JP2000011048A - Device and method for evaluating management operation for project management - Google Patents

Device and method for evaluating management operation for project management

Info

Publication number
JP2000011048A
JP2000011048A JP17747498A JP17747498A JP2000011048A JP 2000011048 A JP2000011048 A JP 2000011048A JP 17747498 A JP17747498 A JP 17747498A JP 17747498 A JP17747498 A JP 17747498A JP 2000011048 A JP2000011048 A JP 2000011048A
Authority
JP
Japan
Prior art keywords
management
project
level
data
risk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17747498A
Other languages
Japanese (ja)
Other versions
JP3639434B2 (en
Inventor
Tadamasa Kamikubo
忠正 上久保
Kimiharu Okada
公治 岡田
Akira Tada
彰 多田
Yoshie Matsuzaki
吉衛 松崎
Toshiko Takamura
稔子 高村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP17747498A priority Critical patent/JP3639434B2/en
Publication of JP2000011048A publication Critical patent/JP2000011048A/en
Application granted granted Critical
Publication of JP3639434B2 publication Critical patent/JP3639434B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To indicate guidance for the management level of each management operation in a large scale system software development project based on a rough plan for the management of the project. SOLUTION: A project feature planning means 3 calculates a project feature by using project data consisting of project planning data 8 and project experience data 9. A project risk area calculating means 4 finds out a risk area in each evaluation item from the feature data 11 of a completed project and the project data 10. A project risk evaluation means 5 maps the feature data 11 on the risk area to evaluate the level of the risk. A management operation level determination means 6 determines the management level of each management operation from risk evaluation data 13 and important point management operation data 14 indicating relation between the level of a risk in the evaluation item and each management operation and a management operation level display means 7 provides the management level of each management operation.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、プロジェクト管理
を支援する装置及び方法、特に、プロジェクト開始時点
において、要求仕様が不明確であるため詳細計画の立案
が困難であり、概略計画によって開始される大規模シス
テムソフト開発におけるプロジェクト管理業務を評価す
る装置及び方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus and a method for supporting project management, in particular, at the beginning of a project, it is difficult to make a detailed plan because the required specifications are unclear, and the present invention is started by a rough plan. The present invention relates to an apparatus and a method for evaluating a project management task in large-scale system software development.

【0002】[0002]

【従来の技術】大規模システムを対象としたソフト開発
は、一般に、顧客からの現状の問題点と要求に基づい
て、実現する機能を設計し、その実現方法であるソフト
設計へと詳細化していく。ところが、顧客からの要求仕
様は、初めから確定していることは少なく、開発を進め
るに従って、プロトタイピング等によって明らかになり
確定していくことが多い。従って、プロジェクトの計画
段階では、開発対象や要求納期といった開発概要を基
に、大まかな計画を立案している。その結果、不確定要
素に対する見積り違いから、人の割り当てのアンバラン
ス等が発生し、やるべき作業が的確に行われず、開発遅
延等のトラブルが発生することが少なくない。そのた
め、計画立案時に計画を十分評価し、現時点で実行可能
で最適な工程計画を立案するとともに、遅延発生等のリ
スク要因をとらえ、その要因を低減するよう十分プロジ
ェクト管理をすることが必要である。特に、大規模プロ
ジェクトでは、一旦トラブルが発生すると回復は困難で
あり、かつ混乱時の損失は中小規模のプロジェクトに比
べ大きいので、適切なプロジェクト管理を行うことが非
常に重要になる。
2. Description of the Related Art In general, software development for a large-scale system is performed by designing a function to be realized based on the current problems and requirements of customers and refining the software design as a method of realizing the function. Go. However, specifications required by customers are rarely determined from the beginning, and are often clarified and determined by prototyping or the like as development proceeds. Therefore, at the planning stage of the project, a rough plan is made based on the development outline such as the development target and the required delivery date. As a result, improper estimation of uncertain factors causes imbalance in assignment of persons and the like, and the work to be performed is not accurately performed, and troubles such as development delays often occur. Therefore, it is necessary to fully evaluate the plan at the time of planning, to formulate the most feasible and feasible process plan at the present time, to grasp the risk factors such as delay occurrence, and to manage the project sufficiently to reduce the factors. . In particular, in a large-scale project, once a trouble occurs, it is difficult to recover, and the loss at the time of confusion is greater than that of a small-to-medium-sized project, so it is very important to carry out appropriate project management.

【0003】このような状況において、従来行われてい
る計画立案時における評価方法として、特開平8−18
0106号に開示されている「工程計画作成方法及びそ
の装置」がある。この従来技術においては、過去に実施
した同種の工事(プロジェクト)の実績データを利用し
た各作業工程の作業期間の算出と、各作業工程の作業期
間を加味したネットワーク工程図の作成、計画全体の予
測工期と目標工期との比較、作業工程毎の1日の作業従
事時間の変更による予測工期の再計算、作業工程毎の投
入作業員数の変更による予測工期の再計算の各機能を、
システムがサポートしている。すなわち、計画評価方法
に関してシステムがサポートしているのは、予測工期と
目標工期を比較することにより、工程計画の妥当性を評
価することである。
In such a situation, a conventional evaluation method at the time of planning is described in JP-A-8-18.
No. 0106 discloses a “process plan creation method and apparatus”. In this prior art, the work period of each work process is calculated using the actual data of the same type of construction (project) performed in the past, a network process diagram taking into account the work period of each work process is created, and the entire plan is created. The functions of comparing the predicted construction period with the target construction period, recalculating the predicted construction period by changing the daily work hours for each work process, and recalculating the predicted construction period by changing the number of input workers for each work process,
Supported by the system. That is, the system supports the plan evaluation method by evaluating the validity of the process plan by comparing the predicted work period and the target work period.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記従
来技術においては、プロジェクトの管理方法についての
情報は提示されていない。すなわち、従来は、あるプロ
ジェクトを管理するにあたって、要求管理、工程管理、
品質管理等の各管理業務をどのくらい重点的に行えばよ
いのか、その管理レベルを示す技術がなく、各管理業務
をどのくらい重点的に行うかは、プロジェクト管理者の
個人的経験や能力に基づいた各自の判断に委ねられてい
た。
However, the above-mentioned prior art does not disclose information on a project management method. That is, conventionally, when managing a project, requirements management, process management,
How much priority should be given to each management work such as quality control, there is no technology to indicate the management level, and how much focus should be placed on each management work is based on the personal experience and ability of the project manager It was left to their own judgment.

【0005】本発明の目的は、大規模システムソフト開
発等のプロジェクト管理において、概略計画から、各管
理業務の管理レベルの指針を示すことができるプロジェ
クト管理を支援する装置及び方法を提供することにあ
る。
An object of the present invention is to provide an apparatus and a method for supporting project management which can indicate a guideline of a management level of each management work from a rough plan in project management such as large-scale system software development. is there.

【0006】[0006]

【課題を解決するための手段】本発明に係る第1の管理
業務評価装置は、プロジェクト計画データとプロジェク
ト実績データとからなるプロジェクトデータに基づい
て、プロジェクト特徴を計算するプロジェクト特徴計算
手段と、完了したプロジェクトに関するプロジェクトデ
ータとプロジェクト特徴とに基づいて、評価項目のリス
ク領域を計算するプロジェクトリスク領域計算手段と、
プロジェクト特徴とリスク領域とに基づいて、プロジェ
クトのリスクを評価するプロジェクトリスク評価手段
と、プロジェクト特徴の各評価項目についてのリスクと
各管理業務との関連を示す重点管理業務データと、評価
対象プロジェクトのリスクとに基づいて、評価対象プロ
ジェクトの各管理業務の管理レベルを決定する管理業務
レベル決定手段と、評価対象プロジェクトにおける各管
理業務の管理レベルを提示する管理業務レベル表示手段
とから構成されることを特徴とする。
According to a first aspect of the present invention, there is provided a management service evaluation apparatus for calculating a project feature based on project data including project plan data and project performance data; Project risk area calculation means for calculating a risk area of an evaluation item based on project data and project characteristics related to the
A project risk assessment method that evaluates project risks based on project characteristics and risk areas, key management work data indicating the relationship between risks for each evaluation item of project characteristics and each management work, Management task level determination means for determining the management level of each management task in the evaluation target project based on risk, and management task level display means for presenting the management level of each management task in the evaluation target project It is characterized by.

【0007】また、本発明に係る第2の管理業務評価装
置は、プロジェクト計画データとプロジェクト実績デー
タとからなるプロジェクトデータに基づいて、プロジェ
クト特徴を計算するプロジェクト特徴計算手段と、完了
したプロジェクトに関するプロジェクトデータとプロジ
ェクト特徴とに基づいて、評価項目のリスク領域を計算
するプロジェクトリスク領域計算手段と、プロジェクト
特徴とリスク領域とに基づいて、プロジェクトのリスク
を評価するプロジェクトリスク評価手段と、完了したプ
ロジェクトに関するプロジェクトデータに基づいて、各
管理業務の管理業務レベル尺度を、複数の管理レベル領
域に区分する管理業務レベル分け計算手段と、プロジェ
クト特徴の各評価項目についてのリスクと各管理業務と
の関連を示す重点管理業務データと、評価対象プロジェ
クトのリスクと、前記複数の管理レベル領域とに基づい
て、評価対象プロジェクトの各管理業務の管理レベルを
決定する管理業務レベル決定手段と、評価対象プロジェ
クトにおける各管理業務の管理レベルを提示する管理業
務レベル表示手段とから構成されることを特徴とする。
Further, a second management work evaluation apparatus according to the present invention includes a project feature calculation means for calculating a project feature based on project data including project plan data and project performance data, and a project related to a completed project. A project risk area calculation means for calculating a risk area of an evaluation item based on data and project characteristics; a project risk evaluation means for evaluating a project risk based on the project characteristics and the risk area; Based on the project data, the management work level scale of each management work is divided into a plurality of management level areas. The management work level division calculation means, and the relationship between the risk for each evaluation item of the project characteristics and each management work is shown. Emphasis Management operation level determining means for determining the management level of each management operation of the evaluation target project based on the management operation data, the risk of the evaluation target project, and the plurality of management level areas, and each management operation in the evaluation target project And a management operation level display means for presenting the management level.

【0008】この場合において、前記管理業務レベル分
け計算手段は、完了したプロジェクトにおける、管理業
務レベル尺度の値とトラブルの有無との関係に基づい
て、各管理レベル尺度の値を複数の管理レベル領域に区
分するようにしてもよい。更に、前記管理業務レベル決
定手段は、評価対象プロジェクトにおける各管理業務の
重点度と前記複数の管理レベル領域とに基づいて、各管
理業務の管理レベルとして、管理業務の重点度に対応す
る管理レベル尺度の領域を決定するようにしてもよい。
[0008] In this case, the management work level division calculating means may convert the value of each management level scale into a plurality of management level areas based on the relationship between the value of the management work level scale and the presence or absence of a trouble in the completed project. May be classified. Further, the management operation level determining means determines a management level corresponding to the importance of the management operation as a management level of each management operation based on the importance of each management operation in the evaluation target project and the plurality of management level areas. The scale area may be determined.

【0009】本発明に係る第3の管理業務評価装置は、
プロジェクト計画データとプロジェクト実績データとか
らなるプロジェクトデータに基づいて、プロジェクト特
徴を計算するプロジェクト特徴計算手段と、完了したプ
ロジェクトに関するプロジェクトデータとプロジェクト
特徴とに基づいて、評価項目のリスク領域を計算するプ
ロジェクトリスク領域計算手段と、プロジェクト特徴と
リスク領域とに基づいて、プロジェクトのリスクを評価
するプロジェクトリスク評価手段と、完了したプロジェ
クトに関するプロジェクトデータ及びリスク評価に基づ
いて、リスクレベル毎に、管理業務レベル尺度を、複数
の管理レベル領域に区分する管理業務レベル分け計算手
段と、評価対象プロジェクトのリスクとリスクレベル毎
の前記複数の管理レベル領域とに基づいて、評価対象プ
ロジェクトのリスクの大きさに対応する管理業務レベル
尺度の領域を、評価対象プロジェクトの各管理業務の管
理レベルとして決定する管理業務レベル決定手段と、評
価対象プロジェクトにおける各管理業務の管理レベルを
提示する管理業務レベル表示手段とから構成されること
を特徴とする。
A third management work evaluation device according to the present invention comprises:
A project feature calculation means for calculating project features based on project data composed of project plan data and project performance data, and a project for calculating a risk area of an evaluation item based on project data and project features relating to completed projects. Risk area calculation means, project risk evaluation means for evaluating project risks based on project characteristics and risk areas, and management operation level scale for each risk level based on project data and risk evaluation on completed projects Based on the management task level dividing calculation means for classifying the project into a plurality of management level areas, and the plurality of management level areas for each risk level and risk of the evaluation target project. Management task level determining means for determining the area of the management task level scale corresponding to the size of the management task as the management level of each management task of the evaluation target project, and the management task level for presenting the management level of each management task in the evaluation target project And display means.

【0010】この場合において、前記管理業務レベル分
け計算手段は、完了したプロジェクトにおける、評価項
目のリスクの大きさと管理業務レベル尺度の値とトラブ
ルの有無との関係に基づいて、前記評価項目のリスクの
大きさ別に、管理レベル尺度を複数の管理レベル領域に
区分するようにしてもよい。更に、前記管理レベル決定
手段は、プロジェクト特徴の各評価項目について、リス
クの大きさ別に管理レベル尺度の管理レベル領域を、そ
れぞれの管理レベル尺度について示す管理レベル分けデ
ータから、評価項目のリスクの大きさに対応する管理レ
ベル尺度の管理レベル領域を各評価項目について求め、
評価対象プロジェクトにおける各管理業務の管理レベル
を、その積集合の領域で示すようにしてもよい。
[0010] In this case, the management work level classification calculation means calculates the risk of the evaluation item based on the relationship between the magnitude of the risk of the evaluation item, the value of the management work level scale, and the presence or absence of a trouble in the completed project. The management level scale may be divided into a plurality of management level areas according to the size of the management level. Further, the management level determining means may determine, for each evaluation item of the project characteristics, a management level area of the management level scale for each of the risk sizes from the management level classification data indicating the management level scale, for each of the management item scales. For each evaluation item, the management level area of the management level scale corresponding to
The management level of each management task in the evaluation target project may be indicated by its intersection area.

【0011】また、本発明に係る管理状況監視システム
は、前記本発明に係る重点管理業務評価装置のいずれか
と、この重点管理業務評価装置によって提示される各管
理業務の管理レベルを示すデータとプロジェクト進捗デ
ータとを比較し、管理レベルの達成状況を評価する管理
レベル達成状況評価手段とから構成されることを特徴と
する。
Further, the management status monitoring system according to the present invention may include any one of the above-mentioned important management work evaluation devices, data indicating the management level of each management work presented by this important management business evaluation device, and a project. A management level achievement status evaluation means for comparing the progress data with the progress data and evaluating the achievement status of the management level.

【0012】本発明に係る第1の管理業務評価方法は、
プロジェクト計画データとプロジェクト実績データとか
らなるプロジェクトデータに基づいて、プロジェクトの
特徴データを計算し、完了したプロジェクトに関するプ
ロジェクトデータと特徴データとから、評価項目のリス
ク領域を計算し、特徴データとリスク領域とに基づい
て、評価対象プロジェクトのリスクを評価し、特徴デー
タの各評価項目についてのリスクと各管理業務との関連
を示す重点管理業務データとリスク評価とに基づいて、
評価対象プロジェクトの各管理業務の管理レベルを複数
ランクの重点度で決定し、評価対象プロジェクトにおけ
る各管理業務の管理レベルを提示することを特徴とす
る。
[0012] The first management work evaluation method according to the present invention comprises:
Based on the project data consisting of the project plan data and the project actual data, calculate the characteristic data of the project, calculate the risk area of the evaluation item from the project data and the characteristic data related to the completed project, and calculate the characteristic data and the risk area. Based on the above, the risk of the evaluation target project is evaluated, and based on the priority management work data indicating the relationship between the risk for each evaluation item of the characteristic data and each management work and the risk evaluation,
The management level of each management operation of the evaluation target project is determined by a plurality of ranks, and the management level of each management operation of the evaluation target project is presented.

【0013】また、本発明に係る第2の管理業務評価方
法は、プロジェクト計画データとプロジェクト実績デー
タとからなるプロジェクトデータに基づいて、プロジェ
クトの特徴データを計算し、完了したプロジェクトに関
するプロジェクトデータと特徴データとから、評価項目
のリスク領域を計算し、特徴データとリスク領域とに基
づいて、評価対象プロジェクトのリスクを評価し、完了
したプロジェクトにおける管理業務レベル尺度の値とト
ラブルの有無との関係に基づいて、各管理業務の管理業
務レベル尺度の値を、複数の管理レベル領域に区分し、
特徴データの各評価項目についてのリスクと各管理業務
との関連を示す重点管理業務データと、前記複数の管理
レベル領域とリスク評価とに基づいて、評価対象プロジ
ェクトの各管理業務の管理レベルを決定し、評価対象プ
ロジェクトにおける各管理業務の管理レベルを提示する
ことを特徴とする。
[0013] A second management work evaluation method according to the present invention calculates project characteristic data based on project data composed of project plan data and project actual data. The risk area of the evaluation item is calculated from the data, the risk of the evaluation target project is evaluated based on the characteristic data and the risk area, and the relationship between the value of the management operation level scale and the presence or absence of trouble in the completed project is calculated. Based on this, the value of the management task level scale for each management task is divided into multiple management level areas,
Determine the management level of each management task of the project to be evaluated based on the priority management task data indicating the relationship between the risk for each evaluation item of the characteristic data and each management task, and the plurality of management level areas and the risk assessment. The management level of each management task in the project to be evaluated is presented.

【0014】そして、評価対象プロジェクトの各管理業
務の管理レベルを決定する際、評価対象プロジェクトに
おける各管理業務の重点度を求め、当該重点度と前記複
数の管理レベル領域とに基づいて、各管理業務の管理レ
ベルとして、管理業務の重点度に対応する管理レベル尺
度の領域を決定するようにしてもよい。
When deciding the management level of each management task of the project to be evaluated, the priority of each management task in the project to be evaluated is determined, and each management task is determined based on the priority and the plurality of management level areas. As the business management level, an area of the management level scale corresponding to the priority of the management business may be determined.

【0015】本発明に係る第3の管理業務評価方法は、
プロジェクト計画データとプロジェクト実績データとか
らなるプロジェクトデータに基づいて、プロジェクトの
特徴データを計算し、完了したプロジェクトに関するプ
ロジェクトデータと特徴データとから、評価項目のリス
ク領域を計算し、特徴データとリスク領域に基づいて、
プロジェクトのリスクを評価し、完了したプロジェクト
における、リスクの大きさ及び管理業務レベル尺度の値
とトラブルの有無との関係に基づいて、リスクの大きさ
毎に、各管理業務の管理業務レベル尺度の値を、複数の
管理レベル領域に区分し、当該区分の結果と評価対象プ
ロジェクトのリスク評価とに基づいて、評価対象プロジ
ェクトの各管理業務の管理レベルとして、評価対象プロ
ジェクトのリスクの大きさに対応する管理業務レベル尺
度の領域を決定し、評価対象プロジェクトにおける各管
理業務の管理レベルを提示することを特徴とする。
[0015] A third management work evaluation method according to the present invention comprises:
Based on the project data consisting of the project plan data and the project actual data, calculate the characteristic data of the project, calculate the risk area of the evaluation item from the project data and the characteristic data related to the completed project, and calculate the characteristic data and the risk area. On the basis of the,
Assess the risk of the project and, based on the relationship between the magnitude of the risk and the value of the management work level scale in the completed project, and the presence / absence of a trouble, evaluate the management work level scale of each management work for each risk size. The values are divided into multiple management level areas, and based on the results of the classification and the risk assessment of the project to be evaluated, the management level of each management task of the project to be evaluated corresponds to the magnitude of the risk of the project to be evaluated. It is characterized in that an area of a management work level scale to be evaluated is determined, and a management level of each management work in the project to be evaluated is presented.

【0016】この場合、評価対象プロジェクトの各管理
業務の管理レベルを決定する際、特徴データの各評価項
目について、リスクの大きさ別に管理レベル尺度の管理
レベル領域を、それぞれの管理レベル尺度について示す
管理レベル分けデータから、評価項目のリスクの大きさ
に対応する管理レベル尺度の管理レベル領域を各評価項
目について求め、評価対象プロジェクトにおける各管理
業務の管理レベルを、その積集合の領域で示すようにし
てもよい。
In this case, when determining the management level of each management operation of the project to be evaluated, for each evaluation item of the characteristic data, the management level area of the management level scale is shown for each management level scale for each magnitude of risk. From the management level classification data, the management level area of the management level scale corresponding to the magnitude of the risk of the evaluation item is obtained for each evaluation item, and the management level of each management work in the evaluation target project is indicated by the intersection area. It may be.

【0017】本発明に係る第1のコンピュータ読み取り
可能な記録媒体は、プロジェクト計画データとプロジェ
クト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算するステップと、
完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域データを計算す
るステップと、特徴データとリスク領域データとに基づ
いて、プロジェクトのリスクを評価してリスク評価デー
タを算出するステップと、プロジェクト特徴の各評価項
目についてのリスクと各管理業務との関連を示す重点管
理業務データとリスク評価データとに基づいて、評価対
象プロジェクトの各管理業務の管理レベルを複数ランク
の重点度で決定するステップと、評価対象プロジェクト
における各管理業務の管理レベルを提示するステップと
からなることを特徴とするプログラムを記録しているも
のである。
A first computer-readable recording medium according to the present invention includes a step of calculating project characteristic data based on project data including project plan data and project actual data;
Calculating the risk area data of the evaluation item from the project data and the characteristic data relating to the completed project; and evaluating the project risk based on the characteristic data and the risk area data to calculate the risk evaluation data. , Based on priority management data and risk evaluation data that indicate the relationship between risks for each evaluation item of project characteristics and each management task, and determine the management level of each management task of the target project with multiple ranks of priority based on risk assessment data And a step of presenting the management level of each management task in the evaluation target project.

【0018】本発明に係る第2のコンピュータ読み取り
可能な記録媒体は、プロジェクト計画データとプロジェ
クト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算するステップと、
完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域データを計算す
るステップと、特徴データとリスク領域データとに基づ
いて、評価対象プロジェクトのリスクを評価してリスク
評価データを算出するステップと、完了したプロジェク
トにおける管理業務レベル尺度の値とトラブルの有無と
の関係に基づいて、各管理業務の管理業務レベル尺度の
値を、複数の領域に区分して管理レベル分けデータを算
出するステップと、プロジェクト特徴の各評価項目につ
いてのリスクと各管理業務との関連を示す重点管理業務
データと、管理レベル分けデータとリスク評価データと
に基づいて、評価対象プロジェクトの各管理業務の管理
レベルを決定するステップと、評価対象プロジェクトに
おける各管理業務の管理レベルを提示するステップとか
らなることを特徴とするプログラムを記録しているもの
である。
A second computer-readable recording medium according to the present invention includes a step of calculating characteristic data of a project based on project data including project plan data and project actual data;
Calculating the risk area data of the evaluation item from the project data and the characteristic data relating to the completed project; and evaluating the risk of the evaluation target project based on the characteristic data and the risk area data to calculate the risk evaluation data Based on the relationship between the step and the value of the management task level scale in the completed project and the presence or absence of trouble, the management task level scale value of each management task is divided into a plurality of areas to calculate management level classification data. The management level of each management work of the project to be evaluated based on the step, priority management work data showing the relationship between the risk for each evaluation item of project characteristics and each management work, management level classification data and risk evaluation data And the management tasks for the project to be evaluated In which it is recorded the program characterized by comprising the step of presenting the management level.

【0019】本発明に係る第3のコンピュータ読み取り
可能な記録媒体は、プロジェクト計画データとプロジェ
クト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算するステップと、
完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域を計算するステ
ップと、特徴データとリスク領域データとに基づいて、
プロジェクトのリスクを評価してリスク領域データを算
出するステップと、完了したプロジェクトにおける、リ
スクの大きさ及び管理業務レベル尺度の値とトラブルの
有無との関係に基づいて、リスクの大きさ毎に、各管理
業務の管理業務レベル尺度の値を、複数の管理レベル領
域に区分して管理レベル分けデータを算出するステップ
と、管理レベル分けデータとリスク評価データとに基づ
いて、評価対象プロジェクトの各管理業務の管理レベル
として、評価対象プロジェクトのリスクの大きさに対応
する管理業務レベル尺度の領域を決定するステップと、
評価対象プロジェクトにおける各管理業務の管理レベル
を提示するステップとからなることを特徴とするプログ
ラムを記録しているものである。
A third computer-readable recording medium according to the present invention includes a step of calculating project characteristic data based on project data including project plan data and project actual data;
Calculating the risk area of the evaluation item from the project data and the characteristic data relating to the completed project, and based on the characteristic data and the risk area data,
Estimating the risk of the project and calculating the risk area data, and, based on the relationship between the magnitude of the risk and the value of the management work level scale and the presence / absence of trouble in the completed project, for each magnitude of risk, Dividing the value of the management operation level scale of each management operation into a plurality of management level areas to calculate management level division data; and performing each management of the project to be evaluated based on the management level division data and the risk evaluation data. Determining the area of the management operation level scale corresponding to the magnitude of the risk of the evaluated project as the operation management level;
Presenting the management level of each management task in the project to be evaluated.

【0020】なお、上記において、評価対象プロジェク
トにおける各管理業務の管理レベルを提示するには、各
管理業務毎に管理レベルをディスプレイやプリンタなど
の出力装置に表示したり印刷したりすることの他に、例
えば、評価対象プロジェクトにおいて重要度が高いと判
断される管理業務(重点管理業務)を表示等することも
含まれる。
In the above, in order to present the management level of each management task in the project to be evaluated, the management level is displayed or printed on an output device such as a display or a printer for each management task. This includes, for example, displaying a management task (priority management task) determined to be highly important in the evaluation target project.

【0021】[0021]

【発明の実施の形態】以下、本発明の実施の形態につい
て、図面を参照しつつ詳細に説明する。
Embodiments of the present invention will be described below in detail with reference to the drawings.

【0022】なお、以下では、大規模システムソフト開
発プロジェクトにおけるプロジェクト管理を例にとっ
て、本発明の実施形態について説明する。
In the following, an embodiment of the present invention will be described taking project management in a large-scale system software development project as an example.

【0023】図1は、本発明による第1の管理業務評価
装置の処理ブロックを示す図である。この管理業務評価
装置は、評価対象(計画段階)のプロジェクトのリスク
を計画データから算出し、当該リスク及び過去のデータ
に基づいて、評価対象プロジェクトにおいて重要度が高
いと判断される管理業務(重点管理業務)や各管理業務
の管理レベルを、ユーザ(プロジェクトマネージャ)に
提示するものである。なお、管理業務とは、要求管理、
工程管理、品質管理等のプロジェクト管理における業務
を細分化したものである。
FIG. 1 is a diagram showing processing blocks of a first management work evaluation device according to the present invention. This management work evaluation device calculates the risk of the project to be evaluated (planning stage) from the plan data, and based on the risk and the past data, the management work (important Management tasks) and the management level of each management task are presented to the user (project manager). In addition, management duties are requirements management,
It is a subdivision of work in project management such as process management and quality management.

【0024】図1に示すように、管理業務評価装置1
は、プロジェクトデータ入力手段2と、プロジェクト特
徴計算手段3と、プロジェクトリスク領域計算手段4
と、プロジェクトリスク評価手段5と、管理業務レベル
決定手段6と、管理業務レベル表示手段7とから構成さ
れる。
As shown in FIG. 1, the management work evaluation device 1
Are project data input means 2, project feature calculation means 3, project risk area calculation means 4
, Project risk evaluation means 5, management work level determination means 6, and management work level display means 7.

【0025】プロジェクトデータ入力手段2は、キーボ
ード等の入力装置16によって入力されるプロジェクト
計画データ8及びプロジェクト実績データ9を取り込ん
で、プロジェクト計画データ8とプロジェクト実績デー
タ9の集合であるプロジェクトデータ10として格納す
る。プロジェクト計画データ8とは、評価対象となるプ
ロジェクト及び既に完了しているプロジェクトについて
の計画段階でのデータである。また、プロジェクト実績
データ9とは、既に完了している過去のプロジェクトに
ついての実績データである。
The project data input means 2 fetches the project plan data 8 and the project actual data 9 inputted by the input device 16 such as a keyboard and the like, and as the project data 10 which is a set of the project plan data 8 and the project actual data 9. Store. The project plan data 8 is data at the planning stage of a project to be evaluated and a project that has already been completed. The project performance data 9 is performance data of a past project that has already been completed.

【0026】プロジェクト特徴計算手段3は、プロジェ
クトデータ10に基づいて、プロジェクトを特徴づける
値を所定の評価項目について計算し、計算結果を特徴デ
ータ11として格納する。プロジェクトリスク領域計算
手段4は、プロジェクトデータ10内の完了したプロジ
ェクトに関するデータと特徴データ11とに基づいて、
プロジェクト特徴の評価項目毎に、リスク領域を計算
し、計算結果をリスク領域データ12として格納する。
プロジェクトリスク評価手段5は、特徴データ11とリ
スク領域データ12とに基づいて、プロジェクトのリス
クをプロジェクト特徴の評価項目別に評価し、評価結果
をリスク評価データ13として格納する。
The project feature calculating means 3 calculates a value characterizing the project for a predetermined evaluation item based on the project data 10, and stores the calculation result as feature data 11. The project risk area calculating means 4 calculates the project risk area based on the data on the completed project in the project data 10 and the characteristic data 11.
The risk area is calculated for each evaluation item of the project feature, and the calculation result is stored as risk area data 12.
The project risk evaluation means 5 evaluates the project risk for each project characteristic evaluation item based on the characteristic data 11 and the risk area data 12, and stores the evaluation result as risk evaluation data 13.

【0027】管理業務レベル決定手段6は、評価対象プ
ロジェクトにおける、各管理業務の管理レベルを決定す
る。具体的には、各管理業務と各評価項目とを関連付け
る重点管理業務データ14とリスク評価データ13とに
基づいて各管理業務の管理レベルを決定し、その結果を
管理レベルデータ15として格納する。管理業務レベル
表示手段7は、管理レベルデータ15に基づいて、評価
対象プロジェクトにおける重点管理業務や、各管理業務
の管理レベルをディスプレイ等の出力装置17に出力す
る。
The management task level determining means 6 determines the management level of each management task in the project to be evaluated. Specifically, the management level of each management task is determined based on the priority management task data 14 and the risk evaluation data 13 that associate each management task with each evaluation item, and the result is stored as management level data 15. The management task level display means 7 outputs the priority management task in the project to be evaluated and the management level of each management task to an output device 17 such as a display based on the management level data 15.

【0028】次に、上記各手段によって行われる処理の
詳細について説明する。本装置で行われる主要な処理
は、大別して、プロジェクト特徴計算処理、プロジェク
トリスク領域計算処理、プロジェクトリスク評価処理、
管理業務レベル決定処理に分かれる。各処理は、それぞ
れ、プロジェクト特徴計算手段3、プロジェクトリスク
領域計算手段4、プロジェクトリスク評価手段5、管理
業務レベル決定手段6によって実行される。なお、これ
らの各処理は、例えば、不図示の中央処理装置(CP
U)と記憶装置に格納されたプログラムによって実現さ
れる。
Next, details of the processing performed by each of the above means will be described. The main processing performed by this device can be roughly classified into project characteristic calculation processing, project risk area calculation processing, project risk evaluation processing,
It is divided into management work level determination processing. Each process is executed by the project characteristic calculation means 3, the project risk area calculation means 4, the project risk evaluation means 5, and the management work level determination means 6, respectively. These processes are performed, for example, by a central processing unit (CP) (not shown).
U) and a program stored in the storage device.

【0029】まず、プロジェクト特徴計算手段3によっ
て実行されるプロジェクト特徴計算処理について説明す
る。プロジェクト特徴計算処理では、プロジェクトの特
徴を表す一つ以上の評価項目の値をそれぞれ計算し、計
算結果を特徴データとして格納する。評価項目の例とし
ては、新規性、納期(余裕)、プログラム規模、要求確
定度等がある。評価項目と、その計算に必要な計算方法
は予め与えられている。例えば、新規性とは、プロジェ
クトの新しさを示す評価項目をいい、以下のような式に
より計算される。
First, the project feature calculation process executed by the project feature calculation means 3 will be described. In the project feature calculation process, the values of one or more evaluation items representing the features of the project are calculated, and the calculation results are stored as feature data. Examples of the evaluation items include novelty, delivery date (margin), program scale, degree of request confirmation, and the like. The evaluation items and the calculation method required for the calculation are given in advance. For example, novelty refers to an evaluation item indicating the newness of a project, and is calculated by the following formula.

【0030】[0030]

【数1】 新規性=新規作成プログラム容量×a+改造プログラム容量×b・・・(式1) (ここで、a、bは係数) あるプロジェクトについて、新規作成プログラム容量=
5、改造プログラム容量=10であり、a=1、b=0.5と
すると、新規性=10となる。
## EQU00001 ## Novelty = Capacity of a newly created program × a + capacity of a remodeling program × b (Equation 1) (where a and b are coefficients) For a certain project, the capacity of a newly created program =
5. Remodeling program capacity = 10, and if a = 1 and b = 0.5, novelty = 10.

【0031】図2は、プロジェクト特徴計算処理の流れ
を示すフローチャートである。
FIG. 2 is a flowchart showing the flow of the project feature calculation process.

【0032】同図に示すように、プロジェクト特徴計算
手段3は、まず、予め与えられたプロジェクト特徴を表
す評価項目のうち、未計算の評価項目を一つ選択する
(ST201)。
As shown in the figure, the project feature calculation means 3 first selects one uncalculated evaluation item from among evaluation items representing project characteristics given in advance (ST201).

【0033】次に、プロジェクト特徴計算手段3は、選
択した評価項目を計算するのに必要なデータを、プロジ
ェクトデータ10から取り出す(ST202)。
Next, the project characteristic calculation means 3 extracts data necessary for calculating the selected evaluation item from the project data 10 (ST202).

【0034】次に、プロジェクト特徴計算手段3は、予
め定められた計算方法(例えば、上記の式1)に従い、
選択されている評価項目の値を計算する(ST20
3)。
Next, the project feature calculation means 3 calculates the project characteristic according to a predetermined calculation method (for example, the above-described formula 1).
Calculate the value of the selected evaluation item (ST20)
3).

【0035】最後に、未だ計算していない評価項目があ
るか否かを判断し(ST204)、未計算の評価項目が
ある場合は、ST201〜ST203の処理を繰り返
す。一方、すべての評価項目の計算が済んでいる場合
は、すべての評価項目の計算結果の集合を、特徴データ
11として格納する(ST205)。
Finally, it is determined whether there is an evaluation item that has not been calculated yet (ST204). If there is an evaluation item that has not been calculated, the processing of ST201 to ST203 is repeated. On the other hand, when all the evaluation items have been calculated, a set of calculation results of all the evaluation items is stored as feature data 11 (ST205).

【0036】以上のような処理の流れによって、すべて
の評価項目について、特徴データ11の計算が行われ
る。
According to the above processing flow, the calculation of the characteristic data 11 is performed for all the evaluation items.

【0037】次に、プロジェクトリスク領域計算手段4
によって実行されるプロジェクトリスク領域計算処理に
ついて説明する。プロジェクトリスク領域計算処理は、
プロジェクト特徴の各評価項目の値を、リスクの大きさ
という観点から、複数の領域に区分する処理である。
Next, the project risk area calculation means 4
A description will be given of the project risk area calculation processing executed by the program. The project risk area calculation process
This is a process of dividing the value of each evaluation item of the project characteristics into a plurality of areas from the viewpoint of the magnitude of risk.

【0038】図3は、リスクの大きさに対応して、評価
項目の値を複数の領域に区分する処理を説明する図であ
る。同図のグラフは、既に完了している過去のプロジェ
クトについて、ある評価項目(例えば、新規性)の値か
ら見た場合の、トラブル(あり)プロジェクトとトラブ
ルなしプロジェクトの分布を示している。このような分
布図は、既に完了している過去の複数のプロジェクトに
ついて、プロジェクト毎に、評価項目の値及び当該プロ
ジェクトがトラブルプロジェクトであったかトラブルな
しプロジェクトあったかを求めることで得られる。
FIG. 3 is a diagram for explaining a process of dividing the value of the evaluation item into a plurality of areas according to the magnitude of the risk. The graph in the figure shows the distribution of trouble (with) projects and trouble-free projects with respect to values of certain evaluation items (for example, novelty) for past projects that have already been completed. Such a distribution map can be obtained for a plurality of past projects that have already been completed by obtaining, for each project, the value of an evaluation item and whether the project was a trouble project or a trouble-free project.

【0039】ここで、評価項目の値は、予め定められた
計算方法(例えば、上記の式1)に従って、計算され
る。また、トラブルプロジェクトか否かの判別は、例え
ば、予定開発期間に対する遅延率がある値以上のプロジ
ェクトをトラブルプロジェクトとし、それ以下をトラブ
ルなしプロジェクトとすればよい。
Here, the value of the evaluation item is calculated according to a predetermined calculation method (for example, the above formula 1). The determination as to whether or not the project is a trouble project may be made, for example, such that a project having a delay rate with respect to a scheduled development period equal to or greater than a certain value is defined as a trouble project, and a project having a delay rate less than that is defined as a trouble-free project.

【0040】予定開発期間に対する遅延率は、以下の式
で計算される。
The delay rate for the scheduled development period is calculated by the following equation.

【0041】遅延率=実開発期間/予定開発期間 ここで、実開発期間とは、プロジェクト開始予定日から
実際に終了した日までの期間をいい、予定開発期間と
は、プロジェクト開始予定日から終了予定日までの期間
をいう。また、プロジェクト開始予定日と終了予定日
は、プロジェクト計画データ8に、プロジェクトが実際
に終了した日は、プロジェクト実績データ9に、それぞ
れ含まれている。
Delay rate = actual development period / scheduled development period Here, the actual development period refers to a period from the scheduled start date of the project to the actual end date, and the scheduled development period is the end of the scheduled start date of the project. The period up to the scheduled date. The planned start date and end date of the project are included in the project plan data 8, and the actual end date of the project is included in the actual project data 9.

【0042】図3に示すような分布図が得られると、次
に、リスクの大きさに応じて(具体的には、過去のトラ
ブルプロジェクト及びトラブルなしプロジェクトの分布
に基づいて)、評価項目の値を、「安全」、「注意」、
「危険」の3領域に区分する。ここでは、「安全」領域
を、トラブルプロジェクトがほとんどない評価項目の値
の領域と定義する。具体的には、評価項目の値がα以下
の領域が該当し、値αは、例えばトラブルプロジェクト
の中での評価項目の最小値、または、評価項目の値の小
さい方からある割合(順番)に位置する値とする。同様
に、「危険」領域は、トラブルなしプロジェクトがほと
んどない評価項目の値の領域と定義する。具体的には、
評価項目の値がβ以上の領域が該当し、値βは、例えば
トラブルなしプロジェクトの中での評価項目の最大値、
または、評価項目の値の大きい方からある割合(順番)
に位置する値とする。そして、残りの領域、すなわち、
「安全」領域でも「危険」領域でもない領域を、「注
意」領域と定義する。具体的には、評価項目の値がαか
らβまでの領域が該当する。
When the distribution chart as shown in FIG. 3 is obtained, next, the evaluation items are evaluated according to the magnitude of the risk (specifically, based on the distribution of past trouble projects and projects without trouble). Values are "safe", "caution",
It is divided into three areas of “danger”. Here, the “safety” area is defined as an area of the value of the evaluation item having almost no trouble project. Specifically, an area in which the value of the evaluation item is equal to or less than α corresponds to, for example, the value α is a minimum value of the evaluation item in the trouble project, or a ratio (order) from the smaller of the evaluation item values. Be the value located at Similarly, the “dangerous” area is defined as an area of the value of the evaluation item with almost no trouble-free project. In particular,
An area where the value of the evaluation item is equal to or more than β corresponds to, for example, the value β is the maximum value of the evaluation item in a trouble-free project,
Or, a percentage (order) from the larger of the evaluation item values
Be the value located at And the remaining area, namely
An area that is neither a “safe” area nor a “dangerous” area is defined as a “caution” area. Specifically, the area in which the value of the evaluation item is from α to β corresponds to this.

【0043】以上のようにして求められた領域区分に関
するデータは、評価項目別に、リスク領域データ12と
して格納される。
The data on the area division obtained as described above is stored as risk area data 12 for each evaluation item.

【0044】なお、図3に示した例は、評価項目の値が
大きくなるに比例してリスクも大きくなる評価項目の場
合を示している。これとは逆に、評価項目の値が小さく
なるに従ってリスクが大きくなる評価項目の場合は、例
えば、「安全」領域がa以上、「危険」領域がb以下、
「注意」領域がaからbまでとなったとすると、aは、
トラブルプロジェクトの中での評価項目の最大値等と
し、bは、トラブルなしプロジェクトの中での評価項目
の最小値等とすればよい。
The example shown in FIG. 3 shows a case of an evaluation item in which the risk increases in proportion to the value of the evaluation item. Conversely, in the case of an evaluation item in which the risk increases as the value of the evaluation item decreases, for example, the “safe” area is equal to or more than a, the “danger” area is equal to or less than b,
Assuming that the “attention” area changes from a to b, a
What is necessary is just to set the maximum value of the evaluation items in the trouble project, and to set b to the minimum value of the evaluation items in the trouble-free project.

【0045】図4は、プロジェクトリスク領域計算処理
の流れを示すフローチャートである。
FIG. 4 is a flowchart showing the flow of the project risk area calculation process.

【0046】同図に示すように、プロジェクトリスク領
域計算手段4は、まず、プロジェクト特徴の評価項目の
うち、リスク領域区分の計算が行われていない評価項目
を一つ選択する(ST301)。
As shown in the figure, the project risk area calculation means 4 first selects one of the evaluation items of the project features, for which the calculation of the risk area classification has not been performed (ST301).

【0047】次に、プロジェクトリスク領域計算手段4
は、既に完了しているプロジェクトすべてについて、選
択した評価項目の値を特徴データ11から取得するとと
もに、各完了プロジェクトがトラブルプロジェクトであ
ったか否かをプロジェクトデータ10に基づいて判別す
る(ST302)。
Next, the project risk area calculation means 4
Acquires the values of the selected evaluation items from the feature data 11 for all the already completed projects, and determines whether each completed project is a trouble project based on the project data 10 (ST302).

【0048】なお、既に完了したプロジェクトすべてに
ついて、評価項目の値とトラブルプロジェクトであった
か否かを求めずに、ある条件(所属部、開発年度等)を
満たすプロジェクトに限定してもよい。
It should be noted that all of the completed projects may be limited to those that satisfy certain conditions (affiliation, development year, etc.) without finding the value of the evaluation item and whether the project was a trouble project.

【0049】次に、プロジェクトリスク領域計算手段4
は、図3で説明したように、各評価項目毎のトラブルプ
ロジェクト及びトラブルなしプロジェクトの分布に基づ
いて、各評価項目の値を、リスクの大きさに対応した複
数の領域に区分する(ST303)。
Next, the project risk area calculation means 4
Divides the value of each evaluation item into a plurality of areas corresponding to the magnitude of the risk based on the distribution of the trouble project and the trouble-free project for each evaluation item as described with reference to FIG. 3 (ST303). .

【0050】最後に、すべての評価項目について、リス
ク領域区分計算を行ったか否かを判断し(ST30
4)、リスク領域区分未計算の評価項目がある場合は、
ST301〜ST303の処理を繰り返す。一方、すべ
ての評価項目について、リスク領域区分計算が済んだ場
合は、すべての評価項目のリスク領域区分の集まりを、
リスク領域データ12として格納する(ST305)。
Finally, it is determined whether or not risk area classification calculation has been performed for all evaluation items (ST30).
4) If there is an evaluation item for which the risk area classification has not been calculated,
The processing of ST301 to ST303 is repeated. On the other hand, when the risk area classification has been calculated for all evaluation items, the collection of risk area classifications for all evaluation items is
It is stored as risk area data 12 (ST305).

【0051】以上のような処理の流れによって、すべて
の評価項目について、リスク領域区分が行われる。
According to the above processing flow, risk area classification is performed for all evaluation items.

【0052】次に、プロジェクトリスク評価手段5によ
って実行されるプロジェクトリスク評価処理について説
明する。プロジェクトリスク評価処理とは、プロジェク
ト特徴の各評価項目毎に、プロジェクトのリスクの大き
さを求める処理である。すなわち、プロジェクト特徴の
各評価項目の値の集合である特徴データ11と、各評価
項目のリスク領域区分の集合であるリスク領域データ1
2とに基づいて、プロジェクト特徴の各評価項目毎に、
評価項目の値がいずれのリスク領域区分に属するかに応
じて、プロジェクトのリスクの大きさを求める。例え
ば、評価項目の値が「危険」領域に属する場合は、リス
クレベルを「3」(最大リスク)とし、「注意」領域に
属する場合は、リスクレベルを「2」とし、「安全」領
域に属する場合は、リスクレベルを「1」(最小リス
ク)とする。
Next, the project risk evaluation processing executed by the project risk evaluation means 5 will be described. The project risk evaluation process is a process for obtaining the magnitude of the risk of the project for each evaluation item of the project characteristics. That is, the feature data 11 which is a set of values of each evaluation item of the project feature, and the risk region data 1 which is a set of risk region divisions of each evaluation item
2 and for each evaluation item of project characteristics,
The magnitude of the project risk is determined according to which risk area category the value of the evaluation item belongs to. For example, when the value of the evaluation item belongs to the “danger” area, the risk level is “3” (maximum risk), and when it belongs to the “caution” area, the risk level is “2” and the risk level is “2”. If so, the risk level is set to “1” (minimum risk).

【0053】図5は、プロジェクトリスク評価処理の流
れを示すフローチャートである。
FIG. 5 is a flowchart showing the flow of the project risk evaluation process.

【0054】同図に示すように、プロジェクトリスク評
価手段5は、まず、リスクの大きさを評価していないプ
ロジェクト特徴の評価項目を一つ選択する(ST40
1)。
As shown in the figure, the project risk evaluation means 5 first selects one evaluation item of a project feature whose risk magnitude has not been evaluated (ST40).
1).

【0055】次に、プロジェクトリスク評価手段5は、
当該評価項目の値を特徴データ11から、また、当該評
価項目のリスク領域区分をリスク領域データ12から、
それぞれ取り出す(ST402)。
Next, the project risk evaluation means 5
The value of the evaluation item is obtained from the feature data 11, and the risk area classification of the evaluation item is obtained from the risk area data 12.
Each is taken out (ST402).

【0056】次に、プロジェクトリスク評価手段5は、
当該評価項目のリスク領域区分から、当該評価項目の値
が、いずれの領域区分に属するかによって、当該評価項
目の値に対応するリスクの大きさを求める(ST40
3)。
Next, the project risk evaluation means 5
From the risk area category of the evaluation item, the magnitude of the risk corresponding to the value of the evaluation item is obtained depending on which area category the value of the evaluation item belongs to (ST40).
3).

【0057】最後に、すべての評価項目についてリスク
の評価を行ったか否かを判断し(ST404)、リスク
未評価の評価項目がある場合は、ST401〜ST40
3の処理を繰り返す。一方、すべての評価項目について
リスク評価が済んだ場合は、すべての評価項目のリスク
の大きさの集合を、リスク評価データ13として格納す
る(ST405)。
Finally, it is determined whether or not the risk has been evaluated for all the evaluation items (ST404). If there is an evaluation item for which the risk has not been evaluated, ST401 to ST40 are determined.
Step 3 is repeated. On the other hand, when risk evaluation has been completed for all evaluation items, a set of risk magnitudes of all evaluation items is stored as risk evaluation data 13 (ST405).

【0058】以上のような処理の流れによって、各評価
項目毎にプロジェクトのリスク評価が行われる。
The risk of the project is evaluated for each evaluation item according to the above processing flow.

【0059】次に、管理業務レベル決定手段6によって
実行される管理業務レベル決定処理について説明する。
この管理業務レベル決定処理は、評価対象プロジェクト
における各管理業務の管理レベルを、複数ランクの重点
度で決定する処理をいう。すなわち、評価対象プロジェ
クトに関するリスク評価データ13と、各評価項目につ
いて、管理業務別の重点度割合を複数のランクで示す重
点管理業務データ14とに基づいて、評価対象プロジェ
クトにおける各管理業務の管理レベルとして、重点度を
決定する。重点度とは、管理業務に対する力の入れ具合
(工数)を示すもので、複数のランクで表現される。例
えば、2つのランクで表現した場合、対象管理業務が重
点管理業務であるか否かが示されることになる。
Next, the management task level determination processing executed by the management task level determination means 6 will be described.
This management work level determination process is a process of determining the management level of each management work in the evaluation target project based on a plurality of ranks. That is, the management level of each management operation in the evaluation target project is based on the risk evaluation data 13 on the evaluation target project and the priority management operation data 14 indicating the importance ratio for each management operation in a plurality of ranks for each evaluation item. To determine the degree of importance. The degree of importance indicates the degree of emphasis (man-hour) on management work, and is expressed by a plurality of ranks. For example, when expressed in two ranks, it indicates whether the target management task is the priority management task.

【0060】図6は、重点管理業務データ14の例を示
す図であり、同図(a)は、そのデータ構造を示し、同
図(b)はその具体例を示す図である。図6(a)に示
すように、重点管理業務データ14は、各評価項目と各
管理業務の重点度の関係を示すものであり、評価項目i
における管理業務jの重点度を重点度割合R(i,j)
で表現する。重点度割合R(i,j)は、評価項目iの
リスクが大きいときにおける管理業務jの重点度割合で
あり、当該リスクを低減させるの必要とされる力の入れ
具合(工数)を示し、複数のレベルで表される。例え
ば、2レベル(1か0)で表現した場合、評価項目iの
リスクが大きいとき、当該管理業務が重点管理業務であ
るか(1の時)、否か(0のとき)を示す。
FIG. 6 is a diagram showing an example of the priority management business data 14, FIG. 6 (a) shows the data structure thereof, and FIG. 6 (b) shows a specific example thereof. As shown in FIG. 6A, the priority management task data 14 indicates the relationship between each evaluation item and the priority of each management task.
The importance of the management job j in the importance ratio R (i, j)
Expressed by The priority ratio R (i, j) is a priority ratio of the management task j when the risk of the evaluation item i is large, and indicates the degree of effort (man-hours) required to reduce the risk. Represented on multiple levels. For example, when expressed in two levels (1 or 0), when the risk of the evaluation item i is large, it indicates whether the management task is a priority management task (1) or not (0).

【0061】図6(b)は、重点管理業務データ14の
具体例を示す図である。同図に示すように、評価項目と
しては、「新規性」、「納期余裕」、「要求確定度」の
3つがあり、管理業務としては、「進捗管理」、「要求
仕様管理」、「品質管理」の3つがある。そして、重点
度割合が2レベル(1:重点、0:その他)で与えられ
ている。この例では、「新規性」のリスクが大きいとき
は、「品質管理」が重点管理業務であり、「納期余裕」
のリスクが大きいときは、「進捗管理」が重点管理業務
であり、「要求確定度」のリスクが大きいときは、「要
求仕様管理」が重点管理業務であることを示している。
FIG. 6B is a diagram showing a specific example of the priority management business data 14. As shown in the figure, there are three evaluation items: "newness", "delivery margin", and "requirement determination degree". Management tasks include "progress management", "requirement specification management", and "quality management". Management ”. The importance ratio is given at two levels (1: importance, 0: other). In this example, when the risk of "novelty" is high, "quality control" is the priority management task, and "delivery margin"
When the risk of “requirement specification” is large, it indicates that “progress management” is a priority management business, and when the risk of “requirement determination degree” is large, “requirement specification management” is a priority management business.

【0062】図7は、管理業務レベル決定処理の流れを
示すフローチャートである。
FIG. 7 is a flowchart showing the flow of the management task level determination process.

【0063】同図に示すように、管理業務レベル決定手
段6は、まず、重点度の計算を行っていない管理業務を
一つ選択する(ST501)。
As shown in the figure, the management task level determining means 6 first selects one management task for which the priority level has not been calculated (ST501).

【0064】次に、管理業務レベル決定手段6は、評価
対象プロジェクトのプロジェクト特徴の各評価項目の値
を、特徴データ11から、また、選択されている管理業
務の各評価項目における重点度割合を重点管理業務デー
タ14からそれぞれ取り出す(ST502)。
Next, the management task level determination means 6 calculates the value of each evaluation item of the project feature of the project to be evaluated from the feature data 11 and the importance ratio in each evaluation item of the selected management task. Each is extracted from the priority management business data 14 (ST502).

【0065】次に、管理業務レベル決定手段6は、当該
管理業務の管理レベルとして、重点度を計算する(ST
503)。管理業務jの重点度の計算は、まず、評価項
目iのリスクの大きさに重点度割合R(i,j)を掛け
た値をすべての評価項目iについて合計する。そして、
その合計値に応じて、複数ランクの重点度を対応づけ
る。
Next, the management task level determining means 6 calculates the importance level as the management level of the management task (ST)
503). In the calculation of the importance of the management task j, first, a value obtained by multiplying the magnitude of the risk of the evaluation item i by the importance ratio R (i, j) is totaled for all the evaluation items i. And
In accordance with the total value, the importance levels of a plurality of ranks are associated.

【0066】例えば、リスクの大きさが2レベル(1:
大、0:小)で表され、各管理業務の管理レベルが2ラ
ンク(1:重点管理業務、0:通常管理業務)で表され
る場合は、リスクの大きさに重点度割合R(i,j)を
掛けたものをすべての評価項目iについて合計した合計
値が0より大きい場合、管理レベルを「1」(重点管理
業務)とし、合計値が0のとき管理レベルを「0」(通
常管理業務)とすればよい。この場合、図6(b)に示
した例において、「新規性」と「要求確定度」のリスク
が大(リスクレベル=1)、「納期余裕」のリスクが小
(リスクレベル=0)とすると、「進捗管理」、「要求
仕様管理」「品質管理」の合計値は、それぞれ、0、
1、1となる。従って、この場合は、「要求仕様管理」
と「品質管理」が重点管理業務となる。
For example, when the magnitude of the risk is two levels (1:
If the management level of each management task is represented by two ranks (1: priority management task, 0: normal management task), the importance level ratio R (i , J), the management level is set to “1” (priority management task) when the sum total of all the evaluation items i is greater than 0, and when the sum is 0, the management level is set to “0” ( Normal management work). In this case, in the example shown in FIG. 6B, the risks of “novelty” and “request confirmation degree” are large (risk level = 1), and the risk of “delivery margin” is small (risk level = 0). Then, the total values of “progress management”, “required specification management” and “quality management” are 0,
1 and 1. Therefore, in this case, "Required specification management"
And “quality management” are the key management tasks.

【0067】最後に、すべての管理業務について重点度
を計算をしたか否かについて判断し(ST504)、重
点度未計算の管理業務がある場合は、ST501〜ST
503の処理を繰り返す。一方、すべての管理業務につ
いて重点度計算が済んだ場合は、すべての管理業務の重
点度の集合を、管理レベルデータ15として格納する
(ST505)。
Finally, it is determined whether or not the priority has been calculated for all the management tasks (ST504). If there is a management task for which the priority has not been calculated, ST501 to ST501 are executed.
Step 503 is repeated. On the other hand, when the priority level calculation is completed for all the management tasks, a set of the priority levels of all the management tasks is stored as the management level data 15 (ST505).

【0068】以上のような処理の流れによって、すべて
の管理業務について重点度の計算が行われる。
According to the above-described processing flow, the degree of importance is calculated for all management tasks.

【0069】このようにして求められた管理レベルデー
タ15に基づいて、管理業務レベル表示手段7は、各管
理業務毎に、管理レベルとして、重点度を表示させる。
また、重点度が2ランクで表される場合は、重点管理業
務と判断された管理業務のみを表示させるようにしても
よい。
On the basis of the management level data 15 obtained in this way, the management task level display means 7 displays the importance level as the management level for each management task.
When the priority level is represented by two ranks, only the management task determined to be the priority management task may be displayed.

【0070】上記実施形態は、各管理業務の管理レベル
を複数のレベルで提示するものであるが、次に、管理業
務毎に設定した管理レベル尺度の値で提示する例につい
て説明する。管理レベル尺度とは、各管理業務の実施の
程度(管理の強さ)を表す尺度をいい、各管理業務毎に
適当な尺度が予め選ばれる。例えば、要求仕様管理にお
ける顧客打合せ頻度、品質管理におけるデザインレビュ
ー頻度、工程管理における工程会議開催頻度等が考えら
れる。
In the above embodiment, the management level of each management task is presented at a plurality of levels. Next, an example will be described in which the management level is presented using the value of the management level scale set for each management task. The management level scale refers to a scale indicating the degree of implementation (management strength) of each management operation, and an appropriate scale is selected in advance for each management operation. For example, a customer meeting frequency in requirements specification management, a design review frequency in quality management, a process meeting frequency in process management, and the like can be considered.

【0071】図8は、本発明による第2の管理業務評価
装置の処理ブロックを示す図である。この管理業務評価
装置は、管理レベルを管理レベル尺度の値で提示するも
のである。図1に示した管理業務評価装置との構成上の
違いは、管理業務レベル分け計算手段18と管理レベル
分けデータ19が追加されて設けられていることであ
る。
FIG. 8 is a diagram showing processing blocks of the second management service evaluation device according to the present invention. This management work evaluation device presents a management level as a value of a management level scale. The difference from the management work evaluation device shown in FIG. 1 is that a management work level classification calculation unit 18 and management level classification data 19 are additionally provided.

【0072】管理業務レベル分け計算手段18は、既に
完了したプロジェクトに関するプロジェクトデータ10
に基づいて、予め決められた管理業務毎の管理レベル尺
度の値を、複数の領域(管理レベル領域)に区分し、領
域分割結果を、管理レベル分けデータ19として格納す
る。管理業務レベル分け計算手段18と管理レベル分け
データ19の追加に伴い、処理については、管理業務レ
ベル決定処理の内容が変更され、新たに管理業務レベル
分け計算処理が追加される。
The management work level division calculating means 18 calculates the project data 10
, The value of the management level scale for each predetermined management task is divided into a plurality of areas (management level areas), and the area division result is stored as management level division data 19. With the addition of the management task level division calculation means 18 and the management level division data 19, the contents of the management task level determination processing are changed, and the management task level division calculation processing is newly added.

【0073】まず、管理業務レベル分け計算手段18に
よって実行される管理業務レベル分け計算処理について
説明する。管理業務レベル分け計算処理は、予め設定さ
れた管理業務毎の管理レベル尺度の値を、過去における
トラブルプロジェクトの発生状況に対応付けた管理の強
さで複数の領域に区分する。
First, the management task level division calculation processing executed by the management task level division calculation means 18 will be described. In the management task level division calculation process, the value of the management level scale for each management task set in advance is divided into a plurality of areas according to the management strength associated with the occurrence situation of the trouble project in the past.

【0074】図9は、トラブルプロジェクトの発生状況
に対応した管理レベル尺度の値の区分処理を説明する図
である。同図のグラフは、既に完了している過去のプロ
ジェクトについて、ある管理レベル尺度(例えば、顧客
打ち合わせ頻度)の値から見た場合の、トラブル(あ
り)プロジェクトとトラブルなしプロジェクトの分布を
示している。このような分布図は、図3と同様に、既に
完了している過去の複数のプロジェクトについて、プロ
ジェクト毎に、管理レベル尺度の値及び当該プロジェク
トがトラブルプロジェクトであったかトラブルなしプロ
ジェクトあったかを求めることで得られる。
FIG. 9 is a diagram for explaining the process of classifying the value of the management level scale corresponding to the occurrence status of a trouble project. The graph in the figure shows the distribution of trouble (with) projects and projects without trouble as seen from the value of a certain management level scale (for example, customer meeting frequency) for past projects that have already been completed. . Similar to FIG. 3, such a distribution map is obtained by obtaining the value of the management level scale and whether the project was a trouble project or a trouble-free project for each of a plurality of completed past projects. can get.

【0075】例えば、管理レベル尺度が顧客打合せ頻度
の場合、プロジェクト実績データ9にある顧客との打合
せ実績(例えば、打合せ日付のデータ)から、打合せ回
数を集計し、その頻度を求める。また、トラブルプロジ
ェクトか否かは、前述のプロジェクトリスク領域計算処
理で示した通り、予定開発期間に対する遅延率がある値
以上のプロジェクトがトラブルプロジェクト、それ以下
がトラブルなしプロジェクトとすればよい。
For example, when the management level scale is the customer meeting frequency, the number of meetings is counted from the meeting results with the customer (for example, data on the meeting date) in the project performance data 9 and the frequency is calculated. Whether or not a project is a trouble project may be determined as a project having a delay rate greater than or equal to a delay rate with respect to a scheduled development period as a trouble project, and a project having no delay is defined as a project having no trouble as described in the project risk area calculation process.

【0076】図9に示すような分布図が得られると、次
に、この分布図に基づいて、管理レベル尺度の値が大き
くなる(管理を強化する)に従って、管理レベル尺度の
値を「不十分」、「標準」、「十分」の3領域に区分す
る。ここでは、「不十分」領域を、トラブルなしプロジ
ェクトがほとんどない管理レベル尺度の領域と定義す
る。具体的には、管理レベル尺度の値がγ以下の領域が
該当し、値γは、例えば、トラブルなしプロジェクトの
中での管理レベル尺度の最小値、または、管理レベル尺
度の値の小さい方からある割合(順番)に位置する値と
する。同様に、「十分」領域を、トラブルプロジェクト
がほとんどない管理レベル尺度の領域と定義する。具体
的には、管理レベル尺度の値がδ以上の領域が該当し、
値δは、例えばトラブルプロジェクトの中での管理レベ
ル尺度の最大値、または、管理レベル尺度の値の大きい
方からある割合(順番)に位置する値とする。そして、
残りの領域、すなわち、「不十分」領域でも「十分」で
もない領域を「標準」領域と定義する。具体的には、管
理レベル尺度の値がγからδまでの領域が該当する。
When a distribution chart as shown in FIG. 9 is obtained, the value of the management level scale is changed to “unfavorable” as the value of the management level scale increases (enhances management) based on this distribution chart. It is divided into three areas, "sufficient", "standard", and "sufficient". Here, the "insufficient" area is defined as the area of the management level scale with few trouble-free projects. Specifically, an area in which the value of the management level scale is equal to or less than γ corresponds to the value γ, for example, from the minimum value of the management level scale in a trouble-free project or the smaller value of the management level scale. The value is located at a certain ratio (order). Similarly, the “sufficient” area is defined as the area of the management level scale with few trouble projects. Specifically, an area where the value of the management level scale is equal to or more than δ,
The value δ is, for example, the maximum value of the management level scale in the trouble project, or a value located at a certain ratio (order) from the larger value of the management level scale. And
The remaining areas, that is, areas that are neither "insufficient" nor "sufficient", are defined as "standard" areas. Specifically, the region in which the value of the management level scale is from γ to δ corresponds.

【0077】以上のようにして求められた領域区分に関
するデータは、管理レベル尺度別に、管理レベル分けデ
ータ19に格納される。
The data on the area division obtained as described above is stored in the management level division data 19 for each management level scale.

【0078】図10は、管理業務レベル分け計算処理の
流れを示すフローチャートである。
FIG. 10 is a flowchart showing the flow of the management task level division calculation process.

【0079】まず、管理業務レベル分け計算手段18
は、各管理業務毎に予め設定された管理レベル尺度のう
ち、管理レベル領域区分の計算が行われていない管理レ
ベル尺度を一つ選択する(ST901)。
First, the management task level division calculating means 18
Selects one of the management level scales for which the management level area division has not been calculated from the management level scales set in advance for each management task (ST901).

【0080】次に、管理業務レベル分け計算手段18
は、完了したプロジェクトすべてについて、プロジェク
トデータ10に基づいて、各プロジェクト毎に、選択し
た管理レベル尺度の値と、当該プロジェクトがトラブル
プロジェクトであったかトラブルなしプロジェクトであ
ったかを求める(ST902)。
Next, the management task level division calculating means 18
Determines the value of the selected management level scale for each completed project and whether the project was a trouble project or a trouble-free project based on the project data 10 (ST902).

【0081】なお、完了したプロジェクトすべてについ
て、管理レベル尺度の値とトラブルプロジェクトか否か
を求めるのではなく、ある条件(所属部、開発年度等)
を満たすプロジェクトに限定してもよい。
It is to be noted that the values of the management level scale and whether or not the project is a trouble project are determined for all completed projects.
It may be limited to projects that satisfy the conditions.

【0082】次に、管理業務レベル分け計算手段18
は、図9で説明したように、選択されている管理レベル
尺度上におけるトラブルプロジェクト及びトラブルなし
プロジェクトの分布から、管理レベル尺度をその値によ
ってトラブルプロジェクトの発生状況に対応した複数の
領域に区分する(ST903)。
Next, the management task level division calculating means 18
Divides the management level scale into a plurality of areas corresponding to the occurrence status of the trouble project based on the distribution of the trouble project and the project without trouble on the selected management level scale as described with reference to FIG. (ST903).

【0083】最後に、すべての管理レベル尺度につい
て、管理レベル領域区分の計算を行ったか否かを判断し
(ST904)、管理レベル領域区分が未計算の管理レ
ベル尺度がある場合は、ST901〜ST903の処理
を繰り返す。一方、すべての管理レベル尺度について管
理レベル領域区分計算が済んだ場合は、すべての管理レ
ベル尺度の管理レベル領域区分の集合を、管理レベル分
けデータ19として格納する(ST905)。
Finally, it is determined whether or not management level area divisions have been calculated for all management level scales (ST904). If there are management level scales for which management level area divisions have not been calculated, ST901 to ST903 are performed. Is repeated. On the other hand, when the management level area division has been calculated for all the management level scales, a set of management level area divisions of all the management level scales is stored as management level division data 19 (ST905).

【0084】以上のような処理の流れによって、すべて
の管理レベル尺度について、管理レベル領域区分の計算
が行われる。
With the above processing flow, the management level area division is calculated for all the management level scales.

【0085】次に、第2の管理業務評価装置で行われる
管理業務レベル決定処理について説明する。ここでの管
理業務レベル決定処理では、まず、前述したのと同様
に、プロジェクト特徴の各評価項目毎に算出されたリス
クの大きさの集合であるリスク評価データ13と、各評
価項目について、管理業務別の重点度を複数のランクで
示す重点管理業務データ14とに基づいて、評価対象プ
ロジェクトにおける各管理業務毎に、複数ランクの重点
度を決定する。次に、管理レベル分けデータ19から、
管理レベル尺度の区分領域を求め、予め与えられている
対応関係に基づいて、管理業務の重点度に対応した管理
レベル尺度の領域を管理レベルとして決定する。例え
ば、各管理業務が、2ランクの重点度(1:重点管理業
務、0:通常管理業務)で表され、管理レベル尺度が、
「不十分」、「標準」、「十分」の3つの領域に区分さ
れているとき、重点管理業務の場合は、管理レベル尺度
の「十分」領域を、通常管理業務の場合は管理レベル尺
度の「標準」領域を対応させ、それぞれの管理業務の管
理レベルとして決定し、その結果を管理レベルデータ1
5として格納する。
Next, the management task level determination processing performed by the second management task evaluation device will be described. In the management work level determination process, first, as described above, first, the risk evaluation data 13 which is a set of the risk magnitudes calculated for each evaluation item of the project characteristics, and the management of each evaluation item are performed. Based on the priority management task data 14 indicating the priority of each task by a plurality of ranks, the priority of a plurality of ranks is determined for each management task in the evaluation target project. Next, from the management level classification data 19,
A division area of the management level scale is obtained, and a management level scale area corresponding to the priority of the management work is determined as a management level based on a predetermined correspondence. For example, each management task is represented by two ranks of importance (1: priority management task, 0: normal management task), and the management level scale is:
When classified into three areas of “insufficient”, “standard” and “sufficient”, the “sufficient” area of the management level scale is used for priority management work, and the management level scale is used for normal management work. The “standard” areas are made to correspond to each other and determined as the management level of each management job, and the result is referred to as management level data 1
5 is stored.

【0086】このように決定された管理レベルデータ1
5に基づいて、管理業務レベル表示手段7は、各管理業
務毎に、対応づけられた管理レベル尺度の値(領域)を
表示する。例えば、進捗管理が重点管理業務と判断さ
れ、当該業務の管理レベル尺度である進捗会議開催頻度
の「十分」領域が「月にN回以上」であった場合、進捗
管理について、「月にN回以上進捗会議を開催するこ
と」等のメッセージがディスプレイ等の出力装置17に
表示されることになる。
The management level data 1 thus determined
5, the management task level display means 7 displays a value (area) of the management level scale associated with each management task. For example, if progress management is determined to be a priority management task, and the “sufficient” area of the frequency of holding a progress meeting, which is a management level scale of the task, is “N or more times a month”, A progress meeting more than once "is displayed on the output device 17 such as a display.

【0087】以上説明したように第2の管理業務評価装
置では、リスク評価データ13と重点管理業務データ1
4とに基づいて、各管理業務の重要度ランクを決定し、
それと管理レベル分けデータ19から各管理業務の管理
レベル尺度の領域を求めているが、次に、重点管理業務
データ14を利用しない実施形態について説明する。
As described above, in the second management work evaluation apparatus, the risk evaluation data 13 and the priority management work data 1
4 and determine the rank of importance of each administrative task,
An area of the management level scale of each management task is obtained from the management level division data 19, but an embodiment in which the priority management task data 14 is not used will be described.

【0088】図11は、本発明による第3の管理業務評
価装置の処理ブロックを示す図である。図8に示した第
2の管理業務評価装置との構成上の違いは、重点管理業
務データ14が用意されていないことと、リスク評価デ
ータ13が管理業務レベル分け計算手段18に入力され
ることである。
FIG. 11 is a diagram showing processing blocks of the third management work evaluation device according to the present invention. The configuration difference from the second management work evaluation device shown in FIG. 8 is that the priority management work data 14 is not prepared and the risk evaluation data 13 is input to the management work level classification calculation means 18. It is.

【0089】この場合、管理業務レベル分け計算手段1
8は、完了したプロジェクトに関するプロジェクトデー
タ10及びリスク評価データ13とに基づいて、プロジ
ェクト特徴評価項目のリスクの大きさ毎に、管理業務毎
の管理レベル尺度の値を、過去におけるトラブルプロジ
ェクトの発生状況に対応付けて、複数の領域に区分し、
領域分割結果を、管理レベル分けデータ19として格納
する。なお、第1の管理業務評価装置においては、リス
ク評価データは、評価対象プロジェクトについてのみ評
価すれば足りたが、ここでは、既に完了しているプロジ
ェクトについても評価する。
In this case, the management work level division calculating means 1
8 shows the value of the management level scale for each management task for each magnitude of the risk of the project characteristic evaluation item based on the project data 10 and the risk evaluation data 13 regarding the completed project, , Divided into multiple areas,
The area division result is stored as management level division data 19. In the first management work evaluation device, it is sufficient that the risk evaluation data is evaluated only for the project to be evaluated. However, here, the already completed project is also evaluated.

【0090】図12は、トラブルプロジェクトの発生状
況に対応した管理レベル尺度の値の区分処理を説明する
図である。同図のグラフは、既に完了している過去のプ
ロジェクトについて、ある管理レベル尺度の値から見た
場合の、トラブル(あり)プロジェクトとトラブルなし
プロジェクトの分布を、各リスクレベル毎に示してい
る。なお、リスクの大きさは、3レベルに区分されてい
るとする。図12の分布図は、図9で示した分布図を、
評価項目iのリスクの大きさによって、3つに分けたも
のといえる。このような分布図は、図9の場合と同様に
して、既に完了している過去の複数のプロジェクトにつ
いて、プロジェクト毎に、評価項目のリスクレベル、管
理レベル尺度の値及び当該プロジェクトがトラブルプロ
ジェクトであったかトラブルなしプロジェクトあったか
を求めることで得られる。
FIG. 12 is a diagram for explaining the process of classifying the value of the management level scale corresponding to the occurrence status of a trouble project. The graph in the figure shows the distribution of trouble (with) projects and trouble-free projects for each risk level when viewed from the values of a certain management level scale for past projects that have already been completed. It is assumed that the magnitude of the risk is divided into three levels. The distribution diagram of FIG. 12 is a distribution diagram shown in FIG.
According to the magnitude of the risk of the evaluation item i, it can be said that it is divided into three. Similar to the case of FIG. 9, such a distribution chart shows, for each of a plurality of past projects that have already been completed, the risk level of the evaluation item, the value of the management level scale, and whether the project is a trouble project. It can be obtained by asking if there was a project with no trouble.

【0091】図12に示すような分布図が得られると、
次に、この分布図に基づいて、各リスクレベル毎に、図
9の場合と同様にして、管理レベル尺度の値を「不十
分」、「標準」、「十分」の3領域に区分する。この場
合、評価項目iのリスクレベルがレベル3のときは、
「不十分」領域は、管理レベル尺度の値がα1以下の領
域、「十分」領域は、管理レベル尺度の値がβ1以上の
領域、「標準」領域は、管理レベル尺度の値がα1から
β1までの領域となる。また、評価項目iのリスクレベ
ルがレベル2のときは、「不十分」領域は、管理レベル
尺度の値がα2以下の領域、「十分」領域は、管理レベ
ル尺度の値がβ2以上の領域、「標準」領域は、管理レ
ベル尺度の値がα2からβ2までの領域となる。また、
評価項目iのリスクレベルがレベル1のときは、「不十
分」領域は、管理レベル尺度の値がα3以下の領域、
「十分」領域は、管理レベル尺度の値がβ3以上の領
域、「標準」領域は、管理レベル尺度の値がα3からβ
3までの領域となる。
When a distribution chart as shown in FIG. 12 is obtained,
Next, based on this distribution map, the value of the management level scale is divided into three areas of “insufficient”, “standard”, and “sufficient” in the same manner as in FIG. 9 for each risk level. In this case, when the risk level of the evaluation item i is level 3,
The “insufficient” area is an area where the management level scale value is equal to or less than α1, the “sufficient” area is an area where the management level scale value is equal to or more than β1, and the “standard” area is where the management level scale value is α1 to β1. The area up to. Further, when the risk level of the evaluation item i is level 2, the “insufficient” area is an area where the value of the management level scale is equal to or less than α2, the “sufficient” area is an area where the value of the management level scale is equal to or more than β2, The “standard” area is an area in which the value of the management level scale is from α2 to β2. Also,
When the risk level of the evaluation item i is level 1, the “insufficient” area is an area where the value of the management level scale is α3 or less,
The “sufficient” area is an area in which the value of the management level scale is β3 or more, and the “standard” area is an area in which the value of the management level scale is α3 to β.
Up to three areas.

【0092】以上のようにして求められた領域区分に関
するデータは、管理レベル尺度別に、対応するリスクレ
ベルと共に管理レベル分けデータ19に格納される。
The data on the area division obtained as described above is stored in the management level division data 19 together with the corresponding risk level for each management level scale.

【0093】図13は、第3の管理業務評価装置におけ
る管理業務レベル分け計算処理の流れを示すフローチャ
ートである。
FIG. 13 is a flowchart showing the flow of the management task level division calculation process in the third management task evaluation device.

【0094】同図に示すように、まず、管理業務レベル
分け計算手段18は、管理レベル尺度のうち、管理レベ
ル領域区分の計算を行っていない管理レベル尺度を一つ
選択し(ST1201)、更に、選択した管理レベル尺
度との関係の評価が行われていないプロジェクト特徴の
評価項目を一つ選択する(ST1202)。
As shown in the figure, first, the management task level division calculating means 18 selects one management level scale for which the management level area division has not been calculated from the management level scales (ST1201). Then, one of the project characteristic evaluation items whose relation to the selected management level scale has not been evaluated is selected (ST1202).

【0095】次に、管理業務レベル分け計算手段18
は、完了した過去のプロジェクトすべてについて、各プ
ロジェクト毎に、選択されている管理レベル尺度の値及
び評価項目のリスクの大きさ、並びにトラブルプロジェ
クトであったかトラブルなしプロジェクトであったかを
求める(ST1203)。この場合、管理レベル尺度の
値及び各プロジェクトがトラブルプロジェクトか否か
は、プロジェクトデータ10に基づいて求め、選択した
プロジェクト特徴評価項目のリスクの大きさは、リスク
評価データ13から求める。
Next, the management task level division calculating means 18
Calculates the value of the selected management level scale and the magnitude of the risk of the evaluation item for each completed past project, and whether the project was a trouble project or a trouble-free project (ST1203). In this case, the value of the management level scale and whether each project is a trouble project is obtained based on the project data 10, and the magnitude of the risk of the selected project characteristic evaluation item is obtained from the risk evaluation data 13.

【0096】次に、管理業務レベル分け計算手段18
は、図14に示したように、選択されている評価項目の
リスクの大きさ(レベル)毎に、ST1203で求めた
値をプロットして、選択された管理レベル尺度から見
た、トラブルプロジェクト及びトラブルなしプロジェク
トの分布を求め、その分布から、当該評価項目のリスク
の大きさ(レベル)毎に、選択された管理レベル尺度の
値を、トラブルプロジェクトの発生状況に対応した複数
の領域に区分する(ST1204)。
Next, the management work level division calculating means 18
As shown in FIG. 14, plotting the value obtained in ST1203 for each risk level (level) of the selected evaluation item, and viewing the trouble project and the risk as viewed from the selected management level scale Obtain the distribution of trouble-free projects and, based on the distribution, classify the value of the selected management level scale into a plurality of areas corresponding to the occurrence status of trouble projects for each risk level (level) of the relevant evaluation item (ST1204).

【0097】次に、すべての評価項目について、選択さ
れている管理レベル尺度との関係を評価したか否かを判
断し(ST1205)、管理レベル尺度との関係が未評
価である評価項目がある場合は、 ST1202〜ST
1204の処理を繰り返す。
Next, for all evaluation items, it is determined whether or not the relationship with the selected management level scale has been evaluated (ST1205), and there is an evaluation item whose relationship with the management level scale has not been evaluated. In case, ST1202-ST
Step 1204 is repeated.

【0098】一方、選択されている管理レベル尺度につ
いて、すべての評価項目との関係評価が済んだ場合は、
続けて、すべての管理レベル尺度について、管理レベル
領域区分の計算を行ったか否かを判断する(ST120
6)。その結果、管理レベル領域区分が未計算の管理レ
ベル尺度がある場合は、ST1201〜ST1205の
処理を繰り返す。一方、すべての管理レベル尺度につい
て、管理レベル領域区分計算が済んだ場合は、プロジェ
クト特徴評価項目のリスクの大きさと管理レベル尺度の
領域区分の関係を、すべての評価項目とすべての管理レ
ベル尺度について示した管理レベル分けデータ19とし
て格納する(ST1207)。
On the other hand, when the evaluation of the relationship between all the evaluation items and the selected management level scale is completed,
Subsequently, it is determined whether or not management level area division has been calculated for all management level scales (ST120).
6). As a result, if there is a management level scale for which the management level area division has not been calculated, the processing of ST1201 to ST1205 is repeated. On the other hand, when the management level area classification has been calculated for all management level scales, the relationship between the magnitude of the risk of the project characteristic evaluation item and the area classification of the management level scale is calculated for all the evaluation items and all management level scales. It is stored as the management level classification data 19 shown (ST1207).

【0099】以上のような処理の流れによって、すべて
の評価項目とすべての管理レベル尺度について管理レベ
ル領域区分の計算が行われる。
With the above processing flow, the management level area division is calculated for all the evaluation items and all the management level scales.

【0100】次に、第3の管理業務評価装置における管
理業務レベル決定処理について説明する。この管理業務
レベル決定処理では、各管理業務の管理レベルとして、
各管理レベル尺度の領域を次のように求める。まず、評
価項目を一つ選択し、リスク評価データ13に基づい
て、当該評価項目についての評価対象プロジェクトのリ
スクの大きさを求め、当該リスクの大きさ(レベル)に
基づいて、管理レベル分けデータ19から当該リスクレ
ベルに対応する領域区分データを取得し、当該領域区分
データに基づいて、適切な(例えば、十分領域に該当す
る)管理レベル尺度の領域を求める。同様に、すべての
評価項目について、リスクの大きさ(レベル)に対応し
た当該管理レベル尺度の領域を求める。そして、その積
集合を最終的に当該管理レベル尺度の領域と決定し、管
理レベルデータ15として格納する。例えば、すべての
管理レベル尺度について、「十分」領域に該当する領域
を選択し、各評価項目と対応づけて格納する。
Next, the management task level determination processing in the third management task evaluation device will be described. In this management task level determination process, as the management level of each management task,
The area of each management level scale is determined as follows. First, one evaluation item is selected, the magnitude of the risk of the project to be evaluated for the evaluation item is determined based on the risk evaluation data 13, and the management level classification data is determined based on the magnitude (level) of the risk. The area division data corresponding to the risk level is acquired from 19, and an appropriate (for example, sufficient area) management level scale area is obtained based on the area division data. Similarly, for all the evaluation items, the area of the management level scale corresponding to the magnitude (level) of the risk is obtained. Then, the intersection is finally determined as the area of the management level scale and stored as management level data 15. For example, for all management level scales, an area corresponding to the “sufficient” area is selected and stored in association with each evaluation item.

【0101】そして、管理業務レベル表示手段7は、こ
のような管理レベルデータ15に基づいて、各評価項目
毎に、対応する管理レベル尺度の値の領域を表示する。
例えば、「新規性」、「納期余裕」、「要求確定度」の
それぞれから見たときの「十分」領域に該当する管理レ
ベル尺度の領域が表示される。
Then, the management task level display means 7 displays the area of the value of the management level scale corresponding to each evaluation item based on the management level data 15 as described above.
For example, the area of the management level scale corresponding to the “sufficient” area when viewed from each of “novelty”, “delivery margin”, and “demand determination degree” is displayed.

【0102】以上説明した実施形態においては、各管理
業務の管理レベルの指針を、管理レベル尺度により定量
的に示すので(例えば、顧客打ち合わせを週1回以上行
え、等)、プロジェクトマネージャに対して実施目標を
明確にすることができ、管理業務の実施状況において、
目標とする管理レベルに達しているか否かを明確に判断
することができる。
In the embodiment described above, the guideline of the management level of each management operation is quantitatively indicated by the management level scale (for example, customer meetings can be performed once a week or more, etc.). Implementation goals can be clarified, and in the implementation status of management work,
It is possible to clearly determine whether the target management level has been reached.

【0103】また、過去のデータに基いて管理レベルの
指針を決めているので、プロジェクトマネージャの能力
や経験に関係なく、管理レベルの安定化が図れる。ま
た、プロジェクトの特徴に応じて管理レベルの指針を決
めているので、問題となりそうな点を考慮した重点管理
ができる。その結果、プロジェクトのトラブル発生を低
減することができる。
Further, since the management level guideline is determined based on past data, the management level can be stabilized irrespective of the ability and experience of the project manager. In addition, since the management level guideline is determined according to the characteristics of the project, priority management can be performed in consideration of potential problems. As a result, the occurrence of project trouble can be reduced.

【0104】最後に、上述した管理業務評価装置を応用
したシステムについて説明する。図14は、本装置を応
用した管理状況監視システム21を示す図である。同図
に示すように、管理状況監視システム21は、管理業務
評価装置1と管理レベル達成状況評価手段20とから構
成される。
Finally, a system to which the above-described management work evaluation device is applied will be described. FIG. 14 is a diagram showing a management status monitoring system 21 to which the present device is applied. As shown in the figure, the management status monitoring system 21 includes the management work evaluation device 1 and the management level achievement status evaluation means 20.

【0105】管理レベル達成状況評価手段20は、管理
業務評価装置1が決定した管理レベルの指針である管理
レベルデータ15と、現在進行中のプロジェクトの進捗
状況を示すプロジェクト進捗データ9とを比較し、管理
レベルの達成状況を監視する。そして、開発の残り期間
等を考慮して、必要な場合は管理を強化するようアラー
ムを出す。このような動作によって、本システムは、適
切なプロジェクト管理が行われるようプロジェクトマネ
ージャを支援する。
The management level achievement status evaluation means 20 compares the management level data 15 which is the guideline of the management level determined by the management work evaluation device 1 with the project progress data 9 which indicates the progress of the project currently in progress. Monitor progress at the management level. Then, in consideration of the remaining period of the development and the like, an alarm is issued to strengthen the management if necessary. With this operation, the present system assists the project manager in performing appropriate project management.

【0106】なお、これまで説明してきた各装置は、パ
ーソナルコンピュータ(PC)などの情報処理装置及び
情報処理装置が実行するプログラムによって実現するこ
とができる。この場合、プログラムは、ハードディスク
等の外部記憶装置に予めインストールされたり、フロッ
ピーディスクやCD−ROM等の記録媒体に記録され
て、各ユーザに提供される。
Each of the devices described so far can be realized by an information processing device such as a personal computer (PC) and a program executed by the information processing device. In this case, the program is installed in an external storage device such as a hard disk in advance, or recorded on a recording medium such as a floppy disk or a CD-ROM, and provided to each user.

【0107】[0107]

【発明の効果】以上詳細に説明したように、本発明によ
れば、概要計画から、各管理業務の管理レベルの指針を
示すことができるので、プロジェクト実施時におけるト
ラブルの発生を低減させることができる。また、過去の
データに基づいて管理レベルの指針を決めているので、
プロジェクトマネージャの個人的能力や経験によらない
でも、管理レベルの安定化が図れる。
As described in detail above, according to the present invention, the guideline of the management level of each management work can be indicated from the outline plan, so that the occurrence of troubles at the time of project implementation can be reduced. it can. In addition, since management level guidelines are determined based on past data,
The management level can be stabilized without depending on the personal ability and experience of the project manager.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明による第1の管理業務評価装置の処理
ブロックを示す図である。
FIG. 1 is a diagram showing processing blocks of a first management work evaluation device according to the present invention.

【図2】 プロジェクト特徴計算処理の流れを示すフロ
ーチャートである。
FIG. 2 is a flowchart illustrating a flow of a project feature calculation process.

【図3】 リスクの大きさに対応した評価項目の区分処
理を説明する図である。
FIG. 3 is a diagram illustrating a process of classifying an evaluation item corresponding to the magnitude of a risk.

【図4】 プロジェクトリスク領域計算処理の流れを示
すフローチャートである。
FIG. 4 is a flowchart illustrating a flow of a project risk area calculation process.

【図5】 プロジェクトリスク評価処理の流れを示すフ
ローチャートである。
FIG. 5 is a flowchart showing a flow of a project risk evaluation process.

【図6】 重点管理業務データ14の例を示す図であ
る。
FIG. 6 is a diagram showing an example of priority management business data 14;

【図7】 管理業務レベル決定処理の流れを示すフロー
チャートである。
FIG. 7 is a flowchart illustrating a flow of a management task level determination process.

【図8】 本発明による第2の管理業務評価装置の処理
ブロックを示す図である。
FIG. 8 is a diagram showing processing blocks of a second management work evaluation device according to the present invention.

【図9】 トラブルプロジェクトの発生状況に対応した
管理レベル尺度の値の区分処理を説明する図である。
FIG. 9 is a diagram illustrating a process of classifying a value of a management level scale corresponding to a situation of occurrence of a trouble project.

【図10】 管理業務レベル分け計算処理の流れを示す
フローチャートである。
FIG. 10 is a flowchart showing the flow of a management task level division calculation process.

【図11】 本発明による第3の管理業務評価装置の処
理ブロックを示す図である。
FIG. 11 is a diagram showing a processing block of a third management work evaluation device according to the present invention.

【図12】 トラブルプロジェクトの発生状況に対応し
た管理レベル尺度の値の区分処理を説明する図である。
FIG. 12 is a diagram illustrating a process of classifying a value of a management level scale corresponding to a situation of occurrence of a trouble project.

【図13】 管理業務レベル分け計算処理の流れを示す
フローチャートである。
FIG. 13 is a flowchart showing the flow of a management task level division calculation process.

【図14】 管理業務評価装置を応用した管理状況監視
システム21を示す図である。
FIG. 14 is a diagram showing a management status monitoring system 21 to which a management service evaluation device is applied.

【符号の説明】[Explanation of symbols]

1 管理業務評価装置 2 プロジェクトデータ入力手段 3 プロジェクト特徴計算手段 4 プロジェクトリスク領域計算手段 5 プロジェクトリスク評価手段 6 管理業務レベル決定手段 7 管理業務レベル表示手段 8 プロジェクト計画データ 9 プロジェクト実績データ 10 プロジェクトデータ 11 特徴データ 12 リスク領域データ 13 リスク評価データ 14 重点管理業務データ 15 管理レベルデータ 16 入力装置 17 出力装置 18 管理業務レベル分け計算手段 19 管理レベル分けデータ Reference Signs List 1 management work evaluation device 2 project data input means 3 project characteristic calculation means 4 project risk area calculation means 5 project risk evaluation means 6 management work level determination means 7 management work level display means 8 project plan data 9 project actual data 10 project data 11 Characteristic data 12 Risk area data 13 Risk evaluation data 14 Priority management work data 15 Management level data 16 Input device 17 Output device 18 Management work level classification calculation means 19 Management level classification data

フロントページの続き (72)発明者 多田 彰 神奈川県横浜市戸塚区吉田町292番地 株 式会社日立製作所生産技術研究所内 (72)発明者 松崎 吉衛 神奈川県横浜市戸塚区吉田町292番地 株 式会社日立製作所生産技術研究所内 (72)発明者 高村 稔子 茨城県日立市大みか町五丁目2番1号 株 式会社日立製作所大みか工場内 Fターム(参考) 5B049 AA00 CC00 DD01 DD05 EE01 EE02 FF01 FF02 FF07 GG04 5B076 EC09 Continued on the front page (72) Inventor Akira Tada 292 Yoshida-cho, Totsuka-ku, Yokohama-shi, Kanagawa Prefecture Inside Hitachi, Ltd.Production Technology Laboratory (72) Inventor Yoshie Matsuzaki 292 Yoshida-cho, Totsuka-ku, Yokohama-shi, Kanagawa Prefecture, Ltd. Hitachi, Ltd. Production Technology Research Laboratory (72) Inventor, Toshiko Takamura 5-2-1, Omika-cho, Hitachi City, Ibaraki Prefecture F-term in the Hitachi, Ltd. Omika Plant F-term (reference) 5B049 AA00 CC00 DD01 DD05 EE01 EE02 FF01 FF02 FF07 GG04 5B076 EC09

Claims (17)

【特許請求の範囲】[Claims] 【請求項1】 プロジェクト計画データとプロジェクト
実績データとからなるプロジェクトデータに基づいて、
プロジェクト特徴を計算するプロジェクト特徴計算手段
と、 完了したプロジェクトに関するプロジェクトデータとプ
ロジェクト特徴とに基づいて、評価項目のリスク領域を
計算するプロジェクトリスク領域計算手段と、 プロジェクト特徴とリスク領域とに基づいて、プロジェ
クトのリスクを評価するプロジェクトリスク評価手段
と、 プロジェクト特徴の各評価項目についてのリスクと各管
理業務との関連を示す重点管理業務データと、評価対象
プロジェクトのリスクとに基づいて、評価対象プロジェ
クトの各管理業務の管理レベルを決定する管理業務レベ
ル決定手段と、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示する管理業務レベル表示手段とから構成されるこ
とを特徴とする管理業務評価装置。
1. Based on project data composed of project plan data and project actual data,
A project risk area calculating means for calculating a risk area of an evaluation item based on a project characteristic calculating means for calculating a project characteristic; a project risk area calculating means for calculating a risk area of a completed project; Based on the project risk assessment method for assessing project risk, priority management work data indicating the relationship between the risk for each evaluation item of project characteristics and each management work, and the risk of the project to be evaluated, A management work evaluation device, comprising: a management work level determining means for determining a management level of each management work; and a management work level display means for presenting a management level of each management work in an evaluation target project.
【請求項2】 プロジェクト計画データとプロジェクト
実績データとからなるプロジェクトデータに基づいて、
プロジェクト特徴を計算するプロジェクト特徴計算手段
と、 完了したプロジェクトに関するプロジェクトデータとプ
ロジェクト特徴とに基づいて、評価項目のリスク領域を
計算するプロジェクトリスク領域計算手段と、 プロジェクト特徴とリスク領域とに基づいて、プロジェ
クトのリスクを評価するプロジェクトリスク評価手段
と、 完了したプロジェクトに関するプロジェクトデータに基
づいて、各管理業務の管理業務レベル尺度を、複数の管
理レベル領域に区分する管理業務レベル分け計算手段
と、 プロジェクト特徴の各評価項目についてのリスクと各管
理業務との関連を示す重点管理業務データと、評価対象
プロジェクトのリスクと、前記複数の管理レベル領域と
に基づいて、評価対象プロジェクトの各管理業務の管理
レベルを決定する管理業務レベル決定手段と、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示する管理業務レベル表示手段とから構成されるこ
とを特徴とする管理業務評価装置。
2. Based on project data comprising project plan data and project actual data,
A project risk area calculating means for calculating a risk area of an evaluation item based on a project characteristic calculating means for calculating a project characteristic; a project risk area calculating means for calculating a risk area of a completed project; A project risk evaluation means for evaluating the risk of the project, a management operation level division calculating means for dividing a management operation level scale of each management operation into a plurality of management level areas based on project data on completed projects, and a project characteristic. The management level of each management operation of the evaluation target project based on the priority management operation data indicating the relationship between the risk for each evaluation item and each management operation, the risk of the evaluation target project, and the plurality of management level areas Determine A management work level determining means, and a management work level display means for presenting a management level of each management work in an evaluation target project.
【請求項3】 前記管理業務レベル分け計算手段は、 完了したプロジェクトにおける、管理業務レベル尺度の
値とトラブルの有無との関係に基づいて、各管理レベル
尺度の値を複数の管理レベル領域に区分することを特徴
とする請求項2に記載の管理業務評価装置。
3. The management task level division calculating means divides the value of each management level measure into a plurality of management level areas based on the relationship between the value of the management task level scale and the presence or absence of a trouble in the completed project. 3. The management work evaluation device according to claim 2, wherein
【請求項4】 前記管理業務レベル決定手段は、 評価対象プロジェクトにおける各管理業務の重点度と前
記複数の管理レベル領域とに基づいて、各管理業務の管
理レベルとして、管理業務の重点度に対応する管理レベ
ル尺度の領域を決定することを特徴とする請求項2又は
請求項3に記載の管理業務評価装置。
4. The management task level determination means, as a management level of each management task, corresponding to the management task priority level, based on the priority level of each management task in the evaluation target project and the plurality of management level areas. The management task evaluation device according to claim 2 or 3, wherein an area of the management level scale to be performed is determined.
【請求項5】 プロジェクト計画データとプロジェクト
実績データとからなるプロジェクトデータに基づいて、
プロジェクト特徴を計算するプロジェクト特徴計算手段
と、 完了したプロジェクトに関するプロジェクトデータとプ
ロジェクト特徴とに基づいて、評価項目のリスク領域を
計算するプロジェクトリスク領域計算手段と、 プロジェクト特徴とリスク領域とに基づいて、プロジェ
クトのリスクを評価するプロジェクトリスク評価手段
と、 完了したプロジェクトに関するプロジェクトデータ及び
リスク評価に基づいて、リスクレベル毎に、管理業務レ
ベル尺度を、複数の管理レベル領域に区分する管理業務
レベル分け計算手段と、 評価対象プロジェクトのリスクとリスクレベル毎の前記
複数の管理レベル領域とに基づいて、評価対象プロジェ
クトのリスクの大きさに対応する管理業務レベル尺度の
領域を、評価対象プロジェクトの各管理業務の管理レベ
ルとして決定する管理業務レベル決定手段と、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示する管理業務レベル表示手段とから構成されるこ
とを特徴とする管理業務評価装置。
5. Based on project data including project plan data and project actual data,
A project risk area calculating means for calculating a risk area of an evaluation item based on a project characteristic calculating means for calculating a project characteristic; a project risk area calculating means for calculating a risk area of a completed project; Project risk evaluation means for assessing project risk, and management operation level classification calculation means for classifying the management operation level scale into a plurality of management level areas for each risk level based on project data and risk evaluation on completed projects Based on the risk of the evaluation target project and the plurality of management level areas for each risk level, the area of the management operation level scale corresponding to the magnitude of the risk of the evaluation target project is determined for each management operation of the evaluation target project. tube A management work evaluation device comprising: a management work level determination means for determining a management level; and a management work level display means for presenting a management level of each management work in an evaluation target project.
【請求項6】 前記管理業務レベル分け計算手段は、 完了したプロジェクトにおける、評価項目のリスクの大
きさと管理業務レベル尺度の値とトラブルの有無との関
係に基づいて、前記評価項目のリスクの大きさ別に、管
理レベル尺度を複数の管理レベル領域に区分することを
特徴とする請求項5に記載の管理業務評価装置。
6. The management task level division calculating means, based on the relationship between the magnitude of the risk of the assessment item, the value of the management task level scale, and the presence or absence of a trouble in the completed project, The management task evaluation device according to claim 5, wherein the management level scale is divided into a plurality of management level areas.
【請求項7】 前記管理レベル決定手段は、 プロジェクト特徴の各評価項目について、リスクの大き
さ別に管理レベル尺度の管理レベル領域を、それぞれの
管理レベル尺度について示す管理レベル分けデータか
ら、評価項目のリスクの大きさに対応する管理レベル尺
度の管理レベル領域を各評価項目について求め、 評価対象プロジェクトにおける各管理業務の管理レベル
を、その積集合の領域で示すことを特徴とする請求項5
又は請求項6に記載の管理業務評価装置。
7. The management level deciding means, for each evaluation item of the project characteristics, a management level area of a management level scale for each risk level, from management level classification data indicating the management level scale, for each evaluation item. 6. The management level area of the management level scale corresponding to the magnitude of the risk is obtained for each evaluation item, and the management level of each management operation in the project to be evaluated is indicated by the intersection area.
Or the management work evaluation device according to claim 6.
【請求項8】 請求項1〜請求項7のいずれか一項に記
載の重点管理業務評価装置と、 該重点管理業務評価装置によって提示される各管理業務
の管理レベルを示すデータとプロジェクト進捗データと
を比較し、管理レベルの達成状況を評価する管理レベル
達成状況評価手段とから構成されることを特徴とする管
理状況監視システム。
8. A priority management task evaluation device according to claim 1, data indicating a management level of each management task presented by the priority management task evaluation device, and project progress data. And a management level achievement status evaluation means for evaluating the achievement status of the management level.
【請求項9】 プロジェクト計画データとプロジェクト
実績データとからなるプロジェクトデータに基づいて、
プロジェクトの特徴データを計算し、 完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域を計算し、 特徴データとリスク領域とに基づいて、評価対象プロジ
ェクトのリスクを評価し、 特徴データの各評価項目についてのリスクと各管理業務
との関連を示す重点管理業務データとリスク評価とに基
づいて、評価対象プロジェクトの各管理業務の管理レベ
ルを複数ランクの重点度で決定し、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示することを特徴とする管理業務評価方法。
9. Based on project data including project plan data and project performance data,
Calculate characteristic data of the project, calculate the risk area of the evaluation item from the project data and characteristic data related to the completed project, evaluate the risk of the target project based on the characteristic data and the risk area, and calculate the characteristic data. The management level of each management operation of the project to be evaluated is determined based on the priority management operation data indicating the relationship between the risk and each management operation for each A management work evaluation method characterized by presenting a management level of each management work in a project.
【請求項10】 プロジェクト計画データとプロジェク
ト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算し、 完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域を計算し、 特徴データとリスク領域とに基づいて、評価対象プロジ
ェクトのリスクを評価し、 完了したプロジェクトにおける管理業務レベル尺度の値
とトラブルの有無との関係に基づいて、各管理業務の管
理業務レベル尺度の値を、複数の管理レベル領域に区分
し、 特徴データの各評価項目についてのリスクと各管理業務
との関連を示す重点管理業務データと、前記複数の管理
レベル領域とリスク評価とに基づいて、評価対象プロジ
ェクトの各管理業務の管理レベルを決定し、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示することを特徴とする管理業務評価方法。
10. A project characteristic data is calculated based on project data including project plan data and project performance data, and a risk area of an evaluation item is calculated from the project data and the characteristic data relating to the completed project. Evaluate the risk of the target project based on the characteristic data and the risk area, and based on the relationship between the value of the management task level scale and the presence or absence of trouble in the completed project, the value of the management task level scale for each management task Is divided into a plurality of management level areas, and the evaluation is performed based on the priority management work data indicating the relationship between the risk for each evaluation item of the characteristic data and each management work, and the plurality of management level areas and the risk evaluation. Determine the management level of each management task of the target project, and Management Operations Evaluation method characterized by presenting a management level of each management operations in transfected.
【請求項11】 評価対象プロジェクトの各管理業務の
管理レベルを決定する際、 評価対象プロジェクトにおける各管理業務の重点度を求
め、 当該重点度と前記複数の管理レベル領域とに基づいて、
各管理業務の管理レベルとして、管理業務の重点度に対
応する管理レベル尺度の領域を決定することを特徴とす
る請求項10に記載の管理業務評価方法。
11. When deciding a management level of each management operation of an evaluation target project, a priority level of each management operation in the evaluation target project is obtained, and based on the priority level and the plurality of management level areas,
11. The management work evaluation method according to claim 10, wherein a management level scale area corresponding to the importance of the management work is determined as the management level of each management work.
【請求項12】 プロジェクト計画データとプロジェク
ト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算し、 完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域を計算し、 特徴データとリスク領域に基づいて、プロジェクトのリ
スクを評価し、 完了したプロジェクトにおける、リスクの大きさ及び管
理業務レベル尺度の値とトラブルの有無との関係に基づ
いて、リスクの大きさ毎に、各管理業務の管理業務レベ
ル尺度の値を、複数の管理レベル領域に区分し、 当該区分の結果と評価対象プロジェクトのリスク評価と
に基づいて、評価対象プロジェクトの各管理業務の管理
レベルとして、評価対象プロジェクトのリスクの大きさ
に対応する管理業務レベル尺度の領域を決定し、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示することを特徴とする管理業務評価方法。
12. A project characteristic data is calculated based on project data including project plan data and project performance data, and a risk area of an evaluation item is calculated from the project data and the characteristic data related to the completed project. The project risk is evaluated based on the characteristic data and the risk area, and based on the relationship between the magnitude of the risk and the value of the management work level scale and the presence or absence of trouble in the completed project, for each magnitude of risk, The value of the management operation level scale for each management operation is divided into a plurality of management level areas, and the management level of each management operation of the evaluation target project is evaluated based on the results of the classification and the risk evaluation of the project to be evaluated. Management work level corresponding to the magnitude of the risk of the target project Management Operations Evaluation method characterized by determining the area of the degree, presents a management level of each management operations in the evaluation target project.
【請求項13】 評価対象プロジェクトの各管理業務の
管理レベルを決定する際、 特徴データの各評価項目について、リスクの大きさ別に
管理レベル尺度の管理レベル領域を、それぞれの管理レ
ベル尺度について示す管理レベル分けデータから、評価
項目のリスクの大きさに対応する管理レベル尺度の管理
レベル領域を各評価項目について求め、 評価対象プロジェクトにおける各管理業務の管理レベル
を、その積集合の領域で示すことを特徴とする請求項1
2に記載の管理業務評価方法。
13. When determining the management level of each management operation of a project to be evaluated, a management level area of a management level scale for each evaluation item of the characteristic data for each magnitude of risk is indicated for each management level scale. From the leveled data, determine the management level area of the management level scale corresponding to the magnitude of the risk of the evaluation item for each evaluation item, and indicate that the management level of each management operation in the project to be evaluated is indicated by its intersection area. Claim 1.
2. The management work evaluation method described in 2.
【請求項14】 概略計画に基づいてプロジェクトの特
徴を評価し、その結果及び過去のデータに基づいて、概
略計画から予測されるトラブル発生要因を低減させるた
めの管理業務を提示することを特徴とする管理業務評価
方法。
14. A project for evaluating characteristics of a project based on a rough plan and presenting a management task for reducing a trouble occurrence factor predicted from the rough plan based on a result and past data. Management work evaluation method.
【請求項15】 プロジェクト計画データとプロジェク
ト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算するステップと、 完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域データを計算す
るステップと、 特徴データとリスク領域データとに基づいて、プロジェ
クトのリスクを評価してリスク評価データを算出するス
テップと、 プロジェクト特徴の各評価項目についてのリスクと各管
理業務との関連を示す重点管理業務データとリスク評価
データとに基づいて、評価対象プロジェクトの各管理業
務の管理レベルを複数ランクの重点度で決定するステッ
プと、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示するステップとからなることを特徴とするプログ
ラムを記録したコンピュータ読み取り可能な記録媒体。
15. A method for calculating characteristic data of a project based on project data composed of project plan data and project performance data; and calculating risk area data of an evaluation item from the project data and characteristic data relating to the completed project. Calculating, evaluating the risk of the project based on the characteristic data and the risk area data, and calculating the risk evaluation data, and indicating a relationship between the risk for each evaluation item of the project characteristic and each management operation. A step of determining the management level of each management operation of the evaluation target project based on the priority management operation data and the risk evaluation data with a plurality of ranks of importance, and a step of presenting the management level of each management operation in the evaluation target project. Specially consist of A computer-readable recording medium storing a program to be.
【請求項16】 プロジェクト計画データとプロジェク
ト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算するステップと、 完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域データを計算す
るステップと、 特徴データとリスク領域データとに基づいて、評価対象
プロジェクトのリスクを評価してリスク評価データを算
出するステップと、 完了したプロジェクトにおける管理業務レベル尺度の値
とトラブルの有無との関係に基づいて、各管理業務の管
理業務レベル尺度の値を、複数の領域に区分して管理レ
ベル分けデータを算出するステップと、 プロジェクト特徴の各評価項目についてのリスクと各管
理業務との関連を示す重点管理業務データと、管理レベ
ル分けデータとリスク評価データとに基づいて、評価対
象プロジェクトの各管理業務の管理レベルを決定するス
テップと、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示するステップとからなることを特徴とするプログ
ラムを記録したコンピュータ読み取り可能な記録媒体。
16. A method for calculating characteristic data of a project based on project data including project plan data and project performance data; and calculating risk area data of an evaluation item from the project data and characteristic data relating to the completed project. Calculating the risk of the project to be evaluated based on the characteristic data and the risk area data, and calculating the risk evaluation data; and comparing the value of the management operation level scale and the presence or absence of trouble in the completed project. Calculating management level classification data by dividing the value of the management task level scale of each management task into a plurality of areas based on the relationship; and relating the risk of each evaluation item of the project characteristics to each management task. Key management business data that indicates Determining the management level of each management operation of the evaluation target project based on the classification data and the risk evaluation data; and presenting the management level of each management operation of the evaluation target project. A computer-readable recording medium on which a program is recorded.
【請求項17】 プロジェクト計画データとプロジェク
ト実績データとからなるプロジェクトデータに基づい
て、プロジェクトの特徴データを計算するステップと、 完了したプロジェクトに関するプロジェクトデータと特
徴データとから、評価項目のリスク領域を計算するステ
ップと、 特徴データとリスク領域データとに基づいて、プロジェ
クトのリスクを評価してリスク領域データを算出するス
テップと、 完了したプロジェクトにおける、リスクの大きさ及び管
理業務レベル尺度の値とトラブルの有無との関係に基づ
いて、リスクの大きさ毎に、各管理業務の管理業務レベ
ル尺度の値を、複数の管理レベル領域に区分して管理レ
ベル分けデータを算出するステップと、 管理レベル分けデータとリスク評価データとに基づい
て、評価対象プロジェクトの各管理業務の管理レベルと
して、評価対象プロジェクトのリスクの大きさに対応す
る管理業務レベル尺度の領域を決定するステップと、 評価対象プロジェクトにおける各管理業務の管理レベル
を提示するステップとからなることを特徴とするプログ
ラムを記録したコンピュータ読み取り可能な記録媒体。
17. A step of calculating characteristic data of a project based on project data including project plan data and project performance data, and calculating a risk area of an evaluation item from the project data and characteristic data relating to a completed project. Evaluating the risk of the project based on the characteristic data and the risk area data, and calculating the risk area data. Calculating the management level classification data by dividing the value of the management operation level scale of each management operation into a plurality of management level areas for each magnitude of risk based on the relationship with the presence / absence; Based on the risk assessment data As a management level of each management task of the project, there are steps of determining the area of the management task level scale corresponding to the magnitude of the risk of the project to be evaluated, and presenting the management level of each management task in the project to be evaluated. A computer-readable recording medium having recorded thereon a program.
JP17747498A 1998-06-24 1998-06-24 Management work evaluation apparatus and method in project management Expired - Fee Related JP3639434B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17747498A JP3639434B2 (en) 1998-06-24 1998-06-24 Management work evaluation apparatus and method in project management

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17747498A JP3639434B2 (en) 1998-06-24 1998-06-24 Management work evaluation apparatus and method in project management

Publications (2)

Publication Number Publication Date
JP2000011048A true JP2000011048A (en) 2000-01-14
JP3639434B2 JP3639434B2 (en) 2005-04-20

Family

ID=16031558

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17747498A Expired - Fee Related JP3639434B2 (en) 1998-06-24 1998-06-24 Management work evaluation apparatus and method in project management

Country Status (1)

Country Link
JP (1) JP3639434B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6321204B1 (en) * 1997-02-26 2001-11-20 Honda Giken Kogyo Kabushiki Kaisha Business operation management system
GB2372843A (en) * 2000-10-12 2002-09-04 Strategic Thought Ltd Integrative project risk management system
JP2003050910A (en) * 2001-08-07 2003-02-21 Sumitomo Mitsui Banking Corp Method and system for business processing management
JP2007265141A (en) * 2006-03-29 2007-10-11 Nec Corp Device, method and program for refining monitoring items
JP2015088141A (en) * 2013-11-01 2015-05-07 日立Geニュークリア・エナジー株式会社 Process planning assistance apparatus and process planning assistance method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6321204B1 (en) * 1997-02-26 2001-11-20 Honda Giken Kogyo Kabushiki Kaisha Business operation management system
GB2372843A (en) * 2000-10-12 2002-09-04 Strategic Thought Ltd Integrative project risk management system
US7440905B2 (en) 2000-10-12 2008-10-21 Strategic Thought Limited Integrative risk management system and method
JP2003050910A (en) * 2001-08-07 2003-02-21 Sumitomo Mitsui Banking Corp Method and system for business processing management
JP2007265141A (en) * 2006-03-29 2007-10-11 Nec Corp Device, method and program for refining monitoring items
JP2015088141A (en) * 2013-11-01 2015-05-07 日立Geニュークリア・エナジー株式会社 Process planning assistance apparatus and process planning assistance method

Also Published As

Publication number Publication date
JP3639434B2 (en) 2005-04-20

Similar Documents

Publication Publication Date Title
US5864822A (en) Benefits tracking and correlation system for use with third-party enabling organization
WO2019056710A1 (en) Supplier recommendation method and apparatus, and computer readable storage medium
US7565331B2 (en) Method for modeling processes in airlines and other industries, including cost asssesment of service disruptions
US20030135481A1 (en) Rules based method and system for project performance monitoring
US20120174017A1 (en) Systems, methods and computer software for innovation management
US20080221950A1 (en) Storage medium having requirement confirmation support program stored therein, requirement confirmation support method, and requirement confirmation support apparatus
JP2003532201A (en) Method and apparatus for facilitating management of information technology investment
US20020042700A1 (en) Method and apparatus for integrating and displaying real-time information related to natural gas pipelines
JP2000011048A (en) Device and method for evaluating management operation for project management
US7222110B2 (en) Charge information processing apparatus, franchise system provided with the charge information processing apparatus, charge calculating method, recording medium, and program
WO2001069421A2 (en) System and method for managing key process indicators
JP3670893B2 (en) Vehicle repair cost estimation system, estimation method, and computer-readable medium recording program
US20050055262A1 (en) System and a method for distributing assignments and receiving report data
JPH07160762A (en) Estimation support device
JPH1166150A (en) Risk evaluation system
WO2023042419A1 (en) Information presentation device, information presentation method, and information presentation program
NZ527578A (en) Method and apparatus for media buying
WO2021153662A1 (en) Mediation system, mediation method, and recording medium
JP6426263B1 (en) Water balance visualization system and water balance visualization method
JP2023114173A (en) Accounting processing device, accounting processing method, and accounting processing program
JP4258360B2 (en) Information system investment effect evaluation method and apparatus
JP2003196474A (en) Credit management system, credit management method and program for it
JP2003323542A (en) Business operation support device based on prediction of sale day
US20100250317A1 (en) Resource Modeling Tool
JP2005338888A (en) Business management device for gas station

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040914

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041115

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050105

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050114

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080121

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090121

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090121

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100121

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110121

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110121

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120121

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130121

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees