GB2187775A - Construction and use of subsea bore holes - Google Patents
Construction and use of subsea bore holes Download PDFInfo
- Publication number
- GB2187775A GB2187775A GB08705864A GB8705864A GB2187775A GB 2187775 A GB2187775 A GB 2187775A GB 08705864 A GB08705864 A GB 08705864A GB 8705864 A GB8705864 A GB 8705864A GB 2187775 A GB2187775 A GB 2187775A
- Authority
- GB
- United Kingdom
- Prior art keywords
- caisson
- ring
- bore hole
- bore holes
- large diameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title description 6
- 238000000034 method Methods 0.000 claims description 17
- 239000000463 material Substances 0.000 claims description 15
- 238000005553 drilling Methods 0.000 claims description 14
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 13
- 230000015572 biosynthetic process Effects 0.000 claims description 12
- 238000005755 formation reaction Methods 0.000 claims description 12
- 239000002699 waste material Substances 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 239000012267 brine Substances 0.000 claims description 5
- 239000012857 radioactive material Substances 0.000 claims description 5
- HPALAKNZSZLMCH-UHFFFAOYSA-M sodium;chloride;hydrate Chemical compound O.[Na+].[Cl-] HPALAKNZSZLMCH-UHFFFAOYSA-M 0.000 claims description 5
- 238000009412 basement excavation Methods 0.000 claims description 4
- 230000008014 freezing Effects 0.000 description 7
- 238000007710 freezing Methods 0.000 description 7
- 239000004576 sand Substances 0.000 description 6
- 239000004927 clay Substances 0.000 description 5
- 238000005065 mining Methods 0.000 description 5
- 239000007789 gas Substances 0.000 description 4
- 238000012544 monitoring process Methods 0.000 description 3
- IJGRMHOSHXDMSA-UHFFFAOYSA-N Atomic nitrogen Chemical compound N#N IJGRMHOSHXDMSA-UHFFFAOYSA-N 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 230000000087 stabilizing effect Effects 0.000 description 2
- 238000013019 agitation Methods 0.000 description 1
- 229910000278 bentonite Inorganic materials 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 238000005422 blasting Methods 0.000 description 1
- 230000005587 bubbling Effects 0.000 description 1
- 238000005253 cladding Methods 0.000 description 1
- 239000004020 conductor Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000001747 exhibiting effect Effects 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 229910052757 nitrogen Inorganic materials 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000002285 radioactive effect Effects 0.000 description 1
- 239000002901 radioactive waste Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B09—DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
- B09B—DISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
- B09B1/00—Dumping solid waste
- B09B1/002—Sea dumping
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
-
- G—PHYSICS
- G21—NUCLEAR PHYSICS; NUCLEAR ENGINEERING
- G21F—PROTECTION AGAINST X-RADIATION, GAMMA RADIATION, CORPUSCULAR RADIATION OR PARTICLE BOMBARDMENT; TREATING RADIOACTIVELY CONTAMINATED MATERIAL; DECONTAMINATION ARRANGEMENTS THEREFOR
- G21F9/00—Treating radioactively contaminated material; Decontamination arrangements therefor
- G21F9/28—Treating solids
- G21F9/34—Disposal of solid waste
- G21F9/36—Disposal of solid waste by packaging; by baling
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- High Energy & Nuclear Physics (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Earth Drilling (AREA)
Description
SPECIFICATION
Construction and use of subsea bore holes
Using existing offshore technology it is now possible to drill holes under the seabed many thousands of metres deep. Drilling operations can be conducted from many different types of platform (e.g. semi-submersible marine platform, jack-up rig, jacket, drilling tender etc).
Generally small diameter bore holes (i.e up to about 3 metres) are drilled for use in locating and producing oil and gas from subsea bedreservoirs. Generally the bore holes are cased, either in concrete or steel, in order to contain oil or gas under pressure and in order to prevent collapse of the bore hole.
It is now proposed to construct a large diameter subsea bore hole (e.g. about 10 to 50 metres in diameter) provided with a stable wall by a method which comprises drilling a number of bore holes around the circumference of a ring of large diameter, supplying to the ring bore holes material to locally stabilise the surrounding geologic formations, and forming a central bore hole, or shaft, within the perimeter of the ring by drilling and reaming or by excavation. The ring bore holes and locally stabilized geologic formations form a stable wall of large diameter for the central bore hole shaft.
After construction the central bore hole may be further stabilized by means of a concrete lining.
Methods and means for carrying out the construction of large diameter subsea bore holes will now be described, by way of example only, with reference to the accompanying drawings in which:
Figure 1 shows schematically an offshore piled caisson structure in plan and elevation views;
Figure 2 shows schematically an offshore caisson structure having battered piles;
Figure 3 shows an alternative caisson structure;
Figure 4 shows a further alternative caisson structure in plan and elevation views;
Figure 5 (A-L) shows schematically a method and means for the construction and use of a large diameter subsea bore hole;
Figure 6 shows a schematic plan view of a ring of small diameter bore holes;
Figure 7 shows a self-supporting riser in place over a large diameter subsea bore hole;
Figures 8A and 8B show schematic crosssections of self-supporting risers; and
Figure 9 shows a jacket in place over a large diameter subsea bore hole.
A first aspect of the invention is described having reference to Figs. 1 to 5.
Fig. 1 illustrates a piled steel caisson structure at an offshore site where the lowest astronomical tide (L.A.T.) provides a water depth of 22m.
The structure comprises two double-skinned caissons; an outer structural caisson 1 and an inner freeze wall caisson 2. The outer caisson 1 extends 25m over LAT and is piled to the seabed by a circumferential ring of piles 3.
The piles 3 are suitably of approximately 2.5m diameter; 20 such piles spaced around the 35m periphery of the illustrated caisson would result in a pile to pile spacing of 5.5m. The piles are preferably stabbed and driven to a depth of about 45m below the mudline by the use of followers and above water hammers (e.g. steam hammers). After driving, the piles may be connected to their enclosing sleeves by cement grout. The outer casing is designed to withstand external wind and wave forces.
It is designed to be connected to water retaining and ground stabilizing means so as to exclude water from the internal space. It is also capable of supporting either a mining module during shaft sinking operations or other operational/maintainance/monitoring modules in use of the completed large diameter bore hole; in order that a deck module may be directly supported at the level of the top of the structural caisson 1 it is preferred that at least some of the piles 3 extend upwardly to the full height of the structural caisson 1.
The inner freeze wall caisson 2 is located within the outer caisson; between the inner and outer caissons there is created an annular space of about 2m gap width. Freeze lines (not shown) for use in freezing pass through the annular space within the walls of the inner caisson 2 and extend downwardly below the mudline through a ring of bored holes. The freeze lines may for example be brine pipes for carrying brine chilled to about -30"C. The annular space within the walls of the inner caisson is filled with a material, such as wet sand, which will freeze to form a rigid wall.
This rigid wall provides a stable transition zone between frozen geologic formations in the seabed below the mudline and any topside units. The height of the freeze wall will preferably be at least that of the highest astronomical tide (HAT). The annular space between the inner and outer caissons may be water filled and in such a case the water may be discouraged from freezing by agitation, e.g. by bubbling air through the water to cause circulation therein.
The freeze wall caisson 2 is designed to be structurally independent of the caisson 1 and this minimises foundation loading close to the freeze wall. In order to ensure stability of the freeze wall caisson, pin piles may be driven through its base into the seabed. The material within the walls of the inner caisson and the geologic formations in the seabed below the mudline are frozen by passing freezing material such as chilled brine through the freeze lines.
Once the inner freeze wall and geologic formations are completely frozen they are maintained in a frozen state with further freezing material whilst the shaft of a large diameter central bore hole is sunk within the space defined by the inner wall of the inner caisson.
The shaft may be sunk to a depth of e.g.
100-500m below the mudline. It is preferable that the central bore hole shaft be provided with a concrete lining 8 for extra stability.
Such a lining can be poured in stages as the shaft is constructed.
In Fig. 2 there is illustrated a caisson structure which is attached to the seabed over geologic formations of clay/sand 4 and chalk 5.
The outer structural caisson 1 is piled by battered piles 3 passing through angled pile guides 6. The caisson may be more difficult to install than the caisson with vertical piles because of the large base diameter of the lower pile guides, but the caisson will have the advantage of exhibiting greater stability, i.e. it will be more stable under impact or extreme storm conditions. As in the caisson structure of Fig. 1, at least some of the piles 3 may extend up to deck height and be loadbeaing.
In Fig. 2 freeze lines 7 are shown extending downwardly through the clay/sand stratum 4 to reach a chalk layer 5. Depending on the surrounding geology it may be necessary to create a frozen wall over only part of the depth of the shaft of the central bore hole; e.g. a lined shaft in a deep chalk stratum may provide a sufficiently stable wall without freezing. For example, soil data for a suitable offshore site might indicate the following deposits: 0-13m silty and sandy clay with gravel
and pebbles; 13-22.5m : fine to medium sand; 22.5-28m : flint gravel; 28-44 : stiff clay; 44-750m : chalk.
Such a site might require a freeze wall to stabilize the surrounding geology to a depth of about 50m below the mudline.
In Fig. 3 there is provided an outer structural caisson 1 piled to the seabed by vertical piles 3. The piles are driven through clay/sand 4 into chalk 5. The caisson 1 is sand filled 10. An inner freeze wall caisson is not provided; instead an annular concrete diaphragm wall 11 is provided to a depth of about 20m below the mudline. The wall 11 is constructed by excavating an annular trench, using material such as bentonite slurry to temporarily support the sides of the trench, and then filling the excavated annulus with concrete. The annular trench may suitably be formed by sequentially cutting adjacent trench sections-for example each section may be about 3m in length, 1 m in width and 60m in depth. Freeze lines 7 are cast into the diaphragm wall 11 and extend downwardly beyond the lower limit of the wall 11.
Whilst a piled steel caisson is currently favoured, it would be possible in an alternative arrangement to use as the outer structural caisson a massive gravity structure fabricated from concrete or steel. Such a structure is shown in Fig. 4, and comprises a wall portion 12 and a base portion 12a. The base size must be large enough to safely transmit dead weight and environmental forces into the seabed. The shaft of a large diameter central bore hole may be constructed within the periphery of the wall 12. Steel skirts (not shown) may extend beneath the base of the gravity structure to improve sliding stability and to lengthen water flow paths (i.e. to improve water cut-off). Freeze lines may, for example, be run with the inner space of the structure or within pipeways in the wall itself.
Fig. 5 (A-L) illustrates the construction and use of a large diameter stabilized subsea bore hole. The following steps are shown:
A) The outer structural caisson 1 and the inner freeze wall caisson 2 are loaded onto a barge 13 and transported to the selected offshore site.
B) The outer caisson 1 is lifted of the barge 13 by a floating crane vessel 14.
C) The outer caisson 1 is lowered and installed on the seabed.
D) Outer piles 3 are stabbed and driven using followers 15 and an above water hammer 16.
E) The inner freeze wall caisson 2 is lifted off the barge 13 by the crane 14 and is installed on the seabed within the outer caisson 1.
F) Inner pin piles 17 are stabbed and driven.
Installation of both caissons is completed by grouting of the piles 3, 17.
G) Freeze walls for carrying freeze lines 7 are constructed by drilling a ring of bore holes within the annular space within the walls of the caisson. Drilling is carried out from a jackup rig 19-alternatively a portable drilling derrick may be mounted over the caisson structure. Freezing of the caisson freeze-wall and the subsoil geology is carried out by pumping chilled brine through the freeze lines to the freeze wells.
H) A deck module 20 and a mining headgear module 21 are loaded onto a barge 13 and transported to the site.
I) The deck module 20 is installed on the outer structural caisson, and is supported by upwardly extended piles 3.
J) The mining headgear module 21 is installed.
K) A jack-up rig 19 installs a span bridge 22 to allow serving of the mining operations.
A large diameter bore hole shaft is excavated to the desired depth below the mudline. The shaft is concrete-cased as it is constructed.
Spoil from the excavation may either be dumped locally or it may be loaded onto suitable vessels and transported away. After completion of the excavation the deck and mining modules are removed, one or more waste objects for disposal are placed in the central bore hole, and the bore hole is backfilled.
L) Once the hole has been filled a module 23 (comprising for example monitoring equipment, maintenance facilities, and emergency personnel shelter and a helideck) is transported to the site and installed on the caisson structure. Since a greater freezing capacity is required to initially freeze the geology than is required to maintain it frozen, it is contemplated that at least some of the ring bore holes of the freeze wells may be used to house down-hole monitoring equipment such as seismographic and radiological survey equipment, temperature and pressure sensors etc.
A second aspect of the invention is described having reference to Figs. 6 to 9.
As shown in Fig. 6 a number of small bore holes 31 are drilled around the circumference of a ring. The holes are of conventional size used in the offshore industry. The holes are perforated after completion and a stabilizing material is pumped into the bores so as to locally penetrate and "freeze" the surrounding areas 32. The material may, for example, be liquid nitrogen or may be a cementatious material or a combination of materials. The effect of the ring of bores is to create a stable wall 33 to hold back the surrounding geologic formations 34. Once the ring wall has been completed the central portions 35 can be bored out and then reamed to the desired large diameter 36.The reaming technique will depend on the geology, but for example, the reaming may be carried out by scraper blades mounted on a conventional drill string or may be carried out by blasting the inside of the bore with a fluid cutting medium expelled under great pressure from a nozzle in a rotating cutter head.
Fig. 7 illustrates a jack-up rig 37 working over a self-supporting riser 38 which is piled (by piles 39 through base 44) to the seabed 40. As shown in plan view in Fig. 8a the selfsupporting riser 38 comprises a central riser body 41 surrounded by a number of drill conductors 42 for guiding a drill string 43 during drilling of the ring of bore holes 31. Clearly, as an alternative, the drill guides could be surrounded by the riser body 41 as shown in
Fig. 8b. The riser 38 is supported on the base 44 by bracing members 4. In Fig. 7 a jack-up rig 37 is shown using a skidded drilling derrick 46 to work over the riser 38; the work over could equally be carried out by another type of platform such as a semi-submersible marine platform, a drilling tender or the like.
It is preferred that the riser and base be shipped to the drill site as an integral unit.
However, an alternative arrangement is possible in which a template having a ring of drill guides is piled to the seabed, the ring of bore holes is drilled through the template and subsequently a riser (without peripheral drill guides) is swaged on to the template.
When the riser is in position on the seabed it will be sealed at the bottom end (e.g. by trenching or grouting) and supplied inside with drilling mud etc. in the normal way.
In deep water a self-supporting riser may not be sufficiently robust and it may be preferred to install a jacket, as illustrated in Fig.
9. A template 47 with drill guides is piled 39 to the seabed 40 and a jacket 48 is positioned over the template. A drilling derrick 49 can be used to work over the template to bore the required holes 31. Once the ring of bores has been drilled and the geologic formations locally frozen the central bore can be drilled and reamed as previously described.
Large diameter subsea bore holes have not previously been drilled. In the offshore oil and gas industry it is usual to drill small diameter bore holes and to case them with rigid casing sections. Until now there has been no call for subsea bore holes for purposes other than those of the offshore oil and gas industry.
It is presently contemplated that a large diameter subsea bore hole of the type described above could be used for the safe emplacement and disposal beneath the seabed of a large waste object such as the shielded reactor core of a decommissioned nuclear submarine.
Depending on the depth of the hole, one or more reactor cores could be entombed in each hole.
When a reactor reaches the end of its useful life it is usual to dismantle it, by removal of the protective shielding and cladding and subsequent removal of radioactive core parts.
Such dismantling is expensive and can be dangerous. Reactor cores are always well shielded and strongly constructed and hence it is proposed to utilise the existing structure of the reactor rather than destroy it. It is more cost effective and safer to dispose of a reactor core as an integral unit rather than in pieces.
In an example of a proposed method of disposal, the decommissioning of a nuclear powered submarine will be considered. The core of such a submarine is typically about 10 to 30 metres in cross section and weighs about 300-800 tonne. When the submarine is to be decommissioned the disposal of radioactive waste from the reactor core poses a problem.
It is proposed that the hull and superstructure of the submarine surrounding the core be cut away leaving an integral shielded unit containing all of the radioactive material. This can be handled more safely than individual brokendown parts of the whole.
It is proposed that a complete reactor core be transported to a suitable offshore site where it is placed at the bottom of a large diameter subsea hole (of the type constructed as described above) and then sealed off from the environment e.g. by back filling the bore hole with cementatious material. Clearly, a waste product of this kind which contains radioactive material is disposed of much more safely and surely by retaining its existing protective shielding, and sealing it in cement deep below the seabed, than by breaking it up into parts and storing or burying the parts on land.
Claims (10)
1. A method of constructing a large diameter subsea bore hole (e.g. about 10 to 50 metres in diameter) provided with a stable wall, which method comprises drilling a number of bore holes around the circumference of a ring of large diameter, supplying to the ring bore holes material to locally stabilise the surrounding geologic formations, and forming a central bore hole, or shaft, within the perimeter of ring by drilling and reaming or by excavation, whereby the ring bore holes and locally stabilised geologic formations form a stable wall of large diameter for the central bore hole shaft.
2. A method according to claim 1, in which the material supplied to the ring bore holes to locally stabilise the surrounding geologic formations comprises brine at about -300C.
3. A method according to claim 1, in which a self supporting caisson structure is provided which has an internal space from which external water may be excluded and through which ring bore holes and a central bore hole may be formed.
4. A method according to claim 3, in which the caisson structure is piled to the sea bed by battered piles passing through angled pile guides.
5. A method according to claim 1, wherein a caisson structure is provided which comprises two double-skinned caissons; an outer structural caisson being designed to withstand external wind and wave forces and to exclude external water and an inner caisson within the parameter of the outer caisson and spaced radially therefrom, the annular space within the walls of the inner caisson carrying means for supplying the ring bore holes with material to locally stabilise the surrounding geologic formations and which annular space is also filled with a material which can form a rigid wall.
6. A self supporting caisson structure for use in a method according to claim 1, which comprises a piled steel caisson structure having a double-skinned outer structural caisson and a structurally independent doubie-skinned inner caisson radially spaced therefrom.
7. A method of disposing of a waste object which comprises constructing a large diameter subsea bore hole by the method defined in claim 1, emplacing one or more waste objects in the bore hole, and back-filling the bore hole to seal it.
8. A method according to claim 7 in which the or each waste object contains radioactive material.
9. A method according to claim 7 in which the or each waste object is a shielded unit containing radioactive material from a nuclear reactor core.
10. A method according to claim 7 in which the or each waste object is an integral shielded unit containing the radioactive material from the reactor core of a nuclear powered submarine.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB8705864A GB2187775B (en) | 1986-03-12 | 1987-03-12 | Construction and use of subsea bore holes |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB868606168A GB8606168D0 (en) | 1986-03-12 | 1986-03-12 | Subsea bore holes |
GB868621281A GB8621281D0 (en) | 1986-09-03 | 1986-09-03 | Bore holes |
GB8705864A GB2187775B (en) | 1986-03-12 | 1987-03-12 | Construction and use of subsea bore holes |
Publications (3)
Publication Number | Publication Date |
---|---|
GB8705864D0 GB8705864D0 (en) | 1987-04-15 |
GB2187775A true GB2187775A (en) | 1987-09-16 |
GB2187775B GB2187775B (en) | 1989-11-29 |
Family
ID=27262950
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB8705864A Expired GB2187775B (en) | 1986-03-12 | 1987-03-12 | Construction and use of subsea bore holes |
Country Status (1)
Country | Link |
---|---|
GB (1) | GB2187775B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT393524B (en) * | 1988-11-28 | 1991-11-11 | Fritscher Gerhard | Method and apparatus for sealing the walls of shafts, trenches or the like |
GB2244171A (en) * | 1990-05-15 | 1991-11-20 | Nuclear Technology | Waste disposal |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1041455A (en) * | 1963-04-05 | 1966-09-07 | Maurice Mauclet | Improvements in shaft sinking |
GB1096340A (en) * | 1964-12-23 | 1967-12-29 | Gaz De France | Ground reservoir for storing liquified gases |
GB1173590A (en) * | 1967-06-28 | 1969-12-10 | Foraky Ltd | Improvements in Ground Freezing. |
GB1180653A (en) * | 1967-09-15 | 1970-02-11 | Foraky Ltd | Improvements in methods of shielding ground to be excavated |
GB1344654A (en) * | 1970-11-16 | 1974-01-23 | Union Carbide Canada Ltd | Ground freezing by means of liquid nitrogen |
GB2160562A (en) * | 1984-06-22 | 1985-12-24 | Foraky Limited | Ground-freezing method |
-
1987
- 1987-03-12 GB GB8705864A patent/GB2187775B/en not_active Expired
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1041455A (en) * | 1963-04-05 | 1966-09-07 | Maurice Mauclet | Improvements in shaft sinking |
GB1096340A (en) * | 1964-12-23 | 1967-12-29 | Gaz De France | Ground reservoir for storing liquified gases |
GB1173590A (en) * | 1967-06-28 | 1969-12-10 | Foraky Ltd | Improvements in Ground Freezing. |
GB1180653A (en) * | 1967-09-15 | 1970-02-11 | Foraky Ltd | Improvements in methods of shielding ground to be excavated |
GB1344654A (en) * | 1970-11-16 | 1974-01-23 | Union Carbide Canada Ltd | Ground freezing by means of liquid nitrogen |
GB2160562A (en) * | 1984-06-22 | 1985-12-24 | Foraky Limited | Ground-freezing method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT393524B (en) * | 1988-11-28 | 1991-11-11 | Fritscher Gerhard | Method and apparatus for sealing the walls of shafts, trenches or the like |
GB2244171A (en) * | 1990-05-15 | 1991-11-20 | Nuclear Technology | Waste disposal |
GB2244171B (en) * | 1990-05-15 | 1994-05-11 | Nuclear Technology | Waste disposal |
Also Published As
Publication number | Publication date |
---|---|
GB2187775B (en) | 1989-11-29 |
GB8705864D0 (en) | 1987-04-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4815894A (en) | Construction and use of subsea bore holes | |
US4055224A (en) | Method for forming an underground cavity | |
US3380256A (en) | Underwater drilling installation and method of construction | |
BE1020365A4 (en) | DEVICE AND METHOD FOR DRILLING SHAFTES IN A SURFACE MADE OF ROCK, CLAY AND / OR RELATED MATERIALS. | |
GB2511520A (en) | Methods for construction and completion of underwater tunnels | |
CN104762942B (en) | Fixed platform soft soil foundation seabed, aquatic building ocean fixed installation construction method | |
US3998061A (en) | Formation of cavities in the bed of a sheet of water | |
US3091937A (en) | Underwater foundation structure and method therefor | |
US2850271A (en) | Method of mining sulfur located underneath bodies of water | |
GB2187775A (en) | Construction and use of subsea bore holes | |
US3830068A (en) | System for earth penetration in deep water at atmospheric pressure | |
Haswell | Thames Cable Tunnel. | |
JP2526333B2 (en) | How to build a vertical shaft | |
CN214170540U (en) | Suspension sinking shaft structure | |
JPH0754076B2 (en) | Excavation method for subsea foundation pile construction | |
US3670813A (en) | Pontoon structures in man-made lake for arctic operations | |
CN214365979U (en) | Wellhead protection device for underwater large-diameter steel cylinder open caisson | |
JPS6213449B2 (en) | ||
Cashman et al. | Groundwater Control for Tunnelling Projects | |
JP2526335B2 (en) | How to build a vertical shaft | |
WO2002063106A1 (en) | A method for installing submerged oil and gas wells, and apparatus for the same | |
Anderson | Secant piles support access shafts for tunnel crossing in difficult geologic conditions | |
RU2149249C1 (en) | Underwater drilling device | |
JP2004003229A (en) | Method for constructing vertical shaft | |
CN114370230A (en) | Pretreatment method for vertical jacking water taking and discharging pipe in rock stratum |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PCNP | Patent ceased through non-payment of renewal fee |
Effective date: 19960312 |