FR2732375A1 - Repairing and realigning device for damaged upper sections of sheet piling along keys, riverbanks or platforms - Google Patents

Repairing and realigning device for damaged upper sections of sheet piling along keys, riverbanks or platforms Download PDF

Info

Publication number
FR2732375A1
FR2732375A1 FR9504058A FR9504058A FR2732375A1 FR 2732375 A1 FR2732375 A1 FR 2732375A1 FR 9504058 A FR9504058 A FR 9504058A FR 9504058 A FR9504058 A FR 9504058A FR 2732375 A1 FR2732375 A1 FR 2732375A1
Authority
FR
France
Prior art keywords
elements
sections
curtain
sheet piling
platforms
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
FR9504058A
Other languages
French (fr)
Other versions
FR2732375B1 (en
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MARCHAND ERIC CAMILLE
Original Assignee
MARCHAND ERIC CAMILLE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MARCHAND ERIC CAMILLE filed Critical MARCHAND ERIC CAMILLE
Priority to FR9504058A priority Critical patent/FR2732375B1/en
Publication of FR2732375A1 publication Critical patent/FR2732375A1/en
Application granted granted Critical
Publication of FR2732375B1 publication Critical patent/FR2732375B1/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Revetment (AREA)

Abstract

The device has prefabricated sections (B) which may also be made on site, which rest on the on the external edge of the upper sections of the sheet piling. These lower sections (B) form a base for self supporting sections (C) which form a vertical wall supporting the upper section of the embankment. The force resulting from the pressure exerted by the sections (B) on the external face of the sheet piling is taken up by existing or new anchor points. The prefabricated sections (B) support the sections (C) so that they can be levelled and aligned. If the B component does not have a horizontal flange an adjustment zone (b) allows the self supporting sections to be aligned.

Description

La présente invention a pour objet des procédé3, des ouvrages pour permettre le réaménagement et la correction de l'alignement des berges, des rives, des quais ou des plates-formes aménagés par un rideau de palplanches tout en renforçant et en redressant la partie sommitale de ce dernier. The present invention relates to process3, works to allow the redevelopment and correction of the alignment of the banks, banks, quays or platforms arranged by a sheet pile wall while strengthening and straightening the top part of the last.

Les aménagements de quais, berges, rives en milieu terrestre ou aquatique sont couramment constitués de rideaux de palplanches. Quays, banks, banks in terrestrial or aquatic environments are commonly made of sheet pile walls.

Dans le temps, la partie supérieure de ces rideaux de palplanches a tendance à se corroder, à bouger voire à s'affaisser. Over time, the upper part of these sheet piling tends to corrode, move or even collapse.

Dans ce genre de situation, la pratique courante consiste au renforcement du rideau par l'ajout d'un second rideau de palplanches de renforcement, ou carrément au remplacement des palplanches du rideau initial. In this type of situation, the current practice consists in reinforcing the curtain by adding a second curtain of reinforcing sheet piles, or outright replacing the sheet piles of the initial curtain.

La présente invention a l'avantage de ne pas déstabiliser la partie amont des remblais par l'enlèvement des palplanches supports, ou la réduction de gabarit par la juxtaposition d'un deuxième rideau. The present invention has the advantage of not destabilizing the upstream part of the embankments by removing the support sheet piles, or reducing the size by juxtaposing a second curtain.

L'objectif de la présente solution est de renforcer le rideau de palplanches existant par des éléments B qui, en reprenant les ancrages antérieurs ou en en créant, vont contribuer à redresser la partie sommitale du susdit rideau et qui peuvent éventuellement servlr de plate-forme de support pour d'autres éléments C. The objective of the present solution is to reinforce the existing sheet pile curtain with elements B which, by taking up the previous anchors or by creating them, will contribute to straightening the top part of the above-mentioned curtain and which may possibly serve as a platform support for other C elements.

Ces derniers éléments C, autoporteurs ou autostables servent à la reconstitution d'un tracé lissé, uniforme, homogène et esthétique de la partie supérieure visible de la berge, de la rive ou du quai.These latter self-supporting or freestanding elements C serve to reconstruct a smooth, uniform, homogeneous and aesthetic layout of the visible upper part of the bank, the shore or the quay.

Un ouvrage selon l'invention pour renforcer et redresser la partie supérieure d'un rideau de palplanches tout en permettant un réaménagement et un réalignement esthétique des berges est composé d'une rangée d'éléments fabriqués en place ou préfabriqués (en béton armé, en bois imputrescible ou non, en métal ou autre alliage, ou en toute autre matière...), qui servent à redresser la partie sommitale du rideau de palplanches en exerçant une pression sur la face externe de la partie supérieure des palplanches, effort qui est repris soit par les ancrages antérieurs du rideau, soit par la création de nouveaux points d'accrochage par quelle que méthode que ce soit. A structure according to the invention for reinforcing and straightening the upper part of a sheet pile wall while allowing a redevelopment and an aesthetic realignment of the banks is composed of a row of elements manufactured in place or prefabricated (in reinforced concrete, in rot-proof wood or not, metal or other alloy, or any other material ...), which are used to straighten the top part of the sheet pile wall by exerting pressure on the external face of the upper part of the sheet pile, effort which is taken up either by the previous anchors of the curtain, or by the creation of new attachment points by any method whatsoever.

La figure 1 représente une vue en perspective d'un ouvrage d'art (mur de quai, nve ou berge...) qui comporte un rideau de palplanches A, séparant le quai de l'eau. FIG. 1 represents a perspective view of a work of art (quay wall, new or bank, etc.) which comprises a sheet pile curtain A, separating the quay from the water.

I1 est à noter qu'à la place de l'eau, le rideau de palplanches peut fort bien délimiter deux parties terrestres de niveaux différents. It should be noted that instead of water, the sheet pile curtain can very well demarcate two land parts of different levels.

Un ouvrage selon la présente invention nécessite un terrassement en arrière du rideau de palplanches de façon à aménager une zone de réglage b visible sur la coupe
I-I figures 2 et 3. Cette zone b, dans le cas de la figure 2, sert de zone de support aux éléments constitutifs B. Dans le cas de la figure 3, cette zone b sert directement de support aux éléments constitutifs C.
A structure according to the present invention requires earthwork behind the sheet pile wall so as to provide an adjustment zone b visible on the section
II Figures 2 and 3. This area b, in the case of Figure 2, serves as a support area for the components B. In the case of Figure 3, this area b directly serves as support for the components C.

L'élément B est mis en place après recépage des palplanches du rideau et sectionnement de l'ancrage éventuellement existant sur la longueur correspondante au susdit élément B. Ensuite l'élément B est mis en pression sur la face externe de la partie supérieure du rideau de palplanches, I'effort étant repris soit par le tirant de l'ancrage existant, soit par la création d'un nouveau point d'accrochage (ancrage ou tout autre procédé...). Il est à noter que les éléments B ne doivent pas appuyer sur la partie de tête du rideau de façon à faciliter tout mouvement lors de la mise sous tension et accrochage de ces éléments B. Element B is put in place after cutting the sheet pile of the curtain and sectioning of the anchor possibly existing on the length corresponding to the above-mentioned element B. Then element B is put under pressure on the external face of the upper part of the curtain sheet piling, the effort being taken up either by the tie of the existing anchor, or by the creation of a new attachment point (anchorage or any other process ...). It should be noted that the elements B must not press on the head part of the curtain so as to facilitate any movement during the tensioning and hanging of these elements B.

Pour l'opération du recépage des palplanches, il est conseillé de procéder progressivement et de sectionner les ancrages existants au fur et à mesure de l'avancement des travaux en s'assurant de la mise en pression du rideau et du bon accrochage des éléments B, et ce afin d'éviter tout risque d'affaissement du rideau. For the operation of capping the sheet piles, it is advisable to proceed gradually and to section the existing anchors as the work progresses, ensuring that the curtain is pressurized and that the B elements are properly attached. to avoid any risk of the curtain sagging.

La partie en retour des éléments B sur figure 2, ou à défaut la zone de réglage b de la figure 3 sert de zone de positionnement et de support des éléments constitutifs C qui sont alignés et posés de façon à former une courbe harmonieuse et continue.  The return part of the elements B in FIG. 2, or failing this the adjustment zone b of FIG. 3 serves as a positioning and support zone for the constituent elements C which are aligned and placed so as to form a harmonious and continuous curve.

Ces éléments C, constitutifs du tracé définitif du quai, de la rive ou de la berge, sont autoporteurs ou autostables et servent de paroi verticale au remblai supérieur à l'amont du rideau de palplanches. These elements C, constituting the final layout of the quay, the shore or the bank, are self-supporting or freestanding and serve as a vertical wall for the upper embankment upstream of the sheet pile wall.

Les figures 1, 2 et 3 représentent une symbolisation des éléments constitutifs de la présente solution sans qu'il n'y ait limitation de forme (L, T, I, poutre ...), ni de nature (béton armé coulé en place ou préfabriqué, bois, métal ou autre alliage, ou toute autre matière ...)
Le dispositif selon la présente invention est applicable au domaine des travaux publics et est destiné plus particulièrement à la rectification et au ré alignement du tracé des quais, rives ou berges constitué par un rideau de palplanches limitant deux milieux terrestres de niveau différent, ou un milieu terrestre et un milieu aquatique.
Figures 1, 2 and 3 represent a symbolization of the constituent elements of the present solution without there being any limitation of form (L, T, I, beam ...), or of nature (reinforced concrete poured in place or prefabricated, wood, metal or other alloy, or any other material ...)
The device according to the present invention is applicable to the field of public works and is intended more particularly for the rectification and realignment of the layout of the quays, banks or banks constituted by a sheet pile wall limiting two terrestrial environments of different level, or a medium terrestrial and an aquatic environment.

Claims (4)

- REVENDICATIONS  - CLAIMS 1. Dispositif pour le réaménagement et la rectification du tracé de quais, berges, nves ou plates-formes délimitées par un rideau de palplanches nécessitant un renforcement et un redressement de sa partie sommitale, caractérisé par le fait que l'on construit un ouvrage composé d'éléments fabriqués en place ou préfabriqués B venant appuyer sur la face externe de la partie supérieure du rideau, et par les éléments constitutifs C, autostables ou autoporteurs, paroi verticale de la partie supérieure du remblai à l'amont du rideau. 1. Device for the redevelopment and the rectification of the layout of quays, banks, nves or platforms delimited by a sheet pile wall requiring a reinforcement and a straightening of its top part, characterized by the fact that a composite work is constructed of elements manufactured in place or prefabricated B coming to bear on the external face of the upper part of the curtain, and by the constituent elements C, freestanding or self-supporting, vertical wall of the upper part of the embankment upstream of the curtain. 2. Dispositif selon la revendication 1, caractérisé par le fait que les efforts, dus à la pression exercée par les éléments B sur la face externe de la partie supérieure du rideau, sont repris par les ancrages existants ou par des points d'ancrage à créer. 2. Device according to claim 1, characterized in that the forces, due to the pressure exerted by the elements B on the external face of the upper part of the curtain, are taken up by the existing anchors or by anchor points at create. 3. Dispositif selon les revendications 1 et 2, caractérisé par le fait que les éléments B servent de support de réglage et d'alignement aux éléments C, autostables ou autoporteurs. 3. Device according to claims 1 and 2, characterized in that the elements B serve as an adjustment and alignment support for the elements C, freestanding or self-supporting. 4. Dispositif selon les revendications 1 et 2, caractérisé par le fait qu'en l'absence d'un retour aux éléments B, une zone de réglage b sert de support de réglage et d'alignements aux éléments C, autostables ou autoporteurs.  4. Device according to claims 1 and 2, characterized in that in the absence of a return to the elements B, an adjustment zone b serves as an adjustment support and alignments to the elements C, freestanding or self-supporting.
FR9504058A 1995-03-29 1995-03-29 REPAIRING THE SUMMARY PART OF A PILING CURTAIN Expired - Fee Related FR2732375B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
FR9504058A FR2732375B1 (en) 1995-03-29 1995-03-29 REPAIRING THE SUMMARY PART OF A PILING CURTAIN

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR9504058A FR2732375B1 (en) 1995-03-29 1995-03-29 REPAIRING THE SUMMARY PART OF A PILING CURTAIN

Publications (2)

Publication Number Publication Date
FR2732375A1 true FR2732375A1 (en) 1996-10-04
FR2732375B1 FR2732375B1 (en) 1997-05-16

Family

ID=9477788

Family Applications (1)

Application Number Title Priority Date Filing Date
FR9504058A Expired - Fee Related FR2732375B1 (en) 1995-03-29 1995-03-29 REPAIRING THE SUMMARY PART OF A PILING CURTAIN

Country Status (1)

Country Link
FR (1) FR2732375B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7670087B1 (en) 2005-01-10 2010-03-02 Darryl Scott Burkett Sheet piling wall having facade

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1408069A (en) * 1918-02-09 1922-02-28 Lackawanna Steel Co Composite sheet piling
US1742947A (en) * 1928-02-14 1930-01-07 Victor G Brash Piling for subaqueous constructions
FR801810A (en) * 1936-02-11 1936-08-19 Entpr De Travaux Publics De L Improvement in the construction and encroachment of metal sheet piles and reinforced concrete of quay walls
US4674921A (en) * 1984-05-04 1987-06-23 Berger Lawrence E Seawall
US4917543A (en) * 1988-10-11 1990-04-17 Dayco Products, Inc. Wall system employing extruded panel sections

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1408069A (en) * 1918-02-09 1922-02-28 Lackawanna Steel Co Composite sheet piling
US1742947A (en) * 1928-02-14 1930-01-07 Victor G Brash Piling for subaqueous constructions
FR801810A (en) * 1936-02-11 1936-08-19 Entpr De Travaux Publics De L Improvement in the construction and encroachment of metal sheet piles and reinforced concrete of quay walls
US4674921A (en) * 1984-05-04 1987-06-23 Berger Lawrence E Seawall
US4917543A (en) * 1988-10-11 1990-04-17 Dayco Products, Inc. Wall system employing extruded panel sections

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7670087B1 (en) 2005-01-10 2010-03-02 Darryl Scott Burkett Sheet piling wall having facade

Also Published As

Publication number Publication date
FR2732375B1 (en) 1997-05-16

Similar Documents

Publication Publication Date Title
US7470093B2 (en) Interlocking seawall construction and installation apparatus
CA1217349A (en) Engineering of reinforced concrete structures, such as tunnels, underpasses and the like, and precast concrete elements used in said engineering processes
JP4433066B2 (en) Wall structure with permanent anchor construction, wall construction method with permanent anchor construction,
JP2004183324A (en) Repair structure and repair construction method for existing pile pier
JP2006233463A (en) Breakwater, repairing/reinforcing structure and construction method of breakwater
JPH07216844A (en) Underwater framed structure and construction method thereof
JP2001107319A (en) Aseismic reinforcing method of pier and aseismic reinforced structure
FR2732375A1 (en) Repairing and realigning device for damaged upper sections of sheet piling along keys, riverbanks or platforms
JP4123058B2 (en) Construction method of wall structure with permanent anchor construction, Wall structure with permanent anchor construction
FR3057286A1 (en) FABRICS FOR SEVERAL USES FOR INCREASING WALL WIDTHS.
JP2003232044A (en) Cofferdam closure method
KR101080943B1 (en) Rahmen bridge construction method using counterfort without abutment parts
FR2789706A1 (en) Propping method and reinforcing pillar for building swimming pool involves supple plate folded and secured with bolts and split tube to form formwork filled with concrete
JP2005097842A (en) Construction method of reinforced soil structure
FR2687711A1 (en) Method for constructing a building, such as an underground shelter, by assembly of prefabricated elements
JPH05118036A (en) Waling material
JP2863440B2 (en) Lining sheet for concrete corrosion protection
FR3036419A1 (en) REINFORCING BEAM FOR WALL FORMWORK OF SWIMMING WALL
JP2003221816A (en) Underwater framed construction and method of construction thereof
US20120117907A1 (en) Apparatus and Method for Casting Concrete Wall Elements
JP7051058B2 (en) Repair method for existing irrigation canals
JP2005139614A (en) Spiral support
JP3612524B2 (en) Septic tank installation and construction method
FR2833029A1 (en) Box for making cavity for upright beam in concrete foundation is made from expanded metal with two opposite holes for transverse bar
KR102016113B1 (en) Connection fixing means of reinforced earth retaining wall structure and construction method of reinforcing earth retaining wall structure using the same

Legal Events

Date Code Title Description
ST Notification of lapse