JP2001220762A - Pipe roof structure and pipe roof construction method - Google Patents
Pipe roof structure and pipe roof construction methodInfo
- Publication number
- JP2001220762A JP2001220762A JP2000030872A JP2000030872A JP2001220762A JP 2001220762 A JP2001220762 A JP 2001220762A JP 2000030872 A JP2000030872 A JP 2000030872A JP 2000030872 A JP2000030872 A JP 2000030872A JP 2001220762 A JP2001220762 A JP 2001220762A
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- jack
- existing structure
- pipe roof
- opening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、パイプルーフ構造
およびパイプルーフ工法に係り、詳細には、プレロード
ジャッキを内部に有するパイプルーフ構造、およびこれ
を構築するためのパイプルーフ工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pipe roof structure and a pipe roof construction method, and more particularly, to a pipe roof structure having a preload jack therein and a pipe roof construction method for constructing the same.
【0002】[0002]
【従来の技術】従来、べた基礎形式の構造物をパイプル
ーフ工法によりアンダーピニングする場合には、既設構
造物を支持するための支持杭が新たに施工される。2. Description of the Related Art Conventionally, when a solid foundation type structure is underpinned by a pipe roof method, a support pile for supporting an existing structure is newly constructed.
【0003】例えば、図3に示すように、地下既設構造
物3(例えば地下鉄など)の下方のパイプルーフ1は、
支持フレーム4を介して、基礎杭5により支持されてい
る。既設構造物3の構造安定を確保するため、既設構造
物3の両サイドと、パイプルーフ1の中間部とに支持杭
が施工されている。For example, as shown in FIG. 3, a pipe roof 1 below an underground existing structure 3 (for example, a subway) is
It is supported by a foundation pile 5 via a support frame 4. In order to secure the structural stability of the existing structure 3, support piles are installed on both sides of the existing structure 3 and the middle part of the pipe roof 1.
【0004】[0004]
【発明が解決しようとする課題】しかし、従来のパイプ
ルーフ工法では、既設構造物3の直下に支持杭を施工す
る必要があったため、先進導坑の掘削、土留め、基礎杭
5の施工および受け替えが閉所作業となり、施工性が悪
い、という問題があった。However, in the conventional pipe roof construction method, it was necessary to construct a support pile immediately below the existing structure 3, so excavation of the advanced shaft, earth retaining, construction of the foundation pile 5, and There was a problem that the replacement was a closed work and the workability was poor.
【0005】また、先進導坑掘削による既設構造物3へ
の影響を軽減するために、高強度の地盤改良工(例え
ば、水平方向の高圧噴射攪拌工法など)が必要であった
ため、経済性が悪い、という問題もあった。[0005] In addition, in order to reduce the influence of the advanced shaft excavation on the existing structure 3, a high-strength ground improvement work (for example, a horizontal high-pressure jet stirring method) is required, so that economic efficiency is reduced. There was also a problem that it was bad.
【0006】本発明の課題は、既設構造物直下の支持杭
を省略できるパイプルーフ構造およびパイプルーフ工法
を提供することである。An object of the present invention is to provide a pipe roof structure and a pipe roof construction method that can omit a support pile immediately below an existing structure.
【0007】[0007]
【課題を解決するための手段】以上の課題を解決するた
め、請求項1記載の発明は、例えば図1に示すように、
既設構造物3をアンダーピニングする場合に適用される
パイプルーフ構造であって、既設構造物3の下部地盤に
推進するパイプ10の中間部内に、既設構造物3を支持
するジャッキ2を設けることを特徴とする。Means for Solving the Problems In order to solve the above problems, the invention described in claim 1 is, for example, as shown in FIG.
A pipe roof structure applied to underpinning of an existing structure 3, wherein a jack 2 for supporting the existing structure 3 is provided in an intermediate portion of a pipe 10 propelled to the lower ground of the existing structure 3. Features.
【0008】請求項1記載の発明によれば、既設構造物
を支持するジャッキの反力を調節して、既設構造物の支
持安定性を確保できる。このため、既設構造物の両サイ
ドで構造物を先受けし、構造物直下においてはジャッキ
により支持できるので、既設構造物直下の支持杭を省略
できる。According to the first aspect of the present invention, the stability of the support of the existing structure can be ensured by adjusting the reaction force of the jack supporting the existing structure. For this reason, the structure can be received on both sides of the existing structure in advance, and can be supported by the jack immediately below the structure, so that the support pile directly below the existing structure can be omitted.
【0009】従って、先進導坑の掘削、土留め、および
先進導坑内での基礎杭の施工、構造物の基礎杭受け替え
などの閉所作業を省略できる。また、先進導坑施工を省
略できるので、高強度の地盤改良工が不要となる。した
がって、例えば止水薬液注入工法などの地盤改良工のみ
で十分対応でき、補助工法に関してコストダウンを図れ
る。Therefore, it is possible to omit the work of closing the excavation and earth retaining of the advanced shaft, the construction of the foundation pile in the advanced shaft, and the replacement of the foundation pile of the structure. In addition, since advanced shaft construction can be omitted, high-strength ground improvement work is not required. Therefore, it is possible to sufficiently cope with only the ground improvement work such as the water-stopping chemical liquid injection method, and the cost can be reduced with respect to the auxiliary method.
【0010】請求項2記載の発明は、請求項1記載のパ
イプルーフ構造において、例えば図2に示すように、パ
イプ10は二重管であることを特徴とする。According to a second aspect of the present invention, in the pipe roof structure of the first aspect, as shown in FIG. 2, for example, the pipe 10 is a double pipe.
【0011】請求項2記載の発明によれば、パイプが二
重管であるので、よりジャッキの反力に耐える構成にで
きる。また、二重管の外管と内管との間の空隙を、モル
タル、コンクリートなどの充填材により充填して、パイ
プの強度を高められる。According to the second aspect of the present invention, since the pipe is a double pipe, it is possible to provide a structure that can withstand the reaction force of the jack. Further, the gap between the outer pipe and the inner pipe of the double pipe is filled with a filler such as mortar, concrete, or the like, so that the strength of the pipe can be increased.
【0012】請求項3記載の発明は、請求項1または2
記載のパイプルーフ構造において、パイプ10には、上
方へ開口して、ジャッキ2により既設構造物3を支持す
る支持部材32が突出する開口部16が形成されている
ことを特徴とする。The invention described in claim 3 is the first or second invention.
The pipe roof structure described above is characterized in that the pipe 10 is formed with an opening 16 that opens upward and from which a support member 32 that supports the existing structure 3 with the jack 2 projects.
【0013】請求項3記載の発明によれば、開口部が形
成されているので、パイプ内に設置するジャッキによ
り、開口部より突出する支持部材を介して既設構造物を
支持できる。According to the third aspect of the present invention, since the opening is formed, the existing structure can be supported by the jack installed in the pipe via the support member projecting from the opening.
【0014】請求項4記載の発明は、請求項3記載のパ
イプルーフ構造において、パイプ10内に打設したコン
クリート14上にジャッキ2が設置されていることを特
徴とする。According to a fourth aspect of the present invention, in the pipe roof structure according to the third aspect, the jack 2 is installed on the concrete 14 cast in the pipe 10.
【0015】請求項4記載の発明によれば、開口部が形
成されたパイプの強度を、コンクリートにより補強でき
る。According to the fourth aspect of the invention, the strength of the pipe in which the opening is formed can be reinforced by concrete.
【0016】請求項5記載の発明は、請求項1から4の
いずれかに記載のパイプルーフ構造を構築するためのパ
イプルーフ工法において、既設構造物3の下部地盤にパ
イプ10を推進する第1工程と、推進後のパイプ10内
にジャッキ2を設置する第2工程と、既設構造物3の下
部地盤を掘削する第3工程と、を備え、第3工程では、
パイプ10内に設置される各ジャッキ2の反力がほぼ一
定となるように、各ジャッキ2を調整することを特徴と
する。According to a fifth aspect of the present invention, there is provided a pipe roof construction method for constructing a pipe roof structure according to any one of the first to fourth aspects, wherein the pipe 10 is propelled to the lower ground of the existing structure 3. And a second step of installing the jack 2 in the pipe 10 after propulsion, and a third step of excavating the lower ground of the existing structure 3. In the third step,
Each jack 2 is adjusted so that the reaction force of each jack 2 installed in the pipe 10 becomes substantially constant.
【0017】ここで、各ジャッキの調整は、集中制御な
どにより管理される。また、計測工を併用して、構造物
への影響度にしたがって、各ジャッキの調整を行うもの
としても良い。Here, adjustment of each jack is managed by centralized control or the like. Further, the jacks may be adjusted in accordance with the degree of influence on the structure by using a measuring instrument.
【0018】請求項5記載の発明によれば、既設構造物
の下部地盤を掘削する際に、構造物の支持安定性を保つ
ことができる。According to the invention described in claim 5, when excavating the lower ground of the existing structure, the support stability of the structure can be maintained.
【0019】請求項6記載の発明は、請求項3または4
記載のパイプルーフ構造を構築するためのパイプルーフ
工法において、既設構造物3の下部地盤にパイプ10を
推進する第1工程と、推進後のパイプ10内にジャッキ
2を設置する第2工程と、を備え、第1工程時には、パ
イプ10の開口部16に仮蓋を設置した状態とし、第2
工程時には、開口部16から仮蓋を撤去した状態とする
ことを特徴とする。The invention according to claim 6 is the invention according to claim 3 or 4.
In the pipe roof construction method for constructing the described pipe roof structure, a first step of propelling the pipe 10 on the lower ground of the existing structure 3, a second step of installing the jack 2 in the pipe 10 after the propulsion, At the time of the first step, the temporary lid is set in the opening 16 of the pipe 10, and the second step is performed.
During the process, the temporary lid is removed from the opening 16.
【0020】請求項6記載の発明によれば、第1工程に
おいて、従来のパイプ推進作業と同様にして、開口部が
形成されたパイプを推進設置できる。また、第2工程に
おいて、仮蓋を撤去するのみで、容易にパイプに開口部
を設けられる。According to the sixth aspect of the present invention, in the first step, a pipe having an opening can be propelled and installed in the same manner as a conventional pipe propelling operation. Also, in the second step, the opening can be easily provided in the pipe only by removing the temporary lid.
【0021】[0021]
【発明の実施の形態】以下、図を参照して本発明の実施
の形態を詳細に説明する。Embodiments of the present invention will be described below in detail with reference to the drawings.
【0022】まず、構成を説明する。図1に示すよう
に、本発明を適用した一実施の形態のパイプルーフ構造
は、既設構造物3のアンダーピニングに適用されてい
る。既設構造物3の両サイドは、支持フレーム4を介し
て、基礎杭5により支持されている。パイプルーフを構
成するパイプ10の中間部内には、ジャッキ2が設けら
れている。ジャッキ2により、既設構造物3が下方から
支持されている。First, the configuration will be described. As shown in FIG. 1, a pipe roof structure according to an embodiment of the present invention is applied to underpinning of an existing structure 3. Both sides of the existing structure 3 are supported by a foundation pile 5 via a support frame 4. A jack 2 is provided in an intermediate portion of the pipe 10 constituting the pipe roof. The existing structure 3 is supported by the jack 2 from below.
【0023】図2に示すように、既設構造物3の底版3
1は、支持部材32を介して、パイプ10内に設けられ
たジャッキ2により支持されている。ここで、図2は、
パイプ10の要部断面図である。As shown in FIG. 2, the bottom plate 3 of the existing structure 3
1 is supported by a jack 2 provided in the pipe 10 via a support member 32. Here, FIG.
FIG. 2 is a sectional view of a main part of the pipe 10.
【0024】パイプ10は、二重管である。外管11、
内管12の直径は、例えば、それぞれ、1200mm、1
100mmである。外管11と内管12との間の空隙に
は、例えば、モルタル、コンクリートなどの充填材13
が充填されている。The pipe 10 is a double pipe. Outer tube 11,
The diameter of the inner tube 12 is, for example, 1200 mm and 1 mm, respectively.
100 mm. In the gap between the outer pipe 11 and the inner pipe 12, for example, a filler 13 such as mortar or concrete is provided.
Is filled.
【0025】パイプ10のジャッキ設置位置には、上方
に開口する開口部16が形成されている。開口部16周
りには、補強リブ15a、15bが形成されており、開
口部16が補強されている。また、パイプ10内の下部
には、コンクリート14が打設されている。An opening 16 opening upward is formed at the jack installation position of the pipe 10. Around the opening 16, reinforcing ribs 15a and 15b are formed, and the opening 16 is reinforced. Further, concrete 14 is cast in a lower portion in the pipe 10.
【0026】パイプ10内のコンクリート14上に、ジ
ャッキ2が設置されている。ジャッキ2には、例えば三
枚のフラットジャッキが用いられるが、これに限らず、
油圧ジャッキなどを用いても良い。また、ジャッキ2に
より、鋼材ブロックなどの支持部材32が、開口部16
から上方へ突出して設置されている。支持部材32は、
既設構造物3の底版31を支持している。The jack 2 is placed on the concrete 14 in the pipe 10. For example, three flat jacks are used for the jack 2, but the invention is not limited to this.
A hydraulic jack or the like may be used. In addition, the jack 2 allows the support member 32 such as a steel block to be moved to the opening 16.
It is installed to protrude from above. The support member 32
The bottom plate 31 of the existing structure 3 is supported.
【0027】次に、本実施の形態のパイプルーフ工法を
説明する。Next, the pipe roof method according to the present embodiment will be described.
【0028】まず、基礎杭5の施工位置周辺において、
地盤改良工を行う。その後、既設構造物3の両サイド
に、基礎杭5を施工し、支持フレーム4を建て込む。既
設構造物3の両側において、立坑部を掘削し、土留め施
工および基礎コンクリート打設を行う。次に、ルーフパ
イプおよびサイドパイプを打設する位置に、薬液注入す
る。First, around the construction position of the foundation pile 5,
Perform ground improvement work. After that, the foundation pile 5 is constructed on both sides of the existing structure 3 and the support frame 4 is built. On both sides of the existing structure 3, the shaft is excavated, and earth retaining work and foundation concrete casting are performed. Next, a chemical solution is injected into a position where the roof pipe and the side pipe are cast.
【0029】次に、ルーフパイプ位置に、パイプ10の
開口部16に仮蓋をした状態で、パイプ10を推進す
る。このとき、パイプ10の開口部16の位置を、ジャ
ッキアップ位置に合わせる。Next, the pipe 10 is propelled at the position of the roof pipe, with the opening 16 of the pipe 10 temporarily covered. At this time, the position of the opening 16 of the pipe 10 is adjusted to the jack-up position.
【0030】パイプ10推進完了後、パイプ10内にコ
ンクリート14を打設し、コンクリート14上にジャッ
キ2を設置する。仮蓋を撤去し、支持部材32を介して
既設構造物3の底版31を下方から支持する。After the completion of the propulsion of the pipe 10, concrete 14 is poured into the pipe 10, and the jack 2 is placed on the concrete 14. The temporary lid is removed, and the bottom plate 31 of the existing structure 3 is supported from below via the support member 32.
【0031】その後、サイドパイプを推進する。全ての
パイプの貫入が終了した後、既設構造物3の下部地盤を
掘削する。必要に応じて、止水薬液注入を追加施工す
る。地盤掘削時においては、ルーフパイプ内のパイプ1
0に設置された各ジャッキ2の圧力を、集中制御により
管理し、一定に保つ。また、計測工の併用により、構造
物への影響を管理する。Thereafter, the side pipe is propelled. After the penetration of all the pipes is completed, the lower ground of the existing structure 3 is excavated. If necessary, add water stoppage chemical injection. When excavating the ground, the pipe 1
The pressure of each jack 2 installed at 0 is managed by centralized control and kept constant. In addition, the influence on the structure is managed by using the mechanic.
【0032】以上のように、既設構造物3の下部地盤に
推進するパイプ10の中間部内に、既設構造物3を支持
するジャッキ2が設けられているので、ジャッキ2の反
力を調節して、既設構造物3の支持安定性を確保でき
る。このため、構造物をジャッキ2により支持でき、既
設構造物3直下の支持杭を省略できる。As described above, since the jack 2 for supporting the existing structure 3 is provided in the middle of the pipe 10 propelled to the lower ground of the existing structure 3, the reaction force of the jack 2 is adjusted. Thus, the support stability of the existing structure 3 can be ensured. For this reason, the structure can be supported by the jack 2, and the support pile immediately below the existing structure 3 can be omitted.
【0033】従って、先進導坑の掘削、土留め、および
先進導坑内での基礎杭の施工、構造物の基礎杭受け替え
などの閉所作業を省略できる。また、施工工程数を少な
くできる。Therefore, it is possible to omit the closing work such as excavation and retaining of the advanced shaft, construction of the foundation pile in the advanced shaft, and replacement of the foundation pile of the structure. Further, the number of construction steps can be reduced.
【0034】また、先進導坑施工を省略できるので、従
来と異なり、高強度の地盤改良工が不要となる。従っ
て、止水薬液注入工法などの地盤改良工のみで十分対応
でき、補助工法に関してコストダウンを図れる。In addition, since the construction of the advanced shaft can be omitted, unlike the conventional art, a high-strength ground improvement work is not required. Therefore, it is possible to sufficiently cope with only the ground improvement work such as the water-stopping chemical liquid injection method, and the cost can be reduced with respect to the auxiliary method.
【0035】また、パイプ10は二重管であるので、よ
りジャッキ2の反力に耐える構成にできる。また、外管
11と内管12との間に充填された充填材13により、
パイプ10の剛性を強くできる。また、パイプ10内に
打設したコンクリート14により、開口部16が形成さ
れたパイプ10の強度を補強できる。Further, since the pipe 10 is a double pipe, the pipe 10 can be configured to withstand the reaction force of the jack 2 more. Further, the filler 13 filled between the outer pipe 11 and the inner pipe 12 allows
The rigidity of the pipe 10 can be increased. Moreover, the strength of the pipe 10 in which the opening 16 is formed can be reinforced by the concrete 14 cast in the pipe 10.
【0036】また、既設構造物3の下部地盤を掘削する
際、パイプ10内に設置される各ジャッキ2の反力がほ
ぼ一定となるように調整されるので、構造物の支持安定
性を確保できる。Further, when excavating the lower ground of the existing structure 3, the reaction force of each jack 2 installed in the pipe 10 is adjusted to be substantially constant, so that the support stability of the structure is ensured. it can.
【0037】また、パイプ10の推進時には、パイプ1
0の開口部16に仮蓋を設置するので、開口部のない従
来のパイプを推進する作業と同様にして、開口部16が
形成されたパイプ10を推進設置できる。また、パイプ
10推進後、仮蓋を撤去する作業のみで、容易にパイプ
10に開口部16を設けられる。When the pipe 10 is propelled, the pipe 1
Since the temporary lid is installed in the opening 16 of the zero, the pipe 10 having the opening 16 can be propelled and installed in the same manner as the conventional operation of propelling a pipe having no opening. After the pipe 10 is propelled, the opening 16 can be easily provided in the pipe 10 only by removing the temporary lid.
【0038】なお、以上の実施の形態においては、パイ
プ10が二重管であるものとしたが、本発明はこれに限
定されるものではなく、一重のパイプを用いるものとし
てもよい。In the above embodiment, the pipe 10 is a double pipe, but the present invention is not limited to this, and a single pipe may be used.
【0039】[0039]
【発明の効果】請求項1記載の発明によれば、パイプル
ーフ工法によりアンダーピニングする場合において、既
設構造物直下の支持杭を省略できる。したがって、先進
導坑の掘削、土留め、および先進導坑内での基礎杭の施
工、構造物の基礎杭受け替えなどの閉所作業を省略でき
る。また、高強度の地盤改良工が不要となり、補助工法
に関してコストダウンを図れる。According to the first aspect of the invention, when underpinning is performed by the pipe roof method, the support pile immediately below the existing structure can be omitted. Therefore, the closing work such as excavation of the advanced shaft, earth retaining, construction of the foundation pile in the advanced shaft, and replacement of the foundation pile of the structure can be omitted. In addition, high-strength ground improvement work is not required, and costs can be reduced for the auxiliary construction method.
【0040】請求項2記載の発明によれば、請求項1記
載の発明と同様の効果が得られるのは勿論のこと、パイ
プを、よりジャッキの反力に耐える構成にできる。According to the second aspect of the invention, the same effect as that of the first aspect of the invention can be obtained, and the pipe can be configured to withstand the reaction force of the jack.
【0041】請求項3記載の発明によれば、請求項1ま
たは2記載の発明と同様の効果が得られるのは勿論のこ
と、パイプ内に設置するジャッキにより、支持部材を介
して既設構造物を支持できる。According to the third aspect of the present invention, the same effects as those of the first or second aspect can be obtained, and of course, the existing structure can be provided via the support member by the jack installed in the pipe. Can be supported.
【0042】請求項4記載の発明によれば、請求項3記
載の発明と同様の効果が得られるのは勿論のこと、開口
部が形成されたパイプの強度を、コンクリートにより補
強できる。According to the fourth aspect of the present invention, the same effect as that of the third aspect of the invention can be obtained, and the strength of the pipe having the opening can be reinforced by concrete.
【0043】請求項5記載の発明によれば、請求項1か
ら4のいずれかに記載の発明と同様の効果が得られるの
は勿論のこと、既設構造物の下部地盤を掘削する際に、
構造物の支持安定性を保つことができる。According to the fifth aspect of the present invention, the same effects as those of the first to fourth aspects can be obtained, and when excavating the lower ground of the existing structure,
The support stability of the structure can be maintained.
【0044】請求項6記載の発明によれば、請求項3ま
たは4記載の発明と同様の効果が得られるのは勿論のこ
と、従来のパイプ推進作業と同様にして、開口部が形成
されたパイプを推進設置できる。また、仮蓋を撤去する
作業のみで、容易にパイプに開口部を設けられる。According to the sixth aspect of the invention, the same effects as those of the third or fourth aspect can be obtained, and the opening is formed in the same manner as in the conventional pipe propulsion operation. The pipe can be propelled and installed. Also, the opening can be easily provided in the pipe only by removing the temporary lid.
【図1】本発明を適用した一実施の形態のパイプルーフ
構造の構成を示す断面図である。FIG. 1 is a cross-sectional view illustrating a configuration of a pipe roof structure according to an embodiment of the present invention.
【図2】図1のパイプおよびジャッキの構成を示す断面
図である。FIG. 2 is a sectional view showing a configuration of a pipe and a jack of FIG.
【図3】従来のパイプルーフ構造の構成を示す断面図で
ある。FIG. 3 is a sectional view showing a configuration of a conventional pipe roof structure.
2 ジャッキ 3 既設構造物 10 パイプ 14 コンクリート 16 開口部 32 支持部材 2 jack 3 existing structure 10 pipe 14 concrete 16 opening 32 support member
───────────────────────────────────────────────────── フロントページの続き (72)発明者 鳥居 雅之 東京都港区虎ノ門一丁目20番10号 西松建 設株式会社内 Fターム(参考) 2D047 AB00 ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Masayuki Torii 1-20-10 Toranomon, Minato-ku, Tokyo Nishimatsu Construction F-term (reference) 2D047 AB00
Claims (6)
適用されるパイプルーフ構造であって、 既設構造物の下部地盤に推進するパイプの中間部内に、
既設構造物を支持するジャッキを設けることを特徴とす
るパイプルーフ構造。1. A pipe roof structure applied to underpinning of an existing structure, wherein the pipe roof is propelled to the lower ground of the existing structure,
A pipe roof structure comprising a jack for supporting an existing structure.
求項1記載のパイプルーフ構造。2. The pipe roof structure according to claim 1, wherein the pipe is a double pipe.
より既設構造物を支持する支持部材が突出する開口部が
形成されていることを特徴とする請求項1または2記載
のパイプルーフ構造。3. The pipe roof structure according to claim 1, wherein the pipe is formed with an opening that opens upward and through which a support member for supporting an existing structure with a jack protrudes. .
ッキが設置されていることを特徴とする請求項3記載の
パイプルーフ構造。4. The pipe roof structure according to claim 3, wherein a jack is installed on the concrete cast in the pipe.
ルーフ構造を構築するためのパイプルーフ工法におい
て、 既設構造物の下部地盤にパイプを推進する第1工程と、 推進後のパイプ内にジャッキを設置する第2工程と、 既設構造物の下部地盤を掘削する第3工程と、を備え、 第3工程では、パイプ内に設置される各ジャッキの反力
がほぼ一定となるように、各ジャッキを調整することを
特徴とするパイプルーフ工法。5. A pipe roof construction method for constructing a pipe roof structure according to any one of claims 1 to 4, wherein a first step of propelling the pipe to a lower ground of an existing structure; And a third step for excavating the lower ground of the existing structure. In the third step, the reaction force of each jack installed in the pipe is substantially constant. The pipe roof method is characterized by adjusting each jack.
を構築するためのパイプルーフ工法において、 既設構造物の下部地盤にパイプを推進する第1工程と、 推進後のパイプ内にジャッキを設置する第2工程と、を
備え、 第1工程時では、パイプの開口部に仮蓋を設置した状態
とし、 第2工程時では、開口部から仮蓋を撤去した状態とする
ことを特徴とするパイプルーフ工法。6. A pipe roof construction method for constructing a pipe roof structure according to claim 3 or 4, wherein a first step of propelling the pipe to the lower ground of the existing structure, and installing a jack in the pipe after the propulsion. A first step in which a temporary lid is placed at the opening of the pipe, and a second step, in which the temporary lid is removed from the opening. Pipe roof method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000030872A JP4302274B2 (en) | 2000-02-08 | 2000-02-08 | Pipe roof structure and pipe roof construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000030872A JP4302274B2 (en) | 2000-02-08 | 2000-02-08 | Pipe roof structure and pipe roof construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001220762A true JP2001220762A (en) | 2001-08-17 |
JP4302274B2 JP4302274B2 (en) | 2009-07-22 |
Family
ID=18555826
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000030872A Expired - Fee Related JP4302274B2 (en) | 2000-02-08 | 2000-02-08 | Pipe roof structure and pipe roof construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4302274B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115198797A (en) * | 2022-07-01 | 2022-10-18 | 上海建工一建集团有限公司 | Construction method for underground communication channel combining three-side enclosing pipe curtain method and open cut |
CN115467367A (en) * | 2022-08-17 | 2022-12-13 | 湖北工业大学 | Construction method for actively compensating deformation of underpass operation tunnel in upper-layer engineering construction |
-
2000
- 2000-02-08 JP JP2000030872A patent/JP4302274B2/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115198797A (en) * | 2022-07-01 | 2022-10-18 | 上海建工一建集团有限公司 | Construction method for underground communication channel combining three-side enclosing pipe curtain method and open cut |
CN115198797B (en) * | 2022-07-01 | 2023-11-14 | 上海建工一建集团有限公司 | Underground communication channel construction method combining three-side surrounding pipe curtain method and open cut |
CN115467367A (en) * | 2022-08-17 | 2022-12-13 | 湖北工业大学 | Construction method for actively compensating deformation of underpass operation tunnel in upper-layer engineering construction |
Also Published As
Publication number | Publication date |
---|---|
JP4302274B2 (en) | 2009-07-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101736749B (en) | Method for constructing soft soil foundation continuous caisson | |
CN103321246B (en) | Underground diaphragm wall based foundation pit construction method | |
KR100656194B1 (en) | Open cut and cover method applying tunnel cut method | |
KR101018282B1 (en) | Method for constructing fabric for undergound tunnel | |
CN113550317B (en) | Permanent-temporary combined supporting structure and construction method for open excavation reverse construction foundation pit of large shield starting well | |
KR100313720B1 (en) | Composite Underground Structure Construction Method | |
CN110468873A (en) | Piles underpinning structure and application method under a kind of small space | |
CN111255462B (en) | Pipe curtain cover excavation top-down construction method for subway station construction | |
CN104480945B (en) | A kind of foundation ditch reversed construction method | |
CN104499489B (en) | Foundation pit construction method | |
JP4226954B2 (en) | Underpinning method and viaduct | |
JP2001220762A (en) | Pipe roof structure and pipe roof construction method | |
KR20130021949A (en) | Reinforcement structure for wall of underground structure and construction method of underground structure using the same | |
CN208650067U (en) | Underground increasing layer excavates new supporting structure | |
JPH10168915A (en) | Method of ground excavation construction in coffering sheet pile | |
JPH1077644A (en) | Earthquake resisting pile foundation construction method | |
JP2004100281A (en) | Positioning method for permanent substructural column without using casing | |
JP3886275B2 (en) | Underground tank structure | |
CN104612161A (en) | Method for reversed construction of foundation pit with underground diaphragm wall | |
CN219261048U (en) | Working well | |
JP3030622B2 (en) | How to build a tunnel | |
KR102664851B1 (en) | Existing underground building demolition method using sheet pile | |
JPH116164A (en) | Construction method for underground structure | |
JPH11166242A (en) | Underground space constructing method and supporting structure in underground space construction | |
KR20100087505A (en) | Underground structure and method for constructing thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20061110 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080821 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080924 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081125 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090421 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090422 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120501 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150501 Year of fee payment: 6 |
|
LAPS | Cancellation because of no payment of annual fees |