EP4339377A1 - Pieu tubulaire et procédé de formation d'un pieu de fondation - Google Patents

Pieu tubulaire et procédé de formation d'un pieu de fondation Download PDF

Info

Publication number
EP4339377A1
EP4339377A1 EP22196155.0A EP22196155A EP4339377A1 EP 4339377 A1 EP4339377 A1 EP 4339377A1 EP 22196155 A EP22196155 A EP 22196155A EP 4339377 A1 EP4339377 A1 EP 4339377A1
Authority
EP
European Patent Office
Prior art keywords
pile
opening
base body
bulkhead plate
tubular base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
EP22196155.0A
Other languages
German (de)
English (en)
Inventor
Paul Scheller
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bauer Spezialtiefbau GmbH
Original Assignee
Bauer Spezialtiefbau GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bauer Spezialtiefbau GmbH filed Critical Bauer Spezialtiefbau GmbH
Priority to EP22196155.0A priority Critical patent/EP4339377A1/fr
Priority to PCT/EP2023/074411 priority patent/WO2024056480A1/fr
Publication of EP4339377A1 publication Critical patent/EP4339377A1/fr
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/28Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground

Definitions

  • the invention relates to a pile tube for forming a foundation pile in the ground with a tubular base body according to the preamble of claim 1.
  • the invention further relates to a method for forming a foundation pile in a hole in the ground, in which a pile tube is inserted into the hole and a hardenable medium is introduced into an annular space between a wall of the hole and an outer circumference of the pile tube, according to the preamble of claim 14 .
  • From the EP 2 930 275 A1 disclose a method and an arrangement for producing a foundation pile for a structure in water.
  • a borehole with a support pipe is first created in the ground.
  • the resulting hole is filled with a liquid, especially water.
  • a pile pipe is inserted into the cased borehole created in this way, for which a simple steel pipe with a tubular base body is used.
  • the external support pipe is then pulled out and the annular space between the inserted pile pipe standing on the bottom of the borehole and the surrounding bore wall is filled with a hardenable medium.
  • the surrounding water can remain within the pile tube.
  • the load-bearing capacity of the foundation pile created in this way is determined by the outer surface of the pile tube used in relation to the surrounding soil with the hardened medium in the surrounding annular space. If necessary, the interior space, which is only filled with water, can be used to install measuring or testing equipment.
  • the problem can arise that when the borehole base on which the pile pipe is placed is uneven, when the borehole is introduced curable medium in the annular space reinforces the flowable curable medium from below into the interior of the pile tube and fills at least part of the interior. This can lead to a significant increase in the need for curable medium.
  • an uncontrolled transfer of the hardenable mass or medium from the annular space into the interior of the pile tube can lead to defects in the surrounding annular space and thus to an impairment of the load-bearing capacity of the foundation pile.
  • the at least partially filled interior is not available to accommodate certain facilities.
  • a device for handling and inserting a pile pipe into a bore is known.
  • the device is designed to be attached to a suspension cable of a crane. Using gripping elements, an annular edge of the pile tube can be gripped in a non-positive manner.
  • the device is designed such that the pile tube can be pivoted from a horizontal storage position into a vertical insertion position.
  • the underwater drilling rig can be placed on a body of water.
  • a foundation hole is created using tubular elements.
  • the tubular elements can also be used to anchor the drilling device under water.
  • the invention is based on the object of specifying a pile tube and a method with which a foundation pile can be created particularly efficiently and reliably in a hole in the ground.
  • the pile tube according to the invention is characterized in that a bulkhead plate is arranged in an interior region of the tubular base body, which divides the interior region into a lower section and an upper section and seals them off from each other, and that at least one through opening on the bulkhead plate is arranged with a closure device with which the through opening can be closed and opened.
  • a basic idea of the invention is to design the pile tube in a special way to produce a foundation pile in the ground, with the interior of the tubular base body being divided into a lower section and an upper section by means of a bulkhead plate and these two sections of the interior of the tubular base body being sealed off from one another , i.e. can be separated from one another in a pressure-tight or essentially pressure-tight manner.
  • a further aspect of the invention is that at least one through opening with a closure device, in particular a valve, is arranged on the bulkhead plate, with which the through opening can be closed and opened.
  • a closure device in particular a valve
  • two different states can be set on the pile tube, namely a closed state, in which the two sections of the interior are sealed off from one another, and an open state, in which the two sections of the interior are open to one another and connected by lines.
  • the pile pipe can be easily inserted into a bore filled with liquid like a conventional pile pipe. Liquid present in the bore can easily flow into the interior of the pile tube, so that there is pressure equalization and the same filling level inside and outside the pile tube in the bore used.
  • the closure device If the at least one through opening is closed by the closure device to achieve the sealed off state, in particular when the pile tube is placed on the bottom of a borehole, the lower section in the interior of the tubular base body, which lies below the bulkhead plate, is sealed off from the upper section above it, i.e separated pressure-tight or essentially pressure-tight. If an annular space between the bore wall and the outside of the pile tube is now filled in a known manner with a hardenable medium, in particular a cement suspension or mortar, the arrangement according to the invention results in increased penetration of the hardenable medium Medium is prevented from entering the interior of the pile pipe from below, even if the borehole base is uneven.
  • a hardenable medium in particular a cement suspension or mortar
  • the hardenable mass or the medium which is preferably introduced into a lower region of the pile tube on the outer circumference, will tend to fill the annular outer space, which, due to its upwardly open top, displaces water, particularly due to a higher density than surrounding water upwards from the annular space.
  • the pile tube designed according to the invention enables a particularly efficient creation of a foundation pile in the ground, especially under water in a body of water, since undesirable penetration of the hardenable medium into the interior of the pile tube is reliably counteracted.
  • This reduces the consumption of hardenable medium, such as expensive cement suspension or mortar, and also enables reliable and controlled filling of the annular space between the foundation pile and the bore wall with the hardenable medium. This ensures the desired load-bearing capacity of the foundation pile created in this way.
  • the interior can also be kept largely free of hardenable medium and can continue to be used in a variety of ways.
  • a preferred embodiment of the invention is that in order to lower the pile tube into a hole in the ground which is filled with a liquid, the at least one through opening in the bulkhead plate is opened, and to introduce a hardenable medium into an annular space between the outer circumference of the pile tube and a wall of the bore which has at least one through opening closed.
  • the through opening it is also possible to keep the through opening open for a certain time when introducing the curable medium, so that a certain amount of curable medium can flow into the lower section of the pile tube. If a desired degree of filling of the lower section is reached, the at least one through opening can be closed, so that a further inflow of curable medium into the lower section is prevented.
  • at least a lower edge region of the pile tube can be specifically embedded in the hardenable medium on its outside and inside, so that after hardening a defined pile base is formed on the pile tube and this reliably closes off the pile tube at the bottom. This can also further increase the load-bearing capacity of the foundation pile.
  • one or more supply lines can be provided on the outside of the pile pipe or in the annular space itself to introduce the curable medium.
  • An advantageous embodiment of the invention is that at least one feed opening for feeding a curable medium is arranged on the bulkhead plate. The curable medium can thus be supplied at least partially within the interior of the pile tube. This enables a protected arrangement of one or more supply lines within the pile pipe.
  • At least one line extends from the at least one feed opening along the lower section of the tubular base body and that the at least one line extends through the tube wall of the tubular base body and opens into an outlet opening.
  • the at least one line for supplying the curable medium can run partially or entirely within the pile tube and in particular within the upper section and/or the lower section.
  • the passage through the bulkhead plate occurs via a feed opening, which may itself have a separate closure device.
  • a feed opening which may itself have a separate closure device.
  • the at least one line for supplying the medium is passed through the pipe wall, so that the line opens on the outside of the tubular base body into the annular space to be filled.
  • a plurality of outlet openings can also be formed along the circumference of the tubular base body, in particular at a lower end region.
  • a further improvement is achieved in an embodiment variant of the invention in that at least two lines extend along the lower section of the tubular base body and in that the at least two lines can be connected in series for a flushing operation.
  • the at least two lines can initially be connected in parallel to supply the curable medium, so that the annular space can be filled particularly quickly by using both lines.
  • the two lines as a whole or at least sections of the lines can be connected in series via a switchable connecting device, i.e. connected to one another in terms of lines.
  • a switchable connecting device i.e. connected to one another in terms of lines.
  • a check valve it may be expedient for a check valve to be arranged in the area of the at least one feed opening.
  • the check valve can in particular be designed in such a way that the downward sealing effect is not impaired by the feed opening in the bulkhead plate. This means that the check valve is arranged in such a way that supply can take place from top to bottom, but not from bottom to top.
  • the check valve can also be adjustable so that in certain cases the check function can be canceled in order to direct liquid through the feed opening from bottom to top in certain cases.
  • the check valve can also be switched so that it is blocking overall.
  • the check valve can thus form a controllable closure device with an additional check function as safety.
  • the bulkhead plate has a coupling element to which a feed device for feeding a curable medium to the feed opening can be coupled.
  • the bulkhead plate basically has a preferably metallic plate which is fastened, in particular welded, to a designated position along the inner wall of the tubular base body.
  • a line does not have to be formed entirely within the interior of the pile tube.
  • the curable medium can be supplied at least over a partial area of the pile tube by means of a separate feed device that can be inserted into the pile tube.
  • this separate feeding device can be coupled to a coupling element provided for this purpose on the bulkhead plate. This enables a defined positioning and connection of the feed device with the feed opening and the at least one line along the lower section on the pile pipe.
  • the feed device After filling the annular space, the feed device can be detached or uncoupled from the bulkhead plate again and used to form another foundation pile on another pile pipe.
  • a particularly advantageous embodiment variant consists in that the closure device is designed to be actuated by the feed device in the coupled state. If a feed device is coupled in the bulkhead plate in order to introduce curable medium, the coupling process can cause the at least one through opening to be closed. This can be done, for example, via a mechanical lever and/or flap arrangement. This makes it possible to ensure that the lower area is reliably sealed off when the curable medium is fed via the feed device.
  • an adjusting device on the feed device it is in principle also possible to open and close the at least one through opening in a targeted manner by appropriately controlling the closure device, so that a targeted and defined inflow of a curable medium into the lower section can also be achieved.
  • the actuating device can in particular comprise a motor or actuating cylinder.
  • the closure device is designed to close the at least one through opening when curable medium is supplied.
  • a further embodiment of the invention is that the bulkhead plate is attached to the tubular base body in a fixed or detachable manner.
  • a fixed arrangement of the bulkhead plate, for example by welding, is simple and cost-effective in terms of manufacturing technology.
  • the bulkhead plate is firmly connected to the pile tube and remains as a lost element in the foundation pile.
  • the bulkhead plate can be connected to the tubular base body in a detachable and in particular sealing manner, in particular at its outer area. After the medium has been introduced and hardened to form the foundation pile, it is therefore possible to detach the bulkhead plate from the tubular base body and recover it from the foundation pile.
  • the bulkhead plate can thus be used repeatedly on different pile tubes to form additional foundation piles.
  • a releasable holding of the bulkhead plate can preferably take place via an appropriate clamping or clamping device or a screw or bayonet connection.
  • a fastening element such as an annular fastening flange, can also be arranged on the inner wall of the tubular base body, on which the releasable bulkhead plate can be placed and releasably fastened.
  • all suitable fastening options can be used which are suitable for releasably and sealingly attaching a plate to a tubular inner wall.
  • a particularly efficient supply of the curable medium, in particular via a line to the supply opening on the bulkhead plate can be achieved in that an inlet funnel is arranged at the supply opening.
  • Several feed openings can also be provided, at which some or all of the inlet funnels are arranged.
  • An efficient and quick line connection can be established via the inlet funnels.
  • the funnels can also be referred to as inlet funnels, which make it easier to insert and thus connect the outlet device and the feed opening.
  • At least one holding element in particular an annular shoulder, projecting radially inwards is arranged on an inside of the tubular base body.
  • the bulkhead plate can be attached to the ring shoulder in a fixed or detachable manner.
  • an annular sealing element is arranged on a lower edge of the tubular base body of a pile tube.
  • the sealing element can in particular be an annular rubber element, which can compensate for unevenness in the bottom of a borehole and thus seal a joint between the lower edge of the pile tube and the bottom of the borehole.
  • the sealing element can be solid or designed with a cavity for an improved compensating effect.
  • an actively operable sealing element can also be provided, such as an annular, hose-like sealing element that can be inflated with compressed air.
  • the arrangement of the sealing element can also basically be used independently of the arrangement of a bulkhead plate on a pile pipe and can be viewed as an independent invention.
  • the method according to the invention is characterized in that a pile pipe according to the invention is used, as described above.
  • the process can be used to achieve the advantages described above when creating a Foundation pile can be achieved.
  • the process can in principle be used on land. It is particularly advantageous that the method is used to form a foundation pile underwater, in particular on a body of water or seabed.
  • a preferred embodiment variant consists in that when the pile tube is lowered into the hole in the ground, which is filled with liquid, the at least one through opening is opened and in order to introduce the curable medium into the annular space between the outer circumference of the pile tube and the wall the hole at least one through opening is closed. This allows the foundation pile to be manufactured particularly reliably and cost-effectively.
  • a pile tube 10 with a tubular base body 12 is provided.
  • a bulkhead plate 20 directed transversely to the longitudinal axis of the tubular base body 12, which divides the interior region 13 into a lower section 14 and an upper section 15 and separates them from each other.
  • An annular sealing element 19 can be arranged on a lower edge of the tubular base body 12, with which the pile tube 10 can be placed on a borehole base in as sealing as possible.
  • the bulkhead plate 20 has two schematically indicated through openings 22, which can be opened or closed in a targeted manner by means of a closure device 24, which is also schematically indicated.
  • a feed device 30 with two schematically indicated feed openings 32, each with an insertion funnel 34, is arranged, as will be described in more detail below in connection with Fig. 3 is described.
  • the feed openings 32 with the insertion funnels 34 serve to supply a hardenable medium, in particular mortar or cement suspension, whereby the hardenable medium can be guided below the bulkhead 20 via lines 26 to a lower end region of the tubular base body 12.
  • the lines 26 extend through a tube wall 16 of the base body 12 and each open into an outlet opening 28 on the outer circumference 17 of the base body 12. Curable medium can thus be passed over an inner area 13 of the pile tube 10 to a lower end area and via the outlet openings 28 exit outside the pile tube 10, as described in more detail below in connection with Fig. 2 is explained.
  • FIG. 2 A lower end region of a pile tube 10 according to the invention is shown schematically and not to scale, which is inserted into a hole 4 in the ground 1. Only the lower area of the hole 4 is shown, whereby the hole 4 can have a depth of several meters, typically between 5m and 30m.
  • the bore 4 is filled with a liquid, in particular water or another supporting liquid, for support, so that the bore 4 does not collapse even at greater bore depths.
  • a support tube can also be provided at least in some areas.
  • the pile tube 10 with a bulkhead plate 20 can be easily inserted into a bore 4 filled with liquid in this way if the through openings 22 on the bulkhead plate 20 are opened by the closure devices 24.
  • the through openings 22 can be closed again with the closure devices 24.
  • Hardenable medium can now be introduced into the bore 4 via the lines 26, wherein the curable medium is supplied within the pile pipe 10 in the lower region with the lines 26 and passes through the pipe wall 16 at the lower end region and can exit into an annular space 6 via the outlet opening 28.
  • the annular space 6 is formed between an outer circumference 17 of the tubular base body 12 and a substantially cylindrical wall 8 of the bore 4.
  • the curable medium can fill the annular space 6 from bottom to top due to its higher density compared to the liquid in the bore 4. Liquid is displaced upwards from the annular space 6 by the curable medium.
  • the intended bulkhead plate 20 seals a lower section 14 of the interior area 13 of the pile tube 10 at the top with the through openings 22 closed.
  • the liquid in the lower section 14 of the pile tube 10 cannot be displaced upwards, so that no or hardly hardenable medium can penetrate into the inner region 13 of the pile tube 10.
  • the interior area 13 can be reliably kept clear and curable medium or suspension can be saved.
  • Fig. 3 is the feed device 30 of the pile pipe 10 Fig. 1 shown in more detail.
  • the feed device 30 can have a cup-shaped receptacle 31, which is attached in a central region of the bulkhead plate 20.
  • the feed openings 32 for the downwardly leading lines 26 are formed in the cup-shaped receptacle 31.
  • the feed openings 32 have introduction funnels 34 at their upper area.
  • the feed openings 32 can also be designed with check valves 36, shown only schematically, which prevent undesirable backflow of the curable medium from the lines 26 in the example shown.
  • a handling device 50 can be used to supply the curable medium Fig. 4 be used.
  • the handling device 50 has a base body 52 with a cover plate 54, on which an attachment element 58 for placing or arranging the handling device 50 on or on a pile tube 10 is arranged.
  • the handling device 50 in the illustrated embodiment can be releasably attached to an inside of the pile tube 10 with at least one clamping or gripping element 57 via a gripping device 56, which can alternatively or additionally also be designed as a non-positive clamping device.
  • a gripping device 56 which can alternatively or additionally also be designed as a non-positive clamping device.
  • several gripping elements 57 are arranged along the circumference of the approximately tubular or barrel-shaped base body 52.
  • a pile pipe 10 can already be grabbed from a pile pipe storage on a ground surface or a watercraft.
  • the pile tube 10 can have any position when gripped, for example horizontally or vertically.
  • the handling device 50 can be connected to a lifting device, in particular a crane, via a holding element 55 at the upper end region of the base body 52. A pile tube 10 can thus be inserted from a storage position into a bore 4 in the ground 1 via the handling device 50.
  • the handling device 50 is provided with a feed device 60, which is only indicated schematically, which in the exemplary embodiment shown has delivery lines 64 which extend from an inlet device 62 at the upper end of the base body 52 to a lower outlet device 66.
  • the outlet device 66 is designed to be connected to a pile pipe 10 via the insertion funnel 34 of the feed device 30 Fig. 3 to engage in the supply of a curable medium.
  • a corresponding coupling unit can be provided on the handling device 50 in order to ensure precise positioning and position securing in cooperation with the coupling element 23 on the feed device 30 of the pile tube 10.
  • a supply line 80 which can also be referred to as an umbilical, curable medium, energy and/or data can be supplied via a detachable connecting device 70, the curable medium being transferred to the inlet device 62 at the upper end region of the base body 52.
  • a single supply line or separate lines can be provided.
  • the connecting line 80 and/or the hoist can be detached from the holding element 55, whereby the handling device 50 can remain on the pile pipe 10 as an additional load, at least until the curable medium is used to form the foundation element in soil 1 has hardened.
  • the handling device 50 can then be detached from the pile pipe 10 and retrieved.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)
EP22196155.0A 2022-09-16 2022-09-16 Pieu tubulaire et procédé de formation d'un pieu de fondation Pending EP4339377A1 (fr)

Priority Applications (2)

Application Number Priority Date Filing Date Title
EP22196155.0A EP4339377A1 (fr) 2022-09-16 2022-09-16 Pieu tubulaire et procédé de formation d'un pieu de fondation
PCT/EP2023/074411 WO2024056480A1 (fr) 2022-09-16 2023-09-06 Tube de pieu et procédé de formation d'un pieu de fondation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP22196155.0A EP4339377A1 (fr) 2022-09-16 2022-09-16 Pieu tubulaire et procédé de formation d'un pieu de fondation

Publications (1)

Publication Number Publication Date
EP4339377A1 true EP4339377A1 (fr) 2024-03-20

Family

ID=83361215

Family Applications (1)

Application Number Title Priority Date Filing Date
EP22196155.0A Pending EP4339377A1 (fr) 2022-09-16 2022-09-16 Pieu tubulaire et procédé de formation d'un pieu de fondation

Country Status (2)

Country Link
EP (1) EP4339377A1 (fr)
WO (1) WO2024056480A1 (fr)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1999051821A1 (fr) * 1998-04-02 1999-10-14 Suction Pile Technology B.V. Structure marine
WO2008012414A2 (fr) * 2006-07-27 2008-01-31 Technip France Pile de succion adaptee aux faibles profondeurs
US20100296875A1 (en) 2007-10-05 2010-11-25 Aquamarine Power Limited Underwater foundation
DE102010035025A1 (de) * 2010-08-20 2012-02-23 Hilgefort Gmbh Anlagenkomponenten Und Apparatebau Gündungsstruktur für ein Wasserbauwerk und Verfahren zum Errichten einer Gründungsstruktur
DE202013009850U1 (de) * 2013-12-06 2015-03-09 Emilio Reales Bertomeo Rammpfahl mit einem Schott zur Verankerung einer Gründungsstruktur eines Offshore-Bauwerks im Meeresboden
EP2930275A1 (fr) 2014-04-08 2015-10-14 Herrenknecht AG Système et procédé de fabrication d'une fondation pour un ouvrage situé dans l'eau
WO2021180515A1 (fr) 2020-03-11 2021-09-16 Itrec B.V. Outil de retournement et de levage

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1999051821A1 (fr) * 1998-04-02 1999-10-14 Suction Pile Technology B.V. Structure marine
WO2008012414A2 (fr) * 2006-07-27 2008-01-31 Technip France Pile de succion adaptee aux faibles profondeurs
US20100296875A1 (en) 2007-10-05 2010-11-25 Aquamarine Power Limited Underwater foundation
DE102010035025A1 (de) * 2010-08-20 2012-02-23 Hilgefort Gmbh Anlagenkomponenten Und Apparatebau Gündungsstruktur für ein Wasserbauwerk und Verfahren zum Errichten einer Gründungsstruktur
DE202013009850U1 (de) * 2013-12-06 2015-03-09 Emilio Reales Bertomeo Rammpfahl mit einem Schott zur Verankerung einer Gründungsstruktur eines Offshore-Bauwerks im Meeresboden
EP2930275A1 (fr) 2014-04-08 2015-10-14 Herrenknecht AG Système et procédé de fabrication d'une fondation pour un ouvrage situé dans l'eau
WO2021180515A1 (fr) 2020-03-11 2021-09-16 Itrec B.V. Outil de retournement et de levage

Also Published As

Publication number Publication date
WO2024056480A1 (fr) 2024-03-21

Similar Documents

Publication Publication Date Title
DE1927864C3 (de) Vorrichtung zum Einzementieren eines Futterrohrstranges
DE1634233A1 (de) Verfahren zum Verankern von Bauwerken und Bauelementen im Erdboden mit Hilfe von Stabankern
EP3485097B1 (fr) Vibrofonceur
DE60124942T2 (de) Bohrlochkern-bohrvorrichtung
DE3535320A1 (de) Verfahren und vorrichtung zum setzen eines stab-, draht- oder rohrfoermigen einbauteils in eine bodenformation mit drueckendem wasser
DE1918201A1 (de) Zementiervorrichtung fuer Tiefbohrungen
EP3330441B1 (fr) Dispositif de réduction d'eau d'aval et procédé de réduction
DE10225980A1 (de) Verfahren zur auftriebsgesicherten Verankerung von Betonkörpern
EP2246482B1 (fr) Procédé et dispositif d'établissement d'un élément de fondation à friction partiellement réduite
EP4339377A1 (fr) Pieu tubulaire et procédé de formation d'un pieu de fondation
DE3726472C2 (fr)
EP0177623A1 (fr) Méthode et installations pour l'installation de puits forés, en particulier ceux produisant de l'eau
EP1580325B1 (fr) Dépot pour béton et procédé de rétraction d' équipement de forage d' une forure
EP2258903A1 (fr) Procédé et installation de réalisation de colonnes vibrées au niveau du sol d'étendues d'eau
DE3115182A1 (de) Vorrichtung zum verteilen einer vergussmasse wie zement in hohlkoerpern
EP1328687A1 (fr) Dispositif et procede de production de colonnes de materiaux au fond des eaux
EP4339378A1 (fr) Dispositif de manipulation et procédé de préhension et d'insertion d'un tube de pieu dans un forage
WO2024056237A1 (fr) Procédé de formation d'un pieu de fondation dans le sol
DE3410830C2 (fr)
EP3564446B1 (fr) Dispositif d'extraction sous marine et procédé d'extraction
DE102010025717B4 (de) Verschließen und Abdichten eines Unterwasser-Bohrlochs
EP0346941B1 (fr) Méthode pour réaliser des éléments de construction dans le sol tels que des pieux, des ancrages ou similaires ainsi qu'un dispositif pour l'application de cette méthode
EP3542000B1 (fr) Procédé de démantèlement de structures de fondation en mer
DE3000776A1 (de) Bohrloch zum aussohlen unterirdischer salzlagerstaetten und verfahren zum betrieb eines solchen bohrloches
DE3841316C2 (fr)

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20230905

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR