JP2001034321A - Method and device for preparing optimum production plan - Google Patents

Method and device for preparing optimum production plan

Info

Publication number
JP2001034321A
JP2001034321A JP11209120A JP20912099A JP2001034321A JP 2001034321 A JP2001034321 A JP 2001034321A JP 11209120 A JP11209120 A JP 11209120A JP 20912099 A JP20912099 A JP 20912099A JP 2001034321 A JP2001034321 A JP 2001034321A
Authority
JP
Japan
Prior art keywords
load
production plan
product
unit
bottleneck
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11209120A
Other languages
Japanese (ja)
Inventor
Noriyuki Yasuo
典之 安尾
Taizo Kominami
泰三 小南
Koichi Narahara
康一 楢原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Holdings Corp
Original Assignee
Matsushita Electric Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Electric Industrial Co Ltd filed Critical Matsushita Electric Industrial Co Ltd
Priority to JP11209120A priority Critical patent/JP2001034321A/en
Publication of JP2001034321A publication Critical patent/JP2001034321A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

PROBLEM TO BE SOLVED: To prepare a production plan capable of averaging loads in each unit of packet in both of a production assembling process and a source process to be a bottleneck. SOLUTION: The load is averaged in each unit of packet in both of a product assembling process and a source process to be a bottleneck on the basis of order receiving information necessary for preparing a production plan 11 consisting of plural processes, basic data of a product included in the order receiving information, the basic data of a unit 10 constituting the product and source process information for preparing the unit 10.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、製品組立工程とボ
トルネックとなる源泉工程の両方でバケット単位の負荷
平準化を図った最適生産計画を作成する最適生産計画作
成方法及び装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for creating an optimum production plan in which a load is leveled in bucket units in both a product assembling process and a bottleneck source process. .

【0002】[0002]

【従来の技術】近年、スケジューリングシステムは、注
文納期を遵守しながら既存設備の高稼働率の維持及び切
替回数削減を達成する生産計画の自動作成手段として注
目されている。
2. Description of the Related Art In recent years, a scheduling system has attracted attention as a means for automatically creating a production plan that maintains a high operation rate of existing equipment and reduces the number of times of switching while complying with order delivery dates.

【0003】従来は、研究開発のレベルにとどまってい
たが、近年になりコンピュータの低価格化、高速化が飛
躍的に進んだのと、人工知能、シミュレーション手法な
どの自動立案を支えるソフト技術が完成したことによ
り、実用に値するスケジューリングシステムパッケージ
が数多く提案されるに至っている。
[0003] In the past, the level of research and development was limited, but in recent years the cost and speed of computers have been dramatically reduced, and software technologies that support automatic planning such as artificial intelligence and simulation methods have been developed. With its completion, many practical scheduling system packages have been proposed.

【0004】以下に、従来のスケジューリングシステム
による生産計画立案方法について説明する。図7におい
て、1は受注情報を入力するための入力装置、2はデー
タを記憶するための記憶装置、3は中央処理装置、4は
結果を表示する表示装置、5は結果を印字する印字装
置、6は入力装置1で入力した受注情報を一定期間分登
録した受注データ、7は設備余剰能力データ、8は製品
マスタ、11は作成された生産計画、22は生産計画立
案手段である。
[0004] A production planning method using a conventional scheduling system will be described below. 7, 1 is an input device for inputting order information, 2 is a storage device for storing data, 3 is a central processing unit, 4 is a display device for displaying results, and 5 is a printing device for printing results. Reference numeral 6 denotes order data in which the order information input by the input device 1 is registered for a certain period of time, 7 denotes equipment surplus capacity data, 8 denotes a product master, 11 denotes a created production plan, and 22 denotes a production plan drafting means.

【0005】次に、動作を説明すると、まず担当者が電
話、FAXなどで受けた受注情報を入力装置1を用いて
受注データ6に登録する。なお、受注情報には生産計画
立案に必要な製品データ、納期情報、数量などが含まれ
る。登録結果は、1日〜1ケ月の一定期間蓄積される。
そして、定期的に受注データ6と設備余剰能力データ7
と製品マスタ8をもとに生産計画立案手段22により生
産計画11を作成する。生産計画11は表示装置4及び
印字装置5を用いて画面への表示及び紙への印刷が行わ
れる。
Next, the operation will be described. First, the person in charge registers order information received by telephone, facsimile or the like in the order data 6 using the input device 1. Note that the order information includes product data, delivery date information, quantities, and the like necessary for production planning. The registration result is accumulated for a certain period of one day to one month.
The order data 6 and the surplus capacity data 7
The production plan 11 is created by the production plan drafting unit 22 based on the product master 8 and the product master 8. In the production plan 11, display on the screen and printing on paper are performed using the display device 4 and the printing device 5.

【0006】生産計画立案手段22は、受注データ6に
含まれる数量と製品マスタ8に含まれるタクトタイムを
乗じた負荷を考慮して納期内に生産が完了する生産計画
を立案する。
[0006] The production plan drafting means 22 drafts a production plan to complete the production within the due date in consideration of the load obtained by multiplying the quantity included in the order data 6 and the takt time included in the product master 8.

【0007】[0007]

【発明が解決しようとする課題】しかしながら、上記生
産計画作成装置は、受注に対して生産を行う単一工程の
生産計画作成を目的としている。例えば、顧客注文に対
しての組立工程生産計画作成、あるいは組立工程生産計
画に対しての源泉工程生産計画作成である。
SUMMARY OF THE INVENTION However, the above-mentioned production plan creating apparatus aims at creating a single-step production plan for producing an order. For example, creation of an assembly process production plan for a customer order or creation of a source process production plan for an assembly process production plan.

【0008】近年、源泉工程から組立工程までのトータ
ル生産リードタイム短縮が要求され、工場トータルとし
ての生産計画作成の必要性が高まっている。
In recent years, it has been required to reduce the total production lead time from the source process to the assembly process, and the need to create a production plan as a whole factory has been increasing.

【0009】上記生産計画作成装置を用いて工場トータ
ルの生産計画を作成する手順は次のようになる。 1)顧客注文に対して組立工程生産計画を作成する 2)組立工程生産計画を注文とし、それに対して源泉工
程生産計画を作成する 3)源泉工程が複数存在する場合は2)の処理を繰り返
す 工程の生産能力バランスが取れている場合は、上記手順
で工場トータルの生産計画を作成することができる。
The procedure for creating a factory-wide production plan using the above-described production plan creation apparatus is as follows. 1) Create an assembly process production plan for a customer order 2) Create an assembly process production plan as an order and create a source process production plan for it 3) If there are multiple source processes, repeat step 2) When the production capacity of the process is balanced, a factory-wide production plan can be created by the above procedure.

【0010】ところが、実際の生産現場では、組立工程
と源泉工程間の生産能力バランスがとれていない場合が
多く、そのような状態で上記手順により生産計画を作成
すると、組立工程の生産計画は作成できても、源泉工程
の生産計画作成では次のような問題が発生する。 1)生産能力不足のため組立工程の注文納期に遅れる 2)源泉工程が遅れることを見越して組立工程が注文を
前倒しする 3)前倒しの結果、源泉工程の負荷が前半集中になり、
さらに組立注文に遅れる 工程全体での設備能力不足は、稼働延長、設備追加、外
部への生産委託により解消できるが、一定期間内の負荷
平準化は、上記工程生産計画の段階から考慮しないと達
成できない。ところが、従来の生産計画作成装置は、源
泉工程側の負荷状況を考慮していないため、負荷平準化
は不可能である。
However, in an actual production site, the production capacity is often not balanced between the assembling process and the source process. In such a state, if a production plan is created by the above procedure, the production plan for the assembling process is created. Even if possible, the following problems occur in the production planning of the source process. 1) Delay in order delivery of assembly process due to insufficient production capacity 2) Order of assembly process is advanced in anticipation of delay of source process 3) As a result of advance, load of source process is concentrated in the first half,
Insufficient equipment capacity for the entire process can be resolved by extending the operation, adding equipment, or outsourcing production.However, load leveling within a certain period can be achieved without considering the above process production planning stage. Can not. However, the conventional production plan creation device does not consider the load situation on the source process side, so that load leveling is impossible.

【0011】本発明は、上記従来の問題点に鑑み、製品
組立工程とボトルネックとなる源泉工程の両方でバケッ
ト単位の負荷平準化を図った生産計画を作成する最適生
産計画作成方法及び装置を提供することを目的としてい
る。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned conventional problems, and provides an optimum production plan creation method and apparatus for creating a production plan in which a load is leveled in bucket units in both a product assembly process and a bottleneck source process. It is intended to provide.

【0012】[0012]

【課題を解決するための手段】本発明の最適生産計画作
成方法は、複数工程の生産計画を作成する際に必要な受
注情報と、受注情報に含まれる製品に関する基礎データ
と、製品を構成するユニットに関する基礎データと、ユ
ニットを生産する源泉工程情報をもとに、製品組立工程
とボトルネックとなる源泉工程の両方でバケット単位の
負荷平準化を図るものであり、製品組立工程とボトルネ
ックとなる源泉工程の両方でバケット単位で負荷平準化
した生産計画を作成できる。ここで、バケットとは、例
えば1週間単位といった受注を割付ける期間の単位であ
り、本発明により受注をバケット毎に負荷を平準化して
割付けることができる。なお、バケットのサイズは本生
産計画作成方法を適応する工場により異なる。
According to the present invention, there is provided an optimum production plan creating method comprising: order information necessary for creating a production plan of a plurality of processes; basic data on a product included in the order information; Based on basic data about the unit and information on the source process that produces the unit, load leveling is performed for each bucket in both the product assembly process and the bottleneck source process. It is possible to create a load-balanced production plan for both source processes. Here, the bucket is a unit of a period in which orders are allocated, for example, on a weekly basis, and according to the present invention, orders can be allocated by leveling the load for each bucket. Note that the size of the bucket differs depending on the factory to which the production plan creation method is applied.

【0013】具体的には、全ての受注情報に対して組立
工程負荷とボトルネック工程負荷を計算する過程と、組
立工程とボトルネック工程の負荷値を偏差値に変換して
分散を一致させる過程と、全ての受注情報に対して両工
程の偏差値を重み係数Wを用いて結合した負荷評価値を
計算する過程と、負荷評価値を用いて受注をバケットに
割り付ける過程と、割付結果の負荷平準度を求める過程
と、負荷平準度を向上させるべく重み係数Wを更新して
負荷評価値を計算する過程に戻る過程にて最適な負荷平
準度が得られるバケット割付を求めるものである。
More specifically, a process of calculating the assembly process load and the bottleneck process load for all the order information, and a process of converting the load values of the assembly process and the bottleneck process into deviation values to match the variances. A process of calculating a load evaluation value obtained by combining the deviation values of both processes with respect to all order information using a weight coefficient W; a process of assigning an order to a bucket using the load evaluation value; The bucket allocation for obtaining the optimum load level is obtained in the process of obtaining the level and the process of returning to the process of calculating the load evaluation value by updating the weight coefficient W to improve the load level.

【0014】詳しくは、次のような段階にて作成する。More specifically, it is created at the following stage.

【0015】1)それぞれの受注情報に対して組立工程
負荷を計算する。
1) An assembly process load is calculated for each order information.

【0016】ここで、組立工程負荷は(数1)のように
製品に関する基礎データより組立標準工数を獲得し、こ
れに受注台数を乗じて得る。
Here, the assembling process load is obtained by obtaining an assembling standard man-hour from basic data on a product and multiplying it by the number of orders as shown in (Equation 1).

【0017】[0017]

【数1】 2)それぞれの受注情報に対してボトルネック工程負荷
を計算する。
(Equation 1) 2) Calculate the bottleneck process load for each order information.

【0018】ここで、ユニット及び部品ごとの負荷は製
品に関する基礎データよりボトルネック工程において生
産されるユニット及び部品の一覧及び員数を獲得し、次
にそのユニット及び部品に関する基礎データよりマシン
タクトを獲得し、(数2)のようにユニット及び部品そ
れぞれに対して受注台数と員数とマシンタクトを乗じて
得る。次いで、(数3)のように受注情報に対してのボ
トルネック工程負荷を、(数2)の値を合計して得る。
Here, the load of each unit and part obtains a list and the number of units and parts produced in the bottleneck process from the basic data on the product, and then obtains the machine tact from the basic data on the unit and part. Then, as shown in (Equation 2), it is obtained by multiplying the number of orders, the number of members, and the machine tact for each of the units and parts. Next, the bottleneck process load on the order information as in (Equation 3) is obtained by summing the values in (Equation 2).

【0019】[0019]

【数2】 (Equation 2)

【0020】[0020]

【数3】 3)組立工程とボトルネック工程の負荷分散状態を一致
させる。
(Equation 3) 3) Match the load distribution state in the assembly process and the bottleneck process.

【0021】組立工程負荷は一般的に工数のため分単位
となる。また源泉工程はタクトタイムのため秒単位、さ
らに実装工程などでは打点数などと、工程間で負荷の単
位が一致しない。また、負荷のばらつきも異なるため、
(数1)と(数3)を同じ分散の値とはみなすことがで
きない。そこで、それぞれを元の負荷集合に対しての偏
差値に変換する。例えば組立工程負荷に関する変換式は
(数4)のようになる。このような変換により組立工程
とボトルネック工程の負荷は両方とも平均50、分散1
0になる。
The assembly process load is generally a minute unit because of the man-hour. In addition, the source process has a tact time, and the load unit does not coincide with the number of dots in the mounting process. Also, since the load variation is different,
(Equation 1) and (Equation 3) cannot be regarded as having the same variance. Therefore, each is converted into a deviation value with respect to the original load set. For example, a conversion formula relating to the assembly process load is as shown in (Equation 4). With such a conversion, the loads of the assembly process and the bottleneck process are both 50 on average and 1 variance.
It becomes 0.

【0022】[0022]

【数4】 4)それぞれの受注情報に対して負荷評価値を計算す
る。
(Equation 4) 4) A load evaluation value is calculated for each order information.

【0023】ここで、負荷評価値は(数5)のように、
組立工程負荷(数1)の偏差値とボトルネック工程負荷
(数3)の偏差値を重み係数Wを用いて結合したもので
ある。Wは0から1の範囲の値をとる。本発明ではこの
Wが操作変数となる。
Here, the load evaluation value is given by
The deviation value of the assembly process load (Equation 1) and the deviation value of the bottleneck process load (Equation 3) are combined using a weight coefficient W. W takes a value in the range of 0 to 1. In the present invention, this W is an operation variable.

【0024】[0024]

【数5】 5)評価値を用いて以下の手順で受注をバケットに割り
付ける。
(Equation 5) 5) Assign orders to buckets using the evaluation values in the following procedure.

【0025】5−1)未割付受注の中で最大の負荷評価
値の受注を選択する。
5-1) Select the order with the largest load evaluation value among the unassigned orders.

【0026】5−2)負荷評価値合計が最小のバケット
に5−1)で選択した受注を割り付ける。
5-2) Allocate the order selected in 5-1) to the bucket having the smallest load evaluation value.

【0027】5−3)全ての受注がバケットに割り付く
まで5−1)に戻る。この過程により負荷評価値での大
まかな平準化が行われる。
5-3) Return to 5-1) until all orders are allocated to buckets. Through this process, rough leveling with the load evaluation value is performed.

【0028】6)割付結果の負荷平準度を求める。6) Calculate the load level as a result of the allocation.

【0029】ここで、負荷平準度は(数6)で求められ
る。なお、(数6)中、LAk は組立工程バケットkの
負荷、LPk はボトルネック工程バケットの負荷、SLA
はLAk の偏差値、SLPはLPk の偏差値である。すな
わち負荷平準度は5)で行った負荷評価値の平準化が実
際の負荷値ではどの程度平準化されたのかを示してい
る。
Here, the load level is obtained by (Equation 6). In equation (6), LA k is the load of the assembly process bucket k, LP k is the load of the bottleneck process bucket, and S LA
Is the deviation value of LA k and S LP is the deviation value of LP k . That is, the load level indicates how much the leveling of the load evaluation value performed in 5) is leveled with the actual load value.

【0030】[0030]

【数6】 7)負荷平準度を向上させるべくWの値を更新し、手順
4)に戻る。
(Equation 6) 7) Update the value of W to improve the load level, and return to step 4).

【0031】ここで、Wと負荷平準度の関係は、図4の
ようになるので、一般的な最適化手法を用いて負荷平準
度が最小となるWを決定するのは困難であるため、以下
の手順でWを決定する。
Here, since the relationship between W and the load level is as shown in FIG. 4, it is difficult to determine W that minimizes the load level using a general optimization method. W is determined by the following procedure.

【0032】前処理1)Wを0から1まで一定幅で変化
させ、そのW毎に、上記手順4)〜6)を実行する。
Preprocessing 1) W is changed at a constant width from 0 to 1, and the above procedures 4) to 6) are executed for each W.

【0033】前処理2)負荷平準度が最小となるWを最
適化の初期値とする。
Preprocessing 2) The value W at which the load level is minimized is set as an initial value for optimization.

【0034】最適化処理)Wの値をシミュレーティッド
アニーリング法(SA法)を用いて更新し、最適なWの
値を決定する。
(Optimization process) The value of W is updated using the simulated annealing method (SA method), and the optimum value of W is determined.

【0035】なお、前処理1での一定幅を小さくすれ
ば、前処理2においてより適切な最適化初期値を得るこ
とができるが、前処理に要する計算量は増加する。図4
で示したWと負荷平準度の関係は、最適化対象としてい
る組立工程とボトルネック工程の特性に依存するため受
注状況が変化しても大きく変わらない。従って、一定幅
の設定方法は経験則で決定しても問題ない。また、前処
理段階での負荷平準度最適化で十分な場合はその際のバ
ケット割付状態を最適解としても問題ない。
If the fixed width in the pre-processing 1 is reduced, a more appropriate optimized initial value can be obtained in the pre-processing 2, but the amount of calculation required for the pre-processing increases. FIG.
The relationship between W and the load leveling indicated by depends on the characteristics of the assembling process and the bottleneck process to be optimized, and therefore does not change significantly even if the order receiving status changes. Therefore, there is no problem even if the method of setting the fixed width is determined by an empirical rule. If the load leveling optimization in the preprocessing stage is sufficient, there is no problem even if the bucket allocation state at that time is set as the optimal solution.

【0036】また、上記SA法は、近傍解を順次求めて
いく際、確率的に目的関数すなわち負荷平準度の増加を
受け入れる最適化手法で、局所解への収束を防ぐのに効
果的である。ただし、多峰性を有する場合は最適解が初
期値に依存する可能性が高いため、前処理のような粗い
最適化探索による初期値の設定が有効である。
Further, the SA method is an optimization method that stochastically accepts an increase in the objective function, that is, the load leveling level, when sequentially finding a neighborhood solution, and is effective in preventing convergence to a local solution. . However, in the case of multi-modality, since the optimal solution is highly likely to depend on the initial value, setting of the initial value by a rough optimization search such as preprocessing is effective.

【0037】また、本発明の最適生産計画作成装置は、
受注情報、製品基礎データ、ユニット基礎データの入力
装置と、これらのデータを常時記憶しておく記憶装置
と、作成結果を表示する表示装置と、作成結果を印字す
る印字装置と、入力装置、記憶装置、印字装置を統括的
に管理するとともに請求項1又は2記載の生産計画作成
方法を実行する生産計画作成手段を有する中央処理装置
を備えたものであり、受注情報が入力装置から入力され
ると、記憶装置に記憶された製品及びユニット基礎デー
タを用いて上記生産計画作成方法によりバケット単位の
負荷平準化をした生産計画が作成され、それが表示装置
あるいは印字装置によって担当者が理解できるように画
面表示あるいは紙に印刷される。さらにはデータとして
従来の生産計画立案手法に基づいたスケジューリングシ
ステムに渡され、日別順序計画を作成するための元デー
タとして利用される。
Further, the optimum production plan creating device of the present invention
Input device for order information, product basic data, unit basic data, storage device for constantly storing these data, display device for displaying the created result, printing device for printing the created result, input device, storage And a central processing unit having a production plan creation means for executing the production plan creation method according to claim 1 or 2, and receiving order information from an input device. And a production plan in which the load is leveled in bucket units is created by the above-described production plan creation method using the product and unit basic data stored in the storage device, and the production plan can be understood by a person in charge by a display device or a printing device. Is displayed on the screen or printed on paper. Further, the data is passed as data to a scheduling system based on a conventional production planning method, and is used as original data for creating a daily sequence plan.

【0038】[0038]

【発明の実施の形態】以下、本発明の最適生産計画作成
方法及び装置の一実施形態について、図1〜図6を参照
して説明する。なお、ボトルネック工程は実装工程を例
にして以下説明する。マスプロ製品の場合は、組立工程
と実装工程の一貫生産を行う必要があるので、実装工程
に限らずボトルネック工程は存在しないのが原則であ
る。さらに、マスプロ製品の場合は専用LSIなどによ
りプリント基板も1枚に集約されている。ところが、多
品種少量生産の場合は、コスト的に専用LSIが開発で
きないため1製品当たりのプリント基板が10枚以上の
構成となり、実装工程がボトルネック工程となることが
多い。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of an optimum production plan creating method and apparatus according to the present invention will be described below with reference to FIGS. The bottleneck process will be described below by taking a mounting process as an example. In the case of mass production products, it is necessary to perform integrated production of the assembling process and the mounting process. Therefore, in principle, there is no bottleneck process in addition to the mounting process. Further, in the case of mass production products, the printed circuit boards are also integrated into one by a dedicated LSI or the like. However, in the case of high-mix low-volume production, a dedicated LSI cannot be developed in terms of cost, so that the number of printed boards per product is ten or more, and the mounting process often becomes a bottleneck process.

【0039】本実施形態の生産計画作成装置の構成を示
す図1において、1はデータを入力するための入力装
置、2はデータを記憶するための記憶装置、3は中央処
理装置、4は結果を表示する表示装置、5は結果を印字
する印字装置、6は受注データ、8は製品毎に組立標準
工数を含む基礎データを記憶させた製品マスタ、9は製
品毎にボトルネック工程となるユニット及び部品の構成
を記憶させた部品構成マスタ、10はユニット及び部品
の基礎データを記憶させたユニット・部品マスタ、11
は作成された生産計画、12は生産計画作成手段であ
る。
In FIG. 1 showing the configuration of the production plan creating apparatus of the present embodiment, 1 is an input device for inputting data, 2 is a storage device for storing data, 3 is a central processing unit, and 4 is a result. , A display device for displaying the results, a printing device for printing the results, 6 for order data, 8 for a product master storing basic data including the standard assembly man-hours for each product, and 9 for a unit serving as a bottleneck process for each product And a component / configuration master storing component configurations, 10 is a unit / component master storing basic data of units and components, 11
Is a created production plan, and 12 is a production plan creating means.

【0040】以上の構成の生産計画作成装置の動作を、
生産計画作成処理フローを示す図2を参照して説明す
る。最初に受注管理システムなどより、月間の受注情報
を受注データ6として獲得する。この受注データに含ま
れている項目で、生産計画作成に必要なものは、製品品
番、受注数量、納期である。納期については、生産完了
日付を、月初からその納期の間に設定するための条件と
して用いる。生産完了から出荷までは工場に在庫として
存在することになる。
The operation of the production plan creating apparatus having the above configuration is described as follows.
This will be described with reference to FIG. 2 showing a production plan creation processing flow. First, monthly order information is acquired as order data 6 from an order management system or the like. The items included in the order data that are necessary for creating a production plan include a product number, an order quantity, and a delivery date. As for the delivery date, the production completion date is used as a condition for setting from the beginning of the month to the delivery date. From the end of production to shipment, it will be in stock at the factory.

【0041】この受注データ6と受注情報に含まれる製
品品番の情報を登録した製品マスタ8、製品品番とボト
ルネック工程のユニット・部品の関連を登録したユニッ
ト・部品構成マスタ9、ユニット・部品の情報を登録し
たユニット・部品マスタ10に基づき、負荷値計算手段
13により受注毎の負荷評価値を計算する。
A product master 8 in which the order data 6 and information on the product part number included in the order information are registered, a unit / part configuration master 9 in which the relation between the product part number and the unit / part in the bottleneck process is registered, and a unit / part Based on the unit / part master 10 in which the information has been registered, the load value calculation means 13 calculates a load evaluation value for each order.

【0042】負荷値は、組立工程、ボトルネック工程そ
れぞれに対して計算される。組立工程の負荷値は、受注
データ6の受注数量に製品マスタ8の標準工数を乗じて
計算される。実装工程の負荷値は、まず受注データ6と
製品品番を部品構成マスタ9に基づき、プリント基板品
番に展開し、展開したプリント基板毎に受注数量毎に受
注数量と員数を乗じて所要量を計算する。そして、この
所要量にユニット・部品マスタ10の実装点数を乗じた
ものを展開したプリント基板すべてで合計する。この合
計点数を実装工程での負荷値とする。
The load value is calculated for each of the assembly process and the bottleneck process. The load value of the assembly process is calculated by multiplying the order quantity of the order data 6 by the standard man-hour of the product master 8. First, the load value of the mounting process is calculated based on the order data 6 and the product number based on the component configuration master 9 into the printed circuit board part numbers, and the required quantity is calculated by multiplying the ordered quantity and the number of persons for each developed order. I do. Then, a product obtained by multiplying the required amount by the mounting points of the unit / part master 10 is summed up for all the developed printed circuit boards. The total score is used as a load value in the mounting process.

【0043】次に、組立工程及び実装工程の負荷値分散
を一致させるために、分散一致手段14によりそれぞれ
の負荷値を組立負荷偏差値15a及び実装負荷偏差値1
5bに変換する。以上の処理が生産計画作成の前処理で
ある。
Next, in order to match the load value distributions in the assembling process and the mounting process, the respective load values are set to the assembly load deviation value 15a and the mounting load deviation value 1 by the distribution matching means 14.
Convert to 5b. The above process is the pre-process for creating the production plan.

【0044】次に、以下の処理で、負荷平準度を最小に
する重み係数Wを決定する。最初に重み係数初期値決定
手段16によりWの初期値を決定する。図3は重み係数
初期値決定手段16のフローである。Wの値を0から1
まで一定幅で変化させ、そのW毎にバケット割付手段1
9により受注をバケットに割付け、その割付結果を負荷
平準度計算手段20により負荷平準度を求める。その中
で負荷平準度が最小になるWを最適化の初期値とする。
一定幅を0.1とした場合、バケット割付と負荷平準度
計算は11回行うことになる。なお、図4は、この計算
結果をグラフ化したものである。この場合では、W=
0.1を初期値として採用する。
Next, a weight coefficient W for minimizing the load level is determined by the following processing. First, the initial value of W is determined by the weight coefficient initial value determining means 16. FIG. 3 is a flowchart of the weight coefficient initial value determining means 16. W value from 0 to 1
Up to a fixed width, and bucket allocation means 1 for each W
9, the orders are allocated to the buckets, and the allocation result is calculated by the load level calculating means 20 to obtain the load level. Among them, W that minimizes the load level is set as the initial value of the optimization.
If the fixed width is set to 0.1, the bucket assignment and the load leveling calculation are performed 11 times. FIG. 4 is a graph of the calculation result. In this case, W =
0.1 is adopted as an initial value.

【0045】図5はバケット割付手段のフローである。
バケット割付手段は最初に受注データ6の納期が月末以
外の受注を該当するバケットに割り付ける。これは納期
指定のある受注はその納期を達成するためのバケットに
優先的に割り付ける操作である。ここで、バケットに割
り付ける処理は、偏差値に変換した組立工程負荷値と偏
差値に変換した実装工程負荷値を用いて行う。納期指定
受注を全て割り付けた後にそれ以外の未割付受注がなく
なるまで、未割付受注の中で負荷評価値が大きいものか
ら、既に割り付けられている負荷評価値合計が最も少な
いバケットに割り付けていく。
FIG. 5 is a flowchart of the bucket allocating means.
The bucket allocating means first allocates an order whose delivery date of the order data 6 is other than the end of the month to the corresponding bucket. This is an operation in which an order with a designated delivery date is preferentially assigned to a bucket for achieving the delivery date. Here, the process of assigning to the bucket is performed using the assembly process load value converted into the deviation value and the mounting process load value converted into the deviation value. After allocating all the delivery-order-specified orders, until there are no other unallocated orders, the non-allocated orders are allocated to the buckets with the smallest total load evaluation value already assigned, from the one with the largest load evaluation value.

【0046】負荷平準度計算手段20は、負荷平準度を
組立工程でのバケット毎総組立工数の分散を平均で割っ
た値と、実装工程でのバケット毎総実装点数の分散を平
均で割った値を加えることによって計算する。
The load level calculating means 20 divides the value obtained by dividing the load level by the average of the variance of the total assembly man-hours per bucket in the assembling process, and the variance of the total number of mounting points per bucket in the mounting process by the average. Calculate by adding values.

【0047】終了判定17において、Wの初期値決定の
段階での平準化で十分な場合は、ここで得られたWによ
る割付結果を結果として採用する。初期値段階で更に平
準化が要求される場合には初期値検索に用いた一定幅の
値を小さくすればよい。
In the end judgment 17, if the leveling at the stage of determining the initial value of W is sufficient, the allocation result based on W obtained here is adopted as the result. If further leveling is required at the initial value stage, the value of the fixed width used for the initial value search may be reduced.

【0048】初期値での平準化が十分でない場合は、重
み係数初期値決定手段16で得られたWの初期値より負
荷平準度最適化手段18により負荷平準度を最適、すな
わち最小とするWを求める。図6は負荷平準度最適化手
段のフローである。Wの最適化はシミュレーティッドア
ニーリング法(SA法)により行う。このSA法は、最
適化過程で確率的に目的関数の増加を受け入れることに
より局所解への収束を回避する最適化手法である。ま
た、近傍解を順次求めていくことにより最適化を行うた
め導関数が不要である。最適化の終了条件により処理が
完了した時点で初期値の段階の負荷平準度と終了時の負
荷平準度を比較する。これは開始点より別の局所解に収
束し、かつその局所解が開始点より平準度が劣化してい
る場合の対策である。
If the leveling at the initial value is not sufficient, the load leveling optimizing means 18 optimizes the load leveling from the initial value of W obtained by the weighting coefficient initial value determining means 16, that is, W which minimizes the load leveling. Ask for. FIG. 6 is a flow chart of the load level optimizing means. The optimization of W is performed by a simulated annealing method (SA method). This SA method is an optimization method for avoiding convergence to a local solution by stochastically accepting an increase in the objective function in the optimization process. Further, since the optimization is performed by sequentially obtaining the neighborhood solution, a derivative is not required. When the processing is completed under the optimization end condition, the load level at the stage of the initial value and the load level at the end are compared. This is a countermeasure when the local solution converges to another local solution from the starting point and the level of the local solution is degraded from the starting point.

【0049】以上の処理により組立工程と実装工程の両
方でバケット単位の負荷平準化をした生産計画ができ
る。以上の手法による生産計画は、受注に対してどのバ
ケットで生産するのかを決定するレベルである。したが
って、まずこの計画に基づいて能力オーバー分の受注を
明確にし、稼働延長による能力追加、外部への振替など
の対処により能力オーバーを解消した後に、既存のスケ
ジューリングシステムで設備・日別生産順序計画を立案
することになる。このように2つの装置を組み合わせて
使用することにより、工場トータルでの最適生産計画の
作成ができる。
With the above processing, a production plan can be made in which the load is leveled in bucket units in both the assembling process and the mounting process. The production plan by the above method is a level for determining which bucket is to be produced for an order. Therefore, based on this plan, we will first clarify orders for excess capacity, eliminate excess capacity by taking measures such as adding capacity by extending operation and transferring to outside, and then use the existing scheduling system to plan equipment and daily production sequence. Will be drafted. By using the two devices in combination in this manner, it is possible to create an optimal production plan for the entire factory.

【0050】[0050]

【発明の効果】本発明の最適生産計画作成方法及び装置
によれば、以上のように製品組立工程とボトルネックと
なる源泉工程の両方でバケット単位の負荷平準化をした
生産計画を作成することができる。また、これによりボ
トルネック工程の負荷が平準化されるために能力オーバ
ー分が明確になり、オーバー分を稼働延長又は外部への
振替を行うことにより、割り付けたバケット期間内で生
産計画が実行可能となる。すなわち、ボトルネックとな
る源泉工程能力をオーバーした受注を当初割り付けたバ
ケットより前の余剰負荷に割り付けを移動させることに
よる生産リードタイムの増加の回避、及び能力オーバー
による製品組立工程に対しての納期遅れの回避が可能に
なる。
According to the method and apparatus for creating an optimum production plan of the present invention, as described above, a production plan is created in which the load is leveled in bucket units in both the product assembling process and the bottleneck source process. Can be. In addition, because the load of the bottleneck process is leveled, the excess capacity is clarified, and by extending the operation or transferring the excess capacity to the outside, the production plan can be executed within the allocated bucket period Becomes In other words, avoiding an increase in production lead time by moving the allocation of orders that exceed the source process capacity, which is the bottleneck, to the surplus load before the initially allocated bucket, and the delivery time for the product assembly process due to excess capacity Delays can be avoided.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施形態の生産計画作成装置の構成
図である。
FIG. 1 is a configuration diagram of a production plan creation device according to an embodiment of the present invention.

【図2】同実施形態における生産計画作成処理のフロー
図である。
FIG. 2 is a flowchart of a production plan creation process in the embodiment.

【図3】同実施形態における重み係数初期値決定手段の
フロー図である。
FIG. 3 is a flowchart of a weight coefficient initial value determining unit in the embodiment.

【図4】同実施形態における重み係数とバケット負荷平
準度の関係図である。
FIG. 4 is a relationship diagram between a weighting factor and a bucket load level in the embodiment.

【図5】同実施形態におけるバケット割付手段のフロー
図である。
FIG. 5 is a flowchart of a bucket allocating unit in the embodiment.

【図6】同実施形態における負荷平準度最適化手段のフ
ロー図である。
FIG. 6 is a flowchart of a load leveling optimization unit in the embodiment.

【図7】従来例の生産計画作成装置の構成図である。FIG. 7 is a configuration diagram of a conventional production plan creation device.

【符号の説明】[Explanation of symbols]

1 入力装置 2 記憶装置 3 中央処理装置 4 表示装置 5 印字装置 6 受注データ 8 製品マスタ 9 部品構成マスタ 10 ユニット・部品マスタ 11 生産計画 12 生産計画作成手段 13 負荷評価値計算手段 14 分散一致手段 15a 組立負荷偏差値 15b 実装負荷偏差値 16 重み係数初期値決定手段 18 負荷平準度最適化手段 19 バケット割付手段 20 負荷平準度計算手段 DESCRIPTION OF SYMBOLS 1 Input device 2 Storage device 3 Central processing unit 4 Display device 5 Printing device 6 Order data 8 Product master 9 Part configuration master 10 Unit / part master 11 Production plan 12 Production plan creation means 13 Load evaluation value calculation means 14 Distributed matching means 15a Assembly load deviation value 15b Mounting load deviation value 16 Weight coefficient initial value determination means 18 Load levelness optimization means 19 Bucket allocation means 20 Load levelness calculation means

───────────────────────────────────────────────────── フロントページの続き (72)発明者 楢原 康一 大阪府門真市大字門真1006番地 松下電器 産業株式会社内 Fターム(参考) 3C042 RJ02 RJ03 RJ20 RL01 RL12 5H269 AB17 AB27 BB08 EE11 NN17 QB15 QD06  ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Koichi Narahara 1006 Kazuma Kadoma, Kadoma City, Osaka Prefecture F-term in Matsushita Electric Industrial Co., Ltd. 3C042 RJ02 RJ03 RJ20 RL01 RL12 5H269 AB17 AB27 BB08 EE11 NN17 QB15 QD06

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 複数工程の生産計画を作成する際に必要
な受注情報と、受注情報に含まれる製品に関する基礎デ
ータと、製品を構成するユニットに関する基礎データ
と、ユニットを生産する源泉工程情報をもとに、製品組
立工程とボトルネックとなる源泉工程の両方でバケット
単位の負荷平準化を図ることを特徴とする最適生産計画
作成方法。
An order information necessary for creating a production plan of a plurality of processes, basic data on a product included in the order information, basic data on a unit constituting the product, and source process information on a unit to be produced are included. An optimal production plan creation method based on equalizing the load in bucket units in both the product assembly process and the bottleneck source process.
【請求項2】 全ての受注情報に対して組立工程負荷と
ボトルネック工程負荷を計算する過程と、組立工程とボ
トルネック工程の負荷値を偏差値に変換して分散を一致
させる過程と、全ての受注情報に対して両工程の偏差値
を重み係数Wを用いて結合した負荷評価値を計算する過
程と、負荷評価値を用いて受注をバケットに割り付ける
過程と、割付結果の負荷平準度を求める過程と、負荷平
準度を向上させるべく重み係数Wを更新して負荷評価値
を計算する過程に戻る過程にて最適な負荷平準度が得ら
れるバケット割付を求めることを特徴とする請求項1記
載の最適生産計画作成方法。
2. A process of calculating an assembly process load and a bottleneck process load with respect to all order information, a process of converting load values of the assembly process and the bottleneck process into deviation values and matching variances, Calculating the load evaluation value by combining the deviation values of both processes with the order information using the weighting factor W, allocating the orders to the buckets using the load evaluation value, and determining the load levelness of the allocation result. 2. A bucket allocation that obtains an optimum load level in a step of obtaining and a step of returning to a step of calculating a load evaluation value by updating a weight coefficient W to improve the load level. The optimal production plan creation method described.
【請求項3】 受注情報、製品基礎データ、ユニット基
礎データの入力装置と、これらのデータを常時記憶して
おく記憶装置と、作成結果を表示する表示装置と、作成
結果を印字する印字装置と、入力装置、記憶装置、及び
印字装置を統括的に管理するとともに請求項1又は2記
載の生産計画作成方法を実行する生産計画作成手段を有
する中央処理装置を備えたことを特徴とする最適生産計
画作成装置。
3. An input device for receiving order information, product basic data and unit basic data, a storage device for constantly storing these data, a display device for displaying a created result, and a printing device for printing the created result. And a central processing unit having a production plan creation means for executing the production plan creation method according to claim 1 or 2, wherein the central processing unit manages the input device, the storage device, and the printing device in an integrated manner. Planning equipment.
JP11209120A 1999-07-23 1999-07-23 Method and device for preparing optimum production plan Pending JP2001034321A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11209120A JP2001034321A (en) 1999-07-23 1999-07-23 Method and device for preparing optimum production plan

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11209120A JP2001034321A (en) 1999-07-23 1999-07-23 Method and device for preparing optimum production plan

Publications (1)

Publication Number Publication Date
JP2001034321A true JP2001034321A (en) 2001-02-09

Family

ID=16567628

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11209120A Pending JP2001034321A (en) 1999-07-23 1999-07-23 Method and device for preparing optimum production plan

Country Status (1)

Country Link
JP (1) JP2001034321A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004094687A (en) * 2002-08-30 2004-03-25 Nippon Telegraph & Telephone East Corp Information providing device, program, and recording medium
US7092775B2 (en) 2004-04-08 2006-08-15 Hitachi, Ltd. Production planning apparatus and production planning method
JP2006309302A (en) * 2005-04-26 2006-11-09 Kobe Steel Ltd Operation mode determination method, operation mode determination device and program
EP3316193B1 (en) * 2016-11-01 2023-04-12 Hitachi, Ltd. Production support system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004094687A (en) * 2002-08-30 2004-03-25 Nippon Telegraph & Telephone East Corp Information providing device, program, and recording medium
US7092775B2 (en) 2004-04-08 2006-08-15 Hitachi, Ltd. Production planning apparatus and production planning method
JP2006309302A (en) * 2005-04-26 2006-11-09 Kobe Steel Ltd Operation mode determination method, operation mode determination device and program
JP4648067B2 (en) * 2005-04-26 2011-03-09 株式会社神戸製鋼所 Operation mode determination method, operation mode determination device, and program
EP3316193B1 (en) * 2016-11-01 2023-04-12 Hitachi, Ltd. Production support system

Similar Documents

Publication Publication Date Title
CN105471759B (en) The network traffics dispatching method and device of data center
CN100499492C (en) Method for realizing electronic work order queuing
US5745880A (en) System to predict optimum computer platform
US5343387A (en) Cyclic maintenance work schedule table preparation system
US7389249B2 (en) Automated supply management method for dynamically fulfilling a customer requested order
CN108734353A (en) A kind of public bus network route plan generation method and device
CN108154298B (en) Distribution task allocation method and device, electronic equipment and computer storage medium
CN106919449A (en) The dispatch control method and electronic equipment of a kind of calculating task
CN106959894A (en) Resource allocation methods and device
CN109697637A (en) Object type determines method, apparatus, electronic equipment and computer storage medium
CN111353663A (en) Task allocation method, device, equipment and storage medium thereof
CN107066322A (en) A kind of online task allocating method towards self-organizing intelligent perception system
US8494893B2 (en) Production plan making program, device, and method
JP2001034321A (en) Method and device for preparing optimum production plan
JP3474682B2 (en) Mounting component distribution method and mounting equipment
CN109214645A (en) Development approach and system based on module metering
CN111598432A (en) Task allocation method and device
US20160203428A1 (en) System and method for adaptive and dynamic pricing of self-storage storage units
CN108764697A (en) Task work dispatching method, server and computer readable storage medium
CN110647715B (en) Ranking list voting processing method and device
CN115456566A (en) Scheduling list processing method, system, electronic equipment and storage medium
US20050177411A1 (en) System and method for managing demand influencing factors
JP2007317103A (en) Workforce efectively utilizing system, method, program, and recording medium which stores workforce efectively utilizing program
CN110457923A (en) A kind of sensitive data scan method, device, electronic equipment and readable storage medium storing program for executing
JP2004145591A (en) System and method for distributing production capacity