EP2811119A1 - Method for testing an overspeed protection system of a combined cycle plant with single shaft system - Google Patents

Method for testing an overspeed protection system of a combined cycle plant with single shaft system Download PDF

Info

Publication number
EP2811119A1
EP2811119A1 EP13170738.2A EP13170738A EP2811119A1 EP 2811119 A1 EP2811119 A1 EP 2811119A1 EP 13170738 A EP13170738 A EP 13170738A EP 2811119 A1 EP2811119 A1 EP 2811119A1
Authority
EP
European Patent Office
Prior art keywords
overspeed protection
steam turbine
gas turbine
test
speed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP13170738.2A
Other languages
German (de)
French (fr)
Inventor
Martin Bennauer
Edwin Gobrecht
Martin Hallekamp
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens AG
Original Assignee
Siemens AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens AG filed Critical Siemens AG
Priority to EP13170738.2A priority Critical patent/EP2811119A1/en
Priority to CN201480032268.1A priority patent/CN105264182B/en
Priority to JP2016517228A priority patent/JP6185162B2/en
Priority to PL14728486T priority patent/PL2984301T3/en
Priority to KR1020157037052A priority patent/KR101846639B1/en
Priority to PCT/EP2014/060773 priority patent/WO2014195163A1/en
Priority to EP14728486.3A priority patent/EP2984301B1/en
Priority to RU2015155901A priority patent/RU2629244C2/en
Priority to US14/895,071 priority patent/US9976440B2/en
Publication of EP2811119A1 publication Critical patent/EP2811119A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01DNON-POSITIVE DISPLACEMENT MACHINES OR ENGINES, e.g. STEAM TURBINES
    • F01D21/00Shutting-down of machines or engines, e.g. in emergency; Regulating, controlling, or safety means not otherwise provided for
    • F01D21/003Arrangements for testing or measuring
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01DNON-POSITIVE DISPLACEMENT MACHINES OR ENGINES, e.g. STEAM TURBINES
    • F01D21/00Shutting-down of machines or engines, e.g. in emergency; Regulating, controlling, or safety means not otherwise provided for
    • F01D21/20Checking operation of shut-down devices
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05DINDEXING SCHEME FOR ASPECTS RELATING TO NON-POSITIVE-DISPLACEMENT MACHINES OR ENGINES, GAS-TURBINES OR JET-PROPULSION PLANTS
    • F05D2220/00Application
    • F05D2220/30Application in turbines
    • F05D2220/31Application in turbines in steam turbines
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05DINDEXING SCHEME FOR ASPECTS RELATING TO NON-POSITIVE-DISPLACEMENT MACHINES OR ENGINES, GAS-TURBINES OR JET-PROPULSION PLANTS
    • F05D2220/00Application
    • F05D2220/30Application in turbines
    • F05D2220/32Application in turbines in gas turbines

Definitions

  • the invention relates to a method for testing an overspeed protection of a combined cycle single-shaft plant, wherein during a test operation, the gas turbine and steam turbine are operated at a test speed, the generator is operated with a connected load and during the test operation, a load shedding takes place.
  • the speeds are determined and monitored.
  • the speed of a combined cycle power plant is at a constant frequency of 50 Hz or 60 Hz. It may happen that this speed is exceeded, which can be referred to as overspeed. If this overspeed exceeds a critical value, a protective mechanism should be provided by taking action and preventing any further increase in speed. In general, this will be done switching off the steam supply to the steam turbine and switching off the fuel supply to the gas turbine. In this case, a trip of the steam turbine to the gas turbine will thus take place.
  • the object of the invention is to provide a method for testing a GuD single-shaft system, wherein the overspeed protection test of operating speeds from feasible.
  • This object is achieved by a method for testing an overspeed protection of a combined cycle gas turbine plant, wherein during a test operation, the gas turbine and steam turbine are operated at a test speed, wherein the generator is operated with a connected load, wherein during the test operation, a load shedding takes place The speed of the steam turbine increases and a DT overspeed protection is triggered when a DT tripping limit value is reached.
  • An essential idea of the invention is therefore that the steam and gas turbine is driven to a test speed corresponding to the operating speed of 50 Hz or 60 Hz, an electric generator, wherein an electric load is arranged on the electric generator.
  • This electrical load leads to an increased torque on the rotors of the gas and steam turbine.
  • a load shedding i. the electric load is abruptly switched off, the counteracting of the torque changes at the gas and steam turbine rotors, with the result that the speed increases more or less abruptly, since the control of the steam supply and fuel supply to the gas turbine as a result of the inertia of the system does not comply.
  • the steam turbine initially reaches the DT triggering limit value, the DT overspeed protection being triggered, and subsequently the gas turbine reaches a GT limit value, the GT overspeed protection being triggered after reaching the GT limit value.
  • two triggering conditions must be achieved in succession in order first to trigger the overspeed protection of the steam turbine and then of the gas turbine.
  • the DT trip limit must be reached and then the GT limit.
  • the steam turbine is in test operation in a fully warmed condition. This means that the operating parameters of the steam turbine in the test mode are ideally achieved and no temporary effects are to be considered in the sharp operation.
  • the gas turbine is operated in test mode with lower power.
  • the gas turbine is operated in test mode with a constant exhaust gas temperature.
  • a time t tripping elapses between the triggering of the DT overspeed protection and the load shedding, and the triggering ⁇ t max applies, with a steam turbine trip taking place, if t triggering is > t max and triggering of the DT Overspeed protection has not yet occurred.
  • the FIG. 1 shows a GuD single-shaft system 1.
  • This GuD single-shaft system 1 comprises a steam turbine 2, a gas turbine 3 and an electric generator 4, which are connected to each other via a common shaft 5 to transmit torque.
  • a clutch 6 is arranged, with which the torque transmission can be interrupted.
  • an electrical load 9 or an electrical load 9 is connected via a switch 8.
  • the switch 8 is shown in the closed state.
  • the FIG. 2 shows a speed curve of the gas turbine (n GT ) and the steam turbine (n DT ).
  • speed curves show the speed curve of the gas turbine 3 and the steam turbine 2 with the clutch closed 6.
  • the gas turbine 3 and steam turbine 2 is operated at a constant speed of 3000 revolutions per minute.
  • the time t t load shedding the electrical load 9 is disconnected from the generator 4 via the switch 8.
  • the result is that the speed of the gas turbine (n GT ) and the steam turbine (n DT ) goes high for a short time and if a tripping limit has been reached, a trip of the steam turbine 2 3 takes place, resulting in a sharp decrease in the speed, as in FIG. 2 recognizable leads.
  • the sharp overspeed protection must be carried out with a, compared to normal operation, unaltered trip limit value of the overspeed protection.
  • the gas turbine Defines 3 and steam turbine 2 to the trigger limit of the associated overspeed protection defined.
  • the overspeed protection must ab juryn when exceeding the tripping limits, the corresponding actuators of gas turbine 3 and steam turbine 2 and thus prevent critical overspeed.
  • the sharp overspeed protection test is not a real safety requirement for functional safety, as the controllers approach the appropriate trip limits with a defined dynamic range and do not reach a critical overspeed.
  • both the gas turbine 3 and the steam turbine 2 are each equipped with a separate overspeed protection. Due to the mechanical coupling 6 between the gas turbine 3 and the steam turbine 2 in single-shaft systems, the speed of the steam turbine 2 can not be higher than the speed of the gas turbine 3. Furthermore, the gas turbine 3 must provide a sufficient boiler output for the sharp overspeed test of the steam turbine 2. Thus, the over-speed test of the steam turbine 2 can not be performed independently of the gas turbine 3.
  • the method for testing the overspeed protection of the CCGT 1 takes place as follows: during a test operation, the gas turbine 3 and the steam turbine 2 are operated at a test speed equal to the operating speed of 3000 revolutions per minute.
  • the generator 4 is operated with a connected load 9, wherein during the test operation at the time t load shedding takes place, whereby the speed of the steam turbine 2 and the gas turbine 3 increases and upon reaching a DT tripping limit DT overspeed protection and upon reaching the GT Trip Limit GT over-speed protection is triggered. The result is that the speed of the steam turbine 2 and the gas turbine 3 is reduced.
  • the mass moment of inertia or the start-up time constant influences the dynamic behavior of gas turbine 3 and steam turbine 2 after load shedding.
  • the ratio of the start-up time constants has an influence on the selection of the trip limit value.
  • the triggering limit value of the steam turbine overspeed protection can be set just above the maximum mains frequency (eg 61.5 Hz) without reducing the system availability (eg at 104 %).
  • the distance between the maximum permissible mains frequency and the triggering limit value of the steam turbine overspeed protection is selected such that no undesired trip occurs during operation.
  • Another constraint is that the triggering limit of the steam turbine overspeed protection is not greater than the gas turbine overspeed protection trip limit.
  • the gas turbine overspeed protection trip limit must be set to a value above the maximum speed after a load dump and below the critical overspeed.
  • the choice of the tripping limit value must be such that the steam turbine 2 reaches the tripping limit value before the gas turbine 3.
  • the control technology of the gas turbine 3 and steam turbines 2 of a CCGT 1 is extended so that a switch is installed, with which the sharp overspeed test is activated.
  • This function is automatically deactivated after a maximum period of time to be set in order to protect the steam turbine 2 from contact with cold steam.
  • the maximum period must be selected according to the duration of the sharp overspeed test with the condition that the steam temperatures remain within the allowable range during the test.
  • the method is characterized as follows: depending on the switch, the load dump detection is first blocked in the gas turbine 3 and an automated, for example, a time-delayed opening of the switch 8 of the generator 4 is generated.
  • the switch In the steam turbine 2 is dependent the switch first the speed controller setpoint to a value just above the tripping limit value of the steam turbine overspeed protection, which may for example be 105%, set, the controller should approach the limit with a defined acceleration. The amount of acceleration affects the duration of the test. Thereafter, the limit frequency influence is deactivated, and then the influence of the gas turbine fire power on the steam turbine controller is suppressed. In this case, if necessary, the total quick-closing in the case of coupling failures must be regulated for the duration of the overspeed test, which is only necessary if the gas turbine 3 is tripped by the total quick-closing before the triggering limit value is reached.
  • the method for testing the overspeed protection of the CCGT 1 occurs as long as the steam turbine 2 is completely warmed up and is in operation for more than 5 hours.
  • the gas turbine 3 is operated with the lowest possible power and constant exhaust gas temperature, which is reflected by the IGV point. Pressing the switch in the control system activates the overspeed test. When the overspeed test is activated, the necessary switching operations will be automated, and the automated opening of the switch 8 will be delayed. Then, the gas turbine 3 and steam turbine 2 will drive the trip limit value in a defined manner.
  • the steam turbine 2 reaches its triggering limit first, with the gas turbine 3 shortly thereafter reaching its trip limit. This total process must not exceed a certain time to be set, since the steam then becomes inadmissibly cold. Therefore, the function of sharp over-speed tester is automatically deactivated automatically after a few seconds that can be adjusted, thereby generating a steam turbine trip.

Abstract

Die Erfindung betrifft ein Verfahren zum Testen eines Überdrehzahlschutzes einer GuD-Einwellenanlage (1), wobei während des Testbetriebs eine elektrische Last zunächst am Generator (4) angeschlossen ist und zu einem Testzeitpunkt ein Lastabwurf erfolgt und ein Auslösegrenzwert erreicht werden kann, wodurch der Überdrehzahlschutz ausgelöst wird.The invention relates to a method for testing an overspeed protection of a CCGT (1), wherein during the test operation, an electrical load is first connected to the generator (4) and at a test time a load shedding takes place and a trip limit can be achieved, whereby the overspeed protection triggered becomes.

Description

Die Erfindung betrifft ein Verfahren zum Testen eines Überdrehzahlschutzes einer GuD-Einwellenanlage, wobei während eines Testbetriebs die Gasturbine und Dampfturbine mit einer Test-Drehzahl betrieben werden, wobei der Generator mit einer angeschlossenen Last betrieben wird und während des Testbetriebs ein Lastabwurf erfolgt.The invention relates to a method for testing an overspeed protection of a combined cycle single-shaft plant, wherein during a test operation, the gas turbine and steam turbine are operated at a test speed, the generator is operated with a connected load and during the test operation, a load shedding takes place.

Zum sicheren Betrieb einer Gas- und Dampfturbinenanlage ist es erforderlich, dass die Drehzahlen ermittelt und überwacht werden. In der Regel liegt die Drehzahl eines Gas- und Dampfturbinenkraftwerks bei einer konstanten Frequenz von 50 Hz bzw. 60 Hz. Unter Umständen kann es vorkommen, dass diese Drehzahl überschritten wird, was als Überdrehzahl bezeichnet werden kann. Sofern diese Überdrehzahl einen kritischen Wert übersteigt, sollte ein Schutzmechanismus erfolgen, indem Maßnahmen ergriffen und ein weiteres Ansteigen der Drehzahl verhindert werden. In der Regel wird hierbei ein Abschalten der Dampfzufuhr zur Dampfturbine und ein Abschalten der Brennstoffzufuhr zur Gasturbine erfolgen. In diesem Fall wird somit ein Trip der Dampfturbine nach der Gasturbine erfolgen.For safe operation of a gas and steam turbine plant, it is necessary that the speeds are determined and monitored. In general, the speed of a combined cycle power plant is at a constant frequency of 50 Hz or 60 Hz. It may happen that this speed is exceeded, which can be referred to as overspeed. If this overspeed exceeds a critical value, a protective mechanism should be provided by taking action and preventing any further increase in speed. In general, this will be done switching off the steam supply to the steam turbine and switching off the fuel supply to the gas turbine. In this case, a trip of the steam turbine to the gas turbine will thus take place.

Bisher konnten die Testmechanismen für den Überdrehzahlschutz von Dampf- und Gasturbinenanlagen überprüft werden, indem der Auslösegrenzwert für den Überdrehzahlschutz auf eine gegenüber der Betriebsdrehzahl geringere Drehzahl gesetzt wird. Im Testbetrieb kann diese geringere Testdrehzahl überschritten werden und überprüft werden, ob der Überdrehzahlschutz funktioniert.So far, the over-speed protection mechanisms of steam and gas turbine plants have been tested by setting the overspeed trip trip limit to a lower speed than the operating speed. In test mode, this lower test speed can be exceeded and checked whether the overspeed protection works.

Wünschenswert wäre es allerdings, diesen Testbetrieb auch mit Original-Auslösegrenzwerten durchzuführen. Das bedeutet, dass die Prüfung des Überdrehzahlschutzes von den Betriebsdrehzahlen aus erfolgen soll. Dies ist ebenso wünschenswert unter dem Aspekt, dass in bestimmten Ländern ein Gesetz solch einen Überdrehzahlschutz vorschreibt, der mit Original-Auslösegrenzwerten erfolgen soll. Solch eine Prüfung kann bei Einwellenanlagen nur gemeinsam für Gas- und Dampfturbine unter Berücksichtigung der zulässigen Auslegungsparameter durchgeführt werden.However, it would be desirable to perform this test operation with original trip limits. That means checking the overspeed protection from the operating speeds should be made. This is also desirable in view of the fact that in certain countries a law requires such overspeed protection to be provided with original trip limit values. Such a test can only be carried out jointly for gas and steam turbines in single-shaft systems, taking into account the permissible design parameters.

Die Aufgabe der Erfindung liegt darin, ein Verfahren zum Testen einer GuD-Einwellenanlage anzugeben, wobei der Überdrehzahlschutztest von Betriebsdrehzahlen aus durchführbar ist.The object of the invention is to provide a method for testing a GuD single-shaft system, wherein the overspeed protection test of operating speeds from feasible.

Gelöst wird diese Aufgabe durch ein Verfahren zum Testen eines Überdrehzahlschutzes einer GuD-Einwellenanlage, wobei während eines Testbetriebs die Gasturbine und Dampfturbine mit einer Testdrehzahl betrieben werden, wobei der Generator mit einer angeschlossenen Last betrieben wird, wobei während des Testbetriebs ein Lastabwurf erfolgt, wobei die Drehzahl der Dampfturbine sich erhöht und bei Erreichen eines DT-Auslösegrenzwertes ein DT-Überdrehzahlschutz ausgelöst wird.This object is achieved by a method for testing an overspeed protection of a combined cycle gas turbine plant, wherein during a test operation, the gas turbine and steam turbine are operated at a test speed, wherein the generator is operated with a connected load, wherein during the test operation, a load shedding takes place The speed of the steam turbine increases and a DT overspeed protection is triggered when a DT tripping limit value is reached.

Ein wesentlicher Gedanke der Erfindung ist somit, dass die Dampf- und Gasturbine auf eine Test-Drehzahl, die der Betriebsdrehzahl von 50 Hz bzw. 60 Hz entspricht, ein elektrischer Generator angetrieben wird, wobei an den elektrischen Generator eine elektrische Last angeordnet ist. Diese elektrische Last führt zu einem erhöhten Drehmoment an den Rotoren der Gas- und Dampfturbine. Durch einen Lastabwurf, d.h. die elektrische Last wird schlagartig abgeschaltet, ändert sich das Entgegenwirken des Drehmoments an den Gas- und Dampfturbinenrotoren, was zur Folge hat, dass die Drehzahl sich mehr oder weniger schlagartig erhöht, da die Regelung der Dampfzufuhr und Brennstoffzufuhr zur Gasturbine in Folge der Trägheit des Systems nicht nachkommt.An essential idea of the invention is therefore that the steam and gas turbine is driven to a test speed corresponding to the operating speed of 50 Hz or 60 Hz, an electric generator, wherein an electric load is arranged on the electric generator. This electrical load leads to an increased torque on the rotors of the gas and steam turbine. By a load shedding, i. the electric load is abruptly switched off, the counteracting of the torque changes at the gas and steam turbine rotors, with the result that the speed increases more or less abruptly, since the control of the steam supply and fuel supply to the gas turbine as a result of the inertia of the system does not comply.

Durch den Lastabwurf erhöht sich somit die Drehzahl der Dampfturbine und zwingend der Gasturbine und soll bei Erreichen eines DT-Auslösegrenzwertes ein DT-Überdrehzahlschutz ausgelöst werden.Due to the load shedding thus increases the speed of the steam turbine and mandatory the gas turbine and should be on reaching of a DT tripping limit a DT overspeed protection is triggered.

Vorteilhafte Weiterbildungen sind in den Unteransprüchen angegeben.Advantageous developments are specified in the subclaims.

In einer ersten vorteilhaften Weiterbildung erreicht die Dampfturbine den DT-Auslösegrenzwert zunächst, wobei der DT-Überdrehzahlschutz ausgelöst wird und anschließend erreicht die Gasturbine einen GT-Grenzwert, wobei der GT-Überdrehzahlschutz nach Erreichen des GT-Grenzwertes ausgelöst wird. Somit werden in dieser vorteilhaften Weiterbildung zwei Auslösebedingungen nacheinander erreicht werden müssen, um zuerst den Überdrehzahlschutz der Dampfturbine und danach der Gasturbine auszulösen. Zunächst müsste der DT-Auslösegrenzwert erreicht werden und anschließend der GT-Grenzwert.In a first advantageous development, the steam turbine initially reaches the DT triggering limit value, the DT overspeed protection being triggered, and subsequently the gas turbine reaches a GT limit value, the GT overspeed protection being triggered after reaching the GT limit value. Thus, in this advantageous development, two triggering conditions must be achieved in succession in order first to trigger the overspeed protection of the steam turbine and then of the gas turbine. First, the DT trip limit must be reached and then the GT limit.

In einer weiteren vorteilhaften Weiterbildung befindet sich die Dampfturbine im Testbetrieb in einem vollständig durchgewärmten Zustand. Das bedeutet, dass die Betriebsparameter der Dampfturbine im Testbetrieb idealerweise erreicht werden und keine temporären Effekte im scharfen Betrieb zu berücksichtigen sind.In a further advantageous development, the steam turbine is in test operation in a fully warmed condition. This means that the operating parameters of the steam turbine in the test mode are ideally achieved and no temporary effects are to be considered in the sharp operation.

In einer vorteilhaften Weiterbildung wird die Gasturbine im Testbetrieb mit geringerer Leistung betrieben.In an advantageous development, the gas turbine is operated in test mode with lower power.

In einer weiteren vorteilhaften Weiterbildung wird die Gasturbine im Testbetrieb mit einer konstanten Abgastemperatur betrieben.In a further advantageous development, the gas turbine is operated in test mode with a constant exhaust gas temperature.

In einer weiteren vorteilhaften Weiterbildung wird zwischen dem Auslösen des DT-Überdrehzahlschutzes und dem Lastabwurf eine Zeit tAuslösung vergehen und es gilt tAuslösung < tmax, wobei ein Dampfturbinen-Trip erfolgt, sofern tAuslösung > tmax ist und das Auslösen des DT-Überdrehzahlschutzes noch nicht erfolgt ist.In a further advantageous development, a time t tripping elapses between the triggering of the DT overspeed protection and the load shedding, and the triggering <t max applies, with a steam turbine trip taking place, if t triggering is > t max and triggering of the DT Overspeed protection has not yet occurred.

Im Folgenden wird ein Ausführungsbeispiel der Erfindung näher beschrieben. Die Figuren zeigen in schematischer Weise:

Figur 1
eine schematische Übersicht einer GuD-Einwellenanlage,
Figur 2
einen Drehzahlverlauf nach einem Lastabwurf.
In the following an embodiment of the invention will be described in more detail. The figures show schematically:
FIG. 1
a schematic overview of a GuD single-shaft system,
FIG. 2
a speed curve after a load shedding.

Die Figur 1 zeigt eine GuD-Einwellenanlage 1. Diese GuD-Einwellenanlage 1 umfasst ein Dampfturbine 2, eine Gasturbine 3 und einen elektrischen Generator 4, die über eine gemeinsame Welle 5 drehmomentübertragend miteinander verbunden sind. Zwischen der Gasturbine 3 und dem elektrischen Generator 4 ist eine Kupplung 6 angeordnet, mit der die Drehmomentübertragung unterbrochen werden kann.The FIG. 1 shows a GuD single-shaft system 1. This GuD single-shaft system 1 comprises a steam turbine 2, a gas turbine 3 and an electric generator 4, which are connected to each other via a common shaft 5 to transmit torque. Between the gas turbine 3 and the electric generator 4, a clutch 6 is arranged, with which the torque transmission can be interrupted.

An einem Ausgang 7 des elektrischen Generators 4 ist über einen Schalter 8 ein elektrischer Verbraucher 9 bzw. eine elektrische Last 9 angeschlossen. In Figur 1 ist der Schalter 8 im geschlossenen Zustand dargestellt.At an output 7 of the electric generator 4, an electrical load 9 or an electrical load 9 is connected via a switch 8. In FIG. 1 the switch 8 is shown in the closed state.

Die Figur 2 zeigt einen Drehzahlverlauf der Gasturbine (nGT) und der Dampfturbine (nDT). Die in Figur 2 dargestellten Drehzahlverläufe zeigen den Drehzahlverlauf der Gasturbine 3 und der Dampfturbine 2 bei geschlossener Kupplung 6. Zunächst wird die Gasturbine 3 und Dampfturbine 2 mit einer konstanten Drehzahl von 3000 Umdrehungen pro Minute betrieben. Zum Zeitpunkt t = tLastabwurf wird der elektrische Verbraucher 9 über den Schalter 8 vom Generator 4 getrennt. Die Folge ist, dass die Drehzahl der Gasturbine (nGT) und der Dampfturbine (nDT) kurzzeitig hoch geht und sofern ein Auslösegrenzwert erreicht wurde, ein Trip der Dampfturbine 2 3 erfolgt, was zu einem starken Absinken der Drehzahl, wie in Figur 2 erkennbar ist, führt.The FIG. 2 shows a speed curve of the gas turbine (n GT ) and the steam turbine (n DT ). In the FIG. 2 shown speed curves show the speed curve of the gas turbine 3 and the steam turbine 2 with the clutch closed 6. First, the gas turbine 3 and steam turbine 2 is operated at a constant speed of 3000 revolutions per minute. At the time t = t load shedding the electrical load 9 is disconnected from the generator 4 via the switch 8. The result is that the speed of the gas turbine (n GT ) and the steam turbine (n DT ) goes high for a short time and if a tripping limit has been reached, a trip of the steam turbine 2 3 takes place, resulting in a sharp decrease in the speed, as in FIG. 2 recognizable leads.

Der scharfe Überdrehzahlschutz muss mit einem, gegenüber dem normalen Betrieb, unveränderten Auslösegrenzwert des Überdrehzahlschutzes erfolgen. Während des Tests werden die Gasturbine 3 und Dampfturbine 2 bis zum Auslösegrenzwert des zugehörigen Überdrehzahlschutzes definiert beschleunigt. Der Überdrehzahlschutz muss bei Überschreiten der Auslösegrenzwerte die entsprechende Aktuatorik von Gasturbine 3 und Dampfturbine 2 absteuern und so kritische Überdrehzahlen verhindern. Der scharfe Überdrehzahlschutztest ist im Sinne der funktionalen Sicherheit keine echte Anforderung an den Schutz, da die Regler die entsprechenden Auslösegrenzwerte mit definierter Dynamik anfahren und es nicht zu einer kritischen Überdrehzahl kommt.The sharp overspeed protection must be carried out with a, compared to normal operation, unaltered trip limit value of the overspeed protection. During the test, the gas turbine Defines 3 and steam turbine 2 to the trigger limit of the associated overspeed protection defined. The overspeed protection must absteuern when exceeding the tripping limits, the corresponding actuators of gas turbine 3 and steam turbine 2 and thus prevent critical overspeed. The sharp overspeed protection test is not a real safety requirement for functional safety, as the controllers approach the appropriate trip limits with a defined dynamic range and do not reach a critical overspeed.

Bei GuD-Einwellenanlagen 1 sind sowohl die Gasturbine 3 als auch die Dampfturbine 2 mit je einem separaten Überdrehzahlschutz ausgestattet. Aufgrund der mechanischen Kupplung 6 zwischen der Gasturbine 3 und der Dampfturbine 2 bei Einwellenanlagen kann die Drehzahl der Dampfturbine 2 nicht höher sein als die Drehzahl der Gasturbine 3. Weiterhin muss von der Gasturbine 3 eine ausreichende Kesselleistung für den scharfen Überdrehzahltest der Dampfturbine 2 bereitgestellt werden. Somit kann der Überdrehzahltest der Dampfturbine 2 nicht unabhängig von der Gasturbine 3 erfolgen. Das Verfahren zum Testen des Überdrehzahlschutzes der GuD-Einwellenanlage 1 erfolgt folgendermaßen: während eines Testbetriebs wird die Gasturbine 3 und die Dampfturbine 2 mit einer Testdrehzahl betrieben, die der Betriebsdrehzahl von 3000 Umdrehungen pro Minute gleicht. Der Generator 4 wird mit einer angeschlossenen Last 9 betrieben, wobei während des Testbetriebes zum Zeitpunkt tLastabwurf ein Lastabwurf erfolgt, wodurch die Drehzahl der Dampfturbine 2 und der Gasturbine 3 sich erhöht und bei Erreichen eines DT-Auslösegrenzwertes ein DT-Überdrehzahlschutz und bei Erreichen des GT-Auslösegrenzwertes ein GT-Überdrehzahlschutz ausgelöst wird. Die Folge ist, dass die Drehzahl der Dampfturbine 2 und der Gasturbine 3 verringert wird.In GuD single-shaft systems 1, both the gas turbine 3 and the steam turbine 2 are each equipped with a separate overspeed protection. Due to the mechanical coupling 6 between the gas turbine 3 and the steam turbine 2 in single-shaft systems, the speed of the steam turbine 2 can not be higher than the speed of the gas turbine 3. Furthermore, the gas turbine 3 must provide a sufficient boiler output for the sharp overspeed test of the steam turbine 2. Thus, the over-speed test of the steam turbine 2 can not be performed independently of the gas turbine 3. The method for testing the overspeed protection of the CCGT 1 takes place as follows: during a test operation, the gas turbine 3 and the steam turbine 2 are operated at a test speed equal to the operating speed of 3000 revolutions per minute. The generator 4 is operated with a connected load 9, wherein during the test operation at the time t load shedding takes place, whereby the speed of the steam turbine 2 and the gas turbine 3 increases and upon reaching a DT tripping limit DT overspeed protection and upon reaching the GT Trip Limit GT over-speed protection is triggered. The result is that the speed of the steam turbine 2 and the gas turbine 3 is reduced.

Das Massenträgheitsmoment bzw. die Anlaufzeitkonstante beeinflusst das dynamische Verhalten von Gasturbine 3 und Dampfturbine 2 nach dem Lastabwurf. Das Verhältnis der Anlaufzeitkonstanten hat einen Einfluss auf die Wahl des Auslösegrenzwertes.The mass moment of inertia or the start-up time constant influences the dynamic behavior of gas turbine 3 and steam turbine 2 after load shedding. The ratio of the start-up time constants has an influence on the selection of the trip limit value.

Ein Lastabwurf führt bei der GuD-Einwellenanlage 1 automatisch zu einem Schnellschluss der Dampfturbine 2. Daher kann der Auslösegrenzwert des Dampfturbinen-Überdrehzahlschutzes ohne Reduzierung der Anlagenverfügbarkeit auch einen Wert knapp oberhalb der maximalen Netzfrequenz (beispielsweise 61,5 Hz) eingestellt werden (z.B. bei 104%). Der Abstand zwischen maximaler zulässiger Netzfrequenz und Auslösegrenzwert des Dampfturbinen-Überdrehzahlschutzes wird so gewählt, dass es während des Betriebs zu keinem unerwünschten Trip kommt.With the GuD single-shaft system 1, a load shedding automatically leads to a rapid shutdown of the steam turbine 2. Therefore, the triggering limit value of the steam turbine overspeed protection can be set just above the maximum mains frequency (eg 61.5 Hz) without reducing the system availability (eg at 104 %). The distance between the maximum permissible mains frequency and the triggering limit value of the steam turbine overspeed protection is selected such that no undesired trip occurs during operation.

Eine weitere Randbedingung ist, dass der Auslösegrenzwert des Dampfturbinen-Überdrehzahlschutzes nicht größer ist als der Auslösegrenzwert des Gasturbinen-Überdrehzahlschutzes.Another constraint is that the triggering limit of the steam turbine overspeed protection is not greater than the gas turbine overspeed protection trip limit.

Der Auslösegrenzwert des Gasturbinen-Überdrehzahlschutzes muss auf einen Wert oberhalb der maximalen Drehzahl nach einem Lastabwurf und unterhalb der kritischen Überdrehzahl eingestellt werden. Die Wahl des Auslösegrenzwertes muss derart erfolgen, dass die Dampfturbine 2 vor der Gasturbine 3 den Auslösegrenzwert erreicht.The gas turbine overspeed protection trip limit must be set to a value above the maximum speed after a load dump and below the critical overspeed. The choice of the tripping limit value must be such that the steam turbine 2 reaches the tripping limit value before the gas turbine 3.

Die Leittechnik der Gasturbine 3 und Dampfturbinen 2 einer GuD-Einwellenanlage 1 wird derart erweitert, dass ein Schalter installiert wird, mit dem der scharfe Überdrehzahltest aktiviert wird. Diese Funktion wird nach einem maximalen einzustellenden Zeitraum automatisch deaktiviert, um die Dampfturbine 2 vor Kontakt mit zu kaltem Dampf zu schützen. Der maximale Zeitraum muss entsprechend der Dauer des scharfen Überdrehzahltests gewählt werden mit der Randbedingung, dass die Dampftemperaturen während des Tests im zulässigen Bereich bleiben. Das Verfahren zeichnet sich folgendermaßen aus: in Abhängigkeit des Schalters wird bei der Gasturbine 3 zunächst die Lastabwurferkennung blockiert und ein automatisiertes, beispielsweise ein zeitversetztes Öffnen des Schalters 8 des Generators 4 erzeugt. Bei der Dampfturbine 2 wird in Abhängigkeit des Schalters zunächst der Drehzahlreglersollwert auf einen Wert knapp oberhalb des Auslösegrenzwertes des Dampfturbinen-Überdrehzahlschutzes, der beispielsweise bei 105% liegen kann, eingestellt, wobei der Regler den Grenzwert mit definierter Beschleunigung anfahren soll. Die Höhe der Beschleunigung beeinflusst die Testdauer. Danach wird der Grenzfrequenzeinfluss deaktiviert und anschließend wird der Einfluss der Gasturbinenfeuerleistung auf den Dampfturbinenregler unterdrückt. Hierbei muss anschließend ggf. der Gesamtschnellschluss bei Kupplungsstörungen für die Dauer des Überdrehzahltests geregelt werden, der nur erforderlich ist, wenn die Gasturbine 3 durch den Gesamtschnellschluss vor Erreichen des Auslösegrenzwertes getrippt wird.The control technology of the gas turbine 3 and steam turbines 2 of a CCGT 1 is extended so that a switch is installed, with which the sharp overspeed test is activated. This function is automatically deactivated after a maximum period of time to be set in order to protect the steam turbine 2 from contact with cold steam. The maximum period must be selected according to the duration of the sharp overspeed test with the condition that the steam temperatures remain within the allowable range during the test. The method is characterized as follows: depending on the switch, the load dump detection is first blocked in the gas turbine 3 and an automated, for example, a time-delayed opening of the switch 8 of the generator 4 is generated. In the steam turbine 2 is dependent the switch first the speed controller setpoint to a value just above the tripping limit value of the steam turbine overspeed protection, which may for example be 105%, set, the controller should approach the limit with a defined acceleration. The amount of acceleration affects the duration of the test. Thereafter, the limit frequency influence is deactivated, and then the influence of the gas turbine fire power on the steam turbine controller is suppressed. In this case, if necessary, the total quick-closing in the case of coupling failures must be regulated for the duration of the overspeed test, which is only necessary if the gas turbine 3 is tripped by the total quick-closing before the triggering limit value is reached.

Das Verfahren zum Testen des Überdrehzahlschutzes der GuD-Einwellenanlage 1 erfolgt, sofern die Dampfturbine 2 vollständig durchgewärmt ist und länger als 5 Stunden im Betrieb ist. Die Gasturbine 3 wird mit möglichst geringer Leistung und konstanter Abgastemperatur betrieben, was durch den IGV-Punkt widergespiegelt wird. Durch Betätigen des Schalters in der Leittechnik wird der Überdrehzahltest aktiviert. Bei aktiviertem Überdrehzahltest werden die notwendigen Umschaltungen automatisiert erfolgen, und etwas verzögert erfolgt das automatisierte Öffnen des Schalters 8. Anschließend fahren die Gasturbine 3 und Dampfturbine 2 den Auslösegrenzwert definiert an. Die Dampfturbine 2 erreicht ihren Auslösegrenzwert als erstes, wobei die Gasturbine 3 kurz danach ihren Auslösegrenzwert erreicht. Dieser Gesamtvorgang darf eine bestimmte einzustellende Zeit nicht überschreiten, da der Dampf dann unzulässig kalt wird. Daher wird die Funktion scharfer Überdrehzahltester aktiv automatisch nach einigen Sekunden, die eingestellt werden können, deaktiviert, wodurch ein Dampfturbinentrip erzeugt wird.The method for testing the overspeed protection of the CCGT 1 occurs as long as the steam turbine 2 is completely warmed up and is in operation for more than 5 hours. The gas turbine 3 is operated with the lowest possible power and constant exhaust gas temperature, which is reflected by the IGV point. Pressing the switch in the control system activates the overspeed test. When the overspeed test is activated, the necessary switching operations will be automated, and the automated opening of the switch 8 will be delayed. Then, the gas turbine 3 and steam turbine 2 will drive the trip limit value in a defined manner. The steam turbine 2 reaches its triggering limit first, with the gas turbine 3 shortly thereafter reaching its trip limit. This total process must not exceed a certain time to be set, since the steam then becomes inadmissibly cold. Therefore, the function of sharp over-speed tester is automatically deactivated automatically after a few seconds that can be adjusted, thereby generating a steam turbine trip.

Claims (7)

Verfahren zum Testen eines Überdrehzahlschutzes einer GuD-Einwellenanlage (1),
wobei während eines Testbetriebs die Gasturbine (3) und Dampfturbine (2) mit einer Testdrehzahl betrieben werden, wobei der Generator (4) mit einer angeschlossenen Last betrieben wird,
wobei während des Testbetriebs ein Lastabwurf erfolgt, wobei die Drehzahl der Dampfturbine (2) sich erhöht und bei Erreichen eines DT-Auslösegrenzwertes ein Überdrehzahlschutz ausgelöst wird.
Method for testing an overspeed protection of a CCGT (1),
wherein, during a test operation, the gas turbine (3) and steam turbine (2) are operated at a test speed, the generator (4) being operated with a connected load,
wherein a load shedding occurs during the test operation, wherein the speed of the steam turbine (2) increases and upon reaching a DT trip limit an overspeed protection is triggered.
Verfahren nach Anspruch 1,
bei dem die Dampfturbine (2) den DT-Auslösegrenzwert zunächst erreicht und anschließend die Gasturbine (3) einen GT-Grenzwert erreicht und der Überdrehzahlschutz nach Erreichen des DT-Grenzwertes ausgelöst wird.
Method according to claim 1,
in which the steam turbine (2) first reaches the DT trip limit and then the gas turbine (3) reaches a GT limit and the overspeed protection is triggered after reaching the DT limit.
Verfahren nach Anspruch 2,
wobei der GT-Überdrehzahlschutz nach Erreichen des GT-Grenzwertes ausgelöst wird.
Method according to claim 2,
whereby the GT overspeed protection is triggered after reaching the GT limit value.
Verfahren nach Anspruch 1, 2 oder 3,
wobei die Dampfturbine (2) im Testbetrieb in einem vollständig durchgewärmten Zustand sich befindet.
Method according to claim 1, 2 or 3,
wherein the steam turbine (2) is in test operation in a fully warmed condition.
Verfahren nach einem der vorhergehenden Ansprüche, wobei die Gasturbine (3) im Testbetrieb mit geringer Leistung betrieben wird.Method according to one of the preceding claims, wherein the gas turbine (3) is operated in the test mode with low power. Verfahren nach einem der vorhergehenden Ansprüche, wobei die Gasturbine (3) im Testbetrieb mit einer konstanten Abgastemperatur betrieben wird.Method according to one of the preceding claims, wherein the gas turbine (3) is operated in test mode with a constant exhaust gas temperature. Verfahren nach einem der vorhergehenden Ansprüche, wobei zwischen dem Auslösen des DT-Überdrehzahlschutzes und dem Lastabwurf eine Zeit tauslösung vergeht und es gilt tAuslösung < tmax, wobei ein Dampfturbinen-Trip erfolgt sofern tAuslösung > tmax ist und das Auslösen des DT-Überdrehzahlschutzes noch nicht erfolgt ist.Method according to one of the preceding claims, wherein between the triggering of the DT overspeed protection and the load shedding a time t tripping passes and it applies t trigger <t max , wherein a steam turbine trip occurs if t trigger > t max and the triggering of the DT Overspeed protection has not yet occurred.
EP13170738.2A 2013-06-06 2013-06-06 Method for testing an overspeed protection system of a combined cycle plant with single shaft system Withdrawn EP2811119A1 (en)

Priority Applications (9)

Application Number Priority Date Filing Date Title
EP13170738.2A EP2811119A1 (en) 2013-06-06 2013-06-06 Method for testing an overspeed protection system of a combined cycle plant with single shaft system
CN201480032268.1A CN105264182B (en) 2013-06-06 2014-05-26 For the method testing the overspeed protective device of combustion gas and steam turbine combined cycle single-axle units
JP2016517228A JP6185162B2 (en) 2013-06-06 2014-05-26 Method for testing an overspeed prevention device in a single shaft combined cycle plant
PL14728486T PL2984301T3 (en) 2013-06-06 2014-05-26 Method for testing an overspeed protection system of a combined cycle plant with single shaft system
KR1020157037052A KR101846639B1 (en) 2013-06-06 2014-05-26 Method for testing an overspeed protection mechanism of a single-shaft combined-cycle plant
PCT/EP2014/060773 WO2014195163A1 (en) 2013-06-06 2014-05-26 Method for testing an overspeed protection mechanism of a single-shaft combined-cycle plant
EP14728486.3A EP2984301B1 (en) 2013-06-06 2014-05-26 Method for testing an overspeed protection system of a combined cycle plant with single shaft system
RU2015155901A RU2629244C2 (en) 2013-06-06 2014-05-26 Testing method of protection from super-nominal rotation speed of single shaft gas-steam turbine plant
US14/895,071 US9976440B2 (en) 2013-06-06 2014-05-26 Method for testing an overspeed protection mechanism of a single-shaft combined-cycle plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP13170738.2A EP2811119A1 (en) 2013-06-06 2013-06-06 Method for testing an overspeed protection system of a combined cycle plant with single shaft system

Publications (1)

Publication Number Publication Date
EP2811119A1 true EP2811119A1 (en) 2014-12-10

Family

ID=48577560

Family Applications (2)

Application Number Title Priority Date Filing Date
EP13170738.2A Withdrawn EP2811119A1 (en) 2013-06-06 2013-06-06 Method for testing an overspeed protection system of a combined cycle plant with single shaft system
EP14728486.3A Not-in-force EP2984301B1 (en) 2013-06-06 2014-05-26 Method for testing an overspeed protection system of a combined cycle plant with single shaft system

Family Applications After (1)

Application Number Title Priority Date Filing Date
EP14728486.3A Not-in-force EP2984301B1 (en) 2013-06-06 2014-05-26 Method for testing an overspeed protection system of a combined cycle plant with single shaft system

Country Status (8)

Country Link
US (1) US9976440B2 (en)
EP (2) EP2811119A1 (en)
JP (1) JP6185162B2 (en)
KR (1) KR101846639B1 (en)
CN (1) CN105264182B (en)
PL (1) PL2984301T3 (en)
RU (1) RU2629244C2 (en)
WO (1) WO2014195163A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3262284B1 (en) * 2015-02-24 2019-01-02 Siemens Aktiengesellschaft Combined cycle power plant having supercritical steam turbine
JP6944406B2 (en) 2018-03-29 2021-10-06 三菱パワー株式会社 Test method for uniaxial combined cycle plant, uniaxial combined cycle plant and controller for uniaxial combined cycle plant

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29908581U1 (en) * 1998-11-13 1999-08-12 Siemens Ag Device for checking the operational safety of a turbine in the event of a load shedding
FR2947300A1 (en) * 2009-06-25 2010-12-31 Snecma Protection chain test realizing method for e.g. turbojet engine of aircraft, involves transmitting information on defect of overspeed protection chain by electronic regulation system, if closing state check result is negative
EP2372482A2 (en) * 2010-03-23 2011-10-05 General Electric Company Method and system for testing an overspeed protection system of a powerplant machine

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU848710A1 (en) 1979-12-25 1981-07-23 Предприятие П/Я А-3513 Automatic regulating system for steam-gas unit
US6785633B2 (en) 2001-12-28 2004-08-31 General Electric Company Method and apparatus for assessing performance of combined cycle power-plants
JP3930462B2 (en) * 2003-08-01 2007-06-13 株式会社日立製作所 Single-shaft combined cycle power generation facility and operation method thereof
US7194865B2 (en) * 2004-08-30 2007-03-27 Compressor Controls Corporation Turbine overspeed protection
JP2008248875A (en) 2007-03-08 2008-10-16 Kawasaki Plant Systems Ltd Gas turbine power generation system and its operation control method
CN105587351B (en) * 2008-03-25 2018-12-21 通用电器技术有限公司 Power station plant and its operation method
US8370100B2 (en) * 2010-03-23 2013-02-05 General Electric Company Method for determining when to perform a test of an overspeed protection system of a powerplant machine
US8661880B2 (en) 2010-03-23 2014-03-04 General Electric Company Method and system for testing an overspeed protection system of a powerplant
US8756939B2 (en) 2010-03-23 2014-06-24 General Electric Company Method and system for testing an overspeed protection system of a powerplant machine
EP2458180A1 (en) 2010-11-30 2012-05-30 Siemens Aktiengesellschaft Method for operating a gas turbine during load control, device for regulating the operation of a gas turbine and power plant
CN102071978A (en) 2010-12-08 2011-05-25 广东电网公司电力科学研究院 Method for over-speed protection of turbine under load shedding working condition
JP5781312B2 (en) 2011-01-12 2015-09-16 三菱日立パワーシステムズ株式会社 Gas turbine reliability evaluation test method
JP2012197750A (en) * 2011-03-22 2012-10-18 Toshiba Corp Power plant and power plant operating method
EP2848773A1 (en) * 2013-09-17 2015-03-18 Siemens Aktiengesellschaft Method for testing an overspeed protection system of a single-shaft system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29908581U1 (en) * 1998-11-13 1999-08-12 Siemens Ag Device for checking the operational safety of a turbine in the event of a load shedding
FR2947300A1 (en) * 2009-06-25 2010-12-31 Snecma Protection chain test realizing method for e.g. turbojet engine of aircraft, involves transmitting information on defect of overspeed protection chain by electronic regulation system, if closing state check result is negative
EP2372482A2 (en) * 2010-03-23 2011-10-05 General Electric Company Method and system for testing an overspeed protection system of a powerplant machine

Also Published As

Publication number Publication date
JP6185162B2 (en) 2017-08-23
JP2016523331A (en) 2016-08-08
WO2014195163A1 (en) 2014-12-11
EP2984301B1 (en) 2017-04-26
RU2629244C2 (en) 2017-08-28
US20160123183A1 (en) 2016-05-05
EP2984301A1 (en) 2016-02-17
US9976440B2 (en) 2018-05-22
KR101846639B1 (en) 2018-04-06
KR20160015310A (en) 2016-02-12
CN105264182A (en) 2016-01-20
PL2984301T3 (en) 2017-10-31
CN105264182B (en) 2016-12-28
RU2015155901A (en) 2017-07-17

Similar Documents

Publication Publication Date Title
DE10322703B4 (en) Gas turbine control system
DE2049825A1 (en) Method and device for the prevention of overspeeding as a result of partial or complete load losses in a steam turbine power generation plant
EP2330296A2 (en) Method for operating a speed regulated wind turbine and wind turbine
DE112015000664T5 (en) Gas turbine control apparatus, gas turbine, and gas turbine control method
EP3017150B1 (en) Method for testing an overspeed protection apparatus of a single-shaft system
EP2808501A1 (en) Method for operating a combined cycle power plant assembly
EP2984301B1 (en) Method for testing an overspeed protection system of a combined cycle plant with single shaft system
DE10361755A1 (en) System and method for back pressure monitoring in steam turbines using dynamic pressure sensors
EP2609301A1 (en) Method for controlling a turboset
DE2159696A1 (en) Method for improving the removal of residual heat in the event of an emergency shutdown of a gas-cooled nuclear reactor and device for carrying out the method
DE2354050A1 (en) PROCEDURE AND DEVICE FOR PROTECTING AN EQUIPMENT
DE102008002610A1 (en) Online method for monitoring and controlling a gas-turbine installation calculates a mathematical-cum-physical processing model for a gas turbine
EP3238338B1 (en) Method and apparatus for monitoring the operation of a power generating installation
EP3044428B1 (en) Method for testing an overspeed protection system of a single-shaft system
DE112018003526T5 (en) GAS TURBINE POWER SUPPLY SYSTEM AND CONTROL STRATEGY TO LIMIT RETURN SHUTDOWN
DE19621824C2 (en) Process for regulating gas pressures when using gas expansion turbines
DE2550059C2 (en) Safety system for a steam turbine plant
DE102017124709B3 (en) Generator for feeding energy into an electric power grid and method therefor
EP3022402B1 (en) Method for testing an overspeed protection device of a single-shaft plant
DE102018215222A1 (en) Method for dissipating residual energy from an electrical machine in a power plant in the event of a sudden load drop
EP3022401B1 (en) Method for testing an overspeed protection system of a single-shaft unit
DE878052C (en) Control device for steam or gas turbines
DE102016217216A1 (en) Turbine system and method for operating a turbine system
EP2899373A1 (en) Method of operating a stationary gas turbine during load shedding
WO2019001947A1 (en) Method for operating a gas turbine system

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20130606

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20150611