JP2000282791A - Tunneling method - Google Patents

Tunneling method

Info

Publication number
JP2000282791A
JP2000282791A JP11086701A JP8670199A JP2000282791A JP 2000282791 A JP2000282791 A JP 2000282791A JP 11086701 A JP11086701 A JP 11086701A JP 8670199 A JP8670199 A JP 8670199A JP 2000282791 A JP2000282791 A JP 2000282791A
Authority
JP
Japan
Prior art keywords
excavated
tunnel
mixer
concrete
carrying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11086701A
Other languages
Japanese (ja)
Other versions
JP3253931B2 (en
Inventor
Kyuichi Suzuki
久一 鈴木
Yoshiro Tanaka
義郎 田中
Shinichi Saida
信一 齋田
Yasuhiko Sato
靖彦 佐藤
Noriyuki Nishida
徳行 西田
Shinichi Kanamaru
信一 金丸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP08670199A priority Critical patent/JP3253931B2/en
Publication of JP2000282791A publication Critical patent/JP2000282791A/en
Application granted granted Critical
Publication of JP3253931B2 publication Critical patent/JP3253931B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a tunneling method which can reuse excavated soil as concrete without constructing a special plant on the ground, can easily adjust the amount of excavated soil for construction of the concrete, and further can reuse excavated soil generated in a mud shield method. SOLUTION: A mud shield method for carrying out excavation and concrete placement in a tunnel pit 22, comprises an excavated soil carrying-out step of carrying excavated soil to the outside 20 of the tunnel pit, an excavated soil introducing step of introducing part of the excavated soil in a mixer 8 in the tunnel pit 22, a hardener charging step of charging a harder in the mixer 8, and a kneading step of kneading the excavated soil and the hardener in the mixer 8, by the same. The excavated soil carrying-out step corresponds to a step of carrying the excavated soil to the outside via soil conveying pipes 4, 5 of two systems, and the excavated soil introducing step corresponds to a step of introducing the excavated soil in the soil conveying pipe 5 to the mixer 8, by operating a switching valve 6 provided for the soil conveying pipe 5.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、トンネル坑内で
掘削処理とコンクリート打設とを行なうトンネル工法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a tunneling method for performing excavation and concrete placement in a tunnel.

【0002】[0002]

【従来の技術】トンネル工法には、例えば、土砂地盤に
トンネルを構築するのに、大きな鋼製筒で土圧を支え且
つ前面の切羽にあるカッター面板を回転させるシールド
掘進機を用いてトンネルを掘り進むシールド工法や、老
朽化したトンネルの内壁(例えばインバート部)を破砕
した後にコンクリートを打設し直す改修工法など、様々
な工法がある。また、シールド工法にも、泥水加圧式シ
ールド工法や泥土圧式シールド工法など種々の工法があ
る。泥水加圧式シールド工法は、シールド掘進機の掘削
室に地上よりポンプで泥水を圧送封入して地下水を泥水
圧で押さえ、切羽の安定を図りながら、切削された土砂
を泥水の還流によってトンネル坑外に排出する工法であ
る。
2. Description of the Related Art In a tunnel construction method, for example, a tunnel is constructed by using a shield excavator that supports a soil pressure with a large steel cylinder and rotates a cutter face plate on a front face in order to construct a tunnel in soil. There are various construction methods, such as a digging shield method and a renovation method in which concrete is cast after crushing the inner wall of an aged tunnel (for example, the invert portion). Also, there are various shield methods such as a muddy water pressure shield method and a mud pressure shield method. The muddy pressurized shield method uses a pump to pump muddy water from the ground into the excavation room of the shield machine, pressurize the groundwater with muddy water pressure, stabilize the face, and return the cut soil to the outside of the tunnel by returning the muddy water. It is a construction method to discharge to.

【0003】泥土圧式シールド工法は、シールド掘進機
のカッターチャンバー内に、例えば流動性・不透水性を
有した状態の削土を充満させ、掘削土砂量と排土量との
関係を適宜制御すること及び作泥材の適宜注入によりカ
ッターチャンバー内を加圧し、切羽の安定を図ると共
に、排土を例えばスクリューコンベアにより排出し搬送
管を通して圧送しトンネル坑外に排出する。
In the mud pressure shield method, a cutter chamber of a shield machine is filled with, for example, soil having fluidity and water impermeability, and the relationship between the amount of excavated soil and the amount of earth removed is appropriately controlled. The inside of the cutter chamber is pressurized by appropriately injecting the mud material and stabilizing the face, and the discharged soil is discharged by, for example, a screw conveyor, fed through a conveying pipe, and discharged out of the tunnel pit.

【0004】ところで、泥水加圧式シールド工法で発生
される掘削土砂(泥水を多く含んだ土砂)を利用してコ
ンクリートを生成し、インバート材として用いる技術は
多く研究開発がなされ実用化もされている。泥水加圧式
シールド工法の工事で掘削土砂を利用したコンクリート
製造は、一般に、地上に専用プラントを設置し、この専
用プラントにトンネル坑内から搬出した掘削土砂を導入
することで行なわれる。しかしながら、例えば都市部の
施工現場などでは上記専用プラントを設営するヤード
(土地)が確保できない場合が多く、掘削土砂を再利用
したコンクリート製造が行なえないという課題があっ
た。
By the way, many technologies have been developed and put into practical use for producing concrete by using excavated earth and sand (soil and sand containing a large amount of mud) generated by a slurry pressurization shield method and using it as an invert material. . Concrete production using excavated earth and sand in the construction of the muddy pressure shield method is generally performed by installing a dedicated plant on the ground and introducing the excavated earth and sand taken out of the tunnel mine into this dedicated plant. However, in many cases, for example, at a construction site in an urban area, a yard (land) for setting up the above-mentioned dedicated plant cannot be secured, and there has been a problem that concrete production using recycled excavated soil cannot be performed.

【0005】そこで、トンネル坑内で掘削土砂を再利用
したコンクリート製造を行なう技術の開発が望まれる。
従来、トンネル坑内で発生した掘削土砂をトンネル坑内
で骨材として再利用する技術として、例えば、特開平2
−190600号公報に開示のシールド工法や特開平2
−266096号公報に開示のシールドトンネルにおけ
るインバートの製造方法などがある。上記のシールド工
法(特開平2−190600号)は、水分を多く含まな
い地層を掘進し、水分を含まない掘削土砂をふるいに掛
けて所定の粒径以上の土砂を骨材として分級・分離し使
用するものである。また、コンクリート製造には予め坑
内にセメント等の硬化材を蓄えておき、このセメントと
上記掘削土砂とを攪拌・混合してコンクリートを製造す
る。
[0005] Therefore, it is desired to develop a technique for producing concrete by reusing excavated earth and sand in a tunnel.
Conventionally, a technique for reusing excavated earth and sand generated in a tunnel pit as an aggregate in the tunnel pit is disclosed in, for example,
Shielding method disclosed in Japanese Unexamined Patent Publication No.
No. 2,660,096 discloses a method of manufacturing an invert in a shield tunnel. The above-mentioned shield method (Japanese Patent Application Laid-Open No. 2-190600) excavates a stratum not containing much moisture, sieves excavated soil containing no moisture, and classifies and separates soil having a predetermined particle size or more as aggregate. To use. In the production of concrete, a hardening material such as cement is stored in advance in a pit, and the cement and the excavated earth and sand are stirred and mixed to produce concrete.

【0006】また、上記シールドトンネルにおけるイン
バートの製造方法(特開平2−266096号)は、泥
水加圧式シールド工法において掘削土砂を搬出する1本
の圧送管の途中に、所定粒径以上の土砂を分級・分離す
る分級装置を介設し、泥水土砂の中から所定粒径の土砂
を取り出して骨材に使用するものである。また、坑内で
のコンクリート製造のために、予めトンネル坑内にセメ
ント等を入れた硬化材槽を搬入しておき、上記取り出し
た骨材と硬化材槽のセメント等を混練してコンクリート
を製造する。
[0006] The above-mentioned method of manufacturing an invert in a shield tunnel (Japanese Patent Application Laid-Open No. 2-266096) is based on a muddy pressurized shield method, in which a piece of sand having a predetermined particle size or more is placed in the middle of one pressure pipe for carrying out excavated earth and sand. A classifying device for classifying and separating is interposed, and sediment having a predetermined particle size is taken out of muddy soil and used for aggregate. Further, for the production of concrete in the pit, a hardening material tank containing cement or the like is previously loaded into the tunnel pit, and the aggregate and the cement or the like in the hardening material tank are kneaded to produce concrete.

【0007】[0007]

【発明が解決しようとする課題】しかしながら、トンネ
ル坑内で掘削土砂を再利用してコンクリートを製造する
上記従来のシールド工法(特開平2−190600号、
特開平2−266096号)では、掘削土砂を搬出する
搬出路が1系統しかなく、コンクリート製造を行なうタ
イミングであれ行なわないタイミングであれ、また、コ
ンクリートを多量に製造する場合であれ少量製造する場
合であれ、一定した量の土砂がコンクリート製造用とし
て発生してしまい、その量の調整が行ないにくいと云う
課題があった。また、トンネル坑内で掘削土砂を再利用
してコンクリートを製造する上記従来のシールド工法で
は、硬化材であるセメントを予めトンネル坑内に備蓄し
ておき、備蓄したセメントを使用しながらコンクリート
を製造する。つまり、長い時間セメント(硬化材)を備
蓄する必要があるので、セメントは水を加えていない粉
状のものに限られ、生コンクリートや生モルタルは固ま
ってしまうため使用できなかった。それゆえ、セメント
の投入量や水の投入量、並びに骨材の投入量を坑内で正
確に計量してコントロールする必要があり、その作業は
高度で繁雑なものであった。
However, the above-mentioned conventional shield method for producing concrete by recycling excavated earth and sand in a tunnel pit (Japanese Patent Laid-Open No. 190600/1990).
In Japanese Patent Application Laid-Open No. 2-266096, there is only one system for carrying out the excavated earth and sand, and the timing for performing concrete production or not, the case for producing a large amount of concrete, and the case for producing a small amount of concrete. However, there is a problem that a fixed amount of earth and sand is generated for concrete production, and it is difficult to adjust the amount. In the above-mentioned conventional shield method in which concrete is manufactured by reusing excavated earth and sand in a tunnel pit, cement as a hardening material is stored in the tunnel pit in advance, and concrete is manufactured using the stored cement. In other words, cement (hardening material) needs to be stockpiled for a long time, so that the cement is limited to a powdery one to which water is not added, and ready-mixed concrete or mortar cannot be used because it hardens. Therefore, it was necessary to accurately measure and control the input amount of cement, the input amount of water, and the input amount of aggregate in the mine, and the operation was complicated and complicated.

【0008】また、トンネル坑内で掘削土砂を再利用し
てコンクリートを製造する上記従来のシールド工法で
は、掘削土砂をそのまま再利用するのでなく、掘削土砂
の中から骨材となる粒径の土砂を分級・分離して使用す
る。それゆえ、掘削土砂の再利用率はそれほど高くな
く、また、圧送管を通して掘削土砂を坑外に搬出するシ
ールド工法においては、分離・分級が行ないにくく、例
えば、特開平2−266096号に開示のような大掛か
りな分級装置を必要とした。
In the above-mentioned conventional shield method in which concrete is manufactured by reusing excavated soil in a tunnel pit, the excavated soil is not reused as it is, but sediment having a particle size to become an aggregate is obtained from the excavated soil. Use after classification and separation. Therefore, the reuse rate of excavated earth and sand is not so high, and in the shield method in which the excavated earth and sand is carried out through a pumping pipe, separation and classification are difficult to be performed. For example, Japanese Unexamined Patent Publication No. 2-266096 discloses a shield method. Such a large classifier was required.

【0009】また、トンネル坑外に排出した掘削土砂を
利用するコンクリート製造は、従来、泥水加圧式シール
ド工法で発生した泥水を多く含んだ土砂に限られ、泥土
圧式シールド工法で発生される掘削土砂(例えば止水性
と流動性とを有する掘削土砂)を利用したコンクリート
製造については実用化されておらず、その研究・開発が
望まれていた。
Conventionally, concrete production using excavated sediment discharged outside the tunnel pit is limited to sediment containing a large amount of muddy water generated by the muddy pressure shield method, and excavated sediment generated by the mud pressure shield method. Concrete production using (for example, excavated earth and sand having water blocking property and fluidity) has not been put to practical use, and research and development thereof have been desired.

【0010】この発明の目的は、上記実状に鑑み、地上
に専用プラントを設営する必要なく、且つ、掘削土砂を
分級・分離することなくコンクリートとして再利用を図
れるトンネル工法であり、更には、掘削進度と関係なく
コンクリート製造に使用する掘削土砂の量を容易に調整
可能であり、また、硬化材の配合比率の制御がさほど難
しくないトンネル工法、更には、泥土圧式シールド工法
で発生した掘削土砂の再利用を図ることの出来るトンネ
ル工法を提供することである。
An object of the present invention is to provide a tunnel construction method capable of reusing concrete as excavated earth and sand without classifying and separating the excavated earth and sand, in view of the above situation. The amount of excavated sediment used for concrete production can be easily adjusted regardless of the progress, and the control of the mixing ratio of hardened material is not so difficult. The purpose is to provide a tunnel construction method that can be reused.

【0011】[0011]

【課題を解決するための手段】次の手段の説明中、かぎ
括弧により実施の形態に対応する構成を1例として例示
する。実施の形態と同一の単語を使用している場合には
符号のみ記す。上記課題を解決するため、請求項1記載
の発明は、トンネル坑内〔22〕で掘削処理とコンクリ
ート打設とを行なうトンネル工法において、掘削処理に
より生じた掘削物をトンネル坑外〔地上20〕まで搬出
する掘削物搬出工程と、掘削物の1部をトンネル坑内
〔22〕のミキサー〔8〕に導入する掘削物導入工程
と、ミキサー〔8〕に硬化材を注入する硬化材注入工程
と、ミキサー〔8〕内に入れられた掘削物および硬化材
とをミキサー〔8〕により混練する混練工程と、混練さ
れたコンクリートを坑内〔22〕に打設するコンクリー
ト打設工程とを有し、前記掘削物搬出工程が、前記掘削
物を複数系統の搬送手段〔土砂圧送管4,5〕を介して
トンネル坑外〔地上20〕まで搬出する工程であり、前
記掘削物導入工程は、前記複数系統の搬送手段の少なく
とも1つに設けられた切換え手段〔切換えバルブ6〕を
操作することで該少なくとも1つの搬送手段〔土砂圧送
管5〕の掘削物を前記ミキサー〔8〕に導入する工程で
ある構成とした。
Means for Solving the Problems In the description of the following means, a configuration corresponding to the embodiment will be exemplified by angle brackets as an example. In the case where the same words as those in the embodiment are used, only symbols are described. In order to solve the above-mentioned problem, the invention according to claim 1 is directed to a tunnel construction method in which excavation processing and concrete casting are performed in a tunnel pit [22]. A step of carrying out the excavated matter to be carried out, a step of introducing a part of the excavated matter into the mixer [8] in the tunnel [22], a step of injecting a hardened material into the mixer [8], and a mixer [8] The excavating method includes a kneading step of kneading the excavated matter and the hardened material put in the mixer with a mixer [8], and a concrete placing step of placing the kneaded concrete in a pit [22]. The unloading step is a step of unloading the excavated matter to the outside of the tunnel mine [above ground 20] via a plurality of systems of transport means [sediment pressure pipes 4, 5], and the excavated matter introducing step is performed by the plurality of systems. By operating a switching means [switching valve 6] provided in at least one of the feeding means, the excavated material of the at least one conveying means [sediment pressure feeding pipe 5] is introduced into the mixer [8]. And

【0012】この請求項1記載の発明によれば、掘削物
をトンネル坑外に搬出するのに複数系統の搬送手段を用
いており、これらのうち1系統の搬送手段から掘削物を
ミキサーに導入するので、ミキサーに導入する掘削物の
量の調整が掘削物の総量に関係なく容易に行なえる。即
ち、ミキサーに導入する量を減らしたい時には、他系統
の搬送手段の搬送量が増加することで、搬送総量を一定
としたまま対応できる。その逆も然りである。また、一
般に、トンネル坑内でコンクリート打設を行なうのは、
常時ではなく所定の一定期間のみに限られることが多
い。そこで、この発明では、切換え手段により掘削物の
搬送先をミキサーとトンネル坑外とに切換え可能なの
で、ミキサーを作動させてコンクリート製造を行なうと
きのみミキサーに搬送し、そうでないときはトンネル坑
外に搬出することが出来る。なお、トンネル工法は、主
にシールド掘進機によりトンネルを掘進していくシール
ド工法などであるが、老朽したトンネルを改修する改修
工法など、トンネル坑内で掘削とコンクリート打設を行
なう工法であれば種々のトンネル工法も含まれる。
According to the first aspect of the present invention, a plurality of transporting means are used to carry the excavated material out of the tunnel mine, and the excavated material is introduced into the mixer from one of the transporting means. Therefore, the amount of excavated material introduced into the mixer can be easily adjusted regardless of the total amount of excavated material. That is, when it is desired to reduce the amount to be introduced into the mixer, it is possible to cope with keeping the total transport amount constant by increasing the transport amount of the transport means of another system. The reverse is also true. Also, in general, concrete is cast in tunnel tunnels.
It is often limited to only a predetermined period, not always. Therefore, in the present invention, the transport destination of the excavated material can be switched between the mixer and the outside of the tunnel by the switching means, so that the excavated material is transported to the mixer only when the concrete is produced by operating the mixer, and when the concrete is not produced, the transport is performed outside the tunnel. Can be carried out. The tunnel method is mainly a shield method that excavates a tunnel with a shield excavator. The tunnel construction method is also included.

【0013】請求項2記載の発明は、トンネル坑内〔2
2〕で掘削処理とコンクリート打設とを行なうトンネル
工法において、掘削処理により生じた掘削物をトンネル
坑外〔地上20〕まで搬出する掘削物搬出工程と、掘削
物の1部をトンネル坑内〔22〕のミキサー〔8〕に導
入する掘削物導入工程と、トンネル坑外〔地上20〕か
らトンネル坑内〔22〕に流動状の硬化材(例えば生コ
ンクリートや生モルタルなど)を搬入する硬化材搬入工
程と、該流動状の硬化材を前記ミキサー〔8〕に注入す
る硬化材注入工程と、ミキサー〔8〕内に入れられた掘
削物および流動状の硬化材とをミキサー〔8〕により混
練する混練工程と、混練されたコンクリートを坑内〔2
2〕に打設するコンクリート打設工程とを備えた構成と
した。
[0013] The invention according to claim 2 is a method according to claim 2, wherein
2] In the tunnel construction method in which the excavation process and the concrete placement are carried out in the tunnel excavation process, the excavated material generated by the excavation process is carried out to the outside of the tunnel pit [20 above the ground], and a part of the excavated material is placed in the tunnel pit [22]. And a hardening material loading process of loading a fluid hardening material (for example, ready-mixed concrete or mortar) from the outside of the tunnel [20 above the ground] to the inside of the tunnel [22]. And a hardening material injecting step of injecting the fluid hardening material into the mixer [8], and kneading the excavated material and the fluid hardening material placed in the mixer [8] by the mixer [8]. Process and kneaded concrete in the pit [2
2) and a concrete casting step.

【0014】この請求項2記載の発明によれば、ミキサ
ーに注入する硬化材としてトンネル坑外から搬入する流
動状の硬化材(例えば生コンクリートや生モルタルな
ど)を使用するので、従来の粉セメントと水とを用いて
一から混練する場合に較べて、混練に要する時間が短縮
され、また、硬化材の配合比率の管理も簡易化できる。
According to the second aspect of the present invention, a fluid hardening material (for example, fresh concrete or fresh mortar) carried from outside the tunnel is used as the hardening material to be injected into the mixer. The time required for kneading is shorter than in the case of kneading from the beginning using water and water, and the management of the mixing ratio of the curing material can be simplified.

【0015】請求項3記載の発明は、請求項2記載のト
ンネル工法において、前記掘削物搬出工程は、前記掘削
物を複数系統の搬送手段〔土砂圧送管4,5〕を介して
トンネル坑外〔地上20〕まで搬出する工程であり、前
記掘削物導入工程は、前記複数系統の搬送手段〔土砂圧
送管4,5〕の少なくとも1つに設けられた切換え手段
〔切換えバルブ6〕を操作することで該少なくとも1つ
の搬送手段〔土砂圧送管5〕の掘削物を前記ミキサー
〔8〕に導入する工程である構成とした。
According to a third aspect of the present invention, in the tunnel construction method according to the second aspect, the excavated material carrying out step is carried out outside the tunnel via a plurality of systems of conveying means [sediment pumping pipes 4, 5]. In the excavated matter introduction step, switching means [switching valve 6] provided in at least one of the plurality of systems of conveying means [sediment pressure feeding pipes 4, 5] is operated. In this way, the excavated material of the at least one conveying means [the sediment pressing pipe 5] is introduced into the mixer [8].

【0016】この請求項3記載の発明によれば、請求項
2の作用効果に加えて請求項1の作用効果も付加でき
る。また、流動状の硬化材を使用する場合、硬化材の搬
送を停止させたりすると搬送経路上で硬化が進んでしま
うため、硬化材側の供給量の調整は急激に行ないがた
い。そこで、本発明では、掘削物の供給側で導入量が調
整可能なので、この調整によりコンクリート材料の配合
比率を適切なものに調整できる。
According to the third aspect of the invention, the operation and effect of the first aspect can be added to the operation and effect of the second aspect. In addition, when a fluidized hardening material is used, if the transport of the hardening material is stopped, the hardening proceeds on the transport path, so that it is difficult to rapidly adjust the supply amount on the hardening material side. Therefore, in the present invention, the introduction amount can be adjusted on the supply side of the excavated material, and thus the mixing ratio of the concrete material can be adjusted appropriately by this adjustment.

【0017】請求項4記載の発明は、請求項1〜3の何
れかに記載のトンネル工法であって、前記掘削物として
流動性を有する掘削土砂が発生される泥土圧式シールド
工法に適用し、前記ミキサー〔8〕に導入する掘削物と
して、分級・分離を行なわないそのままの掘削土砂を用
いる構成とした。
According to a fourth aspect of the present invention, there is provided the tunnel construction method according to any one of the first to third aspects, wherein the tunnel construction method is applied to a mud pressure shield method in which excavated soil having fluidity is generated as the excavated material. As the excavated material to be introduced into the mixer [8], the excavated sediment without classification and separation was used.

【0018】この請求項4記載の発明によれば、泥土圧
式シールド工法に適用して、掘削物をそのままの状態で
ミキサーに導入して混練することでコンクリートを製造
するので、例えば、従来の所定粒径以上の土砂を分級・
分離して骨材に使用する工法に較べて、土砂の再使用率
が良く、分級するための装置などが不用でトンネル坑内
を広く使用できる。また、泥水加圧式シールド工法の掘
削土を使用する場合、脱水装置等の大型の装置を使用す
る必要があることから、トンネル坑内でコンクリート製
造することが困難であったが、泥土圧式シールド工法に
適用することで、そのままの掘削土が利用できるのでト
ンネル坑内でコンクリート製造する場合でも、脱水機な
どの装置によりトンネル坑内の空間が大きく占められる
といった不都合がない。
According to the fourth aspect of the present invention, concrete is manufactured by applying the excavated material as it is to the mixer and kneading it by applying to the mud pressure shield method, so that, for example, a conventional predetermined method is used. Classification of sediment above the particle size
Compared with the method of separating and using aggregates, the reuse rate of earth and sand is better, and no equipment for classifying is required, and the tunnel pit can be widely used. In addition, when using excavated soil of the muddy pressure shield method, it was necessary to use large equipment such as a dewatering device, so it was difficult to produce concrete in the tunnel pit. By applying the same, the excavated soil can be used as it is, so that even when concrete is manufactured in the tunnel pit, there is no inconvenience that the space in the tunnel pit is largely occupied by a device such as a dehydrator.

【0019】請求項5記載の発明は、請求項1〜4の何
れかに記載のトンネル工法において、前記コンクリート
打設工程が、トンネル坑内〔22〕のインバート部のコ
ンクリート打設を行なう工程である構成とした。一般
に、インバート部のコンクリート打設は、常時行なわれ
るものでなく任意の時間間隔おきに行なわれる。また、
トンネル壁の覆工に用いられるコンクリートなどに較べ
てそれほど高くない品質のコンクリートが使用できる。
そこで、この請求項5記載の発明のように、請求項1〜
4の掘削物を再利用したコンクリート打設としてインバ
ート部のコンクリート打設を行なうことで最も適合した
実施態様となる。
According to a fifth aspect of the present invention, in the tunnel method according to any one of the first to fourth aspects, the concrete placing step is a step of placing concrete in an invert portion in the tunnel pit [22]. The configuration was adopted. In general, concrete placement in the invert portion is not always performed, but is performed at arbitrary time intervals. Also,
Concrete that is not so high in quality as concrete used for lining tunnel walls can be used.
Therefore, as in the invention of claim 5, claims 1 to 5
The most suitable embodiment is achieved by concrete in the invert part as concrete in which the excavated material of No. 4 is reused.

【0020】[0020]

【発明の実施の形態】以下、この発明の実施の形態につ
いて、図面を参照しながら説明する。図1は、本発明の
実施の形態のトンネル工法の実施態様を示す模式図であ
る。同図中、11はインバート材、20は地上、21は
立杭、22はトンネル坑内である。この実施の形態のト
ンネル工法を実施するシールド工事システムは、図1に
示すように、シールド掘進機1、スクリューコンベア
2、シールド掘進機1の後方台車あるいは坑内の適当な
定位置のコンクリート製造場所3に搭載されたミキサー
8、複数系統の搬出手段である2系統の土砂圧送管4,
5、切換え手段としての切換えバルブ6、ミキサー8に
連なる分岐管7、コンクリート圧送管9、モルタル搬入
用圧送管10、掘削土砂を貯蔵する土砂ホッパー13、
および、生コンクリート工場で製造されたモルタルの流
動性を有する硬化材を現場まで搬送するトラックアジテ
ータ車14などから構成される。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a schematic view showing an embodiment of a tunnel construction method according to an embodiment of the present invention. In the figure, 11 is an inverted material, 20 is the ground, 21 is a standing pile, and 22 is inside a tunnel. As shown in FIG. 1, a shield construction system that implements a tunnel construction method according to this embodiment includes a shield excavator 1, a screw conveyor 2, a rear bogie of the shield excavator 1, or a concrete production place 3 at an appropriate fixed position in a mine. Mixer 8 mounted on the ground, two systems of sediment pressure feed pipes 4 as a plurality of systems of unloading means 4,
5, a switching valve 6 as a switching means, a branch pipe 7 connected to the mixer 8, a concrete feeding pipe 9, a mortar loading feeding pipe 10, a sand hopper 13 for storing excavated earth and sand,
And a truck agitator wheel 14 that conveys a hardening material having fluidity of mortar manufactured at a ready-mixed concrete factory to a site.

【0021】この実施の形態のトンネル工法は、上記シ
ールド工事システムなどにより実施され、泥土圧式シー
ルド工法によりトンネル掘進を行ないながらシールド掘
進機1の後方台車あるいは坑内の適当な定位置のコンク
リート製造場所3で掘削土砂(掘削物)を再利用したコ
ンクリート製造を行ない、このコンクリートをトンネル
坑内22のインバート部に打設していく工法である。具
体的には、このトンネル工法は、トンネル掘進工程、掘
削土砂搬出工程、発生した掘削土砂の1部をミキサー8
内に導入する掘削物導入工程、地上20から生モルタル
(流動状の硬化材)を搬入しミキサー8に注入する硬化
材搬入注入工程(硬化材搬入工程および硬化材注入工
程)、ミキサー8内で掘削土砂とモルタルとを混練する
混練工程、および、混練されて出来たコンクリートをイ
ンバート部に打設するコンクリート打設工程を有して構
成される。
The tunnel construction method according to this embodiment is carried out by the above-mentioned shield construction system or the like. While performing tunnel excavation by the mud pressure type shield construction method, a concrete production place 3 in a bogie behind the shield excavator 1 or an appropriate fixed position in the pit. In this method, concrete is produced by reusing excavated earth and sand (excavated material), and the concrete is poured into the invert portion of the tunnel pit 22. Specifically, in this tunnel method, a tunnel excavation process, an excavation earth and sand removal process, and a part of the generated excavation earth and sand are mixed with a mixer 8.
In the excavated matter introducing step, the raw mortar (flowable hardened material) is loaded from the ground 20 and injected into the mixer 8 (the hardened material importing step and the hardened material injection step). It comprises a kneading step of kneading excavated earth and sand and mortar, and a concrete placing step of placing the kneaded concrete in an invert portion.

【0022】トンネル掘進工程は、泥土圧式シールド工
法によりシールド掘進機1でトンネルを掘進していく工
程であり、シールド掘進機1のカッターチャンバー1B
内に、例えば流動性・不透水性を有した状態の削土を充
満させ、掘削土砂量と排土量との関係を適宜制御するこ
と及び作泥材の適宜注入によりカッターチャンバー1B
内を加圧し、切羽1Aの旋回の安定を図る工法である。
カッターチャンバー1B内の掘削土砂はスクリューコン
ベア2によりホッパー2Aに排出される。掘削土砂搬出
工程は、トンネル掘進により発生する掘削土砂をホッパ
ー2Aから地上20まで排出する工程である。排出に
は、2系統の土砂圧送管4,5が用いられ、土砂圧送管
4,5の途中に設けられたポンプ4a,4b,5a,5
bの推力により、トンネル坑内22と立坑21を通過し
て地上20の土砂ホッパー13まで搬出する。
The tunnel excavation step is a step of excavating a tunnel with the shield excavator 1 by a mud pressure shield method, and the cutter chamber 1B of the shield excavator 1
The cutter chamber 1B is filled with, for example, soil having fluidity and water impermeability, appropriately controlling the relationship between the amount of excavated soil and the amount of earth removed, and appropriately injecting mud material.
The inside is pressurized to stabilize the turning of the face 1A.
The excavated earth and sand in the cutter chamber 1B is discharged to the hopper 2A by the screw conveyor 2. The excavated earth and sand carrying out step is a step of discharging the excavated earth and sand generated by tunnel excavation from the hopper 2A to the ground 20. For discharging, two systems of sediment pressure feed pipes 4, 5 are used, and pumps 4a, 4b, 5a, 5 provided in the middle of the sediment pressure feed pipes 4, 5 are provided.
By the thrust of b, it passes through the inside of the tunnel 22 and the shaft 21 and is carried out to the earth and sand hopper 13 on the ground 20.

【0023】掘削物導入工程は、発生した掘削土砂の1
部をミキサー8内に導入する工程で、1系統の土砂圧送
管5の途中に設けられた切換えバルブ6を操作すること
で、土砂圧送管5に圧送される掘削土砂を分岐管7に分
岐させふミキサー8内に導入する。ミキサー8に導入さ
れる掘削土砂の量は、例えばポンプ5aの推力や切換え
バルブ6の開閉時間を調整することで、適宜調整可能に
なっている。この導入工程は、常時行なうものでなく、
トンネル坑内でコンクリート打設を行なう際のみ行な
い、それ以外のタイミングでは、切換えバルブ6は土砂
圧送管5側に掘削土砂が搬送されるようにしておく。
In the excavated matter introduction step, one of the excavated earth and sand is generated.
In the step of introducing the part into the mixer 8, by operating a switching valve 6 provided in the middle of the one-system sediment pressure feeding pipe 5, the excavated sediment fed into the sediment pressure feeding pipe 5 is branched into the branch pipe 7. Into the mixer 8. The amount of excavated earth and sand introduced into the mixer 8 can be appropriately adjusted, for example, by adjusting the thrust of the pump 5a and the opening and closing time of the switching valve 6. This introduction process is not always performed,
It is performed only when concrete is poured in the tunnel pit, and at other times, the switching valve 6 is set so that the excavated earth and sand is conveyed to the earth and sand pressure feeding pipe 5 side.

【0024】硬化材搬入注入工程は、地上20から立坑
21を通してトンネル坑内22に生モルタル(流動状の
硬化材)を搬入しミキサー8内に注入する工程である。
搬入は、モルタル搬入用圧送管10を介して行なわれ、
途中、ポンプ10aにより推力が加えられてミキサー8
まで圧送される。ミキサー8はシールド掘進機1の後方
台車に積載され、シールド掘進機1と共に進んでいき、
その進行に伴ってモルタル搬入用圧送管10も伸ばして
いく。生モルタルには、圧送管10を圧送する間に硬化
が進まないようにするための凝結遅延剤(材)や、コン
クリート打込み時の流動性を改善する高性能AE減水剤
(材)や増粘剤(材)などの薬剤(材)を適宜混合して
も良い。この工程も、常時行なうものでなく、トンネル
坑内でコンクリート打設を行なう際のみ行なう。
The hardening material carry-in / injecting step is a process of carrying raw mortar (flowable hardening material) from the ground 20 through the shaft 21 into the tunnel pit 22 and injecting it into the mixer 8.
Carrying in is performed via a mortar carrying pressure feeding pipe 10,
On the way, thrust is applied by the pump 10a and the mixer 8
Pumped up to. The mixer 8 is mounted on the bogie behind the shield machine 1 and proceeds with the shield machine 1.
As the process proceeds, the mortar carry-in pressure feed pipe 10 also extends. In the raw mortar, a setting retarder (material) for preventing the hardening from proceeding while the pumping tube 10 is being pumped, a high-performance AE water reducing agent (material) for improving the fluidity during concrete pouring, and a thickening agent An agent (material) such as an agent (material) may be appropriately mixed. This step is not always performed, but is performed only when concrete is cast in the tunnel pit.

【0025】混練工程は、ミキサー8内で掘削土砂とモ
ルタルとを混練する工程である。掘削土砂とモルタルの
配合比率は、掘削土砂の土質(例えば粘土質のものや砂
礫分が多い土質など)に応じて適宜制御する。例えば、
粘土質の掘削土砂(例えば粉体粘土と同等)を使用した
場合、砂:セメントが1:0.8〜1.2のモルタル
で、土砂:モルタルが5:4〜6、水:セメントが8:
9〜11となるような配合の混練をすることで、目標強
度60kgf/cm2以上、且つ、ポンプ打設可能な程
度の粘性を有するコンクリートが製造できる。
The kneading step is a step of kneading the excavated earth and sand and the mortar in the mixer 8. The mixing ratio of the excavated earth and mortar is appropriately controlled according to the soil quality of the excavated earth and sand (for example, a clay-based earth and a soil with a large amount of gravel). For example,
When clay excavated soil (e.g., equivalent to powdered clay) is used, the mortar is 1: 0.8 to 1.2 for sand: cement, 5: 4 to 6 for sand: mortar, and 8 for water: cement. :
By kneading the mixture so as to have a mixing ratio of 9 to 11, concrete having a target strength of 60 kgf / cm 2 or more and a viscosity that can be pumped can be produced.

【0026】また、砂礫分が多い掘削土砂を使用した場
合では、砂:セメントが1:0.8〜1.2のモルタル
で、土砂:モルタルが5:4〜6、高性能AE減水剤や
増粘剤の添加量を調整して混練することで、目標強度6
0kgf/cm2以上、且つ、ポンプ打設可能な程度の
粘性を有するコンクリートが製造できる。つまり、掘削
土の性状に応じて土砂とモルタルの配合比率や混和剤
(材)の添加量を適宜調整することで、掘削土の分級・
分離を行なうことなく、ポンプ打設可能で目標強度が得
られるコンクリートを製造できる。
When excavated earth and sand with a large amount of gravel is used, the ratio of sand: cement is 1: 0.8 to 1.2, and the ratio of sand: mortar is 5: 4 to 6, and high performance AE water reducing agent and By adjusting the amount of the thickener to be kneaded, the target strength 6
Concrete having a viscosity of 0 kgf / cm 2 or more and having such a viscosity as can be pumped can be manufactured. In other words, by appropriately adjusting the mixing ratio of soil and mortar and the amount of admixture (material) added according to the properties of the excavated soil,
It is possible to produce concrete that can be pumped and achieve the target strength without separation.

【0027】コンクリート打設工程は、ミキサー8で混
練して製造したコンクリートをコンクリート圧送管9を
介してポンプ圧送し、インバート材11としてトンネル
坑内22のインバート部に打設する工程であり、任意の
時間間隔おきに断続的に適宜行なわれる。
The concrete placing step is a step of pumping concrete produced by kneading with the mixer 8 through the concrete pumping pipe 9 and placing it as an invert material 11 in the invert portion of the tunnel pit 22. It is performed intermittently at appropriate time intervals.

【0028】以上のように、この実施の形態のトンネル
工法によれば、掘削土砂を地上に搬出するのに2系統の
土砂圧送管4,5を用いており、これらのうち1系統の
土砂圧送管5から掘削物をミキサーに導入するので、ミ
キサー8に導入する掘削土砂の量の調整が掘削土砂の総
量に関係なく容易に行なえる。例えば、ミキサー8内に
導入する掘削土砂を少なくする場合には、他方の土砂圧
送管4の送量を多くすることで土砂圧送の総量を一定と
することが出来る。また、切換えバルブ6により掘削物
の搬送先をミキサー8と地上20の土砂ホッパー13と
に切換え可能なので、ミキサー8を作動させてコンクリ
ート製造を行なうときのみ掘削土砂をミキサー8に搬送
し、そうでないときはトンネル坑外に搬出することが出
来る。
As described above, according to the tunnel construction method of this embodiment, two systems of sediment feeding pipes 4 and 5 are used to carry excavated earth and sand to the ground, and one of these two systems is used. Since the excavated material is introduced from the pipe 5 into the mixer, the amount of excavated sediment introduced into the mixer 8 can be easily adjusted regardless of the total amount of excavated sediment. For example, when the excavated earth and sand to be introduced into the mixer 8 is reduced, the total amount of the earth and sand pumping can be made constant by increasing the feeding amount of the other earth and sand pressing pipe 4. In addition, since the transport destination of the excavated material can be switched between the mixer 8 and the earth and sand hopper 13 on the ground 20 by the switching valve 6, the excavated earth and sand is transported to the mixer 8 only when the mixer 8 is operated to perform concrete production. Sometimes it can be carried out of the tunnel pit.

【0029】また、ミキサー8に注入する硬化材として
地上20から搬入した生モルタルを使用するので、従来
の粉セメントと水とを用いて一から混練する場合に較べ
て、混練に要する時間が短縮され、また、硬化材と掘削
土砂との配合比率の管理も簡易化できる。また、モルタ
ルの搬送を停止させると搬送経路上で硬化が進んでしま
うため、モルタル側で供給量の調整は急激に行ないがた
いが、掘削土砂の供給側で導入量が調整であるので、こ
の調整によりコンクリート材料の配合比率を適切なもの
に調整できる。
Further, since the raw mortar carried from the ground 20 is used as the hardening material to be injected into the mixer 8, the time required for kneading is reduced as compared with the case where kneading is carried out from scratch using conventional powder cement and water. In addition, the management of the mixing ratio between the hardened material and the excavated soil can be simplified. Also, if the transport of mortar is stopped, the hardening proceeds on the transport path, so it is difficult to adjust the supply amount on the mortar side rapidly, but since the introduction amount is adjusted on the supply side of excavated earth and sand, this The adjustment allows the mixing ratio of the concrete material to be adjusted appropriately.

【0030】また、泥土圧式シールド工法の掘削土砂を
そのままの状態でミキサー8に導入してコンクリートを
製造するので、例えば、従来の所定粒径以上の土砂を分
級・分離して骨材に使用する工法に較べて、掘削土砂の
再利用率が良く、分級するための装置などが不用でトン
ネル坑内22を広く使用できる。また、泥水加圧式シー
ルド工法の掘削泥土を使用する場合、脱水装置等の大型
の装置を使用する必要があることから、トンネル坑内2
2でコンクリート製造することが困難であったが、泥土
圧式シールド工法に適用することで、そのままの掘削土
砂が利用できるのでトンネル坑内22でコンクリート製
造する場合でも、脱水装置などの装置によりトンネル坑
内22の空間が大きく占められるといった不都合がな
い。
In addition, since excavated earth and sand of the mud pressure shield method is introduced into the mixer 8 as it is to produce concrete, for example, conventional earth and sand having a predetermined particle size or more is classified and separated and used as aggregate. Compared with the construction method, the reuse rate of excavated earth and sand is good, and a device for classifying is unnecessary, so that the inside of tunnel tunnel 22 can be widely used. In addition, when using excavated mud of the mud pressurized shield method, it is necessary to use a large-sized device such as a dewatering device.
Although it was difficult to produce concrete in Step 2, it is possible to use the excavated earth and sand as it is by applying the method to the mud pressure shield method. There is no inconvenience that the space is occupied greatly.

【0031】また、掘削土砂を再利用したコンクリート
打設としてインバート部のコンクリート打設を行なうこ
とで、再利用コンクリートとして最も適合した実施態様
となる。
Further, by laying concrete in the invert portion as concrete laying by reusing excavated earth and sand, an embodiment most suitable as recycled concrete is obtained.

【0032】なお、本発明は、この実施の形態のトンネ
ル工法に限られず、例えば、トンネル工法としてシール
ド工法、詳細には泥土圧式シールド工法を1例として挙
げたが、その他、種々のトンネル工法に適用しても良
い。また、掘削土砂を搬出する搬出手段として2系統の
土砂圧送管を例示しているが、もっと多数系統設けても
良い。また、硬化材としてモルタルを示したが生コンク
リートなどでも良いし、搬送手段を複数系統設けたこと
で得られる効果は、硬化材として粉セメントを使用した
場合でも奏される。また、硬化材、掘削土砂および加水
の配分比率など、具体的に示した細部構成は、発明の主
旨を逸脱しない範囲で適宜変更可能である。
The present invention is not limited to the tunnel method of this embodiment. For example, a shield method, specifically, a mud pressure shield method is given as an example of a tunnel method, but other various tunnel methods are also applicable. May be applied. In addition, as an unloading means for unloading excavated earth and sand, two systems of earth and pressure feeding pipes are illustrated, but more systems may be provided. Although mortar is shown as a hardening material, ready-mixed concrete or the like may be used, and the effect obtained by providing a plurality of conveying means can be obtained even when powder cement is used as the hardening material. Further, the detailed configuration specifically shown, such as the distribution ratio of the hardened material, excavated earth and sand, and water, can be appropriately changed without departing from the gist of the invention.

【0033】[0033]

【発明の効果】請求項1記載の発明によれば、掘削物を
トンネル坑外に搬出するのに複数系統の搬送手段を用い
ており、これらのうち1系統の搬送手段から掘削物をミ
キサーに導入するので、ミキサーに導入する掘削物の量
の調整が掘削物の総量に関係なく容易に行なえる。ま
た、切換え手段により掘削物の搬送先をミキサーとトン
ネル坑外とに切換え可能なので、ミキサーを作動させて
コンクリート製造を行なうときのみ掘削物をミキサーに
搬送し、そうでないときはトンネル坑外に搬出すること
が出来る。
According to the first aspect of the present invention, a plurality of transportation means are used to carry out the excavated material outside the tunnel mine, and the excavated material is transferred from one of these transportation means to the mixer. With the introduction, the amount of excavated material introduced into the mixer can be easily adjusted regardless of the total amount of excavated material. In addition, since the transfer destination of the excavated matter can be switched between the mixer and the outside of the tunnel by the switching means, the excavated matter is transferred to the mixer only when the concrete is manufactured by operating the mixer, and if not, the excavated matter is carried out of the tunnel. You can do it.

【0034】請求項2記載の発明によれば、ミキサーに
注入する硬化材としてトンネル坑外から搬入する流動状
の硬化材(例えば生コンクリートや生モルタルなど)を
使用するので、従来の粉セメントと水とを用いて一から
混練する場合に較べて、混練に要する時間が短縮され、
また、硬化材の配合比率の管理も簡易化できる。
According to the second aspect of the present invention, a fluid hardening material (for example, fresh concrete or fresh mortar) carried from outside the tunnel is used as the hardening material to be injected into the mixer. Compared to the case of kneading from scratch with water, the time required for kneading is reduced,
Also, the management of the mixing ratio of the curing material can be simplified.

【0035】請求項3記載の発明によれば、請求項1と
2の発明効果を合せ持つことが出来る。また、流動状の
硬化材の搬送を停止させたりすると搬送経路上で硬化が
進んでしまうため、硬化材側の供給量の調整は急激に行
ないがたいが、掘削物の供給側で導入量が調整であり、
この調整によりコンクリート材料の配合比率を適切なも
のに調整できる。
According to the third aspect of the invention, the effects of the first and second aspects can be combined. Also, if the flow of the hardened hardening material is stopped, the hardening proceeds on the transport route, so it is difficult to adjust the supply amount on the hardened material side rapidly. Adjustment
By this adjustment, the mixing ratio of the concrete material can be adjusted to an appropriate one.

【0036】請求項4記載の発明によれば、泥土圧式シ
ールド工法の掘削物をそのままの状態でミキサーに導入
してコンクリートを製造するので、例えば、従来の所定
粒径以上の土砂を分級・分離して骨材に使用する工法に
較べて、土砂の再使用率が良く、分級するための装置な
どが不用でトンネル坑内を広く使用できる。また、泥水
加圧式シールド工法の掘削土を使用する場合、脱水装置
等の大型の装置を使用する必要があることから、トンネ
ル坑内でコンクリート製造することが困難であったが、
泥土圧式シールド工法に適用することで、そのままの掘
削土が利用できるのでトンネル坑内でコンクリート製造
する場合でも、脱水装置などの装置によりトンネル坑内
の空間が大きく占められるといった不都合がない。
According to the fourth aspect of the present invention, concrete is manufactured by introducing the excavated material of the mud pressure shield method into the mixer as it is, so that, for example, the conventional method of classifying and separating earth and sand having a predetermined particle size or more. Compared to the method used for aggregate, the reuse rate of earth and sand is better, and no equipment for classifying is required, and the tunnel pit can be widely used. Also, when using excavated soil of the mud pressurized shield method, it was necessary to use a large device such as a dewatering device, so it was difficult to produce concrete in the tunnel pit,
By applying the method to the mud pressure shield method, the excavated soil can be used as it is, so that even when concrete is manufactured in the tunnel, there is no inconvenience that the space in the tunnel is largely occupied by a device such as a dewatering device.

【0037】請求項5記載の発明によれば、掘削物を再
利用したコンクリート打設としてインバート部のコンク
リート打設を行なうことで、再利用コンクリートとして
最も適合した実施態様となる。
According to the fifth aspect of the present invention, the concrete placement of the invert portion is performed as the concrete placement by reusing the excavated material, so that the embodiment most suitable for the recycled concrete is obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態のトンネル工法の実施態様
を示す模式図である
FIG. 1 is a schematic view showing an embodiment of a tunnel construction method according to an embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 シールド掘進機 2 スクリューコンベア 3 シールド掘進機の後方台車あるいは坑内の適当
な定位置のコンクリート製造場所 4,5 2系統の土砂圧送管(搬出手段) 6 切換えバルブ(切換え手段) 7 分岐管 8 ミキサー 9 コンクリート圧送管 10 モルタル搬入用圧送管 11 インバート材(インバート部に打設されたコン
クリート) 13 土砂ホッパー 14 トラックアジテータ車 20 地上 21 立杭 22 トンネル坑内
DESCRIPTION OF SYMBOLS 1 Shield excavator 2 Screw conveyor 3 Rear bogie of shield excavator or concrete production place at an appropriate fixed position in a mine 4, 5 Two-system sediment pressure feeding pipe (unloading means) 6 Switching valve (switching means) 7 Branch pipe 8 Mixer 9 Concrete Pumping Pipe 10 Mortar Carrying Pumping Pipe 11 Invert Material (Concrete Cast Into Invert) 13 Sediment Hopper 14 Truck Agitator Car 20 Ground 21 Standing Pile 22 Inside Tunnel Tunnel

───────────────────────────────────────────────────── フロントページの続き (72)発明者 齋田 信一 東京都港区虎ノ門1丁目20番10号 西松建 設株式会社内 (72)発明者 佐藤 靖彦 東京都港区虎ノ門1丁目20番10号 西松建 設株式会社内 (72)発明者 西田 徳行 東京都港区虎ノ門1丁目20番10号 西松建 設株式会社内 (72)発明者 金丸 信一 東京都港区虎ノ門1丁目20番10号 西松建 設株式会社内 Fターム(参考) 2D054 AC04 CA05 DA03 DA24 2D055 BA01 CA08 KA08 KA09 KA11 KB00  ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Shinichi Saida 1-20-10 Toranomon, Minato-ku, Tokyo Inside Nishimatsu Construction Co., Ltd. (72) Inventor Yasuhiko Sato 1-20-10 Toranomon, Minato-ku, Tokyo Nishimatsu Construction Co., Ltd. (72) Inventor Noriyuki Nishida 1-20-10 Toranomon, Minato-ku, Tokyo Nishimatsu Construction Co., Ltd. (72) Inventor Shinichi Kanamaru 1-20-10 Toranomon, Minato-ku, Tokyo Nishimatsu F-term in Construction Corporation (reference) 2D054 AC04 CA05 DA03 DA24 2D055 BA01 CA08 KA08 KA09 KA11 KB00

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 トンネル坑内で掘削処理とコンクリート
打設とを行なうトンネル工法において、 掘削処理により生じた掘削物をトンネル坑外まで搬出す
る掘削物搬出工程と、 掘削物の1部をトンネル坑内のミキサーに導入する掘削
物導入工程と、 ミキサーに硬化材を注入する硬化材注入工程と、 ミキサー内に入れられた掘削物および硬化材とをミキサ
ーにより混練する混練工程と、 混練されたコンクリートを坑内に打設するコンクリート
打設工程とを有し、 前記掘削物搬出工程は、前記掘削物を複数系統の搬送手
段を介してトンネル坑外まで搬出する工程であり、 前記掘削物導入工程は、前記複数系統の搬送手段の少な
くとも1つに設けられた切換え手段を操作することで該
少なくとも1つの搬送手段の掘削物を前記ミキサーに導
入する工程であることを特徴とするトンネル工法。
1. A tunnel construction method in which excavation processing and concrete casting are carried out in a tunnel pit, wherein an excavated matter is carried out outside the tunnel pit, and a part of the excavated substance is removed from the tunnel pit. Excavated material introduction process for introducing into the mixer, hardened material injecting process for injecting the hardened material into the mixer, kneading process for kneading the excavated material and the hardened material placed in the mixer with the mixer, and mixing the kneaded concrete in the downhole The excavated matter carrying out step is a step of carrying out the excavated matter to the outside of the tunnel mine through a plurality of systems of transporting means, and the excavated matter introducing step includes: By operating a switching means provided in at least one of the plurality of transport means, the excavated material of the at least one transport means is introduced into the mixer. Tunneling method, which is a degree.
【請求項2】 トンネル坑内で掘削処理とコンクリート
打設とを行なうトンネル工法において、 掘削処理により生じた掘削物をトンネル坑外まで搬出す
る掘削物搬出工程と、 掘削物の1部をトンネル坑内のミキサーに導入する掘削
物導入工程と、 トンネル坑外からトンネル坑内に流動状の硬化材を搬入
する硬化材搬入工程と、 該流動状の硬化材を前記ミキサーに注入する硬化材注入
工程と、 ミキサー内に入れられた掘削物および流動状の硬化材と
をミキサーにより混練する混練工程と、 混練されたコンクリートを坑内に打設するコンクリート
打設工程とを有することを特徴とするトンネル工法。
2. A tunnel construction method in which excavation processing and concrete casting are carried out in a tunnel pit, wherein a digging object carrying-out step of carrying out the digging substance generated by the digging processing to the outside of the tunnel pit; An excavated matter introducing step for introducing into the mixer; a hardening material carrying-in step for carrying a flowing hardening material into the tunnel from outside the tunnel; a hardening material injecting step for injecting the flowing hardening material into the mixer; A tunnel construction method, comprising: a kneading step of kneading excavated matter and a fluid hardening material put in the inside with a mixer; and a concrete placing step of placing kneaded concrete into a pit.
【請求項3】 請求項2記載のトンネル工法において、 前記掘削物搬出工程は、前記掘削物を複数系統の搬送手
段を介してトンネル坑外まで搬出する工程であり、 前記掘削物導入工程は、前記複数系統の搬送手段の少な
くとも一つに設けられた切換え手段を操作することで該
少なくとも1つの搬送手段の掘削物を前記ミキサーに導
入する工程であることを特徴とするトンネル工法。
3. The tunnel construction method according to claim 2, wherein the excavated matter carrying out step is a step of carrying out the excavated matter out of the tunnel mine via a plurality of systems of conveying means. A tunnel method, wherein the excavated material of the at least one transport means is introduced into the mixer by operating a switching means provided in at least one of the transport means of the plurality of systems.
【請求項4】 請求項1〜3の何れかに記載のトンネル
工法であって、 前記掘削物として流動性を有する掘削土砂が発生される
泥土圧式シールド工法に適用し、 前記ミキサーに導入する掘削物として、分級・分離を行
なわないそのままの掘削土砂を用いることを特徴とする
トンネル工法。
4. The tunnel construction method according to claim 1, wherein the excavation object is applied to a mud pressure shield construction method in which excavated soil having fluidity is generated, and the excavation is introduced into the mixer. A tunneling method characterized by using uncut excavated earth and sand without classification and separation as the object.
【請求項5】 請求項1〜4の何れかに記載のトンネル
工法において、 前記コンクリート打設工程により、トンネル坑内のイン
バート部のコンクリート打設を行なうことを特徴とする
トンネル工法。
5. The tunnel construction method according to claim 1, wherein the concrete placement step includes placing concrete in an invert portion in a tunnel pit.
JP08670199A 1999-03-29 1999-03-29 Tunnel construction method Expired - Fee Related JP3253931B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08670199A JP3253931B2 (en) 1999-03-29 1999-03-29 Tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08670199A JP3253931B2 (en) 1999-03-29 1999-03-29 Tunnel construction method

Publications (2)

Publication Number Publication Date
JP2000282791A true JP2000282791A (en) 2000-10-10
JP3253931B2 JP3253931B2 (en) 2002-02-04

Family

ID=13894253

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08670199A Expired - Fee Related JP3253931B2 (en) 1999-03-29 1999-03-29 Tunnel construction method

Country Status (1)

Country Link
JP (1) JP3253931B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007191859A (en) * 2006-01-17 2007-08-02 Hanshin Expressway Co Ltd Invert subgrade construction method
JP2009108584A (en) * 2007-10-30 2009-05-21 Shimizu Corp Processing device for tunnel excavated soil
CN103244132A (en) * 2013-04-28 2013-08-14 上海市机械施工有限公司 Construction method for crossing houses by aid of shield tunneling machine in sandy soil and slurry injecting system
JP2014173290A (en) * 2013-03-07 2014-09-22 Japan Railway Construction Transport & Technology Agency Tunnel construction method
JP2017154943A (en) * 2016-03-03 2017-09-07 宇部興産機械株式会社 Manufacturing method and manufacturing device of building material using tunnel excavation muck
JP7154452B1 (en) * 2022-08-22 2022-10-17 大栄工機株式会社 Invert Pier

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111140252A (en) * 2019-12-11 2020-05-12 安徽理工大学 Circulating layering slip casting device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007191859A (en) * 2006-01-17 2007-08-02 Hanshin Expressway Co Ltd Invert subgrade construction method
JP4699218B2 (en) * 2006-01-17 2011-06-08 阪神高速道路株式会社 Invert roadbed construction method
JP2009108584A (en) * 2007-10-30 2009-05-21 Shimizu Corp Processing device for tunnel excavated soil
JP2014173290A (en) * 2013-03-07 2014-09-22 Japan Railway Construction Transport & Technology Agency Tunnel construction method
CN103244132A (en) * 2013-04-28 2013-08-14 上海市机械施工有限公司 Construction method for crossing houses by aid of shield tunneling machine in sandy soil and slurry injecting system
JP2017154943A (en) * 2016-03-03 2017-09-07 宇部興産機械株式会社 Manufacturing method and manufacturing device of building material using tunnel excavation muck
JP7154452B1 (en) * 2022-08-22 2022-10-17 大栄工機株式会社 Invert Pier

Also Published As

Publication number Publication date
JP3253931B2 (en) 2002-02-04

Similar Documents

Publication Publication Date Title
CN100361927C (en) Subsequent backfilled pea gravel concrete for lining back of tunnels and backfilling method
JP3253931B2 (en) Tunnel construction method
KR100902364B1 (en) Shield tunneling apparatus and constructing method thereof
JP4699218B2 (en) Invert roadbed construction method
JP2007162403A (en) Invert subgrade construction method
JP5193575B2 (en) Processing equipment, processing method of excavated sediment, excavator
JP2018021378A (en) Fluidized soil manufacturing method and transport method thereof
JP2000008367A (en) Viscous earth fluidizing method
JPH0732629Y2 (en) Tunnel building system
JP2001115485A (en) Treatment method and treatment device for construction soil
JP5571219B1 (en) Shield excavation residual soil processing method and processing system
JP2817493B2 (en) Construction method of shield tunnel
EP1538302B1 (en) Method of filling void spaces outside a machine produced tunnel wall
JP5158628B2 (en) Tunnel excavation soil treatment equipment
JPH0811084Y2 (en) Tunnel building system
JP2005139840A (en) Shield tunnel construction method and shield tunnel excavator
JP2022110480A (en) Tunnel backfilling method
JPH08105290A (en) Excavated sediment recycling system in mud type shield construction method
JP5670683B2 (en) Backfill injection system and method
JP5206363B2 (en) Sediment transport method and sediment transport system
JP2004169277A (en) Soil improvement method
JP2009001989A (en) Treatment equipment, treatment method for excavated sediment, shield machine, tunnel construction method, and tunnel constructed by the construction method
JP5158627B2 (en) How to use tunnel excavated soil
JP2005016009A (en) Excavated soil recycling method in shield tunneling method
JP2834412B2 (en) Excavated soil processing equipment kneaded with mud mortar

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071122

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081122

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081122

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091122

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091122

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101122

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101122

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111122

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121122

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131122

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees