ES241950A1 - Improvements in the procedures for the construction of water packaging (Machine-translation by Google Translate, not legally binding)
- Google Patents
Improvements in the procedures for the construction of water packaging (Machine-translation by Google Translate, not legally binding)
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IndividualfiledCriticalIndividual
Priority to ES0241950ApriorityCriticalpatent/ES241950A1/en
Publication of ES241950A1publicationCriticalpatent/ES241950A1/en
Improvements in the procedures for the construction of water reservoirs, applicable to dams, marshes, river diversion walls or other similar applications, essentially characterized by the fact of building the wall or dam according to an embodiment in which the condition of absolute mass, but cement concrete is combined in suitable frames with loose stone fillings without there being any material that links them, starting the work by a general foundation based on concrete cement to form the plain of the work, building on it the first frame consisting of four vertical walls of concrete cement, which leave a space that is filled with well placed stone and then proceeds to pour on these layers concrete cement in sufficient quantity to infiltrate through the interstices of those and in addition is forming a lever surface that serves as a basis for next frame, performing the same operation and so on until the last or coronation of the work. (Machine-translation by Google Translate, not legally binding)
ES0241950A1958-05-161958-05-16Improvements in the procedures for the construction of water packaging (Machine-translation by Google Translate, not legally binding)
ExpiredES241950A1
(en)
Procedure for the foundation of prefabricated construction elements and means for carrying out the procedure (Machine-translation by Google Translate, not legally binding)
Method of construction ofa concrete core wallin a streambed which will effectively retain enough water to float by scow or other, the material needed to build over said core, a rockand spoil fill dam or weir
Improvements in the construction of construction elements from mixed fragile molds of concrete, mortar and similar (Machine-translation by Google Translate, not legally binding)
Procedure for the foundation of works below the underground water level in zanja de fundaciºn seca (Machine-translation by Google Translate, not legally binding)