WORK POINT WITH REINFORCEMENT DEVICE Download PDFInfo
- Publication number
- ES2651193B1 ES2651193B1 ES201630998A ES201630998A ES2651193B1 ES 2651193 B1 ES2651193 B1 ES 2651193B1 ES 201630998 A ES201630998 A ES 201630998A ES 201630998 A ES201630998 A ES 201630998A ES 2651193 B1 ES2651193 B1 ES 2651193B1
- Authority
- ES
- Spain
- Prior art keywords
- strut
- tubular sleeve
- inner tube
- holes
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000002787 reinforcement Effects 0.000 title claims abstract description 30
- 238000010276 construction Methods 0.000 claims abstract description 20
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 6
- 238000009434 installation Methods 0.000 description 3
- 230000001010 compromised effect Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
- E04G25/04—Shores or struts; Chocks telescopic
- E04G25/06—Shores or struts; Chocks telescopic with parts held together by positive means
- E04G25/061—Shores or struts; Chocks telescopic with parts held together by positive means by pins
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
- E04G25/04—Shores or struts; Chocks telescopic
- E04G25/06—Shores or struts; Chocks telescopic with parts held together by positive means
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
- E04G25/04—Shores or struts; Chocks telescopic
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
- E04G25/04—Shores or struts; Chocks telescopic
- E04G25/06—Shores or struts; Chocks telescopic with parts held together by positive means
- E04G25/065—Shores or struts; Chocks telescopic with parts held together by positive means by a threaded nut
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/02—Scaffold feet, e.g. with arrangements for adjustment
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D15/00—Props; Chocks, e.g. made of flexible containers filled with backfilling material
- E21D15/14—Telescopic props
- E21D15/15—Means counteracting entry of dirt; Built-in cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
- E04G25/04—Shores or struts; Chocks telescopic
- E04G2025/042—Shores or struts; Chocks telescopic with devices to avoid accidental disengagement of the telescopic elements, e.g. during transport
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Working Measures On Existing Buildindgs (AREA)
- Orthopedics, Nursing, And Contraception (AREA)
- Tents Or Canopies (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
Puntal de obra con dispositivo de refuerzo.#Puntal de obra que comprende un tubo exterior, un tubo interior y una pieza de fijación de los tubos entre sí, comprendiendo el tubo exterior una tuerca de ajuste en su extremo superior, siendo el tubo interior susceptible de desplazarse por el interior del tubo exterior y comprendiendo dicho tubo interior una pluralidad de parejas de agujeros distribuidos a lo largo de su longitud, estando dichos agujeros dispuestos en posiciones diametralmente opuestas del tubo interior, atravesando dicha pieza de fijación una de las citadas parejas de agujeros del tubo interior para impedir el movimiento relativo entre los tubos exterior e interior, caracterizado por disponer de un dispositivo de refuerzo, comprendiendo dicho dispositivo de refuerzo un manguito tubular susceptible de deslizarse por el exterior del tubo interior del puntal de obra y comprendiendo dicho manguito tubular medios de fijación al puntal de obra.Construction strut with reinforcement device. # Construction strut comprising an outer tube, an inner tube and a fixing piece of the tubes with each other, the outer tube comprising an adjustment nut at its upper end, the inner tube being susceptible of moving through the interior of the outer tube and said inner tube comprising a plurality of pairs of holes distributed along its length, said holes being arranged in diametrically opposite positions of the inner tube, said fixing piece passing through one of said pairs of said holes of the inner tube to prevent relative movement between the outer and inner tubes, characterized by having a reinforcement device, said reinforcing device comprising a tubular sleeve capable of sliding outside the inner tube of the work strut and said sleeve comprising tubular fixing means to the work strut.
Description
Puntal de obra con dispositivo de refuerzo Construction strut with reinforcement device
La presente invención se refiere a un puntal de obra con un dispositivo de refuerzo que proporciona un refuerzo en la resistencia al pandeo del puntal. The present invention relates to a construction strut with a reinforcing device that provides a reinforcement in the buckling resistance of the strut.
Un puntal de obra es un elemento telescópico que se utiliza como soporte temporal de estructuras durante trabajos de construcción o reparación de estructuras o en situaciones en las que existe el riesgo de que una estructura colapse, entre otras aplicaciones. Por ejemplo, los puntales de obra se pueden utilizar para soportar las paredes de un molde de enconfrado hasta que el hormigón se haya endurecido y se puedan retirar las paredes del molde. A construction strut is a telescopic element that is used as a temporary support for structures during construction work or repair of structures or in situations where there is a risk that a structure will collapse, among other applications. For example, construction struts can be used to support the walls of a mold for a concrete until the concrete has hardened and the walls of the mold can be removed.
Habitualmente, un puntal de obra comprende dos tubos telescópicos, es decir, un tubo interior que se puede desplazar por el interior de un tubo exterior y un sistema de fijación de los tubos interior y exterior entre sí. Dicho sistema de fijación consiste habitualmente en una pluralidad de parejas de agujeros distribuidos a lo largo de la longitud del tubo interior dispuestos en posiciones diametralmente opuestas y de una pieza de fijación que atraviesa una de las citados parejas de agujeros para imposibilitar el movimiento relativo entre los tubos exterior e interior. Mediante la pieza de fijación se regula discretamente la extensión del puntal. Para el ajuste fino de la extensión del puntal, el tubo exterior comprende en su extremo superior una tuerca sobre la que queda apoyada la pieza de fijación. Usually, a construction strut comprises two telescopic tubes, that is, an inner tube that can be moved inside an outer tube and a system for fixing the inner and outer tubes to each other. Said fixing system usually consists of a plurality of pairs of holes distributed along the length of the inner tube arranged in diametrically opposite positions and of a fixing piece that passes through one of said pairs of holes to prevent relative movement between the outer and inner tubes. The extension of the strut is discretely regulated by means of the fixing piece. For fine adjustment of the extension of the strut, the outer tube comprises at its upper end a nut on which the fixing piece is supported.
La versatilidad que aporta la longitud regulable permite que los puntales de obra abarquen un gran rango de longitudes, siendo su longitud máxima aquella en la que el tubo interior se ha extraído el máximo del tubo exterior. Sin embargo, cuanto mayor es la longitud del puntal durante su uso, menor es su resistencia al pandeo, existiendo el riesgo de que el puntal colapse y cese de efectuar su función estructural cuando opera con longitudes cercanas a su longitud máxima. Por otro lado, cargas elevadas pueden provocar también el pandeo del puntal aunque su longitud no sea cercana a su longitud máxima. Para garantizar la integridad estructural del puntal de obra en estos casos, la única solución existente consiste en aumentar el número de puntales para repartir la carga que soporta cada puntal. Como resultado, el coste del uso de puntales de obra se incrementa al necesitar un mayor número de puntales de obra y, también, por conllevar un mayor tiempo de instalación y retirada de los mismos. The versatility provided by the adjustable length allows the construction struts to cover a wide range of lengths, its maximum length being that in which the inner tube has been removed the maximum from the outer tube. However, the greater the length of the strut during use, the lower its resistance to buckling, with the risk that the strut collapses and ceases to perform its structural function when it operates with lengths close to its maximum length. On the other hand, high loads can also cause the buckling of the strut even if its length is not close to its maximum length. To guarantee the structural integrity of the work strut in these cases, the only existing solution is to increase the number of struts to distribute the load that supports each strut. As a result, the cost of the use of construction struts is increased by the need for a greater number of construction struts and, also, for a longer installation and removal time.
La presente invención pretende solucionar los problemas anteriormente citados de los puntales de obra. En particular, la presente invención da a conocer un puntal de obra que comprende dos tubos telescópicos, formados por un tubo exterior y un tubo interior, y una pieza de fijación de los tubos exterior e interior entre sí, comprendiendo el tubo exterior una tuerca de ajuste en su extremo superior, siendo el tubo interior susceptible de desplazarse por el interior del tubo exterior y comprendiendo dicho tubo interior una pluralidad de parejas de agujeros distribuidos a lo largo de su longitud, estando los agujeros de dichas parejas de agujeros dispuestos en posiciones diametralmente opuestas del tubo interior, atravesando dicha pieza de fijación una de las citadas parejas de agujeros del tubo interior para impedir el movimiento relativo entre los tubos exterior e interior, caracterizado por disponer de un dispositivo de refuerzo, comprendiendo dicho dispositivo de refuerzo un manguito tubular susceptible de deslizarse por el exterior del tubo interior del puntal de obra y comprendiendo dicho manguito tubular medios de fijación al puntal de obra. The present invention aims to solve the aforementioned problems of work props. In particular, the present invention discloses a construction strut comprising two telescopic tubes, formed by an outer tube and an inner tube, and a fixing piece of the outer and inner tubes with each other, the outer tube comprising a nut of adjustment at its upper end, the inner tube being able to move inside the outer tube and said inner tube comprising a plurality of pairs of holes distributed along its length, the holes of said pairs of holes being arranged in diametrically positions opposite the inner tube, said fixing piece passing through one of said pairs of holes in the inner tube to prevent relative movement between the outer and inner tubes, characterized by having a reinforcing device, said reinforcing device comprising a susceptible tubular sleeve of sliding outside the inner tube of the work strut and understood said tubular sleeve said fixing means to the work strut.
Es también objeto de la presente invención un dispositivo de refuerzo para el citado puntal de obra caracterizado por comprender un manguito tubular susceptible de deslizarse por el exterior del tubo interior del puntal de obra y comprendiendo dicho manguito tubular medios de fijación al puntal de obra. Asimismo, otro objeto de la presente invención es el uso del citado dispositivo de refuerzo en un puntal para obras para reforzar la resistencia al pandeo del puntal. The object of the present invention is also a reinforcement device for said work strut characterized by comprising a tubular sleeve capable of sliding outside the inner tube of the work strut and said tubular sleeve comprising means for fixing to the work strut. Likewise, another object of the present invention is the use of said reinforcement device in a construction strut to reinforce the buckling resistance of the strut.
El puntal de obra objeto de la presente invención presenta una resistencia al pandeo reforzada gracias al dispositivo de refuerzo, aumentando la carga necesaria para que el puntal colapse por pandeo. De esta manera, el puntal de obra objeto de la presente invención garantiza la estabilidad y seguridad de una estructura ante cargas axiales elevadas con un menor número de puntales en comparación con puntales de obra que no comprendan el citado dispositivo de refuerzo. En consecuencia, al requerir menor cantidad de puntales de obra, el tiempo de instalación y retirada de los puntales es menor y su coste más económico. The work strut object of the present invention has a reinforced buckling resistance thanks to the reinforcement device, increasing the load necessary for the strut to collapse by buckling. In this way, the work strut object of the present invention guarantees the stability and safety of a structure against high axial loads with a smaller number of struts compared to work struts that do not comprise said reinforcement device. Consequently, by requiring less amount of construction struts, the installation and removal time of the struts is less and its cost more economical.
Por otro lado, el dispositivo de refuerzo objeto de la presente invención requiere poco tiempo de colocación puesto que simplemente se debe deslizar el manguito tubular por el exterior del tubo interior del puntal y fijarlo al puntal de obra. Además, la longitud del dispositivo de refuerzo permite incluso el transporte del puntal sin la necesidad de extraer dicho dispositivo de refuerzo, por lo que el puntal y su dispositivo se pueden trasportar y almacenar sin separarse, evitando la necesidad de colocar el dispositivo de refuerzo en el puntal antes de cada uso. De todos modos, en el caso de ser necesario, el dispositivo de refuerzo se puede extraer también de forma sencilla y rápida, liberándolo del puntal y deslizándolo por el exterior del tubo interior hacia fuera. On the other hand, the reinforcement device object of the present invention requires little installation time since the tubular sleeve must simply be slid outside the inner tube of the strut and fixed to the work strut. In addition, the length of the reinforcement device even allows the strut to be transported without the need to remove said reinforcement device, whereby the strut and its device can be transported and stored without separating, avoiding the need to place the reinforcement device in the strut before each use. However, if necessary, the reinforcement device can also be removed easily and quickly, releasing it from the strut and sliding it outside the inner tube outwards.
En una realización del puntal de obra objeto de la presente invención, los medios de fijación del manguito tubular al puntal comprenden una pareja de agujeros dispuestos en posiciones diametralmente opuestas del manguito tubular de manera que la pieza de fijación atraviesa la pareja de agujeros del manguito tubular para fijarlo al puntal de obra. De esta manera la pieza de fijación de los tubos interior y exterior entre sí atraviesa también los agujeros del manguito tubular, quedando el manguito tubular fijado al puntal de obra. In an embodiment of the work strut object of the present invention, the fixing means of the tubular sleeve to the strut comprise a pair of holes arranged in diametrically opposite positions of the tubular sleeve so that the fixing piece passes through the pair of holes of the tubular sleeve to fix it to the work strut. In this way, the fixing part of the inner and outer tubes also passes through the holes of the tubular sleeve, the tubular sleeve being fixed to the work post.
De forma opcional, el manguito tubular queda en contacto con la tuerca de ajuste del extremo superior del tubo exterior del puntal. En esta posición el posible movimiento angular entre los tubos interior y exterior del puntal de obra debido a cargas queda minimizado. Optionally, the tubular sleeve is in contact with the adjusting nut of the upper end of the outer tube of the strut. In this position the possible angular movement between the inner and outer tubes of the work strut due to loads is minimized.
Preferentemente, el manguito tubular comprende una aleta perimetral en uno de sus extremos. De esta manera, en caso de que haya contacto entre el manguito tubular y la tuerca de ajuste del tubo exterior del puntal, la superficie de contacto es mayor, de forma que las tensiones y esfuerzos generados son menores. Además, la aleta facilita el manejo manual del dispositivo y ayuda a alinear ambos tubos del puntal. Preferably, the tubular sleeve comprises a perimeter fin at one of its ends. Thus, if there is contact between the tubular sleeve and the adjustment nut of the outer tube of the strut, the contact surface is larger, so that the stresses and stresses generated are lower. In addition, the flap facilitates manual operation of the device and helps align both strut tubes.
Para su mejor comprensión y a título explicativo pero no limitativo, se describe a continuación la presente invención en base a un ejemplo de realización representada en unos dibujos. For the best understanding and by way of explanation but not limitation, the present invention is described below on the basis of an exemplary embodiment represented in drawings.
La figura 1 muestra una vista en perspectiva de una realización de un dispositivo de refuerzo para puntales de obra objeto de la presente invención. Figure 1 shows a perspective view of an embodiment of a reinforcement device for work struts object of the present invention.
La figura 2 muestra una vista en alzado frontal del dispositivo de la figura 1. Figure 2 shows a front elevation view of the device of Figure 1.
La figura 3 muestra una vista en perspectiva de un puntal de obra incorporando un dispositivo de refuerzo según la presente invención. Figure 3 shows a perspective view of a construction strut incorporating a reinforcement device according to the present invention.
La figura 4 muestra una vista en perspectiva ampliada de un detalle de la figura 3 en el que se ha aumentado la zona del puntal de obra en la que se encuentra el dispositivo de refuerzo. Figure 4 shows an enlarged perspective view of a detail of Figure 3 in which the area of the construction strut in which the reinforcement device is located has been enlarged.
La figura 5 muestra una vista en alzado frontal de 5 puntales para obra en diferentes configuraciones de longitud, en la que únicamente los puntales de obra b y c comprenden un dispositivo de refuerzo objeto de la presente invención. Figure 5 shows a front elevation view of 5 construction struts in different length configurations, in which only the construction struts b and c comprise a reinforcement device object of the present invention.
Tal como se observa en las figuras 1 y 2, el dispositivo de refuerzo -1-para puntal de obra objeto de la presente invención consiste en un manguito tubular -10-que comprende en uno de sus extremos una aleta perimetral -11-. Además, el manguito tubular -10-comprende dos agujeros -12-, -12'-dispuestos en posiciones diametralmente opuestas. As can be seen in Figures 1 and 2, the reinforcement device -1-for the work strut object of the present invention consists of a tubular sleeve -10- comprising at one of its ends a perimetral fin -11-. In addition, the tubular sleeve -10- comprises two holes -12-, -12'-arranged in diametrically opposite positions.
Las figuras 3 y 4 muestran un puntal de obra -2-objeto de la presente invención que comprende el dispositivo de refuerzo -1-de las figuras 1 y 2. El puntal -2-comprende un tubo interior -20-y un tubo exterior -21-fijados entre sí a través de una pieza de fijación -22-, presentando el tubo exterior -21-, en su parte superior, una tuerca de ajuste -21'-para la regulación más precisa de la extensión del puntal -2-que dispone de asas -21''-para su manejo manual. Además, el puntal -2-presenta en sus extremos unas piezas planas -23-, -23'-que facilitan el contacto del puntal -2-con las superficies de las estructuras que soporta. Figures 3 and 4 show a work post -2-object of the present invention comprising the reinforcement device -1-of figures 1 and 2. The prop -2- comprises an inner tube -20- and an outer tube -21-fixed to each other through a fixing piece -22-, presenting the outer tube -21-, in its upper part, an adjusting nut -21'-for the most precise regulation of the extension of the strut -2 -which has handles -21 '' - for manual operation. In addition, the strut -2-presents at its ends flat pieces -23-, -23'-which facilitate the contact of the strut -2-with the surfaces of the structures it supports.
Por otro lado, el tubo interior -20-del puntal -2-comprende una pluralidad de parejas de agujeros dispuestos en posiciones diametralmente opuestas, observándose en las figuras 3 y 4 únicamente un agujero -24-de cada pareja de agujeros. On the other hand, the inner tube -20-of the strut -2- comprises a plurality of pairs of holes arranged in diametrically opposite positions, only one hole -24- of each pair of holes being observed in Figures 3 and 4.
El tubo interior -20-del puntal -2-queda introducido en el interior del manguito tubular -10-, quedando dicho manguito tubular -10-apoyado sobre la tuerca de ajuste -21'-del extremo superior del tubo exterior -21-a través de la aleta perimetral -11-. Los agujeros -12-, -12'-del manguito tubular -10-, al estar dispuestos de forma diametralmente opuesta, del mismo modo que las parejas de agujeros -24-del tubo interior -20-del puntal -2-, permiten que la pieza de fijación -22-atraviese tanto los agujeros -24-del tubo interior como los agujeros -12-,-12'-del manguito tubular -10-, consiguiendo así la fijación del manguito tubular -10-al puntal -2-(figuras 3 y 4). The inner tube -20-of the strut -2-is inserted inside the tubular sleeve -10-, said tubular sleeve -10-resting on the adjusting nut -21'-of the upper end of the outer tube -21-a through the perimeter fin -11-. The holes -12-, -12'-of the tubular sleeve -10-, being arranged diametrically opposite, in the same way as the pairs of holes -24-of the inner tube -20-of the strut -2-, allow the fixing piece -22-crosses both the holes -24-of the inner tube and the holes -12 -, - 12'-of the tubular sleeve -10-, thus achieving the fixation of the tubular sleeve -10-to the strut -2- (Figures 3 and 4).
La regulación de las posiciones relativas entre los tubos interior -20-y exterior -21-del puntal -2-permite conseguir un amplio rango de longitudes, tal como muestran las diferentes configuraciones de la figura 5. En configuraciones en las que la longitud del puntal -2-es cercana a su longitud máxima (ver figuras 5a, 5b) la resistencia al pandeo del puntal -2-se ve reducida y aparece el riesgo de colapso. La utilización del dispositivo de refuerzo -1aumenta la resistencia al pandeo del puntal -2-, por lo que el puntal -2-de la figura 5b presenta un riesgo de colapso por pandeo menor que el puntal -2-de la figura 5a. The regulation of the relative positions between the inner -20-and outer -21-tubes of the strut -2-allows to achieve a wide range of lengths, as shown by the different configurations of Figure 5. In configurations in which the length of the strut -2-is close to its maximum length (see figures 5a, 5b) the buckling resistance of strut -2-is reduced and the risk of collapse appears. The use of the reinforcement device -1 increases the buckling resistance of the strut -2-, whereby the strut -2-of Figure 5b presents a risk of collapse due to buckling less than the strut -2-of Figure 5a.
La configuración de la figura 5c corresponde a la posición de menor longitud del puntal -2cuando dispone del dispositivo de refuerzo -1-objeto de la presente invención, mostrando la figura 5d la misma longitud de puntal -2-sin dispositivo de refuerzo -1-Para poder utilizar el puntal -2-en longitudes menores (ver figuras 5e y 5f) se debe extraer el dispositivo de refuerzo -1-, casos en los que no es posible la utilización del dispositivo de refuerzo -1-para aumentar la resistencia al pandeo del puntal -2-debido a que no existe espacio. En estos casos, no obstante, debido a la poca longitud del puntal -2-, la resistencia al pandeo no se ve comprometida, y el uso del dispositivo -1-objeto de la presente invención no suele ser necesario. The configuration of figure 5c corresponds to the position of shorter strut length -2 when it has the reinforcement device -1-object of the present invention, showing figure 5d the same strut length -2-without reinforcement device -1- In order to use the strut -2-in smaller lengths (see figures 5e and 5f), the reinforcement device -1- must be removed, in which cases it is not possible to use the reinforcement device -1- to increase the resistance to buckling of the strut -2-because there is no space. In these cases, however, due to the short length of the strut -2-, the buckling resistance is not compromised, and the use of the device -1-object of the present invention is usually not necessary.
Si bien la invención se ha presentado y descrito con referencia a realizaciones de la misma, se comprenderá que éstas no son limitativas de la invención, por lo que podrían ser variables múltiples detalles constructivos u otros que podrán resultar evidentes para los técnicos del sector después de interpretar la materia que se da a conocer en la presente descripción, reivindicaciones y dibujos. Así pues, todas las variantes y equivalentes quedarán incluidas dentro del alcance de la presente invención si se pueden considerar comprendidas dentro del ámbito más extenso de las siguientes reivindicaciones. Although the invention has been presented and described with reference to embodiments thereof, it will be understood that these are not limiting of the invention, so that multiple constructive or other details that could be evident to the technicians of the sector could be variable after Interpret the subject matter disclosed in the present description, claims and drawings. Thus, all variants and equivalents will be included within the scope of the present invention if they can be considered to be within the broadest scope of the following claims.
Claims (7)
Priority Applications (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ES201630998A ES2651193B1 (en) | 2016-07-21 | 2016-07-21 | WORK POINT WITH REINFORCEMENT DEVICE |
EP17768163.2A EP3489437A1 (en) | 2016-07-21 | 2017-07-20 | Construction post with reinforcement device |
MX2018016256A MX2018016256A (en) | 2016-07-21 | 2017-07-20 | Construction post with reinforcement device. |
PCT/ES2017/070523 WO2018015603A1 (en) | 2016-07-21 | 2017-07-20 | Construction post with reinforcement device |
CONC2018/0013823A CO2018013823A2 (en) | 2016-07-21 | 2018-12-19 | Construction strut with reinforcement device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ES201630998A ES2651193B1 (en) | 2016-07-21 | 2016-07-21 | WORK POINT WITH REINFORCEMENT DEVICE |
Publications (2)
Publication Number | Publication Date |
---|---|
ES2651193A1 ES2651193A1 (en) | 2018-01-24 |
ES2651193B1 true ES2651193B1 (en) | 2018-11-30 |
Family
ID=59887298
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
ES201630998A Active ES2651193B1 (en) | 2016-07-21 | 2016-07-21 | WORK POINT WITH REINFORCEMENT DEVICE |
Country Status (5)
Country | Link |
---|---|
EP (1) | EP3489437A1 (en) |
CO (1) | CO2018013823A2 (en) |
ES (1) | ES2651193B1 (en) |
MX (1) | MX2018016256A (en) |
WO (1) | WO2018015603A1 (en) |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1356174A (en) * | 1964-06-26 | Pin for locking in relation to each other two tubes sliding telescopically one inside the other | ||
FR904545A (en) * | 1944-05-24 | 1945-11-08 | extendable prop, especially for construction work | |
FR1144762A (en) * | 1956-01-24 | 1957-10-17 | tubular prop constituting a lifting cylinder | |
ES361339A1 (en) * | 1968-12-12 | 1970-11-16 | Coal Industry Patens Limited | A deformable support device for a mine ceiling. (Machine-translation by Google Translate, not legally binding) |
FR2323845A1 (en) * | 1975-09-11 | 1977-04-08 | Self Lock Echafaudages | Concrete structure scaffolding form removal - with rotatable cam on sliding units support pin held by lever and lock (NL150377) |
FR2628466A1 (en) * | 1988-03-09 | 1989-09-15 | Rennepont Sa | Adjustable length stay for scaffolding etc. - comprises inner tube moving telescopically on outer shaft, with threaded sleeve for fine adjustment |
ES1028234Y (en) * | 1994-06-07 | 1995-05-16 | Perez Pedro Garcia | DETACHING DEVICE ON TELESCOPIC PROPS FOR WORKS. |
ES2140291B1 (en) * | 1997-04-04 | 2001-02-16 | Ingenieria Encofrados Servi Sl | PERFECTION ON CONSTRUCTION POINTS. |
JP4336273B2 (en) * | 2004-08-27 | 2009-09-30 | 賢司 小林 | Cap for pin receiving nut for temporary construction support |
-
2016
- 2016-07-21 ES ES201630998A patent/ES2651193B1/en active Active
-
2017
- 2017-07-20 WO PCT/ES2017/070523 patent/WO2018015603A1/en unknown
- 2017-07-20 EP EP17768163.2A patent/EP3489437A1/en active Pending
- 2017-07-20 MX MX2018016256A patent/MX2018016256A/en unknown
-
2018
- 2018-12-19 CO CONC2018/0013823A patent/CO2018013823A2/en unknown
Also Published As
Publication number | Publication date |
---|---|
MX2018016256A (en) | 2019-04-15 |
CO2018013823A2 (en) | 2019-01-18 |
WO2018015603A1 (en) | 2018-01-25 |
EP3489437A1 (en) | 2019-05-29 |
ES2651193A1 (en) | 2018-01-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
ES2380466B5 (en) | TELESCOPIC PRESSURE DISTANCER | |
ES2599765T3 (en) | Improvements in the vertical columns of the travelers used in the filming equipment | |
ES2651193B1 (en) | WORK POINT WITH REINFORCEMENT DEVICE | |
ES2921899T1 (en) | High-precision evenly divided sub-reflector device with two-stage posture adjustment function | |
ES2576483T3 (en) | Winding machine | |
ES2876330T3 (en) | Centering clamping device | |
ES2671696T3 (en) | Height adjustment mechanism of an elbow of a folded arm of an awning | |
US11536041B2 (en) | Corner shuttering element for shuttering and deshuttering of inner corners | |
ES2312131T3 (en) | ASSEMBLY OF MOTOR VEHICLE BODY ELEMENTS AND SAID ASSEMBLY PROCEDURE ASSEMBLY ON THE AUTOMOBILE VEHICLE. | |
ES2231036B1 (en) | STRUT. | |
ES2758483T3 (en) | Swivel bearing for height-adjustable steering column | |
ES1144485U (en) | Mechanism of regulation of height of an elbow of a arm folded of awning (Machine-translation by Google Translate, not legally binding) | |
ES2604686A1 (en) | Cutting device. (Machine-translation by Google Translate, not legally binding) | |
ES2595432T3 (en) | Support device for mounting on shower bars | |
ES2553002A1 (en) | Antispam device for topographic tripods (Machine-translation by Google Translate, not legally binding) | |
ES2594344B1 (en) | Device for fixing and securing a formwork structure | |
ES2560036T3 (en) | Mold support system for a machine to form hollow glassware | |
ES2432476B1 (en) | Modular construction system | |
ES2579060B1 (en) | POSITIONING ELEMENT FOR HEAVY PIECES HANDLING SUPPORTS | |
WO2021116515A1 (en) | Safety device for struts | |
ES2593879B1 (en) | SAMPLE SUPPORT DEVICE IN VACUUM ENVIRONMENTS | |
ES2610997B1 (en) | COUPLING PART FOR PROFILES | |
ES2236123T3 (en) | SEPARABLE SUPPORT FOR A TABLE BOARD. | |
WO2016113595A1 (en) | Discharge element for vertical systems for supporting structures | |
ES2852424T3 (en) | Portable stairs |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FG2A | Definitive protection |