EP3276037B1 - Method of manufacturing a hot-dip galvanized steel sheet - Google Patents

Method of manufacturing a hot-dip galvanized steel sheet Download PDF

Info

Publication number
EP3276037B1
EP3276037B1 EP16767930.7A EP16767930A EP3276037B1 EP 3276037 B1 EP3276037 B1 EP 3276037B1 EP 16767930 A EP16767930 A EP 16767930A EP 3276037 B1 EP3276037 B1 EP 3276037B1
Authority
EP
European Patent Office
Prior art keywords
pipe
gas
zone
dry gas
hot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP16767930.7A
Other languages
German (de)
French (fr)
Other versions
EP3276037A1 (en
EP3276037A4 (en
Inventor
Gentaro Takeda
Masaru Miyake
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Publication of EP3276037A1 publication Critical patent/EP3276037A1/en
Publication of EP3276037A4 publication Critical patent/EP3276037A4/en
Application granted granted Critical
Publication of EP3276037B1 publication Critical patent/EP3276037B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/52Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for wires; for strips ; for rods of unlimited length
    • C21D9/54Furnaces for treating strips or wire
    • C21D9/56Continuous furnaces for strip or wire
    • C21D9/561Continuous furnaces for strip or wire with a controlled atmosphere or vacuum
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D1/00General methods or devices for heat treatment, e.g. annealing, hardening, quenching or tempering
    • C21D1/74Methods of treatment in inert gas, controlled atmosphere, vacuum or pulverulent material
    • C21D1/76Adjusting the composition of the atmosphere
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/46Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for sheet metals
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/52Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for wires; for strips ; for rods of unlimited length
    • C21D9/54Furnaces for treating strips or wire
    • C21D9/56Continuous furnaces for strip or wire
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22CALLOYS
    • C22C38/00Ferrous alloys, e.g. steel alloys
    • C22C38/02Ferrous alloys, e.g. steel alloys containing silicon
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C2/00Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor
    • C23C2/003Apparatus
    • C23C2/0038Apparatus characterised by the pre-treatment chambers located immediately upstream of the bath or occurring locally before the dipping process
    • C23C2/004Snouts
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C2/00Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor
    • C23C2/02Pretreatment of the material to be coated, e.g. for coating on selected surface areas
    • C23C2/022Pretreatment of the material to be coated, e.g. for coating on selected surface areas by heating
    • C23C2/0222Pretreatment of the material to be coated, e.g. for coating on selected surface areas by heating in a reactive atmosphere, e.g. oxidising or reducing atmosphere
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C2/00Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor
    • C23C2/02Pretreatment of the material to be coated, e.g. for coating on selected surface areas
    • C23C2/022Pretreatment of the material to be coated, e.g. for coating on selected surface areas by heating
    • C23C2/0224Two or more thermal pretreatments
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C2/00Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor
    • C23C2/04Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor characterised by the coating material
    • C23C2/06Zinc or cadmium or alloys based thereon
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C2/00Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor
    • C23C2/26After-treatment
    • C23C2/28Thermal after-treatment, e.g. treatment in oil bath
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C2/00Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor
    • C23C2/34Hot-dipping or immersion processes for applying the coating material in the molten state without affecting the shape; Apparatus therefor characterised by the shape of the material to be treated
    • C23C2/36Elongated material
    • C23C2/40Plates; Strips
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22CALLOYS
    • C22C18/00Alloys based on zinc
    • C22C18/04Alloys based on zinc with aluminium as the next major constituent
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22CALLOYS
    • C22C38/00Ferrous alloys, e.g. steel alloys
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22CALLOYS
    • C22C38/00Ferrous alloys, e.g. steel alloys
    • C22C38/14Ferrous alloys, e.g. steel alloys containing titanium or zirconium

Definitions

  • This disclosure relates to a method of producing hot-dip galvanized steel sheets using a continuous hot-dip galvanizing apparatus including an annealing furnace in which a heating zone, a soaking zone, and a cooling zone are arranged in this order and a hot-dip galvanizing line adjacent to the cooling zone.
  • high tensile strength steel sheets which contribute to lighter-weight structures and the like
  • high tensile strength steel materials for example, it is known that a steel sheet with favorable hole expansion formability can be produced through inclusion of Si in steel, and a steel sheet with favorable ductility where retained austenite ( ⁇ ) forms easily can be produced through inclusion of Si or Al in steel.
  • the galvannealed steel sheet is produced by, after heat-annealing the base material steel sheet at a temperature of about 600 °C to 900 °C in a reducing atmosphere or a non-oxidizing atmosphere, hot-dip galvanizing the steel sheet and further heat-alloying the galvanized coating.
  • Si in the steel is an oxidizable element, and is thus selectively oxidized in a typically used reducing atmosphere or non-oxidizing atmosphere, and concentrated at the surface of the steel sheet in the form of an oxide.
  • This oxide decreases wettability with molten zinc in the galvanizing process, and causes non-coating.
  • Si concentration in the steel With an increase of the Si concentration in the steel wettability decreases rapidly and non-coating occurs frequently. Even in the case where non-coating does not occur, there is still a problem of poor coating adhesion.
  • Si in the steel is selectively oxidized and concentrated at the surface of the steel sheet, a significant alloying delay arises in the alloying process after the hot-dip galvanizing, leading to considerably lower productivity.
  • WO2007/043273 A1 (PTL 1) describes the following technique in relation to the problems set forth above.
  • Si is internally oxidized and concentration of Si at the surface of the steel sheet is prevented by performing annealing under conditions including: heating or soaking the steel sheet at a steel sheet temperature in a range of 300 °C or higher by indirect heating; setting the atmosphere inside the furnace in each zone to an atmosphere of 1 vol% to 10 vol% hydrogen with the balance being nitrogen and incidental impurities; setting the steel sheet end-point temperature during heating in the upstream heating zone to 550 °C or higher and 750 °C or lower and the dew point in the upstream heating zone to lower than -25 °C; setting the dew point in the subsequent downstream heating zone and soaking zone to -30 °C or higher and 0
  • PTL 1 also describes humidifying mixed gas of nitrogen and hydrogen and introducing the mixed gas into the downstream heating zone and/or the soaking zone.
  • US 2009/0123651 A1 (PTL 2) describes a continuous annealing and hot dip plating method using an annealing furnace having, in order, a front heating zone, rear heating zone, soaking zone, and cooling zone and a hot dip plating bath, comprising heating or soaking the steel sheet at a steel sheet temperature of a temperature range of at least 300° C or more by indirect heating, wherein an atmosphere of the zones is comprised of hydrogen H: 1 to 10 vol % and a balance of nitrogen and unavoidable impurities, a steel sheet peak temperature during heating at the front heating zone is 550 to 750° C, the dew point is less than -25° C in the front heating zone, the dew points of the following rear heating zone and soaking zone is -30° C to 0° C, and wherein a dew point of the cooling zone less than -25° C.
  • JP 2008 275 185 A (PTL 3) describes a humidified gas supply method for mixing a saturated moist gas supplied from a humidifying passage having a humidifier and a dry gas supplied from a dry gas passage to produce the humidified gas of predetermined flow rate and predetermined moisture amount, and supplying the same to a humidified gas use destination from the humidified gas supply passage, the pressure and temperature of the saturated moist gas are measured, and a flow rate of the saturated moist gas and a flow rate of the dry gas are respectively set on the basis of the moisture amount of the saturated moist gas and the moisture amount and flow rate of the humidified gas calculated on the basis of the measured pressure and temperature.
  • WO 2014/132638 A1 describes a method for manufacturing hot dip galvanized steel sheets using a continuous hot dip galvanization device provided with a direct fire-type heating zone in which burners are disposed facing the surface of the steel sheet, wherein the dew point of the gas input in the burners is adjusted and hot dip galvanized steel sheets of excellent plating appearance can be obtained even with Si-containing steel.
  • humidified gas is supplied to the soaking zone in addition to reducing or non-oxidizing dry gas, as described in PTL 1, in order to raise the dew point in the soaking zone.
  • a normal strength steel sheet hereinafter, referred to as a "normal steel sheet”
  • only reducing or non-oxidizing dry gas is supplied to the soaking zone and humidified gas is not supplied. Therefore, in a situation such as when a high tensile strength steel sheet and a normal steel sheet are to be produced consecutively, it is necessary to switch between use and non-use of humidified gas during operation.
  • the continuous hot-dip galvanizing apparatus 100 includes an annealing furnace 20 in which a heating zone 10, a soaking zone 12, and cooling zones 14 and 16 are arranged in this order, a hot-dip galvanizing bath 22 adjacent to the cooling zone 16 that serves as a hot-dip galvanizing line, and an alloying line 24 adjacent to the hot-dip galvanizing bath 22.
  • the heating zone 10 in this embodiment includes a first heating zone 10A (upstream heating zone) and a second heating zone 10B (downstream heating zone).
  • the cooling zone includes a first cooling zone 14 (rapid cooling zone) and a second cooling zone 16 (slow cooling zone).
  • a snout 18 connected to the second cooling zone 16 has its tip immersed in the hot-dip galvanizing bath 22, thus connecting the annealing furnace 20 and the hot-dip galvanizing bath 22.
  • a steel strip P is introduced into the first heating zone 10A from a steel strip introduction port in a lower part of the first heating zone 10A.
  • One or more hearth rolls are arranged in upper and lower parts of each of the zones 10, 12, 14, and 16.
  • the steel strip P is conveyed vertically a plurality of times inside a corresponding zone of the annealing furnace 20, forming a plurality of passes. While FIG. 1 illustrates an example of having 10 passes in the soaking zone 12, 2 passes in the first cooling zone 14, and 2 passes in the second cooling zone 16, the numbers of passes are not limited to those in this example, and may be set as appropriate depending on the processing conditions.
  • the steel strip P is not folded back but changed in direction at a right angle to move to the next zone.
  • the steel strip P is thus annealed in the annealing furnace 20 by being conveyed through the heating zone 10, the soaking zone 12, and the cooling zones 14 and 16 in this order.
  • Adjacent zones in the annealing furnace 20 communicate through a communication portion connecting the upper parts or lower parts of the respective zones.
  • the first heating zone 10A and the second heating zone 10B communicate through a throat (restriction portion) connecting the upper parts of the respective zones.
  • the second heating zone 10B and the soaking zone 12 communicate through a throat connecting the lower parts of the respective zones.
  • the soaking zone 12 and the first cooling zone 14 communicate through a throat connecting the lower parts of the respective zones.
  • the first cooling zone 14 and the second cooling zone 16 communicate through a throat connecting the lower parts of the respective zones.
  • the height of each throat may be set as appropriate, it is preferable that the height of each throat is as low as possible to enhance the independence of the atmosphere in each zone.
  • Gas in the annealing furnace 20 flows from downstream to upstream and is discharged from the steel strip introduction port in the lower part of the first heating zone 10A.
  • the second heating zone 10B is a direct fired furnace (DFF).
  • the DFF may be a commonly known DFF.
  • Burners are distributed in the inner wall of the direct fired furnace in the second heating zone 10B so as to face the steel strip P (note that these burners are not illustrated in FIG. 1 ). It is preferable that the burners are divided into groups, and that the combustion rate and the air ratio in each group are independently controllable.
  • Combustion exhaust gas in the second heating zone 10B is supplied into the first heating zone 10A, and the steel strip P is preheated by the heat of the gas.
  • the combustion rate is a value obtained by dividing the amount of fuel gas actually introduced into a burner by the amount of fuel gas of the burner under its maximum combustion load.
  • the combustion rate at the time of combustion by the burner under its maximum combustion load is 100 %.
  • the combustion rate is preferably adjusted to 30 % or more.
  • the air ratio is a value obtained by dividing the amount of air actually introduced into a burner by the amount of air necessary for complete combustion of fuel gas.
  • the heating burners in the second heating zone 10B are divided into four groups (#1 to #4), and the three groups (#1 to #3) upstream in the steel sheet traveling direction are made up of oxidizing burners, and the last group (#4) is made up of reducing burners.
  • the air ratio of the oxidizing burners and the air ratio of the reducing burners are independently controllable.
  • the air ratio of the oxidizing burners is preferably adjusted to 0.95 or more and 1.5 or less.
  • the air ratio of the reducing burners is preferably adjusted to 0.5 or more and less than 0.95.
  • the temperature in the second heating zone 10B is preferably adjusted to 800 °C to 1200 °C.
  • the soaking zone 12 is capable of indirectly heating the steel strip P using a radiant tube (RT) (not illustrated) as heating means.
  • the average temperature Tr (°C) in the soaking zone 12 is measured by inserting a thermocouple into the soaking zone 12 and is preferably adjusted to 700 °C to 900 °C.
  • Reducing gas or non-oxidizing gas is supplied to the soaking zone 12.
  • H 2 /N 2 mixed gas is typically used as the reducing gas.
  • An example is gas (dew point: about -60 °C) having a composition containing 1 vol% to 20 vol% H 2 with the balance being N 2 and incidental impurities.
  • An example of the non-oxidizing gas is gas (dew point: about -60 °C) having a composition containing N 2 and incidental impurities.
  • the reducing gas or non-oxidizing gas supplied to the soaking zone 12 is in two forms: mixed gas and dry gas.
  • dry gas refers to reducing gas or non-oxidizing gas that has a dew point of about -60 °C to -50 °C and that is not humidified by a humidifying device.
  • mixed gas refers to gas obtained through mixing of gas that is humidified by the humidifying device and gas that is not humidified by the humidifying device in a specific mixing ratio such as to have a dew point of -20 °C to 10 °C.
  • a supply system for supplying mixed gas and dry gas to the soaking zone 12 is described with reference to FIG. 2 .
  • the supply system includes, from upstream, a first pipe 31, a second pipe 32, a third pipe 33, a fourth pipe 34, a fifth pipe 35, and a sixth pipe 36, and also includes a gas distribution device 40, a humidifying device 50, a gas mixing device 60, and a draining device 80.
  • Dry gas that is supplied from a gas supply source passes through the first pipe 31.
  • the gas distribution device 40 is connected to the first pipe 31 and distributes dry gas that has passed through the first pipe 31 in a freely variable ratio to the following three systems: the second pipe 32, the third pipe 33, and the fourth pipe 34.
  • the second pipe 32, the third pipe 33, and the fourth pipe 34 branch from the gas distribution device 40 and dry gas that has been distributed by the gas distribution device 40 passes therethrough. Specifically, one portion of dry gas that has passed through the first pipe 31 is supplied to the humidifying device 50 through the second pipe 32, another portion of this dry gas is supplied to the gas mixing device 60 through the third pipe 33, and the remaining portion of this dry gas is supplied straight to the soaking zone 12 through the fourth pipe 34.
  • the gas distribution device 40 cuts off distribution to the second pipe 32 and the third pipe 33 during non-use of mixed gas described further below.
  • Dry gas that has passed through the fourth pipe 34 is supplied into the soaking zone 12 via dry gas supply ports 72A, 72B, 72C, and 72D that are disposed in the soaking zone 12.
  • the position and number of dry gas supply ports is not specifically limited and may be set as appropriate in consideration of various conditions. However, it is preferable that a plurality of dry gas supply ports is arranged at the same height position and that dry gas supply ports are arranged uniformly in the steel strip traveling direction.
  • the humidifying device 50 is connected to the second pipe 32 and dry gas that has passed through the second pipe 32 is introduced therein.
  • the fifth pipe 35 extends from the humidifying device 50 and humidified gas that has been humidified by the humidifying device 50 passes therethrough.
  • the gas mixing device 60 is connected to the third pipe 33 and the fifth pipe 35, and prepares mixed gas having a desired dew point by mixing dry gas that has passed through the third pipe and humidified gas that has passed through the fifth pipe in a given ratio that can be varied.
  • the sixth pipe 36 is a mixed gas pipe that extends from the gas mixing device 60, and mixed gas discharged from the gas mixing device 60 passes therethrough. Mixed gas that has passed through the sixth pipe 36 is supplied into the soaking zone 12 via one or more mixed gas supply ports that are disposed in the soaking zone 12.
  • mixed gas is supplied by two systems: a system of mixed gas supply ports 70A, 70B, and 70C and a system of mixed gas supply ports 71A, 71B, and 71C.
  • the position and number of mixed gas supply ports is not specifically limited and may be set as appropriate in consideration of various conditions. It is preferable that, as in this embodiment, a plurality of mixed gas supply ports is arranged at each of two or more different height positions and that mixed gas supply ports are arranged uniformly in the steel strip traveling direction.
  • the dew point of the mixed gas can be measured by a mixed gas dew point meter 74 disposed in the sixth pipe.
  • the humidifying device 50 includes a tube-shaped module 52 and a circulating constant-temperature water bath 54. Vapor permeable membranes 51 are disposed in the module 52.
  • the vapor permeable membranes 51 in this embodiment are fluorine or polyimide hollow fiber membranes. Although only two vapor permeable membranes 51 are illustrated in FIG. 3 , about 50 to 500 membranes are arranged substantially in parallel.
  • the dry gas that has passed through the second pipe 32 flows through the inside 53A of the vapor permeable membranes, whereas pure water adjusted to a specific temperature in the circulating constant-temperature water bath 54 circulates at the outside 53B of the vapor permeable membranes.
  • the outside 53B of the vapor permeable membranes in the module is in communication with the circulating constant-temperature water bath 54 via passages 55A and 55B.
  • the fluorine or polyimide hollow fiber membranes are each a type of ion exchange membrane with affinity for water molecules.
  • moisture concentration differs between the inside and outside of the hollow fiber membrane, a force for equalizing the moisture concentration difference arises and, with this force as a driving force, moisture permeates through the membrane to move to the side with lower moisture concentration.
  • dry gas is humidified to obtain humidified gas when the dry gas passes through the inside 53A of the vapor permeable membranes in the module 52.
  • the temperature of dry gas varies with seasonal or daily air temperature change. In this embodiment, however, heat exchange is possible by ensuring a sufficient contact area between gas and water through the vapor permeable membranes 51.
  • the dry gas is humidified to the same dew point as the set water temperature, thus achieving highly accurate dew point control.
  • the dew point of the humidified gas can be controlled to any value in the range of 5 °C to 50 °C.
  • a humidified gas pipe is, therefore, heated/heat-retained to at least the dew point of the humidified gas and at least the external air temperature.
  • the internal configuration of the module 52 is not limited to the configuration illustrated in FIG. 3 .
  • the vapor permeable membranes may alternatively be fluorine or polyimide flat membranes.
  • the dry gas that has passed through the second pipe 32 is humidified by, while the dry gas passes through one space in the module that is separated by the vapor permeable membranes, circulating water through another space in the module using the circulating constant-temperature water bath 54.
  • a feature of the continuous hot-dip galvanizing apparatus 100 in this embodiment is that the continuous hot-dip galvanizing apparatus 100 includes the draining device 80 for draining water from the space at the outside 53B of the vapor permeable membranes in the module when mixed gas is not supplied to the soaking zone.
  • FIG. 3 illustrates an example of the draining device 80.
  • the draining device 80 includes a first isolation valve 82, a second passage 84, a second isolation valve 86, and a drainage tank 88.
  • the first isolation valve 82 is disposed in the passage 55B through which water passes when moving toward the circulating constant-temperature water bath 54 from the outside 53B of the vapor permeable membranes in the module.
  • the second passage 84 branches from the passage 55B at a section that is further upstream than the first isolation valve 82 (i.e., toward the outside 53B of the vapor permeable membranes). A tip of the second passage 84 is positioned above the drainage tank 88. The second isolation valve 86 is disposed in the second passage 84. The drainage tank 88 holds water that is drained from the second passage 84.
  • the first isolation valve 82 While humidified gas is being produced, the first isolation valve 82 is fully opened, the second isolation valve 86 is fully closed, and the circulating constant-temperature water bath 54 is used to circulate water at the outside 53B of the vapor permeable membranes in the module. While humidified gas is not being produced, water circulation is stopped, the second isolation valve 86 is fully opened, and the first isolation valve 82 is fully closed to drain water toward the drainage tank 88 from the space at the outside 53B of the vapor permeable membranes in the module. In a situation in which it is not possible to position the module 52 at least 200 mm higher than the top of the drainage tank 88, it is preferable that a suction device or the like is disposed at the drainage tank side in order to drain water in the humidifying device.
  • mixed gas containing humidified gas is supplied to the soaking zone 12 in addition to dry gas.
  • this state is referred to as a "first operational state”.
  • second operational state In production of a normal steel sheet, only dry gas is supplied to the soaking zone 12, and mixed gas is not supplied.
  • this state is referred to as a "second operational state”.
  • switching between the first operational state and the second operational state is performed as follows.
  • the first operational state water is circulated using the circulating constant-temperature water bath 54 and humidified gas is produced in a state in which the first isolation valve 82 is fully opened and the second isolation valve 86 is fully closed.
  • the second operational state distribution of dry gas to the second pipe 32 is stopped and water circulation using the circulating constant-temperature water bath 54 is stopped, and subsequently water is drained from the space at the outside 53B of the vapor permeable membranes in the module using the draining device 80.
  • the second isolation valve 86 is fully opened and the first isolation valve 82 is fully closed.
  • Switching in this manner can prevent condensation and accumulation of excessively humidified gas in pipes upstream and downstream of the module 52 (i.e., the second pipe 32 and the fifth pipe 35), and further downstream in the sixth pipe 36, while in the second operational state. Accordingly, condensation and excessively humidified gas do not enter the soaking zone 12 upon switching from the second operational state to the first operational state. This can inhibit the occurrence of roll pick-up in the soaking zone 12 and, as a result, enables favorable coating appearance to be obtained.
  • the gas flow rate Qrd of dry gas supplied to the soaking zone 12 via the fourth pipe 34 in the first operational state and the second operational state is measured by a gas flowmeter (not illustrated) disposed in the fourth pipe 34.
  • the gas flow rate Qrd is about 0 Nm 3 /hr to 600 Nm 3 /hr. This maintains the furnace pressure in the soaking zone 12 at an appropriate pressure (higher than the direct fired zone) but without the furnace pressure becoming excessively high.
  • the gas flow rate Qrw of mixed gas supplied to the soaking zone 12 via the sixth pipe 36 in the first operational state is measured by a gas flowmeter (not illustrated) disposed in the sixth pipe 36.
  • a gas flowmeter not illustrated
  • the gas flow rate Qrw is about 100 Nm 3 /hr to 500 Nm 3 /hr. This maintains the furnace pressure in the soaking zone 12 at an appropriate pressure (higher than the direct fired zone) but without the furnace pressure becoming excessively high.
  • the dew point in the soaking zone 12 is constantly controlled to -20 °C or higher and 0 °C or lower in the first operational state.
  • Dew point meters are installed at at least one location (dew point measurement position 75A) near lower part hearth rolls 73B (lowest part of the soaking zone) and at least one location (dew point measurement position 75B) below upper part hearth rolls 73A at a higher position than half way up the soaking zone in a height direction (upper part of the soaking zone). Controlling the dew point in the soaking zone 12 to -20°C or higher enables an appropriate alloying temperature in subsequent alloying treatment and enables desired mechanical properties to be obtained.
  • the upper limit of the dew point is preferably 0 °C in terms of uniformity of the dew point distribution in the soaking zone 12 and minimization of the dew point variation range.
  • Mixed gas having a freely selected dew point can be supplied into the soaking zone 12 by adjusting the mixing proportions of gases in the gas mixing device 30.
  • Mixed gas having a high dew point may be supplied to the soaking zone 1 2 if the dew point in the soaking zone 12 is about to fall below the target range.
  • mixed gas having a low dew point may be supplied to the soaking zone 12 if the dew point in the soaking zone 12 is about to rise above the target range.
  • the dew point in the soaking zone 12 can be constantly controlled to -20 °C or higher and 0 °C or lower in the first operational state.
  • the cooling zones 14 and 16 cool the steel strip P.
  • the steel strip P is cooled to about 480 °C to 530 °C in the first cooling zone 14, and cooled to about 470 °C to 500 °C in the second cooling zone 16.
  • the cooling zones 14 and 16 are also supplied with the aforementioned reducing gas or non-oxidizing gas, but in the case of the cooling zones 14 and 16, only dry gas is supplied. Although no specific limitations are placed on supply of dry gas to the cooling zones 14 and 16, it is preferable that the dry gas is supplied from supply ports at at least two locations in a height direction and at least two locations in a longitudinal direction to enable uniform supply into the cooling zone.
  • the total gas flow rate Qcd of dry gas supplied to the cooling zones 14 and 16 is measured by one or more gas flowmeters (not illustrated) disposed in pipes. Although no specific limitations are placed on the total gas flow rate Qcd, the total gas flow rate Qcd is about 200 Nm 3 /hr to 1,000 Nm 3 /hr. This maintains the furnace pressure in the soaking zone 12 at an appropriate pressure (higher than the direct fired zone) but without the furnace pressure becoming excessively high.
  • the hot-dip galvanizing bath 22 can be used to apply a hot-dip galvanized coating onto the steel strip P exiting from the second cooling zone 16.
  • the hot-dip galvanizing may be performed according to a usual method.
  • the alloying line 24 can be used to heat-alloy the galvanized coating applied onto the steel strip P.
  • the alloying treatment may be performed according to a usual method. In this embodiment, the alloying temperature is kept from being high, thus preventing a decrease in tensile strength of the produced galvannealed steel sheet.
  • the alloying line 24 and the alloying treatment performed thereby are not essential to the disclosed techniques because the effects of inhibiting roll pick-up in the soaking zone caused by condensation or the like in a humidified gas pipe and obtaining favorable coating appearance can be achieved even when the alloying treatment is omitted.
  • the continuous hot-dip galvanizing apparatus illustrated in FIGS. 1 to 3 was used to anneal steel strips having chemical compositions shown in Table 1 under annealing conditions shown in Table 2, and then hot-dip galvanize and alloy the steel strips.
  • Steel sample ID A is normal steel and steel sample ID B is high tensile strength steel.
  • annealing, hot-dip galvanizing, and alloying treatment were performed continuously with a sheet passing order shown in Table 2.
  • a DFF was used as the second heating zone. Heating burners were divided into four groups (#1 to #4) where the three groups (#1 to #3) upstream in the steel sheet traveling direction were made up of oxidizing burners and the last group (#4) was made up of reducing burners, and the air ratios of the oxidizing burners and reducing burners were set to the values shown in Table 2. The length of each group in the steel sheet conveyance direction was 4 m.
  • An RT furnace having a volume Vr of 700 m 3 was used as the soaking zone.
  • the average temperature Tr in the soaking zone was set to the value shown in Table 2.
  • Gas (dew point: -50 °C) having a composition containing 15 vol% H 2 with the balance being N 2 and incidental impurities was used as dry gas.
  • a portion of the dry gas was humidified by a humidifying device having 10 hollow fiber membrane-type humidifying modules to prepare mixed gas. In each of the modules, the maximum dry gas flow rate was 500 L/min and the maximum water circulation rate was 10 L/min.
  • a circulating constant-temperature water bath capable of supplying a total of 100 L/min of pure water was used as a common water bath for each of the modules. Dry gas supply ports and mixed gas supply ports were arranged at the positions illustrated in FIG. 2 .
  • the draining device illustrated in FIG. 3 was also set-up.
  • gas was supplied to the soaking zone by adopting the second operational state during passing of a sheet with steel sample ID A and adopting the first operational state during passing of a sheet with steel sample ID B.
  • the dry gas flow rate Qrd, mixed gas flow rate Qrw, and mixed gas dew point shown in Table 2 are each a stable value during passing of a corresponding sheet.
  • the dry gas (dew point: -50 °C) was supplied to the first and second cooling zones at the lowest part of each of the zones with the flow rate shown in Table 2.
  • the temperature of the molten bath was set to 460 °C
  • the Al concentration in the molten bath was set to 0.130 %
  • the coating weight was adjusted to 45 g/m 2 per surface by gas wiping.
  • the line speed was set to 80 mpm to 100 mpm.
  • alloying treatment was performed in an induction heating-type alloying furnace so that the coating alloying degree (Fe content) was 10 % to 13 %.
  • the alloying temperature in the treatment was as shown in Table 2.
  • Evaluation of the coating appearance was conducted through inspection by an optical surface defect meter (detection of non-coating defects or overoxidation defects of ⁇ 0.5 or more) and visual determination of alloying unevenness. Samples passing all criteria were rated “excellent”, samples having a low degree of alloying unevenness were rated “good”, and samples failing at least one of the criteria were rated “poor”. The results are shown in Table 2.
  • Comparative Example No. 1 mixed gas was supplied to raise the dew point of the soaking zone during passing of a sheet with steel sample ID B, and thus it was not necessary to excessively raise the alloying temperature and there was no problem in terms of tensile strength.
  • moisture that had condensed in pipes was supplied into the soaking zone when supply of humidified gas was started for passing of the second sheet. This caused localized elevation of the dew point near the hearth rolls, leading to the occurrence of roll pick-up, and scratches due to this roll pick-up were formed in the steel strip surface. This resulted in poorer coating appearance for the second passed sheet through to the fourth passed sheet.

Description

    TECHNICAL FIELD
  • This disclosure relates to a method of producing hot-dip galvanized steel sheets using a continuous hot-dip galvanizing apparatus including an annealing furnace in which a heating zone, a soaking zone, and a cooling zone are arranged in this order and a hot-dip galvanizing line adjacent to the cooling zone.
  • BACKGROUND
  • In recent years, the demand for high tensile strength steel sheets (high tensile steel sheets) which contribute to lighter-weight structures and the like is increasing in the fields of automobiles, household appliances, building products, and so forth. As high tensile strength steel materials, for example, it is known that a steel sheet with favorable hole expansion formability can be produced through inclusion of Si in steel, and a steel sheet with favorable ductility where retained austenite (γ) forms easily can be produced through inclusion of Si or Al in steel.
  • However, in the case of producing a galvannealed steel sheet using, as a base material, a high tensile strength steel sheet containing a large amount of Si (particularly, 0.2 mass% or more), the following problem arises. The galvannealed steel sheet is produced by, after heat-annealing the base material steel sheet at a temperature of about 600 °C to 900 °C in a reducing atmosphere or a non-oxidizing atmosphere, hot-dip galvanizing the steel sheet and further heat-alloying the galvanized coating.
  • Si in the steel is an oxidizable element, and is thus selectively oxidized in a typically used reducing atmosphere or non-oxidizing atmosphere, and concentrated at the surface of the steel sheet in the form of an oxide. This oxide decreases wettability with molten zinc in the galvanizing process, and causes non-coating. With an increase of the Si concentration in the steel wettability decreases rapidly and non-coating occurs frequently. Even in the case where non-coating does not occur, there is still a problem of poor coating adhesion. Moreover, if Si in the steel is selectively oxidized and concentrated at the surface of the steel sheet, a significant alloying delay arises in the alloying process after the hot-dip galvanizing, leading to considerably lower productivity.
  • WO2007/043273 A1 (PTL 1) describes the following technique in relation to the problems set forth above. In a continuous annealing and hot-dip coating method that uses an annealing furnace having an upstream heating zone, a downstream heating zone, a soaking zone, and a cooling zone arranged in this order and a hot-dip molten bath, Si is internally oxidized and concentration of Si at the surface of the steel sheet is prevented by performing annealing under conditions including: heating or soaking the steel sheet at a steel sheet temperature in a range of 300 °C or higher by indirect heating; setting the atmosphere inside the furnace in each zone to an atmosphere of 1 vol% to 10 vol% hydrogen with the balance being nitrogen and incidental impurities; setting the steel sheet end-point temperature during heating in the upstream heating zone to 550 °C or higher and 750 °C or lower and the dew point in the upstream heating zone to lower than -25 °C; setting the dew point in the subsequent downstream heating zone and soaking zone to -30 °C or higher and 0 °C or lower; and setting the dew point in the cooling zone to lower than -25 °C. PTL 1 also describes humidifying mixed gas of nitrogen and hydrogen and introducing the mixed gas into the downstream heating zone and/or the soaking zone.
    US 2009/0123651 A1 (PTL 2) describes a continuous annealing and hot dip plating method using an annealing furnace having, in order, a front heating zone, rear heating zone, soaking zone, and cooling zone and a hot dip plating bath, comprising heating or soaking the steel sheet at a steel sheet temperature of a temperature range of at least 300° C or more by indirect heating, wherein an atmosphere of the zones is comprised of hydrogen H: 1 to 10 vol % and a balance of nitrogen and unavoidable impurities, a steel sheet peak temperature during heating at the front heating zone is 550 to 750° C, the dew point is less than -25° C in the front heating zone, the dew points of the following rear heating zone and soaking zone is -30° C to 0° C, and wherein a dew point of the cooling zone less than -25° C. JP 2008 275 185 A (PTL 3) describes a humidified gas supply method for mixing a saturated moist gas supplied from a humidifying passage having a humidifier and a dry gas supplied from a dry gas passage to produce the humidified gas of predetermined flow rate and predetermined moisture amount, and supplying the same to a humidified gas use destination from the humidified gas supply passage, the pressure and temperature of the saturated moist gas are measured, and a flow rate of the saturated moist gas and a flow rate of the dry gas are respectively set on the basis of the moisture amount of the saturated moist gas and the moisture amount and flow rate of the humidified gas calculated on the basis of the measured pressure and temperature.
    WO 2014/132638 A1 (PTL 4) describes a method for manufacturing hot dip galvanized steel sheets using a continuous hot dip galvanization device provided with a direct fire-type heating zone in which burners are disposed facing the surface of the steel sheet, wherein the dew point of the gas input in the burners is adjusted and hot dip galvanized steel sheets of excellent plating appearance can be obtained even with Si-containing steel.
  • CITATION LIST Patent Literature
  • SUMMARY (Technical Problem)
  • In production of a high tensile strength steel sheet, humidified gas is supplied to the soaking zone in addition to reducing or non-oxidizing dry gas, as described in PTL 1, in order to raise the dew point in the soaking zone. In contrast, in production of a normal strength steel sheet (hereinafter, referred to as a "normal steel sheet"), only reducing or non-oxidizing dry gas is supplied to the soaking zone and humidified gas is not supplied. Therefore, in a situation such as when a high tensile strength steel sheet and a normal steel sheet are to be produced consecutively, it is necessary to switch between use and non-use of humidified gas during operation.
  • We recognized that the problem set forth below occurs when switching between use and non-use of humidified gas during operation. Specifically, we realized that if gas in a humidifying system is simply stopped during non-use of humidified gas, water from a humidifying device may spread and condense, and excessively humidified gas may accumulate in pipes of the humidifying system. Consequently, condensation or excessively humidified gas in the pipes may be sprayed into the soaking zone upon switching from non-use of the humidifying system to use of the humidifying system, and this may cause problems such as damage to a hearth roll and pick-up in the soaking zone, and formation of a water drop pattern on the steel sheet. Moreover, this may cause non-coating to occur in subsequent hot-dip galvanizing and may lead to poorer coating appearance.
  • In light of the problems set forth above, it would be helpful to provide a method of producing hot-dip galvanized steel sheets that can inhibit roll pick-up in a soaking zone caused by condensation or the like in a humidified gas pipe and with which favorable coating appearance can be obtained.
  • (Solution to Problem)
  • In order to solve the problems set forth above, we conducted detailed studies in relation to means for preventing the formation of condensation and the accumulation of excessively humidified gas in humidified gas pipes during non-use of humidified gas (i.e., while supply of humidified gas to a soaking zone is stopped). We discovered that the above objective can be achieved through the inventive method according to claim 1. Preferred embodiments of the inventive method are defined in the dependent claims 2-4.
  • (Advantageous Effect)
  • Through the disclosed method of producing hot-dip galvanized steel sheets, it is possible to inhibit roll pick-up in a soaking zone caused by condensation or the like in a humidified gas pipe and obtain favorable coating appearance.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • In the accompanying drawings:
    • FIG. 1 is a schematic view illustrating a configuration of a continuous hot-dip galvanizing apparatus 100 used in an embodiment of the present invention;
    • FIG. 2 is a schematic view illustrating a supply system for supplying mixed gas and dry gas to a soaking zone 12 in FIG. 1; and
    • FIG. 3 is an enlarged schematic view illustrating a humidifying device 50 and a draining device 80 in FIG. 2.
    DETAILED DESCRIPTION
  • A configuration of a continuous hot-dip galvanizing apparatus 100 used in an embodiment is described with reference to FIG. 1. The continuous hot-dip galvanizing apparatus 100 includes an annealing furnace 20 in which a heating zone 10, a soaking zone 12, and cooling zones 14 and 16 are arranged in this order, a hot-dip galvanizing bath 22 adjacent to the cooling zone 16 that serves as a hot-dip galvanizing line, and an alloying line 24 adjacent to the hot-dip galvanizing bath 22. The heating zone 10 in this embodiment includes a first heating zone 10A (upstream heating zone) and a second heating zone 10B (downstream heating zone). The cooling zone includes a first cooling zone 14 (rapid cooling zone) and a second cooling zone 16 (slow cooling zone). A snout 18 connected to the second cooling zone 16 has its tip immersed in the hot-dip galvanizing bath 22, thus connecting the annealing furnace 20 and the hot-dip galvanizing bath 22.
  • A steel strip P is introduced into the first heating zone 10A from a steel strip introduction port in a lower part of the first heating zone 10A. One or more hearth rolls are arranged in upper and lower parts of each of the zones 10, 12, 14, and 16. In the case where the steel strip P is folded back by 180 degrees at one or more hearth rolls, the steel strip P is conveyed vertically a plurality of times inside a corresponding zone of the annealing furnace 20, forming a plurality of passes. While FIG. 1 illustrates an example of having 10 passes in the soaking zone 12, 2 passes in the first cooling zone 14, and 2 passes in the second cooling zone 16, the numbers of passes are not limited to those in this example, and may be set as appropriate depending on the processing conditions. At some hearth rolls, the steel strip P is not folded back but changed in direction at a right angle to move to the next zone. The steel strip P is thus annealed in the annealing furnace 20 by being conveyed through the heating zone 10, the soaking zone 12, and the cooling zones 14 and 16 in this order.
  • Adjacent zones in the annealing furnace 20 communicate through a communication portion connecting the upper parts or lower parts of the respective zones. In this embodiment, the first heating zone 10A and the second heating zone 10B communicate through a throat (restriction portion) connecting the upper parts of the respective zones. The second heating zone 10B and the soaking zone 12 communicate through a throat connecting the lower parts of the respective zones. The soaking zone 12 and the first cooling zone 14 communicate through a throat connecting the lower parts of the respective zones. The first cooling zone 14 and the second cooling zone 16 communicate through a throat connecting the lower parts of the respective zones. Although the height of each throat may be set as appropriate, it is preferable that the height of each throat is as low as possible to enhance the independence of the atmosphere in each zone. Gas in the annealing furnace 20 flows from downstream to upstream and is discharged from the steel strip introduction port in the lower part of the first heating zone 10A.
  • (Heating zone)
  • In this embodiment, the second heating zone 10B is a direct fired furnace (DFF). The DFF may be a commonly known DFF. Burners are distributed in the inner wall of the direct fired furnace in the second heating zone 10B so as to face the steel strip P (note that these burners are not illustrated in FIG. 1). It is preferable that the burners are divided into groups, and that the combustion rate and the air ratio in each group are independently controllable. Combustion exhaust gas in the second heating zone 10B is supplied into the first heating zone 10A, and the steel strip P is preheated by the heat of the gas.
  • The combustion rate is a value obtained by dividing the amount of fuel gas actually introduced into a burner by the amount of fuel gas of the burner under its maximum combustion load. The combustion rate at the time of combustion by the burner under its maximum combustion load is 100 %. When the combustion load is low, the burner cannot maintain a stable combustion state. Accordingly, the combustion rate is preferably adjusted to 30 % or more.
  • The air ratio is a value obtained by dividing the amount of air actually introduced into a burner by the amount of air necessary for complete combustion of fuel gas. In this embodiment, the heating burners in the second heating zone 10B are divided into four groups (#1 to #4), and the three groups (#1 to #3) upstream in the steel sheet traveling direction are made up of oxidizing burners, and the last group (#4) is made up of reducing burners. The air ratio of the oxidizing burners and the air ratio of the reducing burners are independently controllable. The air ratio of the oxidizing burners is preferably adjusted to 0.95 or more and 1.5 or less. The air ratio of the reducing burners is preferably adjusted to 0.5 or more and less than 0.95. The temperature in the second heating zone 10B is preferably adjusted to 800 °C to 1200 °C.
  • (Soaking zone)
  • In this embodiment, the soaking zone 12 is capable of indirectly heating the steel strip P using a radiant tube (RT) (not illustrated) as heating means. The average temperature Tr (°C) in the soaking zone 12 is measured by inserting a thermocouple into the soaking zone 12 and is preferably adjusted to 700 °C to 900 °C.
  • Reducing gas or non-oxidizing gas is supplied to the soaking zone 12. H2/N2 mixed gas is typically used as the reducing gas. An example is gas (dew point: about -60 °C) having a composition containing 1 vol% to 20 vol% H2 with the balance being N2 and incidental impurities. An example of the non-oxidizing gas is gas (dew point: about -60 °C) having a composition containing N2 and incidental impurities.
  • In this embodiment, the reducing gas or non-oxidizing gas supplied to the soaking zone 12 is in two forms: mixed gas and dry gas. Herein, "dry gas" refers to reducing gas or non-oxidizing gas that has a dew point of about -60 °C to -50 °C and that is not humidified by a humidifying device. On the other hand, "mixed gas" refers to gas obtained through mixing of gas that is humidified by the humidifying device and gas that is not humidified by the humidifying device in a specific mixing ratio such as to have a dew point of -20 °C to 10 °C.
  • A supply system for supplying mixed gas and dry gas to the soaking zone 12 is described with reference to FIG. 2. The supply system includes, from upstream, a first pipe 31, a second pipe 32, a third pipe 33, a fourth pipe 34, a fifth pipe 35, and a sixth pipe 36, and also includes a gas distribution device 40, a humidifying device 50, a gas mixing device 60, and a draining device 80.
  • Dry gas that is supplied from a gas supply source (not illustrated) passes through the first pipe 31.
  • The gas distribution device 40 is connected to the first pipe 31 and distributes dry gas that has passed through the first pipe 31 in a freely variable ratio to the following three systems: the second pipe 32, the third pipe 33, and the fourth pipe 34. The second pipe 32, the third pipe 33, and the fourth pipe 34 branch from the gas distribution device 40 and dry gas that has been distributed by the gas distribution device 40 passes therethrough. Specifically, one portion of dry gas that has passed through the first pipe 31 is supplied to the humidifying device 50 through the second pipe 32, another portion of this dry gas is supplied to the gas mixing device 60 through the third pipe 33, and the remaining portion of this dry gas is supplied straight to the soaking zone 12 through the fourth pipe 34. The gas distribution device 40 cuts off distribution to the second pipe 32 and the third pipe 33 during non-use of mixed gas described further below.
  • First, supply of dry gas is described. Dry gas that has passed through the fourth pipe 34 is supplied into the soaking zone 12 via dry gas supply ports 72A, 72B, 72C, and 72D that are disposed in the soaking zone 12. The position and number of dry gas supply ports is not specifically limited and may be set as appropriate in consideration of various conditions. However, it is preferable that a plurality of dry gas supply ports is arranged at the same height position and that dry gas supply ports are arranged uniformly in the steel strip traveling direction.
  • Next, supply of mixed gas is described. The humidifying device 50 is connected to the second pipe 32 and dry gas that has passed through the second pipe 32 is introduced therein. The fifth pipe 35 extends from the humidifying device 50 and humidified gas that has been humidified by the humidifying device 50 passes therethrough.
  • The gas mixing device 60 is connected to the third pipe 33 and the fifth pipe 35, and prepares mixed gas having a desired dew point by mixing dry gas that has passed through the third pipe and humidified gas that has passed through the fifth pipe in a given ratio that can be varied. The sixth pipe 36 is a mixed gas pipe that extends from the gas mixing device 60, and mixed gas discharged from the gas mixing device 60 passes therethrough. Mixed gas that has passed through the sixth pipe 36 is supplied into the soaking zone 12 via one or more mixed gas supply ports that are disposed in the soaking zone 12. In this embodiment, mixed gas is supplied by two systems: a system of mixed gas supply ports 70A, 70B, and 70C and a system of mixed gas supply ports 71A, 71B, and 71C. The position and number of mixed gas supply ports is not specifically limited and may be set as appropriate in consideration of various conditions. It is preferable that, as in this embodiment, a plurality of mixed gas supply ports is arranged at each of two or more different height positions and that mixed gas supply ports are arranged uniformly in the steel strip traveling direction. The dew point of the mixed gas can be measured by a mixed gas dew point meter 74 disposed in the sixth pipe.
  • Next, configurations of the humidifying device 50 and the draining device 80, which is a disclosed feature, are described with reference to FIG. 3. The humidifying device 50 includes a tube-shaped module 52 and a circulating constant-temperature water bath 54. Vapor permeable membranes 51 are disposed in the module 52. The vapor permeable membranes 51 in this embodiment are fluorine or polyimide hollow fiber membranes. Although only two vapor permeable membranes 51 are illustrated in FIG. 3, about 50 to 500 membranes are arranged substantially in parallel. In the module 52, the dry gas that has passed through the second pipe 32 flows through the inside 53A of the vapor permeable membranes, whereas pure water adjusted to a specific temperature in the circulating constant-temperature water bath 54 circulates at the outside 53B of the vapor permeable membranes. Specifically, the outside 53B of the vapor permeable membranes in the module is in communication with the circulating constant-temperature water bath 54 via passages 55A and 55B.
  • The fluorine or polyimide hollow fiber membranes are each a type of ion exchange membrane with affinity for water molecules. When moisture concentration differs between the inside and outside of the hollow fiber membrane, a force for equalizing the moisture concentration difference arises and, with this force as a driving force, moisture permeates through the membrane to move to the side with lower moisture concentration. Accordingly, dry gas is humidified to obtain humidified gas when the dry gas passes through the inside 53A of the vapor permeable membranes in the module 52. The temperature of dry gas varies with seasonal or daily air temperature change. In this embodiment, however, heat exchange is possible by ensuring a sufficient contact area between gas and water through the vapor permeable membranes 51. Accordingly, regardless of whether the dry gas temperature is higher or lower than the circulating water temperature, the dry gas is humidified to the same dew point as the set water temperature, thus achieving highly accurate dew point control. The dew point of the humidified gas can be controlled to any value in the range of 5 °C to 50 °C. When the dew point of the humidified gas is higher than the temperature of a pipe, there is a possibility that condensation occurs in the pipe and that condensation enters directly into the furnace. A humidified gas pipe is, therefore, heated/heat-retained to at least the dew point of the humidified gas and at least the external air temperature.
  • Note that the internal configuration of the module 52 is not limited to the configuration illustrated in FIG. 3. For example, the vapor permeable membranes may alternatively be fluorine or polyimide flat membranes. In such a configuration, the dry gas that has passed through the second pipe 32 is humidified by, while the dry gas passes through one space in the module that is separated by the vapor permeable membranes, circulating water through another space in the module using the circulating constant-temperature water bath 54.
  • A feature of the continuous hot-dip galvanizing apparatus 100 in this embodiment is that the continuous hot-dip galvanizing apparatus 100 includes the draining device 80 for draining water from the space at the outside 53B of the vapor permeable membranes in the module when mixed gas is not supplied to the soaking zone. FIG. 3 illustrates an example of the draining device 80. The draining device 80 includes a first isolation valve 82, a second passage 84, a second isolation valve 86, and a drainage tank 88. The first isolation valve 82 is disposed in the passage 55B through which water passes when moving toward the circulating constant-temperature water bath 54 from the outside 53B of the vapor permeable membranes in the module. The second passage 84 branches from the passage 55B at a section that is further upstream than the first isolation valve 82 (i.e., toward the outside 53B of the vapor permeable membranes). A tip of the second passage 84 is positioned above the drainage tank 88. The second isolation valve 86 is disposed in the second passage 84. The drainage tank 88 holds water that is drained from the second passage 84.
  • While humidified gas is being produced, the first isolation valve 82 is fully opened, the second isolation valve 86 is fully closed, and the circulating constant-temperature water bath 54 is used to circulate water at the outside 53B of the vapor permeable membranes in the module. While humidified gas is not being produced, water circulation is stopped, the second isolation valve 86 is fully opened, and the first isolation valve 82 is fully closed to drain water toward the drainage tank 88 from the space at the outside 53B of the vapor permeable membranes in the module. In a situation in which it is not possible to position the module 52 at least 200 mm higher than the top of the drainage tank 88, it is preferable that a suction device or the like is disposed at the drainage tank side in order to drain water in the humidifying device.
  • In production of a high tensile strength steel sheet, mixed gas containing humidified gas is supplied to the soaking zone 12 in addition to dry gas. Herein, this state is referred to as a "first operational state". In contrast, in production of a normal steel sheet, only dry gas is supplied to the soaking zone 12, and mixed gas is not supplied. Herein, this state is referred to as a "second operational state".
  • When humidified gas is not required in the second operational state, distribution of dry gas to the second pipe 32 and the humidifying device 50 can be stopped so that dry gas does not flow through the inside 53A of the vapor permeable membranes in the module. However, if water circulation using the circulating constant-temperature water bath 54 is allowed to continue over a long period, condensation occurs in pipes upstream and downstream of the module 52 (i.e., in the second pipe 32 and the fifth pipe 35), and further downstream in the sixth pipe 36. Even supposing that these pipes are heated/heat-retained, excessively humidified gas accumulates in the pipes since the inside of the pipes is in a constantly saturated state with moisture. Moreover, even supposing that water circulation is stopped, the same problems may arise if the space at the outside 53B of the vapor permeable membranes in the module is left in a water-filled state for a long period.
  • Therefore, switching between the first operational state and the second operational state is performed as follows. In the first operational state, water is circulated using the circulating constant-temperature water bath 54 and humidified gas is produced in a state in which the first isolation valve 82 is fully opened and the second isolation valve 86 is fully closed. In the second operational state, distribution of dry gas to the second pipe 32 is stopped and water circulation using the circulating constant-temperature water bath 54 is stopped, and subsequently water is drained from the space at the outside 53B of the vapor permeable membranes in the module using the draining device 80. Specifically, the second isolation valve 86 is fully opened and the first isolation valve 82 is fully closed. In other words, in the second operational state, a state in which water is not present in the space at the outside 53B of the vapor permeable membranes is obtained and water is not circulated using the circulating constant-temperature water bath 54. However, note that temperature adjustment of the circulating constant-temperature water bath 54 may be continued.
  • Switching in this manner can prevent condensation and accumulation of excessively humidified gas in pipes upstream and downstream of the module 52 (i.e., the second pipe 32 and the fifth pipe 35), and further downstream in the sixth pipe 36, while in the second operational state. Accordingly, condensation and excessively humidified gas do not enter the soaking zone 12 upon switching from the second operational state to the first operational state. This can inhibit the occurrence of roll pick-up in the soaking zone 12 and, as a result, enables favorable coating appearance to be obtained.
  • When switching from the second operational state to the first operational state (when switching from production of a normal steel sheet to production of a high tensile strength steel sheet), water circulation using the circulating constant-temperature water bath 54 is restarted and subsequently distribution of dry gas to the second pipe 32 is restarted.
  • The gas flow rate Qrd of dry gas supplied to the soaking zone 12 via the fourth pipe 34 in the first operational state and the second operational state is measured by a gas flowmeter (not illustrated) disposed in the fourth pipe 34. Although no specific limitations are placed on the gas flow rate Qrd, the gas flow rate Qrd is about 0 Nm3/hr to 600 Nm3/hr. This maintains the furnace pressure in the soaking zone 12 at an appropriate pressure (higher than the direct fired zone) but without the furnace pressure becoming excessively high.
  • The gas flow rate Qrw of mixed gas supplied to the soaking zone 12 via the sixth pipe 36 in the first operational state is measured by a gas flowmeter (not illustrated) disposed in the sixth pipe 36. Although no specific limitations are placed on the gas flow rate Qrw the gas flow rate Qrw is about 100 Nm3/hr to 500 Nm3/hr. This maintains the furnace pressure in the soaking zone 12 at an appropriate pressure (higher than the direct fired zone) but without the furnace pressure becoming excessively high.
  • It is preferable that the dew point in the soaking zone 12 is constantly controlled to -20 °C or higher and 0 °C or lower in the first operational state. Dew point meters are installed at at least one location (dew point measurement position 75A) near lower part hearth rolls 73B (lowest part of the soaking zone) and at least one location (dew point measurement position 75B) below upper part hearth rolls 73A at a higher position than half way up the soaking zone in a height direction (upper part of the soaking zone). Controlling the dew point in the soaking zone 12 to -20°C or higher enables an appropriate alloying temperature in subsequent alloying treatment and enables desired mechanical properties to be obtained. On the other hand, since the steel substrate of the steel strip starts oxidizing when the dew point in the soaking zone 12 is +10 °C or higher, the upper limit of the dew point is preferably 0 °C in terms of uniformity of the dew point distribution in the soaking zone 12 and minimization of the dew point variation range.
  • Mixed gas having a freely selected dew point can be supplied into the soaking zone 12 by adjusting the mixing proportions of gases in the gas mixing device 30. Mixed gas having a high dew point may be supplied to the soaking zone 1 2 if the dew point in the soaking zone 12 is about to fall below the target range. Conversely, mixed gas having a low dew point may be supplied to the soaking zone 12 if the dew point in the soaking zone 12 is about to rise above the target range. In this manner, the dew point in the soaking zone 12 can be constantly controlled to -20 °C or higher and 0 °C or lower in the first operational state.
  • (Cooling zone)
  • In this embodiment, the cooling zones 14 and 16 cool the steel strip P. The steel strip P is cooled to about 480 °C to 530 °C in the first cooling zone 14, and cooled to about 470 °C to 500 °C in the second cooling zone 16.
  • The cooling zones 14 and 16 are also supplied with the aforementioned reducing gas or non-oxidizing gas, but in the case of the cooling zones 14 and 16, only dry gas is supplied. Although no specific limitations are placed on supply of dry gas to the cooling zones 14 and 16, it is preferable that the dry gas is supplied from supply ports at at least two locations in a height direction and at least two locations in a longitudinal direction to enable uniform supply into the cooling zone. The total gas flow rate Qcd of dry gas supplied to the cooling zones 14 and 16 is measured by one or more gas flowmeters (not illustrated) disposed in pipes. Although no specific limitations are placed on the total gas flow rate Qcd, the total gas flow rate Qcd is about 200 Nm3/hr to 1,000 Nm3/hr. This maintains the furnace pressure in the soaking zone 12 at an appropriate pressure (higher than the direct fired zone) but without the furnace pressure becoming excessively high.
  • (Hot-dip galvanizing bath)
  • The hot-dip galvanizing bath 22 can be used to apply a hot-dip galvanized coating onto the steel strip P exiting from the second cooling zone 16. The hot-dip galvanizing may be performed according to a usual method.
  • (Alloying line)
  • The alloying line 24 can be used to heat-alloy the galvanized coating applied onto the steel strip P. The alloying treatment may be performed according to a usual method. In this embodiment, the alloying temperature is kept from being high, thus preventing a decrease in tensile strength of the produced galvannealed steel sheet. However, the alloying line 24 and the alloying treatment performed thereby are not essential to the disclosed techniques because the effects of inhibiting roll pick-up in the soaking zone caused by condensation or the like in a humidified gas pipe and obtaining favorable coating appearance can be achieved even when the alloying treatment is omitted.
  • EXAMPLES (Experimental conditions)
  • The continuous hot-dip galvanizing apparatus illustrated in FIGS. 1 to 3 was used to anneal steel strips having chemical compositions shown in Table 1 under annealing conditions shown in Table 2, and then hot-dip galvanize and alloy the steel strips. Steel sample ID A is normal steel and steel sample ID B is high tensile strength steel. In the example and comparative example, annealing, hot-dip galvanizing, and alloying treatment were performed continuously with a sheet passing order shown in Table 2.
  • A DFF was used as the second heating zone. Heating burners were divided into four groups (#1 to #4) where the three groups (#1 to #3) upstream in the steel sheet traveling direction were made up of oxidizing burners and the last group (#4) was made up of reducing burners, and the air ratios of the oxidizing burners and reducing burners were set to the values shown in Table 2. The length of each group in the steel sheet conveyance direction was 4 m.
  • An RT furnace having a volume Vr of 700 m3 was used as the soaking zone. The average temperature Tr in the soaking zone was set to the value shown in Table 2. Gas (dew point: -50 °C) having a composition containing 15 vol% H2 with the balance being N2 and incidental impurities was used as dry gas. A portion of the dry gas was humidified by a humidifying device having 10 hollow fiber membrane-type humidifying modules to prepare mixed gas. In each of the modules, the maximum dry gas flow rate was 500 L/min and the maximum water circulation rate was 10 L/min. A circulating constant-temperature water bath capable of supplying a total of 100 L/min of pure water was used as a common water bath for each of the modules. Dry gas supply ports and mixed gas supply ports were arranged at the positions illustrated in FIG. 2. The draining device illustrated in FIG. 3 was also set-up.
  • In the example and comparative example, gas was supplied to the soaking zone by adopting the second operational state during passing of a sheet with steel sample ID A and adopting the first operational state during passing of a sheet with steel sample ID B. The dry gas flow rate Qrd, mixed gas flow rate Qrw, and mixed gas dew point shown in Table 2 are each a stable value during passing of a corresponding sheet.
  • In the comparative example, supply of dry gas to the second pipe was stopped during passing of a sheet with steel sample ID A in the second operational state, but water circulation using the circulating constant-temperature water bath was continued. In contrast, during passing of a sheet with steel sample ID A in the second operational state in the example, distribution of dry gas to the second pipe was stopped and water circulation using the circulating constant-temperature water bath was stopped, and subsequently water was drained from space at the outside of vapor permeable membranes in the modules using the draining device.
  • The dry gas (dew point: -50 °C) was supplied to the first and second cooling zones at the lowest part of each of the zones with the flow rate shown in Table 2.
  • The temperature of the molten bath was set to 460 °C, the Al concentration in the molten bath was set to 0.130 %, and the coating weight was adjusted to 45 g/m2 per surface by gas wiping. The line speed was set to 80 mpm to 100 mpm. After the hot-dip galvanizing, alloying treatment was performed in an induction heating-type alloying furnace so that the coating alloying degree (Fe content) was 10 % to 13 %. The alloying temperature in the treatment was as shown in Table 2.
  • (Evaluation method)
  • Evaluation of the coating appearance was conducted through inspection by an optical surface defect meter (detection of non-coating defects or overoxidation defects of φ0.5 or more) and visual determination of alloying unevenness. Samples passing all criteria were rated "excellent", samples having a low degree of alloying unevenness were rated "good", and samples failing at least one of the criteria were rated "poor". The results are shown in Table 2.
  • In addition, the tensile strength of a galvannealed steel sheet produced under each set of conditions was measured. Normal steel with steel sample ID A was evaluated to pass when the tensile strength was 270 MPa or more, and high tensile strength steel with steel sample ID B was evaluated to pass when the tensile strength was 980 MPa or more. The results are shown in Table 2.
  • (Evaluation results)
  • In Comparative Example No. 1, mixed gas was supplied to raise the dew point of the soaking zone during passing of a sheet with steel sample ID B, and thus it was not necessary to excessively raise the alloying temperature and there was no problem in terms of tensile strength. However, moisture that had condensed in pipes was supplied into the soaking zone when supply of humidified gas was started for passing of the second sheet. This caused localized elevation of the dew point near the hearth rolls, leading to the occurrence of roll pick-up, and scratches due to this roll pick-up were formed in the steel strip surface. This resulted in poorer coating appearance for the second passed sheet through to the fourth passed sheet. In contrast, it was possible to perform switching of humidified gas without formation of condensation in pipes in Example No. 2. As a result, all the evaluation criteria were passed.
  • [Table 1]
  • Table I
    (Mass%)
    Steel sample ID C Si Mn P S Nb Ti
    A 0.001 0.01 0.15 0.01 0.005 0.005 0.03
    B 0.11 1.5 2.7 0.01 0.001 0.001 0.001
  • [Table 2]
  • Table 2
    No. Sheet passing order Steel sample ID Healting zone (DFF) Soaking zone (RTF) Cooling zone Aloying treatment Coating appearance Tensile Strength (MPa) Classification
    Oxylcing burner ratio Reducing burner in ratio Discharge side teraperature (°C) Upper part dew port (°C) Lowest part dew port (°C) Average temperature Tr (°C) Dry gas flow rate Qrd (Nm3/hr) Mixed gas flow rate Qrw (Nm3/hr) Mixed gas dew port (°C) Water circulation in humudifying device Gas flow rate Qcd (Nm3 /hr) Alloying temperature (°C)
    1 1 A 0 95 085 680 -29,3 -39 8 800 452 0 - Yes 480 500 Excellent 308 Comparative example
    2 B 1.15 0.85 721 1.2 -9.2 830 280 170 5.0 Yes 472 508 Poor 1080
    3 B 1.15 0.85 723 -1.11 -18.5 831 282 170 5.0 Yes 475 520 Poor 1030
    4 A 095 0.85 680 -27.4 -34.3 800 455 0 - Yes 462 501 Poor 310
    2 1 A 095 0.85 680 -32.5 -38.2 801 470 0 - No 470 512 Excellent 305 Example
    2 B 1.15 0.85 721 -12.3 -16.2 830 272 200 5.0 Yes 472 513 Excellent 10.45
    3 B 1.15 0.85 723 -13.5 -18.4 849 305 170 5.0 Yes 468 510 Excellent 1052
    4 A 095 0.85 680 -27.2 -35.9 810 460 0 - No 470 503 Excellent 301
    5 B 1.15 0.85 725 -11.3 -16.1 852 241 250 5.0 Yes 467 509 Excellent 1030
    6 A 0.95 0.85 680 -28.2 -365 811 465 0 - No 480 500 Excellent 303
  • INDUSTRIAL APPLICABILITY
  • Through the disclosed method of producing hot-dip galvanized steel sheets, it is possible to inhibit roll pick-up in a soaking zone caused by condensation or the like in a humidified gas pipe and obtain favorable coating appearance.
  • REFERENCE SIGNS LIST
  • 100
    continuous hot-dip galvanizing apparatus
    10
    heating zone
    10A
    first heating zone (upstream)
    10B
    second heating zone (downstream, direct fired furnace)
    12
    soaking zone
    14
    first cooling zone (rapid cooling zone)
    16
    second cooling zone (slow cooling zone)
    18
    snout
    20
    annealing furnace
    22
    hot-dip galvanizing bath
    24
    alloying line
    31
    first pipe
    32
    second pipe
    33
    third pipe
    34
    fourth pipe
    35
    fifth pipe
    36
    sixth pipe
    40
    gas distribution device
    50
    humidifying device
    51
    vapor permeable membrane
    52
    module
    53A
    inside of vapor permeable membrane (one space)
    53B
    outside of vapor permeable membrane (other space)
    54
    circulating constant-temperature water bath
    55A, 55B
    passage
    60
    gas mixing device
    70A, 70B, 70C
    mixed gas supply port
    71A, 71B, 71C
    mixed gas supply port
    72A, 72B, 72C, 72D
    dry gas supply port
    73A
    upper part hearth roll
    73B
    lower part hearth roll
    74
    mixed gas dew point meter
    75A, 75B
    dew point measurement position
    80
    draining device
    82
    first isolation valve
    84
    second passage
    86
    second isolation valve
    88
    drainage tank
    P
    steel strip

Claims (4)

  1. A method of producing hot-dip galvanized steel sheets using a continuous hot-dip galvanizing apparatus (100) comprising:
    an annealing furnace (20) in which a heating zone (10), a soaking zone (12), and a cooling zone (14, 16) are arranged in this order;
    a hot-dip galvanizing line (22) adjacent to the cooling zone (14, 16);
    a first pipe (31) through which a reducing or non-oxidizing dry gas passes;
    a gas distribution device (40) that is connected to the first pipe (31) and that distributes dry gas that has passed through the first pipe (31);
    a second pipe (32), a third pipe (33), and a fourth pipe (34) that branch from the gas distribution device (40) and through which dry gas that has been distributed by the gas distribution device (40) passes;
    a humidifying device (50) that is connected to the second pipe (32) and into which dry gas that has passed through the second pipe (32) is introduced;
    a fifth pipe (35) that extends from the humidifying device (50) and through which humidified gas that has been humidified by the humidifying device (50) passes;
    a gas mixing device (60) that is connected to the third pipe (33) and the fifth pipe (35) and that prepares mixed gas by mixing dry gas that has passed through the third pipe (33) and humidified gas that has passed through the fifth pipe (35);
    a sixth pipe (36) that extends from the gas mixing device (60) and through which the mixed gas passes;
    a mixed gas supply port (70A, 70B, 70C, 71A, 71B, 71C) disposed in the soaking zone (12) for supplying mixed gas that has passed through the sixth pipe (36) into the soaking zone (12); and
    a dry gas supply port (72A,72B, 72C, 72D) disposed in the soaking zone (12) for supplying dry gas that has passed through the fourth pipe (34) into the soaking zone (12), wherein
    the humidifying device (50) includes a module (52) including a vapor permeable membrane (51), and is configured to humidify the dry gas that has passed through the second pipe (32) by, while the dry gas passes through a space (53A) in the module (52) that is separated by the vapor permeable membrane (51), circulating water through another space (53B) in the module (52) using a circulating constant-temperature water bath (54), and
    the continuous hot-dip galvanizing apparatus (100) further comprises a draining device (80) for draining water from the other space (53B) in the module (52) when the mixed gas is not supplied to the soaking zone (12),
    wherein the method comprises:
    annealing a steel strip (P) by conveying the steel strip (P) through the heating zone (10), the soaking zone (12), and the cooling zone (14, 16) inside of the annealing furnace (20), in this order; and
    applying a hot-dip galvanized coating onto the steel strip (P) exiting from the cooling zone (14, 16) using the hot-dip galvanizing line (22), wherein the method is carried out consecutively in
    a first operational state, in which a high tensile strength steel sheet is produced and in which the mixed gas and the dry gas are supplied to the soaking zone (12) and water circulation is performed using the circulating constant-temperature water bath (54), and
    a second operational state, in which a normal tensile strength steel sheet is produced and in which only the dry gas is supplied to the soaking zone (12) and the mixed gas is not supplied, distribution of the dry gas to the second pipe (32) is stopped, water is drained from the other space (53B) in the module (52) using the draining device (80), and water circulation with the circulating constant-temperature water bath (54) is not performed.
  2. The method of producing hot-dip galvanized steel sheets according to claim 1, characterized in that,
    when switching from the second operational state to the first operational state, water circulation using the circulating constant-temperature water bath (54) is restarted and subsequently distribution of the dry gas to the second pipe (32) is restarted.
  3. The method of producing hot-dip galvanized steel sheets according to claim 1 or 2, characterized in that
    a dew point in the soaking zone (12) is controlled to -20 °C or higher and 0 °C or lower in the first operational state.
  4. The method of producing hot-dip galvanized steel sheets according to any one of claims 1 to 3, characterized by
    heat-alloying the galvanized coating applied onto the steel strip (P) using an alloying line (24) adjacent to the hot-dip galvanizing line (22).
EP16767930.7A 2015-03-23 2016-02-19 Method of manufacturing a hot-dip galvanized steel sheet Active EP3276037B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2015060139A JP6008007B2 (en) 2015-03-23 2015-03-23 Continuous hot dip galvanizing apparatus and method for producing hot dip galvanized steel sheet
PCT/JP2016/000899 WO2016152018A1 (en) 2015-03-23 2016-02-19 Continuous hot-dip galvanization apparatus and hot-dip galvanized steel sheet manufacturing method

Publications (3)

Publication Number Publication Date
EP3276037A1 EP3276037A1 (en) 2018-01-31
EP3276037A4 EP3276037A4 (en) 2018-03-21
EP3276037B1 true EP3276037B1 (en) 2021-04-07

Family

ID=56978131

Family Applications (1)

Application Number Title Priority Date Filing Date
EP16767930.7A Active EP3276037B1 (en) 2015-03-23 2016-02-19 Method of manufacturing a hot-dip galvanized steel sheet

Country Status (6)

Country Link
EP (1) EP3276037B1 (en)
JP (1) JP6008007B2 (en)
KR (1) KR102026708B1 (en)
CN (1) CN107429374B (en)
MX (1) MX2017012192A (en)
WO (1) WO2016152018A1 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6439654B2 (en) * 2015-10-27 2018-12-19 Jfeスチール株式会社 Method for producing hot-dip galvanized steel sheet
KR102231412B1 (en) 2016-10-25 2021-03-23 제이에프이 스틸 가부시키가이샤 Manufacturing method of high-strength hot-dip galvanized steel sheet
EP3617339A4 (en) * 2017-04-27 2020-04-08 JFE Steel Corporation Method for producing galvannealed steel sheet, and continuous hot dip galvanizing apparatus
JP6822934B2 (en) * 2017-10-26 2021-01-27 株式会社神戸製鋼所 Manufacturing method of hot-dip galvanized steel sheet
CN109722516B (en) * 2019-02-01 2020-07-17 北京钢研新冶工程设计有限公司 Device and method for quickly regulating and controlling gas dew point in annealing furnace
CN111321364A (en) * 2020-03-31 2020-06-23 无锡聚永丰环保科技有限公司 High-efficient galvanizing rig of galvanized steel wire
CN112481484B (en) * 2020-11-10 2022-04-01 马鞍山钢铁股份有限公司 Dew point self-adaptive control method for hot-dip galvanized products with different alloy components
CN115287567A (en) * 2022-08-04 2022-11-04 江阴市华达机械科技有限公司 Stove nose humidification system

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000290762A (en) * 1999-04-07 2000-10-17 Kawasaki Steel Corp Production of hot dip metal coated steel sheet
JP4123690B2 (en) * 2000-06-20 2008-07-23 住友金属工業株式会社 Method for supplying atmospheric gas into continuous annealing furnace
JP5000116B2 (en) * 2005-09-29 2012-08-15 新日本製鐵株式会社 Soaking furnace operation method in steel strip continuous treatment equipment
KR101011897B1 (en) * 2005-10-14 2011-02-01 신닛뽄세이테쯔 카부시키카이샤 Method of continous annealing/hot-dipping of steel sheet containing silicon and apparatus for continuous annealing/hot-dipping
JP5108365B2 (en) * 2007-04-25 2012-12-26 大陽日酸株式会社 Humidified gas supply method and apparatus
JP5834775B2 (en) * 2011-10-31 2015-12-24 Jfeスチール株式会社 Manufacturing equipment and manufacturing method for continuous hot-dip galvanized steel sheet
CN102776460B (en) * 2012-03-19 2013-12-04 江苏大力神科技股份有限公司 Production method of thin steel strip hot galvanizing
KR101564870B1 (en) * 2012-04-09 2015-10-30 제이에프이 스틸 가부시키가이샤 Method for reducing dew point of atmosphere gas in annealing furnace, apparatus for the same and method for producing cold-rolled and annealed steel sheet
EP2927342A4 (en) * 2012-12-04 2016-01-06 Jfe Steel Corp Facility and method for manufacturing continuous hot-dip zinc-coated steel sheet
JP5915569B2 (en) * 2013-03-01 2016-05-11 Jfeスチール株式会社 Method for producing hot dip galvanized steel sheet and continuous hot dip galvanizing apparatus

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
None *

Also Published As

Publication number Publication date
WO2016152018A1 (en) 2016-09-29
KR20170117522A (en) 2017-10-23
EP3276037A1 (en) 2018-01-31
MX2017012192A (en) 2017-12-15
JP6008007B2 (en) 2016-10-19
CN107429374B (en) 2020-01-14
KR102026708B1 (en) 2019-09-30
EP3276037A4 (en) 2018-03-21
CN107429374A (en) 2017-12-01
JP2016180137A (en) 2016-10-13

Similar Documents

Publication Publication Date Title
EP3276037B1 (en) Method of manufacturing a hot-dip galvanized steel sheet
CN110612359B (en) Method for producing hot-dip galvanized steel sheet
EP3243924B1 (en) Method of producing galvannealed steel sheet
US10752975B2 (en) Method of producing galvannealed steel sheet
US11649520B2 (en) Continuous hot dip galvanizing apparatus
US20230323501A1 (en) Continuous hot-dip galvanizing apparatus
CN108138297B (en) Method for producing hot-dip galvanized steel sheet
JP6269547B2 (en) Continuous hot dip galvanizing apparatus and method for producing hot dip galvanized steel sheet
CN117616146A (en) Method for producing hot dip galvanized steel sheet

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20171017

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

A4 Supplementary search report drawn up and despatched

Effective date: 20180220

RIC1 Information provided on ipc code assigned before grant

Ipc: C21D 9/56 20060101ALI20180212BHEP

Ipc: C21D 1/76 20060101ALI20180212BHEP

Ipc: C22C 18/04 20060101ALI20180212BHEP

Ipc: C23C 2/40 20060101ALI20180212BHEP

Ipc: C22C 38/00 20060101ALI20180212BHEP

Ipc: C23C 2/28 20060101ALI20180212BHEP

Ipc: C21D 9/46 20060101ALI20180212BHEP

Ipc: C22C 38/14 20060101ALI20180212BHEP

Ipc: C23C 2/02 20060101AFI20180212BHEP

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20181204

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20200515

GRAJ Information related to disapproval of communication of intention to grant by the applicant or resumption of examination proceedings by the epo deleted

Free format text: ORIGINAL CODE: EPIDOSDIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

INTC Intention to grant announced (deleted)
GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20201016

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 1379782

Country of ref document: AT

Kind code of ref document: T

Effective date: 20210415

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602016055696

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20210407

Ref country code: AT

Ref legal event code: MK05

Ref document number: 1379782

Country of ref document: AT

Kind code of ref document: T

Effective date: 20210407

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210707

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210809

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210707

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210708

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210807

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602016055696

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20211230

Year of fee payment: 7

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20220110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210807

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20210407

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20220228

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220219

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220228

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220219

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220228

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220228

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20230110

Year of fee payment: 8

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20221229

Year of fee payment: 8

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20230219

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230219

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230219

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20160219