JP2001348873A - Land slide protection wall support structure and construction method - Google Patents
Land slide protection wall support structure and construction methodInfo
- Publication number
- JP2001348873A JP2001348873A JP2000171871A JP2000171871A JP2001348873A JP 2001348873 A JP2001348873 A JP 2001348873A JP 2000171871 A JP2000171871 A JP 2000171871A JP 2000171871 A JP2000171871 A JP 2000171871A JP 2001348873 A JP2001348873 A JP 2001348873A
- Authority
- JP
- Japan
- Prior art keywords
- retaining wall
- anchor
- ground
- support structure
- tension
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は山留め壁の支持構造
に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a support structure for a retaining wall.
【0002】[0002]
【従来の技術】山留め壁12は、根切り底16より深く
まで構築され、主働崩壊線15より上側の地盤から土圧
を受けており、この土圧に対抗するため、例えば、図2
に示したようにアンカー14,15あるいは切梁が設け
られている。しかしながら、掘削する平面が不整形であ
る場合には、切梁を効果的に配置することが困難なた
め、多くの場合、アンカーにより支持されている。2. Description of the Related Art A mountain retaining wall 12 is constructed deeper than a root bottom 16 and receives earth pressure from the ground above the active collapse line 15. For example, FIG.
Are provided with anchors 14, 15 or cutting beams. However, when the plane to be excavated is irregular, it is difficult to effectively arrange the girder, so that it is often supported by the anchor.
【0003】上記アンカー14,15は、定着層18に
アンカー体14c,15cを埋設し、鋼材の撚り線等か
らなる引張材14b,15bをアンカー体14c,15
cから山留め壁12まで延ばし、この山留め壁12にア
ンカー頭部14a,15aを定着している。The anchors 14 and 15 have anchoring members 14c and 15c buried in a fixing layer 18 and tension members 14b and 15b made of steel stranded wires or the like are attached to the anchoring members 14c and 15c.
c to the retaining wall 12, and anchor heads 14 a and 15 a are fixed to the retaining wall 12.
【0004】[0004]
【発明が解決しようとする課題】しかしながら、上記従
来の支持構造において、アンカー体14c,15cを埋
設する定着層18が深い位置に存在する場合、非常に長
い引張材14b,15bを要するため、施工が煩雑にな
ると共に、引張材14b,15bの材料コストも上昇す
るという欠点がある。また非常に長い引張材14b,1
5bでは、アンカー体14c,15cが敷地境界線15
から外側に出てしまうことがあり、この場合、隣接する
地主の許可を得なければ施工することができないといっ
た問題が生じる。However, in the above-mentioned conventional support structure, if the anchoring layer 18 for burying the anchors 14c, 15c is located at a deep position, very long tensile members 14b, 15b are required. However, there is a disadvantage that the material cost of the tensile members 14b and 15b also increases. In addition, very long tensile members 14b, 1
5b, the anchor bodies 14c and 15c are
From the outside, and in this case, there is a problem that the construction cannot be performed without the permission of the adjacent landowner.
【0005】本発明は、上記従来技術の問題点を解決せ
んとしたものであり、その課題は、たとえ、定着層が深
い位置に存在する場合であっても、引張材の長さを短く
抑えることができる山留め壁の支持構造を提供すること
にある。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems of the prior art, and has a problem that the length of the tensile member is reduced even if the fixing layer is located at a deep position. It is an object of the present invention to provide a support structure of a retaining wall which can be used.
【0006】[0006]
【課題を解決するための手段】本発明では、山留め壁外
周の地盤内に形成した地盤改良体と、該地盤改良体内に
配置したアンカー体と、該アンカー体から前記山留め壁
まで延設して緊張力が導入された引張材と、該引張材に
導入された緊張力を保持するため引張材端部を前記山留
め壁に定着するアンカー頭部を備えることを特徴とする
山留め壁の支持構造が提供される。According to the present invention, there is provided a ground improvement body formed in the ground around the retaining wall, an anchor disposed in the ground improvement, and extending from the anchor to the retaining wall. A tensioning member to which a tension is introduced, and an anchor head for fixing an end portion of the tensioning member to the mountain retaining wall to hold the tension introduced to the tensioning member, the support structure for the mountain retaining wall is provided. Provided.
【0007】本発明の山留め壁の支持構造において、前
記地盤改良体はアンカー体を埋設することにより、引張
材やアンカー頭部を介して山留め壁に充分な反力を提供
できるようなものであれば、その構造や工法は特に限定
されず、例えば、アースオーガの掘削軸部材により地盤
を掘削し、所定深度において掘削軸部材の先端からセメ
ントミルクを出しながら現地土と混合攪拌する機械攪拌
方式の工法により構築しても良く、あるいはボーリング
ロッドにより地盤を削孔し、所定の深度において高圧の
空気または水によって改良範囲の原地盤を粉砕し、切削
部分に改良材を充填あるいは切削土と混合する高圧噴射
方式の工法により構築したものであっても良い。In the support structure for a retaining wall according to the present invention, the ground improvement body may be one which can provide a sufficient reaction force to the retaining wall via a tensile member or an anchor head by embedding an anchor body. For example, the structure and construction method are not particularly limited.For example, a mechanical stirring method of excavating the ground with a drill shaft member of an earth auger and mixing and stirring with the soil at a predetermined depth while discharging cement milk from the tip of the drill shaft member. The ground may be constructed by a construction method, or the ground may be drilled with a boring rod, the ground ground in the area to be improved crushed with high-pressure air or water at a predetermined depth, and the cut portion may be filled with the improved material or mixed with the cut soil It may be constructed by a high-pressure injection method.
【0008】また本発明では、山留め壁外周の地盤内に
地盤改良体を形成する工程と、該山留め壁の根切り側か
ら前記地盤改良体に向けて削孔して孔内に引張材を延設
すると共に前記地盤改良体内にアンカー体を形成する工
程と、前記引張材に緊張力を導入する工程と、前記引張
材の緊張力を保持するため前記引張材端部にアンカー頭
部を設けて前記山留め壁に定着する工程とを含む山留め
壁の支持工法が提供される。Further, in the present invention, a step of forming a ground improvement body in the ground around the retaining wall, drilling a hole from the root cutting side of the retaining wall toward the ground improvement body, and extending a tensile material into the hole. Forming an anchor body in the ground improvement body, introducing tension into the tension member, and providing an anchor head at an end of the tension member to maintain the tension of the tension member. Fixing to the retaining wall, and a method for supporting the retaining wall.
【0009】[0009]
【実施例】以下、添付図面に基づいて実施例を説明する
が、本発明はこれに限定されるものではない。図1は本
発明にかかる山留め壁の支持構造を示した断面図であ
る。図1において、山留め壁の支持構造10は、山留め
壁12の外側、かつ敷地境界線15の内側の地盤17に
構築した地盤改良体11と、アンカー13とから構成さ
れ、さらに、このアンカー13は、地盤改良体11に埋
設したアンカー体13cと、このアンカー体13cから
角度(θ≦45°)で山留め壁12まで延ばして緊張力
を導入した鋼材の撚り線等からなる引張材13bと、こ
の引張材13bに導入した緊張力を保持するため引張材
13bの端部を山留め壁12に固定するアンカー頭部1
3aとから構成される。DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments will be described below with reference to the accompanying drawings, but the present invention is not limited to these embodiments. FIG. 1 is a cross-sectional view showing a support structure of a retaining wall according to the present invention. In FIG. 1, a retaining structure 10 for a retaining wall is composed of a ground improvement body 11 constructed on a ground 17 outside a retaining wall 12 and inside a site boundary line 15, and an anchor 13. An anchor body 13c buried in the ground improvement body 11, a tension member 13b made of a stranded wire or the like of a steel material which is extended from the anchor body 13c at an angle (θ ≦ 45 °) to the retaining wall 12 and tension is introduced. An anchor head 1 for fixing the end of the tension member 13b to the retaining wall 12 to maintain the tension introduced into the tension member 13b
3a.
【0010】ここで、前記地盤改良体11は、アンカー
13における引張材13bの長さを短くして施工の容易
化及び材料コストの低減を図るため、山留め壁12に比
較的近く且つ浅い位置に設けることが好ましく、少なく
ともアンカー体13cを埋設する箇所のみに配置すれば
良く、その強度はアンカー体13cが充分な付着力を得
ることができるものであれば良く、例えば、一軸圧縮強
度が約20N/cm2以上になるように形成する。Here, the ground improvement body 11 is located at a position relatively close and shallow to the retaining wall 12 in order to shorten the length of the tension member 13b in the anchor 13 to facilitate construction and reduce material costs. The anchor body 13c is preferably provided only at a place where the anchor body 13c is buried, and its strength may be any as long as the anchor body 13c can obtain a sufficient adhesive force. For example, the uniaxial compressive strength is about 20N. / Cm 2 or more.
【0011】なお、山留め壁の支持構造10では、上記
アンカー13に加えて、定着層18にアンカー体14c
を埋設するアンカー14を併用しても良く、何れの箇所
に、何れのアンカーを使用するかは、敷地境界線15の
内側の定着層18にアンカー体を埋設できるか否かによ
って判断すれば良い。In the support structure 10 of the retaining wall, in addition to the anchor 13, an anchor 14 c is attached to the fixing layer 18.
May be used together, and which anchor to use in which location may be determined by whether or not the anchor body can be embedded in the anchoring layer 18 inside the site boundary 15. .
【0012】上記構成の山留め壁12の支持構造におい
て、地盤17から山留め壁12に作用する土圧は、アン
カー頭部13aを介して引張材13bに引張力として伝
達し、さらに引張材13bからアンカー体13cにまで
伝わる。このとき、アンカー体13cは地盤改良体11
に確実に付着して支持されるとともに、地盤改良体11
自体も比較的大きな圧縮強度に形成されているので、ア
ンカー13はアンカー体13cにおいて充分な反力を得
ることができて、山留め壁12は確実に支持される。In the support structure of the retaining wall 12 having the above-described structure, the earth pressure acting on the retaining wall 12 from the ground 17 is transmitted as a tensile force to the tension member 13b via the anchor head 13a, and further the anchoring force is transmitted from the tension member 13b to the anchor. It reaches the body 13c. At this time, the anchor body 13c is
To the ground improvement body 11
Since the anchor 13 itself is formed with a relatively large compressive strength, the anchor 13 can obtain a sufficient reaction force in the anchor body 13c, and the retaining wall 12 is securely supported.
【0013】次に、山留め壁の支持工法について説明す
る。山留め壁の支持工法では、最初に、施工敷地内にお
いて掘削平面の周りに地中壁を構築してこれを山留め壁
12と為し、この山留め壁構築工程の前後または同時に
山留め壁12の外周地盤17の所定深さに地盤改良体1
1を形成する。この地盤改良体11は、例えば、地盤1
7の所定深さにおいて現地土とセメントミルクを攪拌混
合することにより地盤を改良する深層混合処理工法によ
り構築することができる。Next, a method for supporting the retaining wall will be described. In the method of supporting a mountain retaining wall, first, an underground wall is constructed around an excavation plane in a construction site, and this is used as a mountain retaining wall 12, and before or after or simultaneously with this mountain retaining wall construction step, an outer peripheral ground of the mountain retaining wall 12 is constructed. Ground improvement body 1 at a predetermined depth of 17
Form one. This ground improvement body 11 is, for example, ground 1
It can be constructed by a deep mixing method in which the ground is improved by stirring and mixing the local soil and cement milk at a predetermined depth of 7.
【0014】次に、地盤改良体11の構築後、山留め壁
12で囲まれた掘削平面を掘削しながらアンカー13,
14を設ける。すなわち、山留め壁12に貫通孔(図示
せず)を形成し、この貫通孔から地盤改良体11に向け
て外周地盤17を削孔し、孔が地盤改良体11に到達し
たら、アンカー体13cを形成するために孔内にセメン
ト等からなるグラウト材を充填する。そして、グラウト
材に引張材13bを挿入して山留め壁12の根切り側ま
で延ばし、グラウト材が充分に固化したら引張材13b
に緊張力を導入して引張材13bの端部をアンカー頭部
13aで定着する。以上の工程により所定箇所の全てに
アンカー13を設け、必要に応じて適宜アンカー14を
設ければ、山留め壁の支持構造を構築することができ
る。Next, after constructing the ground improvement body 11, while excavating the excavation plane surrounded by the retaining wall 12, the anchor 13,
14 are provided. That is, a through hole (not shown) is formed in the retaining wall 12, and the outer peripheral ground 17 is drilled from the through hole toward the ground improvement body 11, and when the hole reaches the ground improvement body 11, the anchor body 13c is removed. A grout material made of cement or the like is filled into the holes to form the holes. Then, the tension member 13b is inserted into the grout material and extended to the root cutting side of the retaining wall 12, and when the grout material is sufficiently solidified, the tension member 13b
And an end of the tension member 13b is fixed by the anchor head 13a. By providing the anchors 13 at all of the predetermined locations by the above steps and providing the anchors 14 as needed, a support structure for the retaining wall can be constructed.
【0015】[0015]
【発明の効果】本発明では、山留め壁外周の地盤内に構
築された地盤改良体にアンカー体を埋設する構成を採用
しているため、このアンカー体は確実に地盤改良体内で
保持されて強い反力が得られ、たとえ、定着層が深い位
置に存在する場合であっても、山留め壁に比較的近く且
つ浅い位置に地盤改良体を設ければ、アンカーの引張材
の長さは比較的短く抑えることができて、山留め壁の支
持構造は容易に構築することができると共に引張材の材
料コストも抑制される。According to the present invention, the anchor body is buried in the ground improvement body constructed in the ground around the retaining wall, so that the anchor body is securely held in the ground improvement body. A reaction force is obtained, and even if the anchoring layer is present at a deep position, if the ground improvement body is provided relatively close to the retaining wall and at a shallow position, the tensile material of the anchor can be relatively long. Since it can be kept short, the support structure of the retaining wall can be easily constructed, and the material cost of the tensile member is also suppressed.
【図1】本発明にかかる山留め壁の支持構造を示した断
面図である。FIG. 1 is a cross-sectional view showing a support structure for a retaining wall according to the present invention.
【図2】従来の山留め壁の支持構造を示した断面図であ
る。FIG. 2 is a cross-sectional view illustrating a conventional retaining structure for a mountain retaining wall.
10 山留め壁の支持構造 11 地盤改良体 12 山留め壁 13 アンカー 13a アンカー頭部 13b 引張材 13c アンカー体 15 敷地境界線 17 外周の地盤 DESCRIPTION OF SYMBOLS 10 Support structure of retaining wall 11 Ground improvement body 12 Retaining wall 13 Anchor 13a Anchor head 13b Tensile material 13c Anchor body 15 Site boundary line 17 Peripheral ground
Claims (2)
良体と、該地盤改良体内に配置したアンカー体と、該ア
ンカー体から前記山留め壁まで延設して緊張力が導入さ
れた引張材と、該引張材に導入された緊張力を保持する
ため引張材端部を前記山留め壁に定着するアンカー頭部
を備えることを特徴とする山留め壁の支持構造。1. A ground improvement body formed in the ground around a retaining wall, an anchor disposed in the ground improvement, and a tension member extending from the anchor to the retaining wall and receiving tension. And an anchor head for fixing an end portion of the tensile member to the retaining wall in order to maintain the tension introduced into the tension member, and a support structure for the retaining wall.
成する工程と、該山留め壁の根切り側から前記地盤改良
体に向けて削孔して孔内に引張材を延設すると共に前記
地盤改良体内にアンカー体を形成する工程と、前記引張
材に緊張力を導入する工程と、前記引張材の緊張力を保
持するため前記引張材端部にアンカー頭部を設けて前記
山留め壁に定着する工程とを含む山留め壁の支持工法。2. A step of forming a ground improvement body in the ground around an outer periphery of a retaining wall, drilling a hole from the root cutting side of the retaining wall toward the ground improvement body, and extending a tensile material into the hole. A step of forming an anchor body in the ground improvement body, a step of applying tension to the tension member, and providing an anchor head at an end of the tension member to maintain the tension of the tension member; A method of supporting a mountain retaining wall, including a step of fixing to a mountain.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000171871A JP2001348873A (en) | 2000-06-08 | 2000-06-08 | Land slide protection wall support structure and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000171871A JP2001348873A (en) | 2000-06-08 | 2000-06-08 | Land slide protection wall support structure and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2001348873A true JP2001348873A (en) | 2001-12-21 |
Family
ID=18674362
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000171871A Pending JP2001348873A (en) | 2000-06-08 | 2000-06-08 | Land slide protection wall support structure and construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2001348873A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100726984B1 (en) * | 2006-01-17 | 2007-06-14 | (주)리튼브릿지 | Temporary system for land-side protection wall |
JP2015001089A (en) * | 2013-06-14 | 2015-01-05 | 大成建設株式会社 | Anchor reinforcement structure |
CN105926633A (en) * | 2016-03-25 | 2016-09-07 | 曹信江 | Method for protecting surrounding soil or building in foundation pit construction |
CN105986580A (en) * | 2015-04-29 | 2016-10-05 | 孔志坚 | Subway station basement support construction method |
JP2017031727A (en) * | 2015-08-04 | 2017-02-09 | 株式会社大林組 | Deformation suppressing structure for earth retaining wall and deformation suppressing method for earth retaining wall |
CN112627189A (en) * | 2020-12-11 | 2021-04-09 | 王杰 | Be used for excavation supporting batter pile structure |
-
2000
- 2000-06-08 JP JP2000171871A patent/JP2001348873A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100726984B1 (en) * | 2006-01-17 | 2007-06-14 | (주)리튼브릿지 | Temporary system for land-side protection wall |
JP2015001089A (en) * | 2013-06-14 | 2015-01-05 | 大成建設株式会社 | Anchor reinforcement structure |
CN105986580A (en) * | 2015-04-29 | 2016-10-05 | 孔志坚 | Subway station basement support construction method |
JP2017031727A (en) * | 2015-08-04 | 2017-02-09 | 株式会社大林組 | Deformation suppressing structure for earth retaining wall and deformation suppressing method for earth retaining wall |
CN105926633A (en) * | 2016-03-25 | 2016-09-07 | 曹信江 | Method for protecting surrounding soil or building in foundation pit construction |
CN112627189A (en) * | 2020-12-11 | 2021-04-09 | 王杰 | Be used for excavation supporting batter pile structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2007239420A (en) | Structure of foundation for preventing floating of structure, its execution method and structure of pile used for its foundation or execution method | |
US6939084B2 (en) | Soil nailing system | |
JP4946695B2 (en) | Construction method of double pipe type pile head structure | |
JP2001348873A (en) | Land slide protection wall support structure and construction method | |
JP2003119775A (en) | Construction of foundation pile | |
JPH11280067A (en) | Method for embedding existing concrete pile and structure of foundation pile and existing concrete pile | |
JP2003055965A (en) | Soil cement columnar body with thin steel pipe present as core material and its construction method | |
JP2011236705A (en) | Foundation structure of structure and method of constructing the same | |
JP2003105757A (en) | Tapered pile with anchor and pile foundation using it | |
JP2000234493A (en) | Method for constructing face part earth retaining wall of shield starting shaft | |
JP2001226968A (en) | Earth retaining anchor method for soft sandy earth ground | |
JPH0931996A (en) | Method for driving landslide-preventing pile, anchor base and landslide preventing pile | |
JP5499335B2 (en) | Steel pipe pile and support structure and construction method using the steel pipe pile | |
JP3633326B2 (en) | Ground reinforcement method | |
JP4853132B2 (en) | Construction method of foundation pile | |
JP2001271347A (en) | Drop method for ready-made pile | |
JP2006257743A (en) | Soil cement column wall, soil cement wall pile, soil cement structure, and foundation structure | |
JPH04115024A (en) | Sheathing method | |
JP3813781B2 (en) | Anchor device installation method | |
JP2002054135A (en) | Composite structure | |
JPH0325120A (en) | Rock anchor method in widened borehole wall type | |
JPH0724493Y2 (en) | PC steel edge fixing device | |
JPH10159088A (en) | Method of under-reamed anchor construction | |
JP2002371550A (en) | Construction method of soil cement composite precast pile | |
JP2002201638A (en) | Soil-cement composite pile and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070416 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090223 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090303 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20090707 |