EP3810500B1 - Method and vessel for deploying heavy objects - Google Patents
Method and vessel for deploying heavy objects Download PDFInfo
- Publication number
- EP3810500B1 EP3810500B1 EP19743076.2A EP19743076A EP3810500B1 EP 3810500 B1 EP3810500 B1 EP 3810500B1 EP 19743076 A EP19743076 A EP 19743076A EP 3810500 B1 EP3810500 B1 EP 3810500B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- vessel
- cargo deck
- heavy lift
- lift crane
- deck
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims description 30
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 36
- 238000009434 installation Methods 0.000 claims description 14
- 230000008901 benefit Effects 0.000 description 5
- 230000005484 gravity Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000007704 transition Effects 0.000 description 2
- 230000004308 accommodation Effects 0.000 description 1
- NEHMKBQYUWJMIP-UHFFFAOYSA-N chloromethane Chemical compound ClC NEHMKBQYUWJMIP-UHFFFAOYSA-N 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000007654 immersion Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/003—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting very large loads, e.g. offshore structure modules
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B25/00—Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
- B63B25/28—Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for deck loads
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B27/00—Arrangement of ship-based loading or unloading equipment for cargo or passengers
- B63B27/10—Arrangement of ship-based loading or unloading equipment for cargo or passengers of cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B1/00—Hydrodynamic or hydrostatic features of hulls or of hydrofoils
- B63B1/02—Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement
- B63B1/04—Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with single hull
- B63B2001/044—Hydrodynamic or hydrostatic features of hulls or of hydrofoils deriving lift mainly from water displacement with single hull with a small waterline area compared to total displacement, e.g. of semi-submersible type
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/40—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting marine vessels
- B63B35/42—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting marine vessels with adjustable draught
Definitions
- the present invention relates to a method for deploying objects, such as offshore wind turbine foundations or subsea installations, from a vessel.
- the invention also relates to such a vessel.
- Offshore wind turbine foundations are typically installed using cargo barges and crane vessels working together.
- the cargo barges ship the foundations to a desired offshore site.
- the crane vessel which is equipped with a heavy lift crane, lifts each foundation off the cargo barge and places it on the seabed.
- the cargo barge supplying the crane vessel is typically slow which limits the number of foundations that can be placed per unit of time. Lifting each foundation from the barge and placing it on the seabed is a complex task, due to movement of the vessels and swinging of the cargo, which may lead to damage.
- An example of a crane vessel is disclosed in WO 2012/070937 .
- Another crane vessel is disclosed in WO 2013/191543 , which allows the hull to be ballasted between a transit draft and a maximum draft in order to increase the metacentre height. This is favourable for certain installation operations.
- Wind turbine foundations can also be installed using jack-up vessels such as shown in WO 2012/175091 . Although use of such vessels can reduce the influence of waves and weather, they typically operate more slowly, due to the time required to complete the jack-up operation. Also, they tend to have a higher centre of gravity, increasing the moment of forces on the vessel. Jack-up vessels can also only operate in relatively shallow waters.
- a method for deploying an object such as an off-shore wind turbine foundation or subsea installation, from a vessel according to the features of claim 1.
- the method comprises: providing a vessel comprising a submersible cargo deck and a heavy lift crane, wherein the object is present on the cargo deck; submerging the cargo deck to a position below a level of the water; lifting the object from the submerged cargo deck using the heavy lift crane to a desired position overboard, at least partially below the level of the water; and releasing the object at the desired position.
- the vessel may be a mono hull vessel.
- the cargo deck (or working deck) is submersible.
- the person skilled in the art will understand that this means that the cargo deck can be submerged until it is completely flooded, i.e. to a position below a level of the water.
- the cargo deck may also be raised to a position entirely above the water level.
- the cargo deck can be lowered until at least 5 meters below the water level, more preferably at least 10 meters below the water level, more preferably 15 meters below the water level.
- the draught of the vessel is typically controlled by water ballast tanks in the hull of the vessel. The draught can be controlled between 5 meters to 28 meters.
- the cargo deck is preferably substantially planar, meaning that it is planar apart from any necessary facilities such as fences or staircases. It is however not excluded that the cargo deck could be stepped i.e. have different levels that could be submerged sequentially as the vessel is lowered in the water.
- the deployment zone will be defined as the part of the cargo deck from which objects can be lifted by the crane. It will be appreciated that other parts of the vessel may be submersible and/or carry cargo but will not fall within the definition of the deployment zone if the crane cannot lift from this location.
- the cargo deck may be equal to the deployment zone. Preferably the deployment zone area is more than 30% of the area of the cargo deck.
- the deployment zone and possibly the entire cargo deck are also preferably unobstructed, i.e. have no deck above them for substantially their entire area such that also very high structures such as wind turbine foundations can be supported by the cargo deck.
- the submersible cargo deck has the advantage that the objects, such as wind turbine foundations or subsea installations, are not subjected to the dynamic forces of the splash zone at the water surface, since they are already at or below the water level once the cargo deck has submerged.
- the impact on the object and on the crane is thus greatly reduced when the object is lifted from the cargo deck while the cargo deck is submerged, especially when the object itself remains (partially) under water as well.
- the water thus efficiently dampens any swinging motion of the object.
- the submerging of the cargo deck also improves the motion performance of the vessel as a whole.
- the movement is reduced because the area of the vessel crossing the water level is reduced, and the centre of mass is lowered with respect to the water level. This is important in combination with the lifting of the heavy object, since vessel motion creates additional loads on the crane, especially if the heavy lift crane is placed off-centre with respect to the centre line (a line connecting the bow and stern of the vessel).
- the installation of wind turbine foundations or similar structures is made more convenient, safer and with less damage, since swinging of objects is reduced.
- the present method can be applied in more severe weather conditions in which the usual method is not sufficient. The method can therefore be used throughout the entire year, which also makes the use of the vessel, equipment and personnel more cost-effective.
- deployment from a submerged cargo deck may be preferred during rough weather, while during fair weather the cargo deck may remain raised. This may shorten transit time between loading locations and deployment locations.
- the cargo deck is an elongated area and the heavy lift crane is located at one end of the cargo deck.
- the vessel may serve two different functionalities. Firstly, it is adapted to lift heavy objects from its submerged deployment zone, as part of the cargo deck. Secondly, if the crane is located at one end of the cargo deck, the vessel can serve as a floating dock. Because the cargo deck is a large unobstructed area, it allows for carrying large loads such as other ships or barges.
- the desired position is at the seabed and the method further comprises lowering the object to the seabed.
- the object is a wind turbine foundation or subsea installation.
- the crane will be able to lower objects to a depth of 400 meters below the water level or more.
- a plurality of objects are initially present on the cargo deck and the method comprises sequentially deploying each of the objects.
- offshore wind turbines are installed in groups. Therefore it is advantageous to install a sequence of wind turbine foundations.
- the cargo deck can hold at least 10 Jacket type wind turbine foundations of 1500 tonnes with a foot print of 28 meters by 28 meters or 11 Monopile type wind turbine foundations of 2000 tonnes each.
- the method comprises raising the cargo deck to a position above the level of the water and navigating the vessel from a first desired position after deploying a first object to a second desired location for deploying a second object. This is especially useful if the locations are far apart.
- the method further comprises loading the object onto the cargo deck at a dock and navigating the vessel to the desired position.
- the journey from the dock can take place in the raised position with the cargo deck only being submerged at the desired deployment location if weather conditions so require.
- the object remains at least partially submerged while lifting. As discussed above, this reduces the impact on the object because it avoids breaking the splash zone. It will be understood that for this to be achieved, there should be no upstanding obstructions between the cargo deck and the desired location that would require the object to be lifted up out of the water.
- the invention is in particular applicable to objects having a mass of greater than 100 tonnes or 500 tonnes, or even objects having a mass greater than 1000 tonnes or even objects having a mass greater than 3000 tonnes. Still further, it will be understood that it is particularly applicable to objects that are not buoyant i.e. objects that cannot be floated from a submerged cargo deck but must be lifted from the deck to their desired position.
- the object comprises a wind turbine foundation or subsea installation.
- a vessel for the transportation of objects, such as off-shore wind turbine foundations or subsea installations, and for deployment of such objects to desired positions overboard according to the features of claim 8.
- the vessel comprises: a bow and a stern; a submersible cargo deck located between the bow and the stern, the cargo deck comprising a deployment zone having an area of at least 1000 m2; and a heavy lift crane, adapted to lift the objects from the deployment zone while the deployment zone is submerged, and move the objects in an at least partially submerged state, to the desired position overboard.
- overboard is intended to refer to a position from which the object can be lowered into the water and, if required, to the sea bed.
- overboard will refer to positions beyond the extent of the vessel hull, it is not excluded that the object may be lowered through a moonpool or similar opening through the vessel.
- the vessel is preferably adapted for the method as described herein.
- the vessel may have all features and advantages as described in the context of the method. The person skilled in the art will understand that this is not a jack-up vessel. Jack-up vessels require to place legs to the seafloor in order to be able to use any heavy lift cranes. In contrast, the present vessel is able to use its heavy lift crane without the need to lower any legs. This saves operational time and thus lowers costs.
- the present vessel is self-propelled and may have a typical cruising speed / maximum velocity of at least 13 knots.
- the vessel comprises propulsion capacity sufficient for worldwide navigation, possibly excluding artic areas. Additionally, it may have thrusters or mooring equipment, sufficient for maintaining the vessel on station during deployment operations both in submerged and raised positions..
- vessels with submersible decks are known for transport of heavy floatable items.
- Ships, rigs, barges and the like may be transported on such semi-submersible vessels, whereby the vessel is initially ballasted to sink the cargo deck below the water level. Once the cargo is floated above the submersible deck, the vessel is then raised to lift the cargo out of the water. The vessel can then navigate to a new location with sea-handling similar to a conventional vessel (to the extent that the cargo is adequately secured). The cargo is unloaded be reversing the operation.
- a vessel of this type is the Dockwise Vanguard.
- Such known vessels have hitherto been used for buoyant loads that are capable of floating from the submersible deck once the vessel is sufficiently submerged. Nevertheless, existing vessels of this type have not been intended for lifting from and too the submersible deck and have thus not been provided with heavy lift cranes commensurate to the potential capacity of the vessel.
- the cargo deck is an elongated area and the heavy lift crane is located at a bow side of the cargo deck.
- the bow is adapted to remain unsubmerged during submergence of the cargo deck, and the heavy lift crane is located on a forecastle on the bow, preferably adjacent to the cargo deck.
- the operations bridge may be located on the forecastle and may also be positioned at least around the crane pedestal in order to improve visibility. It will also be understood that reference to the stern and bow sections is with respect to the normal direction of movement of the vessel.
- the vessel can have a larger cargo deck area, thus allowing for carrying more cargo.
- the forecastle extends across the full width of the vessel or the hull.
- the forecastle has a forecastle deck, which may have a width of at least 30 meters, preferably at least 50 meters, and a length of at least 40 meters, preferably at least 60 meters.
- the forecastle deck may be used for objects such as wind turbine transition pieces or relatively small wind turbine components.
- the forecastle deck is reachable by the heavy lift crane over its entire area.
- the forecastle may comprise all accommodation for the vessel's personnel.
- the advantage of having a large and especially wide, forecastle is that the area crossing the water level is relatively large, which increases the stability of the vessel even in the lowered condition when the cargo deck is submerged.
- the heavy lift crane is located off-centre with respect to a centre line connecting a bow and a stern of the vessel, preferably adjacent to a port-side or a starboard-side of the vessel. This provides for increased reach of the crane overboard on this side. It will be understood that the lift capacity at maximum sideways reach will be increased in the case that the vessel is lowered.
- the vessel further comprises at least one stern section, which is adapted to remain unsubmerged during submergence of the cargo deck.
- the stern section improves the stability of the vessel in a longitudinal direction.
- the one or more stern sections may have a combined minimum reserve buoyancy of at least 1.5%.
- the stern sections preferably have a waterline area of less than 1000 m2, more preferably less than 500 m2. In certain circumstances, the stern section may be omitted completely.
- the stern section comprises one or more tanks which can be displaced across the cargo deck or removed completely.
- the tanks can be placed at the most convenient positions depending on the particular objects to be shipped.
- the exact shape of the cargo deck area is thus variable. Variation of the cargo deck by movement of such tanks may be a constructional process to be carried out e.g. in port by external interaction or may be integral to the vessel i.e. the vessel may reconfigure itself using e.g. the heavy lift crane.
- the heavy lift crane has a lift capacity of at least 1000 tonnes, preferably at least 2000 tonnes and more preferably at least 3000 tonnes.
- the radius of the heavy lift crane may be more than 50 meters, preferably about 70 meters.
- the height of the heavy lift crane may be more than 80 meters above the deployment zone, preferably about 105 meters above the deployment zone.
- the cargo deck and deployment zone may have a width which is substantially equal to the width of the hull of the vessel, i.e. which extends from a port-side to a starboard-side of the hull.
- the cargo deck and the deployment zone extend over at least 80% of the width of the hull.
- the width of the cargo deck and deployment zone may be more than 30 meters, preferably more than 40 meters, more preferably more than 50 meters.
- the deployment zone has an area larger than 1000 m2, preferably larger than 2000 m2, more preferably larger than 2500 m2.
- the length of the cargo deck may be more than 80 meters, preferably more than 120 meters, more preferably about 150 meters.
- the cargo deck extends along at least 50% of the length of the vessel, more preferably at least 70% of the length of the vessel.
- the cargo deck may have a maximum tonnage / maximum load of 48000 tonnes.
- the cargo deck is typically provided at a height of 13 meters above the bottom of the hull.
- FIG. 1 schematically shows a vessel 1 which is intended for performing the method according to the invention.
- the vessel 1 comprises a cargo deck 2 which is located amidships in between a forecastle 10 at the bow 11 and a stern section 15 adjacent to the stern 12.
- the cargo deck 2 extends from the port-side 13 to the starboard-side 14.
- a heavy lift crane 3, intended to lift objects from the cargo deck 2, is located on the forecastle 10.
- the heavy lift crane 3 is located off-centre with respect to a centre-line CL connecting the bow 11 and stern 12 of the vessel 1, in this case adjacent to the starboard-side 14.
- the heavy lift crane 3 is located close to the bow end 20 of the cargo deck 2, such that it can reach over a substantial part of the cargo deck 2.
- the part of the cargo deck 2 that can be reached by the heavy lift crane 3 is referred to as the deployment zone 6.
- the crane 3 has a lifting capacity of 3000 tonnes and a radius of operation of 70 metres.
- the submersible cargo deck 2 has a width of 56 metres and an overall length of 150 metres, whereby it will be understood that only the first ⁇ 70 metres closest to the crane 3 serves as the deployment zone 6 according to the invention.
- the forecastle 10 has a width of 56 metres and a length of 65 metres.
- the stern section 15 has a total horizontal cross-section of 470 m2.
- the total deadweight tonnage/capacity of the vessel 1 is 48000 tonnes..
- FIG 2A schematically shows the vessel 1 of Figure 1 , wherein the cargo deck 2 including objects 4, 4a - wind turbine foundations - extends above the water level WL.
- FIG 2B the same vessel 1 is shown, but now the cargo deck 2 including deployment zone 6 is submerged and provided below the water level WL. Submerging of the cargo deck 2 may take place by filling of suitable ballast tanks in the hull (not shown). Only the forecastle 10 including the heavy lift crane 3, the stern section 15 and the objects 4, 4a partially extend above the water level WL. It will be understood that for certain smaller objects, the objects may be submerged entirely below the water level WL. When submerged, the movement of the vessel 1 is significantly improved, which is especially advantageous in severe weather conditions. Furthermore, the object 4 can be lifted more easily since the water provides buoyancy to the object 4.
- Figure 2C shows the vessel 1 where the heavy lift crane 3 has been employed to lift the object 4.
- the object 4 is lifted such that it can be moved freely but is still partially below the water level WL. In this way, swinging of the object 4 is reduced and lowering the object 4 involve less impact since the splash zone has already been passed by the object 4.
- Figure 2D shows the vessel 1 where the object 4 is lowered overboard at a lateral side of the vessel 1.
- the heavy lift crane 3 positions the object 4 on the seabed 5.
- the vessel 1 can proceed to lift and lower a subsequent object 4a from the cargo deck 2, more specifically from the deployment zone 6. This may take place at the same location or at a different location.
- the vessel 1 may be raised by pumping water from the ballast tanks to lift the cargo deck 2 above the water level. Alternatively, depending on the distance and the weather conditions, the vessel 1 may be moved to the new location with the cargo deck 2 submerged.
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Transportation (AREA)
- Jib Cranes (AREA)
- Wind Motors (AREA)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NL2021166A NL2021166B1 (en) | 2018-06-21 | 2018-06-21 | Method And Vessel For Deploying Heavy Objects |
PCT/NL2019/050385 WO2019245374A1 (en) | 2018-06-21 | 2019-06-21 | Method and vessel for deploying heavy objects |
Publications (2)
Publication Number | Publication Date |
---|---|
EP3810500A1 EP3810500A1 (en) | 2021-04-28 |
EP3810500B1 true EP3810500B1 (en) | 2022-08-03 |
Family
ID=63638255
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP19743076.2A Active EP3810500B1 (en) | 2018-06-21 | 2019-06-21 | Method and vessel for deploying heavy objects |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP3810500B1 (nl) |
NL (1) | NL2021166B1 (nl) |
WO (1) | WO2019245374A1 (nl) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112407171B (zh) * | 2020-12-28 | 2021-08-24 | 上海大学 | 一种无人潜航器布放回收系统及布放回收方法 |
WO2022229455A1 (en) | 2021-04-30 | 2022-11-03 | Itrec B.V. | Upend crane and installation vessel |
EP4389579A1 (en) * | 2022-12-20 | 2024-06-26 | Technip Energies France | Offshore floating intervention vessel, intended to temporarily support an offshore wind turbine platform, related assembly and intervention method |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5568495A (en) * | 1978-11-14 | 1980-05-23 | Mitsubishi Heavy Ind Ltd | Submarine type barge |
DK175261B1 (da) * | 2003-04-04 | 2004-08-02 | Logima V Svend Erik Hansen | Et fartöj til vindmölletransport, fremgangsmåder til flytning af en vindmölle samt en vindmölle til en offshore vindmöllepark |
EP2477882A1 (en) * | 2009-09-14 | 2012-07-25 | Eide Marine Services AS | Offshore equipment deploying and retrieving vessel |
NL2007833C2 (en) | 2010-11-22 | 2012-07-05 | Suction Pile Technology B V | Method of installing a high above the sea projecting slender offshore tower with suction pile foundation. |
DK201170319A (en) | 2011-06-21 | 2012-12-22 | Logima Aps | A self-propelled semi-submersible offshore wind farm installation vessel with a large crane |
NL2009028C2 (en) * | 2012-06-18 | 2013-12-23 | Itrec Bv | Off-shore installation vessel, method of operating an off-shore installation vessel. |
RU2668020C2 (ru) * | 2013-02-28 | 2018-09-25 | Кеппел Оффшор Энд Марин Текнолоджи Сентр Пте. Лтд. | Судно, совмещающее функции перевозки тяжеловесных грузов и логистики |
-
2018
- 2018-06-21 NL NL2021166A patent/NL2021166B1/en not_active IP Right Cessation
-
2019
- 2019-06-21 EP EP19743076.2A patent/EP3810500B1/en active Active
- 2019-06-21 WO PCT/NL2019/050385 patent/WO2019245374A1/en active Search and Examination
Also Published As
Publication number | Publication date |
---|---|
EP3810500A1 (en) | 2021-04-28 |
WO2019245374A1 (en) | 2019-12-26 |
NL2021166B1 (en) | 2020-01-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101785965B1 (ko) | 단일 선체 선박 및 장비를 잠수시키거나 잠수된 장비를 회수하는 방법 | |
EP1766143B1 (en) | Ballasting offshore platform with buoy assistance | |
AU701557B2 (en) | Offshore apparatus and method for oil operations | |
EP1984237B1 (en) | Deep water installation vessel | |
US8707882B2 (en) | Offshore platform with outset columns | |
EP3529141B1 (en) | Self-propelled jack-up vessel | |
EP3810500B1 (en) | Method and vessel for deploying heavy objects | |
FI114306B (fi) | Menetelmä ja ponttoni kannen asentamiseksi kelluvalle meritekniselle alusrakenteelle | |
EP2726362A1 (en) | Offshore platform with outset columns | |
CN104203746B (zh) | 具有用于干式停靠船只的可动潜式平台的半潜式平台 | |
RU2145289C1 (ru) | Способ швартовки плавучего наливного судна и система для швартовки плавучего наливного судна | |
WO2007097610A1 (en) | Semi-submersible vessel, method for operating a semi-submersible vessel and method for manufacturing a semi-submersible vessel | |
WO2001064507A1 (en) | Submersible heavy lift catamaran | |
EP2961649B1 (en) | An integrated heavy lift and logistics vessel | |
CN107187554B (zh) | 用于半潜式钻井平台干拖运输的双体半潜驳船及作业方法 | |
WO2017141177A1 (en) | Barge system | |
CN206297709U (zh) | 半潜式船 | |
WO2003086852A1 (en) | Submersible watercraft | |
KR20130003914A (ko) | 선박용 아지무스 쓰러스터의 육상 설치 방법 | |
US20220355907A1 (en) | Systems and methods for a rack structure for a transport vessel adapted for use with an offshore self-elevating vessel | |
WO2024218286A1 (en) | Load out method and system for an offshore floating wind turbine | |
GB2628092A (en) | Semi-submersible floating offshore wind vessel having a submersible hull comprising variable ballast pontoons | |
KR20140111123A (ko) | 소규모 도크를 이용한 반 잠수형 시추선 건조 공법 | |
Macy et al. | TOWING, MOTIONS, AND STABILITY CHARACTERISTICS OF OCEAN PLATFORMS | |
KR20180040254A (ko) | 생산물 운반선 측방 계류를 위한 선체 구조를 가지는 수리용 부선거 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: UNKNOWN |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20201224 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
DAV | Request for validation of the european patent (deleted) | ||
DAX | Request for extension of the european patent (deleted) | ||
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20211014 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20220124 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 1508538 Country of ref document: AT Kind code of ref document: T Effective date: 20220815 Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602019017849 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: FP |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG9D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20221205 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20221103 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 1508538 Country of ref document: AT Kind code of ref document: T Effective date: 20220803 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20221203 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20221104 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602019017849 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 |
|
26N | No opposition filed |
Effective date: 20230504 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602019017849 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20230630 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20230621 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230621 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230621 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230621 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230621 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20240103 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230630 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230621 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220803 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230630 Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230630 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20240610 Year of fee payment: 6 |