridge cranes 13, 14, which suspend the bridge girder blocks 11, 12, on the erection girder 2, 2, and the bridge girder 15, 16 is formed sequentially. Thereafter, the erection girders 2 and 2 are further advanced, and a new bridge girder is installed between the piers. In addition, erection girder 2,
2 is advanced, as described above,
This prevents the girders 2 and 2 from escaping.

【0006】しかしながら、こうした従来の方法には以
下のような問題点がある。まず、架設桁2,2の前進に
伴って、駆動装置5および惜しみ装置8をも移動(盛替
え)させなければならず、これに要する時間や工程、人
員が必要となる。また、架設桁2,2を水平に支持する
ために、図示のようにピロン柱17を架設桁2,2上に設
置し、ステイケーブル18を掛け渡した場合、これらが橋
形クレーン13,14の移動の支障になり、橋桁ブロック1
1,12を組み立てる際には一旦撤去する必要がある。さ
らに、スパン、すなわち隣接する橋脚の間隔が広い(例
えば70m〜80m、あるいはそれ以上)場合、架設桁2,
2および手延桁3,3も大型化、重量化し、これに伴っ
て駆動装置5や惜しみ装置8も大型化するため、作業に
要する時間や人員が必要となり、建設コストを上昇させ
る要因ともなる。その結果、近年問題となっている建設
現場における人手不足や工期短縮、作業の効率化の実現
も困難となる。
However, such a conventional method has the following problems. First, as the erection girders 2 and 2 move forward, the drive device 5 and the spare device 8 also need to be moved (replaced), and the time, process and personnel required for this are required. In order to support the erection girders 2 and 2 horizontally, a pillow post 17 is installed on the erection girders 2 and 2 as shown in the figure, and when a stay cable 18 is laid, they are bridge crane 13 and 14. Hindering the movement of the bridge girder block 1
When assembling 1 and 12, it is necessary to remove it once. Further, when the span, that is, the distance between adjacent piers is wide (for example, 70 m to 80 m or more),
2 and the hand girders 3 and 3 are also increased in size and weight, and accordingly the drive device 5 and the spare device 8 are also increased in size, so that the time and personnel required for the work are required, which also increases the construction cost. . As a result, it is difficult to achieve labor shortage, shorten the construction period, and improve work efficiency at construction sites, which have recently become problems.

【0007】[0007]

【発明が解決しようとする課題】本発明は上記の問題点
に鑑み、橋桁の設置の際に用いる架設桁や手延桁を比較
的軽量なものとすることができ、またこれらを移動させ
るための装置をも軽量化・簡素化可能で、さらには工数
やコストの削減等も実現できる、架設桁の送り出し方法
を提案するものである。
SUMMARY OF THE INVENTION In view of the above-mentioned problems, the present invention makes it possible to reduce the weight of an installation girder or a hand girder used for installing a bridge girder, and to move these girders. The present invention proposes a method of sending out an installation girder, which can reduce the weight and simplification of the device, and can also reduce the number of steps and costs.

【0008】[0008]

【課題を解決するための手段】すなわち本発明は、橋脚
上への橋桁の設置において、前記橋桁の設置のために橋
脚間に掛け渡して配置した少なくとも1本の架設桁の、
前記橋桁の設置の進行に伴う送り出しを行うに際し、前
記架設桁と手延桁とを互いに平行に前記橋脚間に掛け渡
して配置し、前記架設桁と前記手延桁との間に、これら
をそれぞれ前進させる架設桁駆動手段および手延桁駆動
手段を配置し、前記架設桁駆動手段および手延桁駆動手
段により、前記架設桁と前記手延桁とを、前記橋桁の設
置の進行方向に交互に相対変位させることにより前記架
設桁を送り出すことを特徴とするものである。
That is, the present invention relates to a method of installing a bridge girder on a pier, comprising: installing at least one erection girder spanned between the piers for installing the bridge girder;
When sending out along with the progress of installation of the bridge girder, the erection girder and hand-rolling girder are arranged so as to be bridged between the piers in parallel with each other, and between the erection girder and the hand-rolling girder, Arranging the erection girder driving means and the hand girder driving means for moving forward respectively, the erection girder driving means and the hand girder driving means alternately move the erection girder and the hand girder in the traveling direction of installation of the bridge girder. The erection girder is sent out by relatively displacing the erection girder.

【0009】本発明による架設桁の送り出し方法は、架
設桁と手延桁とを独立させ、これらを交互に移動させる
ことで、架設桁を前進させる。そのため、架設桁および
手延桁を小型化(小断面化)・軽量化を図ることができ
る。また両者の間にこれらを移動させる駆動手段を設け
たことにより、工事の進行による架設桁の移動に伴うこ
れら駆動手段の盛替えも必要としなくなると共に、駆動
手段自体を軽量化することも可能となる。その結果、比
較的単純な構成により架設桁の送り出しを行うことが可
能となり、工数の削減や省力化を図ることができ、建設
コストの低減化に寄与することが可能である。
In the method of sending out a construction girder according to the present invention, the construction girder and the hand girder are made independent, and the construction girder is advanced by moving them alternately. Therefore, it is possible to reduce the size (small cross section) and weight of the erection girder and the hand girder. In addition, by providing a driving means for moving these between them, it is not necessary to change the driving means due to the movement of the erection girder as the construction progresses, and it is also possible to reduce the weight of the driving means itself. Become. As a result, it is possible to send out the erection girder with a relatively simple configuration, and it is possible to reduce man-hours and labor, thereby contributing to a reduction in construction cost.

【0010】本発明による架設桁の送り出し方法の好適
な実施形態においては、1本の前記手延桁を1本の前記
架設桁の直上または直下に配置した構成としても良く、
また1本の前記手延桁を2本の前記架設桁の間に配置し
た構成としても良い。それによって上述した本発明の効
果をさらに確実なものとすることができる。
[0010] In a preferred embodiment of the method of sending out a bridge girder according to the present invention, a configuration may be employed in which one hand girder is disposed immediately above or immediately below one bridge girder.
In addition, a configuration may be adopted in which one hand girder is disposed between two bridge girder. Thereby, the effect of the present invention described above can be further ensured.

【0011】また本発明による架設桁の送り出し方法
は、前記架設桁駆動手段および手延桁駆動手段を、前記
架設桁または前記手延桁のいずれか一方に固定して配置
し、前記架設桁の前進に際しては、前記第1の駆動手段
を前記架設桁を前進させる方向に駆動させると共に、前
記第2の駆動手段を前記架設桁の逸走を防止する方向に
駆動させ、前記手延桁の前進に際しては、前記第2の駆
動手段を前記手延桁を前進させる方向に駆動させると共
に、前記第1の駆動手段を前記手延桁の逸走を防止する
方向に駆動させることを特徴とする。この様な構成とす
ることにより、各駆動手段が惜しみ装置をも兼ねること
となり、構成全体を簡略化・軽量化することが可能とな
る。
Further, in the method of sending out a construction girder according to the present invention, the construction girder driving means and the hand girder driving means are fixedly arranged on one of the construction girder and the hand girder, and At the time of forward movement, the first drive means is driven in a direction to advance the bridge girder, and the second drive means is driven in a direction to prevent the escape of the bridge girder. Is characterized in that the second driving means is driven in a direction in which the hand girder advances, and the first driving means is driven in a direction in which the hand girder is prevented from running away. By adopting such a configuration, each drive unit also serves as a spare device, and the entire configuration can be simplified and lightened.

【0012】さらに本発明による架設桁の送り出し方法
の好適な実施形態においては、前記第1および第2の駆
動手段が、それぞれ前記架設桁または前記手延桁を牽引
するためのワイヤと、このワイヤにより前記架設桁また
は手延桁を牽引するジャッキまたはウィンチとを具える
こととしても良く、また、前記第1および第2の駆動手
段が、それぞれ前記架設桁または前記手延桁を牽引する
ためのロッドと、このロッドにより前記架設桁または手
延桁を牽引するジャッキとを具えることとしても良い。
それによって、これら駆動手段の構成を簡素化し、小型
・軽量化を図ることが可能となる。
Further, in a preferred embodiment of the method of sending out a bridge girder according to the present invention, the first and second driving means each include a wire for pulling the bridge girder or the hand-rolled girder, And a jack or winch for pulling the erection girder or the hand-rolled girder, and wherein the first and second driving means are for pulling the erection girder or the hand-rolled girder, respectively. A rod and a jack for pulling the erection girder or hand girder by the rod may be provided.
This makes it possible to simplify the configuration of these driving means and to reduce the size and weight.

【0013】また本発明は、架設桁の送り出しを行う送
り出し装置に関するものでもある。
[0013] The present invention also relates to a delivery device for delivering a bridge girder.

【0014】本発明による架設桁の送り出し装置は、橋
脚上への橋桁の設置に際し、前記橋桁の設置のために橋
脚間に掛け渡して配置した少なくとも1本の架設桁を、
前記橋桁の設置の進行に伴って送り出しを行う装置であ
って、前記架設桁と平行に配置した手延桁と、前記架設
桁と前記手延桁との間に配置した、これらをそれぞれ前
進させる架設桁駆動装置および手延桁駆動装置とを具
え、前記架設桁駆動装置および手延桁駆動装置により、
前記架設桁と前記手延桁とを、前記橋桁の設置の進行方
向に交互に相対変位させることにより前記架設桁を送り
出すことを特徴とする。
According to the present invention, when a bridge girder is installed on a pier, at least one erection girder placed between the piers for installation of the bridge girder is provided.
An apparatus for feeding the bridge girder along with the progress of installation thereof, wherein a hand-rolled girder arranged in parallel with the bridge girder, and a hand-rolled girder arranged between the bridge girder and the hand-rolled girder, are respectively advanced. Equipped with a construction girder drive and a hand girder drive, by the construction girder drive and the hand girder drive,
The bridging girder is sent out by alternately displacing the bridging girder and the hand girder alternately in the direction of installation of the bridge girder.

【0015】本発明による架設桁の送り出し装置は、架
設桁と手延桁とを独立させ、両者の間にこれらを移動さ
せる駆動装置を設け、この駆動装置により架設桁と手延
桁とを交互に前進させることとしている。そのため、装
置全体の構成を簡略化できるとともに、軽量化をも図る
ことが可能となる。なお、本発明による架設桁の送り出
し装置の好適な実施形態においては、1本の前記手延桁
を1本の前記架設桁の直上または直下に配置した構成と
しても良く、また1本の前記手延桁を2本の前記架設桁
の間に配置した構成としても良い。
According to the present invention, there is provided an apparatus for feeding a bridge girder, wherein the bridge girder and the hand girder are separated from each other, and a driving device for moving the girder between the girder and the hand girder is provided. To move forward. Therefore, the configuration of the entire device can be simplified, and the weight can be reduced. In a preferred embodiment of the construction girder feeding device according to the present invention, one hand extension girder may be arranged directly above or below one construction girder, and one hand girder may be arranged. A configuration may be adopted in which an extension girder is arranged between the two bridge girder.

【0016】本発明による架設桁の送り出し装置におい
ては、前記第1および第2の駆動装置を前記架設桁また
は前記手延桁のいずれか一方に固定して配置し、前記架
設桁の前進に際しては、前記第1の駆動装置を前記架設
桁を前進させる方向に駆動させると共に、前記第2の駆
動装置を前記架設桁の逸走を防止する方向に駆動させ、
前記手延桁の前進に際しては、前記第2の駆動装置を前
記手延桁を前進させる方向に駆動させると共に、前記第
1の駆動装置を前記手延桁の逸走を防止する方向に駆動
させることを特徴とする。それによって、各駆動装置が
惜しみ装置をも兼ねることとなり、装置全体を簡略化・
軽量化することが可能となる。
In the apparatus for feeding a bridge girder according to the present invention, the first and second driving devices are fixedly arranged on one of the bridge girder and the hand-render girder. Driving the first drive device in a direction to advance the erection girder, and driving the second drive device in a direction to prevent the escape of the erection girder;
When the hand girder advances, the second driving device is driven in a direction to advance the hand girder and the first driving device is driven in a direction for preventing the hand girder from escaping. It is characterized by. As a result, each drive device also serves as a spare device, simplifying the entire device.
It is possible to reduce the weight.

【0017】本発明による架設桁の送り出し装置の好適
な実施形態においては、前記第1および第2の駆動装置
が、それぞれ前記架設桁または前記手延桁を牽引するた
めのワイヤと、このワイヤにより前記架設桁または手延
桁を牽引するジャッキまたはウィンチとを具えることと
しても良く、また、前記第1および第2の駆動手段が、
それぞれ前記架設桁または前記手延桁を牽引するための
ロッドと、このロッドにより前記架設桁または手延桁を
牽引するジャッキとを具えることとしても良い。それに
よって、これら駆動装置の構成を簡素化し、小型・軽量
化を図ることが可能となる。
In a preferred embodiment of the construction girder sending device according to the present invention, the first and second driving devices each include a wire for pulling the construction girder or the hand girder, and A jack or a winch for pulling the erection girder or hand girder may be provided, and the first and second driving means may include:
A rod for pulling the bridging girder or the hand girder, and a jack for pulling the bridging girder or the girder with the rod, respectively, may be provided. This makes it possible to simplify the configuration of these driving devices and reduce the size and weight.

【0018】[0018]

【発明の実施の形態】以下、図面を参照して本発明の好
適な実施形態について説明する。
Preferred embodiments of the present invention will be described below with reference to the accompanying drawings.

【0019】図2は、本発明に係る架設桁の送り出し方
法による橋桁の設置工事を示すものであり、図2(a)は
側面図、図2(b)は平面図である。
FIGS. 2A and 2B show the installation work of the bridge girder by the method of sending out the bridge girder according to the present invention. FIG. 2A is a side view, and FIG. 2B is a plan view.

【0020】図においては、既設の橋脚21A〜21D上に、
平行に配置した二本の架設桁22,22が設置され、架設桁
22,22の間には一本の手延桁23が配置されている。手延
桁23は、架設桁22,22上を走行可能な2台の門型の吊り
台車24,25により、ワイヤ26で吊り下げられて支持され
ている。また、図示の架設桁22,22は、橋脚21A〜21C上
では、例えば支持柱27A〜27Dによって移動可能に支持さ
れている。これら支持柱27A〜27Dには架設桁22,22およ
び手延桁23を移動可能に支持するためのローラと、架設
桁22,22および手延桁23を固定するための仮受設備がそ
れぞれ設けられている。また橋桁30上には架設桁22,22
と共に前進する支持台車28も設置されている。なお、本
図でも紙面の左から右に向かって工事が進行するものと
している。
In the figure, on existing piers 21A to 21D,
Two erection girders 22, 22 arranged in parallel are installed,
One hand girder 23 is arranged between 22 and 22. The hand girders 23 are suspended and supported by wires 26 by two gate-shaped hanging carts 24 and 25 that can travel on the bridge girders 22 and 22. In addition, the illustrated erection girders 22, 22 are movably supported on the piers 21A to 21C by, for example, support columns 27A to 27D. These support columns 27A to 27D are provided with rollers for movably supporting the erection girder 22, 22 and the hand girder 23, and temporary receiving equipment for fixing the erection girder 22, 22 and the hand girder 23, respectively. Have been. In addition, on the bridge girder 30 erection girder 22,22
A supporting truck 28 that moves forward with the vehicle is also provided. Also in this drawing, the construction proceeds from left to right on the paper.

【0021】架設桁22の前端部には、駆動装置31が設置
されている。この駆動装置31は、ここでは後述するよう
に2台の油圧ジャッキ32A,32Bおよび、これら油圧ジャ
ッキ32A,32Bによって牽引されるワイヤ33A,33Bからな
り、この駆動装置31によって架設桁22,22および手延桁
23が工事の進行方向に相対変位することにより、架設桁
22,22および手延桁23の送り出しが行われる。なお、こ
の手順については後に詳述する。
A driving device 31 is provided at the front end of the bridge girder 22. The driving device 31 includes two hydraulic jacks 32A and 32B and wires 33A and 33B pulled by the hydraulic jacks 32A and 32B, as described later. Girder
23 is relatively displaced in the construction direction,
Feeding of 22, 22 and hand girder 23 is performed. This procedure will be described later in detail.

【0022】図3および図4は架設桁22,22の外観を示
すものであり、図3(a)は側面図、図3(b)は平面図、ま
た図4は正面図をそれぞれ示す。図示のように、架設桁
22は、多数の型鋼をトラス状に組んだボックスガーダー
形状をなす。一方、図5および図6は手延桁23の外観を
示すものであり、図5(a)は側面図、図5(b)は平面図、
また図6は正面図をそれぞれ示す。図示のように、手延
桁23は本体23Aおよび先端部(手延部)23Bからなり、共
に架設桁22と同様に、多数の型鋼をトラス状に組んだボ
ックスガーダー形状をなす。なお、これら架設桁22およ
び手延桁23の形状および構造は、基本的には従来と同様
のものである。
FIGS. 3 and 4 show the appearance of the erection girders 22, 22, FIG. 3 (a) is a side view, FIG. 3 (b) is a plan view, and FIG. 4 is a front view. As shown,
22 has a box girder shape in which a number of steel shapes are assembled in a truss shape. 5 and 6 show the appearance of the hand girders 23. FIG. 5 (a) is a side view, FIG. 5 (b) is a plan view,
FIG. 6 shows a front view. As shown in the drawing, the hand spread girder 23 includes a main body 23A and a tip portion (hand spread portion) 23B. Like the bridge girder 22, both have a box girder shape in which a number of mold steels are assembled in a truss shape. Note that the shapes and structures of the erection girder 22 and the hand-girder girder 23 are basically the same as those in the related art.

【0023】図7および図8は、手延桁23を吊り下げて
支持する吊り台車24の外観を示すものであり、図7は後
方から見た図を、図8は側方から見た図である。吊り台
車24は架設桁22,22間に掛け渡した梁部材34と、架設桁
22,22上を走行する走行台車35A,35Bを具える。走行台
車35A,35Bの車輪36が架設桁22上面のレール37上を走行
することにより、吊り台車24が移動する。梁部材34には
ワイヤクランプ38A,38Bが設置され、ここからワイヤ2
6,26が吊り下げられ、その一端が手延桁23と接続す
る。それによって手延桁23は吊り台車24に支持されるこ
ととなる。なお、この吊り台車24と手延桁23との間には
2本のテンションジャッキ39A,39Bが設けられ、手延桁
23支持を補助すると共に、吊り下げる高さの調整も行っ
ている。
FIGS. 7 and 8 show the appearance of a suspension cart 24 that suspends and supports the hand girders 23. FIG. 7 is a view seen from the rear, and FIG. 8 is a view seen from the side. It is. The suspension trolley 24 includes a beam member 34 bridged between the erection girders 22, 22, and the erection girder.
It has traveling carts 35A and 35B that travel on 22,22. When the wheels 36 of the traveling carts 35A and 35B travel on the rails 37 on the upper surface of the erection girder 22, the suspension cart 24 moves. Wire clamps 38A and 38B are installed on the beam member 34, and the wire 2
6 and 26 are suspended, and one end thereof is connected to the hand girder 23. As a result, the hand girders 23 are supported by the suspension carts 24. Two tension jacks 39A and 39B are provided between the suspension trolley 24 and the hand-rolled girder 23.
23 In addition to assisting the support, the suspension height is adjusted.

【0024】図9および図10は、手延桁23を吊り下げて
支持するもう1台の吊り台車25の外観を示すものであ
り、図9は後方から見た図を、図10は側方から見た図で
ある。吊り台車25もまた架設桁22,22間に掛け渡した梁
部材40と、架設桁22,22上を走行する走行台車41A,41B
を具える。走行台車41A,41Bの車輪42が架設桁22上面の
レール43上を走行することにより、吊り台車25が移動す
る。梁部材40にはワイヤクランプ44A,44Bが設置され、
ここからワイヤ26,26が吊り下げられ、その一端が手延
桁23と接続する。それによって手延桁23は吊り台車25に
支持されることとなる。
FIGS. 9 and 10 show the appearance of another hanging cart 25 for suspending and supporting the hand girders 23. FIG. 9 is a view seen from the rear, and FIG. FIG. The suspension trolley 25 also has a beam member 40 spanned between the erection girders 22, 22 and traveling trolleys 41A, 41B running on the erection girders 22, 22.
Equipped. When the wheels 42 of the traveling carriages 41A and 41B travel on the rails 43 on the upper surface of the erection girder 22, the suspension carriage 25 moves. Wire clamps 44A and 44B are installed on the beam member 40,
Wires 26 are suspended from here, and one end thereof is connected to the hand girder 23. As a result, the hand girders 23 are supported by the suspension carts 25.

【0025】図11〜図13は、駆動装置31の構成を概略示
すものであり、図11は側面図、図12は平面図、図13は正
面図をそれぞれ示す。駆動装置31は、架設桁22,22に固
定して支持されたステージ45と、このステージ45上に配
置した2台の油圧ジャッキ32A,32B、これら油圧ジャッ
キを動作させるための油圧ポンプ46、油圧ポンプ46を駆
動するための電力を供給する発電機47および制御器48を
具える。また、ステージ45は、手延桁23上に設けたレー
ル49,49上を、下面に設けた車輪50,50が走行すること
により移動可能となっている。それによって架設桁22,
22と手延桁23が相対変位可能となっている。
FIGS. 11 to 13 schematically show the structure of the driving device 31. FIG. 11 is a side view, FIG. 12 is a plan view, and FIG. 13 is a front view. The driving device 31 includes a stage 45 fixedly supported on the erection girders 22, 22, two hydraulic jacks 32A, 32B arranged on the stage 45, a hydraulic pump 46 for operating these hydraulic jacks, and a hydraulic pump 46. It comprises a generator 47 and a controller 48 for supplying electric power for driving the pump 46. The stage 45 is movable by running wheels 50, 50 provided on the lower surface on rails 49, 49 provided on the hand girders 23. As a result, the erection girder 22,
22 and hand girder 23 can be relatively displaced.

【0026】図示のように、2台の油圧ジャッキ32A,2
3Bは互いに反対方向に設置されている。これは、後述す
るように架設桁22および手延桁23をそれぞれ前進させる
際に、図示しないワイヤを牽引する方向が異なるためで
ある。
As shown, two hydraulic jacks 32A, 2A
3B are installed in opposite directions. This is because the direction in which a wire (not shown) is pulled is different when the bridge girder 22 and the hand girder 23 are respectively advanced as described later.

【0027】図14は、本発明に係る方法を用いた橋桁の
設置と、そのための架設桁および手延桁の送り出し手順
を示すものである。以下、この手順を説明する。
FIG. 14 shows a procedure of installing a bridge girder using the method according to the present invention and sending out an erecting girder and a hand girder therefor. Hereinafter, this procedure will be described.

【0028】まず、図14(a)に示すように、橋脚61Aから
61E間に橋桁を設置する場合を考える。図では各橋脚61A
〜61Eには後述する架設桁を支持するための支持柱62A〜
62Eが設けられ、また橋脚61Aには既に橋桁63,64が設置
されている。ここで、図2に示すと同様に、支持柱62A
〜62Eにも、架設桁および手延桁を移動可能に支持する
ためのローラと、固定するための仮受設備とが設けられ
ている。
First, as shown in FIG.
Consider the case where a bridge girder is installed between 61E. In the figure, each pier 61A
~ 61E has support columns 62A for supporting the erection girder described later ~
62E is provided, and bridge girders 63 and 64 are already installed on pier 61A. Here, as shown in FIG.
-62E are also provided with rollers for movably supporting the erection girder and the hand girder, and temporary receiving equipment for fixing.

【0029】架設桁65は支持柱62A〜62C上に設置され、
手延桁66は架設桁65上の吊り台車67,68により、ワイヤ
69を介して吊り下げられている。また、架設桁65の前端
には駆動装置70が設けられている。なお、図では架設桁
65は1本のみが示されているが、ここでは図2と同様
に、架設桁65は2本平行に配置され、その間に1本の手
延桁66が吊り下げられているものとする。
The erection girder 65 is installed on support columns 62A to 62C,
The hand girder 66 is connected to the suspension bogies 67 and 68 on the
Hanged through 69. A drive device 70 is provided at the front end of the bridge girder 65. In the figure, the installation girder
Although only one bridge 65 is shown here, it is assumed here that two bridge girders 65 are arranged in parallel, and one hand girder 66 is suspended between them, as in FIG.

【0030】次に、図14(b)に示すように、架設桁65を
静止、すなわち支持柱62A〜62C上に、前述した仮受設備
を用いて固定した状態で駆動装置70を動作させて手延桁
66を前進させ、その前端部を支持柱62Dで支持させるよ
うにする。
Next, as shown in FIG. 14 (b), the driving device 70 is operated while the erection girder 65 is stationary, that is, fixed on the support columns 62A to 62C using the above-mentioned temporary receiving equipment. Girder
66 is advanced so that its front end is supported by the support pillar 62D.

【0031】さらに図14(c)に示すように、手延桁66を
さらに前進させて支持柱62C,62Dで支持させるように
し、一旦、これら支持柱に設けた仮受設備を用いて固定
する。その後、橋形クレーン71,72から橋桁ブロック7
3,74を吊り下げ、橋形クレーン71,72を架設桁65上を
走行させて橋桁ブロック73,74を橋桁の設置箇所、ここ
では橋脚61Bまで輸送し、図14(d)に示すように、橋桁7
6,77を組み立てる。その後、架設桁65の後端部近くの
橋桁64上に、架設桁65の移動時に、架設桁65を支持しつ
つ移動する支持台車75を配置する。
Further, as shown in FIG. 14 (c), the hand girders 66 are further advanced so as to be supported by the supporting columns 62C and 62D, and are temporarily fixed by using the temporary receiving facilities provided on these supporting columns. . After that, bridge bridge blocks 7
3 and 74 are suspended, the bridge cranes 71 and 72 are moved on the erection girder 65, and the bridge girder blocks 73 and 74 are transported to the installation position of the bridge girder, here the pier 61B, as shown in FIG. 14 (d). , Bridge girder 7
Assemble 6, 77. After that, on the bridge girder 64 near the rear end of the bridge girder 65, a support cart 75 that moves while supporting the bridge girder 65 when the bridge girder 65 moves is arranged.

【0032】最後に駆動装置70を動作させて、図14(e)
に示すように、今度は架設桁65を前進させ、支持柱62B
〜62Dで支持かつ固定する。この架設桁65の固定は、各
支持柱62B〜62Dに設けた仮受設備を用いる。以上の手順
を繰り返すことにより、架設桁を送り出すと共に新たに
橋桁を設置する。
Finally, the driving device 70 is operated, and FIG.
As shown in the figure, the erection girder 65 is advanced this time,
Support and secure at ~ 62D. The fixing of the erection girder 65 uses temporary receiving equipment provided on each of the support columns 62B to 62D. By repeating the above procedure, the bridge girder is sent out and a new bridge girder is installed.

【0033】図15は、架設桁および手延桁の送り出しに
おける駆動装置の動作手順を示すものである。以下、そ
の手順を説明する。なお、図では簡略化のために、構成
部材等を簡略化および一部を省略して示している。ま
た、ここで述べる手順は図14で述べた手順にほぼ対応
し、また各構成部材の符号は、図14と同じものを用いて
いる。
FIG. 15 shows an operation procedure of the driving device in sending out the bridge girder and the hand girder. Hereinafter, the procedure will be described. In the drawings, for the sake of simplicity, constituent members and the like are simplified and some parts are omitted. The procedure described here substantially corresponds to the procedure described with reference to FIG. 14, and the reference numerals of the respective components are the same as those in FIG.

【0034】図示の架設桁65の前端部に設けた駆動装置
70は、油圧ジャッキ71,72およびこれらジャッキによっ
てそれぞれ牽引されるワイヤ73,74を具え、また車輪75
によって手延桁66上を相対移動可能となっている。また
ワイヤ73はその一端が手延桁66の後端66Bと、ワイヤ74
はその一端が手延桁66の前端66Aとそれぞれ接続してい
る。
Driving device provided at the front end of the bridge girder 65 shown
70 comprises hydraulic jacks 71, 72 and wires 73, 74 respectively drawn by these jacks, and wheels 75,
This makes it possible to move relatively on the girder 66. Also, one end of the wire 73 has a rear end 66B
Has one end connected to the front end 66A of the hand girder 66, respectively.

【0035】まず、図15(a)に示すように、架設桁65は
支持柱62A〜62C上に固定(静止)した状態にあり、一方
手延桁66は支持柱62C,62Dに移動可能に支持された状態
にある。この状態から、図15(b)に示すように、油圧ジ
ャッキ71を動作させてワイヤ73を牽引する。また、この
とき、もう一つの油圧ジャッキ72も同時に動作させ、ワ
イヤ74を油圧ジャッキ72と手延桁66の前端66Aとの間で
後方、すなわち手延桁66の進行方法と逆の方向に牽引し
て緊張させるようにする。
First, as shown in FIG. 15 (a), the bridge girder 65 is fixed (stationary) on the support columns 62A to 62C, while the hand girder 66 is movable on the support columns 62C and 62D. It is in a supported state. From this state, the hydraulic jack 71 is operated to pull the wire 73 as shown in FIG. 15 (b). At this time, the other hydraulic jack 72 is also operated at the same time, and the wire 74 is pulled rearward between the hydraulic jack 72 and the front end 66A of the hand spread girder 66, that is, in the direction opposite to the direction in which the hand spread girder 66 advances. And be nervous.

【0036】すると、ワイヤ73は一端が手延桁66の後端
66Bと接続しており、かつ手延桁66は支持柱62C,62Dに
移動可能に支持されているため、図15(c)に示すよう
に、手延桁66は架設桁65に対して前進する。ここで、図
15(b)および図15(c)に示すように、ワイヤ74もまた油圧
ジャッキ72と手延機66の前端66Aとの間で後方に牽引さ
れて緊張した状態となっているため、油圧ジャッキ72と
ワイヤ74が惜しみ装置として働き、手延桁66の逸送を防
ぐこととなる。
Then, one end of the wire 73 is at the rear end of the hand-rolled girder 66.
As shown in FIG. 15 (c), since the hand girder 66 is movably supported by the support columns 62C and 62D, the hand girder 66 moves forward with respect to the erection girder 65 as shown in FIG. I do. Where the figure
As shown in FIG. 15 (b) and FIG. 15 (c), the wire 74 is also pulled rearward between the hydraulic jack 72 and the front end 66A of the hand-rolling machine 66 and is in a tension state. The wire 72 and the wire 74 function as a spare device, and prevent the hand girder 66 from being retreated.

【0037】次に、図15(d)に示すように、架設桁65を
支持柱62A〜62C上を移動可能な状態にし、一方、手延桁
66は支持柱62C,62Dに固定した状態にする。そして、今
度は油圧ジャッキ72を動作させてワイヤ74を牽引する
と、ワイヤ74は一端が手延桁66の前端66Aと接続してお
り、かつ架設桁65は支持柱62A〜62Cに移動可能に支持さ
れているため、図15(e)および図15(f)に示すように、架
設桁65は手延桁66に対して前進する。
Next, as shown in FIG. 15D, the erection girder 65 is made movable on the support columns 62A to 62C.
66 is fixed to the supporting columns 62C and 62D. Then, when the hydraulic jack 72 is operated and the wire 74 is pulled, the wire 74 has one end connected to the front end 66A of the hand spread girder 66, and the erected girder 65 is movably supported by the support columns 62A to 62C. 15 (e) and 15 (f), the bridge girder 65 advances with respect to the hand girder 66.

【0038】この場合も、図15(e)および図15(f)に示す
ように、油圧ジャッキ72によってワイヤ74を牽引する一
方で、もう一つの油圧ジャッキ71を動作させて、ワイヤ
73を油圧ジャッキ71と手延桁66の後端66Bとの間で前
方、すなわち架設桁65の進行方向に牽引して緊張させる
ようにしている。その結果、油圧ジャッキ71とワイヤ73
が惜しみ装置として働き、架設桁65の逸走を防ぐことが
できる。
In this case as well, as shown in FIGS. 15 (e) and 15 (f), while the wire 74 is pulled by the hydraulic jack 72, the other hydraulic jack 71 is operated to move the wire 74.
73 is pulled forward between the hydraulic jack 71 and the rear end 66B of the hand-rolled girder 66, that is, in the traveling direction of the bridge girder 65, so as to be tensioned. As a result, the hydraulic jack 71 and the wire 73
Works as a spare device, and can prevent the escape of the erection girder 65.

【0039】上記の手順によって架設桁65と手延桁66を
交互に相対移動させることにより、橋桁の設置に伴う架
設桁65および手延桁66の送り出しが行われる。
By alternately moving the bridge girder 65 and the hand girder 66 alternately according to the above-described procedure, the bridge girder 65 and the hand girder 66 are sent out when the bridge girder is installed.

【0040】以上説明したように、本発明による架設桁
の送り出し方法によれば、架設桁と手延桁とを分離して
配置し、両者を交互に相対変位させることにより送り出
しを行うこととなる。そのため架設桁および手延桁の軽
量化を図ることができ、また長スパンの橋梁等の建設に
も対応できる。
As described above, according to the method of sending out a construction girder according to the present invention, the construction girder and the hand girder are separated and arranged, and the delivery is performed by alternately displacing the two. . Therefore, the weight of the erection girder and the hand girder can be reduced, and the construction of a long span bridge or the like can be supported.

【0041】さらに、送り出しのための駆動装置を架設
桁と手延桁との間に設け、かつ惜しみ装置の機能をも兼
ね備えるようにしたことから、架設桁を含む設備の構成
全体を簡素化することができ、省力化に加えて建設コス
ト削減にも寄与できることとなる。
Further, since the driving device for sending out is provided between the bridge girder and the hand girder and has the function of a spare device, the entire configuration of the equipment including the bridge girder is simplified. This can contribute to not only labor saving but also construction cost reduction.

【0042】なお、本発明は上述した実施形態に限定さ
れるものではない。例えば、架設桁を1本とし、手延桁
をその真上または真下に配置することとしても良い。
The present invention is not limited to the above embodiment. For example, the number of the erection girder may be one, and the hand-rolled girder may be arranged directly above or below it.

【0043】また駆動装置としては、油圧ジャッキの他
ウィンチなども利用することが可能であり、さらにはワ
イヤに替えて鋼棒なども使用可能である。
As the driving device, a winch other than the hydraulic jack can be used, and a steel rod or the like can be used instead of the wire.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 従来の架設桁の送り出し方法による橋桁の設
置工事を示す側面図である。
FIG. 1 is a side view showing a construction work of a bridge girder by a conventional method of sending out a construction girder.

【図2】 本発明に係る架設桁の送り出し方法による橋
桁の設置工事を示す側面図である。
FIG. 2 is a side view showing an installation work of a bridge girder according to the method of sending out a bridge girder according to the present invention.

【図3】 本発明に係る架設桁の外観を示す側面図およ
び平面図である。
FIGS. 3A and 3B are a side view and a plan view showing an appearance of a bridge girder according to the present invention.

【図4】 本発明に係る架設桁の外観を示す正面図であ
る。
FIG. 4 is a front view showing an external appearance of a bridge girder according to the present invention.

【図5】 本発明に係る手延桁の外観を示す側面図およ
び平面図である。
FIG. 5 is a side view and a plan view showing the appearance of a hand-rolled girder according to the present invention.

【図6】 本発明に係る手延桁の外観を示す正面図であ
る。
FIG. 6 is a front view showing the appearance of a hand-rolled girder according to the present invention.

【図7】 後方側吊り台車の外観を示す正面図である。FIG. 7 is a front view showing the appearance of the rear suspension cart.

【図8】 後方側吊り台車の外観を示す側面図である。FIG. 8 is a side view showing the appearance of the rear suspension cart.

【図9】 前方側吊り台車の外観を示す正面図である。FIG. 9 is a front view showing the appearance of the front suspension cart.

【図10】 前方側吊り台車の外観を示す側面図であ
る。
FIG. 10 is a side view showing the appearance of the front suspension cart.

【図11】 駆動装置の構成を示す側面図である。FIG. 11 is a side view showing a configuration of a driving device.

【図12】 駆動装置の構成を示す平面図である。FIG. 12 is a plan view showing a configuration of a driving device.

【図13】 駆動装置の構成を示す正面図である。FIG. 13 is a front view illustrating a configuration of a driving device.

【図14】 本発明に係る方法を用いた橋桁の設置と、
そのための架設桁および手延桁の送り出し手順を概略示
す図である。
FIG. 14: Installation of a bridge girder using the method according to the invention;
It is a figure which shows roughly the sending-out procedure of the erection girder and the hand girder for that.

【図15】 架設桁および手延桁の送り出しにおける駆
動装置の動作手順を概略示す図である。
FIG. 15 is a view schematically showing an operation procedure of a driving device in sending out the erection girder and the hand girder.

【符号の説明】[Explanation of symbols]

1,21,61 橋脚 2,22,65 架設桁 3,23,66 手延桁 4 ローラ 5,31,70 駆動装置 6,9 ウィンチ 7,10,26,33,69,73,74 ワイヤ 8 惜しみ装置 11,12,73,74 橋桁ブロック 13,14,71,72 橋形クレーン 15,16,29,30,63,64 橋桁 17 ピロン柱 18 ステイケーブル 24,25,67,68 吊り台車 27,62 支持柱 28,75 支持台車 32,71,72 油圧ジャッキ 34,40 梁部材 35,41 走行台車 36,42,50,75 車輪 37,43,49 レール 38,44 ワイヤクランプ 39 テンションジャッキ 45 ステージ 46 油圧ポンプ 47 発電機 48 制御器 1,21,61 Bridge piers 2,22,65 Bridge girder 3,23,66 Hand girder 4 Roller 5,31,70 Drive 6,9 Winch 7,10,26,33,69,73,74 Wire 8 Equipment 11, 12, 73, 74 Bridge girder block 13, 14, 71, 72 Bridge crane 15, 16, 29, 30, 63, 64 Bridge girder 17 Pilon column 18 Stay cable 24, 25, 67, 68 Suspension bogie 27, 62 Support pillar 28,75 Support trolley 32,71,72 Hydraulic jack 34,40 Beam member 35,41 Traveling trolley 36,42,50,75 Wheel 37,43,49 Rail 38,44 Wire clamp 39 Tension jack 45 Stage 46 Hydraulic Pump 47 Generator 48 Controller

Claims (12)

【特許請求の範囲】[Claims] 【請求項1】 橋脚上への橋桁の設置において、前記橋
桁の設置のために橋脚間に掛け渡して配置した少なくと
も1本の架設桁の、前記橋桁の設置の進行に伴う送り出
しを行うに際し、 前記架設桁と手延桁とを互いに平行に前記橋脚間に掛け
渡して配置し、 前記架設桁と前記手延桁との間に、これらをそれぞれ前
進させる第1の駆動手段および第2の駆動手段を配置
し、 前記第1および第2の駆動手段により、前記架設桁と前
記手延桁とを、前記橋桁の設置の進行方向に交互に相対
変位させることにより前記架設桁を送り出すことを特徴
とする、架設桁の送り出し方法。
In the installation of a bridge girder on a pier, when sending out at least one erection girder placed between piers for installation of the bridge girder along with the progress of the installation of the bridge girder, A first drive unit and a second drive for arranging the erection girder and the hand-rolling girder so as to extend between the piers in parallel with each other, and for advancing them between the erection girder and the hand-rolling girder, Means for disposing the erection girder by alternately displacing the erection girder and the hand girder alternately in the traveling direction of the installation of the bridge girder by the first and second driving means. The method of sending out the construction girder.
【請求項2】 1本の前記手延桁を1本の前記架設桁の
直上または直下に配置したことを特徴とする、請求項1
記載の架設桁の送り出し方法。
2. The hand-held girder is disposed immediately above or immediately below one of the bridge girder.
How to send out the erection girder described.
【請求項3】 1本の前記手延桁を2本の前記架設桁の
間に配置したことを特徴とする、請求項1記載の架設桁
の送り出し方法。
3. The method according to claim 1, wherein one of the girders is disposed between two of the girders.
【請求項4】 前記第1および第2の駆動手段を前記架
設桁または前記手延桁のいずれか一方に固定して配置
し、 前記架設桁の前進に際しては、前記第1の駆動手段を前
記架設桁を前進させる方向に駆動させると共に、前記第
2の駆動手段を前記架設桁の逸走を防止する方向に駆動
させ、 前記手延桁の前進に際しては、前記第2の駆動手段を前
記手延桁を前進させる方向に駆動させると共に、前記第
1の駆動手段を前記手延桁の逸走を防止する方向に駆動
させることを特徴とする、請求項1〜3のいずれか1項
記載の架設桁の送り出し方法。
4. The first and second driving means are fixedly arranged on one of the bridge girder and the hand girder, and when the bridge girder is advanced, the first driving means is connected to the first girder. The erection girder is driven in a direction of moving forward, and the second drive means is driven in a direction for preventing the escape of the erection girder. The bridge girder according to any one of claims 1 to 3, wherein the girder is driven in a direction in which the girder advances, and the first driving means is driven in a direction for preventing the hand-rolling girder from escaping. How to send out.
【請求項5】 前記第1および第2の駆動手段が、それ
ぞれ前記架設桁または前記手延桁を牽引するためのワイ
ヤと、このワイヤにより前記架設桁または手延桁を牽引
するジャッキまたはウィンチとを具えることを特徴とす
る、請求項5記載の架設桁の送り出し方法。
5. The apparatus according to claim 1, wherein the first and second driving means each include a wire for pulling the erection girder or the hand-rolled girder, and a jack or winch for pulling the erection girder or the hand-rolled girder with the wire. The method according to claim 5, further comprising the step of:
【請求項6】 前記第1および第2の駆動手段が、それ
ぞれ前記架設桁または前記手延桁を牽引するためのロッ
ドと、このロッドにより前記架設桁または手延桁を牽引
するジャッキとを具えることを特徴とする、請求項5記
載の架設桁の送り出し方法。
6. The first and second drive means each include a rod for pulling the erection girder or the hand girder, and a jack for pulling the erection girder or the hand girder with the rod. 6. The method according to claim 5, wherein:
【請求項7】 橋脚上への橋桁の設置において、前記橋
桁の設置のために橋脚間に掛け渡して配置した少なくと
も1本の架設桁を、前記橋桁の設置の進行に伴って送り
出しを行う装置であって、 前記架設桁と平行に配置した手延桁と、 前記架設桁と前記手延桁との間に配置した、これらをそ
れぞれ前進させる第1の駆動装置および第2の駆動装置
とを具え、 前記第1および第2の駆動装置により、前記架設桁と前
記手延桁とを、前記橋桁の設置の進行方向に交互に相対
変位させることにより前記架設桁を送り出すことを特徴
とする、架設桁の送り出し装置。
7. An apparatus for, when installing a bridge girder on a pier, sending out at least one erection girder placed between bridge piers for installation of the bridge girder as the installation of the bridge girder proceeds. And a first drive device and a second drive device, respectively, which are disposed between the erection girder and the hander girder, and which respectively advance these, and which are arranged in parallel with the erection girder. The first and second drive units are configured to send out the erection girder by alternately displacing the erection girder and the hand girder alternately in the traveling direction of installation of the bridge girder, A feeder for the erection girder.
【請求項8】 前記手延桁を1本の前記架設桁の直上ま
たは直下に配置したことを特徴とする、請求項7記載の
架設桁の送り出し装置。
8. The apparatus according to claim 7, wherein the hand girder is disposed immediately above or immediately below one of the bridge girders.
【請求項9】 前記手延桁を2本の前記架設桁の間に配
置したことを特徴とする、請求項7記載の架設桁の送り
出し装置。
9. The apparatus according to claim 7, wherein the hand girder is disposed between two of the bridge girder.
【請求項10】 前記第1および第2の駆動装置を前記
架設桁または前記手延桁のいずれか一方に固定して配置
し、 前記架設桁の前進に際しては、前記第1の駆動装置を前
記架設桁を前進させる方向に駆動させると共に、前記第
2の駆動装置を前記架設桁の逸走を防止する方向に駆動
させ、 前記手延桁の前進に際しては、前記第2の駆動装置を前
記手延桁を前進させる方向に駆動させると共に、前記第
1の駆動装置を前記手延桁の逸走を防止する方向に駆動
させることを特徴とする、請求項7〜9のいずれか1項
記載の架設桁の送り出し装置。
10. The first and second driving devices are fixedly arranged on one of the erection girder and the hand girder, and when the erection girder advances, the first driving device is connected to the first girder. Driving the erection girder in the forward direction and driving the second driving device in a direction for preventing the erection girder from escaping; The bridge girder according to any one of claims 7 to 9, wherein the girder is driven in a direction in which the girder advances, and the first driving device is driven in a direction for preventing the hand-rolling girder from escaping. Feeding device.
【請求項11】 前記第1および第2の駆動装置が、そ
れぞれ前記架設桁または前記手延桁を牽引するためのワ
イヤと、このワイヤにより前記架設桁または手延桁を牽
引するジャッキまたはウィンチとを具えることを特徴と
する、請求項10記載の架設桁の送り出し装置。
11. The first and second driving devices each include a wire for pulling the erection girder or the hand girder, and a jack or a winch for pulling the erection girder or the hand girder with the wire. The delivery device for a bridge girder according to claim 10, characterized by comprising:
【請求項12】 前記第1および第2の駆動装置が、そ
れぞれ前記架設桁または前記手延桁を牽引するためのロ
ッドと、このロッドにより前記架設桁または手延桁を牽
引するジャッキとを具えることを特徴とする、請求項1
0記載の架設桁の送り出し装置
12. The first and second driving devices each include a rod for pulling the erection girder or the hand girder, and a jack for pulling the erection girder or the hand girder with the rod. 2. The method according to claim 1, wherein
Feeding device for erection girder described in 0
JP2000315134A 2000-10-16 2000-10-16 Method and device for launching erection girder Pending JP2002121710A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000315134A JP2002121710A (en) 2000-10-16 2000-10-16 Method and device for launching erection girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000315134A JP2002121710A (en) 2000-10-16 2000-10-16 Method and device for launching erection girder

Publications (1)

Publication Number Publication Date
JP2002121710A true JP2002121710A (en) 2002-04-26

Family

ID=18794282

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000315134A Pending JP2002121710A (en) 2000-10-16 2000-10-16 Method and device for launching erection girder

Country Status (1)

Country Link
JP (1) JP2002121710A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006241738A (en) * 2005-03-01 2006-09-14 Oriental Construction Co Ltd Girder erecting method according to divided girder double drawing method
CN105064220A (en) * 2015-09-14 2015-11-18 山东恒堃机械有限公司 Anti-skid device for moving formwork
CN109629456A (en) * 2019-01-16 2019-04-16 中交公局海威工程建设有限公司 A kind of precast beam traverse displacement unit and precast beam crossing system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006241738A (en) * 2005-03-01 2006-09-14 Oriental Construction Co Ltd Girder erecting method according to divided girder double drawing method
JP4490311B2 (en) * 2005-03-01 2010-06-23 オリエンタル白石株式会社 Girder laying method by double pulling method of split girder
CN105064220A (en) * 2015-09-14 2015-11-18 山东恒堃机械有限公司 Anti-skid device for moving formwork
CN105064220B (en) * 2015-09-14 2016-09-07 山东恒堃机械有限公司 Mobile formwork shoe
CN109629456A (en) * 2019-01-16 2019-04-16 中交公局海威工程建设有限公司 A kind of precast beam traverse displacement unit and precast beam crossing system
CN109629456B (en) * 2019-01-16 2024-03-22 中交一公局海威工程建设有限公司 Precast beam sideslip device and precast beam sideslip system

Similar Documents

Publication Publication Date Title
JP2004232426A (en) Floor panel laying apparatus
CN101250854B (en) Large span double-linear-box beam bunching-frame method construction bridging machine
CN109372529B (en) In-tunnel dismantling device and method for hard rock heading machine
JP4264470B2 (en) Bridge girder member erection method and erection device
CN211397597U (en) Template trolley and tunnel construction vehicle set
JP2001146716A (en) Erection method for bridge beam
JP4474444B2 (en) Delivery cart
JP4361775B2 (en) Bridge erection method and bridge erection device
JP2768283B2 (en) Bridge construction method
JP2894226B2 (en) Bridge construction method
JP4962252B2 (en) Bridge erection method and erection device
CN101949133A (en) Straddle type bridge girder erection machine
GB2468883A (en) Method and apparatus for the installation of cables or pipes in tunnels
JP2002121710A (en) Method and device for launching erection girder
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
JP4489872B2 (en) Bridge erection method and apparatus
JP2768280B2 (en) Bridge construction method
JP2009185564A (en) Sending-off method of bridge
JP2015068055A (en) Girder block installation device and girder block installation method
CN201809726U (en) Straddle-type bridge girder erection machine
JP2020122359A (en) Floor slab erection system, additional floor slab installation method, and floor slab removing method
JP2021031878A (en) Construction system and construction method of elevated structure
JP2768279B2 (en) Construction girder for precast block method
CN113982645B (en) Needle beam type steel strand full section construction operation trolley
CN220539633U (en) Prefabricated inverted arch assembling trolley