JP2001271303A - Joint-section structure of road - Google Patents
Joint-section structure of roadInfo
- Publication number
- JP2001271303A JP2001271303A JP2000087180A JP2000087180A JP2001271303A JP 2001271303 A JP2001271303 A JP 2001271303A JP 2000087180 A JP2000087180 A JP 2000087180A JP 2000087180 A JP2000087180 A JP 2000087180A JP 2001271303 A JP2001271303 A JP 2001271303A
- Authority
- JP
- Japan
- Prior art keywords
- road
- roadbed
- concrete
- steel plate
- subgrade
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、道路を延長・拡幅
する場合などに生じる隣り合う道路間の目地部構造に関
するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a joint structure between adjacent roads which is generated when a road is extended or widened.
【0002】[0002]
【従来の技術】たとえば、傾斜地に既設された既存道路
1を使用可能な状態のまま、道路の拡幅工事を行う場合
には、例えば、図1に示すように、既存道路1の谷側に
隣接して、つまり既存道路1と独立させて拡幅道路構造
物2を構築することで拡幅を実現する。上記拡幅道路構
造物2は、地盤に固定される杭3及び桁4からなる支持
体と、その支持体の上部に載置されて路盤を構成する床
版5とからなる。2. Description of the Related Art For example, in a case where a road is widened while an existing road 1 existing on a sloping land can be used, for example, as shown in FIG. In other words, the widening is realized by constructing the widening road structure 2 independently of the existing road 1. The widened road structure 2 includes a support composed of a stake 3 and a girder 4 fixed to the ground, and a floor slab 5 mounted on the support and constituting a roadbed.
【0003】このとき、上記既存道路1及びその地盤と
上記拡幅道路構造物2との境界接合部6については、既
存道路1の路肩及びそれに続く谷側斜面を掘削し、続い
てその掘削面7と拡幅道路構造物2との間に、土留めの
ための擁壁8を現場打ちコンクリートで構築し、その擁
壁8の背面と上記掘削面との間を土砂で埋め戻した後、
その上に砕石を敷設して砕石路盤とすることで行われ、
その後、その埋戻部9の表層(砕石路盤10部分)、擁
壁8の上面(コンクリート路盤8aとなる部分)、及び
上記拡幅道路構造物2の床版5の上に対し、一体にアス
ファルトなどの舗装材料11で舗装して舗装表層を形成
し、もって拡幅道路とする。At this time, with respect to the boundary joint 6 between the existing road 1 and the ground thereof and the widened road structure 2, a shoulder of the existing road 1 and a valley-side slope following it are excavated, and then the excavated surface 7 is excavated. And a widening road structure 2, a retaining wall 8 for retaining the ground is constructed of cast-in-place concrete, and a space between the back surface of the retaining wall 8 and the excavated surface is backfilled with earth and sand.
It is performed by laying crushed stone on it and making it a crushed stone roadbed,
Thereafter, asphalt or the like is integrally formed on the surface layer of the backfilled portion 9 (the portion of the crushed stone roadbed 10), the upper surface of the retaining wall 8 (the portion to be the concrete roadbed 8a), and the floor slab 5 of the widened road structure 2. To form a pavement surface layer, thereby forming a widened road.
【0004】[0004]
【発明が解決しようとする課題】上述のようにコンクリ
ート擁壁8の背面(既存道路1側)の空間を砂や砕石で
埋め戻すが、掘削する範囲が広く且つ土砂などで埋め戻
して境界接合部6の地盤を構築することから接合部6の
路床が軟弱となる。このため、拡幅工事完了後の車両の
通行により、つまり通行する車両荷重により埋戻部9が
経年的に沈下する。このとき、床版5からなる拡幅道路
部分は、路床を構成する杭3等で堅固に支持されている
ことからさほど沈下せず、また、擁壁8部分についても
路床が強固なコンクリート及びその下側の強固な地盤
(掘削・埋め戻しを行っていない地盤)であるためにさ
ほど沈下しない。As described above, the space behind the concrete retaining wall 8 (on the side of the existing road 1) is backfilled with sand or crushed stone, but the area to be excavated is wide and backfilled with earth and sand to join the boundary. Since the ground of the part 6 is constructed, the roadbed of the joint part 6 becomes soft. For this reason, the backfilling portion 9 sinks down with the passage of the vehicle after the completion of the widening work, that is, with the passing vehicle load. At this time, the widened road portion composed of the floor slab 5 does not sink much because it is firmly supported by the piles 3 and the like constituting the subgrade. It does not sink much because of the strong ground below (the ground that has not been excavated and backfilled).
【0005】このため、長年使用していくうちに擁壁8
部分の道路と埋戻部7の道路との境界Aで著しい段差や
クラックが生じるおそれある。また、境界Aほどではな
いが、床版5部分の道路と擁壁8部分の道路の境界Bに
おいても、支持機構の違いから段差やクラックが生じる
恐れがある。本発明は、上述のような点に着目したもの
で、原地盤上の直接基礎と、埋め戻し部あるいは杭基礎
といった道路を支持する路床部分の強度が異なる道路の
接合部において、一方が相対的に地盤沈下を起こしても
その上方に位置する路面においては、安全交通に影響を
及ぼす局所的な著しい段差を生じることが防止できる道
路の目地部構造を提供することを課題とするものであ
る。[0005] For this reason, the retaining wall 8 has been used for many years.
At the boundary A between the part of the road and the road of the backfill part 7, there is a possibility that a significant step or crack may occur. Although not as large as the boundary A, a step or a crack may also occur at the boundary B between the road of the floor slab 5 and the road of the retaining wall 8 due to the difference in the support mechanism. The present invention focuses on the above points, and in a joint of a direct foundation on the original ground and a road where the strength of a subgrade portion supporting the road such as a backfill portion or a pile foundation is different, one of the two is relatively. It is an object of the present invention to provide a joint structure of a road that can prevent a significant local step from affecting a safe traffic on a road surface located above the ground surface even if the land subsidence occurs. .
【0006】[0006]
【課題を解決するための手段】上記課題を解決するため
に、本発明のうち請求項1に記載した発明は、支持する
路床部分の強度が異なる道路の境界となる道路の目地部
構造であり且つ少なくとも一方の道路の路盤がコンクリ
ート路盤で構成される道路の目地部構造において、上記
コンクリート路盤に固定されて当該コンクリート路盤か
ら他方の道路の路盤に向けて水平若しくは略水平に突出
する鋼板を舗装表層底部に設けたことを特徴とするもの
である。In order to solve the above-mentioned problems, the invention according to claim 1 of the present invention is a joint structure of a road which is a boundary of a road having different strengths of a supporting subgrade. In a joint structure of a road having a roadbed of at least one road formed of a concrete roadbed, a steel plate fixed to the concrete roadbed and projecting horizontally or substantially horizontally from the concrete roadbed toward the roadbed of the other road is provided. It is characterized by being provided at the bottom of the pavement surface layer.
【0007】次に、請求項2に記載した発明は、道路の
コンクリート路盤と砕石路盤との間の目地部構造であっ
て、コンクリート路盤に固定されて当該コンクリート路
盤から砕石路盤に向けて水平若しくは略水平に突出する
舗装表層底部に鋼板を設けたことを特徴とするものであ
る。一方の路盤がコンクリート製であるので、当該路盤
に鋼板を確実に固定して水平に突出させた状態にするこ
とができる。なお、鋼板のコンクリート路盤への固定
は、例えば、アンカーボルトによって行えば良い。Next, an invention according to claim 2 is a joint structure between a concrete roadbed and a crushed stone roadbed, which is fixed to the concrete roadbed and is horizontal or sloping from the concrete roadbed toward the crushed stone roadbed. A steel plate is provided at the bottom of the pavement surface layer that projects substantially horizontally. Since one of the roadbeds is made of concrete, a steel plate can be securely fixed to the roadbed and can be made to project horizontally. In addition, what is necessary is just to fix a steel plate to a concrete roadbed with an anchor bolt, for example.
【0008】さらに、請求項3に記載した発明は、拡幅
道路と既存道路との間の目地部構造であって、拡幅道路
部の床版と既存道路の路盤との間に水平若しくは略水平
に鋼板を舗装表層底部に設けたことこと特徴とするもの
である。また、境界部の舗装表層の底部において路盤間
に段差が生じた状態で車両荷重が負荷されても、鋼板が
撓むように変形することで、舗装表層に急峻な段差が形
成されることは防止される。つまり、舗装面上では、境
界の対向方向に沿ったなだらかな傾斜となって、段差が
緩和される。Further, the invention according to claim 3 is a joint structure between the widened road and the existing road, wherein the joint is horizontally or substantially horizontally between the floor slab of the widened road and the roadbed of the existing road. The steel plate is provided at the bottom of the pavement surface layer. Further, even when a vehicle load is applied in a state where a step is generated between the roadbeds at the bottom of the pavement surface layer at the boundary, the steel plate is deformed so as to bend, thereby preventing a steep step from being formed on the pavement surface layer. You. That is, on the pavement surface, the slope is gentle along the direction facing the boundary, and the step is reduced.
【0009】[0009]
【発明の実施の形態】次に、本発明の第1実施形態につ
いて図面を参照しつつ説明する。なお、上記従来例と同
様な部材などについては同一の符号を付して説明する。
本実施形態では、上記従来例と同様に、傾斜面の既存道
路1を拡幅道路構造物2で拡張した場合を例に説明す
る。ただし、道路の拡幅工事による拡張された道路の基
本構成は、上記従来例と同様であるため、その詳細は省
略して、その各道路間の目地部構造について、図面を参
照しつつ以下に説明する。Next, a first embodiment of the present invention will be described with reference to the drawings. The same members and the like as those in the above-described conventional example are denoted by the same reference numerals and described.
In the present embodiment, similarly to the above-described conventional example, a case where an existing road 1 having an inclined surface is expanded by a widened road structure 2 will be described as an example. However, since the basic configuration of the road expanded by the road widening work is the same as the conventional example described above, the details are omitted, and the joint structure between the roads will be described below with reference to the drawings. I do.
【0010】すなわち、図2に示すように、擁壁8の上
部からなるコンクリート路盤8aが、拡幅道路構造物2
の床版5、及び接合部分の上部に形成された砕石路盤1
0とそれぞれ隣り合って配置されている。まず、上記コ
ンクリート路盤8aと上記砕石路盤10との間の道路の
目地部構造の施工について図2を参照しつつ説明する。That is, as shown in FIG. 2, the concrete roadbed 8a comprising the upper part of the retaining wall 8 is
Floor slab 5 and crushed stone roadbed 1 formed on the upper part of the joint
0 are arranged adjacent to each other. First, the construction of the joint structure of the road between the concrete base 8a and the crushed stone base 10 will be described with reference to FIG.
【0011】まず、砕石路盤10におけるコンクリート
路盤8aに近接部分を当該コンクリート路盤8a上面と
ほぼ同じ高さレベルに調整する。次に、コンクリート路
盤8a及び砕石路盤10の上面における鋼板21を設置
する位置に均しモルタル20を敷設して不陸を解消す
る。これによって、鋼板21を載置する下面が平坦とな
る。均しモルタル20を敷設する理由は、コンクリート
路盤8aの上面と砕石路盤10の上面を完全に面一とす
るのは困難であり、また砕石路盤10の上面には必然的
に凹凸が存在するためである。この均しモルタル20を
敷設しない場合には、拡幅道路の施工が完了した後、路
面23に車両荷重等が負荷された場合に、鋼板21下面
における砕石路盤10側の不陸によって鋼板21が常時
揺動変形しやすくなって好ましくない。First, the portion of the crushed stone subgrade 10 near the concrete subgrade 8a is adjusted to a level substantially equal to the upper surface of the concrete subgrade 8a. Next, a leveling mortar 20 is laid on the upper surface of the concrete roadbed 8a and the crushed stone roadbed 10 at the position where the steel plate 21 is to be installed, thereby eliminating unevenness. Thereby, the lower surface on which the steel plate 21 is placed becomes flat. The reason for laying the leveling mortar 20 is that it is difficult to make the upper surface of the concrete roadbed 8a and the upper surface of the crushed stone bed 10 completely flush with each other, and since the upper surface of the crushed stone bed 10 necessarily has unevenness. It is. When the leveling mortar 20 is not laid, after the construction of the widened road is completed, when a vehicle load or the like is applied to the road surface 23, the steel plate 21 is constantly owing to the unevenness of the crushed stone roadbed 10 side on the lower surface of the steel plate 21. It is not preferable because it easily swings and deforms.
【0012】次に、上記未固結状態の均しモルタル20
の上に鋼板21を載置し、鋼板21をアンカー22でコ
ンクリート路盤8aに固定する。図1に図示するアンカ
ー22では、コンクリート路盤8aから突設する筒体に
アンカーボルトを螺合させて固定しているが、アンカー
構成は、これに限定されることはなく。公知の他のアン
カーを採用しても良い。Next, the unconsolidated leveling mortar 20
The steel plate 21 is placed on the concrete base plate 8a, and the steel plate 21 is fixed to the concrete roadbed 8a by the anchor 22. In the anchor 22 shown in FIG. 1, an anchor bolt is screwed and fixed to a cylindrical body projecting from the concrete roadbed 8a, but the anchor configuration is not limited to this. Other known anchors may be employed.
【0013】次に、コンクリート路盤8aと床版5との
間の道路の目地部について説明する。コンクリート路盤
8aと床版5との間には間隙があるので、当該間隙を目
地材24で塞ぐ。図2中、符号25は目地受け鋼板であ
る。次に、目地材24の上方に鋼板ずれ止め材26が予
め溶接された鋼板28を取り付ける。このとき、コンク
リート路盤8a及び床版5との間隙を確保するように取
り付ける。Next, the joint of the road between the concrete subgrade 8a and the floor slab 5 will be described. Since there is a gap between the concrete roadbed 8a and the floor slab 5, the gap is closed with the joint material 24. In FIG. 2, reference numeral 25 denotes a joint receiving steel plate. Next, a steel plate 28 to which a steel plate slip stopper 26 has been welded in advance is attached above the joint material 24. At this time, it is attached so as to secure a gap between the concrete roadbed 8a and the floor slab 5.
【0014】次に、上記間隙に均しモルタル27を注入
する。なお、本実施形態では、コンクリート路盤8aの
上面と床版5上面との面をあわせるために、床版5上面
を多少はつっている。これは鋼板28のずれ止め効果と
施工誤差によって生じるコンクリート路盤8aと床版5
との間の段差の解消を目的とする。ここで、上記各鋼板
21、28としては、厚さが4.5mm以上12mm以下が
好ましい。厚さが4.5mm未満では、車両荷重によって
撓まないで折れるように変形する可能性があるためであ
る。また、厚さが12mmを越えると車両荷重によって鋼
板21が撓まずに、鋼板による舗装破壊が生じるおそれ
があるためである。Next, a mortar 27 is injected into the gap. In the present embodiment, the upper surface of the floor slab 5 is slightly attached so that the upper surface of the concrete roadbed 8a and the upper surface of the floor slab 5 are aligned. This is because the concrete roadbed 8a and the floor slab 5a, which are caused by the slip prevention effect of the steel plate 28 and the construction error,
The purpose is to eliminate the step between the two. Here, each of the steel plates 21 and 28 preferably has a thickness of 4.5 mm or more and 12 mm or less. This is because if the thickness is less than 4.5 mm, it may be deformed so as to be bent without being bent by the vehicle load. On the other hand, if the thickness exceeds 12 mm, the steel plate 21 does not bend due to the vehicle load, and the pavement may be broken by the steel plate.
【0015】また、上記鋼板21は幅が約400mmの鋼
板21であり、コンクリート路盤8aから砕石路盤10
に向けて200mmだけ突出させている。また、鋼板21
は、道路の延在方向に沿って、連続的に配置されてい
る。上述のように、各路盤間の目地部の施工が完了した
ら、路盤上面に対し、一体にアスファルトなどの舗装材
料11を舗装して路面23を形成する。The steel plate 21 is a steel plate 21 having a width of about 400 mm.
To 200mm. In addition, the steel plate 21
Are continuously arranged along the extending direction of the road. As described above, when the joints between the roadbeds are completed, the pavement material 11 such as asphalt is paved integrally with the upper surface of the roadbed to form the road surface 23.
【0016】次に、上記構成のコンクリート路盤8aと
砕石路盤10との間の道路の目地構造の作用・効果につ
いて説明する。コンクリート路盤8aにあっては、路床
がコンクリート及び強固な地盤で構成されるために、車
両荷重による経年沈下はさほど生じないが、砕石路盤1
0にあっては、路床が埋め戻した土砂からなるために車
両荷重による経年沈下が生じる。Next, the operation and effect of the joint structure of the road between the concrete roadbed 8a and the crushed stone roadbed 10 having the above configuration will be described. In the concrete subbase 8a, since the subgrade is made of concrete and solid ground, the sedimentation due to vehicle load does not occur much, but the crushed stone subbase 1
In the case of 0, the roadbed is made of backfilled earth and sand, and the vehicle load causes secular settlement.
【0017】この結果、経年的に、コンクリート路盤8
aと砕石路盤10との間に段差が生じて、その上方の道
路面23に局所的な段差が生じるおそれがある。しか
し、本実施形態にあってはコンクリート路盤8aと砕石
路盤10との間に段差が生じても、車両荷重によって鋼
板21が撓むように変形することで、当該路盤8a、1
0の上方に位置する道路面23(図2中、符号C部分)
の道路に目地部に局所的な段差やクラックが形成される
ことが防止される。つまり、路面23上では、路盤8
a、10間の対向方向に沿ったなだらかな傾斜となっ
て、道路表面23での段差が緩和される。As a result, the concrete roadbed 8
There is a possibility that a step is generated between the road surface a and the crushed stone roadbed 10, and a local step is generated on the road surface 23 above the road. However, in the present embodiment, even if a step is formed between the concrete roadbed 8a and the crushed stone roadbed 10, the steel plate 21 is deformed so as to be bent by the vehicle load, so that the roadbed 8a, 1
Road surface 23 located above 0 (in FIG. 2, reference C).
The formation of local steps or cracks at joints on the road is prevented. That is, on the road surface 23, the roadbed 8
a, a gentle slope along the facing direction between the a and the 10 and the step on the road surface 23 is alleviated.
【0018】なお、地震動による水平挙動に対しても、
路盤8a、10間の道路の目地部を上記鋼板21が覆う
こととなる。次に、上記構成のコンクリート路盤8aと
床版5との目地構造の作用・効果について説明する。コ
ンクリート路盤8a及び床版5は、その路床がともに強
固であるために経年沈下はさほど生じないが、擁壁8及
び拡幅道路構造物2は共に独立して自立する構造体であ
るため、杭基礎と直接基礎といった支持機構の違いによ
る不等沈下のおそれがある。また、地震によって両者に
相対的に水平変位が生じる。この水平変位があっても、
鋼板28があることで、コンクリート路盤8aと床版5
との間の路面23でクラックなどが生じることが防止さ
れる。Note that the horizontal behavior due to the seismic motion also
The steel plate 21 covers the joint of the road between the roadbeds 8a and 10. Next, the operation and effect of the joint structure between the concrete subgrade 8a and the floor slab 5 having the above configuration will be described. The concrete subbase 8a and the floor slab 5 do not suffer much secular settlement because their subgrades are strong, but the retaining wall 8 and the widened road structure 2 are both independent and independent structures. There is a possibility of uneven settlement due to the difference in the support mechanism between the foundation and the direct foundation. In addition, the earthquake causes a horizontal displacement relative to both. Even with this horizontal displacement,
Since the steel plate 28 is provided, the concrete roadbed 8a and the floor slab 5
The occurrence of cracks and the like on the road surface 23 is prevented.
【0019】ここで、各鋼板21、28としては、縞鋼
板など、上面の粗度が粗い鋼板を使用することが好まし
い。鋼板21、28に上面が粗いものを使用すると、鋼
板21、28と舗装表層となるアスファルトの間の摩擦
力が大きくなって、鋼板21、28に対するアスファル
トの密着性が増加する。これによって、車両の制動・加
速により路面23が受ける荷重によって、アスファルト
が鋼板21、28から剥がれ難くなる。交通量が多い場
合に有効である。Here, as each of the steel plates 21 and 28, it is preferable to use a steel plate having a rough upper surface such as a striped steel plate. If the upper surfaces of the steel plates 21 and 28 are rough, the frictional force between the steel plates 21 and 28 and the asphalt as the pavement surface layer increases, and the adhesion of the asphalt to the steel plates 21 and 28 increases. This makes it difficult for the asphalt to peel off the steel plates 21 and 28 due to the load on the road surface 23 due to the braking and acceleration of the vehicle. This is effective when there is a lot of traffic.
【0020】なお、上記実施形態では、コンクリート路
盤8aから砕石路盤10に突設した鋼板21が、当該砕
石路盤10の上面に配置されているが、当該鋼板21の
上面に砕石を敷設しておいても良い。つまり、鋼板21
は、必ずしも砕石路盤10の上面に配置されていなくて
も良い。但し、この場合には、コンクリート路盤8aの
上面にも砕石を敷いて置くことが好ましい。In the above embodiment, the steel plate 21 projecting from the concrete roadbed 8a to the crushed stone base 10 is disposed on the upper surface of the crushed stone base 10, but the crushed stone is laid on the upper surface of the steel plate 21. May be. That is, the steel plate 21
May not necessarily be arranged on the upper surface of the crushed stone roadbed 10. However, in this case, it is preferable to lay crushed stone on the upper surface of the concrete roadbed 8a.
【0021】次に、第2実施形態について図面を参照し
つつ説明する。なお、上記実施形態と同様な部材等につ
いては同一の符号を付して説明する。本実施形態も、上
記第1実施形態と同様に、傾斜面の既存道路1を拡幅道
路構造物2で拡張した場合を例に説明する。ただし、図
3に示すように、拡幅道路構造物2と既存道路1との間
に擁壁8を構築せず、既存道路1の路肩側の掘削面7と
上記拡幅道路構造物2との間の接合部6の溝に、コンク
リート30を打設することで埋め戻しを行った場合の例
である。Next, a second embodiment will be described with reference to the drawings. Note that the same members and the like as those in the above embodiment will be described with the same reference numerals. In the present embodiment, similarly to the first embodiment, an example will be described in which the existing road 1 having an inclined surface is expanded by the widened road structure 2. However, as shown in FIG. 3, the retaining wall 8 is not constructed between the widened road structure 2 and the existing road 1, and between the excavated surface 7 on the shoulder side of the existing road 1 and the widened road structure 2. This is an example of a case where the concrete 30 is cast into the groove of the joint 6 of FIG.
【0022】この場合には、接合部分の現場打ちコンク
リート30の上面がコンクリート路盤30aとなる。ま
た、既存道路1部分は砕石路盤1aとなっている。そし
て、図4に示すように、上記第1実施形態と同様に、コ
ンクリート路盤30aにアンカー22で固定された鋼板
21を砕石路盤1aに向けて水平若しくは略水平に突設
させて構成されている。In this case, the upper surface of the cast-in-place concrete 30 at the joint portion becomes the concrete roadbed 30a. The existing road 1 is a crushed stone roadbed 1a. As shown in FIG. 4, similarly to the first embodiment, the steel plate 21 fixed to the concrete roadbed 30a with the anchor 22 is protruded horizontally or substantially horizontally toward the crushed stone roadbed 1a. .
【0023】これによって、路面23における既存道路
1部分と接合部6との間の安全交通に影響を及ぼす局所
的な著しい段差やクラックの発生が防止される。他の構
成や作用・効果等については、上記第1実施形態と同様
である。なお、コンクリート路盤30aと床版5との目
地については、コンクリートが打ち込まれることで、コ
ンクリート30が拡幅道路構造物2の杭3や桁4と一体
的に固着されて、当該コンクリート路盤30aと床版5
とが一体となって杭基礎により支持されることから不等
沈下の恐れがないので、鋼板21の設置を実施していな
い。As a result, the occurrence of local significant steps and cracks which affect the safety traffic between the existing road 1 and the junction 6 on the road surface 23 is prevented. Other configurations, operations, effects, and the like are the same as those in the first embodiment. As for the joint between the concrete roadbed 30a and the floor slab 5, the concrete 30 is integrally fixed to the pile 3 and the girder 4 of the widened road structure 2 by being driven into the concrete. Edition 5
The steel plate 21 is not installed because there is no possibility of unequal settlement because the and are integrally supported by the pile foundation.
【0024】次に、第3実施形態について図面を参照し
つつ説明する。本実施形態は、図5に示すように、隣り
合う路盤が共にコンクリート路盤31a、32である
が、一方の路盤31aの路床がコンクリートから構成さ
れて強度が高く、且つ他方の路盤32の路床33が埋め
戻した土砂から構成された相対的に路床の強度が低い場
合である。Next, a third embodiment will be described with reference to the drawings. In this embodiment, as shown in FIG. 5, the adjacent sub-bases are both concrete sub-bases 31a and 32, but the sub-base of one sub-base 31a is made of concrete and has high strength, and the road of the other sub-base 32 is used. This is the case where the strength of the subgrade made of the backfilled earth and sand is relatively low.
【0025】この場合も、両路盤31a、32間の施工
誤差から生じる段差を埋めて不陸を解消するために、鋼
板21を設置する部分に均しモルタル20を敷設し、そ
の上に鋼板21を設置して、当該鋼板21を相対的に路
床強度の大きい側のコンクリート路盤30aにアンカー
22で固定している。これによって、既存道路1部分と
埋め戻し部との間の安全交通に影響を及ぼす局所的な著
しい段差やクラックの発生が防止される。In this case, too, in order to fill in a step caused by a construction error between the roadbeds 31a and 32 and eliminate unevenness, a leveling mortar 20 is laid on a portion where the steel plate 21 is installed, and the steel plate 21 is placed thereon. Is installed, and the steel plate 21 is fixed to the concrete roadbed 30a on the side with relatively large roadbed strength by the anchor 22. As a result, the occurrence of significant local steps and cracks that affect the safety traffic between the existing road 1 portion and the backfill portion is prevented.
【0026】他の構成や作用・効果等については、上記
第1及び第2実施形態と同様である。Other structures, operations, effects, and the like are the same as those in the first and second embodiments.
【0027】[0027]
【発明の効果】以上説明してきたように、本発明の道路
の目地部構造を採用すると、経年的に路盤間に段差が生
じても、その上面の路面に安全交通に影響を及ぼす局所
的な著しい段差やクラックが生じ難くなるという効果が
ある。As described above, when the joint structure of a road according to the present invention is employed, even if a step is generated between roadbeds over time, a local surface which affects safety traffic on the upper surface of the roadbed. There is an effect that significant steps and cracks hardly occur.
【図1】従来の拡幅道路の構成を示す図である。FIG. 1 is a diagram showing a configuration of a conventional widened road.
【図2】本発明に基づく第1実施形態に係る道路の目地
部構造を説明する拡大図である。FIG. 2 is an enlarged view illustrating a joint structure of a road according to the first embodiment of the present invention.
【図3】本発明に基づく第2実施形態に係る拡幅道路の
構成を示す図である。FIG. 3 is a diagram showing a configuration of a widened road according to a second embodiment based on the present invention.
【図4】本発明に基づく第2実施形態に係る道路の目地
部構造を説明する拡大図である。FIG. 4 is an enlarged view illustrating a joint structure of a road according to a second embodiment of the present invention.
【図5】本発明に基づく第3実施形態に係る道路の目地
部構造を説明する拡大図である。FIG. 5 is an enlarged view illustrating a joint structure of a road according to a third embodiment of the present invention.
1 既存道路 1a 砕石路盤 2 拡幅道路構造物 3 杭 4 桁 5 床版 6 接合部 7 掘削面 8 擁壁 8a コンクリート路盤 9 埋戻部 10 砕石路盤 11 舗装材料 20 均しモルタル 21 鋼板(目地鋼板) 22 アンカー 23 路面 24 目地材 26 鋼板ずれ止め材 27 均しモルタル 28 鋼板(踏掛鋼板) 30 コンクリート 30a コンクリート路盤 31 コンクリート 31a コンクリート路盤 32 コンクリート路盤 33 路床 DESCRIPTION OF SYMBOLS 1 Existing road 1a Crushed stone roadbed 2 Widening road structure 3 Pile 4 Girder 5 Floor slab 6 Joint 7 Excavation surface 8 Retaining wall 8a Concrete roadbed 9 Backfill part 10 Crushed stone roadbed 11 Pavement material 20 Leveling mortar 21 Steel plate (joint steel plate) Reference Signs List 22 anchor 23 road surface 24 joint material 26 steel plate slip stopper 27 leveling mortar 28 steel plate (steel plate) 30 concrete 30a concrete roadbed 31 concrete 31a concrete roadbed 32 concrete roadbed 33 roadbed
フロントページの続き (72)発明者 吉武 英樹 東京都千代田区内幸町2丁目2番3号 川 崎製鉄株式会社内 (72)発明者 塩田 啓介 東京都千代田区内幸町2丁目2番3号 川 崎製鉄株式会社内 Fターム(参考) 2D051 AC04 AF01 AF03 CA01 Continuing from the front page (72) Inventor Hideki Yoshitake 2-3-2 Uchisaiwaicho, Chiyoda-ku, Tokyo Inside Kawasaki Steel Corporation (72) Inventor Keisuke Shiota 2-3-2 Uchisaiwaicho, Chiyoda-ku, Tokyo Kawasaki Steel Co., Ltd. F term in the company (reference) 2D051 AC04 AF01 AF03 CA01
Claims (3)
境界となる、道路の目地部構造であり且つ少なくとも一
方の道路の路盤がコンクリート路盤で構成される道路の
目地部構造において、上記コンクリート路盤に固定され
て当該コンクリート路盤から他方の道路の路盤に向けて
水平若しくは略水平に突出する鋼板を舗装表層底部に設
けたことを特徴とする道路の目地部構造。1. The joint structure of a road, which is a joint structure of a road, which is a boundary of a road having different strengths of a supporting subgrade, and wherein at least one of the road bases is a concrete base. A jointed road structure comprising a steel plate fixed to a roadbed and projecting horizontally or substantially horizontally from the concrete roadbed toward the roadbed of the other road at a bottom portion of a pavement surface layer.
間の目地部構造であって、コンクリート路盤に固定され
て当該コンクリート路盤から砕石路盤に向けて水平若し
くは略水平に突出する舗装表層底部に鋼板を設けたこと
を特徴とする道路の目地部構造。2. A joint structure between a concrete roadbed and a crushed stone roadbed, which is fixed to the concrete roadbed and projects horizontally or substantially horizontally from the concrete roadbed toward the crushed stone roadbed. Joint structure of road characterized by having provided.
であって、拡幅道路部の床版と既存道路の路盤との間に
水平若しくは略水平に鋼板を舗装表層底部に設けたこと
こと特徴とする道路の目地部構造。3. A joint structure between a widened road and an existing road, wherein a steel plate is provided horizontally or substantially horizontally between a floor slab of the widened road and a roadbed of the existing road at a bottom portion of a pavement surface layer. A joint structure of a road characterized by the following.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000087180A JP2001271303A (en) | 2000-03-27 | 2000-03-27 | Joint-section structure of road |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000087180A JP2001271303A (en) | 2000-03-27 | 2000-03-27 | Joint-section structure of road |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2001271303A true JP2001271303A (en) | 2001-10-05 |
Family
ID=18603229
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000087180A Pending JP2001271303A (en) | 2000-03-27 | 2000-03-27 | Joint-section structure of road |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2001271303A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010163769A (en) * | 2009-01-14 | 2010-07-29 | Tokyo Geotech Kk | Step preventive construction method and structure for paved road |
CN108642988A (en) * | 2018-06-26 | 2018-10-12 | 杭州江润科技有限公司 | Embankment base disease Comprehensive Treatment repairs structure and construction method |
CN110725162A (en) * | 2019-10-22 | 2020-01-24 | 中铁十局集团第八工程有限公司 | Roadbed device for rail transit and manufacturing method |
CN114381977A (en) * | 2022-01-26 | 2022-04-22 | 西安公路研究院有限公司 | Reinforcement treatment method for regenerated resources of road steep slope back |
CN116180536A (en) * | 2023-03-07 | 2023-05-30 | 北京市政建设集团有限责任公司 | Municipal road widening anti-cracking structure and construction method thereof |
CN116497700A (en) * | 2023-04-24 | 2023-07-28 | 安徽省交通控股集团有限公司 | Seamless pile plate type road |
-
2000
- 2000-03-27 JP JP2000087180A patent/JP2001271303A/en active Pending
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010163769A (en) * | 2009-01-14 | 2010-07-29 | Tokyo Geotech Kk | Step preventive construction method and structure for paved road |
CN108642988A (en) * | 2018-06-26 | 2018-10-12 | 杭州江润科技有限公司 | Embankment base disease Comprehensive Treatment repairs structure and construction method |
CN108642988B (en) * | 2018-06-26 | 2020-08-04 | 杭州江润科技有限公司 | Comprehensive treatment and repair structure for embankment base layer diseases and construction method |
CN110725162A (en) * | 2019-10-22 | 2020-01-24 | 中铁十局集团第八工程有限公司 | Roadbed device for rail transit and manufacturing method |
CN114381977A (en) * | 2022-01-26 | 2022-04-22 | 西安公路研究院有限公司 | Reinforcement treatment method for regenerated resources of road steep slope back |
CN116180536A (en) * | 2023-03-07 | 2023-05-30 | 北京市政建设集团有限责任公司 | Municipal road widening anti-cracking structure and construction method thereof |
CN116497700A (en) * | 2023-04-24 | 2023-07-28 | 安徽省交通控股集团有限公司 | Seamless pile plate type road |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20160089215A (en) | Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same | |
JP2009250006A (en) | Countermeasure structure for ground subsidence | |
JP6301718B2 (en) | Method for suppressing level difference in roadbed material laid across concrete and earth structures | |
KR101726725B1 (en) | Construction method for a sidewalk enlargement installation | |
JP2001271303A (en) | Joint-section structure of road | |
JP2004162362A (en) | Aseismatic reinforcing structure for pile foundation structure | |
JPH06116942A (en) | Construction method of critical sheathing wall | |
JP5800546B2 (en) | Precast foundation plates, foundations for precast structures and construction methods for earth retaining structures | |
KR100975673B1 (en) | Expanded bicycle road built around road and construction method thereof | |
KR101544756B1 (en) | Retaining wall block construction method using stone | |
JP2000345502A (en) | Boundary jointing structure for road with enlarged width and method for jointing boundary | |
JP2018115475A (en) | Concrete block and laying structure using the same | |
JP2006028796A (en) | Uneven step elimination structure of road | |
KR20020025856A (en) | Prevention of approach slab settlement by applying non-com paction abutment backfilling method | |
JPH0473310A (en) | Construction technique of structure in wear subsoil | |
JPH07300845A (en) | Preventive method against liquefaction of underground linear structure | |
JPH11280087A (en) | Ground solidifying construction method for damping and preventing liquefaction | |
JP2000297403A (en) | Passage and construction method therefor | |
JP3714475B2 (en) | Road extension method and road extension structure | |
KR20030036508A (en) | The method of consolidation for excavating tunnel and the lagging being in used in this method | |
JPH0692641B2 (en) | Road widening method | |
JP3595281B2 (en) | Road repair method and PCa version | |
KR20030008288A (en) | Construction method for back-fill area of abutment | |
JPH073829A (en) | Vibration controlling method by buried board block | |
JP3352951B2 (en) | Installation method of invert and underground drainage in mountain tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20041015 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20041026 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20050315 |