JP2002013300A - Method for collapsing chimney structure supported by three or four columns - Google Patents

Method for collapsing chimney structure supported by three or four columns

Info

Publication number
JP2002013300A
JP2002013300A JP2000194138A JP2000194138A JP2002013300A JP 2002013300 A JP2002013300 A JP 2002013300A JP 2000194138 A JP2000194138 A JP 2000194138A JP 2000194138 A JP2000194138 A JP 2000194138A JP 2002013300 A JP2002013300 A JP 2002013300A
Authority
JP
Japan
Prior art keywords
collapse
pillars
columns
structure supported
chimney
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2000194138A
Other languages
Japanese (ja)
Inventor
Yuji Iida
雄二 飯田
Toshimi Masuda
利美 増田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP2000194138A priority Critical patent/JP2002013300A/en
Publication of JP2002013300A publication Critical patent/JP2002013300A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To safely and economically collapse a chimney structure supported by three or four columns in a short construction period in a satisfactory direction. SOLUTION: In this method for collapsing the chimney structure supported by the three columns, the chimney structure supported by the three columns is provide with a balance structure in which tie rods 1 are joined to integrate a cylinder D with the three columns A, B, and C. The lower part of one column A to be in the direction of collapse is removed. A notch is formed in the cylinder D, and the axis of collapse is reinforced. The above-mentioned processes are performed in any given procedure. The remaining two columns B and C are cut, lifted up by jacks, etc., and collapsed in the direction of the column A with its lower part removed with the cylinder D to be the fulcrum of collapse as an axis.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、3本または4本
の柱で支持された煙突構造物を安全且つ経済的で短工期
に、また、方向性良く倒壊する工法に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for collapsing a chimney structure supported by three or four pillars safely, economically, in a short period of time, and with good directionality.

【0002】[0002]

【従来の技術】老朽化や工場が休止になることにより、
第1図・第2図に示すような高さが100m以上といっ
た3本柱(A)、(B)、(C)から成る煙突の撤去が
必要となる場合があり、従来この種の撤去工法として
は、建て方の逆順序解体工法が主流であった。
2. Description of the Related Art Due to aging and factory shutdown,
In some cases, it is necessary to remove a chimney consisting of three pillars (A), (B) and (C) with a height of 100 m or more as shown in Fig. 1 and Fig. 2; As a rule, the reverse order demolition method of construction was the mainstream.

【0003】また図9・図10に示す如く、高さが10
0m以上といった4本柱(E)、(F)、(G)、(H)
から成る煙突を、前記と同理由で撤去する場合には、建
て方の逆順序解体工法や、特開昭63−14962号
(特公平6−33684号)による倒壊工法が主流あっ
た。
Further, as shown in FIGS.
Four pillars (E), (F), (G), (H) such as 0 m or more
In order to remove the chimney composed of the above, for the same reason as described above, the reverse order of the construction method and the collapse method according to JP-A-63-14962 (Japanese Patent Publication No. 6-33684) were the mainstream.

【0004】[0004]

【発明が解決しようとする課題】しかし、上述した建て
方の逆順序解体工法は、高所作業が多く極めて危険性が
高いうえ、解体工事費が高く、また、工期が長いといっ
た難点があった。
[0005] However, the above-mentioned reverse order disassembly method of erecting method has many drawbacks in that it involves a lot of work at high places, is extremely dangerous, and has high dismantlement construction costs and a long construction period. .

【0005】本発明は、上記従来工法の欠点を解決し、
倒壊の方向性が優れていると共に、安全性・工事費およ
び工期においても有利な、3本柱で支持された煙突構造
物の倒壊工法を提供するものである。
[0005] The present invention solves the above-mentioned drawbacks of the conventional method,
An object of the present invention is to provide a method of collapsing a chimney structure supported by three pillars, which is excellent in direction of collapse and also advantageous in safety, construction cost and construction period.

【0006】また、4本柱で支持された煙突構造物の特
開昭63−14962号(特公平6−33684号)に
よる倒壊工法は、図10に示す如く、1本の柱を撤去
し、撤去した柱の方向(Y1、Y2、Y3またはY4)
へ倒壊させる工法によるもので、倒壊方向としては、4
方向に限定される。このため、各倒壊方向に対して、十
分な空地が確保できない場合は、採用が困難であった。
A collapse method of a chimney structure supported by four pillars according to Japanese Patent Application Laid-Open No. 63-14962 (Japanese Patent Publication No. 6-33684) removes one pillar as shown in FIG. Direction of the removed column (Y1, Y2, Y3 or Y4)
The collapse direction is 4 and the collapse direction is 4
Limited to direction. For this reason, if sufficient vacant land cannot be secured in each collapse direction, it has been difficult to adopt the method.

【0007】本発明は、2本の柱に直交する方向(X
1、X2、X3またはX4)へ倒壊させることを可能と
するもので、この方向に対して十分な空地がある場合に
有利な、4本柱で支持された煙突構造物の倒壊工法を提
供するものである。
According to the present invention, a direction (X
1, X2, X3 or X4) to provide a method of collapsing a chimney structure supported by four pillars, which is advantageous when there is sufficient open space in this direction. Things.

【0008】[0008]

【課題を解決するための手段】(1) 3本柱で支持さ
れた煙突構造物において、筒身と3本の柱を一体化させ
る繋ぎ材を接合して天秤構造とすること、倒壊方向とす
る1本の柱の下部を撤去すること、筒身を切り欠くと共
に倒壊軸補強を行うことを任意の手順で行い、残された
2本の支柱を切断しジャッキなどを使用して持ち上げ、
上記倒壊の支点となる筒身を軸に、下部を撤去した柱の
方向へ倒壊させること、よりなる、3本柱で支持された
煙突構造物の倒壊工法。 (2) 4本柱で支持された煙突構造物において、筒身
と4本の柱を一体化させる繋ぎ材を接合して天秤構造と
すること、平面で見て四角形の倒壊方向側で該方向に直
交する一辺の両端の2本の柱の下部を撤去すること、筒
身を切り欠くと共に倒壊軸補強を行うことを任意の手順
で行い、残された2本の支柱を切断しジャッキなどを使
用して持ち上げ、上記倒壊の支点となる筒身を軸に、下
部を撤去した2本の柱を結ぶ一辺に直交する方向へ倒壊
させること、よりなる、4本柱で支持された煙突構造物
の倒壊工法。
Means for Solving the Problems (1) In a chimney structure supported by three pillars, a tubular body and a connecting material for integrating the three pillars are joined to form a balance structure, To remove the lower part of one pillar, cut out the tubular body and reinforce the collapsing axis in any procedure, cut the remaining two pillars and lift them using jacks, etc.
A method of collapsing a chimney structure supported by three pillars, comprising collapsing in the direction of a pillar whose lower part has been removed, with the cylinder body serving as the fulcrum of the collapse as an axis. (2) In a chimney structure supported by four pillars, a connecting member that integrates the cylindrical body and the four pillars is joined to form a balance structure. Remove the lower parts of the two pillars at both ends of one side perpendicular to the direction, cut out the tubular body and reinforce the collapsible shaft by any procedure, cut the remaining two pillars and use jacks etc. A chimney structure supported by four pillars, wherein the chimney structure supported by four pillars is lifted and collapsed in a direction orthogonal to one side connecting two pillars whose lower parts have been removed, with the cylinder body serving as a fulcrum of the collapse being used as an axis Collapse method.

【0009】なお、上記において「天秤構造」というの
は、各支柱の重量を全て筒身に受け持たせ、筒身を軸に
各支柱が吊り合うように設けられた構造をいう。
In the above description, the "balance structure" means a structure in which all the weights of the columns are received by the cylinder, and the columns are suspended from the cylinder.

【0010】[0010]

【発明の実施の形態】この発明の第1の特徴である3本
柱で支持された煙突構造物の倒壊の特徴は次ぎの通りで
ある。
BEST MODE FOR CARRYING OUT THE INVENTION The first feature of the present invention, which is the collapse feature of a chimney structure supported by three pillars, is as follows.

【0011】図2に示す如く、筒身(D)を支持する3
本の柱(A),(B)、(C)は、平面的に正三角形をし
ている。一般に規模が小さい煙突の倒壊は、例えば、図
2に示す如く、2本の柱(A),(B)を支点として、
Y方向へ倒壊させることが可能である。しかし、冒頭に
も述べた如く、煙突の高さが、100mもあり、また、
柱支点間が30m以上にも及ぶ大規模なものにあって
は、重心が筒身位置にあり、これを2本の柱(A),
(B)の支点を越えて自由倒壊せしめるまでには、柱
(C)をかなりの高さまで押し上げるか、または、手前
からワイヤーなどで、引っ張ることが必要になるが、い
ずれも実際には採用し難いものである。
As shown in FIG. 2, a support 3 for supporting the tubular body (D) is provided.
The columns (A), (B), and (C) have an equilateral triangle in plan view. In general, the collapse of a small-scale chimney is, for example, as shown in FIG. 2, with two pillars (A) and (B) as fulcrums.
It is possible to collapse in the Y direction. However, as mentioned at the beginning, the height of the chimney is as high as 100m,
In the case of a large-scale one where the distance between the column fulcrums is more than 30 m, the center of gravity is located at the cylindrical body position, and this is divided into two columns (A),
Until the fulcrum of (B) can be freely collapsed, it is necessary to push up the column (C) to a considerable height or to pull it with a wire or the like from the near side, but in practice, both are used. It is difficult.

【0012】この発明では、平面で見て、筒身(D)を
支点として、例えばX方向に倒壊せんとするもので、ま
ず、図1・図2に示す如く、3本の柱(A),(B)、
(C)と筒身(D)を、図3に示す如く、筒身から各柱
へ斜め下がりに取り付ける斜材1により、一体化させた
天秤構造とする。そして、倒壊に支障となる倒壊方向に
ある柱(A)を柱脚部から倒壊時に支障とならない高さ
まで、撤去13する(図5参照)ものである。これは、
煙突の構造として、稼働中に受ける排気からの熱によ
り、筒身(D)が熱伸縮を起こすため、ほとんどの煙突
構造物が、筒身(D)と柱(A),(B)、(C)とを、
構造上分離させており、第1図に示す如く、風や地震荷
重を受け持つ支持リング設置位置(、、、、
、)の部分でも、図4に示す如く、柱(A),
(B)、(C)の部材から接続された支持リングと、
筒身(D)との間に隙間が設けられている。このため、
上述した斜材1を用いて構成する天秤構造を設けずに柱
(A)の撤去作業を行う場合、柱(A),(B)、(C)
全体が倒壊方向へ傾き、重心位置が筒身(D)から倒壊
方向に偏心し、倒壊設計が困難になる上、倒壊作業手順
中に倒壊する危険性が非常に高くなる。この懸念事項を
解消するため、天秤構造とすることで、柱(A)を撤去
した後も、筒身(D)を軸に、柱(A)の一部を撤去し
たことによる重量減を考慮しつつ、各柱(A),(B)、
(C)が互いに吊り合い、傾くことを防止出来ると共
に、全体の重心位置を筒身(D)に位置させた状態を保
つことを可能としたものである。そして、残された2本
の柱(B)、(C)を小さな力、かつ少しの高さで押し
上げることで、倒壊できるものである。
In the present invention, when viewed in a plane, the tube body (D) is used as a fulcrum to collapse in the X direction, for example. First, as shown in FIGS. 1 and 2, three pillars (A) are used. , (B),
As shown in FIG. 3, (C) and the tubular body (D) are integrated into a balance structure by a diagonal member 1 attached diagonally downward from the tubular body to each column. Then, the column (A) in the collapse direction that obstructs collapse is removed 13 from the column base to a height that does not obstruct collapse (see FIG. 5). this is,
As the structure of the chimney, since the cylinder body (D) undergoes thermal expansion and contraction due to the heat from the exhaust received during operation, most of the chimney structures are composed of the cylinder body (D) and the columns (A), (B), ( C) and
As shown in Fig. 1, the support ring installation positions (,,,
,), As shown in FIG. 4, the pillars (A),
(B) a support ring connected from the members of (C);
A gap is provided between the cylindrical body (D). For this reason,
When removing the column (A) without providing the balance structure constituted by using the above-described diagonal member 1, the columns (A), (B), and (C)
The entire body is tilted in the collapse direction, the center of gravity is eccentric from the cylinder body (D) in the collapse direction, and the collapse design becomes difficult, and the danger of collapse during the collapse work procedure is greatly increased. In order to solve this concern, a balance structure was adopted to take into account the weight reduction due to the removal of part of the pillar (A) around the tubular body (D) even after the pillar (A) was removed. While doing, each pillar (A), (B),
(C) can be prevented from hanging and tilting with each other, and it is possible to maintain the state where the position of the center of gravity of the entire body is positioned on the cylindrical body (D). Then, the remaining two columns (B) and (C) can be collapsed by pushing them up with a small force and a small height.

【0013】また、この発明では筒身を倒壊軸としてい
るため、煙突構造物全体から見ると、1支点となり、非
常に不安定な倒壊となるため、筒身を切り欠くと共に倒
壊支点として安定性や倒壊の方向性の信頼度を高めるこ
とが好ましく、これにより、後述する実施例で詳細に説
明する如く、支点となる筒身(D)に対して、特殊な補
強材を接合し、切り欠くことにより、懸念事項を解消す
ることができる。
Further, in the present invention, since the cylindrical body is used as the collapse axis, it becomes one fulcrum when viewed from the whole of the chimney structure, and the collapse becomes very unstable. It is preferable to increase the reliability of the direction of collapse or collapse, so that a special reinforcing material is joined to the tubular body (D) serving as a fulcrum and cut out as described in detail in an embodiment described later. By doing so, concerns can be resolved.

【0014】またこの発明の第2の特徴である4本柱で
支持された煙突構造物の倒壊の特徴は次ぎの通りであ
る。
The collapse of the chimney structure supported by four pillars, which is the second feature of the present invention, is as follows.

【0015】図10に示す如く、筒身(I)を支持する
4本の柱(E)、(F)、(G)、(H)は、平面的に正
四角形の各頂点位置に配置されている。特開昭63−1
4962号(特公平6−33684号)による倒壊工法
によれば、1本の柱の下部を撤去し、撤去した柱の方向
(Y1、Y2、Y3またはY4)へ倒壊させるものであ
るが、倒壊方向としては、4方向に限定されるため、各
倒壊方向に対して、十分な空地が確保できない場合は、
採用が困難である。
As shown in FIG. 10, four pillars (E), (F), (G), and (H) supporting the tubular body (I) are arranged at respective vertex positions of a regular square in plan view. ing. JP-A-63-1
According to the collapse method according to No. 4962 (Japanese Patent Publication No. 6-33684), the lower part of one pillar is removed and collapsed in the direction of the removed pillar (Y1, Y2, Y3 or Y4). Since the direction is limited to four directions, if there is not enough open space for each collapse direction,
Difficult to hire.

【0016】この発明では、前記(2)項の工法を採用
することにより、隣接する頂点位置の2本の柱を結ぶ線
に直交する方向(X1、X2、X3またはX4)へ倒壊
させることを可能とするもので、この方向に対して十分
な空地がある場合に有利な、4本柱で支持された煙突構
造物の倒壊工法を提供できる。つまり従来工法を含め
て、倒壊方向を倍増した8方向の中から選択できる。
In the present invention, by adopting the method of the above-mentioned item (2), the collapse in the direction (X1, X2, X3 or X4) orthogonal to the line connecting the two columns at the adjacent vertices is realized. It is possible to provide a collapse method of a chimney structure supported by four pillars, which is advantageous when there is sufficient open space in this direction. In other words, it is possible to select from eight directions in which the collapse direction is doubled, including the conventional method.

【0017】これを具体的に説明すると、図10に示す
如く、平面で見て、筒身(I)を支点として、例えばX
1方向に倒壊せんとするもので、4本の柱(E)、
(F)、(G)、(H)と筒身(I)を、図3に示すと同
様に、筒身から各柱へ斜め下がりに取り付ける斜材1に
より、一体化させた天秤構造とし、倒壊に支障となる倒
壊方向側にある柱(E)、(F)を柱脚部から倒壊時に
支障とならない高さまで撤去して、以下、前記(1)項
の3本柱の場合と同様に実施するものである。
More specifically, as shown in FIG. 10, when viewed in a plane, the cylinder body (I) is used as a fulcrum, for example, X
Four pillars (E), which will collapse in one direction
(F), (G), (H) and the tubular body (I) have a balance structure integrated by a diagonal member 1 attached diagonally downward from the tubular body to each column, as shown in FIG. Pillars (E) and (F) on the collapsing direction that hinder the collapse are removed from the column base to a height that does not hinder the collapsing, and the same as in the case of the three pillars in the above item (1). It is to be implemented.

【0018】[0018]

【実施例】実施例1 3本柱で支持された煙突構造物の倒壊の実施例を以下の
(1a〜1i)により説明する。 (1a) 倒壊方向の決定 煙突が建設されている周囲に広大な空地がある場合に
は、倒壊方向は特に問わないが、本実施例では、図2の
X方向に倒壊に十分な空地があり、近隣住民から離れた
方向であることから、倒壊方向は(X)とした。 (1b) 天秤構造とする斜材1の設置 図3に示す如く、筒身(D)と各柱(A),(B)、
(C)とを繋ぐ斜材1を筒身(D)から斜め下がりに設
置し、各柱(A),(B)、(C)の重量に十分耐える部
材とする。また斜材1が接合される筒身(D)および柱
(A),(B)、(C)に局部座屈が生じる場合は、補強
を行う。 (1c) 支持リング(、)の接合 上述でも説明したように、筒身(D)と柱(A),
(B)、(C)は、通常の状態では結合されていないた
め、柱(B)、(C)を押し上げた力を、筒身(D)へ
伝達させるために、図1,図4に示す如く、支持リング
(本実施例では、の部分)のクリアランス部に鋼板
2などを差し込み溶接により接続する。
EXAMPLE 1 An example of collapse of a chimney structure supported by three pillars will be described with reference to the following (1a to 1i). (1a) Determining the collapse direction If there is a large open space around the area where the chimney is constructed, the collapse direction is not particularly limited, but in this embodiment, there is enough open space for the collapse in the X direction of FIG. The direction of collapse was (X) because it was away from the neighboring residents. (1b) Installation of the oblique material 1 having a balance structure As shown in FIG. 3, the cylindrical body (D) and the columns (A), (B),
The diagonal member 1 connecting to (C) is installed obliquely downward from the tubular body (D) to be a member that can sufficiently withstand the weight of each of the columns (A), (B), and (C). When local buckling occurs in the cylindrical body (D) and the columns (A), (B), and (C) to which the diagonal members 1 are joined, reinforcement is performed. (1c) Joining of support rings (,) As described above, the tubular body (D) and the column (A),
(B) and (C) are not connected in a normal state, so that the force pushing up the columns (B) and (C) is transmitted to the cylindrical body (D). As shown in the figure, a steel plate 2 or the like is inserted into the clearance of the support ring (in this embodiment) and connected by welding.

【0019】この、支持リング(、)を筒身(D)
に接合することにより、柱(B)、(C)の押し上げ時
に、筒身(D)を中心に柱(A),(B)、(C)が回転
することを防止できる利点も得られる。
The support ring (,) is connected to a cylindrical body (D).
The advantage of being able to prevent the columns (A), (B) and (C) from rotating around the tubular body (D) when the columns (B) and (C) are pushed up is obtained.

【0020】尚、筒身(D)への力を伝達する手段とし
て、前記(1b)項で述べた斜材1を利用することも考
えられるが、圧縮部材となるため、斜材1十分な圧縮強
度が求められるため過大な部材が必要となるので、上記
方式が好ましい。 (1d) 柱(B)、(C)への押し上げ装置の設置 図6,図7に示す如く、倒壊方向と反対側にある柱
(B)、(C)の下部に押し上げ力受け部材3を、溶接
固定し、この部材3と基礎コンクリート4との間に複数
個のジャッキ5を設置する。
As a means for transmitting the force to the cylindrical body (D), it is conceivable to use the diagonal member 1 described in the above (1b). However, since it becomes a compression member, the diagonal member 1 is sufficient. The above method is preferable because an excessively large member is required because the compressive strength is required. (1d) Installation of the lifting device on the columns (B) and (C) As shown in FIGS. 6 and 7, the lifting force receiving member 3 is placed below the columns (B) and (C) on the opposite side to the collapse direction. Then, a plurality of jacks 5 are installed between the member 3 and the foundation concrete 4 by welding.

【0021】ジャッキ5の設置個所に適当な基礎コンク
リート4が無い場合は、はじめに製作する。 (1e) 筒身(D)の補強 図7,図8に示す如く、例えば直径6400mmの筒身
(D)に対し、倒壊方向(X)と直交する方向の両側部
分に、筒身補強材6を筒身(D)に溶接で接合する。こ
の補強材6は筒身(D)のベースプレート7上に置いた
だけのもので、煙突構造物の重量に対しては、全断面で
十分耐え、且つ倒壊時には倒壊方向側となるフランジ8
の部分で倒壊支点となる強度を確保すればよい。
If there is no suitable foundation concrete 4 at the place where the jack 5 is installed, it is manufactured first. (1e) Reinforcement of tubular body (D) As shown in FIGS. 7 and 8, for a tubular body (D) having a diameter of, for example, 6400 mm, a tubular body reinforcing material 6 is provided on both sides in a direction orthogonal to the collapse direction (X). To the cylindrical body (D) by welding. The reinforcing member 6 is only placed on the base plate 7 of the tubular body (D), and sufficiently withstands the weight of the chimney structure in its entire cross section, and has a flange 8 which is on the collapse direction side when collapsed.
It is sufficient to secure the strength that becomes the fulcrum of the collapse at the part.

【0022】また、倒壊時における方向の安定性を確保
するため、振れ止め部材9を補強材6に溶接で接合す
る。振れ止め部材9は、ベースプレート7の上面高さ上
まで築造した基礎コンクリート10上に置く。 (1f) 筒身(D)の切断 図7に示す如く、筒身(D)の根元部には、倒壊軸とな
る筒身補強部材6のフランジ8部分から倒壊方向側を、
倒壊時に支障とならない角度で切断11をする。また、
筒身補強部材6から倒壊方向の反対側となる部分は、切
り欠き12を行う。 (1g) 柱(A)の下部の撤去 倒壊方向側にある柱(A)は、倒壊時に支障となり方向
性を損なうため、図5に示す如く、柱脚部から所定の高
さまで撤去13する。撤去13作業は倒壊当日に行うこ
とが好ましい。 (1h) 柱(B)、(C)の切断 図6に示す如く、柱(B)、(C)の切断14は、柱脚
と押し上げ力受け部材3の間で行う。切断14は倒壊直
前に行うことが好ましい。 (1i) 柱(B)、(C)のジャッキアップ 以上の工程を経て、倒壊作業に入るものであり、図5に
示した位置でジャッキ5の作用により押し上げ力を受け
部材3を介して柱(B)、(C)に与えて押し上げ、図
1に示す支持リング(、)から筒身(D)に押し倒
し力を伝え、図7,8に示す筒身(D)の補強材6のフ
ランジ8を支点として、全体が所定の方向(X)へ方向
性良く倒壊させることができる。
Further, in order to secure the directional stability at the time of collapse, the steady rest member 9 is joined to the reinforcing member 6 by welding. The steady rest member 9 is placed on the foundation concrete 10 which has been built up to the upper surface height of the base plate 7. (1f) Cutting of the cylindrical body (D) As shown in FIG. 7, at the base of the cylindrical body (D), the collapse direction side from the flange 8 portion of the cylindrical body reinforcing member 6 serving as the collapse axis is
The cutting 11 is performed at an angle that does not hinder the collapse. Also,
A notch 12 is formed in a portion opposite to the collapse direction from the tubular body reinforcing member 6. (1g) Removal of the lower part of the column (A) The column (A) on the collapse direction side is hindered when collapsing and impairs the directivity. Therefore, as shown in FIG. It is preferable to perform the removal 13 work on the day of collapse. (1h) Cutting of pillars (B) and (C) As shown in FIG. 6, cutting 14 of pillars (B) and (C) is performed between the pillar and the push-up force receiving member 3. Cutting 14 is preferably performed immediately before collapse. (1i) Jack-up of pillars (B) and (C) The collapsing operation is started through the above steps, and the column receives the pushing force by the action of the jack 5 at the position shown in FIG. (B) and (C) to push up, to transmit a pushing force from the support ring (,) shown in FIG. 1 to the tubular body (D), and to provide a flange of the reinforcing member 6 of the tubular body (D) shown in FIGS. With the fulcrum 8 as a fulcrum, the whole can be collapsed in a predetermined direction (X) with good directivity.

【0023】実施例2 次に、4本柱で支持された煙突構造物の倒壊の実施例に
ついて以下の(2a〜2i)により説明する。 (2a) 倒壊方向の決定 図10に示す如く、倒壊方向Y1、Y2、Y3、Y4
は、倒壊に十分な空地が無く、X1に対してのみ十分な
空地があったと仮定し、倒壊方向はX1とする。 (2b) 天秤構造とする斜材1の設置 図3に示す如く(ここでは図中の符号について、Dの標
記をIに、Aの標記をE,Gに、Bの標記をF,Hと読み
替えるものとする:以下同じ)、斜材1を筒身(I)と
各柱(E),(F)、(G)、(H)に繋ぐ斜材1を斜め
下がりに設置し、各柱(E),(F)、(G)、(H)の
重量に十分耐える部材とする。また斜材1が接合される
筒身(I)および柱(E),(F)、(G)、(H)に、
局部座屈が生じる場合は、補強を行う。 (2c) 支持リング(、)の接合 支持リングは、前記3本柱で支持された煙突構造物の倒
壊実施例と同様に鋼板2の接続等の施工がされる。 (2d) 柱(G)、(H)への押し上げ装置の設置 倒壊方向と反対側にある柱(G)、(H)の下部に,図
6に示す如く(図6のB、Cの標記はG,Hと読み替え
る)、押し上げ力受け部材3を溶接固定し、この部材3
と基礎コンクリート4との間に複数個のジャッキ5を設
置する。
Embodiment 2 Next, an embodiment of collapse of a chimney structure supported by four pillars will be described with reference to the following (2a to 2i). (2a) Determination of collapse direction As shown in FIG. 10, collapse directions Y1, Y2, Y3, Y4
Assumes that there is not enough open space for collapse and there is enough open space only for X1, and the collapse direction is X1. (2b) Installation of the oblique material 1 having a balance structure As shown in FIG. 3 (here, the symbols in the diagram are D, I, A, E, G, B, F, H. The same applies to the following.) The diagonal member 1 is connected diagonally to the tubular body (I) and the columns (E), (F), (G), and (H). (E), (F), (G), and (H) are members that can sufficiently bear the weight. In addition, the tubular body (I) and the columns (E), (F), (G), and (H) to which the diagonal members 1 are joined,
If local buckling occurs, reinforce. (2c) Joining of Support Rings (,) The support rings are connected and connected to the steel plates 2 in the same manner as in the collapsed example of the chimney structure supported by the three pillars. (2d) Installation of the lifting device on the pillars (G) and (H) As shown in FIG. 6 (B and C in FIG. 6), beneath the pillars (G) and (H) on the opposite side to the collapse direction. Are replaced with G and H), and the push-up force receiving member 3 is fixed by welding.
A plurality of jacks 5 are installed between the concrete and the foundation concrete 4.

【0024】ジャッキ5の設置個所に適当な基礎コンク
リート4が無い場合は、はじめに製作することは前記
(1d)と同じである。 (2e) 筒身(I)の補強 図7,図8に示す如く(この図のDの標記はIと読み替
える)、筒身(I)に対し倒壊方向X1と直交する方向
の両側部分に筒身補強材6を筒身(I)に溶接で接合す
る。この補強材6は筒身(I)のベースプレート7上に
置いただけのもので、煙突構造物の重量に対しては、全
断面で十分耐え、且つ倒壊時には倒壊方向側となるフラ
ンジ8の部分で倒壊支点となる強度を確保するようにす
る。
If there is no appropriate foundation concrete 4 at the place where the jack 5 is installed, the first manufacturing is the same as the above (1d). (2e) Reinforcement of the tubular body (I) As shown in FIGS. 7 and 8 (the notation of D in this figure is read as I), the tubular body (I) is provided on both sides in the direction orthogonal to the collapse direction X1 with respect to the tubular body (I). The body reinforcement 6 is welded to the tubular body (I). The reinforcing member 6 is only placed on the base plate 7 of the tubular body (I). The reinforcing member 6 sufficiently withstands the weight of the chimney structure in the entire cross section, and the portion of the flange 8 which is on the collapse direction side when collapsed. Ensure the strength to serve as a collapse fulcrum.

【0025】また、倒壊時に方向の安定性を確保するた
め、振れ止め部材9を補強材6に溶接で接合する。振れ
止め部材9は、ベースプレート7の上面高さ上まで築造
した基礎コンクリート10上に置く。 (2f) 筒身(I)の切断 図7に示す如く(Dの標記をIと読み替えた)筒身
(I)には、倒壊軸となる筒身補強部材6のフランジ8
部分から倒壊方向側を、倒壊時に支障とならない角度で
切断11する。また、筒身補強部材6から倒壊方向の反
対側となる部分は、切り欠き12を行う。 (2g) 柱(E)、(F)の下部の撤去 倒壊方向側にある柱(E)、(F)は、倒壊時に支障と
なり方向性を損なう虞れがあるため、図5に示す如く
(ここでは、Aの標記をE,Fに、Bの標記をG,Hと読
み替える)、柱脚部から所定の高さまで撤去13する。
撤去13作業は倒壊当日に行う。 (2h) 柱(G)、(H)の切断 図6に示す如く(この図中のB、Cの標記はG,Hと読
み替える)、柱(G)、(H)の切断14は、柱脚と押
し上げ力受け部材3の間で行う。切断14は倒壊直前に
行うことが望ましい。 (2i) 柱(G)、(H)のジャッキアップ 以上の工程を経て、倒壊作業に入るものであり、図5に
示したジャッキ5の作用により押し上げ力受け部材3を
介して柱(G)、(H)を押し上げ、図1に示す支持リ
ング(、)から筒身(I)への押し倒し力を伝える
ことで、図7に示す筒身(I)の補強材6のフランジ8
を支点として全体が所定の方向X1へ方向性良く倒壊す
ることになる。
Further, in order to secure the directional stability at the time of collapse, the steady rest member 9 is joined to the reinforcing member 6 by welding. The steady rest member 9 is placed on the foundation concrete 10 which has been built up to the upper surface height of the base plate 7. (2f) Cutting of the cylindrical body (I) As shown in FIG. 7, the cylindrical body (I) (in which D is read as I) is provided with a flange 8 of a cylindrical body reinforcing member 6 serving as a collapse axis.
The section 11 is cut 11 from the portion in the direction of collapse at an angle that does not hinder the collapse. Further, a notch 12 is formed in a portion opposite to the collapse direction from the tubular body reinforcing member 6. (2g) Removal of the lower part of pillars (E) and (F) Pillars (E) and (F) on the collapse direction side may hinder the collapse and impair the directivity. Here, the notation of A is replaced with E and F, and the notation of B is replaced with G and H), and then removed 13 from the pedestal to a predetermined height.
The removal 13 work is performed on the day of collapse. (2h) Cutting of pillars (G) and (H) As shown in FIG. 6 (the notations of B and C in this figure are replaced with G and H), the cutting 14 of pillars (G) and (H) is This is performed between the leg and the lifting force receiving member 3. The cutting 14 is desirably performed immediately before collapse. (2i) Jack-up of pillars (G) and (H) The collapse work is performed through the above steps, and the pillar (G) is pushed through the push-up force receiving member 3 by the action of the jack 5 shown in FIG. , (H) is pushed up and the pushing force from the support ring (,) shown in FIG. 1 to the tubular body (I) is transmitted, whereby the flange 8 of the reinforcing member 6 of the tubular body (I) shown in FIG.
With the fulcrum as a fulcrum, the entire body collapses in a predetermined direction X1 with good directivity.

【0026】[0026]

【発明の効果】以上の如く本発明により、3本柱や4本
柱で支持された煙突構造物を安全、且つ経済的で短工期
に、しかも方向性良く倒壊出来き、且つ従来の4本柱で
支持された煙突構造物の限定された倒壊方向に対し、新
たな倒壊方向の選択を可能としたものである。
As described above, according to the present invention, a chimney structure supported by three pillars or four pillars can be safely, economically and quickly collapsed in a short construction period, and can be collapsed with good directionality. A new collapse direction can be selected for the limited collapse direction of the chimney structure supported by the pillar.

【図面の簡単な説明】[Brief description of the drawings]

【図1】3本柱で支持された煙突の立面図FIG. 1 is an elevation view of a chimney supported by three pillars.

【図2】3本柱で支持された煙突の倒壊方向を示す平面
FIG. 2 is a plan view showing a collapse direction of a chimney supported by three pillars.

【図3】天秤構造とした立面図FIG. 3 is an elevation view showing a balance structure.

【図4】の支持リング設置位置の断面図FIG. 4 is a sectional view of a support ring installation position of FIG.

【図5】本発明工法の実施状況の説明図FIG. 5 is an explanatory view of an implementation state of the method of the present invention.

【図6】柱(B)、(C)の補強および切断を示す立面
FIG. 6 is an elevation view showing reinforcement and cutting of columns (B) and (C).

【図7】筒身(D)の補強および切り欠きを示す立面図
であり、(イ)は倒壊軸方向、(ロ)は倒壊軸に直交す
る方向の図
FIGS. 7A and 7B are elevation views showing reinforcement and cutouts of a tubular body (D), wherein FIG. 7A is a direction of a collapse axis, and FIG.

【図8】筒身(D)の補強および切り欠きを示す平面図FIG. 8 is a plan view showing reinforcement and notches of the tubular body (D).

【図9】4本柱で支持された煙突の立面図FIG. 9 is an elevation view of a chimney supported by four pillars.

【図10】4本柱で支持された煙突の倒壊方向を示す平
面図
FIG. 10 is a plan view showing the collapse direction of a chimney supported by four pillars.

【符号の説明】[Explanation of symbols]

(A)、(B)、(C)、(E)、(F)、(G)、
(H)…柱 (D)、(I)…筒身 、、、、、…支持リング設置位置および支
持リング 1…斜材 2…鋼板 3…押し上げ力受け部材 4、10…基礎コンクリート 5…ジャッキ 6…筒
身補強材 7…ベースプレート 8…フランジ 9…振れ止め部
材 11、14…切断 12…切り欠き 13…撤去。
(A), (B), (C), (E), (F), (G),
(H) Pillar (D), (I) Cylindrical body, ..., support ring installation position and support ring 1 ... diagonal member 2 ... steel plate 3 ... push-up force receiving member 4, 10 ... foundation concrete 5 ... jack 6 ... tubular body reinforcement 7 ... base plate 8 ... flange 9 ... steady rest member 11, 14 ... cutting 12 ... notch 13 ... removal.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 3本柱で支持された煙突構造物におい
て、筒身と3本の柱を一体化させる繋ぎ材を接合して天
秤構造とすること、倒壊方向とする1本の柱の下部を撤
去すること、筒身を切り欠くと共に倒壊軸補強を行うこ
とを任意の手順で行い、残された2本の支柱を切断して
持ち上げ、上記倒壊の支点となる筒身を軸に、下部を撤
去した柱の方向へ倒壊させること、よりなる、3本柱で
支持された煙突構造物の倒壊工法。
In a chimney structure supported by three pillars, a connecting member for integrating a cylindrical body and three pillars is joined to form a balance structure, and a lower part of one pillar in a collapse direction. Is removed, the cylindrical body is cut off and the collapsible shaft is reinforced. In any procedure, the remaining two pillars are cut and lifted, and the lower part is pivoted on the cylindrical body serving as the fulcrum of the collapse. Collapse of the chimney structure supported by three pillars, comprising collapsed in the direction of the removed pillar.
【請求項2】 4本柱で支持された煙突構造物におい
て、筒身と4本の柱を一体化させる繋ぎ材を接合して天
秤構造とすること、平面で見て四角形の倒壊方向側で該
方向に直交する一辺の両端の2本の柱の下部を撤去する
こと、筒身を切り欠くと共に倒壊軸補強を行うことを任
意の手順で行い、残された2本の支柱を切断して持ち上
げ、上記倒壊の支点となる筒身を軸に、下部を撤去した
2本の柱を結ぶ一辺に直交する方向へ倒壊させること、
よりなる、4本柱で支持された煙突構造物の倒壊工法。
2. A chimney structure supported by four pillars, wherein a connecting member for integrating the cylindrical body and the four pillars is joined to form a balance structure, and a quadrangular collapsed side in a plan view. Remove the lower part of the two pillars at both ends of one side perpendicular to the direction, cut the tubular body and reinforce the collapsible shaft in any procedure, cut the remaining two pillars Lifting and collapsing in the direction perpendicular to one side connecting the two pillars with the lower part removed, with the cylinder body serving as the fulcrum of the collapse as an axis,
A collapse method for a chimney structure supported by four pillars.
JP2000194138A 2000-06-28 2000-06-28 Method for collapsing chimney structure supported by three or four columns Withdrawn JP2002013300A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000194138A JP2002013300A (en) 2000-06-28 2000-06-28 Method for collapsing chimney structure supported by three or four columns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000194138A JP2002013300A (en) 2000-06-28 2000-06-28 Method for collapsing chimney structure supported by three or four columns

Publications (1)

Publication Number Publication Date
JP2002013300A true JP2002013300A (en) 2002-01-18

Family

ID=18693012

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000194138A Withdrawn JP2002013300A (en) 2000-06-28 2000-06-28 Method for collapsing chimney structure supported by three or four columns

Country Status (1)

Country Link
JP (1) JP2002013300A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007327301A (en) * 2006-06-09 2007-12-20 Besutera Kk Tumbling method for steel tower supported stack structure
CN107476595A (en) * 2017-09-06 2017-12-15 苏州中固建筑科技股份有限公司 Versatility frame structure multilayer integrally takes out column construction method and device
WO2018189852A1 (en) * 2017-04-13 2018-10-18 ベステラ株式会社 Method for toppling tower building in which base is used
CN114923384A (en) * 2022-05-26 2022-08-19 江苏长江爆破工程有限公司 Chimney directional blasting demolition method
EP4230798A1 (en) 2022-02-21 2023-08-23 Mitsubishi Heavy Industries, Ltd. Method of disassembling offshore structure and floating body apparatus

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007327301A (en) * 2006-06-09 2007-12-20 Besutera Kk Tumbling method for steel tower supported stack structure
WO2018189852A1 (en) * 2017-04-13 2018-10-18 ベステラ株式会社 Method for toppling tower building in which base is used
JPWO2018189852A1 (en) * 2017-04-13 2020-05-14 ベステラ株式会社 Method of defeating a tower structure using the foundation
US11053705B2 (en) 2017-04-13 2021-07-06 Besterra Co., Ltd. Method for toppling tower building in which base is used
CN107476595A (en) * 2017-09-06 2017-12-15 苏州中固建筑科技股份有限公司 Versatility frame structure multilayer integrally takes out column construction method and device
CN107476595B (en) * 2017-09-06 2023-01-31 苏州中固建筑科技股份有限公司 Universal frame structure multilayer integral column-drawing construction method and device
EP4230798A1 (en) 2022-02-21 2023-08-23 Mitsubishi Heavy Industries, Ltd. Method of disassembling offshore structure and floating body apparatus
CN114923384A (en) * 2022-05-26 2022-08-19 江苏长江爆破工程有限公司 Chimney directional blasting demolition method
CN114923384B (en) * 2022-05-26 2023-03-17 江苏长江爆破工程有限公司 Chimney directional blasting demolition method

Similar Documents

Publication Publication Date Title
JP2005517849A (en) Wind turbine
JP2007205139A (en) Construction method of arch bridge
US10378173B2 (en) Method of building a foundation comprising a steel monopile and a concrete part and associated foundation for construction work
JP2009220901A (en) Supporting structure and installation method of tower crane
JP2009035884A (en) Lift-up method for steel tower
JP2007046292A (en) Tower constructing block
JP2002013300A (en) Method for collapsing chimney structure supported by three or four columns
JP2010242390A (en) Joining method and structure of column-beam joint part having steel brace
JP2010261270A (en) Composite structure and method for constructing composite structure building
CN216740047U (en) Overhead tool type steel platform with high altitude and large span
JP4623570B2 (en) Construction method of jack base and formwork support
JP2012122200A (en) Temporary roof support structure
JP2927321B2 (en) Dismantling method of large hanging boiler
JP6353678B2 (en) Beam-shaped member construction method
JP5319445B2 (en) Building construction method
JP2006083610A (en) Inverted construction method
JP4504747B2 (en) Building construction method using tower crane
JP6529241B2 (en) Building foundation structure and construction method of building foundation structure
JPH0932120A (en) Method of construction of structure
JP7462475B2 (en) How to build a building
JPS6314962A (en) Construction method for destructing structure supported by four pillars
JP3357882B2 (en) Composite structure of precast panel and steel truss
JP3412505B2 (en) Slip form method
JP7186915B1 (en) Hollow vertical bodies used to construct dome-shaped member networks
JP2005330661A (en) High-rise building construction of existing tower equipped with communication apparatus such as antenna

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20070904