ES2434176A1 - Pre-fabricated structural element - Google Patents

Pre-fabricated structural element Download PDF

Info

Publication number
ES2434176A1
ES2434176A1 ES201330822A ES201330822A ES2434176A1 ES 2434176 A1 ES2434176 A1 ES 2434176A1 ES 201330822 A ES201330822 A ES 201330822A ES 201330822 A ES201330822 A ES 201330822A ES 2434176 A1 ES2434176 A1 ES 2434176A1
Authority
ES
Spain
Prior art keywords
bars
structural element
longitudinal
uprights
prefabricated structural
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
ES201330822A
Other languages
Spanish (es)
Other versions
ES2434176B2 (en
Inventor
Javier CASTELLÓN LÓPEZ
Josep Oriol COLOMÉS GENÉ
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Proadveng Ingenieros Consultores S L
PROADVENG INGENIEROS CONSULTORES SL
Original Assignee
Proadveng Ingenieros Consultores S L
PROADVENG INGENIEROS CONSULTORES SL
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Proadveng Ingenieros Consultores S L, PROADVENG INGENIEROS CONSULTORES SL filed Critical Proadveng Ingenieros Consultores S L
Priority to ES201330822A priority Critical patent/ES2434176B2/en
Publication of ES2434176A1 publication Critical patent/ES2434176A1/en
Priority to PCT/ES2014/070320 priority patent/WO2014195542A1/en
Application granted granted Critical
Publication of ES2434176B2 publication Critical patent/ES2434176B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/28Cross-ribbed floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
    • E04C3/293Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
    • E04C3/294Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete of concrete combined with a girder-like structure extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/065Light-weight girders, e.g. with precast parts
    • E04C5/0653Light-weight girders, e.g. with precast parts with precast parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The invention relates to a pre-fabricated structural element comprising a pre-stressed concrete base and at least one vertical bar structure, such that the concrete base comprises a longitudinal active frame and/or a longitudinal and/or transverse passive frame, and the vertical bar structure is formed by a plurality of consecutively arranged posts alternating with another plurality of diagonal members, such that the diagonal members connect the upper and lower part of the consecutive posts, said posts and diagonal members comprising pins on the lower part thereof, which are connected to the concrete base, and there is at least one longitudinal bar in the form of a course on the upper part of the posts and diagonal members, which runs at least partially along the plurality of different posts and diagonal members.

Description

ELEMENTO ESTRUCTURAL PREFABRICADO PREFABRICATED STRUCTURAL ELEMENT

OBJETO DE LA INVENCIÓN OBJECT OF THE INVENTION

La presente solicitud de Patente de Invención tiene por objeto el registro de un elemento estructural prefabricado, que incorpora notables innovaciones y ventajas frente a las técnicas utilizadas hasta el momento. The purpose of the present invention patent application is to register a prefabricated structural element, which incorporates notable innovations and advantages over the techniques used so far.

Más concretamente, la invención propone el desarrollo de un elemento estructural prefabricado, que por su particular disposición, permite facilitar sumamente los trabajos de obtención de una viga final en obra, así como mejorar las condiciones de transporte hasta la propia obra. More specifically, the invention proposes the development of a prefabricated structural element, which, due to its particular arrangement, makes it possible to greatly facilitate the work of obtaining a final beam on site, as well as improving transport conditions to the site itself.

ANTECEDENTES DE LA INVENCIÓN BACKGROUND OF THE INVENTION

Es conocida en el actual estado de la técnica la utilización del hormigón armado como material para la construcción. The use of reinforced concrete as a material for construction is known in the current state of the art.

El hormigón armado es el resultado de la combinación de forma inteligente del hormigón y el acero en base a las características de cada material. El acero, normalmente en forma de barras, se dispone en el interior del hormigón, quedando adherido a este, lo que permite trabajar de forma conjunta a ambos materiales. Para incrementar la adherencia entre estos dos materiales, se pasó en su momento de utilizar barras de acero liso a barras de acero corrugado. Reinforced concrete is the result of the intelligent combination of concrete and steel based on the characteristics of each material. The steel, usually in the form of bars, is arranged inside the concrete, remaining adhered to it, which allows both materials to work together. To increase the adhesion between these two materials, it was passed at the time to use smooth steel bars to corrugated steel bars.

Se trata pues, de un material compuesto, donde la función principal del hormigón es la de soportar tensiones de compresión y la función principal del acero es la de soportar tensiones de tracción, ya que hormigón no resiste bien este último tipo de tensiones, dando lugar a la aparición de fisuras en el mismo. Otras características del hormigón y el acero hacen del hormigón armado un material con grandes virtudes como material de construcción, como puede ser su durabilidad. It is therefore a composite material, where the main function of concrete is to withstand compression stresses and the main function of steel is to withstand tensile stresses, since concrete does not resist this last type of stress well, resulting in to the appearance of fissures in it. Other characteristics of concrete and steel make reinforced concrete a material with great virtues as a construction material, such as its durability.

Con el hormigón armado se puede construir gran tipología de estructuras. No obstante, la aparición de fisuras en el hormigón ante tensiones de tracción, y una limitada resistencia a compresión del hormigón, son factores limitantes para su uso en determinadas estructuras, como pueden ser elementos con grandes luces o sometidos a grandes cargas. With reinforced concrete you can build great typology of structures. However, the appearance of cracks in concrete against tensile stresses, and a limited compressive strength of concrete, are limiting factors for use in certain structures, such as elements with large lights or under heavy loads.

5 Basado en los principios del hormigón armado es conocido también otro tipo de material compuesto, llamado hormigón pretensado. Las estructuras realizadas con elementos de hormigón pretensado generalmente son menos costosas y de mayor durabilidad que las estructuras hechas de acero laminado. Su objetivo es el de resolver las limitaciones que 5 Based on the principles of reinforced concrete, another type of composite material, called prestressed concrete, is also known. Structures made with prestressed concrete elements are generally less expensive and of greater durability than structures made of rolled steel. Its objective is to solve the limitations that

10 presenta el hormigón armado, mediante el uso de hormigones y aceros de alta resistencia. La idea fundamental del hormigón pretensado radica en pretensar o postensar los alambres 10 presents reinforced concrete, through the use of high strength concrete and steels. The fundamental idea of prestressed concrete lies in prestressing or post-tensioning the wires

o cordones de acero de alta resistencia (armadura activa) dispuestos en el interior del hormigón, lo que transmite una compresión al hormigón, alejándolo así de las situaciones de descompresión y fisuración. Además del acero activo, también se emplean barras de acero or high-strength steel cords (active reinforcement) arranged inside the concrete, which transmits a compression to the concrete, thus removing it from decompression and cracking situations. In addition to active steel, steel bars are also used

15 corrugado (armadura pasiva) como en el hormigón armado. 15 corrugated (passive reinforcement) as in reinforced concrete.

Por criterio de notación suele denominarse habitualmente “estructuras de hormigón pretensado” a aquellas estructuras que se construyen con hormigón de alta resistencia, armadura pasiva y armadura activa pretesa o postesa. By notation criteria, structures that are constructed of high-strength concrete, passive reinforcement and active or prestressed active reinforcement are usually referred to as “prestressed concrete structures”.

20 En las armaduras pretesas se sigue el siguiente proceso: tesado de la armadura previo al fraguado del hormigón, transferencia de la fuerza de pretensado y anclaje de la armadura al hormigón de forma continua por adherencia con el hormigón endurecido. En las armaduras postesas se sigue el siguiente proceso: tesado de la armadura posterior al fraguado del 20 In the prestressed reinforcements the following process is followed: testing of the reinforcement prior to setting the concrete, transfer of the prestressing force and anchoring of the reinforcement to the concrete continuously by adhesion with the hardened concrete. In post-tensioned reinforcements the following process is followed: testing of the post-setting reinforcement

25 hormigón, transferencia de la fuerza de pretensado, fijación de los elementos de anclaje de la armadura, y relleno de vainas con material adherente o no adherente. 25 concrete, transfer of the prestressing force, fixing of the anchoring elements of the reinforcement, and filling of sheaths with adherent or non-adherent material.

El hormigón pretensado ha permitido construir estructuras en las que no hubiera sido posible utilizar únicamente hormigón armado. Actualmente, el hormigón pretensado es uno de los 30 materiales de construcción más utilizados, tanto en obra civil e industrial, como en edificación. Prestressed concrete has allowed the construction of structures in which it would not have been possible to use only reinforced concrete. Currently, prestressed concrete is one of the 30 most used construction materials, both in civil and industrial work, and in building.

En las últimas décadas el uso de elementos prefabricados de hormigón pretensado (generalmente con armadura pretesa) se ha impuesto en la construcción de gran tipología 35 de estructuras. Ello se explica por los beneficios que proporciona este tipo de producto, In recent decades the use of precast reinforced concrete elements (usually with prestressed reinforcement) has been imposed on the construction of a large typology of structures. This is explained by the benefits that this type of product provides,

entre los que están: la posibilidad de construir elementos de gran luz que soporten grandes cargas, la industrialización del proceso, la calidad durante la fabricación, la velocidad de producción, la facilidad de transporte y colocación en obra de los elementos, el ahorro de material, la resistencia al fuego, la durabilidad, etc. Among those that are: the possibility of building high-light elements that support large loads, the industrialization of the process, the quality during manufacturing, the speed of production, the ease of transport and placement on site of the elements, the saving of material , fire resistance, durability, etc.

En el campo de los elementos prefabricados pretensados, es muy necesario que la cantidad de material a emplear en el elemento prefabricado sea mínimo, y que éste pueda completarse en una fase posterior en obra, por los enormes beneficios que ello conlleva para la empresa prefabricadora: reducción del tiempo de prefabricación, reducción del material utilizado en la fabricación del prefabricado, reducción de las dimensiones de los moldes, reducción del peso de la pieza prefabricada, lo que repercute directamente en el coste del transporte y el alcance territorial del producto, etc. In the field of prestressed prefabricated elements, it is very necessary that the amount of material to be used in the prefabricated element be minimal, and that this can be completed at a later stage in the work, due to the enormous benefits that this entails for the prefabricated company: reduction of the prefabrication time, reduction of the material used in the manufacture of the prefabrication, reduction of the dimensions of the molds, reduction of the weight of the prefabricated piece, which directly affects the cost of transport and the territorial scope of the product, etc.

También es sumamente útil, dados los beneficios que ello conlleva a la empresa constructora, que por un lado, el elemento prefabricado sea autoportante, y por otro lado, que el elemento prefabricado sea capaz de soportar las cargas que provienen de los trabajos de hormigonado de aquellas partes del elemento que deben ejecutarse en obra, sin necesidad de apuntalar las piezas prefabricadas durante estos trabajos ni disponer estructuras adicionales para conformar encofrados autoportantes. Es necesario comentar que en determinadas actuaciones, es inviable emplear elementos de apuntalamiento o determinadas estructuras auxiliares, como pueden ser en estructuras sobre cauces de ríos, en estructuras sobre carreteras o vías ferroviarias en servicio, etc. It is also extremely useful, given the benefits that this entails to the construction company, which on the one hand, the prefabricated element is self-supporting, and on the other hand, that the prefabricated element is capable of supporting the loads that come from the concrete work of those parts of the element that must be executed on site, without the need to prop up prefabricated parts during these works or provide additional structures to form self-supporting formwork. It is necessary to comment that in certain actions, it is unfeasible to use shoring elements or certain auxiliary structures, such as in structures on riverbeds, in structures on roads or railways in service, etc.

Estas dos cualidades útiles (mínimo material para construir el prefabricado y capacidad autoportante incluyendo los trabajos de hormigonado) son contrapuestas: a menor cantidad de material empleado en la producción del elemento prefabricado, mayor necesidad de apuntalar dicho elemento en obra, puesto que éste no será autoportante, y viceversa. These two useful qualities (minimum material to build the prefabricated and self-supporting capacity including concrete work) are contrasted: the smaller the amount of material used in the production of the prefabricated element, the greater the need to prop up said element in work, since this will not be self-supporting, and vice versa.

Es por ello que actualmente los elementos prefabricados autoportantes para luces y cargas considerables, son aquellos que tienen gran parte de su sección final hormigonada en la fase de prefabricación, puesto que dicha sección requiere unas determinadas propiedades mecánicas que no tendría en otro caso. That is why currently the self-supporting prefabricated elements for lights and considerable loads are those that have a large part of their final section concreted in the prefabrication phase, since said section requires certain mechanical properties that it would not otherwise have.

Concretamente, en el caso de vigas prefabricadas autoportantes (normalmente pretensadas) para luces y cargas considerables, suele procederse a prefabricar prácticamente todo el elemento (a excepción de la capas de compresión). Specifically, in the case of self-supporting prefabricated beams (normally prestressed) for considerable lights and loads, practically the entire element is prefabricated (except for the compression layers).

5 A modo de ejemplo, tenemos las vigas en H invertida (con al menos un nervio para el alma), donde suelen prefabricarse las dos alas y el alma, o bien el ala inferior y el alma; las vigas artesas, donde suele prefabricarse la losa inferior y los dos nervios laterales; las vigas en T invertida, donde suele prefabricarse el ala inferior y el alma; las vigas en T, donde suele prefabricarse el ala superior y el alma; las placas alveolares, donde suele prefabricarse toda 5 As an example, we have the beams in inverted H (with at least one nerve for the soul), where the two wings and the soul are usually prefabricated, or the lower wing and the soul; trough beams, where the lower slab and the two lateral nerves are usually prefabricated; the inverted T-beams, where the lower wing and the soul are usually prefabricated; the T-beams, where the upper wing and the soul are usually prefabricated; alveolar plates, where all prefabricated is usually

10 la placa; etc. 10 the plate; etc.

En todos estos elementos se deja parte de la armadura de acero corrugado de espera que sirve para unir estructuralmente la pieza prefabricada con las partes que se hormigonan posteriormente en obra, con el objetivo de que el elemento terminado trabaje como una In all these elements, part of the waiting corrugated steel reinforcement is left that serves to structurally join the prefabricated piece with the parts that are concreted later in the work, with the aim that the finished element works as a

15 única pieza. Debe destarcarse que esta armadura en espera no tiene ninguna función estructural por sí misma hasta que se hormigona la sección en la obra, momento en el que pasa a trabajar conjuntamente con el hormigón endurecido. 15 single piece. It should be noted that this standby reinforcement does not have any structural function by itself until the section is concreted in the work, at which time it goes to work together with the hardened concrete.

Después de todas las consideraciones explicadas, el problema que por tanto se plantea es After all the considerations explained, the problem that therefore arises is

20 el de diseñar un elemento prefabricado con una sección prefabricada de dimensiones mínimas, sencillo de producir y de peso reducido para facilitar su transporte. El elemento debe ser autoportante y capaz de soportar los trabajos de hormigonado una vez dispuesto en obra, sin necesidad de utilizar elementos auxiliares de apuntalamiento o encofrados autoportantes. 20 to design a prefabricated element with a prefabricated section of minimum dimensions, simple to produce and of reduced weight for easy transport. The element must be self-supporting and capable of supporting concrete work once it has been installed on site, without the need to use auxiliary shoring elements or self-supporting formwork.

25 El elemento debe poder cubrir luces considerables y soportar, durante su vida útil, elevadas cargas de diseño. Estos requerimientos son muy típicos de estructuras para obra civil e industrial (como por ejemplo puentes, etc.), y en algunos casos puntuales, de edificación. 25 The element must be able to cover considerable lights and withstand, during its lifetime, high design loads. These requirements are very typical of structures for civil and industrial works (such as bridges, etc.), and in some specific cases, of building.

30 Actualmente no son conocidos elementos con estas prestaciones. Sí se conocen, no obstante, elementos especialmente empleados en forjados y cubiertas de edificación, de poco canto, y que sólo en algunos casos, bajo determinadas condiciones, son autoportantes para luces reducidas (luces típicas de edificación). Se demuestra que incrementando las dimensiones de estos elementos homotéticamente, para cubrir las luces y cargas previstas 30 Currently there are no known elements with these benefits. However, elements specially used in building slabs and roofs are known, with little edge, and that only in some cases, under certain conditions, are self-supporting for reduced lights (typical building lights). It is shown that by increasing the dimensions of these elements homothetically, to cover the expected lights and loads

35 en el planteamiento del presente diseño, dichos elementos no serían autoportantes y no serían capaces de soportar las cargas de diseño. Esto se debe a varios factores, entre ellos, la geometría de la sección y el pandeo de determinadas barras de acero comprimidas. También existen elementos con un mayor grado de prefabricación que el elemento objeto de la presente invención (con todos los inconvenientes que ello supone), que se han expuesto 35 in the approach of the present design, said elements would not be self-supporting and would not be able to withstand design loads. This is due to several factors, including section geometry and buckling of certain compressed steel bars. There are also elements with a higher degree of prefabrication than the element object of the present invention (with all the drawbacks that this entails), which have been exposed

5 anteriormente, con características similares en cuanto a la propiedad autoportante. 5 above, with similar characteristics in terms of self-supporting property.

La presente invención contribuye a solucionar y solventar la presente problemática, pues aúna, de forma innovadora e inventiva, conceptos de la técnica del hormigón armado y pretensado, y conceptos de la técnica de estructuras metálicas de acero laminado, aplicados The present invention contributes to solve and solve the present problem, since it combines, in an innovative and inventive way, concepts of the technique of reinforced and prestressed concrete, and concepts of the technique of metallic structures of rolled steel, applied

10 sobre barras de acero corrugado. 10 on corrugated steel bars.

DESCRIPCIÓN DE LA INVENCIÓN DESCRIPTION OF THE INVENTION

La presente invención se ha desarrollado con el fin de proporcionar un elemento estructural The present invention has been developed in order to provide a structural element

15 prefabricado, y se caracteriza esencialmente por el hecho de que comprende una base de hormigón pretensada y al menos una estructura vertical de barras, tal que la base de hormigón comprende una armadura activa longitudinal y/o una armadura pasiva longitudinal y/o transversal; tal que la estructura vertical de barras está conformada por una pluralidad de estribos verticales transversales con forma de “U” invertida a modo de montantes dispuestos 15 prefabricated, and is essentially characterized by the fact that it comprises a prestressed concrete base and at least one vertical bar structure, such that the concrete base comprises a longitudinal active reinforcement and / or a longitudinal and / or transverse passive reinforcement; such that the vertical bar structure is formed by a plurality of inverted vertical U-shaped stirrups in the form of uprights arranged

20 consecutivamente, que se alternan con otra pluralidad de estribos inclinados transversales también con forma de “U” invertida a modo de diagonales, más largos que los estribos verticales transversales anteriormente citados, tal que las diagonales unen la parte superior e inferior de los montantes consecutivos, y disponiendo estos montantes y diagonales de unas patillas en su parte inferior abierta en contacto con la base de hormigón estando dichas 20 consecutively, which alternate with another plurality of transverse inclined stirrups also with an inverted "U" shape as diagonals, longer than the aforementioned transverse vertical stirrups, such that the diagonals join the upper and lower part of the consecutive uprights , and arranging these uprights and diagonals of pins in their lower part open in contact with the concrete base being said

25 patillas embebidas en la base de hormigón, y por lo tanto los montantes y diagonales están unidos a la misma base de hormigón, y en la parte superior de los montantes y diagonales están dispuestas al menos una barra longitudinal a modo de cordón que recorre al menos parcialmente la pluralidad de los diferentes montantes y diagonales. 25 pins embedded in the concrete base, and therefore the uprights and diagonals are attached to the same concrete base, and at the top of the uprights and diagonals are arranged at least one longitudinal bar as a cord that runs to the less partially the plurality of the different uprights and diagonals.

30 Preferentemente, en el elemento estructural prefabricado la armadura activa longitudinal y/o la armadura pasiva longitudinal y/o transversal están en el interior de la base de hormigón pretensada. Preferably, in the prefabricated structural element the longitudinal active reinforcement and / or the longitudinal and / or transverse passive reinforcement are inside the prestressed concrete base.

Además de ello, en el elemento estructural prefabricado, las barras integrantes de la 35 estructura vertical, o los alambres o cordones integrantes de la armadura activa longitudinal, o las barras integrantes de la armadura pasiva longitudinal y/o transversal, son metálicas o de aleación. In addition, in the prefabricated structural element, the integral bars of the vertical structure, or the integral wires or cords of the longitudinal active reinforcement, or the integral bars of the longitudinal and / or transverse passive reinforcement, are metallic or alloy .

Por añadidura, en el elemento estructural prefabricado, las barras integrantes de la estructura vertical, o los alambres o cordones integrantes de la armadura activa longitudinal, In addition, in the prefabricated structural element, the integral bars of the vertical structure, or the integral wires or cords of the longitudinal active reinforcement,

o las barras integrantes de la armadura pasiva longitudinal y/o transversal, son de acero. or the integral bars of the longitudinal and / or transverse passive reinforcement are made of steel.

Añadidamente, en el elemento estructural prefabricado, las barras integrantes de la estructura vertical o de la armadura pasiva longitudinal y/o transversal son de acero corrugado, y los alambres o cordones integrantes de la armadura activa longitudinal son de acero de alta resistencia. Additionally, in the prefabricated structural element, the integral bars of the vertical structure or of the longitudinal and / or transverse passive reinforcement are made of corrugated steel, and the integral wires or cords of the longitudinal active reinforcement are made of high strength steel.

Igualmente, en el elemento estructural prefabricado, la estructura vertical dispone de una estructura de barras en forma de cruces de arriostramiento transversales en unos planos verticales y transversales a la base de hormigón y estando dichos planos formados por los estribos verticales transversales con forma de “U” invertida a modo de montantes, y la estructura vertical dispone además de unas barras horizontales transversales que unen las dos barras del montante en los puntos de convergencia de las cruces de arriostramiento transversales. Likewise, in the prefabricated structural element, the vertical structure has a bar structure in the form of transverse bracing crosses in vertical planes and transverse to the concrete base and said planes being formed by the vertical U-shaped stirrups ”Inverted as uprights, and the vertical structure also has horizontal crossbars that connect the two bars of the upright at the convergence points of the cross bracing crossings.

En tal sentido, en el elemento estructural prefabricado, la estructura vertical dispone de unas barras horizontales longitudinales paralelas a la base de hormigón pretensada que recorren al menos parcialmente la longitud de la estructura vertical y que unen cada uno de los puntos de convergencia de las cruces de arriostramiento transversales. In this sense, in the prefabricated structural element, the vertical structure has longitudinal horizontal bars parallel to the prestressed concrete base that cover at least partially the length of the vertical structure and that join each of the points of convergence of the crosses of transverse bracing.

Del mismo modo, en el elemento estructural prefabricado, la estructura vertical dispone de otras cruces de arriostramiento longitudinales al menos entre el primer y segundo montante de los dos extremos de la propia estructura vertical y en unos planos verticales que recorren longitudinalmente la base de hormigón y que contienen los montantes consecutivos. Similarly, in the prefabricated structural element, the vertical structure has other longitudinal bracing crosses at least between the first and second uprights of the two ends of the vertical structure itself and in vertical planes that run longitudinally through the concrete base and which contain the consecutive uprights.

Asimismo, en el elemento estructural prefabricado, las cruces de arriostramiento transversales se componen de unas barras dobladas en zig-zag, con un gancho en su extremo superior y una patilla en su extremo inferior. Also, in the prefabricated structural element, cross bracing crossings are made up of zigzag bent bars, with a hook at its upper end and a pin at its lower end.

Preferentemente, en el elemento estructural prefabricado, las barras dobladas en zig-zag que componen las cruces de arriostramiento transversales presentan un tramo recto en los puntos de doblado, adecuado para una soldadura con otras barras metálicas o de aleación. Preferably, in the prefabricated structural element, the zig-zag bent bars that make up the cross bracing crossings have a straight section at the bending points, suitable for welding with other metal or alloy bars.

Alternativamente, en el elemento estructural prefabricado, las barras horizontales transversales presentan un gancho en cada uno de sus extremos. Alternatively, in the prefabricated structural element, the horizontal crossbars have a hook at each of their ends.

Además de ello, en el elemento estructural prefabricado, las cruces de arriostramiento longitudinales se componen de dos barras dobladas en zig-zag, con una patilla en cada uno de los extremos de las barras. In addition, in the prefabricated structural element, the longitudinal bracing crossings are composed of two zigzag bent bars, with a pin at each end of the bars.

Por añadidura, en el elemento estructural prefabricado, las barras dobladas en zig-zag que componen las cruces de arriostramiento longitudinales presentan un tramo recto en los puntos de doblado, adecuado para una soldadura con otras barras metálicas o de aleación. In addition, in the prefabricated structural element, the zigzag bent bars that make up the longitudinal bracing crossings have a straight section at the bending points, suitable for welding with other metal or alloy bars.

Añadidamente, en el elemento estructural prefabricado, las siguientes barras están Additionally, in the prefabricated structural element, the following bars are

soldadas: − los montantes con las diagonales en su parte superior; − los ganchos de las cruces de arriostramiento transversales con los montantes y/o welded: - the uprights with the diagonals on top; - the hooks of the cross bracing crossings with the uprights and / or

diagonales; − los ganchos de las cruces de arriostramiento transversales con los cordones diagonals; - hooks of cross bracing crossings with cords

superiores; − las diagonales y/o montantes con los cordones superiores; − los tramos rectos en los puntos de doblado de las cruces de arriostramiento superior; - the diagonals and / or uprights with the upper cords; - the straight sections at the bending points of the bracing crossings

transversales con los montantes; − los ganchos de las barras horizontales transversales que unen los puntos de convergencia de las cruces de arriostramiento transversales con los montantes; − las barras horizontales longitudinales que unen los puntos de convergencia de las cruces de arriostramiento transversales con los montantes; − los tramos rectos en los puntos de doblado de las cruces de arriostramiento longitudinales con los montantes. − las patillas superiores de las cruces de arriostramiento longitudinales con los montantes. transversal with the uprights; - the hooks of the horizontal crossbars that connect the points of convergence of the crossbars with the uprights; - the longitudinal horizontal bars that connect the points of convergence of the cross bracing crossings with the uprights; - the straight sections at the bending points of the longitudinal bracing crossings with the uprights. - the upper pins of the longitudinal bracing crossings with the uprights.

Del mismo modo, el elemento estructural prefabricado, comprende una única estructura vertical, o dos estructuras verticales, o tres estructuras verticales, o cuatro estructuras verticales. Similarly, the prefabricated structural element comprises a single vertical structure, or two vertical structures, or three vertical structures, or four vertical structures.

5 Alternativamente, un procedimiento de fabricación de un elemento estructural prefabricado, comprende una colocación de la estructura vertical con las patillas de los montantes y diagonales presentes en la estructura vertical insertadas entre algunas de las armaduras, y con las patillas de las cruces de arriostramiento transversales y longitudinales presentes en la estructura vertical situadas en la región de la futura base de hormigón, y posteriormente 5 Alternatively, a method of manufacturing a prefabricated structural element, comprises placing the vertical structure with the posts of the uprights and diagonals present in the vertical structure inserted between some of the reinforcements, and with the pins of the transverse bracing crosses and longitudinals present in the vertical structure located in the region of the future concrete base, and subsequently

10 un hormigonado de las armaduras. 10 a concreting of the armor.

Añadidamente, en un procedimiento de fabricación de un elemento estructural prefabricado, la elaboración de la estructura vertical y sus uniones se realiza fuera de una pista de tesado, y posteriormente se sitúa la estructura vertical en la pista de tesado. Additionally, in a manufacturing process of a prefabricated structural element, the vertical structure and its joints are made outside a test track, and then the vertical structure is placed on the test track.

De manera alternativa, en un procedimiento de fabricación de un elemento estructural prefabricado, la elaboración de la estructura vertical y sus uniones se realiza total o parcialmente en una pista de tesado. Alternatively, in a manufacturing process of a prefabricated structural element, the development of the vertical structure and its joints is carried out totally or partially on a test track.

20 Además de ello, en un procedimiento de fabricación de un elemento estructural prefabricado, se utiliza un accesorio provisional que sostiene temporalmente a las barras que conforman la estructura vertical para su adecuado montaje, y utilizándose tal que primero se sitúan los cordones superiores sostenidos por el elemento provisional, en los que a su vez, se cuelgan y disponen adecuadamente los montantes y las diagonales, seguidos 20 In addition, in a manufacturing process of a prefabricated structural element, a provisional accessory is used that temporarily supports the bars that make up the vertical structure for proper assembly, and using such that first the upper cords supported by the provisional element, in which, in turn, the uprights and diagonals are hung and arranged properly, followed

25 de las cruces de arriostramiento transversales mediante los ganchos, seguidos de las cruces de arriostramiento longitudinales, seguidos de las barras horizontales transversales mediante los ganchos que atan los puntos de unión de barras, y finalmente las barras horizontales longitudinales, y con posterioridad se sueldan entre sí las barras metálicas o de aleación. 25 of the cross bracing crossings by means of the hooks, followed by the longitudinal bracing crossings, followed by the horizontal crossbars by means of the hooks that tie the bar attachment points, and finally the longitudinal horizontal bars, and subsequently welded between yes the metal or alloy bars.

30 Por añadidura, en un procedimiento de fabricación de un elemento estructural prefabricado, las soldaduras de las barras metálicas o de aleación de la estructura vertical se realizan antes del hormigonado, fraguado y endurecimento de la base de hormigón pretensada, o al menos una de tales soldaduras se realizan posteriormente al hormigonado, fraguado y In addition, in a manufacturing process of a prefabricated structural element, welds of the metal or alloy bars of the vertical structure are made before concreting, setting and hardening of the prestressed concrete base, or at least one of such welds are made after concreting, setting and

35 endurecimento de la base de hormigón pretensada. 35 hardening of the prestressed concrete base.

Preferentemente, en un procedimiento de fabricación de un elemento estructural Preferably, in a method of manufacturing a structural element

prefabricado, un orden de fabricación es el siguiente: − Colocación de la armadura pasiva en una pista de tesado, en caso de requerirse tal armadura. Prefabricated, a production order is as follows: - Placement of the passive reinforcement in a testing track, if such reinforcement is required.

5 − Colocación de la armadura activa en la pista de tesado. − Tesado de la armadura activa. − Colocación y/o montaje de la estructura vertical en la pista de tesado. − Hormigonado y vibrado de la base de hormigón pretensada. − Transferencia del pretensado mediante el corte de la armadura activa. 5 - Placement of the active reinforcement in the test track. - Tested active armor. - Placement and / or assembly of the vertical structure on the test track. - Concreting and vibrating of the prestressed concrete base. - Transfer of prestressing by cutting the active reinforcement.

10 Gracias a la presente invención, se consigue un elemento conformado por un ala inferior de hormigón, en la que normalmente se colocarán armaduras activas y en algunos casos pasivas, que se une a una estructura vertical de barras metálicas o de aleación, que formará parte de la futura alma y ala superior del elemento, disponiendo al menos de un nervio. El 10 Thanks to the present invention, an element formed by a lower concrete wing is achieved, in which active and in some passive reinforcements will normally be placed, which is attached to a vertical structure of metal or alloy bars, which will form part of the future soul and upper wing of the element, having at least one nerve. He

15 alma se hormigonará en obra, al igual que la capa de compresión del ala superior (en caso de disponerse tal capa). The soul will be concreted on site, as will the compression layer of the upper wing (if such a layer is provided).

Este elemento estructural prefabricado trabaja como estructura mixta. Ante cargas verticales descendentes, el ala inferior actúa como cordón traccionado y la estructura vertical de This prefabricated structural element works as a mixed structure. In the face of downward vertical loads, the lower wing acts as a pulled cord and the vertical structure of

20 barras metálicas o de aleación dispone de barras que actúan como diagonales traccionadas, montantes comprimidos y cordones comprimidos. En un caso de inversión de cargas, los elementos cambian sus papeles. 20 metal or alloy bars have bars that act as traction diagonals, compressed uprights and compressed cords. In a case of load inversion, the elements change their roles.

El funcionamiento de este elemento se basa en la geometría elegida para la estructura de The operation of this element is based on the geometry chosen for the structure of

25 barras del alma, que queda unida al ala inferior. La estructura tridimensional contempla unas determinadas uniones entre barras, así como el correcto arriostramiento de las mismas. Esto último evita el pandeo de las barras comprimidas, lo cual es fundamental y supone el núcleo del éxito del presente diseño, ya que permite a este elemento tan sencillo, cubrir grandes luces para construir elementos que pueden soportar gran variedad de cargas 25 bars of the soul, which is attached to the lower wing. The three-dimensional structure contemplates certain joints between bars, as well as the correct bracing of them. The latter avoids the buckling of the compressed bars, which is fundamental and supposes the core of the success of the present design, since it allows this simple element to cover large lights to build elements that can withstand a variety of loads.

30 de diseño. 30 design

Con el elemento estructural prefabricado de la presente invención, se reduce el tiempo de prefabricación, puesto que sólo es necesario hormigonar y pretensar una base de hormigón de poco espesor, lo que asegura un fraguado rápido del hormigón. Otros productos que 35 requieren hormigonar una mayor parte de su sección requieren un mayor intervalo de tiempo With the prefabricated structural element of the present invention, the prefabrication time is reduced, since it is only necessary to concrete and prestress a concrete base of low thickness, which ensures a rapid setting of the concrete. Other products that require concreting a greater part of their section require a longer time interval

de prefabricación, ya que aumenta el tiempo de fraguado y porque es posible que deban hormigonarse las diferentes partes de la sección por fases, pudiendo ser necesario levantar el elemento y transportarlo de una zona a otra de la fábrica para realizar dichos hormigonados. of prefabrication, since the setting time increases and because it is possible that the different parts of the section must be concreted in phases, it may be necessary to lift the element and transport it from one area to another of the factory to perform said concreting.

5 Se reducen notablemente las dimensiones de los moldes de prefabricado respecto a los productos actuales con funciones similares. También se reduce notablemente el peso de la pieza prefabricada respecto a los productos actuales con funciones similares, lo que repercute directamente en el coste del transporte y el alcance territorial del producto, que 5 The dimensions of prefabricated molds are significantly reduced compared to current products with similar functions. The weight of the prefabricated piece is also significantly reduced compared to current products with similar functions, which directly affects the cost of transport and the territorial scope of the product, which

10 depende de dicho coste. 10 depends on that cost.

Prácticamente cualquier empresa de prefabricados es capaz de fabricar este elemento con la maquinaria de que dispone. Asimismo, una empresa constructora también sería capaz de fabricar este elemento. El producto está, por tanto, al alcance de todo el sector. Virtually any prefabricated company is capable of manufacturing this element with the machinery available to it. Likewise, a construction company would also be able to manufacture this element. The product is, therefore, available to the entire sector.

15 Se trata de un elemento resistente al fuego, lo que supone una ventaja a la alternativa de utilizar vigas metálicas y mixtas. 15 It is a fire-resistant element, which is an advantage to the alternative of using metal and mixed beams.

Gracias a la geometría del elemento, éste puede funcionar fácilmente como jácena. Thanks to the geometry of the element, it can easily function as a jacena.

20 El elemento estructural prefabricado de la presente invención está concebido para su uso preferente en obra civil, aunque para un experto en la materia su uso pudiera ser extendido a otros ámbitos. The prefabricated structural element of the present invention is intended for preferential use in civil works, although for a person skilled in the art, its use could be extended to other areas.

25 Otras características y ventajas del elemento estructural prefabricado resultarán evidentes a partir de la descripción de una realización preferida, pero no exclusiva, que se ilustra a modo de ejemplo no limitativo en los dibujos que se acompañan, en los cuales: Other features and advantages of the prefabricated structural element will be apparent from the description of a preferred but not exclusive embodiment, which is illustrated by way of non-limiting example in the accompanying drawings, in which:

BREVE DESCRIPCIÓN DE LOS DIBUJOS BRIEF DESCRIPTION OF THE DRAWINGS

30 Figura 1.- Es una representación esquemática y en perspectiva de un tramo de una modalidad de realización preferida del elemento estructural prefabricado de la invención, donde se observa la base de hormigón pretensada y la estructura vertical. Figura 2.- Es una representación esquemática de una sección transversal de una modalidad Figure 1.- It is a schematic and perspective representation of a section of a preferred embodiment of the prefabricated structural element of the invention, where the prestressed concrete base and the vertical structure are observed. Figure 2.- It is a schematic representation of a cross section of a modality

35 de realización preferida del elemento estructural prefabricado de la invención. 35 preferred embodiment of the prefabricated structural element of the invention.

Figura 3.- Es una representación esquemática de la sección longitudinal de un tramo de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 4.- Es una vista de una representación esquemática de una sección longitudinal de un tramo con el extremo apoyado, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 5.- Es una vista de una representación esquemática de una sección longitudinal de un tramo con arriostramiento en el plano longitudinal, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 6.- Es una vista de un estribo montante, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 7.- Es una vista de un estribo diagonal, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 8.- Es una vista de las barras que conforman las cruces de arriostramiento para el arriostramiento transversal, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 9.- Son unas vistas de la barra horizontal que une las dos barras del montante en los puntos de convergencia de las cruces de arriostramiento, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 10.- Es una vista de las barras que conforman las cruces de arriostramiento para el arriostramiento longitudinal, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 11.- Son unas vistas de las soldaduras en la unión superior entre una diagonal, un montante, un cordón superior y una de las barras que forma parte de una cruz de arriostramiento transversal, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 12.- Es una vista de las soldaduras en los puntos de convergencia de las cruces de arriostramiento transversales, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 13.- Es una vista de las soldaduras en los puntos de convergencia de las cruces de arriostramiento transversales y longitudinales, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 14.- Es una representación esquemática secuencial de una opción de encofrado único para el alma y el ala superior mediante aligeramiento, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figure 3.- It is a schematic representation of the longitudinal section of a section of a preferred embodiment of the prefabricated structural element of the invention. Figure 4.- It is a view of a schematic representation of a longitudinal section of a section with the end supported, of a preferred embodiment of the prefabricated structural element of the invention. Figure 5.- It is a view of a schematic representation of a longitudinal section of a section with bracing in the longitudinal plane, of a preferred embodiment of the prefabricated structural element of the invention. Figure 6.- It is a view of a mounting bracket, of a preferred embodiment of the prefabricated structural element of the invention. Figure 7.- It is a view of a diagonal stirrup, of a preferred embodiment of the prefabricated structural element of the invention. Figure 8.- It is a view of the bars that form the bracing crossings for transverse bracing, of a preferred embodiment of the prefabricated structural element of the invention. Figure 9.- They are views of the horizontal bar that joins the two bars of the upright at the convergence points of the bracing crossings, of a preferred embodiment of the prefabricated structural element of the invention. Figure 10.- It is a view of the bars that make up the bracing crossings for the longitudinal bracing, of a preferred embodiment of the prefabricated structural element of the invention. Figure 11.- They are views of the welds in the upper joint between a diagonal, a post, a top bead and one of the bars that is part of a cross bracing cross, of a preferred embodiment of the prefabricated structural element of the invention. Figure 12.- It is a view of the welds at the points of convergence of the cross bracing crossings, of a preferred embodiment of the prefabricated structural element of the invention. Figure 13.- It is a view of the welds at the points of convergence of the transversal and longitudinal bracing crossings, of a preferred embodiment of the prefabricated structural element of the invention. Figure 14.- It is a sequential schematic representation of a single formwork option for the soul and the upper wing by lightening, of a preferred embodiment of the prefabricated structural element of the invention.

Figura 15.- Es una representación esquemática secuencial de una opción de encofrado de alma y ala superior con enconfrado del alma y enconfrado perdido para el ala superior, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figure 15.- It is a sequential schematic representation of an option of the formwork of the soul and the upper wing with the core of the soul and the shape of the upper wing, of a preferred embodiment of the prefabricated structural element of the invention.

5 Figura 16.- Es una representación esquemática secuencial de una opción de encofrado único para el alma y el ala superior mediante molde curvilíneo, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 17.- Es una vista esquemática de una sección longitudinal de un tramo de un elemento con estribos dobles, de una modalidad de realización preferida del elemento Figure 16.- It is a sequential schematic representation of a single formwork option for the soul and the upper wing by means of a curvilinear mold, of a preferred embodiment of the prefabricated structural element of the invention. Figure 17.- It is a schematic view of a longitudinal section of a section of an element with double stirrups, of a preferred embodiment of the element

10 estructural prefabricado de la invención. Figura 18.-Es una vista esquemática de una sección transversal de un tramo de un elemento estructural prefabricado donde se han aumentado las barras a modo de cordones superiores, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. 10 prefabricated structural of the invention. Figure 18.- It is a schematic view of a cross section of a section of a prefabricated structural element where the bars have been increased as upper cords, of a preferred embodiment of the prefabricated structural element of the invention.

15 Figura 19.- Es una representación esquemática secuencial de un proceso de hormigonado de una sección de un elemento con un alma de dos nervios, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 20.- Es una representación esquemática de una sección transversal y longitudinal de un elemento con un número variable de cruces de arriostramiento transversales y Figure 19.- It is a sequential schematic representation of a concreting process of a section of an element with a two-ribbed soul, of a preferred embodiment of the prefabricated structural element of the invention. Figure 20.- It is a schematic representation of a cross-sectional and longitudinal section of an element with a variable number of cross bracing crossings and

20 longitudinales, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figura 21.- Es una representación esquemática secuencial de un proceso de colocación en obra y hormigonado por fases de la misma hasta tener la viga final, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. 20, of a preferred embodiment of the prefabricated structural element of the invention. Figure 21.- It is a sequential schematic representation of a work placement process and concreted by phases of the same until the final beam is obtained, of a preferred embodiment of the prefabricated structural element of the invention.

25 Figura 22.- Es una vista esquemática secuencial de un posible proceso de construcción de unos nervios transversales, de una modalidad de realización preferida del elemento estructural prefabricado de la invención. Figure 22.- It is a sequential schematic view of a possible construction process of transverse ribs, of a preferred embodiment of the prefabricated structural element of the invention.

DESCRIPCIÓN DE UNA REALIZACIÓN PREFERENTE DESCRIPTION OF A PREFERRED EMBODIMENT

30 Tal y como se muestra en las figuras, el elemento estructural prefabricado, comprende una base de hormigón 1 pretensada y al menos una estructura 2 vertical de barras, tal que la base de hormigón 1 comprende una armadura activa 3 longitudinal y/o una armadura pasiva 4 longitudinal y/o transversal; tal que la estructura 2 de barras está conformada por una 30 As shown in the figures, the prefabricated structural element comprises a prestressed concrete base 1 and at least one vertical bar structure 2, such that the concrete base 1 comprises a longitudinal active reinforcement 3 and / or a reinforcement passive 4 longitudinal and / or transverse; such that the bar structure 2 is formed by a

35 pluralidad de estribos verticales transversales con forma de “U” invertida a modo de 35 plurality of transverse vertical stirrups with an inverted "U" shape as a

montantes 6 dispuestos consecutivamente, que se alternan con otra pluralidad de estribos inclinados transversales también con forma de “U” invertida a modo de diagonales 7, más largos que los estribos verticales transversales anteriormente citados, tal que las diagonales 7 unen la parte superior e inferior de los montantes 6 consecutivos, y disponiendo estos 5 montantes 6 y diagonales 7 de unas patillas 61, 71 en su parte inferior abierta en contacto con la base de hormigón 1 estando dichas patillas 61, 71 embebidas en la base de hormigón 1, y por lo tanto los montantes 6 y diagonales 7 están unidos a la misma base de hormigón 1, y en la parte superior de los montantes 6 y diagonales 7 están dispuestas al menos una barra longitudinal a modo de cordón 5 que recorre al menos parcialmente la pluralidad de los consecutively arranged uprights 6, which alternate with another plurality of transverse inclined stirrups also with an inverted "U" shape as diagonals 7, longer than the aforementioned transverse vertical stirrups, such that diagonals 7 join the upper and lower part of the consecutive uprights 6, and these 5 and 6 diagonal uprights 7 having pins 61, 71 in their lower part open in contact with the concrete base 1 said pins 61, 71 being embedded in the concrete base 1, and by therefore, the 6 and diagonal struts 7 are connected to the same concrete base 1, and at the top of the 6 and diagonal struts 7, at least one longitudinal bar is arranged as a cord 5 that at least partially covers the plurality of the

10 diferentes montantes 6 y diagonales 7. 10 different uprights 6 and diagonals 7.

Tal y como se puede apreciar en la figura 1, el elemento estructural prefabricado de la invención comprende una base de hormigón 1 pretensada inferior y una estructura 2 vertical de barras sensiblemente perpendicular a la citada base de hormigón 1 pretensada, ambas As can be seen in Figure 1, the prefabricated structural element of the invention comprises a lower prestressed concrete base 1 and a vertical bar structure 2 substantially perpendicular to said prestressed concrete base 1, both

15 diferenciadas entre sí. 15 differentiated from each other.

En la realización preferida descrita en las figuras, el elemento estructural prefabricado de la invención presenta una geometría de elemento estructural lineal. In the preferred embodiment described in the figures, the prefabricated structural element of the invention has a linear structural element geometry.

20 En esta modalidad de realización preferida descrita, el hormigón utilizado es hormigón de alta resistencia adecuado para estructuras de hormigón pretensado. In this preferred embodiment described, the concrete used is high strength concrete suitable for prestressed concrete structures.

Se entiende por vertical una dirección sensiblemente perpendicular a la base de hormigón 1 pretensada. Vertical means a direction substantially perpendicular to the prestressed concrete base 1.

25 El elemento estructural prefabricado de la invención es autoportante y es capaz de soportar las cargas derivadas de los trabajos de hormigonado del alma y ala superior de la futura viga, sin necesidad de apuntalamientos ni estructuras adicionales para encofrados autoportantes. The prefabricated structural element of the invention is self-supporting and is capable of supporting the loads derived from the concrete work of the soul and upper wing of the future beam, without the need for shoring or additional structures for self-supporting formwork.

30 En la fase de previga prefabricada, la base de hormigón 1 pretensada y la estructura 2 vertical trabajan de forma conjunta, dando lugar a una estructura mixta. 30 In the precast phase, the prestressed concrete base 1 and the vertical structure 2 work together, resulting in a mixed structure.

Es común en los casos de estructuras mixtas la utilización de barras o perfiles de acero 35 laminado, aunque en esta modalidad de realización preferida se emplean barras de acero corrugado. Es esta estructura mixta la que permite soportar las cargas durante su fase de utilización como previga prefabricada. It is common in the case of mixed structures the use of rolled steel bars or profiles, although in this preferred embodiment corrugated steel bars are used. It is this mixed structure that allows the loads to be supported during their use phase as anticipated.

Por tanto, en esta modalidad de realización preferida descrita, las barras integrantes de la Therefore, in this preferred embodiment described, the integral bars of the

5 estructura 2 vertical y las barras integrantes de la armadura pasiva 4 longitudinal y/o transversal son de acero corrugado, aunque en otras modalidades de realización, pudieran ser utilizados otros tipos de materiales con las prestaciones adecuadas. Asimismo, en esta modalidad de realización preferida descrita, las barras que integran la armadura activa 3 longitudinal son de acero de alta resistencia, aunque en otras modalidades de realización, 5 vertical structure 2 and the integral bars of the longitudinal and / or transverse passive reinforcement 4 are made of corrugated steel, although in other embodiments, other types of materials with the appropriate performance could be used. Also, in this preferred embodiment described, the bars that integrate the longitudinal active reinforcement 3 are made of high strength steel, although in other embodiments,

10 pudieran ser utilizados otros tipos de materiales con las prestaciones adecuadas. 10 other types of materials could be used with adequate performance.

En otras modalidades de realización, las barras integrantes de la estructura 2 vertical, o de la armadura pasiva 4 longitudinal y/o transversal, así como los alambres o cordones de la armadura activa 3 longitudinal, pudieran estar hechas de otros materiales, como por ejemplo In other embodiments, the integral bars of the vertical structure 2, or of the longitudinal and / or transverse passive reinforcement 4, as well as the wires or cords of the longitudinal active reinforcement 3, could be made of other materials, such as for example

15 de tipo sintético, como fibras de carbono, etc., que presentaran unas prestaciones adecuadas. 15 of a synthetic type, such as carbon fibers, etc., that will have adequate performance.

La estructura 2 vertical y tridimensional tiene dos funciones diferenciadas. Durante la fase de previga prefabricada, las barras correctamente soldadas forman parte de la estructura The vertical and three-dimensional structure 2 has two distinct functions. During the prefabricated pre-phase, properly welded bars are part of the structure

20 resistente, capaz de soportar los esfuerzos ocasionados cuando el objeto de la presente invención deba autosoportarse y sea sometido a solicitaciones varias debidas a su transporte, colocación en obra, etc. 20 resistant, capable of withstanding the stresses caused when the object of the present invention must be self-supporting and subject to various solicitations due to its transportation, work placement, etc.

Tras los trabajos de hormigonado de la sección, la estructura 2 vertical pasa a formar parte After concreting the section, the vertical structure 2 becomes part

25 del armado del alma y del ala superior de la futura viga que se configure, contribuyendo a soportar las tensiones generadas por los esfuerzos cortantes, rasantes, torsores, axiles, y momentos flectores generados por las cargas de diseño, además de cumplir otras funciones, como controlar la retracción y fluencia, dotar a las partes afectadas de la armadura mínima, limitar la flecha del elemento, etc. 25 of the reinforcement of the soul and the upper wing of the future beam that is configured, contributing to withstand the tensions generated by the shear, flush, torso, axial, and bending moments generated by the design loads, in addition to fulfilling other functions, how to control retraction and creep, provide the affected parts with the minimum reinforcement, limit the arrow of the element, etc.

30 En la figura 1 se pueden apreciar también en el interior de la base de hormigón 1 pretensada unas armaduras activas 3 longitudinales y una armaduras pasivas 4 longitudinales y/o transversales. Las armaduras 3,4 pueden disponerse en la base de hormigón 1 pretensada con diferentes espaciados, homogéneos o no. 30 Figure 1 also shows inside the prestressed concrete base 1 longitudinal active reinforcements 3 and passive longitudinal and / or transverse reinforcements 4. The reinforcements 3,4 can be arranged in the prestressed concrete base 1 with different spacings, homogeneous or not.

En esta modalidad de realización, la armadura activa 3 longitudinal y/o la armadura pasiva 4 longitudinal y/o transversal están en el interior de la base de hormigón 1. In this embodiment, the longitudinal active reinforcement 3 and / or the longitudinal and / or transverse passive reinforcement 4 are inside the concrete base 1.

La base de hormigón 1 pretensada y las armaduras activas 3 y las armaduras pasivas 4 de su interior, conforman el cordón traccionado de la estructura en celosía formada por un elemento estructural prefabricado de la invención. The prestressed concrete base 1 and the active reinforcements 3 and the passive reinforcements 4 of its interior, form the tensioned cord of the lattice structure formed by a prefabricated structural element of the invention.

Las armaduras 3, 4 citadas de la base de hormigón 1 pretensada serán las encargadas de soportar las tensiones generadas por los axiles y momentos flectores ocasionados cuando el objeto de la presente invención deba ser autoportante y sea sometido a diferentes solicitaciones varias, como por ejemplo debidas a su transporte, colocación en obra, etc., además de cumplir otras funciones, como controlar la retracción y fluencia, limitar la flecha del elemento, limitar las tensiones en la sección, etc. The mentioned reinforcements 3, 4 of the prestressed concrete base 1 will be in charge of withstanding the stresses generated by the axial and bending moments caused when the object of the present invention must be self-supporting and is subjected to several different solicitations, such as due to its transport, work placement, etc., in addition to fulfilling other functions, such as controlling retraction and creep, limiting the element's arrow, limiting tensions in the section, etc.

En una determinada longitud desde los extremos de un elemento estructural prefabricado, puede ser necesario incorporar una mayor cantidad de acero bajo el/los nervio/s del alma, para atar la última biela a cortante. In a certain length from the ends of a prefabricated structural element, it may be necessary to incorporate a greater amount of steel under the rib (s) of the soul, to tie the last connecting rod to shear.

En las figuras 1 y 2 también se puede apreciar la estructura 2 vertical formada por barras de acero corrugado. Se pueden diferenciar las barras longitudinales superiores que actúan como cordones 5 comprimidos, que proporcionan el brazo de palanca necesario para soportar, junto con la base de hormigón 1 pretensada y las armaduras 3,4, las tensiones generadas por axiles y momentos flectores en la fase previga prefabricada, a la vez que formarán parte de la armadura del ala superior de la viga una vez configurada y terminada. Figures 1 and 2 also show the vertical structure 2 formed by corrugated steel bars. The upper longitudinal bars that act as compressed cords 5 can be distinguished, which provide the lever arm necessary to support, together with the prestressed concrete base 1 and the reinforcements 3,4, the stresses generated by axial and bending moments in the phase provide prefabricated, while they will be part of the upper wing reinforcement of the beam once configured and finished.

Se pueden apreciar también los estribos que actúan como montantes 6 comprimidos y los estribos que actúan como diagonales 7 traccionadas. Ambos estribos permiten absorber las tensiones generadas por el esfuerzo cortante en la fase de previga prefabricada, y formarán parte de la armadura del alma de la viga una vez terminada. You can also see the stirrups that act as uprights 6 tablets and the stirrups that act as diagonals 7 pulled. Both stirrups allow the tensions generated by the shear stress to be absorbed in the prefabricated pre-fabrication phase, and will be part of the reinforcement of the beam core once finished.

También es posible apreciar cómo se unen estos elementos entre sí. Es precisamente esta geometría en celosía la que dota al elemento estructural prefabricado de la invención de la capacidad para resistir las cargas. It is also possible to appreciate how these elements join together. It is precisely this lattice geometry that gives the prefabricated structural element of the invention the ability to withstand loads.

Tal y como se ha explicado, esta estructura 2 vertical principal y tridimensional de barras de acero corrugado está conformada por unos estribos verticales transversales con forma de “U” invertida (que actúan como montantes 6 comprimidos), que se alternan con otros estribos inclinados transversales más largos también con forma de “U” invertida (que actúan como diagonales 7 traccionadas) que unen la parte superior e inferior de estribos verticales contiguos (constituidos por los montantes 6 comprimidos). As explained, this main and three-dimensional vertical structure 2 of corrugated steel bars is formed by vertical transverse stirrups with an inverted “U” shape (which act as 6 compressed uprights), which alternate with other transverse inclined stirrups longer also with an inverted "U" shape (acting as traction diagonals 7) that join the upper and lower part of adjacent vertical stirrups (consisting of 6 compressed uprights).

Estos estribos disponen de unas patillas 61, 71 en su parte inferior abierta en contacto con la base de hormigón 1 pretensada. Estas patillas 61, 71 (más detalladas en figuras posteriores) quedarán embebidas en el hormigón de la base de hormigón 1 pretensada, y por lo tanto, los estribos quedarán unidos a la misma. These stirrups have pins 61, 71 in their lower part open in contact with the prestressed concrete base 1. These pins 61, 71 (more detailed in subsequent figures) will be embedded in the concrete of the prestressed concrete base 1, and therefore, the stirrups will be attached to it.

En la parte superior de los estribos se disponen dos cordones 5 comprimidos longitudinales de acero corrugado. In the upper part of the stirrups there are two cords 5 longitudinal tablets of corrugated steel.

En caso de existir una inversión de carga, los elementos cambiarán su papel de compresión/tracción. If there is a load inversion, the elements will change their compression / traction role.

Finalmente, es posible visualizar el resto de barras de acero corrugado, cuya finalidad es la de arriostrar las diferentes barras comprimidas, lo cual es fundamental para el correcto funcionamiento de la estructura, y en ello radica gran parte de la innovación e inventiva de la presente invención. Finally, it is possible to visualize the rest of corrugated steel bars, whose purpose is to brac the different compressed bars, which is fundamental for the proper functioning of the structure, and in this lies much of the innovation and inventiveness of the present invention.

Para arriostrar los montantes 6 en los planos transversal y longitudinal perpendiculares a la base de hormigón 1 pretensada, se disponen, además de los elementos citados, unas cruces de arriostramiento transversales 8, unas barras horizontales transversales 9, unas barras horizontales longitudinales 10, y unas cruces de arriostramiento 11 longitudinales que se describirán en posteriores figuras. In order to brace the uprights 6 in the transverse and longitudinal planes perpendicular to the prestressed concrete base 1, in addition to the aforementioned elements, transverse bracing crossings 8, horizontal transverse bars 9, longitudinal horizontal bars 10, and some are arranged 11 longitudinal bracing crosses that will be described in later figures.

Las cruces de arriostramiento mencionadas en la presente memoria, también son conocidas habitualmente como cruces de San Andrés. The bracing crosses mentioned herein are also commonly known as San Andres crosses.

Para arriostrar los cordones 5 comprimidos en el plano horizontal y en el plano vertical longitudinal perpendicular a la base de hormigón 1 pretensada, se utilizan los montantes 6, las diagonales 7, las cruces de arriostramiento transversales 8 y las barras horizontales transversales 9. To brace the compressed cords 5 in the horizontal plane and in the longitudinal vertical plane perpendicular to the prestressed concrete base 1, the uprights 6, the diagonals 7, the cross bracing crossings 8 and the horizontal crossbars 9 are used.

La geometría adoptada para la estructura optimiza la cantidad de acero corrugado a utilizar The geometry adopted for the structure optimizes the amount of corrugated steel to use

5 tanto en la fase de previga prefabricada (estructura 2 vertical formando parte de una celosía) como en la fase de futura viga configurada (estructura 2 vertical como armado interior de la futura viga configurada). 5 both in the prefabricated pre-phase (vertical structure 2 forming part of a lattice) and in the future configured beam phase (vertical structure 2 as internal reinforcement of the future configured beam).

En la figura 2 se aprecian con más detalles los diferentes elementos citados anteriormente. The different elements mentioned above can be seen in more detail in Figure 2.

10 Adicionalmente se observan los ganchos 81 de unión de las barras que conforman las cruces de arriostramiento 8 transversales con los cordones 5 superiores comprimidos, las dos pequeñas patillas 82 inferiores, así como las patillas 61 de la parte inferior de los montantes 6. Las diagonales 7 poseen las mismas patillas 71 que los montantes 6. 10 Additionally, the connecting hooks 81 of the bars that make up the transverse bracing crossings 8 with the compressed upper cords 5, the two small lower pins 82, as well as the pins 61 of the lower part of the uprights 6. are observed. 7 have the same pins 71 as the uprights 6.

15 Es aconsejable que las patillas 61, 71 de los montantes 6 y diagonales 7 pasen por debajo de alguna de las armaduras activas 3 o armaduras pasivas 4 de la base de hormigón 1 pretensada, tal y como se aprecia en la figura 2, ya que ello mejora notablemente el anclaje de estas barras a la base de hormigón 1 pretensada. 15 It is advisable that the pins 61, 71 of the uprights 6 and diagonals 7 pass under one of the active reinforcements 3 or passive reinforcements 4 of the prestressed concrete base 1, as shown in Figure 2, since this significantly improves the anchoring of these bars to the prestressed concrete base 1.

20 En la figura 3 se observa una sección longitudinal de un tramo de un elemento estructural prefabricado de la invención propuesta. Se pueden visualizar los elementos citados anteriormente, así como su geometría en sección, observándose de forma clara el mecanismo de funcionamiento estructural de la celosía. En esta figura, las diagonales 7 se inclinan de arriba a abajo de izquierda a derecha entre montantes 6, aunque en el tramo de In Figure 3 a longitudinal section of a section of a prefabricated structural element of the proposed invention is observed. You can visualize the elements mentioned above, as well as their section geometry, clearly observing the mechanism of structural operation of the lattice. In this figure, diagonals 7 are tilted from top to bottom from left to right between uprights 6, although in the section of

25 un elemento prefabricado simétrico a este tramo, las diagonales 7 se dispondrán de forma opuesta, según una simetria axial vertical (de arriba a abajo de derecha a izquierda entre montantes 6). 25 a prefabricated element symmetrical to this section, the diagonals 7 will be arranged opposite, according to a vertical axial symmetry (from top to bottom from right to left between uprights 6).

En base a la geometría adoptada, frente a una solicitación de cargas verticales Based on the geometry adopted, compared to a request for vertical loads

30 descendentes, la base de hormigón 1 pretensada actúa a tracción, los estribos verticales transversales actúan como montantes 6 comprimidos, los estribos inclinados transversales actúan como diagonales 7 traccionadas, y las barras longitudinales superiores actúan como cordones 5 comprimidos. En caso de una inversión de cargas, los papeles de los elementos cambian. Estos son los principales elementos resistentes de la estructura 2 vertical. 30 descending, the prestressed concrete base 1 acts on traction, the vertical transverse stirrups act as compressed uprights 6, the transverse inclined stirrups act as traction diagonals 7, and the upper longitudinal bars act as compressed cords 5. In case of a reversal of charges, the roles of the elements change. These are the main resistant elements of the vertical structure 2.

La base de hormigón 1 pretensada traccionada y los cordones 5 comprimidos aportan un brazo mecánico capaz de soportar las tensiones generadas por los axiles y los momentos flectores, y los montantes 6 y diagonales 7 están dispuestos con una geometría adecuada para soportar las tensiones generadas por los esfuerzos cortantes. The pre-tensioned concrete base 1 pulled and the compressed cords 5 provide a mechanical arm capable of withstanding the stresses generated by the shafts and the bending moments, and the uprights 6 and diagonals 7 are arranged with a suitable geometry to withstand the stresses generated by the shear stresses

Debe asegurarse, no obstante, que ninguna de las barras comprimidas de la estructura pandee, dada la elevada esbeltez de las mismas. Como se ha comentado, esto es fundamental para el correcto funcionamiento de la celosía, y en la solución hallada a este problema radica gran parte de la innovación de la presente invención. It must be ensured, however, that none of the compressed bars of the pandee structure, given their high slenderness. As mentioned, this is essential for the correct functioning of the latticework, and in the solution found to this problem lies much of the innovation of the present invention.

Las barras con especial riesgo de pandeo son los montantes 6 comprimidos y los cordones 5 comprimidos. The bars with special risk of buckling are the 6 compressed uprights and the 5 compressed cords.

Para evitar que los montantes 6 comprimidos pandeen en el plano transversal perpendicular a la base de hormigón 1 pretensada, se dispone, en el plano formado por las dos barras del montante 6, una estructura de barras de acero corrugado en forma de cruces de arriostramiento 8, junto con unas barras horizontales transversales 9 que unen las dos barras del montante 6 en los puntos de convergencia de las cruces de arriostramiento 8. Esta estructura permite fijar los puntos de convergencia de las cruces de arriostramiento 8, logrando una estructura asimilable a un pórtico intraslacional en un plano transversal a un elemento. To prevent the compressed uprights 6 from buckling in the transverse plane perpendicular to the prestressed concrete base 1, a corrugated steel bar structure in the form of bracing crosses 8 is arranged in the plane formed by the two bars of the stud 6 , together with horizontal crossbars 9 that join the two bars of the stud 6 at the convergence points of the bracing crossings 8. This structure allows to fix the convergence points of the bracing crosses 8, achieving a structure similar to a porch intraslational in a transverse plane to an element.

Para evitar que los montantes 6 comprimidos pandeen en los planos longitudinales perpendiculares a la base de hormigón 1 pretensada que contienen a las barras de los montantes 6, se disponen unas nuevas barras horizontales longitudinales 10 de acero corrugado que unen cada uno de los puntos de convergencia de las cruces de arriostramiento 8 situados a la misma cota y lado del montante 6 (estas nuevas barras horizontales longitudinales 10 servirán también de armadura de piel para la sección final de la viga). In order to prevent the compressed uprights 6 from buckling in the longitudinal planes perpendicular to the prestressed concrete base 1 containing the bars of the uprights 6, new longitudinal horizontal bars 10 of corrugated steel are arranged that join each of the convergence points of the bracing crossings 8 located at the same height and side of the stud 6 (these new horizontal horizontal bars 10 will also serve as leather reinforcement for the final section of the beam).

Adicionalmente, se dispone, al menos entre el primer y segundo montante 6 de los dos extremos de un elemento, unas nuevas cruces de arriostramiento 11 longitudinales en los dos planos longitudinales perpendiculares a la base de hormigón 1 pretensada que contienen a las barras de los montantes 6. Gracias a estas nuevas cruces de arriostramiento 11, quedan fijos los puntos de unión entre estas nuevas barras horizontales longitudinales 10 y los montantes 6, logrando que la celosía sea intraslacional en esta dirección. Additionally, at least between the first and second stud 6 of the two ends of an element, there are new longitudinal bracing crossings 11 in the two longitudinal planes perpendicular to the prestressed concrete base 1 containing the stud bars 6. Thanks to these new bracing crossings 11, the junction points between these new longitudinal horizontal bars 10 and the uprights 6 are fixed, making the latticework to be intraslational in this direction.

En la figura 4 se observa uno de los tramos extremos del objeto de la invención. Se pueden observar las cruces de arriostramiento 11 longitudinales. Gracias a estas cruces de arriostramiento 11 longitudinales y a las barras horizontales longitudinales 10, se evita el pandeo de los montantes 6 del elemento estructural prefabricado en los planos longitudinales perpendiculares a la base de hormigón 1 pretensada que pasan por las barras de los montantes 6. Ello se debe a que los montantes 6 junto con los cordones 5 comprimidos y las barras horizontales longitudinales 10 forman pórticos intraslacionales en la dirección longitudinal de estos planos. Figure 4 shows one of the extreme sections of the object of the invention. Longitudinal bracing crosses 11 can be observed. Thanks to these longitudinal bracing crossings 11 and the longitudinal horizontal bars 10, the buckling of the uprights 6 of the prefabricated structural element in the longitudinal planes perpendicular to the prestressed concrete base 1 passing through the bars of the uprights 6. is avoided. it is because the uprights 6 together with the compressed cords 5 and the longitudinal horizontal bars 10 form intraslational porches in the longitudinal direction of these planes.

Tal y como se observa en la figura 5, en algunos casos puede ser necesario disponer un mayor número de cruces de arriostramiento 11 longitudinales entre montantes 6 para rigidificar el conjunto y asegurar el comportamiento intraslacional del mismo en dirección longitudinal. As can be seen in Figure 5, in some cases it may be necessary to arrange a larger number of longitudinal bracing crossings 11 between uprights 6 to stiffen the assembly and ensure its intraslational behavior in the longitudinal direction.

Para evitar que los cordones 5 comprimidos pandeen en el plano horizontal paralelo a la base de hormigón 1 pretensada, se aprovecha la estructura en forma de cruces de arriostramiento 8 transversales descritas anteriormente dispuesta en el plano formado por las dos barras del montante 6. Se limita así la longitud de pandeo en el plano horizontal de los cordones 5 comprimidos, puesto que los montantes 6 se comportan como pórticos intraslacionales en el plano transversal perpendicular a base de hormigón 1 pretensada, fijando, por lo tanto, sus puntos extremos, donde se sitúan los cordones 5 comprimidos. To prevent the compressed cords 5 from panning in the horizontal plane parallel to the prestressed concrete base 1, the structure in the form of cross bracing crossings 8 described above arranged in the plane formed by the two bars of the stud 6 is used. thus, the buckling length in the horizontal plane of the compressed cords 5, since the uprights 6 behave as intraslational porches in the perpendicular transverse plane based on prestressed concrete 1, thus fixing their end points, where they are located the laces 5 tablets.

Para evitar que los cordones 5 comprimidos pandeen en el plano vertical perpendicular a la base de hormigón 1 pretensada, se aprovecha la estructura de montantes 6 y diagonales 7 a los que van unidos estos cordones 5, limitando así la longitud de pandeo de los mismos. To prevent the compressed cords 5 from buckling in the vertical plane perpendicular to the prestressed concrete base 1, the structure of uprights 6 and diagonals 7 to which these cords 5 are attached are used, thus limiting the buckling length thereof.

En la figura 6 puede observarse la geometría de un estribo que actúa como montante 6 de la estructura 2 vertical. Puede verse la patilla 61 inferior de la pieza. En otras modalidades de realización preferidas, es posible adoptar otra tipología de anclaje para unir estas barras de acero corrugado a la base de hormigón 1 pretensada. Figure 6 shows the geometry of a stirrup that acts as an upright 6 of the vertical structure 2. The lower pin 61 of the piece can be seen. In other preferred embodiments, it is possible to adopt another anchor typology to join these corrugated steel bars to the prestressed concrete base 1.

En la figura 7 puede observarse la geometría de un estribo que actúa como una diagonal 7 de la estructura 2 vertical. Puede verse la patilla 71 inferior de la pieza. En otras modalidades de realización preferidas, es posible adoptar otra tipología de anclaje para unir estas barras de acero corrugado a la base de hormigón 1 pretensada. Figure 7 shows the geometry of a stirrup that acts as a diagonal 7 of the vertical structure 2. The lower pin 71 of the piece can be seen. In other preferred embodiments, it is possible to adopt another anchor typology to join these corrugated steel bars to the prestressed concrete base 1.

5 Según se aprecia en la figura 8, las cruces de arriostramiento 8 que se colocan en los planos formados por las dos barras de los montantes 6, se componen de dos barras dobladas en zig-zag, con un gancho 81 en su parte superior para unirse con las barras superiores longitudinales que conforman los cordones 5 comprimidos, y dos pequeñas 5 As shown in Figure 8, the bracing crossings 8 that are placed in the planes formed by the two bars of the uprights 6, are composed of two bars folded in zig-zag, with a hook 81 in their upper part to join with the longitudinal upper bars that make up the 5 compressed cords, and two small

10 patillas 82 en su parte inferior, parte que quedará embebida en la base de hormigón 1 pretensada. En los puntos de doblado de estas cruces de arriostramiento 8 se aconseja dejar un pequeño tramo 83 recto para la correcta soldadura entre barras. En otras modalidades de realización preferidas es posible adoptar otra tipología de anclaje para unir estas barras de acero corrugado a la base de hormigón 1 pretensada. 10 pins 82 in its lower part, part that will be embedded in the prestressed concrete base 1. At the bending points of these bracing crossings 8 it is advisable to leave a small section 83 straight for the correct welding between bars. In other preferred embodiments it is possible to adopt another type of anchoring to join these corrugated steel bars to the prestressed concrete base 1.

15 En la figura 9 pueden observarse las barras horizontales transversales 9 que unen las dos barras de los montantes 6 en los puntos de convergencia de las cruces de arriostramiento 8 transversales. Se pueden apreciar los ganchos 91 en los extremos de la barra para unirlas fácilmente mediante soldaduras al resto de barras. 15 Figure 9 shows the horizontal crossbars 9 that join the two bars of the uprights 6 at the points of convergence of the cross bracing crossings 8. You can see the hooks 91 at the ends of the bar to easily join them by welding to the rest of the bars.

20 En la figura 10 aparecen representadas las cruces de arriostramiento 11 longitudinales que se colocan en los dos planos longitudinales perpendiculares a la base de hormigón 1 pretensada que contienen a las barras de los montantes 6, al menos entre el primer y segundo montante 6 de los dos extremos de un elemento, se componen de dos barras 20 Figure 10 shows the longitudinal bracing crossings 11 that are placed in the two longitudinal planes perpendicular to the prestressed concrete base 1 containing the bars of the uprights 6, at least between the first and second upright 6 of the two ends of an element, are composed of two bars

25 dobladas en zig-zag, con una pequeña patilla 111 en cada uno de sus extremos. En los puntos de doblado de estas cruces de arriostramiento 11 longitudinales se aconseja dejar un pequeño tramo 112 recto para la correcta soldadura entre barras. 25 zig-zag bent, with a small pin 111 at each end. At the bending points of these longitudinal bracing crossings 11, it is advisable to leave a small section 112 straight for proper welding between bars.

En la unión entre las barras, únicamente se efectúa unión con soldadura en las siguientes In the joint between the bars, only welding is carried out in the following

30 barras: los montantes 6 con las diagonales 7 en su parte superior; los ganchos 81 de las cruces de arriostramiento 8 transversales con los montantes 6 y/o diagonales 7; los ganchos 81 de las cruces de arriostramiento 8 transversales con los cordones 5 superiores; las diagonales 7 y/o montantes 6 con los cordones 5 superiores; los pequeños tramos 83 rectos que se aconseja dejar en los puntos de doblado de las cruces de arriostramiento 8 30 bars: the uprights 6 with the diagonals 7 at their top; the hooks 81 of the cross bracing crossings 8 with the 6 and / or diagonal uprights 7; the hooks 81 of the cross bracing crossings 8 with the upper cords 5; diagonals 7 and / or uprights 6 with the upper cords 5; the small 83 straight sections that it is advisable to leave at the bending points of the bracing crossings 8

35 transversales con los montantes 6; los ganchos 91 de las barras horizontales transversales 9 que unen los puntos de convergencia de las cruces de arriostramiento 8 transversales con los montantes 6; las barras horizontales longitudinales 10 que unen los puntos de convergencia de las cruces de arriostramiento 8 transversales con los montantes 6; los tramos rectos 112 que se aconseja dejar en los puntos de doblado de las cruces de 35 transversal with uprights 6; the hooks 91 of the horizontal crossbars 9 that connect the points of convergence of the crossbars 8 with the uprights 6; the longitudinal horizontal bars 10 joining the points of convergence of the cross bracing crossings 8 with the uprights 6; the straight sections 112 that it is advisable to leave at the bending points of the crossings of

5 arriostramiento 11 longitudinales con los montantes 6, las patillas 111 superiores de las cruces de arriostramiento 11 longitudinales con los montantes 6. 5 longitudinal bracing 11 with the uprights 6, the upper pins 111 of the longitudinal bracing crossings 11 with the uprights 6.

En algunos casos, puede ser necesario realizar alguna soldadura adicional entre determinadas barras. Asimismo, en algunos casos puede ser necesario no realizar alguna In some cases, it may be necessary to perform some additional welding between certain bars. Also, in some cases it may be necessary not to perform any

10 de las soldaduras descritas entre determinadas barras. 10 of the welds described between certain bars.

En la figura 11 se pueden ver en mayor detalle las soldaduras 12 de montantes 6, diagonales 7 y cruces de arriostramiento 8 transversales con los cordones 5 superiores comprimidos. Es fundamental la unión entre barras para asegurar el correcto funcionamiento In Figure 11, welds 12 of uprights 6, diagonals 7 and cross bracing crossings 8 with the compressed upper cords 5 can be seen in greater detail. It is essential the connection between bars to ensure proper operation

15 estructural de la celosía. 15 structural lattice.

En la figura 12 se pueden ver en mayor detalle las soldaduras 12 de montantes 6, cruces de arriostramiento 8 transversales, barras horizontales transversales 9, y barra horizontal longitudinal 10. Es fundamental la unión entre barras para asegurar el correcto In Figure 12, welds 12 of uprights 6, cross bracing crossings 8, horizontal crossbars 9, and longitudinal horizontal bar 10 can be seen in greater detail. The joint between bars is essential to ensure correct

20 funcionamiento estructural de la celosía. 20 structural operation of the lattice.

En la figura 13 se pueden ver los detalles de las soldaduras 12 de montantes 6, cruces de arriostramiento 8 transversales, barras horizontales transversales 9, barra horizontal longitudinal 10 y cruces de arriostramiento 11 longitudinales. Es fundamental la unión entre In FIG. 13, details of the welds 12 of uprights 6, cross bracing crossings 8, horizontal crossbars 9, horizontal horizontal bar 10 and longitudinal bracing crossings 11 can be seen. The union between

25 barras para asegurar el correcto funcionamiento estructural de la celosía. 25 bars to ensure the correct structural operation of the lattice.

El número de cruces de arriostramiento 8 transversales y cruces de arriostramiento longitudinales 11 depende fundamentalmente del canto de la futura viga, de la armadura de piel del alma, y de la necesidad de limitar la longitud de pandeo de los montantes 6. The number of transverse bracing crossings 8 and longitudinal bracing crossings 11 depends fundamentally on the edge of the future beam, on the skin reinforcement of the soul, and on the need to limit the buckling length of the uprights 6.

30 Existen diversos moldes para el encofrado del alma y de la losa de compresión de la viga. Es posible utilizar un aligeramiento, que permite hormigonar primero el alma y posteriormente el ala superior de la futura viga. No obstante, en caso de que sea necesario adoptar un intereje entre las vigas y/o la distancia entre nervios sea considerable, es posible 30 There are several molds for the formwork of the soul and the compression slab of the beam. It is possible to use a lightening, which allows the soul to be concreted first and then the upper wing of the future beam. However, if it is necessary to adopt a gap between the beams and / or the distance between nerves is considerable, it is possible

35 que la cantidad de material de aligeramiento a utilizar haga inviable este método. En tal caso, es posible utilizar enconfrados planos verticales unidos por berenjenos u otros elementos para el hormigonado del alma de la viga, y prelosas u otros elementos como encofrado perdido para el ala superior. 35 that the amount of lightening material to be used makes this method unfeasible. In such a case, it is possible to use vertical flat joints joined by eggplants or other elements for the concreting of the soul of the beam, and pre-slabs or other elements as lost formwork for the upper wing.

5 En la figura 14 esquemática se representa secuencialmente un posible procedimiento de utilización del elemento de la invención para construir por fases la viga final a partir del elemento estructural prefabricado de la invención. El primer esquema corresponde a una sección transversal de un conjunto de un objeto de la invención apoyado por sus extremos en obra, con un aligeramiento 13 entre las estructuras 2 verticales unidas a las bases de 5 In schematic figure 14 a possible method of using the element of the invention to phase the final beam from the prefabricated structural element of the invention is sequentially represented. The first scheme corresponds to a cross section of an assembly of an object of the invention supported by its ends in work, with a lightening 13 between the vertical structures 2 attached to the bases of

10 hormigón 1 pretensadas. Este aligeramiento 13 servirá de enconfrado perdido de los nervios y de la losa de compresión de las vigas finales. El segundo esquema corresponde a la finalización de los trabajos de hormigonado de los nervios 14 de las futuras vigas. También se puede ver la armadura de la losa de compresión 15 colocada en su situación final. Finalmente en el tercer esquema se puede ver el hormigonado final de la losa de 10 concrete 1 prestressed. This lightening 13 will serve as a lost finding of the nerves and of the compression slab of the final beams. The second scheme corresponds to the completion of the concrete work of the ribs 14 of the future beams. The reinforcement of the compression slab 15 placed in its final situation can also be seen. Finally in the third scheme you can see the final concreting of the slab of

15 compresión 16, utilizando el contorno superior del aligeramiento como base de encofrado. 15 compression 16, using the upper lightening contour as a formwork base.

En la figura 15 esquemática se representa secuencialmente otro posible procedimiento constructivo de utilización del elemento estructural prefabricado de la invención para construir por fases la viga final a partir de un elemento prefabricado de la invención. El 20 primer esquema corresponde a una sección transversal de un conjunto de un objeto de la invención apoyado por sus extremos en obra, donde se observan las estructuras 2 verticales unidas a las bases de hormigón 1 pretensada, con los moldes de enconfrado verticales 17 para el hormigón de los nervios, unidos entre ellos para soportar el empuje del hormigón. El segundo esquema corresponde a la finalización de los trabajos de hormigonado de los In schematic figure 15, another possible constructive method of using the prefabricated structural element of the invention to phase the final beam from a prefabricated element of the invention is represented sequentially. The first scheme corresponds to a cross-section of an assembly of an object of the invention supported by its ends on site, where the vertical structures 2 attached to the prestressed concrete bases 1 are observed, with the vertical molding molds 17 for the concrete of the nerves, joined together to support the thrust of the concrete. The second scheme corresponds to the completion of the concrete work of the

25 nervios 14 de las futuras vigas. También se puede ver como se coloca una prelosa 18 a modo de enconfrado perdido para la losa de compresión de la futura viga. Por otro lado, se observa como se ha dispuesto la armadura de la losa de compresión 15 de las futuras vigas en su situación final. Finalmente en el tercer esquema se puede ver el hormigonado de la losa de compresión 16 sobre las prelosas 18. 25 nerves 14 of future beams. You can also see how a pre-slab 18 is placed as a lost form for the compression slab of the future beam. On the other hand, it is observed how the reinforcement of the compression slab 15 of the future beams in its final situation has been arranged. Finally, in the third scheme, the concreting of the compression slab 16 on the pre-slabs 18 can be seen.

30 En la figura 16 esquemática se representa secuencialmente otro posible procedimiento constructivo de utilización de un elemento estructural prefabricado de la invención para construir por fases la viga final a partir de un elemento prefabricado de la invención. El primer esquema corresponde a una sección transversal de un conjunto de un objeto de la In schematic figure 16, another possible constructive method of using a prefabricated structural element of the invention for phasing the final beam from a prefabricated element of the invention is represented sequentially. The first scheme corresponds to a cross section of a set of an object of the

35 invención apoyado por sus extremos en obra, donde se observan las estructuras 2 verticales unidas a las bases de hormigón 1 pretensada, con unos moldes semicirculares o semiovalados 19 que actúan como encofrado perdido para los nervios y la losa de compresión de las vigas finales. El segundo esquema corresponde a la finalización de los trabajos de hormigonado de los nervios 14, que en este caso tienen unos contornos curvos. También se puede ver la armadura de la losa de compresión 15 colocada en su situación final. Finalmente en el tercer esquema se puede ver el hormigonado final de la losa de compresión 16. 35 invention supported by its ends in work, where the vertical structures 2 attached to the prestressed concrete bases 1 are observed, with semicircular or semi-oval molds 19 that act as a lost formwork for the nerves and the compression slab of the final beams. The second scheme corresponds to the completion of the concrete work of the ribs 14, which in this case have curved contours. The reinforcement of the compression slab 15 placed in its final situation can also be seen. Finally in the third scheme you can see the final concreting of the compression slab 16.

En los elementos con luces considerables se puede dar la necesidad de duplicar algunos de los montantes 6, especialmente los próximos a los apoyos, para evitar el pandeo de los mismos. También puede darse la necesidad de incrementar el número de cordones 5 comprimidos. Y en el caso de luces mayores, se puede disponer más de una estructura 2 vertical en el alma de un elemento. In the elements with considerable lights, there may be a need to duplicate some of the uprights 6, especially those close to the supports, to avoid buckling them. There may also be a need to increase the number of cords 5 tablets. And in the case of major lights, more than one vertical structure 2 can be arranged in the soul of an element.

En la figura 17 se observa una sección longitudinal de un tramo del elemento prefabricado donde se han duplicado los montantes 6. Se trata de una posible alternativa para evitar el pandeo de los montantes 6 en el caso de luces considerables, especialmente de los montantes 6 próximos a los apoyos, que son los más solicitados a compresión. En algún caso extremo, podría llegar a triplicarse alguno de los montantes 6. Debido a que las barras de los montantes 6 deben ser previamente dobladas, sus diámetros suelen estar limitados a un máximo. Dado que es posible que no puedan disponerse diámetros superiores a ese máximo para reducir la esbeltez de los montantes 6, debe recurrirse a duplicar dichas barras, en determinados casos. Figure 17 shows a longitudinal section of a section of the prefabricated element where the uprights 6 have been duplicated. It is a possible alternative to prevent buckling of the uprights 6 in the case of considerable lights, especially of the next uprights 6 to the supports, which are the most requested compression. In some extreme case, one of the uprights 6 could triple. Because the bars of the uprights 6 must be previously bent, their diameters are usually limited to a maximum. Since it may not be possible to have diameters greater than that maximum to reduce the slenderness of the uprights 6, these bars should be used to duplicate, in certain cases.

Análogamente, en la figura 18 se observa una sección transversal de un tramo del elemento estructural prefabricado donde se han duplicado e incluso triplicado los cordones 5 comprimidos superiores. Con ello se consigue que el elemento estructural prefabricado de la invención tenga mayor capacidad mecánica, y por tanto pueda vencer luces mayores, así como cargas de hormigonado del o los nervios mayores. Además, se limita drásticamente el pandeo de estos cordones 5 comprimidos. Similarly, in Figure 18 a cross section of a section of the prefabricated structural element where the upper compressed cords 5 have been duplicated and even tripled. With this it is achieved that the prefabricated structural element of the invention has greater mechanical capacity, and therefore can overcome major lights, as well as concrete loads of the major nerve (s). In addition, the buckling of these cords 5 tablets is drastically limited.

En la figura 19 se observa una sección transversal del elemento estructural prefabricado de la invención en el que se ha duplicado la estructura 2 vertical de barras de acero corrugado en celosía que conforma los nervios 14 de la futura viga. Se trata de una posible alternativa para evitar el pandeo de los montantes 6 y de los cordones 5 comprimidos en el caso de luces considerables. Figure 19 shows a cross section of the prefabricated structural element of the invention in which the vertical structure 2 of corrugated steel bars in lattice that forms the ribs 14 of the future beam has been duplicated. It is a possible alternative to avoid buckling of the studs 6 and the cords 5 compressed in the case of considerable lights.

En este caso, primero debe de hormigonarse uno de los nervios, puesto que si se hormigonaran todos los nervios a la vez, disponer varios nervios no supondría ninguna ventaja respecto a disponer un único nervio, puesto que, aunque se dispusiera mayor cantidad de acero, también existiría mayor carga al hormigonarse todos los nervios a la vez. Por ello, primero debe hormigonarse sólo un nervio (mientras, todas las celosías verticales resisten la carga de hormigonado de ese nervio). Una vez endurecido el primer nervio se debe hormigonar un segundo nervio (las celosías de los nervios no hormigonados, trabajarán como celosía, mientras que los nervios hormigonados y endurecidos parcialmente trabajarán como sección de hormigón), y así sucesivamente. Estas fases permiten al elemento soportar mayores cargas. In this case, one of the nerves must first be concreted, since if all the nerves were concreted at the same time, arranging several nerves would not imply any advantage over having a single nerve, since, even if more steel were available, there would also be a greater load by concreting all the nerves at once. Therefore, only one nerve must be concreted first (while all vertical lattices resist the concrete load of that nerve). Once the first nerve has hardened, a second nerve must be concreted (the lattices of the non-concreted nerves will work as lattice, while the concreted and partially hardened nerves will work as a concrete section), and so on. These phases allow the element to withstand greater loads.

En la figura 20 se observa una sección longitudinal del elemento estructural prefabricado de la invención junto con una sección transversal del mismo. Como se observa, el número de cruces de arriostramiento 8 transversales y cruces de arriostramiento longitudinales 11 para el arriostramiento de las barras comprimidas, puede ser variable. El número de cruces de arriostramiento transversales 8 depende fundamentalmente del canto de la futura viga, de la armadura de piel del alma, y de la necesidad de limitar la longitud de pandeo de los montantes 6. In Fig. 20 a longitudinal section of the prefabricated structural element of the invention is observed together with a cross section thereof. As can be seen, the number of cross bracing crossings 8 and longitudinal bracing crossings 11 for the bracing of the compressed bars can be variable. The number of transverse bracing crossings 8 depends fundamentally on the edge of the future beam, on the skin reinforcement of the soul, and on the need to limit the buckling length of the uprights 6.

En el caso de que la viga que se desee configurar a partir de un elemento de la invención, sea más larga que las longitudes existentes habituales en el mercado de las barras a modo de cordones 5 y las barras horizontales longitudinales 10, se debe de proceder a unir tramos sucesivos de tales cordones 5 y barras horizontales longitudinales 10. In the event that the beam that is desired to be configured from an element of the invention, is longer than the usual existing lengths in the market of rods 5 and horizontal longitudinal bars 10, it must proceed to join successive sections of such cords 5 and longitudinal horizontal bars 10.

Es aconsejable no hacer esta unión en la zona central de la viga final, o sea, es mejor no unir dos barras consecutivas de la misma longitud. Esto se explica porque en el centro de la viga final (donde iría esta unión), las barras longitudinales comprimidas sufren las compresiones más elevadas. Por ello, es mejor hacer esta unión a uno de los lados de un elemento, es decir, coger una barra más larga, y otra/s barra/s más corta/s, tal que complete/n la longitud del elemento estructural prefabricado. It is advisable not to make this joint in the central area of the final beam, that is, it is better not to join two consecutive bars of the same length. This is explained because in the center of the final beam (where this joint would go), the compressed longitudinal bars suffer the highest compressions. Therefore, it is better to make this connection to one of the sides of an element, that is, to take a longer bar, and another / s bar / s shorter, so that it completes the length of the prefabricated structural element.

En estructuras de hormigón armado, donde no se aprovecha previamente la geometría de las barras de acero del armado como estructura en sí misma, para unir barras de armadura suelen solaparse sin más, unas con otras, para que la futura viga hormigonada funcione correctamente (es la denominada longitud de solape). Pero en el caso de la presente In reinforced concrete structures, where the geometry of the steel bars of the reinforcement as a structure in itself is not previously taken advantage of, to join reinforcement bars they usually overlap one another, so that the future concrete beam works correctly (it is the so-called overlap length). But in the case of this

5 invención no es suficiente, puesto que cada barra debe tener continuidad mecánica antes de que se vierta el hormigón del nervio y de la losa de compresión en obra, ya que antes de ese vertido dichas barras forman parte de una estructura en celosía. The invention is not sufficient, since each bar must have mechanical continuity before the concrete of the nerve and the compression slab is poured on site, since before that pouring said bars are part of a lattice structure.

Para ello pueden existir varios posibles procedimientos. There may be several possible procedures for this.

10 Uno sería solapando las barras y soldándolas a lo largo del solape. Tal opción es contemplable en el caso de barras de pequeño diámetro, como los cordones 5 en elementos estructurales lineales prefabricados de pequeña luz, o las barras horizontales longitudinales 10 One would be overlapping the bars and welding them along the overlap. Such an option is contemplated in the case of small diameter bars, such as cords 5 in prefabricated linear structural elements of small light, or longitudinal horizontal bars

10. 10.

15 Otro procedimiento sería uniendo las barras por los extremos, o dejando cierto solape, por ejemplo aprovechando algún punto de unión con otras barras, como los montantes 6. Posiblemente es lo más recomendable en el caso de barras de poco diámetro, como por ejemplo las barras horizontales longitudinales 10 allí donde se unen con los montantes 6 y 15 Another procedure would be joining the bars at the ends, or leaving some overlap, for example taking advantage of some point of attachment with other bars, such as the uprights 6. Possibly it is most recommended in the case of bars of small diameter, such as longitudinal horizontal bars 10 where they join with the uprights 6 and

20 las cruces de arriostramiento 8 transversales. 20 bracing crossings 8 cross.

Otro procedimiento sería mediante uniones mecánicas, técnica que también es utilizada en estructuras de hormigón armado, sobre todo para unir barras de diámetros elevados. Esta opción sería la más adecuada en el caso de barras de gran diámetro, como los cordones 5 Another procedure would be through mechanical joints, a technique that is also used in reinforced concrete structures, especially to join bars of high diameters. This option would be the most appropriate in the case of large diameter bars, such as cords 5

25 en elementos estructurales lineales prefabricados con luces significativas. 25 in prefabricated linear structural elements with significant lights.

En la figura 21 esquemática se observa secuencialmente el proceso constructivo de un elemento estructural prefabricado objeto de la invención en una la sección longitudinal, apoyado en sus extremos. En el caso de la figura, se apoya sobre dos pantallas de las que In schematic figure 21 the construction process of a prefabricated structural element object of the invention is sequentially observed in a longitudinal section, supported at its ends. In the case of the figure, it rests on two screens of which

30 se pueden ver los espaldines. En el primer esquema se observa la geometría (base de hormigón 1 pretensada y estructura 2 vertical). La geometría de la viga prefabricada, las uniones entre las barras de acero corrugado y los arriostramientos de las barras comprimidas, es lo que permite al elemento estructural prefabricado ser autoportante y soportar las cargas de hormigonado de las partes de la viga final a ejecutar en obra. 30 you can see the sprats. In the first scheme the geometry is observed (prestressed concrete base 1 and vertical structure 2). The geometry of the prefabricated beam, the joints between the corrugated steel bars and the bracing of the compressed bars, is what allows the prefabricated structural element to be self-supporting and withstand the concreting loads of the parts of the final beam to be executed on site. .

En el segundo esquema se observa la misma sección longitudinal con el nervio 14 hormigonado. In the second scheme, the same longitudinal section is observed with the concreted nerve 14.

En el tercer esquema, se observa la misma sección logitudinal con la losa de compresión 16 In the third scheme, the same logitudinal section is observed with compression slab 16

5 hormigonada. En función de las necesidades, esta losa de compresión 16 puede prolongarse hasta la estructura contigua y unirse estructuralmente a la misma o no. Posteriormente a esta fase, se aplicarán las cargas de diseño al elemento. 5 concrete. Depending on the needs, this compression slab 16 can be extended to the adjacent structure and structurally attached to it or not. After this phase, the design loads will be applied to the element.

Finalmente, en el cuarto esquema, se observa la misma sección longitudinal con las cargas 10 de diseño actuando. Finally, in the fourth scheme, the same longitudinal section is observed with the design loads 10 acting.

Otra ventaja de la presente invención respecto a las vigas existentes en el mercado es que no tiene prefabricado el/los nervio/s del alma, ya que se trata de una de las partes que se hormigona en obra. Gracias a ello, si se dejan los correspondientes espacios con los 15 aligeramientos u otros sistemas, es posible construir nervios transversales a lo largo de toda la estructura a realizar de forma sencilla. Estos nervios podrán ir armados con barras de acero corrugado dispuestas en obra. La función de estos nervios es evitar el “efecto piano” o “tecleteo” de las diferentes vigas una vez colocadas en obra. Se trata de un efecto común en todas las vigas prefabricados autoportantes para cargas y luces considerables del mercado, Another advantage of the present invention with respect to the existing beams in the market is that it does not have the nerve (s) prefabricated, since it is one of the parts that is concreted in work. Thanks to this, if the corresponding spaces are left with the lightening or other systems, it is possible to construct transverse ribs along the entire structure to be performed in a simple way. These nerves may be armed with corrugated steel bars arranged on site. The function of these nerves is to avoid the "piano effect" or "typing" of the different beams once placed on site. It is a common effect on all self-supporting prefabricated beams for considerable loads and lights on the market,

20 en las que por el hecho de disponer de nervios longitudinales prefabricados, no es posible hormigonar en obra unos nervios transversales de forma sencilla. 20 in which, due to the fact of having prefabricated longitudinal ribs, it is not possible to concretize transverse ribs in a simple way.

Estos nervios pueden servir también como elemento estructural en la dirección transversal, rigidificando el conjunto, lo que supone una ventaja respecto a los actuales productos del 25 mercado, que no lo permiten de forma sencilla. These nerves can also serve as a structural element in the transverse direction, stiffening the assembly, which is an advantage over the current products of the market, which do not allow it easily.

Estos nervios pueden ser continuos o discretos, y en función del espaciado que se deje entre aligeramientos para su construcción, pueden convertirse en verdaderos macizados de hormigón. These nerves can be continuous or discrete, and depending on the spacing left between lightening for their construction, they can become true concrete massifs.

30 En la figura 22 se observa secuencialmente un modo sencillo de construir nervios continuos 21 en sentido transversal al objeto de la invención para evitar el “efecto piano” o “tecleteo”. Para ello debe dejarse un espacio adicional entre los aligeramientos 13 y posteriormente hormigonar los nervios longitudinales 14 y transversales 21. Es posible disponer una In Figure 22 a simple way of constructing continuous ribs 21 in a transverse direction to the object of the invention is sequentially observed to avoid the "piano effect" or "typing". For this, an additional space must be left between the lightening 13 and subsequently concreting the longitudinal and transverse ribs 21. It is possible to arrange a

35 armadura 20 en los nervios transversales. En función de la distancia dejada entre aligeramientos contiguos, mayor o menor será el ancho de estos nervios, pudiendo llegar a generar verdaderos macizados (continuos o puntuales) para cargas puntuales o en faja, en caso de requerirse. Estos nervios pueden servir también como elemento estructural en la dirección transversal, rigidificando el conjunto. 35 armor 20 in the transverse nerves. Depending on the distance left between contiguous lightening, the width of these nerves will be greater or lesser, being able to generate true solid (continuous or punctual) for point or belt loads, if required. These nerves can also serve as a structural element in the transverse direction, stiffening the assembly.

Los nervios transversales 21 pueden ser armados, y en su construcción se puede dejar un espacio transversal para situarlos y hormigonarlos simultáneamente a los nervios longitudinales 14, quedando así unidos estructuralmente. The transverse ribs 21 can be armed, and in their construction a transverse space can be left to place them and concretize them simultaneously to the longitudinal ribs 14, thus being structurally linked.

Un procedimiento de fabricación de un elemento estructural prefabricado de la invención, comprende una colocación de la estructura 2 con las patillas 61,71 presentes en la estructura 2 insertadas entre algunas de las armaduras 3,4, y con las patillas 82, 111 presentes en la estructura 2 situadas en la región de la futura base de hormigón 1, y posteriormente un hormigonado de las armaduras 3,4. A method of manufacturing a prefabricated structural element of the invention comprises placing the structure 2 with the pins 61,71 present in the structure 2 inserted between some of the reinforcements 3,4, and with the pins 82, 111 present in structure 2 located in the region of the future concrete base 1, and subsequently a concrete reinforcement 3.4.

La elaboración de la estructura 2 y sus uniones se efectúa fuera de una pista de tesado, y posteriormente se sitúa la estructura 2 en la pista de tesado, o también puede elaborarse total o parcialmente la estructura 2 y sus uniones en la propia pista de tesado. The construction of structure 2 and its unions is carried out outside a test track, and then structure 2 is placed on the test track, or structure 2 and its joints can be fully or partially made in the test track itself .

Para la elaboración de la estructura 2 vertical , se utiliza un accesorio provisional que sostiene temporalmente a las barras que conforman la estructura 2 vertical para su adecuado montaje, y utilizándose tal que primero se sitúan los cordones 5 superiores sostenidos por el elemento provisional, en los que a su vez, se cuelgan y disponen adecuadamente los montantes 6 y las diagonales 7, seguidos de las cruces de arriostramiento 8 transversales mediante los ganchos 81, seguidos de las cruces de arriostramiento 11 longitudinales, seguidos de las barras horizontales transversales 9 mediante los ganchos 91 que atan los puntos de unión de barras, y finalmente las barras horizontales longitudinales 10, y con posterioridad se sueldan entre sí las barras de acero corrugado. For the preparation of the vertical structure 2, a provisional accessory is used that temporarily supports the bars that make up the vertical structure 2 for proper assembly, and using such that first the upper cords 5 supported by the provisional element are located, in the which, in turn, the uprights 6 and diagonals 7 are hung and properly arranged, followed by the cross bracing crossings 8 by the hooks 81, followed by the longitudinal bracing crossings 11, followed by the horizontal crossbars 9 by the hooks 91, which tie the bar connection points, and finally the longitudinal horizontal bars 10, and subsequently weld the corrugated steel bars together.

La realización de las soldaduras 12 de las barras de acero corrugado de la estructura 2 vertical se puede efectuar antes o después del hormigonado, fraguado y endurecimento de la base de hormigón 1. Welding 12 of the corrugated steel bars of the vertical structure 2 can be carried out before or after concreting, setting and hardening of the concrete base 1.

Un orden de fabricación del elemento estructural prefabricado de la invención es el An order of manufacture of the prefabricated structural element of the invention is the

siguiente: next:

− Colocación de la armadura pasiva 4 en una pista de tesado, en caso de requerirse tal - Placing passive reinforcement 4 on a test track, if such is required

armadura. armor.

− Colocación de la armadura activa 3 en la pista de tesado. - Placement of active reinforcement 3 on the test track.

− Tesado de la armadura activa 3. - Active armor testing 3.

− Colocación y/o montaje de la estructura 2 vertical en la pista de tesado. - Placing and / or mounting the vertical structure 2 on the test track.

− Hormigonado y vibrado de la base de hormigón 1. - Concreting and vibrating of the concrete base 1.

− Transferencia del pretensado mediante el corte de la armadura activa 3. - Transfer of prestressing by cutting the active reinforcement 3.

Puede resultar más ventajoso realizar las soldaduras de la estructura 2 vertical antes del hormigonado de la base de hormigón 1 pretensada, en cuanto proporciona un estado tensional y una flecha del elemento estructural prefabricado contrarios a los que solicitarán al elemento estructural prefabricado durante la fase de previga prefabricada. It may be more advantageous to weld the vertical structure 2 before concreting the prestressed concrete base 1, insofar as it provides a tensioned state and an arrow of the prefabricated structural element contrary to those that will request the prefabricated structural element during the pre-fabrication phase. prefabricated.

La geometría de las diferentes barras que conforman la estructura 2 vertical asegura el correcto funcionamiento estructural del elemento estructural prefabricado a la vez que facilita el proceso de fabricación del mismo (ensamblaje de barras y unión de barras metálicas o de aleación mediante soldaduras). The geometry of the different bars that make up the vertical structure 2 ensures the correct structural operation of the prefabricated structural element while facilitating the manufacturing process thereof (assembly of bars and joining of metal or alloy bars by welding).

Es posible dividir el procedimiento de construcción del elemento estructural prefabricado en dos partes: por un lado la estructura 2 vertical, y por otro lado la base de hormigón 1 pretensada y sus armaduras 2,3. Esto permite que el proceso de producción sea rápido. It is possible to divide the construction process of the prefabricated structural element into two parts: on the one hand the vertical structure 2, and on the other hand the prestressed concrete base 1 and its reinforcements 2,3. This allows the production process to be fast.

El elemento estructural prefabricado de la presente invención presenta evidentes ventajas en su fabricación, pues al ser sólo necesario hormigonar y pretensar una base de hormigón de poco espesor, se asegura un fraguado rápido del hormigón, disminuyendo por tanto notablemente su tiempo de fabricación. La necesidad que presentan otros productos de hormigonar una mayor parte de su sección, comporta un mayor tiempo de prefabricación, por el incremento del tiempo de fraguado y porque es posible que deban hormigonarse las diferentes partes de la sección por fases, siendo por tanto incluso ser necesario levantar el elemento y transportarlo de una zona a otra de la fábrica para efectuar dichos hormigonados. The prefabricated structural element of the present invention has obvious advantages in its manufacture, since it is only necessary to concrete and prestress a concrete base of low thickness, a quick setting of the concrete is ensured, thus significantly reducing its manufacturing time. The need presented by other products to concretize a greater part of its section, implies a longer prefabrication time, due to the increase in the setting time and because it is possible that the different parts of the section should be concreted by phases, therefore being even It is necessary to lift the element and transport it from one area to another of the factory to carry out said concreting.

Los moldes de prefabricado necesarios son de dimensiones más reducidas que los utilizados para los productos actuales con funciones similares. El peso de la pieza prefabricada también resulta sustancialmente inferior con respecto a los productos actuales con funciones similares, lo cual supone una notable reducción en los costes de transporte y The necessary prefabricated molds are smaller in size than those used for current products with similar functions. The weight of the prefabricated part is also substantially lower compared to current products with similar functions, which means a significant reduction in transport costs and

5 contribuye también a ampliar la difusión territorial del producto. 5 also contributes to expanding the territorial diffusion of the product.

La fabricación del elemento estructural prefabricado de la presente invención es viable para casi cualquier empresa de prefabricados con la maquinaria habitualmente disponible. Asimismo, una empresa constructora también sería capaz de fabricar este elemento. The manufacturing of the prefabricated structural element of the present invention is feasible for almost any prefabricated company with the machinery usually available. Likewise, a construction company would also be able to manufacture this element.

10 Presenta una elevada resistencia al fuego, siendo por tanto ventajosa su utilización frente a la alternativa de utilizar vigas metálicas y mixtas, y además, su geometría permite que pueda ser utilizado como jácena. 10 It has a high resistance to fire, therefore its use is advantageous compared to the alternative of using metal and mixed beams, and in addition, its geometry allows it to be used as a jacena.

15 Los detalles, las formas, las dimensiones y demás elementos accesorios, así como los materiales empleados en la fabricación de un elemento estructural prefabricado de la invención, podrán ser convenientemente sustituidos por otros que sean técnicamente equivalentes y no se aparten de la esencialidad de la invención ni del ámbito definido por las reivindicaciones que se incluyen a continuación. The details, shapes, dimensions and other accessory elements, as well as the materials used in the manufacture of a prefabricated structural element of the invention, may be conveniently replaced by others that are technically equivalent and do not depart from the essentiality of the invention or the scope defined by the claims included below.

Claims (23)

REIVINDICACIONES 1. Elemento estructural prefabricado, caracterizado por el hecho de que comprende una base de hormigón (1) pretensada y al menos una estructura (2) vertical de barras, tal que la 5 base de hormigón (1) comprende una armadura activa (3) longitudinal y/o una armadura pasiva (4) longitudinal y/o transversal; tal que la estructura (2) de barras está conformada por una pluralidad de estribos verticales transversales con forma de “U” invertida a modo de montantes (6) dispuestos consecutivamente, que se alternan con otra pluralidad de estribos inclinados transversales también con forma de “U” invertida a modo de diagonales (7), más 1. Prefabricated structural element, characterized in that it comprises a prestressed concrete base (1) and at least one vertical bar structure (2), such that the concrete base (1) comprises an active reinforcement (3) longitudinal and / or passive reinforcement (4) longitudinal and / or transverse; such that the structure (2) of bars is formed by a plurality of vertical transverse stirrups in the form of an inverted "U" in the form of consecutive uprights (6), which alternate with another plurality of transverse inclined stirrups also in the form of " U ”inverted as diagonals (7), more 10 largos que los estribos verticales transversales anteriormente citados, tal que las diagonales 10 long than the transverse vertical stirrups mentioned above, such that the diagonal ones (7) unen la parte superior e inferior de los montantes (6) consecutivos, y disponiendo estos montantes (6) y diagonales (7) de unas patillas (61, 71) en su parte inferior abierta en contacto con la base de hormigón (1) estando dichas patillas (61, 71) embebidas en la base de hormigón (1), y por lo tanto los montantes (6) y diagonales (7) están unidos a la misma (7) join the upper and lower part of the consecutive uprights (6), and arranging these (6) and diagonal uprights (7) of pins (61, 71) in their lower part open in contact with the concrete base ( 1) said pins (61, 71) being embedded in the concrete base (1), and therefore the uprights (6) and diagonals (7) are attached to it 15 base de hormigón (1), y en la parte superior de los montantes (6) y diagonales (7) están dispuestas al menos una barra longitudinal a modo de cordón (5) que recorre al menos parcialmente la pluralidad de los diferentes montantes (6) y diagonales (7). 15 concrete base (1), and at the top of the uprights (6) and diagonals (7) are arranged at least one longitudinal bar as a cord (5) that runs at least partially the plurality of the different uprights ( 6) and diagonals (7). 2. Elemento estructural prefabricado según la reivindicación 1, caracterizado por el 2. Prefabricated structural element according to claim 1, characterized by the 20 hecho de que la armadura activa (3) longitudinal y/o la armadura pasiva (4) longitudinal y/o transversal están en el interior de la base de hormigón (1). 20 the fact that the longitudinal active reinforcement (3) and / or the longitudinal and / or transverse passive reinforcement (4) are inside the concrete base (1). 3. Elemento estructural prefabricado según la reivindicación 1, caracterizado por el hecho de que las barras integrantes de la estructura (2) vertical, o los alambres o cordones 3. Prefabricated structural element according to claim 1, characterized in that the integral bars of the vertical structure (2), or the wires or cords 25 integrantes de la armadura activa (3) longitudinal, o las barras integrantes de la armadura pasiva (4) longitudinal y/o transversal, son metálicas o de aleación. 25 members of the active longitudinal reinforcement (3), or the integral and / or transverse passive reinforcement (4) bars, are metallic or alloy. 4. Elemento estructural prefabricado según la reivindicación 3, caracterizado por el hecho de que las barras integrantes de la estructura (2), o los alambres o cordones 4. Prefabricated structural element according to claim 3, characterized in that the integral bars of the structure (2), or the wires or cords 30 integrantes de la armadura activa (3) longitudinal, o las barras integrantes de la armadura pasiva (4) longitudinal y/o transversal, son de acero. 30 members of the active longitudinal reinforcement (3), or the integral and / or transverse passive reinforcement (4) bars, are made of steel. 5. Elemento estructural prefabricado según la reivindicación 4, caracterizado por el hecho de que las barras integrantes de la estructura (2) o de la armadura pasiva (4) 35 longitudinal y/o transversal son de acero corrugado, y los alambres o cordones integrantes 5. Prefabricated structural element according to claim 4, characterized in that the integral bars of the structure (2) or the longitudinal and / or transverse passive reinforcement (4) are made of corrugated steel, and the integral wires or cords de la armadura activa longitudinal (3) son de acero de alta resistencia. 31 of the longitudinal active reinforcement (3) are made of high strength steel. 31 6. Elemento estructural prefabricado según la reivindicación 1, caracterizado por el hecho de que la estructura (2) dispone de una estructura de barras en forma de cruces de arriostramiento (8) transversales en unos planos verticales y transversales a la base de 6. Prefabricated structural element according to claim 1, characterized in that the structure (2) has a bar structure in the form of transverse bracing crossings (8) in vertical planes and transverse to the base of 5 hormigón (1) y estando dichos planos formados por los estribos verticales transversales con forma de “U” invertida a modo de montantes (6), y la estructura (2) dispone además de unas barras horizontales transversales (9) que unen las dos barras del montante (6) en los puntos de convergencia de las cruces de arriostramiento (8) transversales. 5 concrete (1) and said planes being formed by the vertical transverse stirrups with an inverted "U" shape as uprights (6), and the structure (2) also has horizontal crossbars (9) joining the two upright bars (6) at the convergence points of the cross bracing crossings (8). 10 7. Elemento estructural prefabricado según la reivindicación 6, caracterizado por el hecho de que la estructura (2) dispone de unas barras horizontales longitudinales (10) paralelas a la base de hormigón (1) que recorren al menos parcialmente la longitud de la estructura (2) y que unen los puntos de convergencia de las cruces de arriostramiento (8) transversales. A prefabricated structural element according to claim 6, characterized in that the structure (2) has longitudinal horizontal bars (10) parallel to the concrete base (1) that run at least partially the length of the structure (2) and that join the convergence points of the cross bracing crossings (8). 8. Elemento estructural prefabricado según la reivindicación 6 o 7, caracterizado por el hecho de que la estructura (2) dispone de otras cruces de arriostramiento (11) longitudinales al menos entre el primer y segundo montante (6) de los dos extremos de la propia estructura 8. Prefabricated structural element according to claim 6 or 7, characterized in that the structure (2) has other longitudinal bracing crossings (11) at least between the first and second upright (6) of the two ends of the own structure (2) y en unos planos verticales que recorren longitudinalmente la base de hormigón (1) y que 20 contienen los montantes (6) consecutivos. (2) and in vertical planes that run longitudinally through the concrete base (1) and which contain 20 consecutive uprights (6). 9. Elemento estructural prefabricado según la reivindicación 6, caracterizado por el hecho de que las cruces de arriostramiento (8) transversales se componen de unas barras dobladas en zig-zag, con un gancho (81) en su extremo superior y una patilla (82) en su 9. Prefabricated structural element according to claim 6, characterized in that the cross bracing crossings (8) are composed of zigzag bent bars, with a hook (81) at its upper end and a pin (82) ) in its 25 extremo inferior. 25 lower end. 10. Elemento estructural prefabricado según la reivindicación 9, caracterizado por el hecho de que las barras dobladas en zig-zag que componen las cruces de arriostramiento 10. Prefabricated structural element according to claim 9, characterized in that the zig-zag bent bars that make up the bracing crossings (8) transversales presentan un tramo (83) recto en los puntos de doblado, adecuado para 30 una soldadura con otras barras metálicas o de aleación. (8) cross sections have a straight section (83) at the bending points, suitable for welding with other metal or alloy bars. 11. Elemento estructural prefabricado según la reivindicación 6, caracterizado por el hecho de que las barras horizontales transversales (9) presentan un gancho (91) en cada uno de sus extremos. 11. Prefabricated structural element according to claim 6, characterized in that the horizontal crossbars (9) have a hook (91) at each of its ends. 12. Elemento estructural prefabricado según la reivindicación 8, caracterizado por el hecho de que las cruces de arriostramiento (11) longitudinales se componen de dos barras dobladas en zig-zag, con una patilla (111) en cada uno de los extremos de las barras. 12. Prefabricated structural element according to claim 8, characterized in that the longitudinal bracing crossings (11) are composed of two zigzag bent bars, with a pin (111) at each end of the bars . 5 13. Elemento estructural prefabricado según la reivindicación 12, caracterizado por el hecho de que las barras dobladas en zig-zag que componen las cruces de arriostramiento 13. Prefabricated structural element according to claim 12, characterized in that the zig-zag bent bars that make up the bracing crossings (11) longitudinales presentan un tramo (112) recto adecuado para una soldadura con otras barras metálicas o de aleación. (11) Longitudinals have a straight section (112) suitable for welding with other metal or alloy bars. 10 14. Elemento estructural prefabricado según alguna de las reivindicaciones anteriores, caracterizado por el hecho de que las siguientes barras están soldadas: 14. Prefabricated structural element according to any one of the preceding claims, characterized in that the following bars are welded: − los montantes (6) con las diagonales (7) en su parte superior; − los ganchos (81) de las cruces de arriostramiento (8) transversales con montantes (6) 15 y/o diagonales (7); − los ganchos (81) de las cruces de arriostramiento (8) transversales con los cordones - the uprights (6) with the diagonals (7) in their upper part; - the hooks (81) of the cross bracing crossings (8) with uprights (6) 15 and / or diagonals (7); - the hooks (81) of the cross bracing crossings (8) with the cords (5) superiores; − las diagonales (7) y/o montantes (6) con los cordones (5) superiores; − los tramos (83) rectos en los puntos de doblado de las cruces de arriostramiento (8) (5) superior; - the diagonals (7) and / or uprights (6) with the upper cords (5); - the straight sections (83) at the bending points of the bracing crossings (8) 20 transversales con los montantes (6); 20 transversal with the uprights (6); − los ganchos (91) de las barras horizontales transversales (9) que unen los puntos de convergencia de las cruces de arriostramiento (8) transversales con los montantes (6); - the hooks (91) of the horizontal crossbars (9) connecting the convergence points of the cross bracing crossings (8) with the uprights (6); − las barras horizontales longitudinales (10) que unen los puntos de convergencia de 25 las cruces de arriostramiento (8) transversales con los montantes (6); − los tramos (112) rectos en los puntos de doblado de las cruces de arriostramiento - the longitudinal horizontal bars (10) joining the convergence points of the cross bracing crossings (8) with the uprights (6); - the straight sections (112) at the bending points of the bracing crossings (11) longitudinales con los montantes (6). − las patillas (111) superiores de las cruces de arriostramiento (11) longitudinales con (11) Longitudinal with the uprights (6). - the upper pins (111) of the longitudinal bracing crossings (11) with los montantes (6). 30 the uprights (6). 30 15. Elemento estructural prefabricado según la reivindicación 1, caracterizado por el hecho de que comprende una única estructura (2). 15. Prefabricated structural element according to claim 1, characterized in that it comprises a single structure (2). 16. Elemento estructural prefabricado según la reivindicación 1, caracterizado por el 35 hecho de que comprende dos estructuras (2). 16. Prefabricated structural element according to claim 1, characterized in that it comprises two structures (2). 17. Elemento estructural prefabricado según la reivindicación 1, caracterizado por el hecho de que comprende tres estructuras (2). 17. Prefabricated structural element according to claim 1, characterized in that it comprises three structures (2). 18. Elemento estructural prefabricado según la reivindicación 1, caracterizado por el 5 hecho de que comprende cuatro estructuras (2). 18. Prefabricated structural element according to claim 1, characterized in that it comprises four structures (2). 19. Procedimiento de fabricación de un elemento estructural prefabricado según alguna de las reivindicaciones anteriores, caracterizado por el hecho de que comprende una colocación de la estructura (2) con las patillas (61,71) presentes en la estructura (2) 19. Method of manufacturing a prefabricated structural element according to one of the preceding claims, characterized in that it comprises placing the structure (2) with the pins (61,71) present in the structure (2) 10 insertadas entre algunas de las armaduras (3,4), y con las patillas (82, 111) presentes en la estructura (2) situadas en la región de la futura base de hormigón (1), y posteriormente un hormigonado de las armaduras (3,4). 10 inserted between some of the reinforcements (3,4), and with the pins (82, 111) present in the structure (2) located in the region of the future concrete base (1), and subsequently a concreting of the reinforcements (3,4). 20. Procedimiento de fabricación de un elemento estructural prefabricado según la 20. Procedure for manufacturing a prefabricated structural element according to the 15 reivindicación 19, caracterizado por el hecho de elaborar la estructura (2) y sus uniones fuera de una pista de tesado, y posteriormente situar la estructura (2) en la pista de tesado. Claim 19, characterized in that the structure (2) and its joints are made out of a testing track, and subsequently placing the structure (2) on the testing track. 21. Procedimiento de fabricación de un elemento estructural prefabricado según la 21. Procedure for manufacturing a prefabricated structural element according to the reivindicación 19, caracterizado por el hecho de elaborar total o parcialmente la estructura 20 (2) y sus uniones en una pista de tesado. claim 19, characterized in that the structure 20 (2) and its joints are fully or partially prepared in a test track.
22. 22
Procedimiento de fabricación de un elemento estructural prefabricado según las reivindicaciones 20 o 21, caracterizado por el hecho de utilizar un accesorio provisional que sostiene temporalmente a las barras que conforman la estructura (2) para su adecuado 25 montaje, y utilizándose tal que primero se sitúan los cordones (5) superiores sostenidos por el elemento provisional, en los que a su vez, se cuelgan y disponen adecuadamente los montantes (6) y las diagonales (7), seguidos de las cruces de arriostramiento (8) transversales mediante los ganchos (81), seguidos de las cruces de arriostramiento (11) longitudinales, seguidos de las barras horizontales transversales (9) mediante los ganchos Method of manufacturing a prefabricated structural element according to claims 20 or 21, characterized in that a temporary accessory is used that temporarily supports the bars that make up the structure (2) for its proper assembly, and using such that they are first placed the upper cords (5) supported by the provisional element, in which, in turn, the uprights (6) and diagonals (7) are hung and properly arranged, followed by the cross bracing crossings (8) by the hooks ( 81), followed by longitudinal bracing crossings (11), followed by horizontal crossbars (9) by hooks
30 (91) que atan los puntos de unión de barras, y finalmente las barras horizontales longitudinales (10), y con posterioridad se sueldan entre sí las barras metálicas o de aleación. 30 (91) that tie the bar attachment points, and finally the horizontal horizontal bars (10), and subsequently weld the metal or alloy bars together.
23. 2. 3.
Procedimiento de fabricación de un elemento estructural prefabricado según la 35 reivindicación 22, caracterizado por el hecho realizar las soldaduras (12) de las barras Method of manufacturing a prefabricated structural element according to claim 22, characterized in that the welds (12) of the bars are made
metálicas o de aleación de la estructura (2) antes del hormigonado, fraguado y endurecimento de la base de hormigón (1). metal or alloy structure (2) before concreting, setting and hardening of the concrete base (1).
24. Procedimiento de fabricación de un elemento estructural prefabricado según la 5 reivindicación 22, caracterizado por el hecho de realizar al menos una de las soldaduras 24. Method of manufacturing a prefabricated structural element according to claim 22, characterized in that at least one of the welds is made (12) de las barras metálicas o de aleación de la estructura (2) posteriormente al hormigonado, fraguado y endurecimento de la base de hormigón (1). (12) of the metal or alloy bars of the structure (2) after concreting, setting and hardening of the concrete base (1). 25. Procedimiento de fabricación de un elemento estructural prefabricado según la 10 reivindicación 19, caracterizado por el siguiente orden de fabricación del elemento 25. Method of manufacturing a prefabricated structural element according to claim 19, characterized by the following order of manufacture of the element estructural prefabricado: − Colocación de la armadura pasiva (4) en una pista de tesado, en caso de requerirse tal armadura. − Colocación de la armadura activa (3) en la pista de tesado. Prefabricated structural structure: - Placement of passive reinforcement (4) on a test track, if such reinforcement is required. - Placement of active reinforcement (3) on the test track. 15 − Tesado de la armadura activa (3). − Colocación y/o montaje de la estructura (2) en la pista de tesado. − Hormigonado y vibrado de la base de hormigón (1). − Transferencia del pretensado mediante el corte de la armadura activa (3). 15 - Tested active armor (3). - Placement and / or assembly of the structure (2) on the test track. - Concreting and vibrating of the concrete base (1). - Transfer of prestressing by cutting the active reinforcement (3). OFICINA ESPAÑOLA DE PATENTES Y MARCAS SPANISH OFFICE OF THE PATENTS AND BRAND N.º solicitud: 201330822 Application no .: 201330822 ESPAÑA SPAIN Fecha de presentación de la solicitud: 04.06.2013 Date of submission of the application: 04.06.2013 Fecha de prioridad: Priority Date: INFORME SOBRE EL ESTADO DE LA TECNICA REPORT ON THE STATE OF THE TECHNIQUE 51 Int. Cl. : Ver Hoja Adicional 51 Int. Cl.: See Additional Sheet DOCUMENTOS RELEVANTES RELEVANT DOCUMENTS
Categoría Category
56 Documentos citados Reivindicaciones afectadas 56 Documents cited Claims Affected
Y Y
EP 1020583 A1 (MARMORITH BETONINDUSTRIE ET AL.) 19/07/2000, columna 3, línea 3 columna 7, línea 2; figuras. 1-4, 14, 15, 17 EP 1020583 A1 (MARMORITH BETONINDUSTRIE ET AL.) 07/19/2000, column 3, line 3 column 7, line 2; figures. 1-4, 14, 15, 17
Y Y
US 3778951 A (OROSCHAKOFF G) 18/12/1973, columna 1, línea 55 -columna 10, línea 9; figuras. 1-4, 14, 15, 17 US 3778951 A (OROSCHAKOFF G) 12/18/1973, column 1, line 55-column 10, line 9; figures. 1-4, 14, 15, 17
A TO
JP H1150468 A (MORI HITOSHI) 23/02/1999, Resumen de la base de datos WPI. Recuperado de EPOQUE; AN 1999-211452 1-3, 15 JP H1150468 A (MORI HITOSHI) 02/23/1999, Summary of the WPI database. Recovered from EPOQUE; AN 1999-211452 1-3, 15
A TO
EP 0143101 A2 (BEST BAUEISEN & STAHL) 29/05/1985, Resumen de la base de datos WPI. Recuperado de EPOQUE; AN 1985-129816 1, 4, 6, 11 EP 0143101 A2 (BEST BAUEISEN & STAHL) 05/29/1985, Summary of the WPI database. Recovered from EPOQUE; AN 1985-129816 1, 4, 6, 11
Categoría de los documentos citados X: de particular relevancia Y: de particular relevancia combinado con otro/s de la misma categoría A: refleja el estado de la técnica O: referido a divulgación no escrita P: publicado entre la fecha de prioridad y la de presentación de la solicitud E: documento anterior, pero publicado después de la fecha de presentación de la solicitud Category of the documents cited X: of particular relevance Y: of particular relevance combined with other / s of the same category A: reflects the state of the art O: refers to unwritten disclosure P: published between the priority date and the date of priority submission of the application E: previous document, but published after the date of submission of the application
El presente informe ha sido realizado • para todas las reivindicaciones • para las reivindicaciones nº: This report has been prepared • for all claims • for claims no:
Fecha de realización del informe 27.11.2013 Date of realization of the report 27.11.2013
Examinador M. B. Hernández Agusti Página 1/4 Examiner M. B. Hernández Agusti Page 1/4
INFORME DEL ESTADO DE LA TÉCNICA REPORT OF THE STATE OF THE TECHNIQUE Nº de solicitud: 201330822 Application number: 201330822 CLASIFICACIÓN OBJETO DE LA SOLICITUD CLASSIFICATION OBJECT OF THE APPLICATION E04C3/294 (2006.01) E04C5/065 (2006.01) E04B5/23 (2006.01) E04B5/38 (2006.01) E04C3 / 294 (2006.01) E04C5 / 065 (2006.01) E04B5 / 23 (2006.01) E04B5 / 38 (2006.01) Documentación mínima buscada (sistema de clasificación seguido de los símbolos de clasificación) Minimum documentation sought (classification system followed by classification symbols) E04B, E04C E04B, E04C Bases de datos electrónicas consultadas durante la búsqueda (nombre de la base de datos y, si es posible, términos de búsqueda utilizados) Electronic databases consulted during the search (name of the database and, if possible, search terms used) INVENES, EPODOC INVENTIONS, EPODOC Informe del Estado de la Técnica Página 2/4 State of the Art Report Page 2/4 OPINIÓN ESCRITA  WRITTEN OPINION Nº de solicitud: 201330822 Application number: 201330822 Fecha de Realización de la Opinión Escrita: 27.11.2013 Date of Written Opinion: 27.11.2013 Declaración Statement
Novedad (Art. 6.1 LP 11/1986) Novelty (Art. 6.1 LP 11/1986)
Reivindicaciones Reivindicaciones 1-25 SI NO Claims Claims 1-25 IF NOT
Actividad inventiva (Art. 8.1 LP11/1986) Inventive activity (Art. 8.1 LP11 / 1986)
Reivindicaciones Reivindicaciones 5-13, 16, 18-25 1-4, 14, 15, 17 SI NO Claims Claims 5-13, 16, 18-25 1-4, 14, 15, 17 IF NOT
Se considera que la solicitud cumple con el requisito de aplicación industrial. Este requisito fue evaluado durante la fase de examen formal y técnico de la solicitud (Artículo 31.2 Ley 11/1986). The application is considered to comply with the industrial application requirement. This requirement was evaluated during the formal and technical examination phase of the application (Article 31.2 Law 11/1986). Base de la Opinión.-  Opinion Base.- La presente opinión se ha realizado sobre la base de la solicitud de patente tal y como se publica. This opinion has been made on the basis of the patent application as published. Informe del Estado de la Técnica Página 3/4 State of the Art Report Page 3/4 OPINIÓN ESCRITA  WRITTEN OPINION Nº de solicitud: 201330822 Application number: 201330822 1. Documentos considerados.-1. Documents considered.- A continuación se relacionan los documentos pertenecientes al estado de la técnica tomados en consideración para la realización de esta opinión. The documents belonging to the state of the art taken into consideration for the realization of this opinion are listed below.
Documento Document
Número Publicación o Identificación Fecha Publicación Publication or Identification Number publication date
D01 D01
EP 1020583 A1 (MARMORITH BETONINDUSTRIE et al.) 19.07.2000 EP 1020583 A1 (MARMORITH BETONINDUSTRIE et al.) 19.07.2000
D02 D02
US 3778951 A (OROSCHAKOFF G) 18.12.1973 US 3778951 A (OROSCHAKOFF G) 18.12.1973
D03 D03
JP H1150468 A (MORI HITOSHI) 23.02.1999 JP H1150468 A (MORI HITOSHI) 23.02.1999
D04 D04
EP 0143101 A2 (BEST BAUEISEN & STAHL) 29.05.1985 EP 0143101 A2 (BEST BAUEISEN & STAHL) 05/29/1985
2. Declaración motivada según los artículos 29.6 y 29.7 del Reglamento de ejecución de la Ley 11/1986, de 20 de marzo, de Patentes sobre la novedad y la actividad inventiva; citas y explicaciones en apoyo de esta declaración 2. Statement motivated according to articles 29.6 and 29.7 of the Regulation of execution of Law 11/1986, of March 20, on Patents on novelty and inventive activity; quotes and explanations in support of this statement La solicitud de patente describe un elemento estructural a modo de viga que comprende una base de hormigón pretensada con armadura activa longitudinal y armadura pasiva trasversal. Dispone también de al menos una estructura vertical de barras conformada por estribos verticales con forma de -Uinvertida a modo de montantes dispuestos consecutivamente y alternados con otra secuencia de estribos trasversales inclinados también con forma de -U-invertida a modo de diagonales y mas largos. Estas diagonales unen la parte superior de un montante vertical con la inferior del siguiente. Ambos tipos de estribos, verticales e inclinados, disponen de unas patillas en su parte inferior abierta la cual esta embebida en la base de hormigón. En la parte superior de los estribos existe al menos una barra longitudinal paralela a la base que recorre un número de estribos. The patent application describes a structural beam-like element comprising a prestressed concrete base with longitudinal active reinforcement and passive transverse reinforcement. It also has at least one vertical structure of bars formed by vertical stirrups in the form of -Uinverted as uprights arranged consecutively and alternated with another sequence of inclined transverse stirrups also with -U-inverted shape as diagonals and longer. These diagonals join the top of a vertical upright with the bottom of the next. Both types of stirrups, vertical and inclined, have pins in their open bottom which is embedded in the concrete base. At the top of the stirrups there is at least one longitudinal bar parallel to the base that runs through a number of stirrups. El documento D01 describe un elemento estructural prefabricado que comprende una base de hormigón y al menos una estructura vertical de barras, tal que la base de hormigón comprende una armadura activa longitudinal y una pasiva y una armadura pasiva trasversal. La estructura de barras está conformada por una pluralidad de estribos verticales con forma de –U-invertida a modo de montantes, dispuestos consecutivamente, (falta que se alternan con los estribos en diagonal). Los estribos disponen de patillas embebidas en la base de hormigón de manera que los estribos están unidos a la base de hormigón. En la parte superior está dispuesta al menos una barra longitudinal a modo de cordón, que recorre aun número de montantes consecutivos. Document D01 describes a prefabricated structural element comprising a concrete base and at least one vertical bar structure, such that the concrete base comprises an active longitudinal and a passive reinforcement and a transverse passive reinforcement. The bar structure is made up of a plurality of vertical stirrups with a U-inverted shape in the form of uprights, arranged consecutively, (missing that alternate with the diagonal stirrups). The stirrups have pins embedded in the concrete base so that the stirrups are attached to the concrete base. At the top, at least one longitudinal bar is arranged as a cord, which runs through a number of consecutive uprights. El documento D02 describe una armadura metálica para elementos estructurales tipo vigas-losa. Están conformadas por al menos dos parrillas que pueden ser ensambladas superponiéndose en uno de sus lados para formar una armadura longitudinal en forma de –U-adaptada a los distintos espesores. En la figura 34 utiliza una configuración de barras verticales y otras en diagonal, de manera que unen la parte superior de una barra vertical con la inferior de la siguiente. Forman los lados de una estructura en forma de –U-concebida como alternativa para grandes vigas. Estos lados quedan unidos mediante soldadura. Document D02 describes a metal reinforcement for structural elements beam-slab type. They are made up of at least two grills that can be assembled by superimposing on one of their sides to form a longitudinal reinforcement in the form of -U-adapted to the different thicknesses. In Figure 34, it uses a configuration of vertical and other diagonal bars, so that they join the upper part of a vertical bar with the lower part of the next one. They form the sides of a U-shaped structure conceived as an alternative for large beams. These sides are joined by welding. El documento D03 describe una viga con base tipo losa armada con parrilla pretensada. Dispone de una estructura de barras (1) que está conformada por una pluralidad de estribos verticales trasversales en forma de –U-invertida a modo de montantes dispuestos consecutivamente. La parte inferior queda embebida en las losa de hormigón. En la parte superior de los montantes está dispuesta una barra longitudinal que recorre un número de montantes. Document D03 describes a beam with slab base type reinforced with prestressed grill. It has a bar structure (1) that is made up of a plurality of vertical transverse stirrups in the form of -U-inverted as consecutive uprights. The lower part is embedded in the concrete slab. In the upper part of the uprights there is a longitudinal bar that runs through a number of uprights. El documento D04 describe una armadura de refuerzo para construcciones de hormigón. Dispone de refuerzos (4) en forma de una serie de estribos que interconectan mediante barras (9) formando una estructura longitudinal. Los extremos de los estribos están doblados para permitir una conexión fácil y rápida con las barras longitudinales a las que envuelven. Document D04 describes a reinforcement reinforcement for concrete constructions. It has reinforcements (4) in the form of a series of stirrups that interconnect by means of bars (9) forming a longitudinal structure. The ends of the stirrups are bent to allow an easy and fast connection with the longitudinal bars to which they wrap. Se considera que la solicitud de invención es nueva para todas sus reivindicaciones pero no tiene actividad inventiva para las reivindicaciones 1-4, 14,15,17, según los Art.6.1 y Art.8.1 de la Ley de Patentes 11/86. The invention application is considered new for all its claims but has no inventive activity for claims 1-4, 14,15.17, according to Art.6.1 and Art.8.1 of Patent Law 11/86. Informe del Estado de la Técnica Página 4/4 State of the Art Report Page 4/4
ES201330822A 2013-06-04 2013-06-04 PREFABRICATED STRUCTURAL ELEMENT Expired - Fee Related ES2434176B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
ES201330822A ES2434176B2 (en) 2013-06-04 2013-06-04 PREFABRICATED STRUCTURAL ELEMENT
PCT/ES2014/070320 WO2014195542A1 (en) 2013-06-04 2014-04-16 Pre-fabricated structural element

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
ES201330822A ES2434176B2 (en) 2013-06-04 2013-06-04 PREFABRICATED STRUCTURAL ELEMENT

Publications (2)

Publication Number Publication Date
ES2434176A1 true ES2434176A1 (en) 2013-12-13
ES2434176B2 ES2434176B2 (en) 2014-06-23

Family

ID=49641409

Family Applications (1)

Application Number Title Priority Date Filing Date
ES201330822A Expired - Fee Related ES2434176B2 (en) 2013-06-04 2013-06-04 PREFABRICATED STRUCTURAL ELEMENT

Country Status (2)

Country Link
ES (1) ES2434176B2 (en)
WO (1) WO2014195542A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2017492B1 (en) * 2016-09-19 2018-03-27 Betonson Prefab B V METHOD FOR BUILDING A PERSONAL ACCESS BUILDING

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3778951A (en) * 1969-11-28 1973-12-18 G Oroschakoff Reinforcement
EP0143101A2 (en) * 1983-08-26 1985-05-29 BEST - Baueisen- und Stahl-Bearbeitungsgesellschaft m.b.H. Reinforcement for reinforced concrete constructions
JPH1150468A (en) * 1997-08-05 1999-02-23 Hitoshi Mori Pc concrete strip footing and installation method thereof
EP1020583A1 (en) * 1999-01-11 2000-07-19 Marmorith Betonindustrie Beam bottom, method for the production thereof and for the production of a beam therewith

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1259548B (en) * 1963-12-04 1968-01-25 Max Gessner Dipl Ing Dipl Ing In reinforced concrete and prestressed concrete beams, plates and plate beams insertable bow basket for extremely high shear stresses
BE714016A (en) * 1968-04-22 1968-09-16
BE754926A (en) * 1970-05-12 1971-02-01 Anvar CONSTRUCTION PROCESS AND REINFORCEMENT FOR THE IMPLEMENTATION OF THE SAID PROCESS
ES2315154B1 (en) * 2007-02-13 2009-12-09 Harley Resources, Inc STRUCTURAL PANELS CONNECTED FOR BUILDINGS.

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3778951A (en) * 1969-11-28 1973-12-18 G Oroschakoff Reinforcement
EP0143101A2 (en) * 1983-08-26 1985-05-29 BEST - Baueisen- und Stahl-Bearbeitungsgesellschaft m.b.H. Reinforcement for reinforced concrete constructions
JPH1150468A (en) * 1997-08-05 1999-02-23 Hitoshi Mori Pc concrete strip footing and installation method thereof
EP1020583A1 (en) * 1999-01-11 2000-07-19 Marmorith Betonindustrie Beam bottom, method for the production thereof and for the production of a beam therewith

Also Published As

Publication number Publication date
WO2014195542A1 (en) 2014-12-11
ES2434176B2 (en) 2014-06-23

Similar Documents

Publication Publication Date Title
KR100971736B1 (en) Shear reinforcement with dual anchorage function each up and down
CN206090996U (en) Connected node of whole thick precast floor plank unit of assembled and floor unit thereof
CN103243804B (en) Pre-stressed combined frame of thin wall section steels and concrete, and construction method thereof
CN201785865U (en) Structure and system for house combining external prestress post tensioning method steel beam and pretensioning method prestress composite beam
CN103195172B (en) A kind of prefabrication and assembly construction concrete frame beam-column connection structure
CN103669194B (en) Based on the continuous rigid frame bridge of steel truss-concrete slab composite beam
CN106351374A (en) Connecting node of assembled whole thick prefabricated slab unit and slab unit thereof
CN102418381B (en) Building structure system combined with steel beam and pre-tensioned prestressing superposed beam and construction method for building structure system
US8578537B2 (en) Partially prefabricated structural concrete beam
KR100676627B1 (en) Shear reinforcement device arranged in the slab-column connection and the shear reinforcement structure using the device
RU2638597C2 (en) System and method for two-axle assembly light-weight concrete slab
ES2434176B2 (en) PREFABRICATED STRUCTURAL ELEMENT
KR20140125754A (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR101734304B1 (en) Manufacturing Method of Efficient Steel-Concrete Composite Girder, Construction Method of Continuous Bridges using such Composite Girder, and Continuous Bridges constructed by such Method
CN212104521U (en) Girdle truss and super high-rise building giant frame
RU165808U1 (en) SPAN STRUCTURE OF A CURTAIN BRIDGE
CN113802450A (en) Steel concrete composite beam structure and construction method
CN111893883B (en) Construction method of full-prefabricated assembled corrugated steel web short-tower cable-stayed bridge
CN203821668U (en) Prestress truss composite slab without extended end anchor bars
RU140555U1 (en) COMBINED MONOLITHIC REINFORCED CONCRETE COVERING
KR20130105091A (en) Light-weight ribbed truss deck consist of ribbed deck and steel bar truss
JP2018091056A (en) Prefabrication structure
CN112144660A (en) Herringbone stiff column base structure and construction method thereof
CN110528686A (en) Assembled architecture and its construction method
AU2009200214A1 (en) Composite Beam

Legal Events

Date Code Title Description
FG2A Definitive protection

Ref document number: 2434176

Country of ref document: ES

Kind code of ref document: B2

Effective date: 20140623

FD2A Announcement of lapse in spain

Effective date: 20210929