KR20160089215A - Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same - Google Patents

Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same Download PDF

Info

Publication number
KR20160089215A
KR20160089215A KR1020150008893A KR20150008893A KR20160089215A KR 20160089215 A KR20160089215 A KR 20160089215A KR 1020150008893 A KR1020150008893 A KR 1020150008893A KR 20150008893 A KR20150008893 A KR 20150008893A KR 20160089215 A KR20160089215 A KR 20160089215A
Authority
KR
South Korea
Prior art keywords
pile
concrete wall
precast concrete
girder
socket
Prior art date
Application number
KR1020150008893A
Other languages
Korean (ko)
Other versions
KR101772939B1 (en
Inventor
최승희
Original Assignee
최승희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최승희 filed Critical 최승희
Priority to KR1020150008893A priority Critical patent/KR101772939B1/en
Publication of KR20160089215A publication Critical patent/KR20160089215A/en
Application granted granted Critical
Publication of KR101772939B1 publication Critical patent/KR101772939B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Foundations (AREA)

Abstract

The present invention relates to a non-abutment rigid-frame bridge using a precast concrete wall and a pile, and a construction method for the same. The purpose of the non-abutment rigid-frame bridge is to: improve constructability as a structure except for a floor unit of an upper structure is constructed using precast concrete; stably induce a movement of a structure by a temperature change; and obtain ground stability of a backfill part. According to the present invention, the non-abutment rigid-frame bridge using the precast concrete wall and the pile includes: one or more piles (10) individually constructed on sides facing each other on both sides of a road or a river in order for a head unit to protrude from the ground whereas a lower part is embedded in the ground; a precast concrete wall (20) constructed in order for the head unit of the pile to penetrate the upper part of a pile insertion hole, wherein the precast concrete wall (20) comprises a hollow unit (21) and the one or more pile insertion holes (22) inside; a socket (50) which is a concrete body with a hole, wherein the socket is mounted on the hollow unit of the precast concrete wall to be able to move and is connected to the head unit of the pile through the hole; an upper structure (30) which is integrated with the pile and the socket through a girder (31) arranged to cross a river or a road, wherein both sides of the girder in the longitudinal direction are mounted on the precast concrete wall, and through a floor unit (32) constructed using concrete across the inside of the socket, a point unit in which the upper part of the socket of the girder are connected to each other, and the upper part of the girder; and a pavement layer constructed on the upper structure. While the precast concrete wall is not moved, the pile and the upper structure are moved in the precast concrete wall.

Description

프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 및 이의 시공 공법{NON-ABUTMENT BRIDGE STRUCTURE USING PRECAST CONCRETE RETAINING WALL AND PILE, AND METHOD FOR CONSTRUCTING THIS SAME}BACKGROUND OF THE INVENTION Field of the Invention [0001] The present invention relates to a pre-cast concrete wall and a pile,

본 발명은 라멘교에 관한 것으로, 더욱 상세하게는 상부 구조물의 바닥부를 제외한 구조물을 프리캐스트 콘크리트로 제작하여 시공성을 향상하고 온도 변화 등에 의한 구조물의 거동을 안정적으로 유도함과 아울러 뒷채움부의 지반안정성을 확보하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 및 이의 시공 공법에 관한 것이다.
The present invention relates to a raymen bridge, and more particularly, to a railway bridges, which is constructed of precast concrete except for the bottom of the upper structure to improve workability, stably induce the behavior of the structure due to temperature changes, and secure the ground stability of the back- The present invention relates to a pre-cast concrete wall and pile-based non-alternating raymen bridge and its construction method.

교량은 소하천, 하천, 계곡을 횡단하도록 하는 등을 목적으로 시공되는 구조물로서, 교량이 위치하게 되는 곳의 지형이나 다양한 지질의 조건에 잘 부합되도록 설치하게 된다.Bridges are constructed for the purpose of crossing small rivers, rivers, and valleys, and they are installed so that they fit well with the topography and various geological conditions of the place where the bridge is located.

교량은 상부 구조 형식에 따라 라멘교, 거더교, 아치교, 트러스교, 사장교, 현수교 등이 있고, 본 발명은 라멘교에 대한 것이므로 이하에서는 라멘교에 대해서만 설명하기로 한다.The bridges can be classified into various kinds of bridges such as ramen bridges, girder bridges, arch bridges, truss bridges, cable-stayed bridge bridges, suspension bridges, etc., and the present invention relates to bridges bridges.

일반적으로 교량을 설치하기 위해서는 우선 교량의 시작점과 끝점에 교량을 받칠 수 있는 교대를 설치하게 되는데, 특히, 연약지반에 교대를 설치하게 되는 경우 교대 배면의 뒷채움 성토로 인해 교대 배면에 직접 횡방향 압력이 작용하게 되고 더불어 성토부의 원지반에 큰 상재하중이 작용하게 되며, 이는 하부 지반을 측방향으로 이동시키려는 압력으로 나타나 교대의 하부 기초에 작용하게 되어 결과적으로 측방유동, 즉 교대 앞쪽으로 밀림현상이 발생되고, 이를 방지하기 위하여 교대의 구조적 강성을 증대하는 기술들이 제안되고 있다.In general, in order to install a bridge, firstly, an alternation which can support the bridge at the starting point and the end point of the bridge is installed. Especially, when the alternation is installed on the soft ground, And the large ground load is applied to the ground of the embankment, which acts as a pressure to move the lower ground in the lateral direction and acts on the lower foundation of the alternation, resulting in a lateral flow, that is, In order to prevent this, alternate structural stiffness enhancement technologies have been proposed.

한편, 라멘교 중에서 터파기를 줄여 시공성을 향상하고 교대 배면의 부등침하의 문제를 해결하는 등의 장점을 갖고 있는 무교대 라멘교가 있다.On the other hand, there is a non-alternating ramen bridge which has advantages such as improving the workability by reducing the tread period in the ramen bridge and solving the problem of the uneven settlement of the alternate back.

특허문헌 1(등록특허 제10-0983861호)은 지중에 근입 정착되는 단주파일과 상부 구조물을 현장 콘크리트 타설하여 무교대화하는 것이며, 현장 콘크리트 타설에 의해 교량시종점부가 단주파일과 일체화되기 때문에 지반의 거동이나 콘크리트 수축팽창 등에 의한 거동이 불가능하므로 단주파일과 교량시종점부에 균열이 발생되는 문제점이 있다.Patent Document 1 (Registered Patent No. 10-0983861) discloses a structure in which a single pile file and an upper structure which are fixedly installed in the ground are paved by putting on-site concrete, and since the end portion of the bridge is integrated with the single pile The behavior due to the behavior and the expansion and contraction of the concrete can not be performed.

그리고, 벽체 배면을 무다짐 골재로 뒷채움하여 시공성이 좋지 못하고, 구조물이 거동할 수 있는 균일한 공간을 제공하지 못하여 구조물과 지반의 안정성이 약한 문제점이 있다.In addition, since the backside of the wall is backed by non-aggregate aggregate, the constructability is poor and the structure and the ground are not stable due to the lack of a uniform space in which the structure can behave.

또한, 상부 구조물과 하부 구조물의 우각부가 구조적으로 균일하게 합성되지 못하여 하부 구조물과 상부 구조물의 거동성이 좋지 못한 문제점도 있다.
Also, since the right angles of the upper structure and the lower structure are not structurally uniformly synthesized, there is a problem that the mobility of the lower structure and the upper structure is poor.

등록특허 제10-0983861호Patent No. 10-0983861

본 발명은 전술한 바와 같은 문제점을 해결하기 위한 것으로, 상부 구조물의 바닥부를 제외한 구조물을 프리캐스트 콘크리트로 제작하여 시공성을 향상하고 온도 변화 등에 의한 구조물의 거동을 안정적으로 유도함과 아울러 뒷채움부의 지반안정성을 확보하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 및 이의 시공 공법을 제공하려는데 그 목적이 있다.
The present invention has been made to solve the above-mentioned problems, and it is an object of the present invention to improve the workability by constructing the structure excluding the bottom part of the upper structure as precast concrete, stably inducing the behavior of the structure by temperature change, It is aimed to provide a non - alternating ramen bridge and a construction method using precast concrete wall and pile to secure.

본 발명에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교는, 서로 마주하도록 설치되는 말뚝과; 상기 말뚝의 두부가 내부에 삽입되도록 시공되는 프리캐스트 콘크리트 벽체와; 상기 프리캐스트 콘크리트 벽체의 중공부에 거동이 가능하도록 장착되면서 상기 말뚝의 두부가 내부에 삽입되는 소켓과; 하천 또는 도로를 횡단하는 방향으로 배열되면서 종방향의 양측이 상기 프리캐스트 콘크리트 벽체 위에 거치되는 거더, 상기 소켓의 내부, 상기 소켓의 상부와 상기 거더가 연결되는 지점부 및 상기 거더의 상부에 걸쳐 콘크리트 시공되는 바닥부를 통해 상기 말뚝 및 소켓과 일체로 합성되는 상부 구조물과; 상기 상부 구조물 위에 시공되는 포장층을 포함하여 이루어지며, 상기 프리캐스트 콘크리트 벽체가 거동하지 않는 상태에서 상기 말뚝과 상기 상부 구조물이 상기 프리캐스트 콘크리트 벽체 안에서 거동하는 것을 특징으로 한다.The precast concrete wall according to the present invention and the non-alternating ramen bridge using the pile include: a pile installed so as to face each other; A precast concrete wall constructed so that a head of the pile is inserted therein; A socket in which a head portion of the pile is inserted into the hollow portion of the precast concrete wall so as to be movable; A girder which is arranged in a direction transverse to a river or a road and on which both longitudinal sides are mounted on the precast concrete wall, an inner portion of the socket, a fulcrum portion where the upper portion of the socket is connected to the girder, An upper structure integrally formed with the pile and the socket through a bottom part to be installed; And a pavement layer formed on the upper structure, wherein the pile and the upper structure move in the precast concrete wall in a state where the precast concrete wall does not move.

본 발명에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교는, 말뚝, 상기 말뚝의 상부에 거치되는 프리캐스트 콘크리트 벽체, 상기 프리캐스트 콘크리트 벽체 상부에 거치되는 거더, 상기 프리캐스트 콘크리트 벽체의 내부와 상기 프리캐스트 콘크리트 벽체와 상기 거더의 지점부 및 상기 거더의 상부에 콘크리트 타설되는 바닥부를 통해 상기 말뚝과 상기 프리캐스트 콘크리트 벽체 및 상부 구조물이 일체로 합성되는 것을 특징으로 한다.
The pre-cast concrete wall and the non-alternating ramming bridge using the pile according to the present invention are characterized by comprising a pile, a pre-cast concrete wall resting on the upper portion of the pile, a girder resting on the precast concrete wall, And the pile and the precast concrete wall and the upper structure are integrally formed through the precast concrete wall, the fulcrums of the girder, and the bottom portion of the concrete placed on the upper portion of the girder.

본 발명에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 및 이의 시공 공법에 의하면, 말뚝의 강성과 말뚝과 상부 구조물간의 강성 증대를 통해 무교대 시공이 가능하고, 상부 구조물의 바닥부를 제외한 구조물을 프리캐스트 콘크리트로 제작하여 시공 현장에서 거치하는 작업을 통해 시공이 이루어지므로 공기를 단축하고 공사비를 절감하는 효과가 있고, 경제적 측면뿐만 아니라 벽체 안에서 말뚝과 상부 구조물을 일체로 합성하여 이 구조물이 온도 변화 등에 의해 벽체 안에서만 거동하도록 함으로써 즉 구조물의 거동이 뒷채움부와 지반에 전달되지 않도록 함으로써 지반을 안정화하고 결과적으로 라멘교 구조물을 안정화하는 효과가 있다.According to the present invention, by using the precast concrete wall and the pile, the non-alternating raymen bridge and the construction method thereof, it is possible to perform the non-alternation construction through the rigidity of the pile and the rigidity between the pile and the upper structure, The prefabricated concrete is constructed as a precast concrete, and the construction is carried out through the operation of mounting at the construction site. Thus, the air is shortened and the construction cost is reduced. In addition, the pile and the upper structure are integrally combined in the wall, It is possible to stabilize the ground by stabilizing the framed structure by preventing the behavior of the structure from being transmitted to the backfill and the ground.

그리고, 아치형 PC 거더의 구조를 통해 하부 구조물과 거더가 연결되는 지점부(우각부)에서 합성력을 증대함으로써 구조물간의 응력전달이 원활 및 균일하여 전체적으로 구조를 안정화하는 효과가 있다.
In addition, through the structure of the arched type PC girder, the composite force is increased at the point where the lower structure and the girder are connected (right part), so that the stress transmission between the structures is smooth and uniform.

도 1은 본 발명의 실시예 1에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교의 시공 상태도.
도 2는 본 발명의 실시예 1에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교에 적용된 말뚝의 구성도.
도 3은 본 발명의 실시예 1에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교에 적용된 프리캐스트 콘크리트 벽체와 소켓의 분리 사시도.
도 4는 본 발명의 실시예 1에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교에 적용된 프리캐스트 콘크리트 벽체의 다른 예를 보인 분해 사시도.
도 5는 도 4의 결합상태 정면도.
도 6 내지 도 8은 각각 본 발명의 실시예 1에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교에 적용된 거더의 예시도.
도 9는 본 발명의 실시예 1에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교에 적용된 소켓과 말뚝의 합성 상태도.
도 10a 내지 도 10h는 본 발명의 실시예 1에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교의 시공 공정도.
도 11은 본 발명의 실시예 2에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교의 시공 상태도.
도 12는 본 발명의 실시예 3에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교의 시공 상태도.
1 is a view showing a construction state of a non-alternating ramen bridge using a precast concrete wall and a pile according to Embodiment 1 of the present invention.
Fig. 2 is a schematic view of a pile applied to a non-alternating raymen bridge using precast concrete walls and piles according to Embodiment 1 of the present invention.
FIG. 3 is a perspective view showing a pre-cast concrete wall and a socket applied to a non-alternating raymen bridge using a pre-cast concrete wall and a pile according to Embodiment 1 of the present invention;
FIG. 4 is an exploded perspective view showing another example of precast concrete wall applied to a non-alternating ramen bridge using a precast concrete wall and pile according to Embodiment 1 of the present invention; FIG.
Fig. 5 is a front view of the coupling state of Fig. 4; Fig.
6 to 8 are views showing examples of a girder applied to a non-alternating ramen bridge using a precast concrete wall and a pile according to Embodiment 1 of the present invention.
9 is a view showing a composite state of a socket and a pile applied to a non-alternating raymen bridge using a precast concrete wall and a pile according to Embodiment 1 of the present invention.
10A to 10H are views showing a construction process of a non-alternating ramen bridge using a precast concrete wall and a pile according to Embodiment 1 of the present invention.
11 is a view showing a construction state of a non-alternating ramen bridge using a precast concrete wall and a pile according to a second embodiment of the present invention.
12 is a view showing a construction state of a non-alternating ramen bridge using a precast concrete wall and a pile according to a third embodiment of the present invention.

<실시예 1>&Lt; Example 1 >

도 1에서 보이는 것처럼, 본 실시예에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교는, 하천의 양측 변에 각각 설치되는 한 쌍의 하부 구조물 및 상기 하부 구조물 위에 시공되는 상부 구조물로 구성된다.As shown in FIG. 1, the precast concrete wall according to the present embodiment and the non-alternating ramen bridge using piles are composed of a pair of lower structures respectively installed on both sides of a river and an upper structure to be installed on the lower structure .

상기 하부 구조물은 파형 단면의 말뚝(10), 말뚝(10)의 두부에 삽입되며 상기 상부 구조물을 지지하는 프리캐스트 콘크리트 벽체(20)(이하 "벽체"라 약칭함)로 구성되며, 상기 상부 구조물(30)은 거더(31) 및 거더(31)와 벽체(20)가 연결되는 우각부와 거더(31) 상부에 콘크리트 시공되는 상부 바닥부(32)로 이루어진다. The lower structure is composed of a pile 10 having a corrugated cross section and a precast concrete wall 20 inserted into a head of the pile 10 and supporting the upper structure (hereinafter, referred to as "wall"), The upper wall portion 30 is composed of a girder 31 and an upper floor portion 32 on which a girder 31 and a wall 20 are connected and a concrete upper portion 32 constructed on the girder 31.

그리고, 상부 구조물(30)과 지반을 접속하는 접속슬래브(40)가 갖추어진다.Then, a connecting slab 40 connecting the upper structure 30 and the ground is provided.

본 실시예는 벽체(20) 안에서 상부 구조물(30)과 말뚝(10)을 합성하는 한편 벽체(20)와는 합성되지 않는 소켓(50)이 적용되어 벽체(20)는 거동하지 않는 상태에서 소켓(50)을 통해 상부 구조물(30)과 말뚝(10)의 거동이 가능하도록 한다.
In this embodiment, the upper structure 30 and the pile 10 are combined with each other in the wall 20 while the socket 50, which is not combined with the wall 20, is applied to the wall 20, 50 so that the upper structure 30 and the pile 10 can be moved.

도 2에서 보이는 바와 같이, 말뚝(10)은 파형 강관(11), 파형 강관(11)의 내부에 배근되는 철근(12) 및 파형 강관(11)의 내부에 타설되는 콘크리트(13)에 의해 이루어지며, 파형 강관(11)이 철근(12)의 둘레부를 감싸기 때문에 철근피복의 축소가 가능하고 유효단면적의 확대로 말뚝 강성을 증대하며 토사와 저촉배제로 품질을 향상하고 주변마찰력 증대로 허용 지지력을 증대한다.2, the pile 10 is composed of a corrugated steel pipe 11, a reinforcing steel 12 laid in the corrugated steel pipe 11, and a concrete 13 placed in the corrugated steel pipe 11 Since the corrugated steel pipe 11 surrounds the periphery of the reinforcing bars 12, it is possible to reduce the sheathing of the reinforcing bars and increase the effective sectional area to increase the stiffness of the pile. Increase.

콘크리트(13)는 파형 강관(11)과 철근(12) 조립체의 현장 시공 후 현장 타설에 의해 이루어질 수 있고 또는 공장에서 제작된 완제품으로 시공되는 것도 가능하다.The concrete 13 can be made by field installation after the field construction of the corrugated steel pipe 11 and the reinforcing steel 12 assembly, or it can be installed as a finished product manufactured at the factory.

파형 강관(11)은 상하부가 개방된 파형 단면의 관이며 내부에 배근되는 철근(12)의 고정을 위하여 하부의 개방부에는 하부 막음판(14)(강판 등)이 용접 등으로 고정되고 상부의 개방부에는 상부 덮개판(15)(강판 등)이 용접 등으로 고정된다. 상부 덮개판(15)은 철근(12)이 통과하는 철근 삽입홀, 콘크리트 채움홀 등이 구비된 판재일 수 있다.The corrugated steel pipe 11 is a tube having a corrugated cross section whose upper and lower portions are opened. A lower blocking plate 14 (steel plate or the like) is fixed to the lower open portion by welding or the like for fixing the reinforcing bars 12, The upper cover plate 15 (steel plate or the like) is fixed to the opening portion by welding or the like. The upper cover plate 15 may be a plate having a reinforcing bar insertion hole or a concrete filling hole through which the reinforcing bar 12 passes.

파형 강판(11)은 단면 구조 상 콘크리트와의 결속력을 증대함은 물론 거푸집의 기능을 겸하므로 구조의 단순화를 도모하고 제조 및 시공을 단순화한다.The corrugated steel plate 11 not only increases the bonding force with the concrete on the cross-sectional structure, but also functions as a formwork, thereby simplifying the structure and simplifying the manufacturing and construction.

철근(12)은 다단의 띠철근(12a)과 원주방향을 따라 일정 간격을 두고 배열되면서 띠철근(12a)에 결합되는 종철근(12b)으로 구성 가능하며, 종철근(12b)은 말뚝(10)의 두부 보강을 위하여 상부가 파형 강관(11)의 상부로 돌출되는 것이 바람직하다.The reinforcing bars 12 may be composed of a longitudinal reinforcing bar 12b connected to the reinforcing bar 12a while being spaced apart from the reinforcing bars 12a at a predetermined interval along the circumferential direction. It is preferable that the upper portion protrudes to the upper portion of the corrugated steel pipe 11.

말뚝(10)은 두부 아래쪽이 지중에 근입되어 지지력을 확보하고 두부가 벽체(20) 안에서 상부 구조물(30)과 일체로 합성됨으로써 큰 지지력을 통해 상기 상부 구조물(30)을 지지하는 것이며, 종철근 중에서 파형 강판(11)의 상부로 돌출된 부분이 소켓(50) 안에 배근되는 형태가 가능하다.The pile 10 supports the upper structure 30 through a large supporting force by inserting the lower part of the head into the ground to secure the supporting force and synthesizing the head part integrally with the upper structure 30 in the wall body 20, A portion protruding to the upper portion of the corrugated steel plate 11 may be arranged in the socket 50. [

말뚝(10)은 전술한 구성으로 한정되지 아니하고 H 빔 등 다양한 구성이 사용 가능하다.The pile 10 is not limited to the above-described configuration, and various configurations such as an H beam can be used.

말뚝(10)이 근입되는 지중의 말뚝공은 바닥에서부터 일정 높이까지는 시멘트 풀이 충진되어 말뚝(10)을 정착하고 상부는 말뚝(10)의 거동을 위하여 토사 등이 충진된다.
The pile of the pile in which the pile 10 is inserted is filled with cement paste from the bottom to a certain height to fix the pile 10 and the pile 10 is filled with soil and the like for the behavior of the pile 10. [

도 1과 도 3에서 보이는 것처럼, 벽체(20)는 지중에 근입 정착된 말뚝(10)의 두부와 상부 구조물이 소켓(50)을 매개로 하여 거동이 가능한 상태로 합성되도록 내부에 상부를 향해 개방되는 중공부(21)가 구비됨과 아울러 바닥부에는 말뚝 삽입공(22)이 구비된 프리캐스트 콘크리트체이다.As shown in FIGS. 1 and 3, the wall 20 is formed so that the head and the upper structure of the pile 10, which are fixedly fitted in the ground, are opened toward the upper portion so as to be synthesized in a state in which the upper structure is movable through the socket 50 And a pile inserting hole 22 is provided at the bottom of the concrete pavement.

벽체(20)는 말뚝(10)과 상부 구조물(30) 및 소켓(50)이 거동하는 여유 공간을 제공하기 위하여 신축용 봉함재(60)가 적용된다.The wall 20 is applied with a sealing member 60 for expansion and contraction to provide a clearance space in which the pile 10, the upper structure 30 and the socket 50 move.

신축용 봉함재(60)는 소켓(50)과 벽체(20) 사이의 둘레부에 장착되며 소켓(50)의 거동에 의해 수축되고 자신의 탄성력에 의해 복원되는 탄성체가 바람직하며, 스티로폼의 발포체도 사용 가능하고 신축용 봉함재(60)의 상단에 차수가 가능한 방수용 봉함재가 추가로 설치될 수도 있다.It is preferable that the elastic sealing member 60 is an elastic body which is attached to the peripheral portion between the socket 50 and the wall body 20 and is contracted by the action of the socket 50 and is restored by its own elastic force, And a waterproof sealing material capable of forming a waterproof sealant may be additionally provided on the upper end of the sealing member 60 for expansion and contraction.

또한, 벽체(20)의 중공부(22)에는 말뚝(10)의 거동을 위하여 비콘크리트재질인 양질의 토사 등의 채움재(61)(도 1에 도시됨)가 채워진다.
The hollow portion 22 of the wall body 20 is filled with a filler material 61 (shown in FIG. 1) of high quality, such as non-concrete, for the behavior of the pile 10.

벽체(20)는 저부에 벽체(20)의 몸체(23)보다 큰 단면적의 기초부(24)가 필요에 따라 형성(단 기존 풋팅부보다는 작은 단면적) 가능하다.The wall 20 is formed with a base portion 24 having a larger cross-sectional area than that of the body 23 of the wall 20 at the bottom (if necessary, but smaller than the existing footing portion).

벽체(20)는 지간이 짧아 접속슬래브(40)가 상부 구조물(30)과 연결되지 않는 경우 상부 구조물(30)의 거동이 접속 슬래브(40)에 영향을 주지 않도록 분리벽(25)이 형성된다.The wall 20 is formed so that the behavior of the upper structure 30 does not affect the connecting slab 40 when the connecting slab 40 is not connected to the upper structure 30 because the staple is short .

또한 벽체(20)의 배면쪽에는 접속슬래브(40)를 지지하는 턱 형태의 거치부가 형성되는 것이 바람직하다.Further, it is preferable that a jaw-shaped mounting portion for supporting the connecting slab 40 is formed on the back side of the wall 20.

따라서, 신축용 봉함재(60)는 분리벽(25)의 앞쪽까지 설치된다.
Therefore, the sealing member 60 for expansion and contraction is installed up to the front of the separating wall 25. [

벽체(20)는 시공성의 향상을 위해 프리캐스트 콘크리트체가 바람직하며, 따라서 라멘교의 크기가 큰 경우 단일 콘크리트체를 사용하는 것이 비현실적이기 때문에 2개 이상의 블록이 결합되어 이루어지는 것이 바람직하고, 3가지 타입의 블록 즉 좌우측 블록과 중앙측 블록의 3가지 타입의 조합에 의해 이루어지는 것이 바람직하다.The wall 20 is preferably a precast concrete for improving the workability, and therefore, it is preferable that two or more blocks are combined because it is not realistic to use a single concrete body when the size of the rammen bridge is large. That is, a combination of three types of blocks, that is, left and right blocks and a center side block.

도 4에서 보이는 바와 같이, 좌측 블록(20-1)과 우측 블록(20-2)은 좌우측의 끝에 시공되고, 중앙측 블록(20-3)은 좌측 블록(20-1)과 우측 블록(20-2)의 사이에 개재되며, 여기서 각각 하나의 좌우측 블록(20-1,20-2) 사이에 한 개 이상의 중앙측 블록(20-3)을 적용함으로써 다양한 크기의 라멘교를 시공하는 이점이 있다. 참고로 도 5는 좌우측 블록(20-1,20-2)의 사이에 하나의 중앙측 블록(20-3)이 적용된 예시도이다.4, the left side block 20-1 and the right side block 20-2 are mounted on the left and right ends, the center side block 20-3 is mounted on the left side block 20-1 and the right side block 20-2, -2), wherein the advantage of constructing a ramen bridge of various sizes by applying one or more central side blocks 20-3 between each of the left and right blocks 20-1, 20-2 have. For reference, FIG. 5 is an example in which one central block 20-3 is applied between the left and right blocks 20-1 and 20-2.

좌우측 블록(20-1,20-2)과 중앙측 블록(20-3)은 모두 중공부(21)가 형성되며, 특히 이웃하는 것들과 서로 연통하도록 중앙측 블록(20-3)의 좌우 양측은 개방되고 좌측 블록(20-1)의 우측과 우측 블록(20-2)의 좌측은 중앙측 블록(20-3)의 내부와 연통하도록 개방된다. 즉, 좌측 블록(20-1)의 좌측과 우측 블록(20-2)의 우측은 각각 마감벽(26-1,26-2)에 의해 막히는 것이다.The left and right side blocks 20-1 and 20-2 and the center side block 20-3 are formed with a hollow portion 21 and are provided on both left and right sides of the center side block 20-3 Is opened and the right side of the left block 20-1 and the left side of the right block 20-2 are opened to communicate with the inside of the central block 20-3. That is, the left side of the left block 20-1 and the right side of the right block 20-2 are blocked by the closing walls 26-1 and 26-2, respectively.

또한 좌측 블록(20-1)의 우측과 우측 블록(20-2)의 좌측 및 중앙측 블록(20-3)의 좌우 양측에는 마감벽(26-1,26-2)보다 낮은 높이의 지지벽(27-1.27-2,27-3)이 형성될 수 있다. Further, on the right and left sides of the left and center blocks 20-3 of the right side and right side blocks 20-2 of the left block 20-1, (27-1-27-2, 27-3) may be formed.

지지벽(27-1.27-2,27-3)들의 사이(27-1,27-3)(27-3,27-2)에는 채움재가 채워지도록 공간이 형성될 수 있고 물론 지지벽(27-1.27-2,27-3)의 바닥은 채움재가 저부로 누출되지 않도록 바닥부가 형성된다.A space can be formed in the spaces 27-1, 27-3, 27-3, 27-2 between the support walls 27-1, 27-2, 27-3 so that the filler is filled, 1.27-2, and 27-3), a bottom portion is formed so that the filler does not leak to the bottom portion.

또한, 좌우측 블록(20-1,20-2)과 중앙측 블록(20-3)의 마주하는 부분에는 인터록킹을 위한 키와 홈이 구성되는 것이 바람직하다.
In addition, it is preferable that a key and a groove for interlocking are formed at the opposing portions of the left and right blocks 20-1 and 20-2 and the center block 20-3.

상부 구조물(30)의 거더(31)는 도 6 내지 도 8에서 보이는 바와 같이, 아치형상의 PCS 거더(도 6), 아치형상의 강합성 거더(도 7), 아치형상의 RC 거더(도 8)가 바람직하다. The girder 31 of the upper structure 30 preferably has an arcuate PCS girder (Fig. 6), an arched steel composite girder (Fig. 7) and an arched RC girder (Fig. 8) Do.

또한 지간이 짧아 아치형상의 거더가 적용되기 어려울 경우는 반단면 PC 슬래브도 적용이 가능하다. In addition, if it is difficult to apply arcuate girder due to short span, half-sided PC slab can be applied.

거더(31)는 길이방향의 양측 단부에 하부 플랜지[벽체(20)의 거치부(28)에 고무받침 설치 후 안착]가 형성되어 벽체(20)과 연결되는 우각부의 합성이 용이하고, 상부 바닥부(32)의 타설시 하면 거푸집 및 동바리의 배제를 가능케 하여 시공성을 향상하다.The girder 31 is formed at the both end portions in the longitudinal direction with a lower flange (after the rubber mount is mounted on the mount portion 28 of the wall body 20) When the part (32) is laid, the workability can be improved by allowing the exclusion of the formwork and the foot.

도 6의 아치형상의 PCS 거더는 본 출원인에 의해 특허(등록특허 제10-1260863호)받은 것으로, 지점부 선단에는 예컨대 "ㄷ"자 형상의 매입철근 일부가 돌출 형성되며, 길이방향에 걸쳐 플랜지가 형성되는데, 상기 플랜지는 지점부에서는 하부에 배치되는 한편 중앙부에서는 상부에 배치(경사부를 통해 연결)되어 벽체(20)와의 지점부에서 합성력을 증대함과 더불어 동바리와 비계가 필요 없어 시공이 간단하고, 긴장력이 도입되는 아치형 PCS빔으로 이루어진다.The arched PCS girder of Fig. 6 is a patent (Patent No. 10-1260863) filed by the applicant of the present invention. A portion of a reinforcing steel rod having a "C" shape protrudes at the tip of a fulcrum portion, The flange is disposed at the lower portion at the fulcrum portion and disposed at the upper portion (connected through the inclined portion) at the central portion to increase the composite force at the fulcrum portion with the wall body 20, , And an arcuate PCS beam into which a tension force is introduced.

물론, 거더(31)는 본 발명에서 예시되지 않은 다른 거더도 사용 가능하다.Of course, the girder 31 can be used as another girder which is not illustrated in the present invention.

상부 바닥부(32)는 거더(31)의 좌우 양측과 벽체(20)의 상부가 연결되는 우각부에 걸쳐 콘크리트 시공되어 이루어지며, 이때, 콘크리트가 소켓(50)의 내부를 통해 말뚝(10) 안에 타설됨으로써 말뚝(10)과 소켓(50) 및 상부 구조물(30)이 일체로 합성된다.The upper floor part 32 is constructed by placing concrete on the right and left sides of the girder 31 and the upper part of the wall body 20. The concrete is inserted into the pile 10 through the inside of the socket 50, So that the pile 10, the socket 50 and the upper structure 30 are integrally combined.

본 실시예는 벽체(20)가 거동하지 않기 때문에 벽체(20) 후방을 통상의 기술에 의해 뒷채움하며, 또한 거동이 가능하도록 일부 재료로만 뒷채움되지 않고 재료의 제약없이 뒷채움이 가능하다.
This embodiment backfills the rear of the wall 20 by conventional techniques because the wall 20 does not behave, and it is possible to backfill without restricting the material without being backfilled with only a part of materials so as to be able to behave.

접속슬래브(40)는 상부 구조물(30)의 연장선에 맞춰 벽체(20)의 상부에서부터 일정 거리만큼 이격된 노면에 걸쳐 시공되는 것으로, 예컨대 프리캐스트 콘크리트 패널, 현장 타설 모두가 가능하고, 벽체(20)의 분리벽(25)에서부터 시공된다.The connection slab 40 is installed on a road surface spaced a certain distance from the upper portion of the wall 20 in conformity with the extended line of the upper structure 30. For example, both the precast concrete panel and the field installation are possible, As shown in Fig.

접속슬래브(40) 상부에는 상부 구조물(30)과 연계하지 않는 포장층이 시공된다.On the upper part of the connecting slab 40, a packaging layer not in contact with the upper structure 30 is applied.

도 3과 도 9에서 보이는 것처럼, 소켓(50)은 말뚝(10)의 두부[종철근(12b)]가 삽입되는 홀(51)을 갖는 구조이며, 파형 강관(52)에 의해 홀(51)을 형성한 프리캐스트 콘크리트체이다. 3 and 9, the socket 50 is a structure having a hole 51 into which a head portion (longitudinal reinforcing bar 12b) of the pile 10 is inserted, and the hole 51 is formed by the corrugated steel pipe 52, Is a precast concrete body.

이와 같이 파형 강관(51)이 거푸집의 기능을 수행하여 홀(51)을 형성함에 따라 소켓(50)의 제조설비를 간소화하는 효과도 있다.As described above, the corrugated steel pipe 51 functions as a mold to form the hole 51, thereby simplifying the manufacturing facility of the socket 50. [

소켓(50)은 소켓 지지브래킷(미도시)을 통해 말뚝(10)에 일정 높이로 설치될 수 있다.The socket 50 may be installed at a predetermined height on the pile 10 through a socket support bracket (not shown).

상기 소켓 지지브래킷은 말뚝(10)의 파형 강관(11)의 둘레부에 용접 등으로 고정되어 소켓(50)을 저부에서 받쳐 지지하는 것으로, 파형 강관(11)의 둘레부 전체에 고정되는 링형, 상호 간에 일정 간격을 두고 고정되는 복수개도 가능하다. The socket support bracket is fixed to the periphery of the corrugated steel pipe 11 of the pile 10 by welding or the like and supports the socket 50 at the bottom. The socket support bracket is fixed to the entire circumference of the corrugated steel pipe 11, It is also possible to have a plurality of units fixed at regular intervals.

소켓(50)은 벽체(20) 내부에 삽입되어 말뚝(10)과 상부 구조물(30)을 합성하도록 하여 벽체(20)가 말뚝(10) 및 상부 구조물(30)과 합성되지 않도록 함으로써 벽체(20) 안에서 구조물의 거동이 가능하도록 한다.
The socket 50 is inserted into the wall 20 to allow the pile 10 and the upper structure 30 to be combined so that the wall 20 is not combined with the pile 10 and the upper structure 30, ) To allow the behavior of the structure within.

도 10a 내지 도 10h를 참조하여 본 실시예에 의한 라멘교의 시공 공법을 설명한다.The construction method of the ramen bridge according to the present embodiment will be described with reference to Figs. 10A to 10H.

1. 부지정지 및 말뚝 시공(도 10a).1. Site stop and pile construction (Fig. 10a).

라멘교의 시공을 위한 설계에 맞춰 하부 구조물을 시공할 지점부의 부지를 정리하고 말뚝(10)을 다음과 같이 시공한다.In accordance with the design for the construction of the ramen bridge, arrange the site of the place where the substructure is to be constructed and construct the pile (10) as follows.

공지의 천공기를 이용하여 지중에 말뚝공(1)을 천공하고, 말뚝공(1) 안에 파형 강관(11)과 철근(12)의 조립체를 삽입하며, 파형 강관(11) 안에 콘크리트를 타설하여 말뚝(10)을 완성하고, 말뚝(10)의 둘레부와 말뚝공(1) 사이에 시멘트 풀과 토사 등을 하부에서부터 그라우팅하여 말뚝(10)의 시공을 완료한다. 말뚝(10)의 시공시 말뚝공(1)의 천공은 강관의 케이싱을 사용하며 그라우팅을 완료한 후 상기 강관의 케이싱을 인발한다.A pile hole 1 is drilled in the ground by using a known perforator and an assembly of the corrugated steel pipe 11 and the reinforcing steel pipe 12 is inserted into the pile hole 1 and concrete is poured into the corrugated steel pipe 11, And completes the construction of the pile 10 by grouting the cement paste and the gravel between the periphery of the pile 10 and the pile 1. [ When piling (10) is installed, the piercing hole of the pile hole (1) uses the casing of the steel pipe and after the grouting is completed, the casing of the steel pipe is pulled out.

말뚝(10)의 파형 강관(11)과 종철근(12b)의 상부는 지면보다 상부로 돌출된다.The upper portions of the corrugated steel pipe 11 and the longitudinal reinforcing bars 12b of the pile 10 are protruded upward from the ground.

이와 같은 방법으로 라멘교의 구조에 맞는 수량의 말뚝(10)을 시공한다.
In this way, a pile (10) of a quantity suitable for the structure of the ramen bridge is constructed.

2. 터파기 및 벽체 설치(도 10b).2. Trencher and wall installation (Figure 10b).

필요한 경우 지면을 터파기하여 시공 공간을 확보하고, 지면 위에 버림콘크리트를 타설한 후 다음과 같이 벽체(20)를 설치한다. If necessary, tile the ground to secure a space for installation, and place concrete on the ground and place the wall (20) as follows.

벽체(20)을 인양하여 말뚝(10)의 상부로 운반하고, 말뚝 삽입공(22)과 말뚝(10)을 일치시킨 후 벽체(20)를 지면에 내려놓으면 말뚝(10)의 두부가 말뚝 삽입공(22)을 관통한다.
When the wall body 20 is lifted and carried to the upper part of the pile 10 and the pile inserting hole 22 and the pile 10 are aligned and the wall body 20 is lowered on the ground, And penetrates the hole 22.

3. 벽체 내 토사 채움 및 뒷채움(도 10c).3. Filling and backfilling the walls (Figure 10c).

벽체(20) 안의 중공부(21)에 토사 등의 채움재를 채우고 벽체(20) 뒤쪽에 뒷채움재를 채워 뒷채움한다. 토사 등의 채움재는 벽체(20)의 바닥보다 돌출된 파형 강관의 높이까지만 채워짐으로써 말뚝(10)의 거동이 가능하도록 한다. 벽체(20)는 거동하지 않기 때문에 벽체(20) 배면을 다짐에 의해 견고하게 뒷채움한다. 뒷채움은 접속슬래브(40)의 접속위치까지만 이루어진다.
The hollow portion 21 in the wall 20 is filled with a filler such as gravel and the back wall is filled with a back filler. The filler material such as gypsum is filled only up to the height of the corrugated steel pipe projecting from the bottom of the wall body 20 so that the pile 10 can be moved. Since the wall 20 does not move, the back surface of the wall 20 is firmly backed by compaction. Backfilling is performed only up to the connecting position of the connecting slab 40.

4. 신축 봉함 및 소켓 설치(도 10d).4. Install the new seal and socket (Fig. 10d).

벽체(20)의 내벽에 신축용 봉함재(60)를 설치하고, 말뚝(10)의 두부에 맞춰 소켓(50)을 설치하여 소켓(50)의 홀(51)에 말뚝(10)의 두부가 삽입되도록 한다.
A sealing material 60 for expansion and contraction is provided on the inner wall of the wall 20 and a socket 50 is provided so as to match the head of the pile 10 so that the head of the pile 10 is inserted into the hole 51 of the socket 50 .

5. 접속슬래브 설치(도 10e).5. Installation of the connecting slab (Figure 10e).

벽체(20)의 배면이면서 뒷채움부의 상부에 프리캐스트 콘크리트체인 접속슬래브(40)를 거치 시공하고, 접속슬래브(40)의 상부를 상부 구조물(30)의 포장층에 맞춰 포장하여 접속부 포장층(41)을 시공한다. 접속부 포장층(41)은 벽체(20)의 분리벽(25)에 의해 상부 구조물(30)과 합성되지 않는다. 여기서 접속부 포장층(41)은 상부 구조물(30)의 시공 후에 진행하는 것도 가능하다.
The precast concrete chain connecting slab 40 is mounted on the backside of the wall 20 and the upper part of the backfill so that the upper part of the connecting slab 40 is packed in accordance with the packing layer of the upper structure 30, ). The connecting portion packaging layer 41 is not combined with the superstructure 30 by the separating wall 25 of the wall 20. Here, the connection portion packaging layer 41 may be formed after the upper structure 30 is formed.

6. 상부 구조물 시공(도 10f, 도 10g, 도 10h).6. Construction of upper structure (Fig. 10F, Fig. 10G, Fig. 10H).

아치형 PCS 거더 등의 거더(31)를 벽체(20) 위에 거치하고(도 10f), 측면 거푸집을 설치한 후 콘크리트를 타설하며(도 10g), 콘크리트는 거더(31)의 상부와 거더(31)와 벽체(20)가 연결되는 우각부 및 소켓(50) 내부의 홀(51)에 타설되어 상부 구조물(30)과 소켓(50) 및 말뚝(10)은 일체로 합성되고, 벽체(20)는 말뚝(10)과 상부 구조물(30) 및 소켓(50)과 합성되지 않고 독립적으로 시공 상태를 유지한다.The concrete is installed on the upper portion of the girder 31 and the upper portion of the girder 31. In this case, the girder 31 is placed on the wall 20 (Fig. 10F) The upper structure 30, the socket 50 and the pile 10 are integrally formed by being inserted into the hole 51 in the socket 20 and the right corner where the wall 20 is connected and the hole 20 in the socket 50, The piles 10, the upper structure 30, and the sockets 50 are not combined with each other but maintained independently of each other.

콘크리트의 타설이 완료된 후 교면 포장을 통해 포장층을 시공한다(도 10h).
After the pouring of the concrete is completed, the pavement layer is constructed through the pavement pavement (FIG. 10H).

<실시예 2>&Lt; Example 2 >

도 11에서 보이는 바와 같이, 본 실시예에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교는, 상부 구조물(30)과 접속부를 일체로 합성하는 것을 특징으로 하며 상부 구조물(30)과 접속부(42)가 함께 콘크리트 시공되어 일체로 합성됨으로써 실시예 1보다 장지간의 라멘교에 적합하다.As shown in FIG. 11, the precast concrete wall according to the present embodiment and the non-alternating ramen bridge using the pile are characterized in that the upper structure 30 and the connecting portion are integrally formed, and the upper structure 30 and the connecting portion 42) are integrally combined with each other by concrete construction.

말뚝(10), 벽체(20), 거더(31), 소켓(50)은 실시예 1과 동일하며 단, 본 실시예의 벽체(20)는 실시예 1의 분리벽을 포함하지 않는 구조이다.The pile 10, the wall 20, the girder 31 and the socket 50 are the same as those of the first embodiment except that the wall 20 of the present embodiment does not include the separation wall of the first embodiment.

본 실시예는 상부 구조물(30)과 접속부(42)가 일체형이기 때문에 함께 거동하며, 따라서, 접속부(42)의 단부에 신축용 봉함재(43)가 설치된다.Since the upper structure 30 and the connecting portion 42 are integral with each other, the present embodiment behaves together, and therefore, the sealing member 43 for expansion and contraction is provided at the end of the connecting portion 42. [

도면 중 미설명 부호 44는 프리캐스트 콘크리트체인 접속슬래브(40)를 설치 및 지지하기 위한 기초블록이고, 45는 신축용 봉함재(43)의 다음에 설치되는 접속부 저판이다.In the drawing, reference numeral 44 denotes a base block for installing and supporting the precast concrete chain connecting slab 40, and 45 is a bottom plate of a connecting portion provided next to the expandable sealing member 43.

본 실시예에 의한 시공 공법은, 실시예 1과 비교하면 상부 구조물의 바닥부(32)를 시공할 때 뒷채움부 상측의 접속부(42)도 함께 콘크리트 시공하는데 차이가 있고 그 이외의 공정은 동일하다.
Compared with the first embodiment, the construction method according to the present embodiment differs from the first embodiment in that concrete is applied to the connection portion 42 on the upper side of the backfill when the bottom portion 32 of the upper structure is constructed, and the other processes are the same .

<실시예 3>&Lt; Example 3 >

도 12에서 보이는 바와 같이, 본 실시예에 의한 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교는, 말뚝(10)에 의한 강성이 충분하고 구조물의 거동이 크지 않은 조건에 적합한 것으로 실시예 1,2의 소켓(50)이 사용되지 않으며 상부 구조물(30)의 바닥부(32)를 콘크리트 시공할 때 콘크리트가 벽체(20)의 중공부 안에 말뚝(10)과 합성되도록 타설됨으로써 말뚝(10)과 벽체(20) 및 상부 구조물(30) 모두가 일체로 합성된다.As shown in FIG. 12, the precast concrete wall and the non-alternating ramming bridge using the pile according to the present embodiment are suitable for conditions in which the rigidity due to the pile 10 is sufficient and the behavior of the structure is not large, 2 is not used and concrete is applied to the bottom portion 32 of the upper structure 30 so that the concrete is combined with the pile 10 in the hollow portion of the wall 20, Both the wall 20 and the superstructure 30 are integrated together.

따라서, 본 실시예에서 접속부(42)는 상부 구조물(30)과 분리 시공되며, 프리캐스트 콘크리트의 접속슬래브(40)와 접속부 포장층(41)으로 구성된다.
Therefore, in the present embodiment, the connecting portion 42 is separated from the upper structure 30, and is composed of the connecting slab 40 of the precast concrete and the connecting packing layer 41.

1 : 말뚝공,
10 : 말뚝, 11 : 파형 강관
12 : 철근, 13 : 콘크리트
20 : 콘크리트 벽체 21 : 중공부
22 : 말뚝 삽입공, 23 : 옹벽몸체
24 : 기초부, 25 : 분리벽
30 : 상부 구조물, 31 : 거더
32 : 상부 바닥부, 40 : 접속슬래브
50 : 소켓,
1: pile balls,
10: pile, 11: corrugated steel pipe
12: reinforcing steel, 13: concrete
20: concrete wall body 21: hollow part
22: pile insertion hole, 23: retaining wall body
24: base portion, 25: separating wall
30: superstructure, 31: girder
32: upper floor, 40: connecting slab
50: socket,

Claims (15)

저부가 지중에 근입되는 한편 두부가 지면 위로 돌출되도록 하천 또는 도로 양쪽의 서로 마주하는 변에 각각 시공되는 하나 이상의 말뚝(10)과;
내부에 중공부(21) 및 하나 이상의 말뚝 삽입공(22)이 형성되어 이루어지며, 상기 말뚝 삽입공을 통해 상기 말뚝의 두부가 상부로 관통되도록 시공되는 프리캐스트 콘크리트 벽체(20)와;
홀이 구비된 콘크리트체이며 상기 프리캐스트 콘크리트 벽체의 중공부에 거동이 가능하도록 장착되면서 상기 홀을 통해 상기 말뚝의 두부가 내부에 삽입되는 소켓(50)과;
하천 또는 도로를 횡단하는 방향으로 배열되면서 종방향의 양측이 상기 프리캐스트 콘크리트 벽체 위에 거치되는 거더(31),
상기 소켓의 내부, 상기 소켓의 상부와 상기 거더가 연결되는 지점부 및 상기 거더의 상부에 걸쳐 콘크리트 시공되는 바닥부(32)를 통해 상기 말뚝 및 소켓과 일체로 합성되는 상부 구조물(30)과;
상기 상부 구조물 위에 시공되는 포장층을 포함하여 이루어지며, 상기 프리캐스트 콘크리트 벽체가 거동하지 않는 상태에서 상기 말뚝과 상기 상부 구조물이 상기 프리캐스트 콘크리트 벽체 안에서 거동하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.
At least one pile (10) installed at the opposite sides of the river or road so that the bottom part projects into the ground and the head part protrudes above the ground;
A precast concrete wall body 20 having a hollow portion 21 and at least one pile insertion hole 22 formed therein and constructed to penetrate the head portion of the pile through the pile insertion hole;
A socket (50) mounted on the hollow part of the precast concrete wall so as to be movable and having a head of the pile inserted into the hole through the hole;
A girder (31) arranged on the precast concrete wall with both longitudinal sides thereof arranged in a direction transverse to a river or a road,
An upper structure 30 integrally formed with the pile and the socket through the bottom of the socket, the upper portion of the socket and the fulcrum to which the girder is connected and the upper portion of the girder;
And a pavement layer formed on the upper structure, wherein the pile and the upper structure behave in the precast concrete wall in a state in which the precast concrete wall does not move. The non - alternating ramen bridge using.
저부가 지중에 근입되는 한편 두부가 지면 위로 돌출되도록 하천 또는 도로 양쪽의 서로 마주하는 변에 각각 시공되는 하나 이상의 말뚝(10)과;
내부에 중공부(21) 및 하나 이상의 말뚝 삽입공(22)이 구비되어 이루어지며, 상기 말뚝 삽입공에 상기 말뚝의 두부가 상부로 관통되는 프리캐스트 콘크리트 벽체(20)와;
하천 또는 도로를 횡단하는 방향으로 배열되면서 종방향의 양측이 상기 프리캐스트 콘크리트 벽체 위에 거치되는 거더(31), 상기 프리캐스트 콘크리트 벽체의 내부, 상기 프리캐스트 콘크리트 벽체의 상부와 상기 거더가 연결되는 지점부 및 상기 거더의 상부에 걸쳐 콘크리트 시공되는 바닥부(32)를 통해 상기 말뚝 및 프리캐스트 콘크리트 벽체와 일체로 합성되는 상부 구조물(30)과;
상기 상부 구조물 위에 시공되는 포장층을 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.
At least one pile (10) installed at the opposite sides of the river or road so that the bottom part projects into the ground and the head part protrudes above the ground;
A precast concrete wall 20 having a hollow portion 21 and at least one pile insertion hole 22 therein and having a head portion of the pile penetrated through the pile insertion hole;
A girder (31) arranged on the precast concrete wall with both longitudinal sides thereof being arranged in a direction transverse to a river or a road, an inside of the precast concrete wall, a point where the upper part of the precast concrete wall and the girder are connected An upper structure 30 integrally formed with the pile and the precast concrete wall through a bottom portion 32 that is constructed of concrete over an upper portion of the girder;
And a pavement layer formed on the upper structure. The pre-cast concrete wall and the pile-based non-alternating ramen bridge.
청구항 1에 있어서, 상기 소켓의 둘레부와 상기 프리캐스트 콘크리트 벽체의 내주면 사이에 장착되며 상기 소켓의 거동을 흡수하는 신축용 봉함재(60)를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.The pneumatic tire according to claim 1, further comprising a sealing member (60) mounted between the periphery of the socket and the inner circumferential surface of the precast concrete wall to absorb the behavior of the socket, Using non-alternating ramen bridge. 청구항 1 또는 청구항 3에 있어서, 상기 소켓과 말뚝의 거동이 가능하도록 상기 프리캐스트 콘크리트 벽체의 중공부에 채워지는 비콘크리트 재질의 채움재를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.The precast concrete wall as claimed in claim 1 or 3, further comprising a filling material filled in the hollow portion of the precast concrete wall so that the socket and the pile can be moved. Ramen Bridge. 청구항 1에 있어서, 상기 상부 구조물의 종방향 양측과 연계하는 접속부를 포함하되, 상기 접속부는 상기 프리캐스트 콘크리트 벽체에 형성된 분리벽(25)을 통해 상기 상부 구조물과 분리 시공되거나 상기 상부 구조물과 일체로 합성 시공되는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.The precast concrete wall as claimed in claim 1, further comprising a connecting portion in connection with both longitudinal sides of the upper structure, wherein the connecting portion is separated from the upper structure through a separating wall (25) formed in the precast concrete wall, And the pre - cast concrete wall and the pile. 청구항 1에 있어서, 상기 소켓은 파형 강관(52)에 의해 내주면이 파형 단면으로 이루어지면서 내부에 상기 홀(51)이 형성되는 프리캐스트 콘크리트체인 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.The pre-cast concrete wall as claimed in claim 1, wherein the socket is a pre-cast concrete having a corrugated inner peripheral surface formed by a corrugated steel pipe (52) and the hole (51) formed therein. Ramen Bridge. 청구항 1 또는 청구항 2에 있어서, 상기 프리캐스트 콘크리트 벽체는, 각각 상부를 향해 개방되는 중공부와 상기 중공부와 연통하도록 바닥부에 말뚝 삽입공이 구비된 좌우측 블록(20-1,20-2) 및 상기 좌우측 블록의 사이에 개재되는 하나 이상의 중앙측 블록(20-3)에 의해 이루어지는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.The precast concrete wall according to claim 1 or 2, wherein the precast concrete wall comprises left and right blocks (20-1, 20-2) each having a hollow portion opened toward the upper portion and a pile insert hole at the bottom portion to communicate with the hollow portion, And one or more central blocks (20-3) interposed between the left and right blocks. The pre-cast concrete wall and the non-alternating ramen bridge using the pile. 청구항 1 또는 청구항 2에 있어서, 상기 말뚝은 파형 강관(11), 상기 파형 강관 내부에 삽입 장착되는 철근(12) 및 상기 파형 강관의 내부에 타설되는 콘크리트(13)로 이루어진 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교. The pile according to claim 1 or 2, wherein the pile comprises a corrugated steel pipe (11), a reinforcing bar (12) inserted into the corrugated steel pipe, and a concrete (13) Non - alternating ramen bridge using concrete wall and pile. 청구항 1 또는 청구항 2에 있어서, 상기 거더는 아치형상의 PC 거더, 아치형상의 강합성 거더, 아치형상의 RC 거더 중 어느 하나이며, 상기 아치형상의 PC 거더는, 지점부 선단에서 매입철근 일부가 돌출 형성되며 지점부에서는 하부에 배치되는 한편 중앙부에는 상부에 배치되도록 플랜지가 구비된 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교.The girder according to claim 1 or 2, wherein the girder is one of an arched PC girder, an arched steel composite girder, and an arched RC girder, wherein the arched PC girder has a portion And a flange is provided at an upper portion of the center portion of the concrete pile. 하천 또는 도로 변의 부지 정지 후 말뚝(10)을 시공하되, 상기 말뚝의 하부가 지중에 근입되고 두부가 지면 위에 돌출되도록 시공하는 제1단계와;
상기 제1단계를 통해 설치된 말뚝의 두부가 바닥부에서부터 내부에 관통되도록 프리캐스트 콘크리트 벽체를 시공하는 제2단계와;
상하로 관통하는 홀이 구비된 소켓을 상기 프리캐스트 콘크리트 벽체 안에 삽입 장착하여 상기 소켓의 홀 안에 상기 말뚝의 두부가 삽입되도록 하는 제3단계와;
상기 제3단계 이후 상기 프리캐스트 콘크리트 벽체의 배면을 뒷채움하는 제4단계와;
상기 제4단계를 통해 시공된 상기 프리캐스트 콘크리트 벽체의 상부에 거더(31)를 거치하고, 상기 소켓의 내부, 상기 소켓의 상부와 상기 거더가 연결되는 지점부, 상기 거더 상부를 콘크리트를 타설하여 상기 말뚝 및 상기 소켓과 일체로 합성되도록 상부 바닥부(32)를 시공하는 제5단계와;
상기 제5단계를 통해 시공된 상부 구조물의 노면을 포장하는 제6단계를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 시공 공법.
A first step of constructing a pile (10) after stopping a river or a side of a road, wherein a lower portion of the pile is inserted into the ground and a head is projected onto the ground;
A second step of constructing the precast concrete wall so that the head of the pile installed through the first step penetrates from the bottom to the inside;
A third step of inserting a socket having holes penetrating up and down into the precast concrete wall to insert the head of the pile into the hole of the socket;
A fourth step of backfilling the back surface of the precast concrete wall after the third step;
The pre-cast concrete wall constructed through the fourth step is placed on the upper part of the girder 31, and the inside of the socket, the upper part of the socket and the point where the girder is connected, A fifth step of constructing an upper floor part (32) so as to be integrated with the pile and the socket;
And a sixth step of packing the road surface of the upper structure constructed through the fifth step. The pre-cast concrete wall and the pile-based non-alternating ramen bridge construction method.
청구항 10에 있어서, 상기 제3단계는 상기 소켓의 둘레부와 상기 프리캐스트 콘크리트 벽체의 내주면 사이에 신축용 봉함재를 장착하여 상기 소켓의 거동이 가능하도록 하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 시공 공법.The pre-cast concrete wall and the pile according to claim 10, wherein in the third step, a sealing member for expansion and contraction is mounted between the periphery of the socket and the inner circumferential surface of the precast concrete wall, Construction method of non - alternating ramen bridge using. 청구항 10 또는 청구항 11에 있어서, 상기 제4단계는 상기 프리캐스트 콘크리트 벽체의 배면을 뒷채움한 후, 상기 뒷채움부의 상측에 접속부를 시공하되, 상기 프리캐스트 콘크리트 벽체의 상부에 형성된 분리벽의 바깥쪽에 접속부를 시공하여 상기 접속부를 상기 상부 구조물과 분리되도록 시공하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 시공 공법.The method as claimed in claim 10 or 11, wherein, in the fourth step, after backing the back surface of the precast concrete wall, a connecting portion is formed on the back side of the backfill, And the connecting part is separated from the upper structure. The method of claim 1, wherein the pre-cast concrete wall and the pile are used as a bridge. 청구항 10 또는 청구항 11에 있어서, 상기 제5단계는 상기 바닥부의 콘크리트 타설시 상기 뒷채움부 상층에 접속부를 함께 콘크리트 타설하여 상기 상부 구조물과 상기 접속부를 일체로 합성하면서 상기 접속부의 단부에 신축용 봉함재를 장착하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 시공 공법.The method according to claim 10 or 11, wherein, in the step of placing the concrete in the bottom part, concrete is put together with the connection part in the upper layer of the backfill to synthesize the upper structure and the connection part integrally, Which is characterized in that the pre-cast concrete wall and the pile are used. 하천 또는 도로 변의 부지 정지 후 말뚝(10)을 시공하되, 상기 말뚝의 하부가 지중에 근입되고 두부가 지면 위에 돌출되도록 시공하는 제1단계와;
상기 제1단계를 통해 설치된 말뚝의 두부가 바닥부에서부터 내부에 관통되도록 프리캐스트 콘크리트 벽체를 시공하는 제2단계와;
상기 제2단계 이후 상기 프리캐스트 콘크리트 벽체의 배면을 뒷채움하는 제3단계와;
상기 제3단계를 통해 시공된 상기 프리캐스트 콘크리트 벽체의 상부에 거더(31)를 거치하고, 상기 프리캐스트 콘크리트 벽체의 내부, 상기 프리캐스트 콘크리트 벽체의 상부와 상기 거더가 연결되는 지점부, 상기 거더 상부를 콘크리트를 타설하여 상기 말뚝 및 프리캐스트 콘크리트 벽체와 일체로 합성되도록 상부 바닥부(32)를 시공하는 제4단계와;
상기 제4단계를 통해 시공된 상부 구조물의 노면을 포장하는 제5단계를 포함하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 시공 공법.
A first step of constructing a pile (10) after stopping a river or a side of a road, wherein a lower portion of the pile is inserted into the ground and a head is projected onto the ground;
A second step of constructing the precast concrete wall so that the head of the pile installed through the first step penetrates from the bottom to the inside;
A third step of backfilling the back surface of the precast concrete wall after the second step;
The girder (31) is placed on the upper part of the precast concrete wall constructed through the third step, and the inner part of the precast concrete wall, the point part where the upper part of the precast concrete wall is connected to the girder, A fourth step of constructing the upper floor part 32 so as to be integrated with the pile and the precast concrete wall by pouring concrete into the upper part;
And a fifth step of paving the road surface of the upper structure constructed through the fourth step. The method for constructing a non-alternating ramming bridge using a precast concrete wall and a pile.
청구항 10 또는 청구항 15에 있어서, 상기 제1단계는 지중에 말뚝공을 천공하고, 상기 말뚝공 안에 철근이 내장된 파형 강관(11)을 근입하며, 상기 파형 강관의 내부에 콘크리트를 채운 후 상기 파형 강관의 외부를 그라우팅하여 말뚝(10)을 시공하는 것을 특징으로 하는 프리캐스트 콘크리트 벽체와 말뚝을 이용한 무교대 라멘교 시공 공법.The method according to claim 10 or 15, wherein the first step comprises drilling a pile hole in the ground, inserting a corrugated steel pipe (11) having reinforcing bars in the pile hole, filling the corrugated steel pipe with concrete, And a pile (10) is formed by grouting the outer surface of the steel pipe. A method for constructing a non-alternating ramen bridge using a precast concrete wall and a pile.
KR1020150008893A 2015-01-19 2015-01-19 Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same KR101772939B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150008893A KR101772939B1 (en) 2015-01-19 2015-01-19 Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150008893A KR101772939B1 (en) 2015-01-19 2015-01-19 Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same

Publications (2)

Publication Number Publication Date
KR20160089215A true KR20160089215A (en) 2016-07-27
KR101772939B1 KR101772939B1 (en) 2017-08-30

Family

ID=56617105

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150008893A KR101772939B1 (en) 2015-01-19 2015-01-19 Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same

Country Status (1)

Country Link
KR (1) KR101772939B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853381A (en) * 2019-01-31 2019-06-07 沈阳建筑大学 A kind of transition structure and its construction method preventing and treating bumping at bridge-head
CN110847162A (en) * 2019-12-21 2020-02-28 福州大学 Novel combined pile foundation structure suitable for integral bridge and construction method thereof
KR102142633B1 (en) * 2019-09-27 2020-08-07 주식회사 길교이앤씨 Accelerated construction method of integral abutment bridge and chambered precast segment wall applied to the same
KR102181805B1 (en) * 2019-10-21 2020-11-24 (주)지승씨앤아이 Precast concrete abutment/pier block unit for jointless bridge and Construction method of jointless bridge using thereof
KR102316098B1 (en) * 2021-04-13 2021-10-22 주식회사 누리플랜 An abutment structure using and reinforced concrete construction method precast concrete block
KR102316106B1 (en) * 2021-04-13 2021-10-22 주식회사 누리플랜 A bridge structure using precast concrete block

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102244029B1 (en) 2020-07-02 2021-04-23 정해용 Rahmen bridge without abuttment and construction method thereof
KR102617262B1 (en) * 2023-06-28 2023-12-27 주식회사 제이콥스 Construction method of integrated girder without abutment and girder constructed by this method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100983861B1 (en) 2008-02-20 2010-09-28 주식회사 동성엔지니어링 Integral composite slab bridge without abutments, supports, and expansion joints, and construction method thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101216511B1 (en) * 2011-01-06 2012-12-31 주식회사 길교이앤씨 Method for constructing a abutment of integral abutment bridge
KR101410443B1 (en) * 2013-04-17 2014-06-20 주식회사 인우 (Inwoo.Co.Ltd) Multipurpos precast concrete block and retaining wall using the same

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100983861B1 (en) 2008-02-20 2010-09-28 주식회사 동성엔지니어링 Integral composite slab bridge without abutments, supports, and expansion joints, and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853381A (en) * 2019-01-31 2019-06-07 沈阳建筑大学 A kind of transition structure and its construction method preventing and treating bumping at bridge-head
CN109853381B (en) * 2019-01-31 2024-03-05 沈阳建筑大学 Transitional structure for preventing bridge head from jumping and construction method thereof
KR102142633B1 (en) * 2019-09-27 2020-08-07 주식회사 길교이앤씨 Accelerated construction method of integral abutment bridge and chambered precast segment wall applied to the same
KR102181805B1 (en) * 2019-10-21 2020-11-24 (주)지승씨앤아이 Precast concrete abutment/pier block unit for jointless bridge and Construction method of jointless bridge using thereof
CN110847162A (en) * 2019-12-21 2020-02-28 福州大学 Novel combined pile foundation structure suitable for integral bridge and construction method thereof
KR102316098B1 (en) * 2021-04-13 2021-10-22 주식회사 누리플랜 An abutment structure using and reinforced concrete construction method precast concrete block
KR102316106B1 (en) * 2021-04-13 2021-10-22 주식회사 누리플랜 A bridge structure using precast concrete block

Also Published As

Publication number Publication date
KR101772939B1 (en) 2017-08-30

Similar Documents

Publication Publication Date Title
KR101772939B1 (en) Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same
CN107542115B (en) Underground engineering waterproof structure and construction method thereof
JP5055249B2 (en) Multiple tunnel construction method and multiple tunnel structure
KR100640716B1 (en) Precast concrete block for cantilever retaining wall and construction method using the same
KR101710075B1 (en) PC Method for constructing underground structure having Precast wall using Hpile and underground structure constructed by the same
KR20140047924A (en) Construction method of cast-in-place step retaining wall using pc panel needless of concrete forms for slope reinforcement
CN105421497A (en) Water-proof construction method for connected nodes of foundation slab and ground wall in composite surround system
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
JP4881555B2 (en) Construction method of underground structure
CN113217022B (en) Construction method of weak surrounding rock tunnel cave collapse foam concrete backfill structure
KR101653606B1 (en) Method for constructing integral abutment bridge
KR101902791B1 (en) Under ground structure construction method using composite steel pile and under ground structure therewith
KR101902786B1 (en) Under ground structure construction method using composite sheet pile and under ground structure therewith
KR20150043913A (en) Biased soil pressure reinforcement rigid-frame bridge and construction method of the same
KR101101927B1 (en) Construction method of basement wall using the precast concrete member
KR102079570B1 (en) Soil nailing slope reinforcement system to panel
KR101710718B1 (en) Method for connecting precast wall and slab, and underground structure constructed by the same
KR101696282B1 (en) Precast wall using soil interception pile, underground structure having Precast wall and Method for connecting precast wall
KR100499338B1 (en) Conduit using phc pile
KR101973657B1 (en) Inverted Arcuate Structure to prevent Lateral Flow of the Bridge Abutments and Reparing Method using the Same
KR101710716B1 (en) Underground structure having Precast wall using H­pile
CN109667278A (en) Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing
KR101288602B1 (en) Underpass using precast concrete pile and method for constructing the same
KR101664103B1 (en) PC Underground structure having Precast wall using Hpile
KR102613254B1 (en) Self-standing fixing type pile and construction method of earth retaining facilities including it

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant