JP2001241013A - Staging erection method in high pier - Google Patents

Staging erection method in high pier

Info

Publication number
JP2001241013A
JP2001241013A JP2000054205A JP2000054205A JP2001241013A JP 2001241013 A JP2001241013 A JP 2001241013A JP 2000054205 A JP2000054205 A JP 2000054205A JP 2000054205 A JP2000054205 A JP 2000054205A JP 2001241013 A JP2001241013 A JP 2001241013A
Authority
JP
Japan
Prior art keywords
scaffold
steel pipe
staging
bracket
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000054205A
Other languages
Japanese (ja)
Other versions
JP3788167B2 (en
Inventor
Masao Fukui
真男 福井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2000054205A priority Critical patent/JP3788167B2/en
Publication of JP2001241013A publication Critical patent/JP2001241013A/en
Application granted granted Critical
Publication of JP3788167B2 publication Critical patent/JP3788167B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a staging erection method in a high pier of steel pipe or the like that enables easy and sure installation or removal of staging to or from a pier structure of a steel pipe or the like when construction requires. SOLUTION: By tilting a receiving bracket 10 that can be tilted at least upward or downward, a staging S can be mounted to, and is fastened to a pier structural material P, the staging S can be hangingly installed or removed along the pier structural material P without splitting the staging S concerned, when installing or removing the staging S.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は橋梁下部構造物のう
ち橋脚を施工するにあたり、所定長の鋼管や鉄筋等を建
て込み、或いは継ぎ足す作業を繰り返す際に必要な仮設
足場の設置・運用方法である高橋脚における足場工法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of installing and operating a temporary scaffold necessary for repeatedly constructing or adding steel pipes and reinforcing bars of a predetermined length when constructing a pier of a bridge substructure. On scaffolding method at Takahashi pier.

【0002】[0002]

【従来の技術】島嶼部と本州とを結ぶ長大橋やあるいは
山間の橋梁等においては、その設置状況からして高橋脚
である場合が多いが、このような高橋脚を施工するには
所定長の鋼管を井筒状に配置して上方に継ぎ足し設置し
たり、或いは基礎コンクリート部分から立ち上げた鉄筋
を橋脚構造の完工に伴って上方に継ぎ足したりといった
繰り返し作業が行われることになる。
2. Description of the Related Art Long bridges or mountain bridges connecting islands and Honshu are often high piers due to their installation status. Such work is repeated, such as disposing the steel pipes in a well shape and adding and installing them upward, or adding reinforcing steel that has been started up from the foundation concrete part upwards with the completion of the pier structure.

【0003】このような作業を行うには橋脚外周に仮設
される環状の足場が上下数段に亘って必要とされる。例
えば上中下の3段の足場が鋼管外周に設けられた場合、
上段足場は次工程の鋼管と建込み済みの鋼管とを溶接す
る作業や鉄筋の建込み・組立作業に主に使用され、中段
及び下段の足場は鉄筋の建込み・組立作業の他、橋脚の
表面処理、各種撤去作業等に供せられるといった具合で
ある。
[0003] In order to perform such a work, an annular scaffold temporarily provided on the outer periphery of the pier is required over several vertical steps. For example, if three stages of upper, middle and lower scaffolds are provided on the outer circumference of the steel pipe,
The upper scaffold is mainly used for welding the steel pipe and the built steel pipe in the next process and for the construction and assembling work of the rebar. The middle and lower scaffolds are used for the construction and assembling of the rebar, It can be used for surface treatment and various removal operations.

【0004】従来この足場は、前記鋼管等の表面に溶接
固定されたブラケット上に載置・固定されることとなっ
ていた。
Conventionally, this scaffold has been mounted and fixed on a bracket welded to the surface of the steel pipe or the like.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、従来の
足場工法にあっては前記ブラケットが固定されたもので
あり、なんらの可動性も備えていなかった。したがっ
て、上記足場を設置あるいは撤去するに際して、各足場
間の最小距離やブラケット形状などに応じて足場を予め
分割しなければ設置や撤去を実行することすら非常に困
難であった。このような状況下で例えば数段の足場を設
置或いは撤去しようと試みると、中間段の足場を設置あ
るいは撤去する場合など、上方の足場と下方の足場との
距離をはかりつつ側方から足場材を滑り入れる(或い
は、出す)といった煩雑で微妙な作業が要求されてい
た。このため、中間段の足場の設置を見送られることも
あった。
However, in the conventional scaffolding method, the bracket is fixed and has no mobility. Therefore, when installing or removing the scaffold, it is very difficult even to install or remove the scaffold unless the scaffold is divided in advance according to the minimum distance between the scaffolds, the bracket shape, and the like. Under such circumstances, for example, when trying to install or remove several steps of scaffolds, when installing or removing intermediate steps of scaffolding, etc., the scaffolding material must be measured from the side while measuring the distance between the upper and lower scaffolds. A complicated and delicate operation such as sliding in (or out) of the robot has been required. For this reason, installation of the intermediate scaffold was sometimes forgotten.

【0006】また、固定された複数のブラケットに対し
て足場を確実に設置するには、かなり正確な位置合わせ
が必要であるにもかかわらず、上記のような施工の難し
さと相まって重量物である足場を効率よく位置決めする
ことは困難であった。そのため、一度ブラケット上に足
場を載置した後に位置不整合が確認され、再度位置決め
と固定作業とを行わなければならないといった問題も頻
発していた。
[0006] Further, in order to reliably install the scaffold with respect to a plurality of fixed brackets, although it is necessary to perform fairly accurate positioning, it is heavy due to the above-mentioned difficulty in construction. It has been difficult to position the scaffold efficiently. For this reason, there has been a frequent problem that a positional mismatch is confirmed after the scaffold is once placed on the bracket, and the positioning and fixing work must be performed again.

【0007】しかして、上述のように煩雑かつ微妙な作
業を仮設作業に要していたのでは、本工事に与えるコス
ト上、工期上の悪影響は図り知れず、このことが施工環
境の悪化を顧みない足場段数の低減にもつながって、施
工サイクル中に効率低下の悪循環を生み出す素因ともな
っていた。
[0007] However, if the temporary work requires complicated and delicate work as described above, the cost of this work and the adverse effect on the construction period cannot be overestimated, and this deteriorates the construction environment. This led to an unneeded reduction in the number of scaffolding steps, which was a predisposition to creating a vicious cycle of reduced efficiency during the construction cycle.

【0008】そこで、本発明はこのような従来の課題に
着目してなされたもので、施工上の必要に応じ簡便確実
に、鋼管等の橋脚構造物に足場を設置或いは撤去するこ
とを可能にする高橋脚における足場工法を提供するもの
である。
Accordingly, the present invention has been made in view of such a conventional problem, and it has become possible to easily and surely install or remove a scaffold on a pier structure such as a steel pipe as required in construction. To provide a scaffolding method for high piers.

【0009】[0009]

【課題を解決するための手段】この発明は上記目的を達
成するためになされたもので、鋼管等の構造材を適宜継
ぎ足して橋脚を施工するにあたり、この施工用の足場を
仮設する足場工法であって、少なくとも上下いずれか一
方に回倒可能でかつ前記足場を載置可能であり、前記構
造材上に固設された受けブラケットを、前記足場の設置
または撤去作業を行う場合に回倒させることにより、足
場を分割することなく構造材に沿って吊り込み設置また
は撤去可能であることを特徴とする。
Means for Solving the Problems The present invention has been made to achieve the above-mentioned object, and when a pier is constructed by appropriately adding structural members such as steel pipes, a scaffolding method for temporarily providing a scaffold for this construction is provided. And at least one of the upper and lower sides can be turned over and the scaffold can be placed, and the receiving bracket fixed on the structural material is turned over when the scaffold is installed or removed. Thereby, it can be suspended and installed or removed along the structural material without dividing the scaffold.

【0010】[0010]

【発明の実施の形態】以下、本発明の好ましい実施の形
態につき、添付図面を参照して詳細に説明する。図1は
本発明の高橋脚における足場工法において用いられる受
けブラケット10の構造を示す説明図である。この受け
ブラケット10は、鋼管などの橋脚構造体Pに取付け治
具11を介して取り付けられるものであり、係る治具1
1との取り合い部分12を回転式とすることで、少なく
とも上下いずれかに回倒可能な構造を備えている。前記
取り合い部分12は、例えば治具11本体に鋼棒を打設
して回倒基点12aとしたピン接合構造をなしており、
この取り合い部分12の先には足場Sを実際に上載する
アーム状の受け部材13が存する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. FIG. 1 is an explanatory view showing the structure of a receiving bracket 10 used in the scaffolding method for a high pier according to the present invention. The receiving bracket 10 is mounted on a pier structure P such as a steel pipe via a mounting jig 11.
By making the connecting portion 12 with 1 a rotary type, a structure is provided that can be turned at least up and down. The connecting portion 12 has, for example, a pin-joining structure in which a steel rod is driven into the jig 11 main body and the turning base 12a is formed.
An arm-shaped receiving member 13 on which the scaffold S is actually mounted is present at the end of the connecting portion 12.

【0011】このような構造を備えた受けブラケット1
0が足場設置が予定される鋼管P上に複数取付けられる
訳だが、その設置数と間隔とについては載置される足場
Sの重量や足場S上に負荷される載荷重等を考慮して工
事状況に応じ決定される。
Receiving bracket 1 having such a structure
Although 0 means that a plurality of scaffolds are to be installed on the steel pipe P on which the scaffold is to be installed, the number and spacing of the installations are taken into account in consideration of the weight of the scaffold S to be placed, the load applied to the scaffold S, and the like. Determined according to the situation.

【0012】受けブラケット10における受け部材13
を回倒させる際には、例えば取り合い部分12の固定ピ
ン12b(回倒基点12aではないもの)を抜去すれば
よく、一方回倒していた受け部材13を引き起こして固
定する際には、回倒基点12aのピンを中心に受け部材
13を上方に引き上げて、取付け治具11と連通するよ
う前記固定ピン12bを打設すればよいのである。以
下、実際に2段の鋼管を継ぎ足す作業を想定し、その手
順を説明する。
The receiving member 13 of the receiving bracket 10
For example, the fixing pin 12b (not the turning base 12a) of the engaging portion 12 may be pulled out. When the receiving member 13 that has been turned down is raised and fixed, The receiving member 13 may be pulled up around the pin at the base point 12a, and the fixing pin 12b may be driven so as to communicate with the mounting jig 11. Hereinafter, the procedure will be described assuming an operation of actually adding two-stage steel pipes.

【0013】図2は本発明の高橋脚における足場工法に
よる鋼管継ぎ足し作業の第1ステップを示す説明図であ
り、図3は同第2ステップを、図4は同第3ステップを
示す説明図である。ここで使用される鋼管は例えば”定
尺もの”と言われる規格サイズの鋼管が一般的であり、
直径900mm〜2000mm、長さは10m前後のも
のが多い。この鋼管を例えばコンクリート製の橋脚基礎
(地下あるいは半地下)と一体に建て込んで上方に順次
継ぎ足し、所望の橋脚高さを得ることとなる。
FIG. 2 is an explanatory view showing a first step of a steel pipe refilling operation by a scaffolding method on a high pier according to the present invention. FIG. 3 is an explanatory view showing the second step, and FIG. 4 is an explanatory view showing the third step. is there. The steel pipe used here is, for example, a standard-sized steel pipe called "standard size".
Many have a diameter of 900 mm to 2000 mm and a length of about 10 m. The steel pipe is built integrally with, for example, a concrete pier foundation (underground or semi-underground) and successively added upward to obtain a desired pier height.

【0014】まず、図2(a)に示す如く、Aブラケッ
ト20は引き起こされた状態に、その上方のBブラケッ
ト21は回倒された状態に各々設定する。次に、地上の
組立ヤード等で地組しておいた足場Sを一段目鋼管P1
上方から吊下搬送し、Aブラケット20から順に足場S
を載置固定することで同(b)図の足場設置状況を得
る。吊下搬送して鋼管P1外周に沿いつつAブラケット
20上に足場Sを載置させる際には、Bブラケット21
は回倒された状態であるからこの搬送作業に対し何らの
不都合な影響を与えないのである。つまり、この搬送作
業を行う側としては単に鋼管P1の外周に沿って足場S
を吊りおろせばよく、従来の様な各足場やブラケット間
の距離などを慎重に判断しつつ微妙な作業を行うなどと
いったことは必要ない。
First, as shown in FIG. 2A, the A bracket 20 is set in a raised state, and the B bracket 21 above it is set in a turned state. Next, the scaffold S, which has been laid in the assembly yard on the ground, is connected to the first-stage steel pipe P1.
Suspended and transported from above, scaffold S
Is fixed to obtain the scaffold installation state shown in FIG. When the scaffold S is mounted on the A bracket 20 while being suspended and conveyed along the outer periphery of the steel pipe P1, the B bracket 21
Has no adverse effect on the transport operation since it has been turned over. In other words, the side that performs this transfer operation simply has the scaffold S along the outer periphery of the steel pipe P1.
It is not necessary to perform a delicate operation while carefully judging the distance between each scaffold and the bracket as in the related art.

【0015】上記の様に設置された足場Sを利用して、
鉄筋や型枠等を建て込んだり、あるいはその他の各種仮
設工を施したりといった作業が行われることになる。こ
の作業が一旦終了し、2段目鋼管P2を1段目鋼管P1
上に継ぎ足す作業に際しては、図3(a)に示す様にA
ブラケット20は撤去し、溶接など継ぎ足し作業用にB
ブラケット21上の足場Sのみを残しておく。継ぎ足さ
れた2段目鋼管P2には1段目鋼管P1と同様に受けブ
ラケット22、23が取り付けられており、Cブラケッ
ト22は引き起こされた状態に、Dブラケット23は回
倒された状態に設定される。
Using the scaffold S installed as described above,
Work such as laying a reinforcing bar or a formwork or performing various other temporary works is performed. After this work is completed, the second-stage steel pipe P2 is replaced with the first-stage steel pipe P1.
At the time of the work of adding on top, as shown in FIG.
Bracket 20 is removed and B is used for additional work such as welding.
Only the scaffold S on the bracket 21 is left. Receiving brackets 22 and 23 are attached to the second-stage steel pipe P2 that has been extended, similarly to the first-stage steel pipe P1, so that the C bracket 22 is set in a raised state, and the D bracket 23 is set in a folded state. Is done.

【0016】回倒されているDブラケット23を素通り
して足場Sが上記同様に吊下搬送され、Cブラケット2
2上に載置固定される。続いてDブラケット23上にも
足場Sを設置すれば(b)図の足場設置状況を得る。こ
のように3段の足場を設けた場合、最上段の足場では次
工程の鋼管(例えば3段目鋼管)と建込み済みの2段目
鋼管P2とを溶接する作業や鉄筋の建込み・組立作業が
実施され、中段及び下段の足場では鉄筋の建込み・組立
作業の他、橋脚の表面処理、各種撤去作業等が行われ
る。
The scaffold S is suspended and conveyed in the same manner as described above through the D bracket 23 that has been turned down,
2 and fixed. Subsequently, if the scaffold S is also installed on the D bracket 23, the scaffold installation status shown in FIG. When the three-stage scaffold is provided in this manner, the work of welding the steel pipe of the next process (for example, the third-stage steel pipe) and the already-installed second-stage steel pipe P2 and the installation / assembly of the reinforcing steel are performed on the uppermost scaffold. The work is carried out, and on the middle and lower scaffolds, in addition to the work of building and assembling the rebar, surface treatment of the piers, various removal work, and the like are performed.

【0017】1段目および2段目の鋼管P1、P2につ
いて必要とされた各種作業が完了したら、図4(a)に
示すように、Dブラケット23上の足場Sをそのまま吊
り上げ撤去した後、このDブラケット23を回倒させて
Cブラケット22上の足場Sを同様に撤去し、同じくB
ブラケット21上の足場Sも撤去する。2段目以降にも
鋼管を継ぎ足す必要がある場合には同(b)図の様にD
ブラケット23を再び引き起こして足場Sを載置固定
し、継ぎ足し作業に備えるのである。以降、何段の鋼管
を継ぎ足すこととなろうと上記同様の手順を繰り返すこ
とで簡便かつ確実に迅速な足場設置及び撤去作業を行う
ことが可能である。
When the various operations required for the first and second stage steel pipes P1 and P2 are completed, as shown in FIG. 4A, the scaffold S on the D-bracket 23 is lifted off and removed. The D bracket 23 is turned down, and the scaffold S on the C bracket 22 is removed in the same manner.
The scaffold S on the bracket 21 is also removed. When steel pipes need to be added to the second and subsequent stages, as shown in FIG.
The bracket 23 is raised again to mount and fix the scaffold S, and prepare for a re-working operation. After that, no matter how many steel pipes are to be added, it is possible to easily and surely quickly perform the scaffold installation and removal work by repeating the same procedure as described above.

【0018】ただし、受けブラケット10の取り合い部
分12の形状及び構造は、実施例の形態に限定されるも
のではなく、形状として環状、鈎状、或いは多枝状に分
岐した受け部材を備えたものでもよいし、回倒を行う機
構としてもピン接合だけでなく回倒さえできれば何れの
機構をも採用することが出来る。
However, the shape and structure of the connecting portion 12 of the receiving bracket 10 are not limited to those of the embodiment, but include a receiving member branched into an annular shape, a hook shape, or a multi-branched shape. However, any mechanism can be adopted as a mechanism for turning over as long as the mechanism can be turned over as well as the pin joint.

【0019】また、鋼管Pの外周において受けブラケッ
ト10を設置して足場Sを設ける工法を示したが、受け
ブラケット10の設置箇所はこの外周だけに限らず鋼管
などの橋脚構造物周囲であればいずれの位置でも問題な
い。
Also, the method of installing the receiving bracket 10 on the outer periphery of the steel pipe P and providing the scaffold S has been described. However, the installing place of the receiving bracket 10 is not limited to this outer periphery, but may be provided around a pier structure such as a steel pipe. There is no problem in any position.

【0020】[0020]

【発明の効果】以上詳細に説明したように、本発明の高
橋脚における足場工法は、鋼管等の構造材を適宜継ぎ足
して橋脚を施工するにあたり、この施工用の足場を仮設
する足場工法であって、少なくとも上下いずれか一方に
回倒可能でかつ前記足場を載置可能であり、前記構造材
上に固設された受けブラケットを、前記足場の設置また
は撤去作業を行う場合に回倒させることにより、足場を
分割することなく構造材に沿って吊り込み設置または撤
去可能であることを特徴とする。
As described in detail above, the scaffolding method for a high pier according to the present invention is a scaffolding method for temporarily attaching a scaffold for this construction when constructing a pier by appropriately adding structural members such as steel pipes. At least one of the upper and lower sides and the scaffold can be placed, and the receiving bracket fixed on the structural material is turned over when the scaffold is installed or removed. Thereby, it can be suspended and installed or removed along the structural material without dividing the scaffold.

【0021】したがって本発明によれば、足場を設置あ
るいは撤去するに際して、従来のように各足場間の最小
距離やブラケット形状などに応じて足場を予め分割する
必要など全くなく、受けブラケットの適宜回倒により一
括して足場を設置あるいは撤去することが可能となる。
Therefore, according to the present invention, when the scaffold is installed or removed, the scaffold does not need to be divided in advance according to the minimum distance between the scaffolds or the shape of the bracket as in the prior art. It becomes possible to install or remove the scaffolding collectively by falling down.

【0022】また、受けブラケットに対する足場の位置
合わせも、上記のように足場の一括設置・撤去作業が可
能であることにより、煩雑かつ微妙な作業を強いられる
こともなく、効率の良い位置決めを容易に行えることと
なる。
Also, the positioning of the scaffold with respect to the receiving bracket can be easily and efficiently performed because the scaffold can be collectively installed / removed as described above, without requiring complicated and delicate work. Can be done.

【0023】しかして、足場工に要される人員、各種機
器類、及びそれらのコスト等が従来より大幅に低減さ
れ、工事全体上もコスト及び工期上の著しい改善効果を
奏するのである。
[0023] Thus, the number of personnel, various devices, and their costs required for the scaffolding work are greatly reduced as compared with the conventional art, and the overall work has a remarkable effect on cost and work period.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の高橋脚における足場工法において用い
られる受けブラケットの構造を示す説明図である。
FIG. 1 is an explanatory view showing a structure of a receiving bracket used in a scaffolding method for a high pier according to the present invention.

【図2】本発明の高橋脚における足場工法による鋼管継
ぎ足し作業の第1ステップを示す説明図である。
FIG. 2 is an explanatory view showing a first step of a steel pipe refilling operation by a scaffolding method on a high pier according to the present invention.

【図3】本発明の高橋脚における足場工法による鋼管継
ぎ足し作業の第2ステップを示す説明図である。
FIG. 3 is an explanatory view showing a second step of the steel pipe replenishing operation by the scaffolding method on the high pier according to the present invention.

【図4】本発明の高橋脚における足場工法による鋼管継
ぎ足し作業の第3ステップを示す説明図である。
FIG. 4 is an explanatory view showing a third step of a steel pipe refilling operation by a scaffolding method on a high pier according to the present invention.

【符号の説明】[Explanation of symbols]

P 鋼管(橋脚構造材) S 足場 10 受けブラケット P Steel pipe (pier structure material) S Scaffold 10 Receiving bracket

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 鋼管等の構造材を適宜継ぎ足して橋脚を
施工するにあたり、この施工用の足場を仮設する足場工
法であって、少なくとも上下いずれか一方に回倒可能で
かつ前記足場を載置可能であり、前記構造材上に固設さ
れた受けブラケットを、前記足場の設置または撤去作業
を行う場合に回倒させることにより、足場を分割するこ
となく構造材に沿って吊り込み設置または撤去可能であ
ることを特徴とする高橋脚における足場工法。
1. A scaffolding method for temporarily constructing a scaffold for construction when constructing a pier by appropriately adding structural members such as steel pipes, wherein the scaffold can be turned over at least one of up and down and the scaffold is placed. It is possible that the receiving bracket fixed on the structural material is turned over when installing or removing the scaffold, so that the mounting bracket is suspended or installed along the structural material without dividing the scaffold. A scaffolding method for high piers, which is possible.
JP2000054205A 2000-02-29 2000-02-29 Scaffolding method on Takahashi pier Expired - Fee Related JP3788167B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000054205A JP3788167B2 (en) 2000-02-29 2000-02-29 Scaffolding method on Takahashi pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000054205A JP3788167B2 (en) 2000-02-29 2000-02-29 Scaffolding method on Takahashi pier

Publications (2)

Publication Number Publication Date
JP2001241013A true JP2001241013A (en) 2001-09-04
JP3788167B2 JP3788167B2 (en) 2006-06-21

Family

ID=18575493

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000054205A Expired - Fee Related JP3788167B2 (en) 2000-02-29 2000-02-29 Scaffolding method on Takahashi pier

Country Status (1)

Country Link
JP (1) JP3788167B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178037A (en) * 2017-05-31 2017-09-19 中交二公局第工程有限公司 The outer frame connecting structure of trestle vase-shaped column-type pier pier shaft and its construction technology
CN113293694A (en) * 2021-07-01 2021-08-24 中交二航局第四工程有限公司 Rollover frame structure for efficient pier body construction and construction process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178037A (en) * 2017-05-31 2017-09-19 中交二公局第工程有限公司 The outer frame connecting structure of trestle vase-shaped column-type pier pier shaft and its construction technology
CN113293694A (en) * 2021-07-01 2021-08-24 中交二航局第四工程有限公司 Rollover frame structure for efficient pier body construction and construction process
CN113293694B (en) * 2021-07-01 2023-03-14 中交二航局第四工程有限公司 Turnover formwork frame structure for efficient pier body construction and construction process

Also Published As

Publication number Publication date
JP3788167B2 (en) 2006-06-21

Similar Documents

Publication Publication Date Title
CN103061506B (en) Construction method of steel structure dome
JP2010018975A (en) Form timbering and horizontal force processing member for form timbering
KR20070010449A (en) Construction method for arched bridge
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
JP2894226B2 (en) Bridge construction method
JP2001241013A (en) Staging erection method in high pier
JP2020060000A (en) Skeleton construction method
JP2022009519A (en) Superstructure member conveyance facility and superstructure member conveyance method
KR100476335B1 (en) The advanced method for arrangement of prefabricated reinforcement for each span for Movable Scaffolding System in the double-T girder bridge
JP2020204263A (en) Superstructure member conveyance facility and superstructure member conveyance method
JPH10299290A (en) Removing method of top section of ultrahigh cylindrical structure and scaffold for removal work
JP3436104B2 (en) Steel pipe construction method
JP6720761B2 (en) How to build a ramen structure
JPH11323838A (en) Construction method of bridge
JP2001262518A (en) Method for replacing lifting equipment joint member on high pier
JP2003313860A (en) Method and device for assembling pit reinforcement
CN114458050B (en) Cast house roof protective dismantling method
JPH09177070A (en) Method and device for placing of steel bar cage for deep foundation
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
JPH0270861A (en) Mounting and overhaulting method of work scaffold in step-up technique
JPH0412296Y2 (en)
JP6798527B2 (en) Superstructure material transportation equipment and superstructure material transportation method
JP2732004B2 (en) Restoration method of temporary opening of floor slab
JP2712121B2 (en) Reinforcing bar mounting method, hanging jig used in the mounting method, and guide device
JP2023175115A (en) Wall reinforcement arrangement method

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20040922

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050802

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20051206

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060203

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060307

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060320

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees