JP2000104272A - Cut formation method for open-cut hole opened in road pavement layer - Google Patents

Cut formation method for open-cut hole opened in road pavement layer

Info

Publication number
JP2000104272A
JP2000104272A JP10273025A JP27302598A JP2000104272A JP 2000104272 A JP2000104272 A JP 2000104272A JP 10273025 A JP10273025 A JP 10273025A JP 27302598 A JP27302598 A JP 27302598A JP 2000104272 A JP2000104272 A JP 2000104272A
Authority
JP
Japan
Prior art keywords
hole
cut
pavement layer
road pavement
circular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10273025A
Other languages
Japanese (ja)
Inventor
Sanemitsu Nakano
実光 中野
Takanobu Mori
隆伸 森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hakko Co Ltd
Original Assignee
Hakko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hakko Co Ltd filed Critical Hakko Co Ltd
Priority to JP10273025A priority Critical patent/JP2000104272A/en
Publication of JP2000104272A publication Critical patent/JP2000104272A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a cut formation method for an open-cut hole causing no outbreak in a part crossing cut lines and simply restoring the pavement, even if a road pavement layer is linearly cut using a conventional, well-known disc cutter used for a long time without using any special equipment. SOLUTION: In a first construction term, a plurality of necessary diameter circular holes 2 are formed at such arrangement intervals as surrounding an opening area of an open-cut hole 1 in circumferential asphalt surrounding the opening area of the planned open-cut hole 1. In the second construction term, the asphalt in an interval formed between opposed, mutually adjoining circular holes is cut in a straight line shape so that the asphalt in a contour formed by connecting a plurality of circular holes 2 can be removed, and its removal can form the open-cut hole 2 of the prescribed dimension in the road.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、道路舗装面に、例えば
マンホール設置用の開削穴を開口する際や、道路下を掘
削工事するときに道路舗装層に作業用の開削穴を開口す
る際に適応される開削穴の切断形成工法に関する。
BACKGROUND OF THE INVENTION The present invention relates to a method for opening a drilled hole on a pavement surface of a road, for example, for installing a manhole, or a method for drilling a drilled hole under a road in a pavement layer. The present invention relates to a method for forming and cutting a drilled hole, which is adapted to the following.

【0002】[0002]

【従来の技術】上述のような開削穴を道路舗装層に形成
する場合に、従来の一般的な工法では、図7に示すよう
に、円盤形カッターを用いて道路舗装層をa点からb点
に、b点からc点に、c点からd点に、d点から最初の
a点へと四角形状に道路舗装層を直線状に切断して、図
中斜線を施した四角形の開削穴を開口形成している。
2. Description of the Related Art In the case of forming the above-mentioned cut-out hole in a road pavement layer, in a conventional general method, as shown in FIG. Point p, point b to point c, point c to point d, point d to the first point a, and cut the road pavement layer into a square shape in a straight line. The opening is formed.

【0003】この場合に、道路舗装層は所要の舗装厚を
有していることから、コーナ部となるa点,b点,c
点,d点では円盤形カッターを交叉して道路舗装層に切
り込む必要があり、これによりコーナ部のa点,b点,
c点,d点には、余切りと呼ばれる余分の舗装切り込み
が発生する。
In this case, since the road pavement layer has a required pavement thickness, points a, b, and c serving as corners are formed.
At points d and d, it is necessary to cross the disk-shaped cutter and cut into the road pavement layer.
At the points c and d, an extra pavement cut called an extra cut occurs.

【0004】[0004]

【発明が解決しようとする課題】ところで、上述のよう
な余切りが発生すると、例えば道路舗装層に開口した開
削穴にマンホール等を設置してから後、その周辺の舗装
を後日復旧処理する際に、余切りの部分が既舗装部分に
対して強度的悪影響とならないように、余切りの部分を
含む拡大した範囲(図7に一点鎖線で示す範囲)の舗装
を切り崩し、破砕した舗装材を除去してから路床を転圧
し再舗装する等の復旧作業を行なう場合に、上述の拡大
範囲の全体を広範囲に復旧処理することが道路管理上、
定められており、このために復旧の資材を多く要し、ま
た復旧の施工時間も長く要してコスト高となる等の不都
合があった。
However, when the above-mentioned surplus occurs, for example, a manhole or the like is installed in an excavated hole opened in a road pavement layer, and then the surrounding pavement is restored at a later date. In order to prevent the remaining portion from having a bad influence on the already-paved portion, the pavement in the enlarged area including the remaining portion (indicated by a dashed line in FIG. 7) is cut and the crushed pavement material is removed. When performing restoration work such as rolling down the roadbed and repaving after removing it, it is necessary to perform restoration processing of the whole of the above-mentioned expanded area extensively in terms of road management,
Therefore, there are inconveniences such as requiring a lot of materials for restoration, and a long construction time for restoration, which increases costs.

【0005】また従来、上述の余切りが発生しない施工
例として特公昭61−25844号公報に記載のように
道路舗装面を、円形状に切断する工法が提案されている
が、この従来例の場合、舗装路面を円形状に切断するた
めの特別なカッターや、特殊な円形切断機構を有する設
備機材が必要となり、その実施には設備費が嵩む上に施
工にも特殊技術が必要となる等の問題点があった。
Conventionally, as a construction example in which the above-mentioned surplus cutting does not occur, a method of cutting a road pavement surface into a circular shape has been proposed as disclosed in Japanese Patent Publication No. 61-25844. In such a case, a special cutter for cutting the pavement road surface into a circular shape and equipment and equipment having a special circular cutting mechanism are required, and the implementation requires high equipment costs and requires special techniques for construction, etc. There was a problem.

【0006】本発明の目的は、これらの問題点を解決す
るために案出されたもので、特殊な設備機材を必要とし
ないで従来より周知の使い馴れた円盤形カッターを用い
て道路舗装層を直線状に切断しても、切断線が交又する
部分に余切りが発生せず、舗装の復旧処理が簡易に行え
る開削穴の切断形成工法を提供するものである。
SUMMARY OF THE INVENTION An object of the present invention is to solve these problems, and a road pavement layer can be formed by using a conventionally-known and familiar disk-shaped cutter without requiring special equipment. The present invention provides a method for forming a cut hole in an excavated hole, in which a pavement can be easily restored even if the cutting line is cut in a straight line without generating any extra cut at the intersection of the cutting lines.

【0007】[0007]

【課題を解決するための手段】この目的を達成するた
め、請求項1記載の発明は、道路舗装層に所要寸法の開
削穴を開口する工法であって、第1工程では、予定する
開削穴の開口領域を取り囲む周辺の道路舗装層に対し
て、上記開削穴の開口領域を取囲む配列間隔でもって複
数個の所要径の円形穴を形成し、第2工程では、上記複
数個の円形穴に対し、相互に隣接する円形穴の対向間の
道路舗装層を直線状に切断することで複数個の円形穴を
結ぶ輪郭内の道路舗装層が除去可能となり、これを除去
することで道路舗装層に所要寸法の開削穴を開口形成す
ることを特徴とする。
In order to achieve this object, an invention according to claim 1 is a method for forming a cut hole having a required size in a road pavement layer. A plurality of circular holes having a required diameter are formed in the peripheral road pavement layer surrounding the opening region at an arrangement interval surrounding the opening region of the cut hole, and in the second step, the plurality of circular holes are formed. On the other hand, a road pavement layer in a contour connecting a plurality of circular holes can be removed by cutting a road pavement layer between opposing circular holes in a straight line. It is characterized in that a cutout hole of a required size is formed in the layer.

【0008】請求項2記載の発明は、上記第1工程にお
いて、開口予定する開削穴が四角形状の場合には、開削
穴の開口領域を取り囲む周辺の道路舗装層に形成する円
形穴を、四角形の開削穴の対角線上4カ所に形成するこ
とを特徴とする。
[0008] In the first aspect of the present invention, in the first step, when the cut hole to be opened is square, the circular hole formed in the road pavement layer surrounding the opening area of the cut hole is square. Are formed at four locations on the diagonal of the cut hole.

【0009】請求項3記載の発明は、上記第1工程にお
いて、開削穴の開口領域を取り囲む周辺の道路舗装層に
形成する円形穴は、道路舗装層の厚みに対応する寸法
を、円形穴の内径寸法に設定していることを特徴とす
る。
According to a third aspect of the present invention, in the first step, the circular hole formed in the peripheral road pavement layer surrounding the opening area of the cutout hole has a dimension corresponding to the thickness of the road pavement layer, and It is characterized in that the inner diameter is set.

【0010】請求項4記載の発明は、上記第2工程にお
いて、隣接する円形穴の対向間の道路舗装層を直線状に
切断する切断線は、相対向する円形穴の外側接線方向を
相互に結ぶように切断することを特徴とする。
According to a fourth aspect of the present invention, in the second step, the cutting line for linearly cutting the road pavement layer between opposing circular holes is formed by connecting the outer tangential directions of the opposing circular holes to each other. It is characterized by cutting to tie.

【0011】請求項5記載の発明は、道路舗装層に所要
寸法の開削穴を開口する工法であって、第1工程では、
予定する開削穴の開口領域周辺の道路舗装層を取囲み且
つ交差しないように直線状に切断し、第2工程では、互
いに隣接する上記直線切断線に接するように所要径の円
形穴を形成することを特徴とする。
According to a fifth aspect of the present invention, there is provided a method of forming a cut hole having a required size in a road pavement layer.
The road pavement layer around the opening area of the planned drilling hole is cut linearly so as to surround and not intersect, and in the second step, a circular hole having a required diameter is formed so as to be in contact with the above-mentioned linear cutting line adjacent to each other. It is characterized by the following.

【0012】[0012]

【作用】上記の本発明による工法の作用は、以下のとお
りである。まず請求項1の発明では、第1工程で形成す
る複数個の円形穴を、円形カッターを用いて、開削穴の
予定開口領域を取り囲む周辺部の道路舗装層に対して複
数個開口する。また第2工程では、従来より周知の円盤
形カッターを用いて、隣接する円形穴相互の対向間の道
路舗装層を直線状に切断する。
The operation of the method according to the present invention is as follows. According to the first aspect of the present invention, a plurality of circular holes formed in the first step are opened in a peripheral road pavement layer surrounding a predetermined opening region of a cut hole using a circular cutter. In the second step, the road pavement layer between the adjacent circular holes is cut straight using a conventionally known disk-shaped cutter.

【0013】この際、上述の道路舗装層の直線切断は、
開削穴の予定開口領域を取り囲むようにその周辺部に開
口された複数個の円形穴に対し、隣接する一方の円形穴
と他方の円形穴とを結ぶように切断するので、切断線の
交又部には所要径の円形穴が存在することで、交又部に
余切りが発生しなくなる。
At this time, the straight cutting of the road pavement layer described above
Since a plurality of circular holes opened in the periphery to surround the planned opening area of the drilled hole are cut so as to connect one adjacent circular hole and the other circular hole, the intersection of the cutting lines is performed. Since there is a circular hole of a required diameter in the portion, no crossover occurs in the crossover portion.

【0014】また、第1工程では、従来周知の使い馴れ
た円形カッターを用いて道路舗装層に円形穴を形成でき
るから、その作業は簡易に行え、また第2工程において
も従来より周知の使い馴れた円盤形カッターを用いて、
隣接する円形穴相互の対向間の道路舗装層を直線状に切
断するから、その作業も簡易に行える。
Further, in the first step, a circular hole can be formed in the road pavement layer by using a conventionally-known and familiar circular cutter, so that the operation can be performed easily. Using a familiar disk-shaped cutter,
Since the road pavement layer between the adjacent circular holes is cut in a straight line, the operation can be easily performed.

【0015】請求項2の発明としては、開口を予定して
いる開削穴が四角形の場合、四角形の開削穴の対角線上
4カ所に円形穴を形成するもので、円形穴を、このよう
に形成する場合には、4カ所の円形穴の相互間を互いに
接続するように直線切断することで四角形の開削穴を極
めて簡易に形成できる。
According to a second aspect of the present invention, when the hole to be opened is a quadrangle, circular holes are formed at four diagonal lines of the rectangular hole, and the circular hole is formed as described above. In such a case, a square cut hole can be formed extremely easily by straight-line cutting such that the four circular holes are connected to each other.

【0016】請求項3の発明としては、円形穴は、道路
舗装層の舗装厚みに対応する寸法と略同一の内径寸法に
設定していることから、円形穴は比較的小径となる。そ
のため、円形穴形成に円形カッターを用いた場合、該円
形カッターは小型なもので良いため、工事機材の小型化
ができ、該工事機材の搬送が楽になる。
According to the third aspect of the present invention, since the circular hole is set to have substantially the same inner diameter as the dimension corresponding to the pavement thickness of the road pavement layer, the circular hole has a relatively small diameter. Therefore, when a circular cutter is used for forming a circular hole, the circular cutter may be small, so that the size of the construction equipment can be reduced, and the transportation of the construction equipment becomes easy.

【0017】請求項4の発明としては、第2工程におい
て隣接する円形穴の対向間の道路舗装層を直線状に切断
する際に、その切断線が、相対向する円形穴の外側接線
方向と連なるように切断されるから、道路舗装層に切断
形成される開削穴はその周壁の切断舗装層に段差が発生
しなくなり、きれいな開削穴が形成できる。
According to a fourth aspect of the present invention, when the road pavement layer between the opposing circular holes is cut in a straight line in the second step, the cutting line is aligned with the outer tangential direction of the opposing circular holes. Since the cut is formed so as to be continuous, the cut hole formed in the road pavement layer has no step in the cut pavement layer on the peripheral wall, and a clean cut hole can be formed.

【0018】請求項5の発明としては、第1工程にて、
開削穴の予定開口領域を取り囲む周辺部の道路舗装層を
交差しないように直線状に切断する。すなわち、開削穴
の予定開口領域を角がない四角形状に切断する。次に、
第2工程にて、互いに隣接する上記直線切断線に接する
ように所要径の円形穴を形成する。このようにすること
で、直線切断線の交又部には所要径の円形穴が存在する
ことで、交又部に余切りが発生しなくなる。
According to a fifth aspect of the present invention, in the first step,
The road pavement layer in the periphery surrounding the planned opening area of the cut hole is cut straight so as not to cross. That is, the planned opening area of the cut hole is cut into a square shape having no corners. next,
In the second step, circular holes having a required diameter are formed so as to be in contact with the above-mentioned straight cutting lines adjacent to each other. In this way, since a circular hole having a required diameter is present at the intersection of the straight cutting lines, the intersection is not cut off.

【0019】[0019]

【実施例】図1に示すものは路面上に開口予定されてい
る開削穴1の平面図である。本実施例では、開削穴1の
形状を四角形状として説明するが、本発明の工法では円
形のマンホール蓋にも対応できる。
FIG. 1 is a plan view of a drilled hole 1 to be opened on a road surface. In the present embodiment, the shape of the cutout hole 1 is described as a square shape, but the method of the present invention can cope with a circular manhole cover.

【0020】まず、第1実施例として、図2に示すよう
に、第1工程として開削穴1の対角線上4カ所、すなわ
ち、開削穴1の四隅に円形穴2を形成する。前記円形穴
2の大きさとしては、アスファルトの厚みと同程度の直
径、例えばアスファルトの厚み20cmの場合,直径2
0cmの円形穴を形成するが、その他直径15〜30c
m程度の大きさの円形穴2でもよい。
First, as a first embodiment, as shown in FIG. 2, circular holes 2 are formed at four diagonal lines of the drilled hole 1, that is, at four corners of the drilled hole 1 as a first step. The diameter of the circular hole 2 is approximately the same as the thickness of the asphalt, for example, when the thickness of the asphalt is 20 cm, the diameter 2
0cm circular hole is formed but other diameter 15 ~ 30c
A circular hole 2 having a size of about m may be used.

【0021】前記円形穴2は円形カッター3を用いて形
成する。該円形カッター3は、図3に示すように、台座
31にラック等の送りが形成されている支柱32が立設
しており、モータ33を備えた稼働部材34が支柱32
を上下に移動する。そして該稼働部材34に円筒状のカ
ッタ35が着脱自在に装着されている。前記カッタ35
の下端には、凹凸状のカッタ刃35aが形成されてお
り、カッタ35を回転させながらアスファルトに圧接す
ることでアスファルトを円形状に切断するように構成さ
れている。
The circular hole 2 is formed by using a circular cutter 3. As shown in FIG. 3, the circular cutter 3 has a pedestal 31 on which a support 32 on which a feed of a rack or the like is formed stands upright.
To move up and down. A cylindrical cutter 35 is detachably mounted on the operating member 34. The cutter 35
An uneven cutter blade 35a is formed at the lower end of the asphalt, and is configured to cut the asphalt into a circular shape by pressing the asphalt while rotating the cutter 35.

【0022】次に第2工程として、隣接する円形穴2の
対向間を直線状に結ぶように上記開削穴1の周辺を取囲
むアスファルトを直線状に切断する。切断手段として
は、従来周知の使い馴れた円盤カッターを使用し、図4
に示すように、上記互いの円形穴2の外側接線方向間の
アスファルトを切断する。このようにすることで、直線
切断線の交又部には円形穴2が存在することで、交又部
に余切りが発生しなくなる。また、直線切断線が、相対
向する円形穴2の外側接線方向と連なるように切断され
るから、アスファルトに切断形成される開削穴1はその
周壁の切断舗装層に段差が発生しなくなり、きれいな開
削穴1が形成でき、切断形状が略長方形となり切断形状
に美観が伴うようになる。
Next, as a second step, the asphalt surrounding the perforated hole 1 is cut linearly so as to linearly connect the opposing circular holes 2 to each other. As a cutting means, a well-known and conventionally used disk cutter is used.
As shown in the figure, the asphalt between the outer tangential directions of the circular holes 2 is cut. In this way, since the circular hole 2 is present at the intersection of the straight cutting lines, no crossover occurs at the intersection. In addition, since the straight cut line is cut so as to be continuous with the outer tangential direction of the opposed circular hole 2, the cut hole 1 cut and formed in the asphalt does not have a step on the cut pavement layer on its peripheral wall, and is clean. The cut hole 1 can be formed, the cut shape becomes substantially rectangular, and the cut shape has an aesthetic appearance.

【0023】そして上記第2工程終了後に、切断した領
域内のアスファルトを排除し、地中の土砂等を排出し開
削穴を深く掘り下げ、マンホールブロックを順次積み重
ね、マンホールを築造する。
After the completion of the second step, the asphalt in the cut area is removed, earth and sand and the like are discharged from the ground, the drilled holes are dug deep, and manhole blocks are sequentially stacked to construct manholes.

【0024】また、第2実施例として、第1工程で、図
5に示すように、開削穴1周辺のアスファルトを該開削
穴1を取囲み且つ交差しないように直線状に切断する。
すなわち、開削穴1の周辺を角がない四角形状に切断す
る。次に、第2工程にて、図6に示すように、互いに隣
接する上記直線切断線に接するように所要径の円形穴2
を形成する。このようにすることで、上記第1実施例同
様、直線切断線の交又部には円形穴2が存在すること
で、交又部に余切りが発生しなくなる。また、直線切断
線が、相対向する円形穴2の外側接線方向と連なるよう
に切断されるから、アスファルトに切断形成される開削
穴1はその周壁の切断舗装層に段差が発生しなくなり、
きれいな開削穴1が形成でき、切断形状が略長方形とな
り切断形状に美観が伴うようになる。
As a second embodiment, as shown in FIG. 5, in the first step, asphalt around the cut hole 1 is cut straight so as to surround the cut hole 1 and not to intersect.
That is, the periphery of the cut hole 1 is cut into a square shape having no corners. Next, in a second step, as shown in FIG. 6, a circular hole 2 having a required diameter so as to be in contact with the above-mentioned linear cutting line adjacent to each other.
To form In this manner, as in the first embodiment, since the circular hole 2 is present at the intersection of the straight cutting lines, the intersection is not cut off. Further, since the straight cutting line is cut so as to be continuous with the outer tangential direction of the opposed circular hole 2, the cut hole 1 cut and formed in the asphalt does not generate a step in the cut pavement layer on its peripheral wall.
A beautiful cut hole 1 can be formed, the cut shape becomes substantially rectangular, and the cut shape has an aesthetic appearance.

【0025】[0025]

【発明の効果】以上請求項1,5の発明によれば、道路
舗装層の直線切断は、開削穴の予定開口領域を取り囲む
ようにその周辺部に開口された複数個の円形穴に対し、
隣接する一方の円形穴と他方の円形穴とを結ぶように切
断するので、切断線の交又部には所要径の円形穴が存在
することで、交又部に余切りが発生しなくなる。
According to the first and fifth aspects of the present invention, the straight cutting of the road pavement layer is performed with respect to a plurality of circular holes opened in the periphery so as to surround the planned opening area of the cut hole.
Since the cutting is performed so as to connect one of the adjacent circular holes and the other circular hole, the crossing portion of the cutting line has a circular hole of a required diameter, so that the crossing portion does not have any remaining portion.

【0026】請求項2の発明としては、開口を予定して
いる開削穴が四角形の場合、四角形の開削穴の対角線上
4カ所に円形穴を形成するもので、円形穴を、このよう
に形成する場合には、4カ所の円形穴の相互間を互いに
接続するように直線切断することで四角形の開削穴を極
めて簡易に形成できる。
According to a second aspect of the present invention, when the hole to be opened is a quadrangle, circular holes are formed at four diagonal lines of the rectangular hole, and the circular hole is formed as described above. In such a case, a square cut hole can be formed extremely easily by straight-line cutting such that the four circular holes are connected to each other.

【0027】請求項3の発明によれば、円形穴は、道路
舗装層の舗装厚みに対応する寸法と略同一の内径寸法に
設定していることから、円形穴は比較的小径となる。そ
のため、円形穴形成に円形カッタを用いた場合、該円形
カッタは小型なもので良いため、工事機材の小型化がで
き、該工事機材の搬送が楽になる。
According to the third aspect of the present invention, since the diameter of the circular hole is set to be substantially the same as the inner diameter of the road pavement layer, the diameter of the circular hole is relatively small. Therefore, when a circular cutter is used to form a circular hole, the circular cutter may be small, so that the construction equipment can be miniaturized and the transportation of the construction equipment becomes easy.

【0028】請求項4の発明としては、第2工程におい
て隣接する円形穴の対向間の道路舗装層を直線状に切断
する際に、その切断線が、相対向する円形穴の外側接線
方向と連なるように切断されるから、道路舗装層に切断
形成される開削穴はその周壁の切断舗装層に段差が発生
しなくなり、きれいな開削穴が形成できる。
According to a fourth aspect of the present invention, when the road pavement layer between the opposing circular holes is cut in a straight line in the second step, the cut line is in the outer tangential direction of the opposing circular holes. Since the cut is formed so as to be continuous, the cut hole formed in the road pavement layer has no step in the cut pavement layer on the peripheral wall, and a clean cut hole can be formed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】マンホール蓋の設置図Fig. 1 Installation diagram of manhole cover

【図2】第1実施例における第1工程の説明図FIG. 2 is an explanatory view of a first step in the first embodiment.

【図3】第1実施例における円形カッターの説明図FIG. 3 is an explanatory view of a circular cutter in the first embodiment.

【図4】第1実施例における第2工程の説明図。FIG. 4 is an explanatory view of a second step in the first embodiment.

【図5】第2実施例における第1工程の説明図。FIG. 5 is an explanatory view of a first step in the second embodiment.

【図6】第2実施例における第2工程の説明図。FIG. 6 is an explanatory view of a second step in the second embodiment.

【図7】従来例の説明図。FIG. 7 is an explanatory diagram of a conventional example.

【符号の説明】[Explanation of symbols]

1 マンホール蓋 2 円形穴 3 円形カッター 1 Manhole cover 2 Circular hole 3 Circular cutter

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 道路舗装層に所要寸法の開削穴を開口す
る工法であって、 第1工程では、予定する開削穴の開口領域を取り囲む周
辺の道路舗装層に対して、上記開削穴の開口領域を取囲
む配列間隔でもって複数個の所要径の円形穴を形成し、 第2工程では、上記複数個の円形穴に対し、相互に隣接
する円形穴の対向間の道路舗装層を直線状に切断するこ
とで複数個の円形穴を結ぶ輪郭内の道路舗装層が除去可
能となり、これを除去することで道路舗装層に所要寸法
の開削穴を開口形成することを特徴とする開削穴の切断
形成工法。
1. A method for opening a drilled hole of a required size in a road pavement layer, wherein in a first step, an opening of the drilled hole is formed in a surrounding road pavement layer surrounding an opening area of the planned drilled hole. A plurality of circular holes having a required diameter are formed at an arrangement interval surrounding the area. In the second step, a road pavement layer between the circular holes adjacent to each other is linearly formed with respect to the circular holes. It is possible to remove a road pavement layer in a contour connecting a plurality of circular holes by cutting into a hole, and by forming an opening in the road pavement layer by removing the road pavement layer, Cutting formation method.
【請求項2】 上記第1工程において、開口予定する開
削穴が四角形状の場合には、開削穴の開口領域を取り囲
む周辺の道路舗装層に形成する円形穴を、四角形の開削
穴の対角線上4カ所に形成することを特徴とする請求項
1記載の開削穴の切断形成工法。
2. The method according to claim 1, wherein, in the first step, when the drilling hole to be opened is square, a circular hole formed in a road pavement layer surrounding the opening area of the drilling hole is formed on a diagonal line of the square drilling hole. 2. The method for forming a cut hole according to claim 1, wherein the hole is formed at four locations.
【請求項3】 上記第1工程において、開削穴の開口領
域を取り囲む周辺の道路舗装層に形成する円形穴は、道
路舗装層の厚みに対応する寸法を、円形穴の内径寸法に
設定していることを特徴とする請求項1,2記載の開削
穴の切断形成工法。
3. In the first step, the circular hole formed in the surrounding road pavement layer surrounding the opening area of the cutout hole is formed by setting a dimension corresponding to the thickness of the road pavement layer to an inner diameter of the circular hole. The method for forming a cut hole according to claim 1 or 2, wherein the hole is cut.
【請求項4】 上記第2工程において、隣接する円形穴
の対向間の道路舗装層を直線状に切断する切断線は、相
対向する円形穴の外側接線方向を相互に結ぶように切断
することを特徴とする請求項1乃至3記載の開削穴の切
断形成工法。
4. In the second step, the cutting line for linearly cutting the road pavement layer between opposing circular holes is cut so as to connect the outer tangential directions of the opposing circular holes to each other. The method for forming a cut hole according to any one of claims 1 to 3, wherein:
【請求項5】 道路舗装層に所要寸法の開削穴を開口す
る工法であって、 第1工程では、予定する開削穴の開口領域周辺の道路舗
装層を取囲み且つ交差しないように直線状に切断し、 第2工程では、互いに隣接する上記直線切断線に接する
ように所要径の円形穴を形成することを特徴とする開削
穴の切断形成工法。
5. A method for opening a drilled hole having a required size in a road pavement layer, wherein in a first step, the road pavement layer is formed in a straight line so as to surround a road pavement layer around an opening area of a planned drilling hole and not to intersect. In a second step, a circular hole having a required diameter is formed so as to be in contact with the above-mentioned linear cutting line adjacent to each other.
JP10273025A 1998-09-28 1998-09-28 Cut formation method for open-cut hole opened in road pavement layer Pending JP2000104272A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10273025A JP2000104272A (en) 1998-09-28 1998-09-28 Cut formation method for open-cut hole opened in road pavement layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10273025A JP2000104272A (en) 1998-09-28 1998-09-28 Cut formation method for open-cut hole opened in road pavement layer

Publications (1)

Publication Number Publication Date
JP2000104272A true JP2000104272A (en) 2000-04-11

Family

ID=17522125

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10273025A Pending JP2000104272A (en) 1998-09-28 1998-09-28 Cut formation method for open-cut hole opened in road pavement layer

Country Status (1)

Country Link
JP (1) JP2000104272A (en)

Similar Documents

Publication Publication Date Title
JP2000104272A (en) Cut formation method for open-cut hole opened in road pavement layer
JP2007016510A (en) Temporary cover for manhole
JP2002363980A (en) Steel pipe pile and pile construction method with drain layer using the same
JP4064544B2 (en) Road pavement layer cutting method
JP3084360B2 (en) Underground obstacle removal method and device
JPH05179607A (en) Cutting overlay construction method
JP3040025U (en) Highly adjustable manhole
JP2008150788A (en) Manhole frame periphery cutting method in cutting overlay construction method
JP4053353B2 (en) Method of compacting the heel
JP3930358B2 (en) How to build a tunnel
JP3038103B2 (en) Manhole frame removal method and replacement method
JPH0535195Y2 (en)
JPH05179606A (en) Overlay construction method
JP3017482B1 (en) Pavement road surface cutting method and cutter used in the method
JP3648670B2 (en) Seismic isolation device installation method for existing foundation deep piles
JP2005097851A (en) Manhole structure exchanging method
KR960004915B1 (en) Overlay method for height adjustable manhole
JPH08177048A (en) Removing method of pile and excavator used for removing method
JP4397797B2 (en) Construction method of underground structure
JP3308351B2 (en) Paving cutting method
JP2014074323A (en) Manhole iron cover repair ring and repair method
JP2004132125A (en) Caisson connecting method
JPH04203119A (en) Method for constructing neck part of manhole and device for cutting neck part of manhole
JP2000178984A (en) Liquefaction preventing method
JPH05179608A (en) Pavement construction method

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20050616

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050621

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20070328

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20070529

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070625

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070911

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080212