JP2001090059A - Soil-improvement method by mixing and agitation, and its device - Google Patents

Soil-improvement method by mixing and agitation, and its device

Info

Publication number
JP2001090059A
JP2001090059A JP26797399A JP26797399A JP2001090059A JP 2001090059 A JP2001090059 A JP 2001090059A JP 26797399 A JP26797399 A JP 26797399A JP 26797399 A JP26797399 A JP 26797399A JP 2001090059 A JP2001090059 A JP 2001090059A
Authority
JP
Japan
Prior art keywords
hardening material
mixing
liquid hardening
fork
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26797399A
Other languages
Japanese (ja)
Other versions
JP3298054B2 (en
Inventor
Hiroaki Kusabe
弘明 草部
Tadashi Chuma
忠司 中馬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Esutekku Kk
Estec Co Ltd
Original Assignee
Esutekku Kk
Estec Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Esutekku Kk, Estec Co Ltd filed Critical Esutekku Kk
Priority to JP26797399A priority Critical patent/JP3298054B2/en
Publication of JP2001090059A publication Critical patent/JP2001090059A/en
Application granted granted Critical
Publication of JP3298054B2 publication Critical patent/JP3298054B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To solve trouble, in which agitation with a ground is difficult to uniformly perform because a mixed liquid is discharged in a striped shape in the excavation direction, besides trouble, in which a discharge opening is clogged in the case of excavation and must be cleaned at all times because the mixed liquid is discharged in the excavation direction from the front end of a mixing agitator in mixing and agitation by a liquefied hardening material which has been developed, regarding soft-ground improvement in a shallow stratum and a medium stratum and the foundation land-formation of a structure. SOLUTION: An object ground is excavated, ejecting or high-pressure injecting a liquefied hardening material from a liquefied hardening-material injection hole by a mixing fork 1, which has the liquefied hardening-material injection hole 21 on a side wall and in which a liquefied hardening-material ejection rod 2 curved in conformity with fork blades 11 is disposed at the central section of the fork blades, and removed soft-ground soil and the liquefied hardening material are mixed and agitated by operating the fork blades and an improved hardened stratum is land-formed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、対象地盤に液状硬
化材を混入すると共に、混合攪拌して軟弱地盤の整地改
良や構築物の基礎を造成するための、混合攪拌による地
盤改良工法とその装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for improving the ground by mixing and stirring, for mixing a liquid hardening material into a target ground and mixing and stirring to improve the leveling of soft ground and to form the foundation of a building. It is about.

【0002】[0002]

【発明が解決しようとする課題】従来、浅層、中層にお
ける軟弱地盤改良や構築物の基礎造成は、バックホウの
ような汎用型の施工機械を用い、セメント系固化材を粉
体で添加しながら混合攪拌する方法が採られてきた。
Conventionally, the improvement of soft ground in the shallow and middle layers and the foundation construction of structures have been carried out by using a general-purpose construction machine such as a backhoe while adding cement-based solidified material as powder. The method of stirring has been adopted.

【0003】しかしながら、粉体混合で発生する周囲へ
の粉塵公害や産業廃棄物となる使いきりコンテナバック
の処理問題が発生し、無粉塵タイプの粉体固化材の開発
や液状硬化材による対象地盤との混合攪拌が行なわれる
ようになってきた。
[0003] However, there is a problem of dust pollution to surroundings generated by powder mixing and a problem of disposal of a used-up container bag which becomes industrial waste. And the mixture has been stirred.

【0004】しかし、無粉塵タイプの粉体固化材では粉
塵は発生しないが、転圧、締め固めが必要であり、混合
攪拌操作に可なりの熟練が必要で操作技術者の熟練度に
よって混合攪拌精度にバラツキが生じ、場合によっては
施工をやり直さなければならないといった問題がある。
[0004] However, dust is not generated in the dust-free type powder solidifying material, but requires compaction and compaction, and requires considerable skill in the mixing and stirring operation. There is a problem that the accuracy varies, and in some cases, the construction must be redone.

【0005】また、これまでに開発された液状硬化材に
よる混合攪拌は、実公平5ー9070号公報に示されるよう
に混合攪拌器の先端から掘進方向に混合液の吐出が行わ
れるため、掘進時に吐出口が目詰まりし絶えず吐出口を
清掃しなければならない問題があるほか、混合液が掘進
方向に対して筋状に吐出されるため地盤との攪拌が均質
に行われ難いという問題もある。
[0005] Further, in the mixing and stirring using the liquid hardening material developed so far, as shown in Japanese Utility Model Publication No. 5-9070, the mixture is discharged from the tip of the mixing stirrer in the excavation direction. In addition to the problem that the discharge port is sometimes clogged and the discharge port must be constantly cleaned, there is also a problem that it is difficult to uniformly mix the ground with the ground because the mixture is discharged in a streak shape in the excavation direction .

【0006】[0006]

【課題を解決するための手段】本発明は上記の課題に対
応してこれを解決するため、側壁に液状硬化材噴出孔を
備え、フォークブレードに同調して湾曲する液状硬化材
噴出ロッドをフォークブレードの中央部に配設したミキ
シングフォークにより、液状硬化材噴出孔から側方に液
状硬化材を噴出しながら対象地盤を掘削し、フォークブ
レードの作動によりすき取り削土と液状硬化材を混合攪
拌して改良硬化層を造成するようにしたものである。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, the present invention provides a liquid hardening material jetting rod which has a liquid hardening material jetting hole on a side wall and is curved in synchronization with a fork blade. Using a mixing fork located in the center of the blade, excavates the target ground while squirting the liquid hardening material laterally from the liquid hardening material ejection holes, and mixes and stirs the excavated soil with the liquid hardening material by operating the fork blade Thus, an improved hardened layer is formed.

【0007】すなわち、側壁に液状硬化材噴出孔を備え
た液状硬化材噴出ロッドをフォークブレードの中央部に
配設することにより、掘進方向に対して直交する側方に
液状硬化材が噴出され対象地盤に幕状に液状硬化材が散
布されて攪拌部に平均して混入されるので地盤との攪拌
が均質に行われる。
That is, by disposing a liquid hardening material ejection rod having a liquid hardening material ejection hole on the side wall at the center of the fork blade, the liquid hardening material is ejected laterally perpendicular to the excavation direction. Since the liquid hardening material is sprayed on the ground like a curtain and mixed with the stirring portion on average, the stirring with the ground is performed uniformly.

【0008】また、硬化材噴出孔が掘進方向に対して対
向することのない側方に向けられるようにして、噴出孔
に掘削土砂が入り込むことがなく、フォークの掘削作動
により噴出孔に目詰まりを生ずることがないようにし
た。
[0008] Further, the hardening material orifice is directed to the side that does not face the excavation direction, so that excavated earth and sand do not enter the orifice, and the orifice is clogged by the excavation operation of the fork. Did not occur.

【0009】更に、液状硬化材噴出孔の対面位置に、噴
出された硬化材噴流を所定方向に案内するガイドプレー
トを設定して、硬化材噴流の方向づけを行いフォークの
攪拌作動の対象部位に硬化材が集中的に注入されるよう
にした。
Further, a guide plate is provided at a position facing the liquid hardening material jetting hole to guide the jetted hardening material jet in a predetermined direction to orient the hardening material jet and harden the target portion of the fork stirring operation. The material was intensively injected.

【0010】また更に、液状硬化材噴出孔を張出ノズル
構造に構成し、ノズルの噴出流路内壁を螺旋構造に構成
して液状硬化材が旋回流として噴出されるようにし、対
象地盤への混入効果を高めるようにした。
[0010] Further, the liquid hardening material ejection hole is formed in an overhanging nozzle structure, and the inner wall of the jet flow path of the nozzle is formed in a spiral structure so that the liquid hardening material is jetted out as a swirling flow. The mixing effect was enhanced.

【0011】更にまた、硬化材噴出ロッドの前方に噴出
流が扇状に広がる液状硬化材噴出孔を設定するように
し、フォーク面と角度をなす方向に扇状に広がる硬化材
噴流を高圧噴射し、フォークが掘削する対象地盤の部位
に硬化材噴流による切削が行われるようにした。
Further, a liquid hardening material ejection hole in which the jet flow spreads in a fan shape in front of the hardening material ejection rod is set, and a high-pressure jet of the hardening material jet which spreads in a fan-shaped direction at an angle to the fork surface is provided. The cutting of the target ground excavated by the hardened material jet is performed.

【0012】[0012]

【発明の実施の形態】以下図面に従って本発明の実施例
を説明する。1はミキシングフォークで、中央部に側壁
に液状硬化材噴出孔21、21を備え、フォークブレードに
同調して湾曲する液状硬化材噴出ロッド2が配設され、
その両側にフォークブレード11、11が支持ロッド12、12
・・によって支持固設されている。
Embodiments of the present invention will be described below with reference to the drawings. Reference numeral 1 denotes a mixing fork, which is provided with liquid hardening material ejection holes 21 and 21 on a side wall at a central portion, and a liquid hardening material ejecting rod 2 which is curved in synchronization with a fork blade is provided.
Fork blades 11, 11 on both sides are supporting rods 12, 12
・ ・ Supported and fixed by

【0013】ミキシングフォーク1の先端側は、掘削刃
31、31・・を植設した掘削盤3、後端基部にはバックホ
ウシステム5への取付け部41、41を備えたベースポート
4となっており、ベースポート4には硬化材噴出ロッド
2に液状硬化材を供給する液状硬化材調製プラント6か
らの供給ホース42が連結されている。
The tip of the mixing fork 1 is a cutting edge.
The excavator 3 in which 31, 31,... Are planted, and the rear end base portion is a base port 4 having attachment portions 41, 41 to the backhoe system 5, and the base port 4 has a hardened material ejection rod 2. A supply hose 42 from the liquid curing material preparation plant 6 for supplying the liquid curing material is connected.

【0014】フォークブレード11、11には、その側面に
攪拌翼13、13・・が適宜植設され、ミキシングフォーク
1の作動時に対象地盤を反転攪拌するようになってい
る。
The fork blades 11, 11 are appropriately provided with stirring blades 13, 13,... On their side surfaces, so that the target ground is inverted and stirred when the mixing fork 1 is operated.

【0015】また、液状硬化材噴出ロッド2の硬化材噴
出孔21、21の対面位置には、硬化材噴流を所定方向に案
内するガイドプレート14、14が設定され、噴出孔21、21
から噴出された硬化材噴流の方向づけを行うようになっ
ている。
Further, guide plates 14, 14 for guiding the hardening material jet in a predetermined direction are set at positions facing the hardening material jetting holes 21, 21 of the liquid hardening material jetting rod 2, and the jetting holes 21, 21 are provided.
The direction of the hardening material jet flow ejected from the nozzle is determined.

【0016】更に、対象地盤の状況に応じて、硬化材噴
出孔21、21を張出ノズル22、22に構成し、ノズル22、22
の噴出流路内壁を螺旋構造に構成して液状硬化材が旋回
流として噴出されるようにし、対象地盤への混入効果を
高めるようにする。この場合、状況によってはガイドプ
レート14、14を設定しないで旋回流の効果を活用するよ
うにする。なお、ガイドプレート14を設定せず、張出ノ
ズル22にも構成せずに噴出孔21のままでも良いことは勿
論である。
Further, according to the condition of the target ground, the hardening material ejection holes 21, 21 are formed as overhanging nozzles 22, 22, and the nozzles 22, 22 are provided.
The inner wall of the ejection flow path is formed in a spiral structure so that the liquid hardening material is ejected as a swirling flow, thereby enhancing the effect of mixing into the target ground. In this case, depending on the situation, the effect of the swirling flow is utilized without setting the guide plates 14 and 14. It is needless to say that the guide plate 14 is not set, and the ejection hole 21 may be left as it is without configuring the projecting nozzle 22.

【0017】また、もう一つの実施例の場合は、砂質土
や砂礫層のような硬質地盤に適用するもので、図3、図
4に示すように硬化材噴出ロッド2の前方に液状硬化材
噴出孔21が設定され、噴出流が扇状に広がるノズルチッ
プがこれに嵌装されて、フォーク面と角度をなす方向に
扇状に広がる硬化材噴流が対向地盤に向けて高圧噴射さ
れるように構成される。
In another embodiment, the present invention is applied to a hard ground such as a sandy soil or a gravel layer. As shown in FIGS. The material jet hole 21 is set, and the nozzle tip where the jet flow spreads in a fan shape is fitted into this, so that the hardened material jet that spreads in a fan shape in the direction making an angle with the fork surface is injected at high pressure toward the opposed ground. Be composed.

【0018】この場合は、液状硬化材の圧送は、100〜1
50kgf/m2 程度の高圧噴射によって行われ、フォーク
が掘削する対象地盤の部位Bに硬化材噴流による切削が
行われて事前に掘削地盤の予備切削が行われる形とな
る。
In this case, the pressure of the liquid hardening material is 100 to 1
The cutting is performed by high pressure injection of about 50 kgf / m 2, and the cutting is performed by a hardened material jet on the portion B of the target ground to be excavated by the fork, so that the preliminary cutting of the excavated ground is performed in advance.

【0019】液状硬化材調製プラント6は、セメント系
固化材を供給する硬化材サイロ61から計量器64を通じて
供給されるセメント系固化材と水タンク63からポンプ65
により供給される水とをスラリー調合プラント62におい
て、W/C(水セメント比)100〜150%に調合し、圧送
ポンプ66により供給ホース42を通じて噴出ロッド2に供
給するものである。
The liquid hardening material preparation plant 6 includes a cement hardening material supplied from a hardening material silo 61 for supplying a cement hardening material through a measuring device 64 and a water tank 63 to a pump 65.
Is supplied to the jetting rod 2 through the supply hose 42 by the pressure pump 66 at a slurry / mixing plant 62 where the W / C (water / cement ratio) is adjusted to 100-150%.

【0020】地盤改良の施工は、先ず、対象地盤の区割
りによりホース配管、硬化材量の設定等を行ったうえ、
上記のように構成されたミキシングフォーク装置によ
り、空掘り部のすき取り等の環境設定を行い、液状硬化
材噴出ロッド2に液状硬化材を圧送して硬化材噴出孔2
1、21から噴出もしくは噴射しながらミキシングフォー
クを作動して対象地盤Aを掘削すると共に掘削土の混合
攪拌を行う。
In the construction of the ground improvement, first, the hose piping and the amount of the hardening material are set according to the division of the target ground, and the like.
With the mixing fork device configured as described above, the environment such as clearance of the digging portion is set, and the liquid hardening material is pressure-fed to the liquid hardening material ejection rod 2 so that the hardening material ejection hole 2 is formed.
The mixing fork is operated while squirting or squirting from 1, 21 to excavate the target ground A and mix and agitate the excavated soil.

【0021】液状硬化材の圧送は、施工環境によって異
なるが、通常は10〜25kgf /m2 程度で行い、液状硬化
材吐出量は1m3 当たり 200リットル程度である。しか
し、前記した他の実施例のように施工環境によっては10
0〜150kgf/m2 程度の高圧噴射を行う場合もある。
The pressure-feeding of the liquid hardening material depends on the working environment, but is usually performed at about 10 to 25 kgf / m 2 , and the discharge amount of the liquid hardening material is about 200 liters per m 3 . However, depending on the construction environment as in the other embodiments described above, 10
In some cases, high pressure injection of about 0 to 150 kgf / m 2 is performed.

【0022】硬化材噴出孔21から噴出もしくは噴射され
る液状硬化材は、対象地盤に掘削挿入される掘削刃31、
31・・とフォークブレード11に並列する硬化材噴出ロッ
ド2によって掘削土中に噴入され掘削刃31、31・・、フ
ォークブレード11と攪拌翼13、13・・の作動により、掘
削土と混合攪拌される。
The liquid hardening material blown out or injected from the hardening material blowout hole 21 is provided with a cutting blade 31, which is drilled and inserted into the target ground,
31 .... and the hardened material spout rod 2 parallel to the fork blade 11 are injected into the excavated soil and mixed with the excavated soil by the operation of the excavating blades 31, 31, ..., the fork blade 11 and the stirring blades 13, 13, ... Stirred.

【0023】掘削が所定深度まで達したところで、硬化
材吐出量が設定量に達していることを確認し硬化材の圧
送を停止する。硬化材の圧送停止後、更に均しによる攪
拌混合を行い表面仕上げと整地をした後、確認試験を行
って施工を終わる。
When the excavation reaches a predetermined depth, it is confirmed that the discharge amount of the hardening material has reached the set amount, and the feeding of the hardening material is stopped. After stopping the pressure feed of the hardening material, the mixture is further stirred and mixed by leveling to perform surface finishing and leveling, and then a confirmation test is performed to complete the construction.

【0024】なお、ミキシングフォーク装置は、対象地
盤の区割り設定により数台を並列して施工することも可
能である。
It should be noted that several mixing forks can be installed in parallel by setting the division of the target ground.

【0025】[0025]

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例を示すもので、施工状況を示す
全体側面図
FIG. 1 shows an embodiment of the present invention, and is an overall side view showing a construction state.

【図2】同じく本発明による実施例を示すもので、硬化
材噴出ロッドに張出ノズルとガイドプレートを設定した
ミキシングフォークの拡大斜視図
FIG. 2 is an enlarged perspective view of a mixing fork in which a protruding nozzle and a guide plate are set on a hardening material ejection rod, similarly showing an embodiment according to the present invention.

【図3】同じく本発明による実施例を示すもので、硬化
材噴出ロッドの前方に噴出流が扇状に広がる硬化材噴出
孔を設定したミキシングフォークの拡大斜視図
FIG. 3 is an enlarged perspective view of a mixing fork in which a hardening material ejection hole in which an ejection flow spreads in a fan shape in front of a hardening material ejection rod according to the embodiment of the present invention.

【図4】同じく本発明による実施例を示すもので、硬化
材噴出ロッドの前方に噴出流が扇状に広がる硬化材噴出
孔を設定した場合の、対象地盤に対する硬化材噴出状況
を示すミキシングフォークの掘削状況側面図
FIG. 4 shows an embodiment according to the present invention, in which a hardening material ejection hole is set in front of a hardening material ejection rod and a hardening material ejection hole spreads in a fan shape. Excavation situation side view

【符号の説明】[Explanation of symbols]

1 ミキシングフォーク 11 フォークブレード 12 支持ロッド 13 フォークブレードの攪拌翼 14 ガイドプレート 2 液状硬化材噴出ロッド 21 硬化材噴出孔 22 張出ノズル 3 掘削盤 31 掘削刃 4 ベースポート 41 バックホウシステムへの取付け部 42 液状硬化材供給ホース 5 バックホウシステム 6 液状硬化材調製プラント 61 硬化材サイロ 62 スラリー調合プラント 63 水タンク 64 硬化材計量器 65 水ポンプ 66 スラリー圧送ポンプ A 対象地盤 B 予備切削部位 DESCRIPTION OF SYMBOLS 1 Mixing fork 11 Fork blade 12 Support rod 13 Stirring blade of fork blade 14 Guide plate 2 Liquid hardening material ejection rod 21 Hardening material ejection hole 22 Overhang nozzle 3 Drilling machine 31 Drilling blade 4 Base port 41 Mounting part to backhoe system 42 Liquid hardening material supply hose 5 Backhoe system 6 Liquid hardening material preparation plant 61 Hardening material silo 62 Slurry preparation plant 63 Water tank 64 Hardening material meter 65 Water pump 66 Slurry pump A

───────────────────────────────────────────────────── フロントページの続き Fターム(参考) 2D012 DA00 2D040 AB11 AC05 BA13 BB03 CA01 CB03 DA11 DA16 EA01 EB04 ──────────────────────────────────────────────────続 き Continued on the front page F term (reference) 2D012 DA00 2D040 AB11 AC05 BA13 BB03 CA01 CB03 DA11 DA16 EA01 EB04

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 側壁に液状硬化材噴出孔を備え、フォー
クブレードに同調して湾曲する液状硬化材噴出ロッドを
フォークブレードの中央部に配設したミキシングフォー
クにより、液状硬化材噴出孔から液状硬化材を噴出もし
くは高圧噴射しながら、対象地盤を掘削し、フォークブ
レードの作動によりすき取り削土と液状硬化材を混合攪
拌して改良硬化層を造成することを特徴とする混合攪拌
による地盤改良工法
1. A liquid hardening material jetting hole is provided on a side wall, and a liquid hardening material jetting rod, which is curved in synchronization with a fork blade, is disposed at a central portion of the fork blade. Ground improvement method by mixing and agitation characterized by excavating the target ground while blasting or injecting high-pressure material, and mixing and stirring the excavated soil and liquid hardening material by operating a fork blade to create an improved hardened layer
【請求項2】 先端部側壁に液状硬化材噴出孔を備え、
フォークブレードに同調して湾曲する液状硬化材噴出ロ
ッドをフォークブレードの中央部に配設したミキシング
フォークを、液状硬化材の供給機構に連絡するバックホ
ウシステムに装着して成る混合攪拌による地盤改良装置
2. A liquid hardening material ejection hole is provided in a side wall of the tip portion,
A ground improvement device by mixing and stirring, in which a mixing fork in which a liquid hardening material ejection rod that curves in synchronization with a fork blade is arranged at the center of the fork blade is attached to a backhoe system that communicates with a liquid hardening material supply mechanism
【請求項3】 液状硬化材噴出孔の対面位置に、噴出さ
れた硬化材噴流を所定方向に案内するガイドプレートを
設定するようにした請求項2記載の混合攪拌による地盤
改良装置
3. A ground improvement apparatus by mixing and stirring according to claim 2, wherein a guide plate for guiding the jetted hardening material jet in a predetermined direction is set at a position facing the liquid hardening material jetting hole.
【請求項4】 液状硬化材噴出孔を張出ノズル構造に構
成し、ノズルの噴出流路内壁を螺旋構造に構成するよう
にした請求項2又は請求項3記載の混合攪拌による地盤
改良装置
4. The ground improvement apparatus by mixing and stirring according to claim 2, wherein the liquid hardening material ejection hole is formed in a projecting nozzle structure, and an inner wall of the nozzle ejection passage is formed in a spiral structure.
【請求項5】 硬化材噴出ロッドの前方に噴出流が扇状
に広がる液状硬化材噴出孔を設定するようにした請求項
2記載の混合攪拌による地盤改良装置
5. A ground improvement device by mixing and stirring according to claim 2, wherein a liquid hardening material jetting hole in which the jet flow spreads in a fan shape in front of the hardening material jetting rod.
JP26797399A 1999-09-22 1999-09-22 Ground improvement method by mixing and stirring and its equipment. Expired - Fee Related JP3298054B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26797399A JP3298054B2 (en) 1999-09-22 1999-09-22 Ground improvement method by mixing and stirring and its equipment.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26797399A JP3298054B2 (en) 1999-09-22 1999-09-22 Ground improvement method by mixing and stirring and its equipment.

Publications (2)

Publication Number Publication Date
JP2001090059A true JP2001090059A (en) 2001-04-03
JP3298054B2 JP3298054B2 (en) 2002-07-02

Family

ID=17452165

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26797399A Expired - Fee Related JP3298054B2 (en) 1999-09-22 1999-09-22 Ground improvement method by mixing and stirring and its equipment.

Country Status (1)

Country Link
JP (1) JP3298054B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002332628A (en) * 2001-05-09 2002-11-22 Area Creation:Kk Soil improvement device and sheet pile driving method
JP2009057748A (en) * 2007-08-31 2009-03-19 Furoo Techno Kk Agitator for shallow ground improvement, shallow ground improver, shallow ground improvement system, construction method for improving shallow ground, and construction method for improving contaminated soil

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002332628A (en) * 2001-05-09 2002-11-22 Area Creation:Kk Soil improvement device and sheet pile driving method
JP4577601B2 (en) * 2001-05-09 2010-11-10 株式会社エリア・クリエイション Recess formation method by burying sheet piles
JP2009057748A (en) * 2007-08-31 2009-03-19 Furoo Techno Kk Agitator for shallow ground improvement, shallow ground improver, shallow ground improvement system, construction method for improving shallow ground, and construction method for improving contaminated soil

Also Published As

Publication number Publication date
JP3298054B2 (en) 2002-07-02

Similar Documents

Publication Publication Date Title
KR101990289B1 (en) Apparatus for ground improvement
JP2620043B2 (en) Ground improvement device and ground improvement method
JP2620042B2 (en) Ground improvement device and ground improvement method
JP5015493B2 (en) Ground improvement device and ground improvement machine
KR100709936B1 (en) Mobile-type soil improver
KR100797845B1 (en) Deep mixing wall-foundation system
JP3298054B2 (en) Ground improvement method by mixing and stirring and its equipment.
JP3547096B2 (en) Fore pile construction method and drilling equipment used for it
JP2005324283A (en) Spray nozzle and injection device using the same
JP3825550B2 (en) Ground improvement and solidified wall construction equipment
JP2023072747A (en) Excavation and agitation device and deep mixing method
JP3357648B2 (en) Cavitation jet ground hardened layer formation method and device by differential pressure confluence
JPH0885940A (en) Mixing method with stirring
JP4615841B2 (en) Synthetic pile construction method and synthetic pile
KR200261599Y1 (en) Base improvement reinforcement system and device
JP2645322B2 (en) Construction method of soil cement composite pile
JP3260337B2 (en) Ground improvement device and ground improvement method
JPS5939039B2 (en) Shield excavation method and device
JP3003538B2 (en) Construction method of mud solidification wall
JP2002302934A (en) Construction method and device for forming hardening layer using slime
JP2006322190A (en) Pile head processing method of cast-in-place concrete pile and concrete processing agent mixing device
JPH03267492A (en) Underground hole excavator
JPS6314923A (en) Method for stirring and mixing earth by multiple shaft excavator
JP3886433B2 (en) Ground hardening layer construction method and equipment
JPH10183602A (en) Air bubble generating method for cement slurry for soil improvement and its equipment

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
R150 Certificate of patent or registration of utility model

Ref document number: 3298054

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080419

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110419

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120419

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130419

Year of fee payment: 11

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140419

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees