EP4234833A1 - Multi-piece pre-assembled raft foundation and construction method thereof - Google Patents

Multi-piece pre-assembled raft foundation and construction method thereof Download PDF

Info

Publication number
EP4234833A1
EP4234833A1 EP23157988.9A EP23157988A EP4234833A1 EP 4234833 A1 EP4234833 A1 EP 4234833A1 EP 23157988 A EP23157988 A EP 23157988A EP 4234833 A1 EP4234833 A1 EP 4234833A1
Authority
EP
European Patent Office
Prior art keywords
foundation
rebars
pivot
sections
columns
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
EP23157988.9A
Other languages
German (de)
French (fr)
Inventor
Fu-yuan LU
Ju-Chuan Ko
Ying-ying LU
Chien-Hui Lu
Cheng-Yu Lee
Mei-Hua Chien
Guang-Le Su
Taner SEN
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cheng Chi Steel Co Ltd
Jyu Sin Steel Co Ltd
Original Assignee
Cheng Chi Steel Co Ltd
Jyu Sin Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cheng Chi Steel Co Ltd, Jyu Sin Steel Co Ltd filed Critical Cheng Chi Steel Co Ltd
Publication of EP4234833A1 publication Critical patent/EP4234833A1/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/08Reinforcements for flat foundations
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0604Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
    • E04C5/0609Closed cages composed of two or more coacting cage parts, e.g. transversally hinged or nested parts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0636Three-dimensional reinforcing mats composed of reinforcing elements laying in two or more parallel planes and connected by separate reinforcing parts
    • E04C5/064Three-dimensional reinforcing mats composed of reinforcing elements laying in two or more parallel planes and connected by separate reinforcing parts the reinforcing elements in each plane being formed by, or forming a, mat of longitunal and transverse bars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form

Definitions

  • the present invention related to a type of raft foundation, specially, a multi-piece pre-assembled raft foundation and construction method thereof.
  • the main objective of the present invention is to provide a pre-assembled raft foundation that reduce construction labor and time.
  • the secondary objective of the present invention is to provide a pivot element for adjusting the installation location so that the rebar installation is more convenient and simple, and the cost of material consumption is less.
  • the pre-assembled raft foundation of the present invention comprises the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars.
  • the bottom layer rebar of the foundation slab comprises bottom layer sections and the first vertical sections that are connected with the bottom layer sections; the bottom layer section and the first vertical section are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars.
  • the foundation steel columns are installed on the bottom layer section, wherein the foundation steel column comprises columns and vertical pivot sections that are installed at the top of the column.
  • the upper layer rebars of the foundation slab are installed on the bottom layer rebars of the foundation slab, wherein the upper layer rebar of the foundation slab comprises the top layer sections and second vertical sections that are connected with the top layer sections; the top layer section and the second vertical section are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars.
  • the foundation rebar installed on the side of the foundation steel columns, comprises a plurality of beams and columns, horizontal pivot sections that are installed at both ends of the beams and columns, and steel mesh structures, wherein the plurality of beams and columns are tied together by circular rebars and are secured by steel mesh structures installed above and below the beams and columns.
  • the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars are assembled into a pre-assembled raft foundation.
  • the pre-assembled raft foundation construction method of the present invention comprises the following steps.
  • the advantages of the multi-piece pre-assembled raft foundation and the construction method thereof include: pre-assembly of the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation in the factory, so that construction workers can skip the step of tying rebars from the start; the construction time is significantly reduced; and the number of construction workers required can be less.
  • the pre-assembled raft foundation 1 of the present invention comprises the bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2.
  • the bottom layer rebars of the foundation slab 11 comprises bottom layer sections 111 and the first vertical sections 112 that are connected with the bottom layer sections 111; the bottom layer section 111 and the first vertical section 112 are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars.
  • the foundation steel columns 12 are installed on the bottom layer section 111 (as shown in Fig. 3 ), wherein the foundation steel column 12 comprises columns 121 and vertical pivot sections 122 that are installed at the top of the column 121.
  • the upper layer rebars of the foundation slab 13 are installed on the bottom layer rebars of the foundation slab 11 (as shown in Fig. 3 ).
  • the upper layer rebar of the foundation slab 13 comprises the top layer sections 131 and second vertical sections 132 that are connected with the top layer sections 131; the top layer section 131 and the second vertical section 132 are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars, wherein the top layer section 1311 has a hollow section 1311 therewithin so that the foundation steel column can be installed therein; when the installation is completed, rebars are used to connect therewith, as show in Fig. 1 .
  • the foundation rebar 2 installed on the side of the foundation steel columns 12, comprises a plurality of beams and columns 21, horizontal pivot sections 22A that are installed at both ends of the beams and columns 2, and steel mesh structures 23, wherein the plurality of beams and columns 21 are tied together by circular rebars and are secured by steel mesh structures 23 installed above and below the beams and columns 21.
  • the horizontal pivot sections 22A can have a form of a screw rod, or the horizontal pivot sections 22B can have a form of a cylinder, or other forms. Different forms are applied to different construction methods or to different pivot elements 5 for connection.
  • the pivot element 5 can be a first pivot element 5A (as shown in Fig. 10 ), or a second pivot element 5B (as shown in Fig. 13 ), or a third pivot element 5C (as shown in Fig. 18 ) for connecting and holding rebars in place.
  • the bottom layer rebars of the foundation slab 11 (as shown in Fig. 3 ), foundation steel columns 12 (as shown in Fig. 4 ), upper layer rebars of the foundation slab (as shown in Fig. 5 ), and foundation rebars are assembled to form a pre-assembled raft foundation 1.
  • the pre-assembled raft foundation construction method 3 of the present invention comprises the following steps.
  • the bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2 of the present invention are manufactured in the factory in advance according to the dimensions of the specification issued by the construction site. Using the method of tying or welding, a plurality of U-shaped rebars, steel bars, stirrups, and tie bars are configured into the structures of bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2.
  • step 42 of Fig. 9 after the bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2 are produced, the aforementioned parts can be shipped directly to the construction site for assembly.
  • workers at the construction site simply place and fix the bottom layer rebars of the foundation slab 11 in position to the ground or spread footing, place the foundation steel columns 12 on the bottom layer rebars of the foundation slab 11, lay down the upper layer rebars of the foundation slab 13 on the bottom layer rebars of the foundation slab 11 and make the foundation steel columns 12 penetrate through the hollow sections 1311, and finally install the foundation rebars 2 to penetrate through the sides of the foundation steel columns 12.
  • Construction workers repeat the aforementioned assembling steps so that the horizontal pivot sections 22A of the foundation rebars 2 and the foundation steel columns 12 are assembled to connect to each other.
  • the assembly process is completed.
  • step 43 of Fig. 9 after the assembly process is completed, construction workers can install the pivot elements 5 on the horizontal pivot sections 22A, making the horizontal pivot sections 22A of the foundation rebars 2 be connected to each other as one piece to form a raft foundation.
  • a formwork not shown in the figure
  • wet concrete is poured in the formwork.
  • the pre-assembled raft foundation construction method of the present invention is completed.
  • the pivot element 5 used in the present invention can be one of the following three forms.
  • the first form is a first pivot element 5A (as shown in Fig. 10 );
  • the second form is a second pivot element 5B (as show in Fig. 13 ), and
  • the third form is a third pivot element 5C. Descriptions of the aforementioned pivot elements 5 are provided in detail.
  • a single mounting element 6 is installed on any one of the two horizontal pivot sections 22A.
  • the first pivot element 5A is installed on one of the horizontal pivot sections 22A and then the other horizontal pivot sections 22A is inserted into the first pivot element 5A for fastening.
  • the first pivot element 5A is rotated to gradually fasten these two horizontal pivot sections 22A together toward the first pivot element 5A.
  • the mounting element 6 is fastened to eliminate the gap between the first pivot element 5A and the two horizontal pivot sections 22A.
  • the first pivot element 5A and the horizontal pivot sections 22A can be with multi-start threads, for example, two-start threads, three-start threads, or multi-start threads.
  • the threads of the internal guide section 512 and the horizontal pivot sections 22A can be right-hand threads of the same direction, or left-hand threads of the same direction. Therefore, the first pivot element 5A can rotate to fine-tune the lock mounting position when the lock mounting distance remains unchanged, and then a single mounting element 6 is used to lock the position of the first pivot element 5A.
  • the aforementioned internal guide section 512 and the horizontal pivot section 22A can also be with right-hand and left-hand threads of different directions.
  • the internal guide section 512 has right-hand threads and the horizontal pivot sections 22A have left-hand threads, or the internal guide section 512 has left-hand threads and the horizontal pivot sections 22A have right-hand threads.
  • Fig. 12 While using the first pivot element 5A, the horizontal pivot sections 22A of two foundation rebars 2 that are set to be fastened to each other can be installed with a mounting element 6 separately in advance.
  • a first pivot element 5A is installed on one of the horizontal pivot sections 22A and then the other horizontal pivot sections 22A to be connected is aligned to the first pivot element 5A for fastening.
  • the first pivot element 5A is rotated to gradually fasten these horizontal pivot sections 22A together toward the first pivot element 5A.
  • the mounting elements 6 placed at both ends of the first pivot element 5A separately to eliminate the gaps among the two horizontal pivot sections 22A, the first pivot element 5A and the beams and columns.
  • the first pivot element 5A and the horizontal pivot sections 22A can be with multi-start threads, for example, two-start threads, three-start threads, or multi-start threads.
  • the threads of the internal guide section 512 and the horizontal pivot sections 22A can be right-hand threads or left-hand threads of the same direction. Therefore, the first pivot element 5A can rotate to fine-tune the lock mounting position when the lock mounting distance remains unchanged, and then two mounting elements 6 are used to lock the position of the first pivot element 5A.
  • the aforementioned internal guide section 512 and the horizontal pivot section 22A can also be with right-hand and left-hand threads of different directions.
  • the internal guide section 512 has right-hand threads and the horizontal pivot sections 22A have left-hand threads, or the internal guide section 512 has left-hand threads and the horizontal pivot sections 22A have right-hand threads.
  • the second form of the pivot element 5 is a second pivot element 5B: Please refer to Fig. 13 together with Fig. 6 .
  • the second pivot element 5B is a frame body 52, wherein the frame body 52 has a plurality of positioning holes 521 thereon, for the horizontal pivot sections 22A to insert, and a containing space 522 that is connected through the positioning holes 521.
  • the second pivot element 5B installed in the containing space 522, holds up the mounting element 6 to be set on the horizontal pivot sections 22A, so that the horizontal pivot sections 22A are mounted on the frame body 52.
  • enhancing elements 523 parallel to the positioning holes 521, can be added to the frame body 52 to make the second pivot element 5B more solid and stronger.
  • the second pivot elements 5B can be used to connect the foundation rebars 2 that penetrate the foundation steel columns 12.
  • the mounting elements 6 and washers 7 are installed on the horizontal pivot sections 22A.
  • the second pivot elements 5B are inserted into the horizontal pivot sections 22A, followed by installing the mounting elements 6 and washers 7 to the horizontal pivot sections 22A again. Last, all mounting elements 6 are fastened.
  • Fig. 17 In addition to the second pivot elements 5B being used to connect two foundation rebars 2 and the foundation steel columns 12, enhancing elements 523 are added.
  • the installation process is the same as the previous descriptions.
  • the mounting elements 6 and washers 7 are installed on the horizontal pivot sections 22A.
  • the second pivot elements 5B are inserted into the horizontal pivot sections 22A, followed by installing the mounting elements 6 and washers 7 to the horizontal pivot sections 22A again.
  • all mounting elements 6 are fastened.
  • the third form of the pivot element 5 is a third pivot element 5C: Please refer to Fig. 18 to Fig. 21 , together with Fig. 7 .
  • the third pivot element 5C is a backing plate 53 made of carbon-based materials, wherein the backing plate 53 is installed on the back of two horizontal pivot sections 22B of the foundation rebars 2 respectively, to fasten these two horizontal pivot sections 22B of the foundation rebars 2 by welding.
  • the backing plate 53 can withstand a high temperature of over 1500°C ;the cross section of the backing plate 53 has an arc shape or a flat shape, or is a flat plate with a groove 531.
  • pivot element 5 when the aforementioned three different forms of pivot element 5 are assembled, there are different forms of assembly.
  • the assembly methods of the first pivot element 5A, the second pivot element 5B, and the third pivot element 5C are described separately as follows.
  • Fig. 22 Place all first pivot elements 5A on the same plane with the horizontal pivot sections 22A, or place all first pivot elements 5A on different planes with the horizontal pivot sections 22A in an interlacing way.
  • the advantage of adopting an interlacing form is to prevent the horizontal pivot sections 22A and the beams and columns 21 to break up simultaneously upon impact.
  • a foundation rebar 2 reaching foundation steel column 12 in the horizontal direction is picked as the standard; the same applies to another foundation rebar 2 that reaches a foundation steel column12 in the vertical direction. If the length of beams and columns 21 of the foundation rebar 2 is not long enough, the beams and columns 21 can be extended with combining steel bars connected by the first pivot elements 5A. Therefore, two foundation rebars 2 can extend and insert into the foundation steel column 12 while these two foundation rebars 2 are connected to each other.
  • the location of the connection joint of the first pivot element 5A can be inside the foundation steel columns 12 and a proper location on the side of the foundation steel columns 12.
  • the beams and columns 21 of two foundation rebars 2 penetrate through the foundation steel columns 12, and are connected and fastened with the horizontal pivot sections 22A within the foundation steel columns 12 using the first pivot elements 5A.
  • This process is a connection method of column-foundation (inside of column) (as shown in Fig. 23 ).
  • the same connecting and fastening operation can be applied to a proper location on the side of the foundation steel columns 12.
  • the mounting and connecting method of the first pivot element 5A is to fasten and mount the beams and columns 21, which are connected to each other in pairs, having the degrees of freedom to be zero so that rotation and movement will not occur and the foundation becomes stronger and firm.
  • the mounting and connecting method of the second pivot element 5B is to fasten and mount the beams and columns 21, which are connected to each other in pairs, having the degrees of freedom to be zero so that rotation and movement will not occur and the foundation becomes stronger and firm.
  • the third pivot element 5C is used to connect two foundation rebars 2 and a foundation steel column 12.
  • the third pivot element 5C is installed on the back of the horizontal pivot sections 22B of two foundation rebars 2 separately that are connected to the foundation steel column 12 individually. Using the welding method, solder in high temperature piles up on the third pivot element 5C and gradually fills up the gap between these two horizontal pivot sections 22B; these two horizontal pivot sections 22B eventually become connected to each other at last.
  • connection joint of the third pivot element 5C can be inside the foundation steel columns 12 and a proper location on the side of the foundation steel columns 12.
  • the beams and columns 21 of two foundation rebars 2 penetrate through the foundation steel columns 12, and are welded to the horizontal pivot sections 22B within the foundation steel columns 12 using the third pivot elements 5C.
  • This process is a connection method of column-foundation (inside of column) (as shown in Fig. 27 ).
  • the same welding operation can be applied to a proper location on the side of the foundation steel columns 12.
  • a foundation rebar 2 is inserted horizontally through the foundation steel column 12 and the horizontal pivot section 22B is in contact with the horizontal pivot section 22B of another foundation rebar 2.
  • a third pivot element 5C is used to connect these two horizontal pivot section 22B separately.
  • the mounting and fastening method of the third pivot element 5C is to fasten and mount the beams and columns 21, which are connected to each other in pairs, having the degrees of freedom to be zero, so that rotation and movement will not occur and the foundation becomes stronger and firm.
  • the aforementioned three forms of pivot connection can be applied by construction workers at the construction site. Construction workers can connect one foundation rebar 2 with different forms of a pivot element 5. These three connection methods of the pivot element 5 can retain and mount the beams and columns, which are connected to each other in pairs, restrain beams and columns from rotating, and increase the stability and firmness of the foundation.
  • the advantages of the multi-piece pre-assembled raft foundation and the construction method thereof is to pre-assemble the bottom layer rebars of the foundation slab 11, foundation steel columns 12, the upper layer rebars of the foundation slab 13, and the foundation rebars 2 completely prior to being transported to the construction site for further assembly. Therefore, the construction workers no longer have to bundle rebars, and the effect of shortening the construction time and reducing the number of needed construction workers can be achieved.

Abstract

A multi-piece pre-assembled raft foundation and the construction method thereof is to pre-assemble the bottom layer rebars of the foundation slab, the foundation steel columns, the upper layer rebars of the foundation slab, and the foundation rebars completely prior to being transported to the construction site for further assembly. Therefore, the construction workers no longer have to bundle or weld rebars, and the effect of shortening the construction time and reducing the number of needed construction workers can be achieved.

Description

    [TECHNICAL FIELD]
  • The present invention related to a type of raft foundation, specially, a multi-piece pre-assembled raft foundation and construction method thereof.
  • [DESCRIPTION OF PRIOR ART]
  • In general, during the construction, all needed rebars will be delivered to and stored in the construction site for construction workers to tie the rebars and build a formwork before grouting. According to the current construction practice, from the start of tying rebars to the last task of demolding rely on labor-based construction.
  • Therefore, to construct a building is considered a labor-intensive operation. When a construction project highly depends on workers to carry out the task will likely result in a slow progress in construction and the vast volume of unused rebars piled up in the construction site may heighten the risk of property theft. Furthermore, when there is a need of secondary grouting for a structure, if it is not carefully done, cold joints may occur after the grouting that damage the concrete structure.
  • [SUMMARY]
  • The main objective of the present invention is to provide a pre-assembled raft foundation that reduce construction labor and time.
  • The secondary objective of the present invention is to provide a pivot element for adjusting the installation location so that the rebar installation is more convenient and simple, and the cost of material consumption is less.
  • To achieve the aforementioned objectives, the pre-assembled raft foundation of the present invention comprises the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars.
  • The bottom layer rebar of the foundation slab comprises bottom layer sections and the first vertical sections that are connected with the bottom layer sections; the bottom layer section and the first vertical section are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars.
  • The foundation steel columns are installed on the bottom layer section, wherein the foundation steel column comprises columns and vertical pivot sections that are installed at the top of the column.
  • The upper layer rebars of the foundation slab are installed on the bottom layer rebars of the foundation slab, wherein the upper layer rebar of the foundation slab comprises the top layer sections and second vertical sections that are connected with the top layer sections; the top layer section and the second vertical section are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars.
  • The foundation rebar, installed on the side of the foundation steel columns, comprises a plurality of beams and columns, horizontal pivot sections that are installed at both ends of the beams and columns, and steel mesh structures, wherein the plurality of beams and columns are tied together by circular rebars and are secured by steel mesh structures installed above and below the beams and columns.
  • Last, the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars are assembled into a pre-assembled raft foundation.
  • Furthermore, the pre-assembled raft foundation construction method of the present invention comprises the following steps.
    1. A. a pre-assembling step: The bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars are pre-assembled in the factory, wherein the bottom layer rebar of the foundation slab comprises bottom layer sections and the first vertical sections that are connected with the bottom layer sections; the foundation steel column comprises columns and vertical pivot sections that are installed at the top of the column; the upper layer rebar of the foundation slab comprises the top layer sections, having a hollow section therewithin, and second vertical sections that are connected with the top layer sections; the foundation rebar comprises beams and columns, horizontal pivot sections that are installed at both ends of the beams and columns, and steel mesh structures installed above and below the beams and columns.
    2. B. an assembling step: The pre-assembled bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars are delivered to the construction site. After the bottom layer rebars of the foundation slab are placed and fixed in position to the ground or spread footing, the foundation steel columns are positioned on the bottom layer rebars of the foundation slab; then the upper layer rebars of the foundation slab are positioned on the bottom layer rebars of the foundation slab, wherein the foundation steel columns penetrate through the hollow section of the upper layer rebars of the foundation slab; last, the foundation rebars are installed and penetrate through the sides of the foundation steel columns.
    3. C. a pivoting step: The pivot element is installed on the horizontal pivot section of the foundation rebar; the horizontal pivot sections of the foundation rebars are assembled using the pivot elements to connect to each other in order to form a pre-assembled raft foundation. Last, the outer part of the frame of the pre-assembled raft foundation is built with a formwork.
    4. D. a grouting step: Concrete is poured into the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars. After the concrete hardens, the construction of the foundation slab is completed.
  • In summary, the advantages of the multi-piece pre-assembled raft foundation and the construction method thereof include: pre-assembly of the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation in the factory, so that construction workers can skip the step of tying rebars from the start; the construction time is significantly reduced; and the number of construction workers required can be less.
  • [BRIEF DESCRIPTION OF THE DRAWINGS]
  • The present invention will become more fully understood from the detailed description given herein below for illustration only which thus does not limit the present invention, wherein:
  • Fig. 1
    a schematic diagram (1) of the pre-assembled raft foundation of the present invention;
    Fig. 2
    a schematic diagram (2) of the pre-assembled raft foundation of the present invention;
    Fig. 3
    a schematic diagram of the bottom layer rebars of the foundation slab of the present invention;
    Fig. 4
    a schematic diagram of the foundation steel columns of the present invention;
    Fig. 5
    a schematic diagram of the upper layer rebars of the foundation slab of the present invention;
    Fig. 6
    a schematic diagram (1) of the foundation rebars of the present invention;
    Fig. 7
    a schematic diagram (2) of the foundation rebars of the present invention;
    Fig. 8
    a construction flow diagram of the pre-assembled raft foundation of the present invention;
    Fig. 9
    an implementation flow diagram of the present invention;
    Fig. 10
    a schematic diagram of the first pivot element of the present invention;
    Fig. 11
    a schematic diagram (1) of an embodiment of the first pivot element of the present invention;
    Fig. 12
    a schematic diagram (2) of an embodiment of the first pivot element of the present invention;
    Fig. 13
    a schematic diagram (1) of the second pivot element of the present invention;
    Fig. 14
    a schematic diagram (2) of the second pivot element of the present invention;
    Fig. 15
    a schematic diagram (1) of an embodiment of the second pivot element of the present invention;
    Fig. 16
    a schematic diagram (2) of an embodiment of the second pivot element of the present invention;
    Fig. 17
    a schematic diagram (3) of an embodiment of the second pivot element of the present invention;
    Fig. 18
    a schematic diagram (1) of the third pivot element of the present invention;
    Fig. 19
    a schematic diagram (2) of the third pivot element of the present invention;
    Fig. 20
    a schematic diagram (3) of the third pivot element of the present invention;
    Fig. 21
    a schematic diagram (4) of the third pivot element of the present invention;
    Fig. 22
    a schematic diagram (1) of the assembly of the first pivot elements of the present invention;
    Fig. 23
    a schematic diagram (2) of the assembly of the first pivot elements of the present invention;
    Fig. 24
    a schematic diagram (3) of the assembly of the first pivot elements of the present invention;
    Fig. 25
    a schematic diagram (4) of the assembly of the first pivot elements of the present invention;
    Fig. 26
    a schematic diagram of the assembly of the second pivot elements of the present invention;
    Fig. 27
    a schematic diagram (1) of the assembly of the third pivot elements of the present invention;
    Fig. 28
    a schematic diagram (2) of the assembly of the third pivot elements of the present invention;
    Fig. 29
    a schematic diagram (3) of the assembly of the third pivot elements of the present invention;
    Fig. 30
    an enlarged partial view of the embodiment of the third pivot element of the present invention;
    [DETAILED DESCRIPTION OF PREFERRED EMBODIMENTS]
  • First, please refer to Fig. 1 and Fig. 2. The pre-assembled raft foundation 1 of the present invention comprises the bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2.
  • Please refer to Fig. 1 and Fig. 2 along with Fig. 3. The bottom layer rebars of the foundation slab 11 comprises bottom layer sections 111 and the first vertical sections 112 that are connected with the bottom layer sections 111; the bottom layer section 111 and the first vertical section 112 are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars.
  • Next, please refer to Fig. 1 and Fig. 2 together with Fig. 4. The foundation steel columns 12 are installed on the bottom layer section 111 (as shown in Fig. 3 ), wherein the foundation steel column 12 comprises columns 121 and vertical pivot sections 122 that are installed at the top of the column 121.
  • Please refer to Fig. 1 and Fig. 2 together with Fig. 5. The upper layer rebars of the foundation slab 13 are installed on the bottom layer rebars of the foundation slab 11 (as shown in Fig. 3). The upper layer rebar of the foundation slab 13 comprises the top layer sections 131 and second vertical sections 132 that are connected with the top layer sections 131; the top layer section 131 and the second vertical section 132 are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars, wherein the top layer section 1311 has a hollow section 1311 therewithin so that the foundation steel column can be installed therein; when the installation is completed, rebars are used to connect therewith, as show in Fig. 1.
  • Please refer to Fig. 1 and Fig. 2 together with Fig. 6 and Fig. 7. (In Fig. 6, there is only one pivot element 5 is displayed for demonstration. However, a plurality of pivot elements 5 can be applied.) The foundation rebar 2, installed on the side of the foundation steel columns 12, comprises a plurality of beams and columns 21, horizontal pivot sections 22A that are installed at both ends of the beams and columns 2, and steel mesh structures 23, wherein the plurality of beams and columns 21 are tied together by circular rebars and are secured by steel mesh structures 23 installed above and below the beams and columns 21.
  • The horizontal pivot sections 22A can have a form of a screw rod, or the horizontal pivot sections 22B can have a form of a cylinder, or other forms. Different forms are applied to different construction methods or to different pivot elements 5 for connection. In the embodiment of the present invention, the pivot element 5 can be a first pivot element 5A (as shown in Fig. 10), or a second pivot element 5B (as shown in Fig. 13), or a third pivot element 5C (as shown in Fig. 18) for connecting and holding rebars in place.
  • The bottom layer rebars of the foundation slab 11 (as shown in Fig. 3), foundation steel columns 12 (as shown in Fig. 4), upper layer rebars of the foundation slab (as shown in Fig. 5), and foundation rebars are assembled to form a pre-assembled raft foundation 1.
  • Please refer to Fig. 8 together with Fig. 1 to Fig. 7. The pre-assembled raft foundation construction method 3 of the present invention comprises the following steps.
    1. A. a pre-assembling step 31: Rebars are tied or welded into the structures of bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2 in advance in the factory according to the dimensions required by the construction site, wherein the bottom layer rebar of the foundation slab 11 comprises bottom layer sections 111 and the first vertical sections 112 that are connected with the bottom layer sections 111; the foundation steel columns 12 comprises columns 121 and vertical pivot sections 122 that are installed at the top of the column 121; the upper layer rebar of the foundation slab 13 comprises the top layer sections 131, having a hollow section 1311 therewithin, and second vertical sections 132 that are connected with the top layer sections 131; the foundation rebar 2 comprises beams and columns 21, horizontal pivot sections 22A that are installed at both ends of the beams and columns 21, and steel mesh structures 23 installed above and below the beams and columns 21.
    2. B. an assembling step 32: The pre-assembled bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2 are delivered to the construction site. After the bottom layer rebars of the foundation slab 11 are placed and fixed in position to the ground or spread footing, the foundation steel columns 12 are positioned on the bottom layer rebars of the foundation slab 11; then the upper layer rebars of the foundation slab 13 are positioned on the bottom layer rebars of the foundation slab 11, wherein the foundation steel columns 12 penetrate through the hollow section 1311 of the upper layer rebars of the foundation slab 13; last, the foundation rebars 2 are installed and penetrate through the sides of the foundation steel columns 12.
    3. C. a pivoting step 33: The pivot element 5 is installed on the horizontal pivot section 22A of the foundation rebar 2; two horizontal pivot sections 22A of the foundation rebars 2 that are in contact with each other are assembled using the pivot elements 5 to connect to each other in order to form a pre-assembled raft foundation 1. Last, the outer part of the frame of the pre-assembled raft foundation 1 is built with a formwork (not shown in the figure).
    4. D. a grouting step 34: Wet concrete is poured into the bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2. After the concrete hardens, the construction of the foundation slab is completed.
  • Furthermore, the formworks (not shown in the figure) used in the present invention can be of timber, steel, etc. and are removable formworks (not shown in the figure). Non-removable formworks (not shown in the figure) can be used as well to replace the commonly available removable formworks (not shown in the figure).
  • Embodiments of the present invention and relevant figures are described in details as follows.
  • Please refer to Fig. 9. As explained in step 41, the bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2 of the present invention are manufactured in the factory in advance according to the dimensions of the specification issued by the construction site. Using the method of tying or welding, a plurality of U-shaped rebars, steel bars, stirrups, and tie bars are configured into the structures of bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2.
  • As described in step 42 of Fig. 9, after the bottom layer rebars of the foundation slab 11, foundation steel columns 12, upper layer rebars of the foundation slab 13, and foundation rebars 2 are produced, the aforementioned parts can be shipped directly to the construction site for assembly. Once the aforementioned parts arrive at the construction site, workers at the construction site simply place and fix the bottom layer rebars of the foundation slab 11 in position to the ground or spread footing, place the foundation steel columns 12 on the bottom layer rebars of the foundation slab 11, lay down the upper layer rebars of the foundation slab 13 on the bottom layer rebars of the foundation slab 11 and make the foundation steel columns 12 penetrate through the hollow sections 1311, and finally install the foundation rebars 2 to penetrate through the sides of the foundation steel columns 12. Construction workers repeat the aforementioned assembling steps so that the horizontal pivot sections 22A of the foundation rebars 2 and the foundation steel columns 12 are assembled to connect to each other. Last, after the hollow section 1311 is filled with steel bars, the assembly process is completed.
  • As described in step 43 of Fig. 9, after the assembly process is completed, construction workers can install the pivot elements 5 on the horizontal pivot sections 22A, making the horizontal pivot sections 22A of the foundation rebars 2 be connected to each other as one piece to form a raft foundation. Next, after the outer part of the frame of the raft foundation is installed with a formwork (not shown in the figure), wet concrete is poured in the formwork. When concrete is cured and hardens, the pre-assembled raft foundation construction method of the present invention is completed.
  • Furthermore, the pivot element 5 used in the present invention can be one of the following three forms. The first form is a first pivot element 5A (as shown in Fig. 10); the second form is a second pivot element 5B (as show in Fig. 13), and the third form is a third pivot element 5C. Descriptions of the aforementioned pivot elements 5 are provided in detail.
    1. 1. The first form of the pivot element 5 is a first pivot element 5A:
      Please refer to Fig. 10 together with Fig. 6. The first pivot element 5A has a through hole 51, having an internal thread 511 through the internal surface of the through hole 51. Both ends of the first pivot element 5A are connected with the horizontal pivot sections 22A, making two foundation rebars 2 to be bound to each other. In addition, both ends of the internal thread 511 of the first pivot element 5A have an internal guide section 512 separately. The design of the internal guide section 512 allows the horizontal pivot section 22A to insert into the through hole 51 more easily. The first pivot element 5A can be with multiple-start threads, for example, two-start threads, three-start threads, or multi-start threads. The threads of the internal guide section 512 and the horizontal pivot section 22A can be right-hand threads of the same direction, or left-hand threads of the same direction, or right-hand and left-hand threads of different directions.
  • Please refer to Fig. 11. A single mounting element 6 is installed on any one of the two horizontal pivot sections 22A. Next, the first pivot element 5A is installed on one of the horizontal pivot sections 22A and then the other horizontal pivot sections 22A is inserted into the first pivot element 5A for fastening. The first pivot element 5A is rotated to gradually fasten these two horizontal pivot sections 22A together toward the first pivot element 5A. Last, the mounting element 6 is fastened to eliminate the gap between the first pivot element 5A and the two horizontal pivot sections 22A.
  • In respect to the aforementioned fastening process, the first pivot element 5A and the horizontal pivot sections 22A can be with multi-start threads, for example, two-start threads, three-start threads, or multi-start threads. The threads of the internal guide section 512 and the horizontal pivot sections 22A can be right-hand threads of the same direction, or left-hand threads of the same direction. Therefore, the first pivot element 5A can rotate to fine-tune the lock mounting position when the lock mounting distance remains unchanged, and then a single mounting element 6 is used to lock the position of the first pivot element 5A.
  • On the contrary, the aforementioned internal guide section 512 and the horizontal pivot section 22A can also be with right-hand and left-hand threads of different directions. In other words, the internal guide section 512 has right-hand threads and the horizontal pivot sections 22A have left-hand threads, or the internal guide section 512 has left-hand threads and the horizontal pivot sections 22A have right-hand threads. Thus, when the first pivot element 5A is rotated, the lock mounting distance will change, whereas the lock mounting position remains unchanged. Last, the adjusted first pivot element 5A is locked and mounted at the position using a single mounting element 6.
  • Please refer to Fig. 12. While using the first pivot element 5A, the horizontal pivot sections 22A of two foundation rebars 2 that are set to be fastened to each other can be installed with a mounting element 6 separately in advance. Next, a first pivot element 5A is installed on one of the horizontal pivot sections 22A and then the other horizontal pivot sections 22A to be connected is aligned to the first pivot element 5A for fastening. The first pivot element 5A is rotated to gradually fasten these horizontal pivot sections 22A together toward the first pivot element 5A. Last, the mounting elements 6 placed at both ends of the first pivot element 5A separately to eliminate the gaps among the two horizontal pivot sections 22A, the first pivot element 5A and the beams and columns.
  • In respect to the aforementioned fastening process, the first pivot element 5A and the horizontal pivot sections 22A can be with multi-start threads, for example, two-start threads, three-start threads, or multi-start threads. The threads of the internal guide section 512 and the horizontal pivot sections 22A can be right-hand threads or left-hand threads of the same direction. Therefore, the first pivot element 5A can rotate to fine-tune the lock mounting position when the lock mounting distance remains unchanged, and then two mounting elements 6 are used to lock the position of the first pivot element 5A.
  • On the contrary, the aforementioned internal guide section 512 and the horizontal pivot section 22A can also be with right-hand and left-hand threads of different directions. In other words, the internal guide section 512 has right-hand threads and the horizontal pivot sections 22A have left-hand threads, or the internal guide section 512 has left-hand threads and the horizontal pivot sections 22A have right-hand threads. Thus, when the first pivot element 5A is rotated, the lock mounting distance will change, whereas the lock mounting position remains unchanged. Last, the adjusted first pivot element 5A is locked and mounted at the position using two mounting elements 6.
  • 2.The second form of the pivot element 5 is a second pivot element 5B:
    Please refer to Fig. 13 together with Fig. 6. The second pivot element 5B is a frame body 52, wherein the frame body 52 has a plurality of positioning holes 521 thereon, for the horizontal pivot sections 22A to insert, and a containing space 522 that is connected through the positioning holes 521. The second pivot element 5B, installed in the containing space 522, holds up the mounting element 6 to be set on the horizontal pivot sections 22A, so that the horizontal pivot sections 22A are mounted on the frame body 52.
  • Please refer to Fig. 14 together with Fig. 6. To increase the overall strength of the second pivot element 5B, enhancing elements 523, parallel to the positioning holes 521, can be added to the frame body 52 to make the second pivot element 5B more solid and stronger.
  • Please refer to Fig. 15 and Fig. 16. To fasten the foundation steel columns 12 and the foundation rebars 2, the second pivot elements 5B can be used to connect the foundation rebars 2 that penetrate the foundation steel columns 12. Before the second pivot elements 5B are used, the mounting elements 6 and washers 7 are installed on the horizontal pivot sections 22A. Next, after the positioning holes 521 of the frame body 52 are aligned with the horizontal pivot sections 22A, the second pivot elements 5B are inserted into the horizontal pivot sections 22A, followed by installing the mounting elements 6 and washers 7 to the horizontal pivot sections 22A again. Last, all mounting elements 6 are fastened.
  • Please refer to Fig. 17. In addition to the second pivot elements 5B being used to connect two foundation rebars 2 and the foundation steel columns 12, enhancing elements 523 are added. The installation process is the same as the previous descriptions. Before the second pivot elements 5B are used, the mounting elements 6 and washers 7 are installed on the horizontal pivot sections 22A. Next, after the positioning holes 521 of the frame body 52 are aligned with the horizontal pivot sections 22A, the second pivot elements 5B are inserted into the horizontal pivot sections 22A, followed by installing the mounting elements 6 and washers 7 to the horizontal pivot sections 22A again. Last, all mounting elements 6 are fastened.
  • 3.The third form of the pivot element 5 is a third pivot element 5C:
    Please refer to Fig. 18 to Fig. 21, together with Fig. 7. The third pivot element 5C is a backing plate 53 made of carbon-based materials, wherein the backing plate 53 is installed on the back of two horizontal pivot sections 22B of the foundation rebars 2 respectively, to fasten these two horizontal pivot sections 22B of the foundation rebars 2 by welding. The backing plate 53 can withstand a high temperature of over 1500°C ;the cross section of the backing plate 53 has an arc shape or a flat shape, or is a flat plate with a groove 531.
  • Furthermore, when the aforementioned three different forms of pivot element 5 are assembled, there are different forms of assembly. The assembly methods of the first pivot element 5A, the second pivot element 5B, and the third pivot element 5C are described separately as follows.
  • 1.The assembly method of the first pivot element 5A.
  • Please refer to Fig. 22. Place all first pivot elements 5A on the same plane with the horizontal pivot sections 22A, or place all first pivot elements 5A on different planes with the horizontal pivot sections 22A in an interlacing way. The advantage of adopting an interlacing form is to prevent the horizontal pivot sections 22A and the beams and columns 21 to break up simultaneously upon impact.
  • A foundation rebar 2 reaching foundation steel column 12 in the horizontal direction is picked as the standard; the same applies to another foundation rebar 2 that reaches a foundation steel column12 in the vertical direction. If the length of beams and columns 21 of the foundation rebar 2 is not long enough, the beams and columns 21 can be extended with combining steel bars connected by the first pivot elements 5A. Therefore, two foundation rebars 2 can extend and insert into the foundation steel column 12 while these two foundation rebars 2 are connected to each other.
  • Please refer to Fig. 23, Fig. 24, and Fig. 25. The location of the connection joint of the first pivot element 5A can be inside the foundation steel columns 12 and a proper location on the side of the foundation steel columns 12. The beams and columns 21 of two foundation rebars 2 penetrate through the foundation steel columns 12, and are connected and fastened with the horizontal pivot sections 22A within the foundation steel columns 12 using the first pivot elements 5A. This process is a connection method of column-foundation (inside of column) (as shown in Fig. 23). The same connecting and fastening operation can be applied to a proper location on the side of the foundation steel columns 12. A foundation rebar 2 is inserted horizontally through the foundation steel column 12 and the horizontal pivot section 22A is in contact with the horizontal pivot section 22A of another foundation rebar 2. A first pivot element 5A is used to connect these two horizontal pivot section 22A separately. This process is a connection method of column-foundation (outside of column) (as shown in Fig. 24). The connection method of column-foundation (outside of column) can be applied to the connection located on both sides of the foundation steel columns 12, as a connection method of column-foundation (outside of column) with double-pivot connection (as shown in Fig. 25).
  • Furthermore, the mounting and connecting method of the first pivot element 5A is to fasten and mount the beams and columns 21, which are connected to each other in pairs, having the degrees of freedom to be zero so that rotation and movement will not occur and the foundation becomes stronger and firm.
  • 2.The assembly method of the second pivot element 5B.
  • Please refer to Fig. 26. Install the mounting elements 6 and washers 7 on one of two horizontal pivot sections 22A of two foundation rebars 2 that are connected to each other. Align the horizontal pivot sections 22A with the positioning holes 521 and insert therein. Next, install the mounting elements 6 and washers 7 on the other of two horizontal pivot sections 22A. Last, all mounting elements 6 are fastened to complete the pivot joint of the second pivot elements 5B.
  • The mounting and connecting method of the second pivot element 5B is to fasten and mount the beams and columns 21, which are connected to each other in pairs, having the degrees of freedom to be zero so that rotation and movement will not occur and the foundation becomes stronger and firm.
  • 3.The assembly method of the third pivot element 5C.
  • Please refer to Fig. 27 to Fig. 30. The third pivot element 5C is used to connect two foundation rebars 2 and a foundation steel column 12. The third pivot element 5C is installed on the back of the horizontal pivot sections 22B of two foundation rebars 2 separately that are connected to the foundation steel column 12 individually. Using the welding method, solder in high temperature piles up on the third pivot element 5C and gradually fills up the gap between these two horizontal pivot sections 22B; these two horizontal pivot sections 22B eventually become connected to each other at last.
  • The location of the connection joint of the third pivot element 5C can be inside the foundation steel columns 12 and a proper location on the side of the foundation steel columns 12. The beams and columns 21 of two foundation rebars 2 penetrate through the foundation steel columns 12, and are welded to the horizontal pivot sections 22B within the foundation steel columns 12 using the third pivot elements 5C. This process is a connection method of column-foundation (inside of column) (as shown in Fig. 27). The same welding operation can be applied to a proper location on the side of the foundation steel columns 12. A foundation rebar 2 is inserted horizontally through the foundation steel column 12 and the horizontal pivot section 22B is in contact with the horizontal pivot section 22B of another foundation rebar 2. A third pivot element 5C is used to connect these two horizontal pivot section 22B separately. This process is a connection method of column-foundation (outside of column) (as shown in Fig. 28). The connection method of column-foundation (outside of column) can be applied to the connection located on both sides of the foundation steel columns 12, as a connection method of column-foundation (outside of column) with double-pivot connection (as shown in Fig. 29). The welding The connection method of column-foundation (outside of column) can be applied to the connection located on both sides of the foundation steel columns 12, as a connection method of column-foundation (outside of column) with double-pivot connection (as shown in Fig. 25).of the aforementioned third pivot element 5C is demonstrated in Fig. 30.
  • In addition, the mounting and fastening method of the third pivot element 5C is to fasten and mount the beams and columns 21, which are connected to each other in pairs, having the degrees of freedom to be zero, so that rotation and movement will not occur and the foundation becomes stronger and firm.
  • The aforementioned three forms of pivot connection can be applied by construction workers at the construction site. Construction workers can connect one foundation rebar 2 with different forms of a pivot element 5. These three connection methods of the pivot element 5 can retain and mount the beams and columns, which are connected to each other in pairs, restrain beams and columns from rotating, and increase the stability and firmness of the foundation.
  • In summary, the advantages of the multi-piece pre-assembled raft foundation and the construction method thereof is to pre-assemble the bottom layer rebars of the foundation slab 11, foundation steel columns 12, the upper layer rebars of the foundation slab 13, and the foundation rebars 2 completely prior to being transported to the construction site for further assembly. Therefore, the construction workers no longer have to bundle rebars, and the effect of shortening the construction time and reducing the number of needed construction workers can be achieved.

Claims (10)

  1. A pre-assembled raft foundation, mainly comprising:
    bottom layer rebars of the foundation slab, wherein the bottom layer rebar of the foundation slab comprises bottom layer sections and the first vertical sections that are connected with the bottom layer sections; the bottom layer section and the first vertical section are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars;
    foundation steel columns which are installed on the bottom layer section, wherein the foundation steel column comprises columns and vertical pivot sections that are installed at the top of the column;
    upper layer rebars of the foundation slab which are installed on the bottom layer rebars of the foundation slab, wherein the upper layer rebar of the foundation slab comprises the top layer sections and second vertical sections that are connected with the top layer sections; the top layer section and the second vertical section are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-shaped rebars; and
    foundation rebars which are installed on the side of the foundation steel columns, wherein the foundation rebar comprises a plurality of beams and columns, horizontal pivot sections that are installed at both ends of the beams and columns, and steel mesh structures, wherein the plurality of beams and columns are tied together by circular rebars and are secured by steel mesh structures installed above and below the beams and columns;
    The aforementioned bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars are assembled into a pre-assembled raft foundation.
  2. The pre-assembled raft foundation as claimed in claim 1, wherein the outer part of the frame of the pre-assembled raft foundation is built with a formwork; the formwork can be a removable formwork or a non-removable formwork.
  3. The pre-assembled raft foundation as claimed in claim 1, wherein the vertical pivot section and the horizontal pivot section are installed with first pivot elements thereon for connecting beams and columns; the first pivot element has a through hole, having an internal thread through the internal surface of the through hole; both ends of the pivot element are connected with the horizontal pivot section and the beams and columns separately; in addition, both ends of the internal thread of the pivot element have an internal guide section separately.
  4. The pre-assembled raft foundation as claimed in claim 1, wherein the vertical pivot section and the horizontal pivot section are installed with second pivot elements thereon for connecting beams and columns; the second pivot element is a frame body, wherein the frame body has a plurality of positioning holes thereon, for the horizontal pivot sections and beams and columns to insert, and a containing space that is connected through the positioning holes; the second pivot element holds up the mounting element to be set on the horizontal pivot sections and beams and columns, so that the horizontal pivot sections and beams and columns are mounted on the frame body.
  5. The pre-assembled raft foundation as claimed in claim 1, wherein the vertical pivot section and the horizontal pivot section are installed with third pivot elements thereon for connecting beams and columns; the third pivot element is a backing plate made of carbon-based materials; the backing plate can withstand a high temperature of over 1500°C ;the outer appearance of the backing plate has an arc shape or a flat shape, or is a flat plate with a groove.
  6. The pre-assembled raft foundation construction method, comprising the following steps:
    a pre-assembling step: The bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars are pre-assembled in the factory, wherein the bottom layer rebar of the foundation slab comprises bottom layer sections and the first vertical sections that are connected with the bottom layer sections; the foundation steel column comprises columns and vertical pivot sections that are installed at the top of the column; the upper layer rebar of the foundation slab comprises the top layer sections, having a hollow section therewithin, and second vertical sections that are connected with the top layer sections; the foundation rebar comprises beams and columns, horizontal pivot sections that are installed at both ends of the beams and columns, and steel mesh structures installed above and below the beams and columns;
    an assembling step: The pre-assembled bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars are delivered to the construction site. After the bottom layer rebars of the foundation slab are placed and fixed in position to the ground or spread footing, the foundation steel columns are positioned on the bottom layer rebars of the foundation slab; then the upper layer rebars of the foundation slab are positioned on the bottom layer rebars of the foundation slab, wherein the foundation steel columns penetrate through the hollow section of the upper layer rebars of the foundation slab; last, the foundation rebars are installed and penetrate through the sides of the foundation steel columns
    a pivoting step: The pivot element is installed on the horizontal pivot section of the foundation rebar; the horizontal pivot sections of the foundation rebars are assembled using the pivot elements to connect to each other in order to form a pre-assembled raft foundation. Last, the outer part of the frame of the pre-assembled raft foundation is built with a formwork.
    a grouting step: Concrete is poured into the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars. After the concrete hardens, the construction of the foundation slab is completed.
  7. The pre-assembled raft foundation construction method as claimed in claim 6, wherein the formwork used in the pivoting step can be a removable formwork or a non-removable formwork.
  8. The pre-assembled raft foundation construction method as claimed in claim 6, wherein the pivot element used in the pivoting step is the first pivot element that comprises a through hole, having an internal thread through the internal surface of the through hole; both ends of the first pivot element are connected with the horizontal pivot sections; both ends of the internal thread of the first pivot element has an internal guide section separately.
  9. The pre-assembled raft foundation construction method as claimed in claim 6, wherein the pivot element used in the pivoting step is the second pivot element and the second pivot element is a frame body, wherein the frame body has a plurality of positioning holes thereon, for the horizontal pivot sections to insert, and a containing space that is connected through the positioning holes; the second pivot element holds up the mounting element to be set on the horizontal pivot sections, so that the horizontal pivot sections are mounted on the frame body.
  10. The pre-assembled raft foundation construction method as claimed in claim 6, wherein the pivot element used in the pivoting step is the third pivot element and the third pivot element is a backing plate made of carbon-based materials; the backing plate can withstand a high temperature of over 1500°C ;the outer appearance of the backing plate has an arc shape or a flat shape, or is a flat plate with a groove.
EP23157988.9A 2022-02-24 2023-02-22 Multi-piece pre-assembled raft foundation and construction method thereof Pending EP4234833A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW111106887A TW202334531A (en) 2022-02-24 2022-02-24 Pre-assembled raft foundation and construction method thereof

Publications (1)

Publication Number Publication Date
EP4234833A1 true EP4234833A1 (en) 2023-08-30

Family

ID=85328823

Family Applications (1)

Application Number Title Priority Date Filing Date
EP23157988.9A Pending EP4234833A1 (en) 2022-02-24 2023-02-22 Multi-piece pre-assembled raft foundation and construction method thereof

Country Status (4)

Country Link
US (1) US20230265635A1 (en)
EP (1) EP4234833A1 (en)
JP (1) JP2023123396A (en)
TW (1) TW202334531A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03191116A (en) * 1989-12-19 1991-08-21 Takenaka Komuten Co Ltd Construction method of underground beam and underground beam driving form
JPH05112948A (en) * 1991-10-23 1993-05-07 Asahi Chem Ind Co Ltd Permanent form and foundation execution method using it
KR100403835B1 (en) * 2001-02-02 2003-10-30 주식회사 힐 엔지니어링 Reinforcements for bending-moment and shear in the part of reinforced concrete footings and construction method of its using
CN107100298A (en) * 2017-07-05 2017-08-29 浙江正合建筑网模有限公司 A kind of reinforcement network die component
CN109457720A (en) * 2019-01-04 2019-03-12 杭州西奥电梯现代化更新有限公司 The foundation precast elements and its construction method of assembled elevator

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03191116A (en) * 1989-12-19 1991-08-21 Takenaka Komuten Co Ltd Construction method of underground beam and underground beam driving form
JPH05112948A (en) * 1991-10-23 1993-05-07 Asahi Chem Ind Co Ltd Permanent form and foundation execution method using it
KR100403835B1 (en) * 2001-02-02 2003-10-30 주식회사 힐 엔지니어링 Reinforcements for bending-moment and shear in the part of reinforced concrete footings and construction method of its using
CN107100298A (en) * 2017-07-05 2017-08-29 浙江正合建筑网模有限公司 A kind of reinforcement network die component
CN109457720A (en) * 2019-01-04 2019-03-12 杭州西奥电梯现代化更新有限公司 The foundation precast elements and its construction method of assembled elevator

Also Published As

Publication number Publication date
TW202334531A (en) 2023-09-01
JP2023123396A (en) 2023-09-05
US20230265635A1 (en) 2023-08-24

Similar Documents

Publication Publication Date Title
KR100971736B1 (en) Shear reinforcement with dual anchorage function each up and down
US10688685B2 (en) Formwork for providing a concrete foundation plinth with exposed horizontal reinforcing bars, plinth provided with such formwork, and structure comprising such plinth
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
KR101339946B1 (en) Precast bridge post
KR102440826B1 (en) Column form system using deckplate form and construction method for the same
KR102357050B1 (en) Column form system using deckplate form
CN106703432A (en) Newly-added steel girder and original reinforced concrete column hoop connecting joint and connecting method thereof
KR20190027232A (en) Joint for Precast Columns and Foundation
CN114319977A (en) Steel pipe concrete row column type connection prefabricated shear wall structure and construction method
EP4234833A1 (en) Multi-piece pre-assembled raft foundation and construction method thereof
JP3690437B2 (en) Seismic reinforcement structure for existing buildings
JPH0476118A (en) Frame of foundation for steel structure building
CN114045750A (en) Construction method of high pier column tie beam
JP2977764B2 (en) Concrete column reinforcement structure
JP6829631B2 (en) Construction method of column base, reinforcement method of existing column base
JPS63268834A (en) Method for constructing body of multi-storied building and reinforcing bar connected cylinder used therein
JPH07292683A (en) Anchor frame and foundation construction method using the frame
JP3222856B2 (en) Construction method of column / beam joint
JPH0827929A (en) Construction method of wall type src structure
JP7303766B2 (en) Construction method of panel unit and structure
JP7321923B2 (en) Structure and its construction method
JP2003161041A (en) Aseismatic reinforcing structure of existing building and execution method therefor
JPH08246587A (en) Successive concrete placing formwork and wall jointing construction method
JPH07103620B2 (en) Construction method for steel structure
JP6358602B2 (en) Reinforcement structure and reinforcement method for existing columns

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC ME MK MT NL NO PL PT RO RS SE SI SK SM TR

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20240220

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC ME MK MT NL NO PL PT RO RS SE SI SK SM TR