JP2000199229A - Frame for slope greening and slope-greening construction method - Google Patents

Frame for slope greening and slope-greening construction method

Info

Publication number
JP2000199229A
JP2000199229A JP11000724A JP72499A JP2000199229A JP 2000199229 A JP2000199229 A JP 2000199229A JP 11000724 A JP11000724 A JP 11000724A JP 72499 A JP72499 A JP 72499A JP 2000199229 A JP2000199229 A JP 2000199229A
Authority
JP
Japan
Prior art keywords
slope
retaining wall
soil
frame
wood
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11000724A
Other languages
Japanese (ja)
Inventor
Hidekazu Kobori
英和 小堀
Hirotaka Sato
裕隆 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Forestry Co Ltd
Original Assignee
Sumitomo Forestry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Forestry Co Ltd filed Critical Sumitomo Forestry Co Ltd
Priority to JP11000724A priority Critical patent/JP2000199229A/en
Publication of JP2000199229A publication Critical patent/JP2000199229A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a frame for slope greening, by which soil required for growing tree saplings can be held stably and for which scrap wood such as timber from thinning can also be utilized, and a slope-greening construction method, by which the face of a slope can be changed into a forest efficiently by using the frame for slope greening. SOLUTION: In the frame for slope greening, a pair of retaining walls 3A, 3B composed of a plurality of wood 2, 2 are connected mutually at each one end section respectively. Both retaining wall sections 3A, 3B are formed by alternately superposing each wood 2, 2 of one retaining wall section 3A and each wood 2, 2 of the other retaining wall section 3B in the connecting section 4 of both retaining wall sections 3A, 3B, and installed onto the face of a slope 5 so as to mutually form specified angles at that time. In the slope-greening construction method, the inside of the frame 1 for slope greening is filled with borrow materials, and trees are planted into the frame 1 for slope greening.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、法面緑化用枠及び
この法面緑化用枠を用いた法面緑化工法に関し、詳細に
は、簡単且つ効率的に施工できると共に、客土を長期間
安定に保持することができ、間伐材等の廃材を利用する
こともできる法面緑化用枠、及びこの法面緑化用枠を用
い、効率的に法面の樹木による緑化を図ることのできる
法面緑化工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a slope revegetation frame and a slope revegetation method using the slope revegetation frame. A slope revegetation frame that can be stably maintained and can also use waste materials such as thinned wood, and a method that can use this slope revegetation frame to efficiently plant trees on slopes using trees It relates to the greening method.

【0002】[0002]

【従来の技術】法面の緑化工法では、一般的に、種子、
肥料及び土壌改良材等を混合した植生基盤材の吹付けに
よって法面上に厚層有機客土を形成する厚層吹付け工法
が行われている。この厚層吹付け工法では、法面上に予
めネットを敷設し、上記植生基盤材を吹付け機によって
圧送して該ネット越しに法面に対して吹き付け、岩盤地
や硬質土壌、瘠悪地等の法面においても、安定した厚層
有機客土を均一に形成できるようにしている。近年、法
面の緑化工法では、法面の安定や景観の改善、自然環境
の保全等の理由から、木本による樹林化を目的とした法
面の緑化技術が求められており、上述したような吹付け
工法では、野草類や牧草類、草花類等の草本に加えて木
本種等の種子を植生基盤材に配合することにより、法面
の樹木による緑化が可能である。
2. Description of the Related Art In the revegetation method of a slope, generally, seeds,
BACKGROUND ART A thick-layer spraying method of forming a thick organic soil on a slope by spraying a vegetation base material mixed with a fertilizer, a soil improving material, and the like has been performed. In this thick-layer spraying method, a net is laid in advance on the slope, and the vegetation base material is pumped by a spraying machine and sprayed on the slope through the net, and the rocky ground, hard soil, or poorly soiled land is laid. And the like, the stable thick organic soil can be formed uniformly. In recent years, the slope revegetation method requires slope revegetation technology for the purpose of planting trees with trees for reasons such as stability of the slope, improvement of the landscape, and conservation of the natural environment. In the spraying method, by adding seeds such as woody species to the vegetation base material in addition to herbs such as wild grasses, pastures, and flowers, it is possible to green the slopes with trees.

【0003】[0003]

【発明が解決しようとする課題】しかし、木本種子は他
の種子からの被圧の影響を受けやすく、特に成長力の旺
盛な外来の牧草種からの被圧を受けて充分に発芽・生育
できないことが多かった。また、種子の大きさ、形状が
吹き付け工法に適した木本の種類が限定されているこ
と、草本に比べて発芽率が安定しないこと、施工時期に
よって発芽、生育が大きく影響されること、隔年結果等
があり安定的に種子の入手ができないことなどの問題が
あった。また、吹き付けた法面客土中で木本種子を発芽
・生育させる場合、環境条件が厳しい場所では自然に委
ねた状態で成長させるのが難しく、また、成長にばらつ
きが生じて美観を損ねるという問題があった。
However, woody seeds are susceptible to pressure from other seeds, and are particularly germinated and grown under pressure from foreign grass species with strong growth potential. I couldn't do much. In addition, the size and shape of seeds are limited to the types of wood that are suitable for the spraying method, the germination rate is not stable compared to grass, the germination and growth are greatly affected by the construction time, There was a problem that the seeds could not be obtained stably due to the results. In addition, when germinating and growing woody seeds in sprayed slope soil, it is difficult to grow them naturally in places with severe environmental conditions, and it is said that growth is uneven and aesthetics are impaired. There was a problem.

【0004】そこで、特に法面の傾斜が急な場合には、
上述した吹付け工法では木本種子の定着が困難となるた
め、苗木を植栽する方法が採られることもある。苗木を
植栽する場合、種子の吹きつけに比べて材料費、施工費
が多く要することから、法面全体を一様に植栽するので
はなく、まず小規模の樹林を群状に法面内に設置し、自
然の遷移によって、ついには全面の樹林化へと誘導する
方法が採られる場合がある。
[0004] Therefore, especially when the slope of the slope is steep,
In the spraying method described above, it is difficult to fix the woody seeds, so a method of planting a seedling may be adopted. When planting seedlings, material and construction costs are higher than when seeds are sprayed.Therefore, instead of planting the entire slope uniformly, small-scale forests must first be grouped into slopes. There is a method that is installed inside the building and eventually leads to full forestation by natural transition.

【0005】法面に苗木を植栽する場合、植栽する苗木
の生育に必要な土壌を確保する必要がある。この方法と
して、斜面に植え穴を掘り、生育に必要な土壌を客土す
る方法や、法面に階段状に段部を設ける方法(特開平8
−134918号公報)、斜面に穴を開け、植物体を挿
し込む方法(特開平8−158372号公報)、斜面に
構造物を設置し、その構造物内に土壌を充填して樹木の
苗を定植する方法(特開平8−27795号公報)等が
開発されている。
[0005] When seedlings are planted on the slope, it is necessary to secure the soil necessary for growing the seedlings to be planted. As this method, a method of digging a planting hole on a slope and cultivating soil necessary for growth, or a method of providing a stepped step on a slope (Japanese Patent Laid-Open No.
-134918), a method of making a hole in a slope and inserting a plant (Japanese Patent Application Laid-Open No. 8-158372), installing a structure on a slope, filling the structure with soil, and planting a tree seedling. A method of planting (JP-A-8-27795) and the like have been developed.

【0006】斜面に構造物を設ける場合、環境への配
慮、施工のし易さ、景観的な優しさ等の理由から、自然
素材である木材あるいは木質系天然素材の利用が求めら
れている。木材を用いた斜面への構造物としては、複数
本の木材を柵状に揃えて形成した柵状部材を対向させて
配設し、連結した枠体内部に土砂等を充填する方法(特
開平7−119166号公報)、木柵材を縦形に平行配
列し鉄筋材によって固定された土留め柵を用いる方法
(特開平8−113946号公報)が、法面の土留めを
目的として開発されている。
[0006] When a structure is provided on a slope, use of natural wood such as wood or a wood-based natural material has been demanded for reasons such as consideration for the environment, ease of construction, and gentle landscape. As a structure on a slope using wood, a method of disposing a fence-shaped member formed by aligning a plurality of woods in a fence shape and facing each other, and filling the inside of the connected frame with earth and sand or the like is disclosed in No. 7-119166), and a method using wooden retaining fences arranged in parallel in a vertical shape and using a retaining fence fixed by a reinforcing bar material (Japanese Patent Application Laid-Open No. 8-113946) has been developed for the purpose of retaining a slope. .

【0007】樹木等の苗木を植栽することを目的とした
構造物としては、植栽土の客土域を囲うように法面に設
置される鉄筋枠と、この鉄筋枠に上方から差し込み保持
されて、互いに当接状態で法面上に立て付けられる複数
本の柱体とから成り、かつ、前記鉄筋枠を、それぞれ柱
体群の内部側と外部側とに位置して柱体の立ち姿勢を規
制する上下の鉄筋枠体と、法面に対する鉄筋枠固定用の
アンカー鉄筋とから構成してあることを特徴とする植栽
土の保護枠(特開平8−302699号公報)、植栽土
の客土域の辺部に立設される複数本の金属製のガイド体
と、前記客土域の辺部に横積みにされて植栽土の擁壁を
形成する柱体とから成り、かつ、前記柱体にはガイド体
挿通用の貫通孔を形成して、この貫通孔にガイド体を挿
通させて前記柱体の横積み姿勢を規制させるように構成
してある植栽土の保護枠(特開平8−302700号公
報)等があるが、斜面の角度や表面の凹凸状況に応じて
木材の長さや切断する角度を調整する必要があり、ま
た、多くの貫通孔を設ける必要があることから加工が複
雑且つ困難で、施工性が著しく悪かった。また、貫通孔
を設けるためにある程度の太さを有する木材を用いる必
要があり、さらに使用する単木材内及び複数木材間での
太さのバラツキが小さいことが必要であった。このた
め、材木の一部を伐採することで発生する間伐材や製材
過程で発生する芯材などの廃材を利用することはできな
かった。
[0007] As a structure intended for planting saplings such as trees, a reinforcing bar frame installed on a slope so as to surround a customer soil area of planting soil, and a reinforcing bar frame is inserted from above and held. And a plurality of pillars that are erected on the slope in a contact state with each other, and the reinforcing bar frames are located on the inner side and the outer side of the pillar group, respectively, and the pillars are Planting soil protection frame (JP-A-8-302699), comprising upper and lower reinforcing bar frames for regulating the posture, and anchor bars for fixing the reinforcing bar frame to the slope. It is composed of a plurality of metal guides erected on the side of the guest soil area of the soil, and a pillar that is horizontally stacked on the side of the guest soil area to form a retaining wall of the planting soil. And a through hole for inserting a guide body is formed in the column, and the guide is inserted through the through hole to form the column. There is a protection frame for planting soil (Japanese Patent Laid-Open No. 8-302700) configured to restrict the horizontal stacking posture, but the length of the wood and the cutting angle in accordance with the angle of the slope and the unevenness of the surface. In addition, since it is necessary to adjust the number of holes and to provide many through holes, the processing is complicated and difficult, and the workability is extremely poor. In addition, it is necessary to use wood having a certain thickness in order to provide the through holes, and it is necessary that the variation in the thickness within a single wood used and among a plurality of woods is small. For this reason, it was not possible to use waste materials such as thinned lumber generated by cutting a part of timber and core materials generated in the lumbering process.

【0008】木材以外の天然系素材を用いる方法として
は、法面上に腐朽性のある材料によるプレート状に形成
された土止め用緑化材に接した状態で配設し、土壌を法
面上の一部に盛り上げて樹木を植栽する方法(特開平1
0−183635号公報)、2枚のパネルをV字型に組
み合わせた土止め部材を、法面上流側に開いたV字状態
で前記各植栽区域に固定した後に、前記土止め部材のV
字状の内側に土壌を入れ、この土壌に樹木を植栽する方
法(特開平10−280418号公報)などがある。し
かし、いずれも特殊に加工された部材を用いるために、
製造コストがかかり、また、主として山間地の施工現場
への資材運搬に多くの費用を要する。これらのいずれの
方法も、土壌を充填する構造物の谷側部分を構造物でほ
ぼ完全に覆うため、植栽直後から樹木が大きく生長し構
造物を十分覆うまでは、法面の下方から構造物が著しく
露見され、景観的に好ましくなかった。また、天然素材
であることから、いずれ腐朽し構造物として残らないも
のであり、腐朽したときには土留めとしての機能、強度
を失うことになる。そのような状態において激しい降雨
や降雪、融雪等に遭遇した場合、腐朽して強度を失った
構造物内に充填された土壌が勢いよく流出して法面を損
傷したり、あるいは、植栽した樹木が倒伏する、根部分
が露出し植栽樹木の生育を抑制するなどの危険性があっ
た。本発明は、以上のような実情に鑑みてなされた。
[0008] As a method of using a natural material other than wood, there is a method in which a soil is disposed in contact with a greening material for earth retaining formed in the shape of a plate made of a decay material on a slope, and soil is removed on the slope. Method of planting a tree by raising a part of the tree
JP-A No. 0-183635) After fixing a retaining member, which is a combination of two panels in a V-shape, to each of the planting areas in a V-shaped state opened on the slope upstream side, the V of the retaining member is fixed.
There is a method of putting soil in the inside of a character shape and planting a tree in the soil (Japanese Patent Laid-Open No. 10-280418). However, in order to use a specially processed member,
Manufacturing costs are high, and a great deal of cost is required mainly for transporting materials to construction sites in mountainous areas. In each of these methods, the valley side of the structure that fills the soil is almost completely covered with the structure, so the structure grows from the bottom of the slope immediately after planting until the trees grow large enough to cover the structure. Things were noticeably exposed, which was not aesthetically pleasing. In addition, since it is a natural material, it eventually rots and does not remain as a structure. When it rots, it loses its function and strength as an earth retaining material. When heavy rainfall, snowfall, snowmelt, etc. were encountered in such a condition, the soil filled in the decayed structure that had lost its strength vigorously flowed out, damaging the slope, or planting. There were dangers such as the trees falling down, the roots being exposed and the growth of the planted trees being suppressed. The present invention has been made in view of the above situation.

【0009】本発明の目的は、簡単且つ効率的に施工で
きると共に、樹木苗の生育に必要な土壌を安定に保持で
き、間伐材等の廃材を利用することもできる法面緑化用
枠、及び該法面緑化用枠を用いて法面を効率的に樹林化
することのできる法面緑化工法を提供することにある。
SUMMARY OF THE INVENTION An object of the present invention is to provide a slope revegetation frame which can be constructed simply and efficiently, can stably hold soil necessary for growing tree seedlings, and can utilize waste materials such as thinned wood. It is an object of the present invention to provide a slope revegetation method capable of efficiently reforesting a slope using the slope revegetation frame.

【0010】[0010]

【課題を解決するための手段】請求項1に記載の発明
は、それぞれ複数本の木材からなる一対の土止め壁部
を、それぞれの一端部において互いに連結させてなる法
面緑化用枠であって、上記両土止め壁部は、該両土止め
壁部の連結部において一方の該土止め壁部の各木材と他
方の該土止め壁部の各木材とが交互に積み重ねられて形
成されており、且つ互いに所定の角度をなすように法面
に設置されていることを特徴とする法面緑化用枠を提供
することにより、上記の目的を達成したものである。
The invention according to claim 1 is a slope greening frame formed by connecting a pair of retaining walls made of a plurality of pieces of wood to each other at one end thereof. The two retaining walls are formed by alternately stacking each piece of wood on one of the retaining walls and each piece of wood on the other retaining wall at a connection portion between the two retaining walls. The above object has been achieved by providing a slope greening frame, which is provided on a slope so as to form a predetermined angle with each other.

【0011】請求項2に記載の発明は、一対の上記土止
め壁部が平面視V字形状に連結されており、両土止め壁
部の連結部が谷側に向けられている請求項1記載の法面
緑化用枠を提供することにより、上記の目的を達成した
ものである。
According to a second aspect of the present invention, the pair of retaining walls are connected in a V-shape in plan view, and the connecting portion of the two retaining walls is directed to the valley side. The above object has been achieved by providing the described slope greening frame.

【0012】請求項3に記載の発明は、上記土止め壁部
おける上記連結部とは反対側の端部において、該土止め
壁部を構成する各木材の端部が互いに結束されている請
求項1又は2記載の法面緑化用枠を提供することによ
り、上記の目的を達成したものである。
According to a third aspect of the present invention, at the end of the retaining wall opposite to the connecting portion, the ends of each piece of wood constituting the retaining wall are bound together. The above object has been achieved by providing a slope greening frame according to Item 1 or 2.

【0013】請求項4に記載の発明は、上記土止め壁部
における上記連結部とは反対側の端部において、該土止
め壁部を構成する上記各木材の端部がそれぞれ法面に接
触させてある請求項1〜3の何れかに記載の法面緑化用
枠を提供することにより、上記の目的を達成したもので
ある。
According to a fourth aspect of the present invention, at the end of the retaining wall opposite to the connecting portion, the end of each piece of wood constituting the retaining wall contacts the slope. The above object has been achieved by providing a slope greening frame according to any one of claims 1 to 3 that has been made.

【0014】請求項5に記載の発明は、上記両土止め壁
部の山側の壁面に、透水性シートが配設されており、各
土止め壁部における各木材間の隙間が該透水性シートに
より閉塞されている請求項1〜4の何れかに記載の法面
緑化用枠を提供することにより、上記の目的を達成した
ものである。
According to a fifth aspect of the present invention, a water permeable sheet is disposed on the mountain-side wall surface of the both retaining wall portions, and a gap between each wood in each retaining wall portion is formed by the water permeable sheet. The above object has been attained by providing the slope greening frame according to any one of claims 1 to 4, which is closed by:

【0015】請求項6に記載の発明は、上記土止め壁部
を、法面に立設した杭により該法面に固定してある請求
項1〜5の何れかに記載の法面緑化用枠を提供すること
により、上記の目的を達成したものである。
According to a sixth aspect of the present invention, the earth retaining wall portion is fixed to the slope by a pile erected on the slope. The above object has been achieved by providing a frame.

【0016】請求項7に記載の発明は、請求項1〜6の
何れかに記載の法面緑化用枠内に客土を充填し、該法面
緑化用枠内に樹木を植樹することを特徴とする法面緑化
工法を提供することにより、上記の目的を達成したもの
である。
According to a seventh aspect of the present invention, there is provided a method of filling a slope greening frame according to any one of claims 1 to 6 with soil and planting trees in the slope greening frame. The above object has been achieved by providing a characteristic slope greening method.

【0017】請求項8に記載の発明は、上記客土に、上
記土止め壁部を構成する各木材間の隙間から苗木を植樹
する請求項7記載の法面緑化工法を提供することによ
り、上記の目的を達成したものである。
[0018] The invention according to claim 8 provides the slope revegetation method according to claim 7, wherein seedlings are planted in the guest soil from gaps between the respective woods constituting the retaining wall portion. The above object has been achieved.

【0018】請求項9に記載の発明は、法面に、植樹用
の開口部を形成した土止め用壁体を設置し、該土止め用
壁体の山側に土壌を盛ると共に該開口部を介して該土壌
中に樹木を植え付けることを特徴とする法面緑化工法を
提供することにより、自然な景観が早期に形成され、法
面の効率的な樹林化を図ることのできる法面緑化工法を
提供するものである。
According to a ninth aspect of the present invention, a soil retaining wall having an opening for tree planting is installed on a slope, and soil is piled on the mountain side of the soil retaining wall, and the opening is formed. A slope revegetation method that provides a slope revegetation method characterized by planting a tree in the soil through the soil, whereby a natural landscape is formed at an early stage and an efficient reforestation of the slope can be achieved. Is provided.

【0019】[0019]

【発明の実施の形態】以下、本発明の好ましい第1実施
形態について図面を参照しながら詳細に説明する。ここ
で、図1は第1実施形態の法面緑化用枠を示す斜視図、
図2は図1の法面緑化用枠内に客土を充填し苗木を植樹
した状態を示す模式図、図3は植樹してから1〜2年後
の状態を模式的に示す断面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a first preferred embodiment of the present invention will be described in detail with reference to the drawings. Here, FIG. 1 is a perspective view showing a slope greening frame of the first embodiment,
FIG. 2 is a schematic view showing a state where the soil is filled in the frame for greening the slope of FIG. 1 and seedlings are planted. FIG. 3 is a cross-sectional view schematically showing a state one to two years after planting. is there.

【0020】先ず、第1実施形態の法面緑化用枠につい
て詳細に説明する。第1実施形態の法面緑化用枠1は、
図1に示すように、それぞれ複数本の木材2,2・から
なる一対の土止め壁部3A,3Bを、それぞれの一端部
において互いに連結させてなる法面緑化用枠であって、
上記両土止め壁部3A,3Bは、該両土止め壁部3A,
3Bの連結部4において一方の該土止め壁部3Aの各木
材2,2・と他方の該土止め壁部3Bの各木材2,2・
とが交互に積み重ねられて形成されており、且つ互いに
所定の角度をなすように法面5に設置されている。各木
材は、元口を連結部方向、末口を端部方向として設置す
ることが望ましい。
First, the slope greening frame of the first embodiment will be described in detail. The slope 1 greening frame 1 of the first embodiment includes:
As shown in FIG. 1, a slope greening frame formed by connecting a pair of retaining walls 3A, 3B made of a plurality of pieces of wood 2, 2, respectively, to each other at one end,
The both retaining walls 3A, 3B are connected to the retaining walls 3A, 3B.
At the connecting portion 4 of 3B, each piece of wood 2,2. On one of the retaining wall sections 3A and each piece of wood 2,2, on the other retaining wall section 3B.
Are alternately stacked, and are installed on the slope 5 so as to form a predetermined angle with each other. Desirably, each piece of wood is installed with the base opening toward the connecting portion and the end opening toward the end.

【0021】一対の上記土止め壁部3A,3Bそれぞれ
は、それぞれ3本の木材2,2・からなる。各木材2
は、断面略円形の木材であり、各木材2の直径(直径が
最大である部分の直径)は10〜30cm、好ましくは
10〜20cmである。各木材2,2・は、最大径と最
小径の差が少ないものが好ましい。各木材2,2・の長
さは1〜5m、好ましくは2m〜4mである。木材2の
樹種は問わないが、抗腐朽性から、例えばスギ、ヒノキ
などの針葉樹が好ましい。尚、各木材2,2・には、耐
久性を向上させるために防蟻処理又は防腐処理を施して
も良い。また、本発明における木材には、竹材も含まれ
る。上記各土止め壁部3A,3Bを形成する各木材2,
2・は、径、長さにバラツキがあっても良いが、均一な
ものを用いるのが望ましい。
Each of the pair of retaining walls 3A, 3B is made of three pieces of wood 2, 2, respectively. Each wood 2
Is wood having a substantially circular cross section, and the diameter of each wood 2 (the diameter of the portion having the largest diameter) is 10 to 30 cm, preferably 10 to 20 cm. It is preferable that each wood 2, 2 · has a small difference between the maximum diameter and the minimum diameter. The length of each wood 2,2 is 1 to 5 m, preferably 2 to 4 m. The species of the wood 2 is not limited, but conifers such as cedar and hinoki are preferable from the viewpoint of anti-rotting property. Each of the woods 2 may be subjected to an ant-proof treatment or an antiseptic treatment in order to improve durability. The wood in the present invention also includes bamboo. Each of the woods forming the above retaining walls 3A, 3B 2,
2) may vary in diameter and length, but it is desirable to use a uniform one.

【0022】一対の上記土止め壁部3A,3Bは、それ
ぞれの端部において、平面視V字形状に連結されてお
り、両土止め壁部3A,3Bの連結部4が谷側に向けら
れている。連結部4において、一方の該土止め壁部3A
の各木材2,2・と他方の該土止め壁部3Bの各木材
2,2・とは交互に積み重ねられており、各土止め壁部
3A,3Bを構成する各木材2,2・間には、所定の隙
間6,6が形成されている。連結部4においては、各木
材2,2の交叉部位よりも多少各木材2,2の端部が突
出するように、各木材2,2を交叉させてある。
The pair of retaining walls 3A, 3B are connected at their respective ends in a V-shape in plan view, and the connecting portions 4 of the retaining walls 3A, 3B are directed to the valley side. ing. In the connecting portion 4, one of the retaining wall portions 3A
And the other timbers 2,2. Of the other retaining wall 3B are alternately stacked, and the respective timbers 2,2. Are formed with predetermined gaps 6,6. In the connecting portion 4, the timbers 2, 2 are crossed such that the ends of the timbers 2, 2 slightly project from the crossing portions of the timbers 2, 2.

【0023】一対の上記両土止め壁部3A,3Bは、互
いに所定の角度をなすように法面5に設置されている。
両土止め壁部3A,3Bのなす角度は、法面5の斜面の
状況に合わせて適宜調節することができるが、60〜1
60度、特に90〜120度が好ましい。法面5の傾斜
が急な場合は、両土止め壁部3A,3Bのなす角度を大
きくして、下方方向への荷重を分散させることが好まし
く、逆に法面5の傾斜が緩やかな場合は、両土止め壁部
3A,3Bのなす角度を適宜に小さくすることができ
る。
The pair of both retaining walls 3A, 3B are installed on the slope 5 so as to form a predetermined angle with each other.
The angle formed by the two retaining walls 3A and 3B can be appropriately adjusted according to the condition of the slope of the slope 5;
60 degrees, particularly preferably 90 to 120 degrees. When the slope of the slope 5 is steep, it is preferable to increase the angle between the retaining walls 3A and 3B to disperse the load in the downward direction, and conversely, when the slope of the slope 5 is gentle. The angle between the retaining walls 3A and 3B can be appropriately reduced.

【0024】上記各土止め壁部3A,3Bにおける上記
連結部4とは反対側の端部においては、該土止め壁部3
A,3Bを構成する各木材2,2・の端部2a,2a・
が番線7により互いに結束されている。このように、各
木材の端部2a,2a・を結束すれば、法面緑化用枠1
がより堅牢なものとなり、土壌を保持性が向上する。ま
た、上記土止め壁部3A,3Bにおける連結部4とは反
対側の端部において、該土止め壁部3A,3Bを構成す
る各木材2,2・の端部2a,2a・は、それぞれ法面
5に接触させてある。各木材2,2・の端部2a,2a
・を、それぞれ法面5に接触させれば、法面緑化用枠1
の安定性が向上し、該法面緑化用枠1を急傾斜の法面5
に設置した場合であっても、該法面緑化用枠1ないし個
々の木材2が、法面5の谷側に、ずれて移動するといっ
たことない。
At the end of each of the retaining walls 3A and 3B opposite to the connecting portion 4, the retaining wall 3 is provided.
A, 3B, ends 2a, 2a.
Are bound together by a line 7. In this manner, by binding the ends 2a of the wood, the slope greening frame 1 is formed.
Becomes more robust and the soil retention is improved. At the ends of the retaining walls 3A, 3B opposite to the connecting portion 4, the ends 2a, 2a of the woods 2, 2, constituting the retaining walls 3A, 3B are respectively It is in contact with the slope 5. Ends 2a, 2a of each wood 2, 2,
・ If each is brought into contact with the slope 5, the slope greening frame 1
The stability of the slope is improved and the slope greening frame 1 is
Even if it is installed in the slope, the slope greening frame 1 or the individual wood 2 does not move to the valley side of the slope 5 while being shifted.

【0025】上記両土止め壁部3A,3Bは、法面5に
打ち込み立設した複数の杭8により、谷側に崩れないよ
うに該法面5に固定してある。各杭8は、土止め壁部3
の谷側の壁面に当接するように立設させてある。これら
の杭8の一本の杭8aは、上記両土止め壁部3A,3B
の連結部4において、両方の土止め壁部3A,3Bに当
接するように配設してある。
The two retaining walls 3A and 3B are fixed to the slope 5 by a plurality of piles 8 driven into the slope 5 so as not to collapse to the valley side. Each pile 8 is a retaining wall 3
It is erected so that it contacts the wall of the valley side. One stake 8a of these stakes 8 is used as the two retaining walls 3A, 3B.
Is provided so as to abut on both of the retaining walls 3A and 3B.

【0026】上記土止め壁部3の山側の壁面には、図2
に示すように、客土の流出を防止する目的で、透水性を
有し、土壌を容易には通過させない透水性シート8が設
置されている。そして、この透水性シート9により各土
止め壁部3A,3Bにおける各木材2,2・間の隙間
6,6が閉塞されている。上記透水性シート9は、土止
め壁部3の山側の壁面と法面緑化用枠1に囲まれた法面
の一部とを覆うように敷設されている。
The wall surface on the mountain side of the retaining wall portion 3 is shown in FIG.
As shown in (1), a water-permeable sheet 8 that has water permeability and does not easily pass through the soil is provided for the purpose of preventing the outflow of the soil. The water-permeable sheet 9 closes the gaps 6, 6 between the woods 2, 2 in the retaining walls 3A, 3B. The water-permeable sheet 9 is laid so as to cover the wall surface on the mountain side of the retaining wall portion 3 and a part of the slope surrounded by the slope greening frame 1.

【0027】透水性シート9としては、網状シート、不
織布、ヤシ繊維シート、こも(イナワラシート)、生分
解性シートなどが用いられるが、これらの中でも、ヤシ
繊維シート、生分解性シート等の将来自然分解されるも
のが好ましい。尚、法面緑化用枠1は、法面5にネット
(網状体)14を敷設しアンカー等で固定した後、該ネ
ット14上に組み上げてある。
As the water permeable sheet 9, a mesh sheet, a nonwoven fabric, a coco fiber sheet, a coconut (inawawara sheet), a biodegradable sheet and the like are used. Those which are naturally degraded are preferred. The slope greening frame 1 is assembled on the net 14 after a net (net-like body) 14 is laid on the slope 5 and fixed with an anchor or the like.

【0028】土止め壁部3の山側の壁面及び/又は法面
緑化用枠1に囲まれた法面に、粗朶を設置し、この粗朶
の上に透水性シート9を敷設しても良い。粗朶の設置に
より、排水性が確保され、植樹した樹木がより良好に生
育する。上記粗朶としては、下枝刈りなどで切り取られ
た直径3cm以下の樹木枝の複数本を長さ1〜2m、直
径10〜20cm程度に束ねて結束したものを用いる。
この粗朶に、例えばヤナギのような発根性のよい樹木の
枝を用いると粗朶自体が根付き、保持枠の谷側面を安定
化することができる。
A scent may be installed on the wall surface on the mountain side of the retaining wall portion 3 and / or the slope surrounded by the slope greening frame 1, and a water-permeable sheet 9 may be laid on the scent. By installing a scent, drainage is ensured and the planted trees grow better. As the above-mentioned scent, a plurality of tree branches having a diameter of 3 cm or less cut out by lower pruning and the like are bundled into a length of about 1 to 2 m and a diameter of about 10 to 20 cm and tied.
If a tree branch having good rooting properties, such as willow, is used for this scent, the scent itself will take root and the valley side surface of the holding frame can be stabilized.

【0029】次に、上述のようにして組まれた法面緑化
用枠3を用いた法面緑化工法、即ち本発明の法面緑化工
法の第1実施形態について説明する。先ず、図2に示す
ように、上記法面緑化用枠1内に客土10を充填する。
上記客土10する土壌は、植物が栽培可能なものならい
ずれのものでもよく、黒土、赤土、真砂土など普通土壌
や、土壌改良材、肥料等を添加し植物の生育に適するよ
うに配合された培養土が用いられる。
Next, the slope greening method using the slope greening frame 3 assembled as described above, that is, the first embodiment of the slope greening method of the present invention will be described. First, as shown in FIG. 2, the soil 10 is filled in the slope greening frame 1.
The soil used for the above-mentioned soil 10 may be any soil as long as the plant can be cultivated, and is added to ordinary soil such as black soil, red soil, and masago, a soil improving material, a fertilizer, and the like to be added to be suitable for plant growth. Culture soil is used.

【0030】上記法面緑化用枠3内に上記客土10を充
填するには、高層吹き付け機又は圧送機にて客土10を
吹き付けるか又は敷き込む方法、あるいは土嚢を充填し
た袋をクレーンで吊り客土する方法等が用いられる。次
いで、客土10が充填された法面緑化用枠1内に樹木の
苗11を植樹する。すなわち、栽培された樹木の苗を、
客土10の上面に掘った植え穴の中に植え付ける。法面
緑化用枠1内に植樹する樹木の苗木の本数は、法面緑化
用枠1のサイズ等に応じて適宜に決定すれば良い。
In order to fill the soil 3 into the slope greening frame 3, a method of spraying or laying the soil 10 with a high-rise spraying machine or a pumping machine, or a method using a crane to fill a bag filled with sandbags is used. For example, a method of hanging a soil is used. Next, tree seedlings 11 are planted in the slope greening frame 1 filled with the soil 10. That is, the seedlings of the grown trees,
It is planted in the planting hole dug on the upper surface of the guest soil 10. The number of tree seedlings to be planted in the slope greening frame 1 may be appropriately determined according to the size of the slope greening frame 1 and the like.

【0031】植栽する苗木としては、法面の樹林化に通
常用いられている各種の樹木の苗木を特に制限なく用い
ることができるが、通常、法面の緑化目標に合わせて、
その土地の周辺の植生に適合した植物や景観形成に役立
つ植物を選択して用いる。例えば、照葉樹林を目標植生
とした場合、スダジイ、ツブラジイ、アラカシ、ウラジ
ロガシ、シラカシ、アカガシ、タブノキ、ヤブニッケ
イ、シロダモ、ヤブツバキ、モチノキ、ヒサカキ、アオ
キなどを選択することができる。また、例えば、落葉広
葉樹林を目標植生とした場合、ブナ、ミズナラなどブナ
科、ハウチワカエデ、ヤマモミジ、イタヤカエデ、シラ
カンバ、ダケカンバ、ミヤマザクラ、マユミ、ツリバ
ナ、ケヤキ、ハルニレ、サワグルミ、カツラ、モミ属、
ツガ属、マツ属、クロモジ、マンサク、アオキ、ヤブツ
バキ、ユズリハ、イヌツゲ、ヤマシキミなどを選択する
ことができる。
As seedlings to be planted, seedlings of various kinds of trees commonly used for forestation of slopes can be used without any particular limitation.
Select and use plants that are suitable for vegetation around the land and those that are useful for landscape formation. For example, when the vegetation is a target vegetation, it is possible to select Sudajii, Tsuburazii, Aracashi, Vladinki, Shirakashi, Akagasi, Tabunoki, Yabunikei, Shirodamo, Yabutsubaki, Mochinoki, Hisakaki, Aoki and the like. Also, for example, when the target vegetation is deciduous broad-leaved forest, beech, falconaceae such as Mizunara, Hauchiwa maple, yamamomiji, itaya maple, white birch, birch birch, yamazakura, mayumi, tsuribana, zelkova, harunire, souramimi, wig, fir genus,
Genus hemlock, genus pine, kuromoji, witch hazel, aoki, japonica camellia, yuzuriha, dogwood, yamashikimi, and the like can be selected.

【0032】更に、法面緑化用枠を構成する各木材2,
2・の間にできた隙間6,6にも樹木を植栽する。各木
材2,2・の間にできた隙間6,6に植樹した樹木の根
が十分に張ることによって、木材2,2・が腐朽により
土留めの機能を失っても客土層を安定的に保つことがで
きる。この場合、図2に示すように、植樹する樹木は、
法面緑化用枠の上面に植樹する苗木と同様にポット苗1
2でも良いが、ヤナギなど発根性のよい樹木の枝13を
挿して植えても良い。ヤナギ等の発根性のよい樹種は、
挿し木後すぐに発根、萌芽、成長するので、法面緑化用
枠1を早期に安定化させることができる。また、各木材
2,2・の間にできた隙間6,6にも樹木を植栽すれ
ば、植樹した樹木の地上部(茎や葉等)が速やかに成長
し繁茂することで、法面緑化用枠を覆い隠され、該法面
緑化用枠1が法面下方から見え難くなるので、法面の下
方からの景観が極めて良好となる。
Further, each of the woods 2 constituting the slope greening frame 2
Trees are also planted in the gaps 6, 6 formed between 2. The roots of the trees planted in the gaps 6 and 6 formed between the timbers 2 and 2 are sufficiently stretched, so that even if the timbers 2 and 2 lose their retaining function due to decay, the customer soil layer can be stably maintained. Can be kept. In this case, as shown in FIG.
Potted seedlings 1 as well as seedlings to be planted on the upper surface of the slope greening frame
2, but may be planted by inserting a branch 13 of a tree having good rooting properties such as willow. Tree species with good rooting properties, such as willow,
Rooting, sprouting, and growing immediately after cutting, the slope greening frame 1 can be stabilized early. In addition, if trees are planted in the gaps 6, 6 formed between the timbers 2, 2, the above-ground parts (stems, leaves, etc.) of the planted trees will grow and prosper quickly, and Since the greening frame is covered and hidden, and the slope greening frame 1 is difficult to be seen from below the slope, the landscape from below the slope is extremely good.

【0033】そして、法面緑化用枠1を設置した法面5
全体に対して、吹付け機等によって草本種子やピートモ
ス、パーク堆肥等を配合した植生基盤材15を吹き付け
る。この植生基盤材15を、法面緑化用枠1の谷側の壁
面にも同時に吹き付けることによって植物による被覆効
果がさらに向上する。また、植生基盤材15として、草
本及び樹木種子を混合した植生基盤材を用いれば、早期
に法面全体を植物で覆うことができる。この場合でも、
それらの植物に被圧されない程度まで生育した樹木を法
面緑化用枠1内に植樹してあるため、施工後、樹木苗が
成長し、最終的に目標とする植生を有する法面が得られ
る。尚、通常、法面には法面緑化用枠1と同様の構成を
有する法面緑化用枠を複数分散させて配置させて、法面
全体の樹林化を図る。この場合、複数の法面緑化用枠の
それぞれには、同一種類の樹木を植えても良いし、異な
る種類の樹木を植えても良い。
Then, the slope 5 on which the slope greening frame 1 is installed.
A vegetation base material 15 containing herbaceous seeds, peat moss, park compost, etc., is sprayed on the whole with a spraying machine or the like. By simultaneously spraying the vegetation base material 15 on the valley-side wall surface of the slope greening frame 1, the covering effect of the plant is further improved. If the vegetation base material 15 is a mixture of herbs and tree seeds, the entire slope can be covered with plants at an early stage. Even in this case,
Trees that have grown to such an extent that they are not pressed by the plants are planted in the slope greening frame 1, so that after construction, tree seedlings grow and finally a slope having the target vegetation is obtained. . Normally, a plurality of slope slope greening frames having the same configuration as the slope slope greenery frame 1 are dispersed and arranged on the slope to achieve a forestation of the entire slope. In this case, the same type of tree may be planted in each of the plurality of slope greening frames, or different types of trees may be planted.

【0034】上述した第1実施形態の法面緑化用枠1に
よれば、簡単且つ効率的に施工でき、樹木苗の生育に必
要な土壌を安定に保持できる法面緑化用枠を得ることが
できる。また、各木材2,2・間に隙間6,6が形成さ
れているため、材木の一部を伐採することで発生する間
伐材や製材過程で発生する芯材、雑木林の更新時に伐採
した伐採木などを利用することもできる。従って、施工
現場に近い地域で伐採した木材を利用することも容易と
なり、これにより資材運搬の費用を大幅に減少させるこ
とも可能である。
According to the slope greening frame 1 of the first embodiment described above, it is possible to obtain a slope greening frame that can be easily and efficiently constructed and can stably hold the soil required for growing tree seedlings. it can. In addition, since the gaps 6, 6 are formed between the timbers 2, 2, the thinnings generated by cutting a part of the timber, the cores generated in the lumbering process, and the cuttings cut down during renewal of the coppice forest Trees can also be used. Therefore, it is easy to use the cut timber in the area near the construction site, and it is possible to greatly reduce the cost of transporting the material.

【0035】また、上記土止め壁部3A,3Bが平面視
V字形上に連結されているため、強度に優れており、そ
れ自体の形態が安定に維持され、激しい降雨や降雪、融
雪等に遭遇した場合であっても、法面緑化用枠1内に充
填された土壌を該法面緑化用枠1内に安定に保持するこ
とができる。しかも、現地での施工がきわめて容易でか
つコスト安となり、特に急斜面や瘠悪地でも健全に緑化
を図ることができる。
Further, since the retaining walls 3A and 3B are connected in a V-shape in plan view, they are excellent in strength, their shape is maintained stably, and they are suitable for severe rainfall, snowfall, snow melting and the like. Even if it encounters, the soil filled in the slope greening frame 1 can be stably held in the slope greening frame 1. In addition, construction at the site is extremely easy and the cost is low, and it is possible to achieve healthy greening especially on steep slopes or poorly lands.

【0036】また、上記土止め壁部3A,3Bにおける
上記連結部4とは反対側の端部において、該土止め壁部
3A,3Bを構成する上記各木材2,2・の端部がそれ
ぞれ法面に接触させてあり、各木材2,2・間の隙間
6,6が、谷側の壁面に斜め上方に開口しているため、
該隙間6,6への樹木の植樹が容易である。また、法面
緑化用枠1が木材により形成されているため、該法面緑
化用枠1により自然環境に悪影響を与えたり、景観を著
しく悪化させることもない。
At the opposite ends of the retaining walls 3A, 3B from the connecting portion 4, the ends of the woods 2, 2 constituting the retaining walls 3A, 3B are respectively connected. Because it is in contact with the slope, and the gaps 6, 6 between the timbers 2, 2, open diagonally upward on the valley-side wall surface,
Tree planting in the gaps 6, 6 is easy. In addition, since the slope greening frame 1 is made of wood, the slope greening frame 1 does not adversely affect the natural environment or significantly degrade the landscape.

【0037】また、上記法面緑化用枠1を用いた第1実
施形態の法面緑化工法によれば、各木材2,2・間の隙
間6,6に樹木を植樹することができ、法面緑化用枠1
の谷側の壁面を早期に植物体で覆うことができるため、
法面の下方からの景観を自然に近い好ましい景観とする
ことができる。また、法面緑化用枠1は、天然素材であ
る木材からなるため、いずれ腐朽し構造物として残らな
いものであるが、腐朽しても植物体の根によって土留め
としての長期間安定に機能することができる。また、樹
木の苗木を植樹しているため、植栽した苗木が他の植物
から被圧を受けることがなく、また、播種工で問題とな
るような施工時期に制約されない利点もある。また、現
地での施工がきわめて容易かつ低コストであり、特に急
斜面や瘠悪地でも健全に緑化を図ることができる。
Further, according to the slope greening method of the first embodiment using the slope greening frame 1, trees can be planted in the gaps 6, 6 between the timbers 2, 2, and so on. Greenery frame 1
Because the valley side wall can be covered with plants early,
The landscape from below the slope can be a preferable landscape close to nature. In addition, since the slope revegetation frame 1 is made of natural wood, it will decay and will not remain as a structure. can do. In addition, since tree seedlings are planted, there is an advantage that the planted seedlings are not subjected to pressure from other plants and that there is no restriction on construction time, which is a problem in sowing work. Moreover, construction on site is extremely easy and low cost, and it is possible to achieve healthy greening especially on steep slopes and poorly lands.

【0038】次に、本発明の好ましい第2実施形態につ
いて図4を参照して説明する。第2実施形態の法面緑化
用枠1’は、第1実施形態の法面緑化用枠1よりも急斜
面の法面(例えば斜度30度)に適した実施形態であ
る。第2実施形態の法面緑化用枠1’は、両土止め壁部
3A,3Bそれぞれが山側に傾斜させてあり、各土止め
壁部3A,3Bの各木材2,2・が階段状に配されてい
る点において第1実施形態の法面緑化用枠1と相違する
が、その他の基本的な構成は、第1実施形態の法面緑化
用枠1におけるのと同様である。従って、以下、第1実
施形態の法面緑化用枠1と相違する点を主として説明
し、同様の部分については同一符号を付して説明を省略
する。
Next, a second preferred embodiment of the present invention will be described with reference to FIG. The slope greening frame 1 ′ of the second embodiment is an embodiment more suitable for a steep slope (for example, a slope of 30 degrees) than the slope greening frame 1 of the first embodiment. In the slope slope greening frame 1 'of the second embodiment, each of the retaining walls 3A, 3B is inclined toward the mountain side, and each of the timbers 2, 2,. Although the arrangement is different from the slope greening frame 1 of the first embodiment, the other basic configuration is the same as that of the slope greening frame 1 of the first embodiment. Therefore, hereinafter, the points different from the slope greening frame 1 of the first embodiment will be mainly described, and the same parts will be denoted by the same reference numerals and description thereof will be omitted.

【0039】第2実施形態においては、各土止め壁部3
A,3Bにおける最下部に位置する一対の木材2,2同
士、各土止め壁部3A,3Bにおける中間部に位置する
一対の木材2,2同士、及び各土止め壁部3A,3Bに
おける最上部に位置する一対の木材2,2同士がそれぞ
れ連結部4において互いにボルト等の連結具16により
連結されている。このように、2本の木材の交さ部位に
穴を設け、ボルト等の連結具16で止めることによっ
て、木材の斜め方向への滑りが防止され、強度を向上さ
せることができる。また、穴に通したボルトを支点に
し、V字型に開いて法面に固定することで、設置作業を
効率的に行うことができる。そして、土止め壁部3A,
3Bの連結部4には、互いに連結された左右一対の木材
2,2毎に一本の杭8a,8b,8cが立設されてお
り、各土止め壁部3A,3Bの階段状の形状が該3本の
杭8a,8b,8cによってより安定に保持される。
In the second embodiment, each retaining wall 3
A, 3B, a pair of timbers 2, 2 located at the lowermost position, a pair of timbers 2, 2 located at an intermediate portion of the retaining wall portions 3A, 3B, and a pair of timbers 2, 2 located at the lowermost position of the retaining wall portions 3A, 3B. A pair of timbers 2 and 2 located at the upper part are connected to each other at a connecting portion 4 by a connecting tool 16 such as a bolt. In this way, by providing a hole at the intersection of the two pieces of wood and fixing it with the connector 16 such as a bolt, the wood can be prevented from sliding in an oblique direction, and the strength can be improved. In addition, the installation work can be efficiently performed by opening a V-shape and fixing it to the slope using the bolt passed through the hole as a fulcrum. And the retaining wall 3A,
One pile 8a, 8b, 8c is erected on each of the pair of left and right timbers 2, 2 connected to each other at the connecting portion 4 of 3B, and the step-like shape of each of the retaining walls 3A, 3B is provided. Is more stably held by the three piles 8a, 8b, 8c.

【0040】第2実施形態の法面緑化用枠1’によって
も、第1実施形態の法面緑化用枠1におけるのと同様の
作用効果が奏し得られる。また、第1実施形態の法面緑
化工法と同様にして、第2実施形態の法面緑化用枠1’
を用いて法面の樹林化を図ることができる。
The same effect can be obtained by the slope greening frame 1 'of the second embodiment as in the slope greening frame 1 of the first embodiment. Moreover, similarly to the slope greening method of the first embodiment, the slope greening frame 1 ′ of the second embodiment.
Can be used to turn the slope into a forest.

【0041】第1及び第2実施形態の樹林化工法は、請
求項7〜9に記載の発明の好ましい一実施形態である。
即ち、請求項9に記載の発明においては、法面5に、植
樹用の開口部(隙間6)を形成した土止め用壁体(法面
緑化用枠1)を設置し、該土止め用壁体(法面緑化用枠
1)の山側に土壌10を盛ると共に該開口部(隙間6)
を介して該土壌10中に樹木12,13を植え付ける。
そして、請求項9に記載の発明によれば、土止め用壁体
の形成材料が、コンクリートであると木質材であるとに
拘わらず、土止め用壁体の谷側の壁面を樹木により早期
に覆い隠すことができ、法面に自然な景観を早期に形成
することができる。また、上記開口部から植え付けた樹
木の根によって、土止め用壁体が安定化する。
The forestation method according to the first and second embodiments is a preferred embodiment of the invention described in claims 7 to 9.
That is, in the invention according to claim 9, a slope wall 5 (a slope greening frame 1) having an opening for tree planting (a gap 6) is provided on the slope 5, and the slope wall 5 is provided with a slope. The soil 10 is piled on the mountain side of the wall (frame 1 for slope greening) and the opening (gap 6).
Trees 12 and 13 are planted in the soil 10 through the above.
According to the ninth aspect of the present invention, the valley-side wall surface of the retaining wall is formed by a tree earlier regardless of whether the material for forming the retaining wall is wood or wood. And a natural landscape can be formed early on the slope. In addition, the soil retaining wall is stabilized by the tree roots planted from the opening.

【0042】尚、請求項9に記載の発明における土止め
用壁体は、植樹用の開口部を有し、土止め機能を有する
ものであれば特に制限されず、上述した法面緑化用枠1
のようなものに限定されるものではない。例えば、複数
の木材を平行に隙間なく鉛直方向に積み上げて形成した
壁体の一部に、植樹用の開口部を設けても良い。植樹用
の開口部には、該開口部からの土壌の流出を防止するた
めに、透水性シート9等の適宜の流出防止手段を配する
ことが好ましい。
The wall for retaining wall according to the ninth aspect of the present invention is not particularly limited as long as it has an opening for tree planting and has a retaining wall function. 1
However, the present invention is not limited to this. For example, an opening for tree planting may be provided in a part of a wall formed by stacking a plurality of wood pieces in a vertical direction without gaps. It is preferable to provide an appropriate outflow preventing means such as the water permeable sheet 9 in the tree planting opening in order to prevent the soil from flowing out from the opening.

【0043】以上、本発明の法面緑化用枠及び法面緑化
工法それぞれの第1及び第2実施形態について説明した
が、本発明は、上記各実施形態に制限されることなく、
本発明それぞれの趣旨を逸脱しない範囲で適宜変更可能
である。
Although the first and second embodiments of the slope greening frame and the slope greening method of the present invention have been described above, the present invention is not limited to the above embodiments.
Modifications can be made as appropriate without departing from the spirit of the present invention.

【0044】第1及び第2実施形態の法面緑化用枠にお
いては、土止め壁部3A,3Bにおける連結部4とは反
対側の端部における各木材の端部を、それぞれ法面に接
触させたが、該各木材の端部を鉛直方向に積み重ねても
良い。また、一つの土止め壁部を、法面の山側と谷側と
を結ぶ直線に対し垂直に配し、該土止め壁部の両側に一
対の土止め壁部を連結させ、中央の土止め壁部と、左右
一対の土止め壁部との連結部を、第1又は第2実施形態
の連結部4と同様に、一方の土止め壁部(中央の土止め
壁部)の各木材と他方の該土止め壁部(左右一対の土止
め壁部)の各木材とが交互に積み重なるように形成して
も良い。この場合、左右一対の上記土止め壁部は、谷側
から山側に向かうに従い離隔するように設置するのが良
い。
In the slope greening frames of the first and second embodiments, the ends of the respective wood pieces at the ends of the retaining walls 3A and 3B opposite to the connecting portion 4 are respectively in contact with the slopes. However, the ends of the respective wood pieces may be stacked in the vertical direction. In addition, one of the retaining walls is arranged perpendicularly to a straight line connecting the mountain side and the valley side of the slope, and a pair of retaining walls is connected to both sides of the retaining wall, and a central retaining wall is provided. The connecting portion between the wall portion and the pair of left and right retaining walls is, like the connecting portion 4 of the first or second embodiment, connected to each wood of one retaining wall portion (central retaining wall portion). Each of the other retaining walls (a pair of left and right retaining walls) may be formed so as to be alternately stacked with the respective wood. In this case, it is preferable that the pair of left and right retaining walls be separated from the valley side toward the mountain side.

【0045】また、第1実施形態における杭8aを、土
止め壁部の谷側に設けるのに代え、又はそれに加えて、
全木材を貫通する貫通孔を形成して該貫通孔を貫通させ
るように配設しても良い。この場合、木材の組立に先だ
って杭を打っておき、該杭を支点にして、各木材を順次
V字型に開いて法面に固定することで、設置作業を効率
的に行うことができる。また、法面の傾斜が30度以上
である場合や、降雨量が多い地域など客土する土壌の流
出が懸念される場合には、木材の交さ部位を木材径の4
分の1程度ずつ両側から削り取り、木材間の隙間を少な
くして設置しても良い。
Also, instead of or in addition to providing the pile 8a in the first embodiment on the valley side of the retaining wall,
A through hole penetrating all the wood may be formed and disposed so as to penetrate the through hole. In this case, the installation work can be efficiently performed by hitting a pile before assembling the wood, and using the pile as a fulcrum, each wood is sequentially opened in a V-shape and fixed to the slope. When the slope of the slope is 30 degrees or more, or when there is a concern about the outflow of soil to be occupied, such as in an area with a large amount of rainfall, the intersection of the timber should be 4 mm in diameter.
It may be installed by shaving it from both sides by about one-half to reduce the gap between the woods.

【0046】また、各土止め壁部を構成する木材の本数
は、樹林化しようとする法面の広さや傾斜等に応じて適
宜に決定することができるが、各土止め壁部それぞれに
ついて2〜5本、特に3〜4本であることが好ましい。
また、各土止め壁部を構成する木材は、角材であっても
良い。また、木材の固定方法としては、木材を安定的に
固定することができれば特に制限はないが、法面に杭
(アンカー)を打ち込み、木材を固定する方法や、番線
(ワイヤー)を用いて固定する方法が用いられる。杭は
連結部の直下や、該連結部とは反対側の木材の端部等に
設置し、また、必要に応じてさらに多く設けても良い。
土止め壁部の連結部部分をワイヤーを用いて固定し、該
連結部とは反対側端部を杭を用いて固定してもよい。杭
を用いて固定する場合、木材間を結束すると良い。尚、
本発明における一の実施形態における説明省略部分及び
一の実施形態のみが有する要件は、それぞれ他の実施形
態に適宜に適用される。また、各実施形態における要件
は各実施形態間で相互に置換可能である。
The number of woods constituting each retaining wall can be appropriately determined in accordance with the width and inclination of the slope to be made into a forest. It is preferably from 5 to 5, especially from 3 to 4.
Further, the timber constituting each of the retaining walls may be a square lumber. There is no particular limitation on the method of fixing the wood as long as the wood can be stably fixed. However, a method of fixing the wood by driving a pile (anchor) into the slope or fixing the wire using a wire (wire) is used. Is used. The stakes are installed immediately below the connection portion or at the end of the wood on the side opposite to the connection portion, and may be provided more if necessary.
The connecting portion of the retaining wall may be fixed using a wire, and the end opposite to the connecting portion may be fixed using a stake. When fixing using piles, it is good to bind wood. still,
The description omitted part in one embodiment of the present invention, and the requirements which only one embodiment has, are appropriately applied to other embodiments. Further, the requirements in each embodiment can be interchanged between the embodiments.

【0047】[0047]

【発明の効果】本発明によれば、樹木苗の生育に必要な
土壌を安定に保持でき、間伐材等の廃材を利用すること
もできる法面緑化用枠、及び該法面緑化用枠を用いて法
面を効率的に樹林化することのできる法面緑化工法を提
供することができる。
According to the present invention, there is provided a slope revegetation frame capable of stably retaining soil required for growing tree seedlings and capable of utilizing waste materials such as thinned wood, and a slope revegetation frame. It is possible to provide a slope revegetation method that can be used to efficiently turn a slope into a forest.

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1は第1実施形態の法面緑化用枠を示す斜視
図である。
FIG. 1 is a perspective view illustrating a slope greening frame according to a first embodiment.

【図2】図2は図1の法面緑化用枠内に客土を充填し苗
木を植樹した状態を模式的に示す一部断面斜視図であ
る。
FIG. 2 is a partial cross-sectional perspective view schematically showing a state in which a soil is filled into a slope greening frame of FIG. 1 and seedlings are planted.

【図3】図3は植樹してから1〜2年後の状態を模式的
に示す断面図である。
FIG. 3 is a cross-sectional view schematically showing a state one to two years after tree planting.

【図4】図4は第2実施形態の法面緑化用枠を示す斜視
図である。
FIG. 4 is a perspective view illustrating a slope greening frame according to a second embodiment.

【符号の説明】[Explanation of symbols]

1,1 法面緑化用枠 2 木材 3,3a,3b 土止め壁部 4 連結部 5 法面 6 隙間 8 杭(アンカー) 10 客土(土壌) 11,12 樹木の苗木(ポット苗) 13 挿し木用の枝 15 植生基盤材 DESCRIPTION OF SYMBOLS 1, 1 Slope greening frame 2 Wood 3, 3a, 3b Retaining wall part 4 Connection part 5 Slope 6 Clearance 8 Pile (anchor) 10 Guest soil (soil) 11, 12 Tree seedling (pot seedling) 13 Cutting For branch 15 vegetation base material

Claims (9)

【特許請求の範囲】[Claims] 【請求項1】 それぞれ複数本の木材からなる一対の土
止め壁部を、それぞれの一端部において互いに連結させ
てなる法面緑化用枠であって、 上記両土止め壁部は、該両土止め壁部の連結部において
一方の該土止め壁部の各木材と他方の該土止め壁部の各
木材とが交互に積み重ねられて形成されており、且つ互
いに所定の角度をなすように法面に設置されていること
を特徴とする法面緑化用枠。
1. A slope greening frame in which a pair of retaining walls made of a plurality of pieces of wood are connected to each other at one end, respectively. At the connecting portion of the retaining wall portion, each of the lumber of one of the retaining wall portions and each of the lumber of the other retaining wall portion are alternately stacked and formed so as to form a predetermined angle with each other. A slope greening frame, which is installed on a surface.
【請求項2】 一対の上記土止め壁部が平面視V字形状
に連結されており、両土止め壁部の連結部が谷側に向け
られている請求項1記載の法面緑化用枠。
2. The slope greening frame according to claim 1, wherein the pair of the retaining walls are connected in a V-shape in plan view, and a connecting portion of the two retaining walls is directed to the valley side. .
【請求項3】 上記土止め壁部における上記連結部とは
反対側の端部において、該土止め壁部を構成する各木材
の端部が互いに結束されている請求項1又は2記載の法
面緑化用枠。
3. The method according to claim 1, wherein ends of each of the woods constituting the retaining wall are bound to each other at an end of the retaining wall opposite to the connecting portion. Greening frame.
【請求項4】 上記土止め壁部における上記連結部とは
反対側の端部において、該土止め壁部を構成する上記各
木材の端部がそれぞれ法面に接触させてある請求項1〜
3の何れかに記載の法面緑化用枠。
4. An end portion of each of the woods constituting the retaining wall portion is in contact with a slope at an end of the retaining wall portion opposite to the connecting portion.
3. The slope greening frame according to any one of 3.
【請求項5】 上記両土止め壁部の山側の壁面に、透水
性シートが配設されており、各土止め壁部における各木
材間の隙間が該透水性シートにより閉塞されている請求
項1〜4の何れかに記載の法面緑化用枠。
5. A water-permeable sheet is provided on a wall surface on the mountain side of the both retaining wall portions, and a gap between each wood in each retaining wall portion is closed by the water-permeable sheet. The slope greening frame according to any one of claims 1 to 4.
【請求項6】 上記土止め壁部を、法面に立設した杭に
より該法面に固定してある請求項1〜5の何れかに記載
の法面緑化用枠。
6. The slope revegetation frame according to claim 1, wherein the retaining wall portion is fixed to the slope by a pile standing on the slope.
【請求項7】 請求項1〜6の何れかに記載の法面緑化
用枠内に客土を充填し、該法面緑化用枠内に樹木を植樹
することを特徴とする法面緑化工法。
7. A slope revegetation method, characterized by filling a soil into the slope revegetation frame according to any one of claims 1 to 6, and planting trees in the slope revegetation frame. .
【請求項8】 上記客土に、上記土止め壁部を構成する
各木材間の隙間から苗木を植樹する請求項7記載の法面
緑化工法。
8. The slope revegetation method according to claim 7, wherein seedlings are planted on the soil from gaps between the respective woods constituting the retaining wall.
【請求項9】 法面に、植樹用の開口部を形成した土止
め用壁体を設置し、該土止め用壁体の山側に土壌を盛る
と共に該開口部を介して該土壌中に樹木を植え付けるこ
とを特徴とする法面緑化工法。
9. A soil retaining wall having an opening for tree planting is installed on the slope, and soil is piled on the mountain side of the soil retaining wall, and a tree is introduced into the soil through the opening. A slope revegetation method characterized by planting.
JP11000724A 1999-01-05 1999-01-05 Frame for slope greening and slope-greening construction method Pending JP2000199229A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11000724A JP2000199229A (en) 1999-01-05 1999-01-05 Frame for slope greening and slope-greening construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11000724A JP2000199229A (en) 1999-01-05 1999-01-05 Frame for slope greening and slope-greening construction method

Publications (1)

Publication Number Publication Date
JP2000199229A true JP2000199229A (en) 2000-07-18

Family

ID=11481702

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11000724A Pending JP2000199229A (en) 1999-01-05 1999-01-05 Frame for slope greening and slope-greening construction method

Country Status (1)

Country Link
JP (1) JP2000199229A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113417298A (en) * 2021-05-22 2021-09-21 山东高速工程建设集团有限公司 Construction method for greening road excavation slope by stacking plant growth bags
CN114134909A (en) * 2021-12-14 2022-03-04 重庆地质矿产研究院 Ecological field ridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113417298A (en) * 2021-05-22 2021-09-21 山东高速工程建设集团有限公司 Construction method for greening road excavation slope by stacking plant growth bags
CN114134909A (en) * 2021-12-14 2022-03-04 重庆地质矿产研究院 Ecological field ridge

Similar Documents

Publication Publication Date Title
US9686921B2 (en) Method of growing grapevines
US20230354757A1 (en) Protective tree tube, method, and revetment using tree contained in same
CN113100010A (en) Mountain tree protection transplanting construction method
CN107232003B (en) Construction method for planting water-resistant arbor in water
KR100830150B1 (en) Inclined plane greening method and tree planting device for the method
US20110030273A1 (en) Method for making a plant wall
JP2000199229A (en) Frame for slope greening and slope-greening construction method
JPS61137922A (en) Sheathing work for slope
EP1185159B1 (en) Plant support and method for manufacturing such plant support
KR20040027146A (en) Recycling eco-revegetation measures
JP3825758B2 (en) Slope revegetation method and greening protection fence and slope revegetation structure
JP2003116357A (en) Stake for fixing plate material for planting
JP3205720B2 (en) Installation structure of slope greening frame and slope greening method
JP3262719B2 (en) Revegetation method of hard slope and fences used for it
Schiechtl FAO watershed management field manual: vegetative and soil treatment measures
KR100425923B1 (en) Method for greening wild ground
Andreu et al. Ecotechnological solutions for unstable slopes: Ground bio-and eco-engineering techniques and strategies
JP2717368B2 (en) Slope planting method
JPH08260468A (en) Protection method for side slope on bedrock with deep-rooting plant
JP3040956B2 (en) Tree-vegetated slope
KR100279285B1 (en) Greening method of slope
JP2002266350A (en) Organic waste processing method, slope greening method, and net structure for wicket
JP2002161537A (en) Greening method for hard sloped face
JPH08326060A (en) Slope protective structure
JP2896654B2 (en) Greening method of slope